SlideShare una empresa de Scribd logo
1 de 31
Descargar para leer sin conexión
1/31




                  A GENTLE INTRODUCTION TO
                  EARNED VALUE
                  MANAGEMENT SYSTEMS
                  “Good metrics let us see if we are doing the right
Glen B. Alleman   things and doing them well."
What Do Project Managers Need to Know to Be
Successful?

   Is the project on schedule?
   Is the project on budget?
   How much will this project cost on the end date?
   What is the end date for this project?
   Simple project analysis tools can answer these questions
    using time and cost tracking
   How much is it costing us to earn each unit of value
    –   $1.00 spent returns $X.00 of value?
    –   How much of the budget “should have been” spent at this point in
        the project?
    –   How much “value” has the work on the project “earned” so far?


                                                                           2/31
What Is Earned Value Analysis?

   It is a way to measure the amount of work actually
    performed on a project.
   It is a way to forecast a project’s cost and
    completion date using historical and statistical
    projections.
   It is a way to tell how well a project is
    “performing” compared to its original plan.
   Given this information it is a way to forecast how
    well the project will perform in the future.

                                                         3/31
Some Introductory Definitions
4/31
       In (olde) and (current )notation
          Budgeted Cost of Work Scheduled (BCWS)(PC)
           “The Planned Cost”
           –   This is the total budgeted cost. It answers the question “how much do we plan to
               spend?” A second question that is answered is “How much work should be been
               completed by this date?”
          Budgeted Cost of Work Performed (BCWP)(PV)
           “Earned Value”
           –   This is the cost originally budgeted to accomplish the work that has been
               completed. It answers the question “how much work has been actually
               completed?”
          Actual Cost of Work Performed (ACWP)(AC)
           “The Investment Cost”
           –   The actual cost to accomplish all the work that was performed by a specific
               date. It answers the question “how much did we actually spend to deliver the
               Earned Value?”
Basic Formulas Of Earned Value Management
            Simple EVMS Terms
BCWS        The planned of the work to be performed
BCWP        The “earned value” of the performed work
ACWP        The actual costs – in dollars – to complete the planned work
BAC         The budget to complete the project
            Cost and Schedule Variance
SV          Schedule Variance                            BCWP – BCWS
CV          Cost Variance                                BCWP – ACWP
SPI         Schedule Performance Index                   BCWP / BCWS
CPI         Cost Performance Index                       BCWP / ACWP
EAC         Estimate at Complete                         ACWP + (BAC – BCWP)
TCPI        To Complete Performance Index                (BAC – BCWP) / (EAC – ACWP)
ISAC        Independent Schedule at Complete             Schedule / SPI
VAC         Variance at Complete                         BAC – EAC
5 Print   this page and keep in your notebook. No one, not even the pros can remember these
                                 acronyms without a cheat sheet
6/31
       A Simple Edible Example
       It’s the holidays, it’s cookie baking time! Let’s use Earned Value to
       manage our Christmas Cookie project.
EVMS Of Our Holiday Cookie Baking
7/31
       Process
          Our Christmas Cookie           Analysis after one (1)
           “Plan”                          hour of baking we’ve
            40 cookies per batch          made …
            5 batches per hour (200          150 edible cookies
             cookies per hour)                  some were burnt,
            Schedule: 5 hours to               some hit the floor,
             make 1,000 cookies (a              the kids ate some of the
             big neighborhood)                   dough,
                                                fed some to the dog.
            Budgeted cost = $0.05
             per cookie                       Actual cost of ingredients
            Total Budget = $50.00
                                               after one hour (ACWP)
             for the 1,000 cookies             = $9.00
After One Hour of Making Cookies

        Simple EVMS
BCWS                                     $10.00     Planned cost
BCWP    150 cookies X $0.05 per Cookie    $7.50     Product cost
ACWP                                      $9.00     Materials cost
        Cost and Schedule Variance
SV      BCWP – BCWS ($7.50 - $10.00)     –$2.50     We’re behind schedule
CV      BCWP – ACWP ($7.50 - $9.00)      –$1.50     We’re over budget
SPI     BCWP / BCWS                        0.75     25% behind schedule
CPI     BCWP / ACWP                        0.833 17% over budget




                                             8/31
What’s Going To Happen At The End
 Of The Project?

