SlideShare una empresa de Scribd logo
1 de 38
Descargar para leer sin conexión
Five Immutable Principles of Project Success
Glen B. Alleman
Niwot Ridge, LLC
glen.alleman@niwotridge.com
+1 303 241 9633
All projects ‒ no matter domain ‒ are fraught with Technical, Cost, and Schedule
uncertainties, that create risk to project success.
Five Principles of Project Success increase the Probability of Project Success (PoPS)
through the application of Risk Management to all Practices and Procedures
Glen B. Alleman, Copyright © 2019
PMI Rocky Mountain Project Management Symposium, 19 April 2019
1/38
Principles are Required before
Practices and Processes can be Successful
Do not undertake a
project unless it is
manifestly important
and nearly impossible
PMI Rocky Mountain Project Management Symposium, 19 April 2019
Glen B. Alleman, Copyright © 2019 2/38
A Few Root Cause’s of Project Failure
(100’s are documented in Data Bases)
§ Unrealistic deadlines,
uninformed by risk without
margin or corrective actions
§ Communication deficits
between customers and
suppliers
§ Uncontrolled scope changes
§ Unmitigated resource
competition or conflicts
§ Uncertain dependencies
between deliverables, risks,
resources and externalities
§ Failure to manage risk
§ Insufficient delivery skills
§ Lack of accountability for
outcomes, with no definition of
needed Capabilities, their
Effectiveness or Performance
§ Disengaged customers or
stakeholders
§ Lack of business vision and
goal with missing tangible
Measures Effectiveness and
Performance
Before we start, let’s look at some failure modes for
projects, independent of any domain
PMI Rocky Mountain Project Management Symposium, 19 April 2019
Glen B. Alleman, Copyright © 2019 3/38
1. What Does Done Look Like
in Units of Measure
Meaningful to the Decision
Makers?
2. How Do We Get to Done as
Needed?
3. Do We Have Enough Time,
Resources, And Money To
Get to Done?
4. What Impediments Will We
Encounter Along The Way
To Done?
5. How Do We Know We Are
Making Progress Toward
Done?
5 Immutable Principles Project Success
4
Glen B. Alleman, Copyright © 2019
PMI Rocky Mountain Project Management Symposium, 19 April 2019
4/38
5 Immutable Principles of Project Success
§ Done means delivered capabilities that fulfill the
project Mission and Vision, described in units of
measure meaningful to the decision makers.
§ There is a Plan to reach Done at needed time for
needed budget
§ There is a Plan for execution of work using the
resources in place when needed to reach Done.
§ Impediments that will be encountered along the way
to Done and the Plan how they are to be handled.
§ Measures of progress to Plan are in units of Physical
Percent Complete to assure we arrive on time, on
budget, with the needed capabilities.
PMI Rocky Mountain Project Management Symposium, 19 April 2019
Glen B. Alleman, Copyright © 2019 5/38
PMI Rocky Mountain Project Management Symposium, 19 April 2019
Glen B. Alleman, Copyright © 2019 6/38
Three steps to success
§ Plan – is the strategy for successful
completion of the project.
§ Schedule – are the steps needed to
fulfill the Plan.
§ Execution – is the physical
performance of the steps needed to
deliver the results defined in the
Plan to implement the Strategy.
PMI Rocky Mountain Project Management Symposium, 19 April 2019
7/38Glen B. Alleman, Copyright © 2019
Scheduling
Only comes
after Planning
§ What are the
individual, dependent
and, sequential steps
needed to deliver
these capabilities?
§ The schedule has
durations,
dependencies, timing,
dates, resources and
other things related
with the Plan.
§ The idea that these
steps “emerge” is
fanciful in many
situations.Glen B. Alleman, Copyright © 2012 8/38
Action Outcome
Implement Strategy
Ensure Capabilities
Prioritize Problems And Solutions
Identify Redundancies
Deliver Solutions
† “Capabilities‒Based Planning: A Methodology for Deciphering
Commander’s Intent,” Peter Kossakowski, 10th ICCRTS, Track 12
PMI Rocky Mountain Project Management Symposium, 19 April 2019
Glen B. Alleman, Copyright © 2019 9/38
What is a Deliverable?
PMI Rocky Mountain Project Management Symposium, 19 April 2019
Glen B. Alleman, Copyright © 2019 10/38
Describe Done in Units of Measure Meaningful
to the Decision Makers
§ Develop a list of Capabilities and describe
their effectiveness, performance and technical
requirements as deliverables.
§ Develop the interdependencies between these
deliverables.
§ From the needed Capabilities develop the
Measures of Effectiveness and Measures of
Performance to assure they are what the
customer ordered.
PMI Rocky Mountain Project Management Symposium, 19 April 2019
Glen B. Alleman, Copyright © 2019 11/38
“Done” Provides the Capability to Accomplish
Something
19 October 1899 Robert Goddard decided that he wanted to "fly without wings" to Moon.
PMI Rocky Mountain Project Management Symposium, 19 April 2019
Glen B. Alleman, Copyright © 2019 12/38
Q2. How Do We Get There?
Some problems
respond to lightweight
approaches, like
Scrum, DSDM, Crystal,
and XP as product
development methods.
Others require more
complex approaches,
like a System of
Systems (SoS) spiral
development processes.
In all cases a disciplined
approach increases the
probability of success –
no matter the
complexity of the
problem or the solution
This approach works
well when we don’t
know what “done”
looks like with enough
clarity
So
Does
This!
Glen B. Alleman, Copyright © 2012 13/38
Q3: Do We Have Everything We Need To Get To Done
as Planned?Glen B. Alleman, Copyright © 2019
PMI Rocky Mountain Project Management Symposium, 19 April 2019
14/38
A Common Problem A Simple Solution
We have undue optimism.
Use documented procedures – no matter the method –
for estimating and planning using historical data.