       Forecasting our production
IEAC   BAC / CPI ($50.00 / 0.833)     $60.00      Our plan was $50.00, darn
VAC    BAC – IEAC ($50.00 – $60.00)   $10.00      We’ll be $10 over budget
ISAC   5 hours / SPI (5 / 0.75)         6.67      And we’re gonna be late




                                           9/31
Can We Catch Up In Time?
10




                                     Forecasting the future
     To Complete Performance Index    (Budget – BCWP) / (EAC – ACWP)
     TCPI                             (50.00 – 7.50) / (500.00 – 9.00)   1.036
                                      42.50 / 41.00
A Simple EVMS Chart
   (The linear form is never this way in practice, it is an S-Curve)


$50.00


$40.00
                                    BCWS                          SV
                                                                  in $   CV
$30.00


$20.00   SV in hours

                            ACWP
$10.00
                           BCWP

                Hour 1     Hour 2   Hour 3    Hour 4     Hour 5



                                                                              11/31
PUTTING THESE “SIMPLE”
CONCEPTS INTO PRACTICE
EVMS can be deployed in many ways. For us the straight
forward way is to “micro–schedule” the work activities.
                                                          12/31
A Micro–Schedule
   Micro–scheduling does NOT mean micro–managing.
   It means planning at a sufficient level of detail to
    identify useful tasks that can be measured in days (3 to
    5) or at most a week.
   Micro–schedules consists of:
     Objective completion criteria – so we know when we are
      done.
     “Budgets” and “Values” – usually representing person days
      and some “measurable” value to the customer in terms of
      dollars.
     Planned Completion Dates – so we know when to expect
      these tasks to be done.

                                      13/31
Some Fundamental Concepts of EVMS

   Never relate what was planned to be spent (BCWS) to
    the actual amount spent (ACWP).
     This tells us nothing of value
     It can warp our thinking into attempting to under–spend our
      allowed amount to report favorable numbers.
     Only report what was actually spent (ACWP) against what
      “value” was delivered for that planned investment (BCWP)
   Cost Performance (CV) reports what has been
    accomplished (BCWP) versus what was invested to
    accomplish that work (ACWP).

                                       14/31
15/31




A FRAMEWORK FOR
DEPLOYING EVMS
Let’s do it the simple way with some common sense†
First the Bad News
16
ANSI/EIA–748A–2002 And Success Criteria Of
Earned Value Management

   The EIA 748 specification calls out 32 performance
    criteria required for compliance.
   These criteria are too complex for our “agile”
    environment.
   There are 10 key criteria that can be deployed
    here.




                                                         17/31
ANSI/EIA–748A–2002 And Success
     Criteria Of Earned Value Management
18
10 Criteria For Successful EVMS
1. Define authorized work elements
2. Identify project organizational structure
5. Provide integrated planning, scheduling, budgeting, work
    authorization, and cost accumulation processes
6. Schedule the authorized work in a sequential manner that
    identifies the significant task dependencies
7. Identify physical products and organizations
8. Establish and maintain time–phased budget baseline
16. Record direct costs consistently in a formal manner
23. Periodically generate project metrics
25. Develop revised cost estimates–at–completion based on
    performance to date
28. Incorporate authorized changes in a timely manner

                                        19/31
10 Criteria For Successful EVMS
20
Define Authorized Work Elements
   Create a Work Breakdown Structure (WBS) for all
    activities at the micro–schedule level
   The scope of the entire project must be defined in order
    to measure performance.
     This is a problem for agile methods, since scope evolves as
      the project evolves
     Schedule major iterations on 2 to 3 week boundaries
     Generate “macro” estimates of future work and “micro”
      estimates of the current iteration's work
   Defined project objectives, deliverables, and key
    milestones are based primarily on experience
                                        21/31
Identify Project Organizational
Structure
   Identify the structure of the functional organizations
    performing the work
   Define all organizational elements responsible for
    delivering value
   Identify who is doing what and what value they are
    delivering
   Assign all tasks to specific named resources
   Identify the major milestones and those responsible
    for meeting the commitments represented by these
    milestones
                                   22/31
Provide Integrated Planning, Scheduling, Budgeting,
Work Authorization, And Cost Accumulation Processes

   Provide integration of the firm’s:
     Planning,

     Scheduling,

     Budgeting,

     Work  Authorization
     Cost accumulation

   Project management processes should be integrated
    with the WBS and the functional organization.