We attempt to avoid risk and
uncertainty.
Understand and prioritize risks for each critical
component empowers management and staff.
Use this knowledge to control your optimism.
We rely too much on intuitive
judgment.
Simple statistical models are more often correct than
human judgment.
Have the numbers to back up your intuition.
The Rational Planning of (Software) Projects, Mark C. Paulk, Software Engineering Institute, Carnegie Mellon University, Pittsburgh, PA
15213–3890
PMI Rocky Mountain Project Management Symposium, 19 April 2019
Glen B. Alleman, Copyright © 2019 15/38
Getting to Done On–time and On–budget,.
With the Needed Capabilities
§ Construct a schedule for all the work needed to
produce the deliverables.
§ Define “packages of work” for all the activities
with deliverables defined as “exit criteria.”
§ Define progress in units of increasing maturity for
each deliverable to it can be compared to the
needed maturity at each point in the schedule
PMI Rocky Mountain Project Management Symposium, 19 April 2019
Glen B. Alleman, Copyright © 2019 16/38
The schedule tells us the order of the planned work
PMI Rocky Mountain Project Management Symposium, 19 April 2019
This sketch is Warner Van Braun’s notional concept to get to the moon from Marshall
Space Flight Center, Huntsville, Alabama
Glen B. Alleman, Copyright © 2019 17/38
The Schedule Shows Progress To Plan
§ Deliverables represent the required mission
capabilities and its value as defined by the business
and shared by the contractor team.
§ When all deliverables and their Work Packages are
complete, they are not revisited or reopened.
– They are 100% done.
§ The progression of Work Packages defines the
increasing maturity of the deliverables.
– The mission value of the deliverables to the customer
increases as Work Packages are completed.
§ Completion of Work Packages is represented by the
Physical Percent Completion of the deliverables.
– Either 0%/100% or Apportioned Milestones are used
to state the completion of each Work Package.
Mission
Capabilities
Technical
Capabilities
Packages of
Work
Deliverables
PMI Rocky Mountain Project Management Symposium, 19 April 2019
Glen B. Alleman, Copyright © 2019 18/38
§ Vertical traceability ACè SAè PE
§ Horizontal traceability WPè WPèAC
Program Deliverables
Define the maturity
of a Capability at a point in
time.
Significant Accomplishments
Represent requirements
that enable Capabilities.
Accomplishment Criteria
Exit Criteria for the Work
Packages that fulfill Requirements.
Package
of Work
Package
of Work
Package
of Work
Package
of Work
Package
of Work
Package
of Work
Package
of Work
Package
Of Work
The Schedule Connects Work to Deliverables
PMI Rocky Mountain Project Management Symposium, 19 April 2019
Glen B. Alleman, Copyright © 2019 19/38
Plan for the needed resources to arrive on time
§ List the needed staff, materials and facilities for
the project.
§ Assign staff and materials to the work
packages.
§ Estimate the cost of the staff and materials and
the impact of this variance on the total project
cost and delivery schedule.
PMI Rocky Mountain Project Management Symposium, 19 April 2019
Glen B. Alleman, Copyright © 2019 20/38
1. Hope is not a strategy
2. No single point estimate of cost or schedule can be correct
3. Cost, Schedule, and Technical Performance are inseparable
4. Risk management requires adherence to a well defined
process
5. Communication is the Number One success factor
Glen B. Alleman, Copyright © 2019
PMI Rocky Mountain Project Management Symposium, 19 April 2019
21/38
Taxonomy of Uncertainties that Create
Irreducible and Reducible Risk.
These Require Estimates of Direct and Residual Impacts
of these Risks on the Probability of Project Success
Glen B. Alleman, Copyright © 2019
PMI Rocky Mountain Project Management Symposium, 19 April 2019
Uncertainty
Irreducible
(Aleatory)
Reducible
(Epistemic)
Natural Variability
Ambiguity about
behavior of process
Ontological
Uncertainty
Probability of
Event’s Occurrence
Probabilistic Impact
from Event
Period of Exposure
to Event
Period of Exposure
to Aleatory Process
22/38
Risk
Management
Demands Direct
Communication
Between All
Participants in
the Project
Glen B. Alleman, Copyright © 2019
PMI Rocky Mountain Project Management Symposium, 19 April 2019
23/38
§ Make a list of risks and rank them by priority.
§ Assess impact on cost and schedule for each risk
and the dependencies of these risks on external
and internal drivers.
§ Assess the probability of occurrence and the
probabilistic impact on cost and schedule
impact, cost of handling, and cost of the residual
risk after handling.
Identify impediments to progress and fix them,
with Direct work or Margin
PMI Rocky Mountain Project Management Symposium, 19 April 2019
Glen B. Alleman, Copyright © 2019 24/38
Q5:
How Do We Know We Are Making Progress
Toward Done?
Glen B. Alleman, Copyright © 2019
PMI Rocky Mountain Project Management Symposium, 19 April 2019
25/38
26/3
Primary Measures of
Progress to Plan
Are We Done?
When will we be Done?
What will it cost to be
Done?
§What does Done look like for
the customer?
§How will we recognize Done
when it arrives?
§What’s our confidence of
getting to Done?
§Are we removing or reducing
impediments to getting to done
as needed?Glen B. Alleman, Copyright © 2019
PMI Rocky Mountain Project Management Symposium, 19 April 2019
26/38
§ Use actual or predicted values from:
¤ Engineering measurements
¤ Tests
¤ Experiments
¤ Prototypes
§ For Example:
¤ Response time
¤ Range
¤ Power
¤ Weight
¤ MTTFF/MTTR/MTBF
Technical Performance Measure(s) …
§ Tell us how well a system is achieving the planned performance
requirements at the planned time, for the planned cost in units of