                                   23/31
Schedule The Authorized Work In A Sequential Manner
That Identifies The Significant Task Dependencies

   Describe the work sequence
   Identify significant dependencies required to meet
    the requirements
   Identify which tasks are impeading the process of
    other tasks
   Create a “master schedule” for larger projects to
    connect the subordinate projects



                                  24/31
Identify Physical Products And The
Organizations That Produce Them
   All project must be able to identify and measure
    physical performance
   Define metrics which convert to “planned values” into
    “earned values”
   Project must specify:
     Physical Products
     Deliverables
     Outputs
     Metrics
     Milestones
     Technical performance indicators



                                         25/31
Establish And Maintain A Time–phased
Performance Measurement Baseline
   Establish initial budgets on internal management
    estimates and external negotiated targets
   Budget for long–term efforts must be held at higher
    levels of the organization
   Time–phased budget is required to measure
    performance
     Staff

     Other   Direct Costs (ODC)


                                   26/31
Record Direct Cost Consistency In A
Formal System
   “Applied Direct Costs” is the preferred method of
    accounting for the accrual of “value”
   Isolate Level of Effort costs in a separate WBS
    element




                                  27/31
Periodically Generate Project Metrics

   The amount of planned versus budget earned for
    the work accomplished
   The amount of budget earned versus the actual
    direct costs for the same work
     This   is the “cost variance”
   This differentiates EVMS from other “actual versus
    budget” cost analysis
     Weekly   measures are now the “norm”
     Comparisons need to be detailed enough to provide
      intervention opportunities

                                      28/31
Develop Revised Cost Estimates–at–completion
(EAC) Based On Performance To Date

   Compare this information with the performance
    measure baseline to identify variances at
    completion




                                29/31
Incorporate Authorized Changes In A
Timely Manner
   All changes must be addressed as they effect
    budget and schedule
   Base changes on the estimated amount and
    assignment to functional organizations needs to be
    recorded as well
   All approved changes must be incorporated into the
    project baseline



                                 30/31
Ten Benefits of EVMS
   It is a single management control system to provide reliable and consistent
    data on project performance.
   It integrates work, schedule, and cost using a work breakdown structure.
   The associated database of completed projects is useful for comparative
    analysis.
   The cumulative cost performance index (CPI) provides an early warning
    signal.
   The schedule performance index provides an early warning signal.
   The CPI is a predictor for the final cost of the project.
   It uses an index–based method to forecast the final cost of the project.
   The “to-complete” performance index allows evaluation of the forecasted
    final cost.
   The periodic (e.g., weekly or monthly) CPI is a benchmark.
   The management by exception principle can reduce information overload.

                                                31/31

Más contenido relacionado

La actualidad más candente

Earned value
Earned valueEarned value
Earned valueOliver
 
Introduction to Earned Value Management
Introduction to Earned Value ManagementIntroduction to Earned Value Management
Introduction to Earned Value ManagementUnanet
 
EVM of Project Management...
EVM of Project Management...EVM of Project Management...
EVM of Project Management...Fahad Ali
 
Program Evaluation and Review Technique
Program Evaluation and Review TechniqueProgram Evaluation and Review Technique
Program Evaluation and Review TechniqueRaymund Sanchez
 
A simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementA simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementProPM Academy
 
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 MeetingDealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 MeetingChris Carson
 
Project Monitoring And Controlling
Project Monitoring And ControllingProject Monitoring And Controlling
Project Monitoring And ControllingTom Milner
 
Project Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge AreaProject Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge AreaJoshua Render
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 waleed hamdy
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTS.Vijaya Bhaskar
 
Earned value analysis - presentation
Earned value analysis  -  presentationEarned value analysis  -  presentation
Earned value analysis - presentationProPM Academy
 
Earned Value Management (EVM) Limitations
Earned Value Management (EVM) LimitationsEarned Value Management (EVM) Limitations
Earned Value Management (EVM) LimitationsIftikhar Anjum
 
Network problem cpm and pert BY MITESH KUMAR
Network problem cpm and pert BY MITESH KUMARNetwork problem cpm and pert BY MITESH KUMAR
Network problem cpm and pert BY MITESH KUMARMitesh Kumar
 

La actualidad más candente (20)

Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Earned value
Earned valueEarned value
Earned value
 
Introduction to Earned Value Management
Introduction to Earned Value ManagementIntroduction to Earned Value Management
Introduction to Earned Value Management
 
EVM of Project Management...
EVM of Project Management...EVM of Project Management...
EVM of Project Management...
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting
 