Physical Percent Complete to Plan
PMI Rocky Mountain Project Management Symposium, 19 April 2019
Glen B. Alleman, Copyright © 2019 27/38
28/3
PMI Rocky Mountain Project Management Symposium, 19 April 2019
28/38
Trade Offs Between
Cost, Schedule,
and
Technical Performance is
a Ponzi Scheme without
Margin and a Risk
Management Plan
When we’re on baseline, the
algebraic relationship
between C,S,P, means when
there is a change in one of
these measures everyone
looses.
Glen B. Alleman, Copyright © 2019
Charles Ponzi,
Born March 3, 1882, Italy.
Died Jan 18, 1949, Brazil.
Served 5 years federal prison,
9 years state prison,
deported to Italy.
PMI Rocky Mountain Project Management Symposium, 19 April 2019
29/38
Cost and Schedule
Performance is informed by
Risk Informed Technical
Performance Measures for
each Deliverable.
Business Performance is
informed with Measures of
Effectiveness and Measures
of Performance for each
Capability produced by the
Project.
Glen B. Alleman, Copyright © 2019
PMI Rocky Mountain Project Management Symposium, 19 April 2019
30/38
§ Measuring Physical Percent Complete is the
core of every successful project
management method.
§ It answers the question of what “done” looks
like in units of measure meaningful to the
decision makers.
§ It answers questions like:
¤ What does done look like for today, this week?
¤ What does done look like for entry/exit into the
technical review?
¤ What does done look like for quality control?
¤ What does done look like for the customer?
Physical Percent Complete
Glen B. Alleman, Copyright © 2019
PMI Rocky Mountain Project Management Symposium, 19 April 2019
31/38
§ Describe the outcomes of the work effort
using language the customer understands
§ Assign Technical Performance Measures to
the Deliverables
§ Assign Measures of Performance, Measures
of Effectiveness, Key Performance
Parameters, and Integrate these throughout
the project
Measure progress to Plan as
“Physical Percent Complete”
PMI Rocky Mountain Project Management Symposium, 19 April 2019
Glen B. Alleman, Copyright © 2019 32/38
The Root Causes Of Program Performance
Impacts
Unrealistic Performance Expectations,
missing Measures of Effectiveness, and
Measures of Performance
Unrealistic Cost and Schedule estimates
based on inadequate risk adjusted
growth models
Inadequate assessment of risk and
unmitigated exposure to these risks
without proper handling plans
Unanticipated Technical issues without
alternative plans and solutions to
maintain effectiveness
Cost and
Schedule
Impacts
TheLensofthePerformance
AssessmentBorrowed from Mr. Gary R. Bliss is the Director,
Performance Assessments and Root Cause
Analyses (PARCA), in the Office of the Assistant
Secretary of Defense for Acquisition.
PMI Rocky Mountain Project Management Symposium, 19 April 2019
Glen B. Alleman, Copyright © 2019 33/38
The Five Principles Of Project Success
Done described in meaningful units
A time and budget plan for Done
Planned resources to reach Done
Handling impediments along the way
Measuring progress to plan
PMI Rocky Mountain Project Management Symposium, 19 April 2019
Glen B. Alleman, Copyright © 2019 34/38
Evidence of the 5 Principles put into Practice in a
range of domains
Principle
Traditional
Practice
Agile
Practice
What does Done Look Like in
Units of Measure Meaningful to
the Decision Makers?
Capabilities Based Planning
with Measures of Effectiveness
and Performance
Product Road Map
How do we get to Done? Integrated Master Plan Release Plan
What Resources needed to get
to Done?
Resource loaded Integrated
Master Schedule
Agile development team staff
assignments to Sprints,
Integration and User
Acceptance Testing
What are the Impediments to
getting to Done?
Management Plan for Reducible and Irreducible Uncertainties
that Create Risk
What are the Meaningful
Measures of Progress toward
Done?
Physical Percent Complete
using risk adjusted Performance
Management to produce
Estimate to Complete
Physical Percent Complete
measuring progress to Release
Plan and Product Roadmap
outcomes as planned
Glen B. Alleman, Copyright © 2019
PMI Rocky Mountain Project Management Symposium, 19 April 2019
35/38
The Project Train Wreck Starts When There Is …
§ Inattention to budget, schedule and technical
responsibilities.
§ Work authorizations not always followed (out of
sequence work).
§ Issues with Budget, Schedule, and Technical data
reconciliation.
§ Lack of an Integrated Management System.
§ Plans fluctuations with frequent replanning.
§ Improper use of Management Reserve.
§ Performance Measures don’t reflect actual
Physical Percent Complete.
PMI Rocky Mountain Project Management Symposium, 19 April 2019
§ Lack of predictive variance analysis from data.
§ Untimely and unrealistic Revised Estimates.
§ Progress to Plan not monitored in a regular and consistent manner.
§ Lack of connection between cost, schedule, and technical performance.
§ Lack of project performance oversight by independent surveillance team.
§ Managerial corrective actions not connected to Risk Management Processes.
Glen B. Alleman, Copyright © 2019 36/38
Five Immutable Principles Tested as Questions
Capabilities Requirements Plans Execution
2. What technical and operational requirements are
needed to deliver these capabilities?
1. What capabilities are needed to fulfill the Concept of Operations,
the Mission and Vision, or the Business System Requirements?
3. What schedule delivers the product or
services on time to meet the requirements?
4. What periodic measures of
physical percent complete
assure progress to plan?
What impediments to success, their mitigations, retirement plans,
or “buy downs are in place to increase the probability of success?”
+ Continuous Risk Management
Œ

Ž


PMI Rocky Mountain Project Management Symposium, 19 April 2019
Glen B. Alleman, Copyright © 2019 37/38
Glen B. Alleman, Copyright © 2019
PMI Rocky Mountain Project Management Symposium, 19 April 2019
38/38

Más contenido relacionado

La actualidad más candente

The simple problem of schedule performance indices
The simple problem of schedule performance indicesThe simple problem of schedule performance indices
The simple problem of schedule performance indices
Glen Alleman
 

La actualidad más candente (20)

Improving Project Performance in the DOE
Improving Project Performance in the DOEImproving Project Performance in the DOE
Improving Project Performance in the DOE
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan Development
 
Capabilities Based Planning
Capabilities Based PlanningCapabilities Based Planning
Capabilities Based Planning
 
Narrated Version Dallas MPUG
Narrated Version Dallas MPUGNarrated Version Dallas MPUG
Narrated Version Dallas MPUG
 
Evm+agile (8.8).chapter 9
Evm+agile (8.8).chapter 9Evm+agile (8.8).chapter 9
Evm+agile (8.8).chapter 9
 
Agile project management is systems management
Agile project management is systems managementAgile project management is systems management
Agile project management is systems management
 
Parametric project metrics
Parametric project metricsParametric project metrics
Parametric project metrics
 
Immutable Principles of Project Management (Toronto PMI)
Immutable Principles of Project Management (Toronto PMI)Immutable Principles of Project Management (Toronto PMI)
Immutable Principles of Project Management (Toronto PMI)
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
 
Lean Scope Project Management
Lean Scope Project ManagementLean Scope Project Management
Lean Scope Project Management
 
Agile at scale resources
Agile at scale resourcesAgile at scale resources
Agile at scale resources
 
The simple problem of schedule performance indices
The simple problem of schedule performance indicesThe simple problem of schedule performance indices
The simple problem of schedule performance indices
 
Failure Modes of Integrating Agile with Earned Value Management
Failure Modes of Integrating Agile with Earned Value ManagementFailure Modes of Integrating Agile with Earned Value Management
Failure Modes of Integrating Agile with Earned Value Management
 
Integrated Agile with EVM -- Executive overview
Integrated Agile with EVM -- Executive overviewIntegrated Agile with EVM -- Executive overview
Integrated Agile with EVM -- Executive overview
 
Project Success: The Basis of the Five Immutable Principles
Project Success: The Basis of the Five Immutable PrinciplesProject Success: The Basis of the Five Immutable Principles
Project Success: The Basis of the Five Immutable Principles
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan Development
 
Earned Value Management and Agile
Earned Value Management and AgileEarned Value Management and Agile
Earned Value Management and Agile
 
Agile Program Management - Moving from Principles to Practices
Agile Program Management - Moving from Principles to PracticesAgile Program Management - Moving from Principles to Practices
Agile Program Management - Moving from Principles to Practices
 
Assessing Enterprise Project Risk
Assessing Enterprise Project RiskAssessing Enterprise Project Risk
Assessing Enterprise Project Risk
 
From WBS to Integrated Master Schedule
From WBS to Integrated Master ScheduleFrom WBS to Integrated Master Schedule
From WBS to Integrated Master Schedule
 

Similar a 5 immutable principles of project success (Denver PMI)

Chapter FiveEstimating Project Times and Costs5–1Copyrig
Chapter FiveEstimating Project Times and Costs5–1CopyrigChapter FiveEstimating Project Times and Costs5–1Copyrig
Chapter FiveEstimating Project Times and Costs5–1Copyrig
JinElias52
 

Similar a 5 immutable principles of project success (Denver PMI) (20)

Getting to Done (PMI Denver)
Getting to Done (PMI Denver)Getting to Done (PMI Denver)
Getting to Done (PMI Denver)
 
Showing how to Increase the Probability of Project Success by applying the ...
Showing how to Increase the Probability of Project Success by applying the ...Showing how to Increase the Probability of Project Success by applying the ...
Showing how to Increase the Probability of Project Success by applying the ...
 