Program Evaluation and Review Technique
Program Evaluation and Review TechniqueProgram Evaluation and Review Technique
Program Evaluation and Review Technique
 
A simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementA simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value Management
 
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 MeetingDealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
 
Project Monitoring And Controlling
Project Monitoring And ControllingProject Monitoring And Controlling
Project Monitoring And Controlling
 
Project Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge AreaProject Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge Area
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
 
Project portfolio management
Project portfolio managementProject portfolio management
Project portfolio management
 
Earned value analysis - presentation
Earned value analysis  -  presentationEarned value analysis  -  presentation
Earned value analysis - presentation
 
Earned Value Management (EVM) Limitations
Earned Value Management (EVM) LimitationsEarned Value Management (EVM) Limitations
Earned Value Management (EVM) Limitations
 
Network problem cpm and pert BY MITESH KUMAR
Network problem cpm and pert BY MITESH KUMARNetwork problem cpm and pert BY MITESH KUMAR
Network problem cpm and pert BY MITESH KUMAR
 
Pert & Cpm
Pert & CpmPert & Cpm
Pert & Cpm
 
Pert Analysis
Pert AnalysisPert Analysis
Pert Analysis
 

Destacado

Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value ManagementGlen Alleman
 
A simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in actionA simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in actionPlanisware
 
Earned Value Reporting
Earned Value ReportingEarned Value Reporting
Earned Value Reportingcfreema7
 
Earned value in five easy pieces
Earned value in five easy piecesEarned value in five easy pieces
Earned value in five easy piecesGlen Alleman
 
Big data meets evm (submitted)
Big data meets evm (submitted)Big data meets evm (submitted)
Big data meets evm (submitted)Glen Alleman
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value ManagementMansoor Shoaib
 
Earned Value Management Meets Big Data
Earned Value Management Meets Big DataEarned Value Management Meets Big Data
Earned Value Management Meets Big DataGlen Alleman
 
Measurement News Webinar
Measurement News WebinarMeasurement News Webinar
Measurement News WebinarGlen Alleman
 
Earned value management with Examples | Control Cost | PMBOK | PMP
Earned value management with Examples | Control Cost | PMBOK | PMPEarned value management with Examples | Control Cost | PMBOK | PMP
Earned value management with Examples | Control Cost | PMBOK | PMPJustAcademy
 
Successfully Integrating Agile and Earned Value
Successfully Integrating Agile and Earned ValueSuccessfully Integrating Agile and Earned Value
Successfully Integrating Agile and Earned ValueGlen Alleman
 
Agile in the government
Agile in the government Agile in the government
Agile in the government Glen Alleman
 
Agile at scale resources
Agile at scale resourcesAgile at scale resources
Agile at scale resourcesGlen Alleman
 
Applying the checklist manifesto for project management success
Applying the checklist manifesto for project management successApplying the checklist manifesto for project management success
Applying the checklist manifesto for project management successGlen Alleman
 
The simple problem of schedule performance indices
The simple problem of schedule performance indicesThe simple problem of schedule performance indices
The simple problem of schedule performance indicesGlen Alleman
 
Flawless Execution
Flawless ExecutionFlawless Execution
Flawless ExecutionGlen Alleman
 
Earned Value Analysis - Basic Concepts
Earned Value Analysis  - Basic ConceptsEarned Value Analysis  - Basic Concepts
Earned Value Analysis - Basic ConceptsRicardo Viana Vargas
 

Destacado (20)

Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value Management
 
A simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in actionA simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in action
 
Earned Value Reporting
Earned Value ReportingEarned Value Reporting
Earned Value Reporting
 
Control systems
Control systemsControl systems
Control systems
 
Earned Value fundamentals
Earned Value fundamentalsEarned Value fundamentals
Earned Value fundamentals
 
Earned value in five easy pieces
Earned value in five easy piecesEarned value in five easy pieces
Earned value in five easy pieces
 
Back to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinarBack to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinar
 
Ev+agile=success
Ev+agile=successEv+agile=success
Ev+agile=success
 
Big data meets evm (submitted)
Big data meets evm (submitted)Big data meets evm (submitted)
Big data meets evm (submitted)
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Earned Value Management Meets Big Data
Earned Value Management Meets Big DataEarned Value Management Meets Big Data
Earned Value Management Meets Big Data
 
Measurement News Webinar
Measurement News WebinarMeasurement News Webinar
Measurement News Webinar
 