Chp 9.0 pb&e agile+evm (v10.3)
Chp 9.0   pb&e agile+evm (v10.3)Chp 9.0   pb&e agile+evm (v10.3)
Chp 9.0 pb&e agile+evm (v10.3)
 
Integrated Program Performance Management
Integrated Program Performance ManagementIntegrated Program Performance Management
Integrated Program Performance Management
 
Integrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master ScheduleIntegrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master Schedule
 
From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...
From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...
From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...
 
Deliverables based planning
Deliverables based planning Deliverables based planning
Deliverables based planning
 
PGCS 2019 Master Class Integrating SE with PPM
PGCS 2019 Master Class Integrating SE with PPMPGCS 2019 Master Class Integrating SE with PPM
PGCS 2019 Master Class Integrating SE with PPM
 
Performance Based Management Handbook
Performance Based Management HandbookPerformance Based Management Handbook
Performance Based Management Handbook
 
Shambaugh & Son
Shambaugh & SonShambaugh & Son
Shambaugh & Son
 
Keynote 2 - SE and PPM a Match Made in Heaven
Keynote 2 - SE and PPM a Match Made in HeavenKeynote 2 - SE and PPM a Match Made in Heaven
Keynote 2 - SE and PPM a Match Made in Heaven
 
Immutable principles of project management
Immutable principles of project managementImmutable principles of project management
Immutable principles of project management
 
Project success 123
Project success 123Project success 123
Project success 123
 
5 Immutable Principles of Capital Project SUccess
5 Immutable Principles of Capital Project SUccess5 Immutable Principles of Capital Project SUccess
5 Immutable Principles of Capital Project SUccess
 
Getting to Done and Some Issues Along the Way
Getting to Done and Some Issues Along the WayGetting to Done and Some Issues Along the Way
Getting to Done and Some Issues Along the Way
 
Value Stream Architecture: What it is and how it can help
Value Stream Architecture: What it is and how it can helpValue Stream Architecture: What it is and how it can help
Value Stream Architecture: What it is and how it can help
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
 
Chapter FiveEstimating Project Times and Costs5–1Copyrig
Chapter FiveEstimating Project Times and Costs5–1CopyrigChapter FiveEstimating Project Times and Costs5–1Copyrig
Chapter FiveEstimating Project Times and Costs5–1Copyrig
 
Breaking the Project Failure Cycle
Breaking the Project Failure CycleBreaking the Project Failure Cycle
Breaking the Project Failure Cycle
 
Ch03_Step_Wise.ppt
Ch03_Step_Wise.pptCh03_Step_Wise.ppt
Ch03_Step_Wise.ppt
 

Más de Glen Alleman

Más de Glen Alleman (20)

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPM
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by Step
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic Abundance
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement Baseline
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
 
Project Management Theory
Project Management TheoryProject Management Theory
Project Management Theory
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and Practices
 

Último

+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
?#DUbAI#??##{{(☎️+971_581248768%)**%*]'#abortion pills for sale in dubai@
 

Último (20)

Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
 
AWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of Terraform
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a Fresher
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processors
 
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
 
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data DiscoveryTrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
 
GenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdfGenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdf
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century education
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
 
Advantages of Hiring UIUX Design Service Providers for Your Business
Advantages of Hiring UIUX Design Service Providers for Your BusinessAdvantages of Hiring UIUX Design Service Providers for Your Business
Advantages of Hiring UIUX Design Service Providers for Your Business
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed texts
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024
 

5 immutable principles of project success (Denver PMI)