Earned value management with Examples | Control Cost | PMBOK | PMP
Earned value management with Examples | Control Cost | PMBOK | PMPEarned value management with Examples | Control Cost | PMBOK | PMP
Earned value management with Examples | Control Cost | PMBOK | PMP
 
Successfully Integrating Agile and Earned Value
Successfully Integrating Agile and Earned ValueSuccessfully Integrating Agile and Earned Value
Successfully Integrating Agile and Earned Value
 
Agile in the government
Agile in the government Agile in the government
Agile in the government
 
Agile at scale resources
Agile at scale resourcesAgile at scale resources
Agile at scale resources
 
Applying the checklist manifesto for project management success
Applying the checklist manifesto for project management successApplying the checklist manifesto for project management success
Applying the checklist manifesto for project management success
 
The simple problem of schedule performance indices
The simple problem of schedule performance indicesThe simple problem of schedule performance indices
The simple problem of schedule performance indices
 
Flawless Execution
Flawless ExecutionFlawless Execution
Flawless Execution
 
Earned Value Analysis - Basic Concepts
Earned Value Analysis  - Basic ConceptsEarned Value Analysis  - Basic Concepts
Earned Value Analysis - Basic Concepts
 

Similar a Earned Value Management for Agile Projects

Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxsagarlesley
 
Symposium 2016 : CONF. 401 Jonathan Shriqui EVM: Go Beyond the Numbers
Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the NumbersSymposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers
Symposium 2016 : CONF. 401 Jonathan Shriqui EVM: Go Beyond the NumbersPMI-Montréal
 
PMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - FormulasPMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - FormulasAnand Bobade
 
EARNED VALUE MANAGEMENT ANALYS 1.ppt
EARNED VALUE MANAGEMENT ANALYS 1.pptEARNED VALUE MANAGEMENT ANALYS 1.ppt
EARNED VALUE MANAGEMENT ANALYS 1.pptBetshaTizazu1
 
Module 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.pptModule 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.pptAsBali1
 
Program Management 2.0: Work Breakdown Structure
Program Management 2.0: Work Breakdown StructureProgram Management 2.0: Work Breakdown Structure
Program Management 2.0: Work Breakdown StructureJohn Carter
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)Ejaz Bhatti
 
The simple problem of schedule performance indices
The simple problem of schedule performance indicesThe simple problem of schedule performance indices
The simple problem of schedule performance indicesGlen Alleman
 
What Is Earned Value Analysis
What Is Earned Value AnalysisWhat Is Earned Value Analysis
What Is Earned Value AnalysisSimonRobertson
 
Project Monitoring and Control
Project Monitoring and ControlProject Monitoring and Control
Project Monitoring and Controlguy_davis
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisBECM, RUET, Bangladesh
 
Pppl evms training_02
Pppl evms training_02Pppl evms training_02
Pppl evms training_02apocalypto1
 

Similar a Earned Value Management for Agile Projects (20)

EVMS Made Simple
EVMS Made SimpleEVMS Made Simple
EVMS Made Simple
 
Basics of EVM.pdf
Basics of  EVM.pdfBasics of  EVM.pdf
Basics of EVM.pdf
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
 
EVA - Metrics.ppt
EVA - Metrics.pptEVA - Metrics.ppt
EVA - Metrics.ppt
 
Symposium 2016 : CONF. 401 Jonathan Shriqui EVM: Go Beyond the Numbers
Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the NumbersSymposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers
Symposium 2016 : CONF. 401 Jonathan Shriqui EVM: Go Beyond the Numbers
 
PMP COST FORMULAE
PMP COST FORMULAEPMP COST FORMULAE
PMP COST FORMULAE
 
Project Management EVM & SCBA
Project Management EVM & SCBAProject Management EVM & SCBA
Project Management EVM & SCBA
 
PMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - FormulasPMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - Formulas
 
EARNED VALUE MANAGEMENT ANALYS 1.ppt
EARNED VALUE MANAGEMENT ANALYS 1.pptEARNED VALUE MANAGEMENT ANALYS 1.ppt
EARNED VALUE MANAGEMENT ANALYS 1.ppt
 
Module 06 Adv PM Budget Mgmt.ppt
Module 06 Adv PM Budget Mgmt.pptModule 06 Adv PM Budget Mgmt.ppt
Module 06 Adv PM Budget Mgmt.ppt
 
Module 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.pptModule 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.ppt
 
Program Management 2.0: Work Breakdown Structure
Program Management 2.0: Work Breakdown StructureProgram Management 2.0: Work Breakdown Structure
Program Management 2.0: Work Breakdown Structure
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)
 
Earned value management
Earned value managementEarned value management
Earned value management
 
The simple problem of schedule performance indices
The simple problem of schedule performance indicesThe simple problem of schedule performance indices
The simple problem of schedule performance indices
 
What Is Earned Value Analysis
What Is Earned Value AnalysisWhat Is Earned Value Analysis
What Is Earned Value Analysis
 
IT Park - Earned Value ppt.ppt
IT Park - Earned Value ppt.pptIT Park - Earned Value ppt.ppt
IT Park - Earned Value ppt.ppt
 
Project Monitoring and Control
Project Monitoring and ControlProject Monitoring and Control
Project Monitoring and Control
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
Pppl evms training_02
Pppl evms training_02Pppl evms training_02
Pppl evms training_02
 

Más de Glen Alleman

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planningGlen Alleman
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSGlen Alleman
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project SuccessGlen Alleman
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMGlen Alleman
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk managementGlen Alleman
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk ManagementGlen Alleman
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Glen Alleman
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringGlen Alleman
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideGlen Alleman
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineGlen Alleman
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Glen Alleman
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by StepGlen Alleman
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)Glen Alleman
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possibleGlen Alleman
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic AbundanceGlen Alleman
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planningGlen Alleman
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for AgileGlen Alleman
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement BaselineGlen Alleman
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaGlen Alleman
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure RolloutGlen Alleman
 

Más de Glen Alleman (20)

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPM
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by Step
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic Abundance
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement Baseline
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
 

Último

08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking MenDelhi Call girls
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking MenDelhi Call girls
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptxHampshireHUG
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationMichael W. Hawkins
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024Results
 
Google AI Hackathon: LLM based Evaluator for RAG
Google AI Hackathon: LLM based Evaluator for RAGGoogle AI Hackathon: LLM based Evaluator for RAG
Google AI Hackathon: LLM based Evaluator for RAGSujit Pal
 
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Alan Dix
 
Maximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxMaximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxOnBoard
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesSinan KOZAK
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdfhans926745
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slidespraypatel2
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Miguel Araújo
 
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking MenDelhi Call girls
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfEnterprise Knowledge
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersThousandEyes
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonetsnaman860154
 
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure servicePooja Nehwal
 
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024BookNet Canada
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationRadu Cotescu
 

Último (20)

08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024
 
Google AI Hackathon: LLM based Evaluator for RAG
Google AI Hackathon: LLM based Evaluator for RAGGoogle AI Hackathon: LLM based Evaluator for RAG
Google AI Hackathon: LLM based Evaluator for RAG
 
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
 
Maximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxMaximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptx
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen Frames
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slides
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
 