  • 1. Five Immutable Principles of Project Success Glen B. Alleman Niwot Ridge, LLC glen.alleman@niwotridge.com +1 303 241 9633 All projects ‒ no matter domain ‒ are fraught with Technical, Cost, and Schedule uncertainties, that create risk to project success. Five Principles of Project Success increase the Probability of Project Success (PoPS) through the application of Risk Management to all Practices and Procedures Glen B. Alleman, Copyright © 2019 PMI Rocky Mountain Project Management Symposium, 19 April 2019 1/38
  • 2. Principles are Required before Practices and Processes can be Successful Do not undertake a project unless it is manifestly important and nearly impossible PMI Rocky Mountain Project Management Symposium, 19 April 2019 Glen B. Alleman, Copyright © 2019 2/38
  • 3. A Few Root Cause’s of Project Failure (100’s are documented in Data Bases) § Unrealistic deadlines, uninformed by risk without margin or corrective actions § Communication deficits between customers and suppliers § Uncontrolled scope changes § Unmitigated resource competition or conflicts § Uncertain dependencies between deliverables, risks, resources and externalities § Failure to manage risk § Insufficient delivery skills § Lack of accountability for outcomes, with no definition of needed Capabilities, their Effectiveness or Performance § Disengaged customers or stakeholders § Lack of business vision and goal with missing tangible Measures Effectiveness and Performance Before we start, let’s look at some failure modes for projects, independent of any domain PMI Rocky Mountain Project Management Symposium, 19 April 2019 Glen B. Alleman, Copyright © 2019 3/38
  • 4. 1. What Does Done Look Like in Units of Measure Meaningful to the Decision Makers? 2. How Do We Get to Done as Needed? 3. Do We Have Enough Time, Resources, And Money To Get to Done? 4. What Impediments Will We Encounter Along The Way To Done? 5. How Do We Know We Are Making Progress Toward Done? 5 Immutable Principles Project Success 4 Glen B. Alleman, Copyright © 2019 PMI Rocky Mountain Project Management Symposium, 19 April 2019 4/38
  • 5. 5 Immutable Principles of Project Success § Done means delivered capabilities that fulfill the project Mission and Vision, described in units of measure meaningful to the decision makers. § There is a Plan to reach Done at needed time for needed budget § There is a Plan for execution of work using the resources in place when needed to reach Done. § Impediments that will be encountered along the way to Done and the Plan how they are to be handled. § Measures of progress to Plan are in units of Physical Percent Complete to assure we arrive on time, on budget, with the needed capabilities. PMI Rocky Mountain Project Management Symposium, 19 April 2019 Glen B. Alleman, Copyright © 2019 5/38
  • 6. PMI Rocky Mountain Project Management Symposium, 19 April 2019 Glen B. Alleman, Copyright © 2019 6/38
  • 7. Three steps to success § Plan – is the strategy for successful completion of the project. § Schedule – are the steps needed to fulfill the Plan. § Execution – is the physical performance of the steps needed to deliver the results defined in the Plan to implement the Strategy. PMI Rocky Mountain Project Management Symposium, 19 April 2019 7/38Glen B. Alleman, Copyright © 2019
  • 8. Scheduling Only comes after Planning § What are the individual, dependent and, sequential steps needed to deliver these capabilities? § The schedule has durations, dependencies, timing, dates, resources and other things related with the Plan. § The idea that these steps “emerge” is fanciful in many situations.Glen B. Alleman, Copyright © 2012 8/38
  • 9. Action Outcome Implement Strategy Ensure Capabilities Prioritize Problems And Solutions Identify Redundancies Deliver Solutions † “Capabilities‒Based Planning: A Methodology for Deciphering Commander’s Intent,” Peter Kossakowski, 10th ICCRTS, Track 12 PMI Rocky Mountain Project Management Symposium, 19 April 2019 Glen B. Alleman, Copyright © 2019 9/38
  • 10. What is a Deliverable? PMI Rocky Mountain Project Management Symposium, 19 April 2019 Glen B. Alleman, Copyright © 2019 10/38
  • 11. Describe Done in Units of Measure Meaningful to the Decision Makers § Develop a list of Capabilities and describe their effectiveness, performance and technical requirements as deliverables. § Develop the interdependencies between these deliverables. § From the needed Capabilities develop the Measures of Effectiveness and Measures of Performance to assure they are what the customer ordered. PMI Rocky Mountain Project Management Symposium, 19 April 2019 Glen B. Alleman, Copyright © 2019 11/38
  • 12. “Done” Provides the Capability to Accomplish Something 19 October 1899 Robert Goddard decided that he wanted to "fly without wings" to Moon. PMI Rocky Mountain Project Management Symposium, 19 April 2019 Glen B. Alleman, Copyright © 2019 12/38
  • 13. Q2. How Do We Get There? Some problems respond to lightweight approaches, like Scrum, DSDM, Crystal, and XP as product development methods. Others require more complex approaches, like a System of Systems (SoS) spiral development processes. In all cases a disciplined approach increases the probability of success – no matter the complexity of the problem or the solution This approach works well when we don’t know what “done” looks like with enough clarity So Does This! Glen B. Alleman, Copyright © 2012 13/38
  • 14. Q3: Do We Have Everything We Need To Get To Done as Planned?Glen B. Alleman, Copyright © 2019 PMI Rocky Mountain Project Management Symposium, 19 April 2019 14/38
  • 15. A Common Problem A Simple Solution We have undue optimism. Use documented procedures – no matter the method – for estimating and planning using historical data. We attempt to avoid risk and uncertainty. Understand and prioritize risks for each critical component empowers management and staff. Use this knowledge to control your optimism. We rely too much on intuitive judgment. Simple statistical models are more often correct than human judgment. Have the numbers to back up your intuition. The Rational Planning of (Software) Projects, Mark C. Paulk, Software Engineering Institute, Carnegie Mellon University, Pittsburgh, PA 15213–3890 PMI Rocky Mountain Project Management Symposium, 19 April 2019 Glen B. Alleman, Copyright © 2019 15/38
  • 16. Getting to Done On–time and On–budget,. With the Needed Capabilities § Construct a schedule for all the work needed to produce the deliverables. § Define “packages of work” for all the activities with deliverables defined as “exit criteria.” § Define progress in units of increasing maturity for each deliverable to it can be compared to the needed maturity at each point in the schedule PMI Rocky Mountain Project Management Symposium, 19 April 2019 Glen B. Alleman, Copyright © 2019 16/38
  • 17. The schedule tells us the order of the planned work PMI Rocky Mountain Project Management Symposium, 19 April 2019 This sketch is Warner Van Braun’s notional concept to get to the moon from Marshall Space Flight Center, Huntsville, Alabama Glen B. Alleman, Copyright © 2019 17/38
  • 18. The Schedule Shows Progress To Plan § Deliverables represent the required mission capabilities and its value as defined by the business and shared by the contractor team. § When all deliverables and their Work Packages are complete, they are not revisited or reopened. – They are 100% done. § The progression of Work Packages defines the increasing maturity of the deliverables. – The mission value of the deliverables to the customer increases as Work Packages are completed. § Completion of Work Packages is represented by the Physical Percent Completion of the deliverables. – Either 0%/100% or Apportioned Milestones are used to state the completion of each Work Package. Mission Capabilities Technical Capabilities Packages of Work Deliverables PMI Rocky Mountain Project Management Symposium, 19 April 2019 Glen B. Alleman, Copyright © 2019 18/38
  • 19. § Vertical traceability ACè SAè PE § Horizontal traceability WPè WPèAC Program Deliverables Define the maturity of a Capability at a point in time. Significant Accomplishments Represent requirements that enable Capabilities. Accomplishment Criteria Exit Criteria for the Work Packages that fulfill Requirements. Package of Work Package of Work Package of Work Package of Work Package of Work Package of Work Package of Work Package Of Work The Schedule Connects Work to Deliverables PMI Rocky Mountain Project Management Symposium, 19 April 2019 Glen B. Alleman, Copyright © 2019 19/38
  • 20. Plan for the needed resources to arrive on time § List the needed staff, materials and facilities for the project. § Assign staff and materials to the work packages. § Estimate the cost of the staff and materials and the impact of this variance on the total project cost and delivery schedule. PMI Rocky Mountain Project Management Symposium, 19 April 2019 Glen B. Alleman, Copyright © 2019 20/38
  • 21. 1. Hope is not a strategy 2. No single point estimate of cost or schedule can be correct 3. Cost, Schedule, and Technical Performance are inseparable 4. Risk management requires adherence to a well defined process 5. Communication is the Number One success factor Glen B. Alleman, Copyright © 2019 PMI Rocky Mountain Project Management Symposium, 19 April 2019 21/38
  • 22. Taxonomy of Uncertainties that Create Irreducible and Reducible Risk. These Require Estimates of Direct and Residual Impacts of these Risks on the Probability of Project Success Glen B. Alleman, Copyright © 2019 PMI Rocky Mountain Project Management Symposium, 19 April 2019 Uncertainty Irreducible (Aleatory) Reducible (Epistemic) Natural Variability Ambiguity about behavior of process Ontological Uncertainty Probability of Event’s Occurrence Probabilistic Impact from Event Period of Exposure to Event Period of Exposure to Aleatory Process 22/38
  • 23. Risk Management Demands Direct Communication Between All Participants in the Project Glen B. Alleman, Copyright © 2019 PMI Rocky Mountain Project Management Symposium, 19 April 2019 23/38
  • 24. § Make a list of risks and rank them by priority. § Assess impact on cost and schedule for each risk and the dependencies of these risks on external and internal drivers. § Assess the probability of occurrence and the probabilistic impact on cost and schedule impact, cost of handling, and cost of the residual risk after handling. Identify impediments to progress and fix them, with Direct work or Margin PMI Rocky Mountain Project Management Symposium, 19 April 2019 Glen B. Alleman, Copyright © 2019 24/38
  • 25. Q5: How Do We Know We Are Making Progress Toward Done? Glen B. Alleman, Copyright © 2019 PMI Rocky Mountain Project Management Symposium, 19 April 2019 25/38
  • 26. 26/3 Primary Measures of Progress to Plan Are We Done? When will we be Done? What will it cost to be Done? §What does Done look like for the customer? §How will we recognize Done when it arrives? §What’s our confidence of getting to Done? §Are we removing or reducing impediments to getting to done as needed?Glen B. Alleman, Copyright © 2019 PMI Rocky Mountain Project Management Symposium, 19 April 2019 26/38
  • 27. § Use actual or predicted values from: ¤ Engineering measurements ¤ Tests ¤ Experiments ¤ Prototypes § For Example: ¤ Response time ¤ Range ¤ Power ¤ Weight ¤ MTTFF/MTTR/MTBF Technical Performance Measure(s) … § Tell us how well a system is achieving the planned performance requirements at the planned time, for the planned cost in units of Physical Percent Complete to Plan PMI Rocky Mountain Project Management Symposium, 19 April 2019 Glen B. Alleman, Copyright © 2019 27/38