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonets
 
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
 
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 

Earned Value Management for Agile Projects

  • 1. 1/31 A GENTLE INTRODUCTION TO EARNED VALUE MANAGEMENT SYSTEMS “Good metrics let us see if we are doing the right Glen B. Alleman things and doing them well."
  • 2. What Do Project Managers Need to Know to Be Successful?  Is the project on schedule?  Is the project on budget?  How much will this project cost on the end date?  What is the end date for this project?  Simple project analysis tools can answer these questions using time and cost tracking  How much is it costing us to earn each unit of value – $1.00 spent returns $X.00 of value? – How much of the budget “should have been” spent at this point in the project? – How much “value” has the work on the project “earned” so far? 2/31
  • 3. What Is Earned Value Analysis?  It is a way to measure the amount of work actually performed on a project.  It is a way to forecast a project’s cost and completion date using historical and statistical projections.  It is a way to tell how well a project is “performing” compared to its original plan.  Given this information it is a way to forecast how well the project will perform in the future. 3/31
  • 4. Some Introductory Definitions 4/31 In (olde) and (current )notation  Budgeted Cost of Work Scheduled (BCWS)(PC) “The Planned Cost” – This is the total budgeted cost. It answers the question “how much do we plan to spend?” A second question that is answered is “How much work should be been completed by this date?”  Budgeted Cost of Work Performed (BCWP)(PV) “Earned Value” – This is the cost originally budgeted to accomplish the work that has been completed. It answers the question “how much work has been actually completed?”  Actual Cost of Work Performed (ACWP)(AC) “The Investment Cost” – The actual cost to accomplish all the work that was performed by a specific date. It answers the question “how much did we actually spend to deliver the Earned Value?”
  • 5. Basic Formulas Of Earned Value Management Simple EVMS Terms BCWS The planned of the work to be performed BCWP The “earned value” of the performed work ACWP The actual costs – in dollars – to complete the planned work BAC The budget to complete the project Cost and Schedule Variance SV Schedule Variance BCWP – BCWS CV Cost Variance BCWP – ACWP SPI Schedule Performance Index BCWP / BCWS CPI Cost Performance Index BCWP / ACWP EAC Estimate at Complete ACWP + (BAC – BCWP) TCPI To Complete Performance Index (BAC – BCWP) / (EAC – ACWP) ISAC Independent Schedule at Complete Schedule / SPI VAC Variance at Complete BAC – EAC 5 Print this page and keep in your notebook. No one, not even the pros can remember these acronyms without a cheat sheet
  • 6. 6/31 A Simple Edible Example It’s the holidays, it’s cookie baking time! Let’s use Earned Value to manage our Christmas Cookie project.
  • 7. EVMS Of Our Holiday Cookie Baking 7/31 Process  Our Christmas Cookie  Analysis after one (1) “Plan” hour of baking we’ve  40 cookies per batch made …  5 batches per hour (200  150 edible cookies cookies per hour)  some were burnt,  Schedule: 5 hours to  some hit the floor, make 1,000 cookies (a  the kids ate some of the big neighborhood) dough,  fed some to the dog.  Budgeted cost = $0.05 per cookie  Actual cost of ingredients  Total Budget = $50.00 after one hour (ACWP) for the 1,000 cookies = $9.00
  • 8. After One Hour of Making Cookies Simple EVMS BCWS $10.00 Planned cost BCWP 150 cookies X $0.05 per Cookie $7.50 Product cost ACWP $9.00 Materials cost Cost and Schedule Variance SV BCWP – BCWS ($7.50 - $10.00) –$2.50 We’re behind schedule CV BCWP – ACWP ($7.50 - $9.00) –$1.50 We’re over budget SPI BCWP / BCWS 0.75 25% behind schedule CPI BCWP / ACWP 0.833 17% over budget 8/31
  • 9. What’s Going To Happen At The End Of The Project? Forecasting our production IEAC BAC / CPI ($50.00 / 0.833) $60.00 Our plan was $50.00, darn VAC BAC – IEAC ($50.00 – $60.00) $10.00 We’ll be $10 over budget ISAC 5 hours / SPI (5 / 0.75) 6.67 And we’re gonna be late 9/31
  • 10. Can We Catch Up In Time? 10 Forecasting the future To Complete Performance Index  (Budget – BCWP) / (EAC – ACWP) TCPI  (50.00 – 7.50) / (500.00 – 9.00) 1.036  42.50 / 41.00
  • 11. A Simple EVMS Chart (The linear form is never this way in practice, it is an S-Curve) $50.00 $40.00 BCWS SV in $ CV $30.00 $20.00 SV in hours ACWP $10.00 BCWP Hour 1 Hour 2 Hour 3 Hour 4 Hour 5 11/31
  • 12. PUTTING THESE “SIMPLE” CONCEPTS INTO PRACTICE EVMS can be deployed in many ways. For us the straight forward way is to “micro–schedule” the work activities. 12/31
  • 13. A Micro–Schedule  Micro–scheduling does NOT mean micro–managing.  It means planning at a sufficient level of detail to identify useful tasks that can be measured in days (3 to 5) or at most a week.  Micro–schedules consists of:  Objective completion criteria – so we know when we are done.  “Budgets” and “Values” – usually representing person days and some “measurable” value to the customer in terms of dollars.  Planned Completion Dates – so we know when to expect these tasks to be done. 13/31
  • 14. Some Fundamental Concepts of EVMS  Never relate what was planned to be spent (BCWS) to the actual amount spent (ACWP).  This tells us nothing of value  It can warp our thinking into attempting to under–spend our allowed amount to report favorable numbers.  Only report what was actually spent (ACWP) against what “value” was delivered for that planned investment (BCWP)  Cost Performance (CV) reports what has been accomplished (BCWP) versus what was invested to accomplish that work (ACWP). 14/31