  • 28. 28/3 PMI Rocky Mountain Project Management Symposium, 19 April 2019 28/38
  • 29. Trade Offs Between Cost, Schedule, and Technical Performance is a Ponzi Scheme without Margin and a Risk Management Plan When we’re on baseline, the algebraic relationship between C,S,P, means when there is a change in one of these measures everyone looses. Glen B. Alleman, Copyright © 2019 Charles Ponzi, Born March 3, 1882, Italy. Died Jan 18, 1949, Brazil. Served 5 years federal prison, 9 years state prison, deported to Italy. PMI Rocky Mountain Project Management Symposium, 19 April 2019 29/38
  • 30. Cost and Schedule Performance is informed by Risk Informed Technical Performance Measures for each Deliverable. Business Performance is informed with Measures of Effectiveness and Measures of Performance for each Capability produced by the Project. Glen B. Alleman, Copyright © 2019 PMI Rocky Mountain Project Management Symposium, 19 April 2019 30/38
  • 31. § Measuring Physical Percent Complete is the core of every successful project management method. § It answers the question of what “done” looks like in units of measure meaningful to the decision makers. § It answers questions like: ¤ What does done look like for today, this week? ¤ What does done look like for entry/exit into the technical review? ¤ What does done look like for quality control? ¤ What does done look like for the customer? Physical Percent Complete Glen B. Alleman, Copyright © 2019 PMI Rocky Mountain Project Management Symposium, 19 April 2019 31/38
  • 32. § Describe the outcomes of the work effort using language the customer understands § Assign Technical Performance Measures to the Deliverables § Assign Measures of Performance, Measures of Effectiveness, Key Performance Parameters, and Integrate these throughout the project Measure progress to Plan as “Physical Percent Complete” PMI Rocky Mountain Project Management Symposium, 19 April 2019 Glen B. Alleman, Copyright © 2019 32/38
  • 33. The Root Causes Of Program Performance Impacts Unrealistic Performance Expectations, missing Measures of Effectiveness, and Measures of Performance Unrealistic Cost and Schedule estimates based on inadequate risk adjusted growth models Inadequate assessment of risk and unmitigated exposure to these risks without proper handling plans Unanticipated Technical issues without alternative plans and solutions to maintain effectiveness Cost and Schedule Impacts TheLensofthePerformance AssessmentBorrowed from Mr. Gary R. Bliss is the Director, Performance Assessments and Root Cause Analyses (PARCA), in the Office of the Assistant Secretary of Defense for Acquisition. PMI Rocky Mountain Project Management Symposium, 19 April 2019 Glen B. Alleman, Copyright © 2019 33/38
  • 34. The Five Principles Of Project Success Done described in meaningful units A time and budget plan for Done Planned resources to reach Done Handling impediments along the way Measuring progress to plan PMI Rocky Mountain Project Management Symposium, 19 April 2019 Glen B. Alleman, Copyright © 2019 34/38
  • 35. Evidence of the 5 Principles put into Practice in a range of domains Principle Traditional Practice Agile Practice What does Done Look Like in Units of Measure Meaningful to the Decision Makers? Capabilities Based Planning with Measures of Effectiveness and Performance Product Road Map How do we get to Done? Integrated Master Plan Release Plan What Resources needed to get to Done? Resource loaded Integrated Master Schedule Agile development team staff assignments to Sprints, Integration and User Acceptance Testing What are the Impediments to getting to Done? Management Plan for Reducible and Irreducible Uncertainties that Create Risk What are the Meaningful Measures of Progress toward Done? Physical Percent Complete using risk adjusted Performance Management to produce Estimate to Complete Physical Percent Complete measuring progress to Release Plan and Product Roadmap outcomes as planned Glen B. Alleman, Copyright © 2019 PMI Rocky Mountain Project Management Symposium, 19 April 2019 35/38
  • 36. The Project Train Wreck Starts When There Is … § Inattention to budget, schedule and technical responsibilities. § Work authorizations not always followed (out of sequence work). § Issues with Budget, Schedule, and Technical data reconciliation. § Lack of an Integrated Management System. § Plans fluctuations with frequent replanning. § Improper use of Management Reserve. § Performance Measures don’t reflect actual Physical Percent Complete. PMI Rocky Mountain Project Management Symposium, 19 April 2019 § Lack of predictive variance analysis from data. § Untimely and unrealistic Revised Estimates. § Progress to Plan not monitored in a regular and consistent manner. § Lack of connection between cost, schedule, and technical performance. § Lack of project performance oversight by independent surveillance team. § Managerial corrective actions not connected to Risk Management Processes. Glen B. Alleman, Copyright © 2019 36/38
  • 37. Five Immutable Principles Tested as Questions Capabilities Requirements Plans Execution 2. What technical and operational requirements are needed to deliver these capabilities? 1. What capabilities are needed to fulfill the Concept of Operations, the Mission and Vision, or the Business System Requirements? 3. What schedule delivers the product or services on time to meet the requirements? 4. What periodic measures of physical percent complete assure progress to plan? What impediments to success, their mitigations, retirement plans, or “buy downs are in place to increase the probability of success?” + Continuous Risk Management Œ  Ž   PMI Rocky Mountain Project Management Symposium, 19 April 2019 Glen B. Alleman, Copyright © 2019 37/38
  • 38. Glen B. Alleman, Copyright © 2019 PMI Rocky Mountain Project Management Symposium, 19 April 2019 38/38