  • 15. 15/31 A FRAMEWORK FOR DEPLOYING EVMS Let’s do it the simple way with some common sense†
  • 16. First the Bad News 16
  • 17. ANSI/EIA–748A–2002 And Success Criteria Of Earned Value Management  The EIA 748 specification calls out 32 performance criteria required for compliance.  These criteria are too complex for our “agile” environment.  There are 10 key criteria that can be deployed here. 17/31
  • 18. ANSI/EIA–748A–2002 And Success Criteria Of Earned Value Management 18
  • 19. 10 Criteria For Successful EVMS 1. Define authorized work elements 2. Identify project organizational structure 5. Provide integrated planning, scheduling, budgeting, work authorization, and cost accumulation processes 6. Schedule the authorized work in a sequential manner that identifies the significant task dependencies 7. Identify physical products and organizations 8. Establish and maintain time–phased budget baseline 16. Record direct costs consistently in a formal manner 23. Periodically generate project metrics 25. Develop revised cost estimates–at–completion based on performance to date 28. Incorporate authorized changes in a timely manner 19/31
  • 20. 10 Criteria For Successful EVMS 20
  • 21. Define Authorized Work Elements  Create a Work Breakdown Structure (WBS) for all activities at the micro–schedule level  The scope of the entire project must be defined in order to measure performance.  This is a problem for agile methods, since scope evolves as the project evolves  Schedule major iterations on 2 to 3 week boundaries  Generate “macro” estimates of future work and “micro” estimates of the current iteration's work  Defined project objectives, deliverables, and key milestones are based primarily on experience 21/31
  • 22. Identify Project Organizational Structure  Identify the structure of the functional organizations performing the work  Define all organizational elements responsible for delivering value  Identify who is doing what and what value they are delivering  Assign all tasks to specific named resources  Identify the major milestones and those responsible for meeting the commitments represented by these milestones 22/31
  • 23. Provide Integrated Planning, Scheduling, Budgeting, Work Authorization, And Cost Accumulation Processes  Provide integration of the firm’s:  Planning,  Scheduling,  Budgeting,  Work Authorization  Cost accumulation  Project management processes should be integrated with the WBS and the functional organization. 23/31
  • 24. Schedule The Authorized Work In A Sequential Manner That Identifies The Significant Task Dependencies  Describe the work sequence  Identify significant dependencies required to meet the requirements  Identify which tasks are impeading the process of other tasks  Create a “master schedule” for larger projects to connect the subordinate projects 24/31
  • 25. Identify Physical Products And The Organizations That Produce Them  All project must be able to identify and measure physical performance  Define metrics which convert to “planned values” into “earned values”  Project must specify:  Physical Products  Deliverables  Outputs  Metrics  Milestones  Technical performance indicators 25/31
  • 26. Establish And Maintain A Time–phased Performance Measurement Baseline  Establish initial budgets on internal management estimates and external negotiated targets  Budget for long–term efforts must be held at higher levels of the organization  Time–phased budget is required to measure performance  Staff  Other Direct Costs (ODC) 26/31
  • 27. Record Direct Cost Consistency In A Formal System  “Applied Direct Costs” is the preferred method of accounting for the accrual of “value”  Isolate Level of Effort costs in a separate WBS element 27/31
  • 28. Periodically Generate Project Metrics  The amount of planned versus budget earned for the work accomplished  The amount of budget earned versus the actual direct costs for the same work  This is the “cost variance”  This differentiates EVMS from other “actual versus budget” cost analysis  Weekly measures are now the “norm”  Comparisons need to be detailed enough to provide intervention opportunities 28/31
  • 29. Develop Revised Cost Estimates–at–completion (EAC) Based On Performance To Date  Compare this information with the performance measure baseline to identify variances at completion 29/31
  • 30. Incorporate Authorized Changes In A Timely Manner  All changes must be addressed as they effect budget and schedule  Base changes on the estimated amount and assignment to functional organizations needs to be recorded as well  All approved changes must be incorporated into the project baseline 30/31
  • 31. Ten Benefits of EVMS  It is a single management control system to provide reliable and consistent data on project performance.  It integrates work, schedule, and cost using a work breakdown structure.  The associated database of completed projects is useful for comparative analysis.  The cumulative cost performance index (CPI) provides an early warning signal.  The schedule performance index provides an early warning signal.  The CPI is a predictor for the final cost of the project.  It uses an index–based method to forecast the final cost of the project.  The “to-complete” performance index allows evaluation of the forecasted final cost.  The periodic (e.g., weekly or monthly) CPI is a benchmark.  The management by exception principle can reduce information overload. 31/31