SlideShare una empresa de Scribd logo
1 de 4
Beyond CPI/SPI
Forecasting the Corrective Actions
Needed to Keep the Program GREEN
Glen Alleman and Tom Coonce
The Situation
We’re a Program Controls Manager on ACAT1 and ACAT2 programs using DCMA
Validated Earned Value Management, with monthly reporting of CPI and SPI
along with the other variables in the IPMR (DI-MGMT-81861).
Our government Program Manager is using our IPMR information to assess the
performance of our program, along with CDRL submittals, and other
performance documentation.
These measures are used to provide the visibility to program performance, the
Estimate At Completion, and Estimate to Complete for the program.
The Risk Register is not a submittal, nor the reporting of Measures of
Effectiveness, Measures of Performance, Technical Performance Measures, and
Key Performance Parameters as part of the submittal for Earned Value
Management.
 Root Cause Analysis of the situation
 Known missing processes and data
The Protagonist
The Program Manager is a key participant. In the EV community we think of
ourselves as the ones providing the information to help manage the program,
there are other participants in the effort to increase the probability of program
success.
These participants start with Systems Engineers. The Program Controls staff are
the planners, scorekeepers, and advisors to those performing the work.`
The Imbalance
The use of Earned Value may be necessary, but it is far from sufficient to plan,
measure, and control the performance of the program to increase the probability
of success.
There are several core reasons for this gap in the ability of Earned Value:
 While EAI 748-C states in the open page that Earned Value should
Objectively assess accomplishments at the work performance level, there is
no guidance on exactly how to do that.
 As well in §3.8 of EAI-748-C, it says, Earned value is a direct measurement
of the quantity of work accomplished. The quality and technical content of
work performed is controlled by other processes. Earned value is computed
based on the budget assigned to the completed work scope.
 The units of measure in Earned Value are dollars. So the meaning of
Schedule Variance (SV) in the IPMR is not defined without looking at the
Integrated Master Schedule (IMS). Knowing where to look is also not
defined in any of the IPMR fields.
The imbalance is obvious everywhere. From OTB’s to Nunn McCurdy’s, to simple
cost and schedule overruns. Add to that, the less than acceptable technical
performance of many of our programs, the imbalance is we can’t show up on
time, using the money we’ve been given, and have some acceptable probability
that the thing we’re producing will actually work as planned.
The source of the imbalance starts when we measure our progress to plan with
the “Gold Card” CPI and SPI that is not based on measures associated with the
technical performance of the product, the effectiveness of that product in the
“mission space,” and the compliance with the Key Performance Parameters
needed to assure the outcome will be useful to those paying for the program.
As well, when we forecast the future performance of the program in the absence
of the risks to that future performance we are not being credible.
Finally when we make any forecast (an estimate of the future) in the absence of
the statistical behavior of the past performance and the statistical performance
of the future performance (risk is an uncertainty that is statistically based), then
the credibility of our numbers is suspect.
 Specific assessment of RCA on ACAT1’s
 Traceability to missing parts in the policy and practice
Aiming for Balance
We must start by recognizing that Earned Value, the BCWP part of Earned Value,
must be informed by more than the passage of time and consumption of
resources. The Control Account Managers assessment of Physical Percent
Complete is not sufficient. Tangible Evidence – as 748 says Objective assessment
of the accomplishments at the work performance level.
But more is needed. Measures of Performance, Measures of Effectiveness,
Technical Performance Measures and their Quantified Backup Data, and the Key
Performance Parameters all contribute to informing BCWP.
These attributes – each a random variable – are related in the following manner:
The result of this picture is that the Integrated Master Plan (IMP) needs to be the
framework for our credible Earned Value Management System. It’s the IMP –
built by Systems Engineering – where the MOE’s, MOP’s, KPP’s, TPM’s, and Risks
live. The Integrated Master Schedule shows the sequence of work traceable to
the IMP.
This vertical traceability is called out in DI-MGMT-81861, starting in §3.7.1.3.
 How do we connect the dots
 What are the units of measure for informing BCWP
 What are some scenarios for doing this – TPMs, MOEs, MOPs, Risk adjusted
everything
The Recommended Solution
 Put the Integrated Master Plan (IMP) back in the mandatory category
with a DID for ACAT1’s – the IMP is the framework for assessing the
increasing maturity of the deliverables. Measuring progress toward those
deliverables in the IMS is necessary but is far from sufficient. CPI/SPI,
later starts, late finishes, labor absorption are all valuable. But without an
assessment of the Effectiveness and Performance of the produces products
and services, being on time, and on budget, doesn’t mean the delivered
outcomes actual work for the end user.
 Update the DOD IMP/IMS Preparation and Use Guide, from V0.9 to V1.O,
and show through examples how to make the connections between MOE,
MOP, TPM, KPP, and risk as the mechanisms for informing of BCWP to
represent Physical Percent Complete in the IMS.
 Develop EAC and ETC forecasts based on sound statistical analysis using
ARIMA (Autoregressive Integrated Moving Average) – Box-Jenkins, using
historical data from Format 1 in the EVMS database.
 Use this statistical data to calculate EAC and ETC
 Start thinking more like a Systems Engineer and less like a cost and schele
analyst – can we recognize what Done looks like in units of measure
meaningful to the decisions makers. These units start with Effectiveness
and Performance and include Risk Retirement, Technical Performance and
the array of …illities associated with program success.
 Require the Risk Register to be submitted and reviewed at IBR and
undergo a review quarterly at least and monthly at best.
 Require a risk adjusted EAC instead of a Management EAC

Más contenido relacionado

La actualidad más candente

Study of Probability Distributions of Cpi and Spi in Earned Value Analysis
Study of Probability Distributions of Cpi and Spi in Earned Value AnalysisStudy of Probability Distributions of Cpi and Spi in Earned Value Analysis
Study of Probability Distributions of Cpi and Spi in Earned Value Analysistheijes
 
Establishing schedule margin using monte carlo simulation
Establishing schedule margin using monte carlo simulation Establishing schedule margin using monte carlo simulation
Establishing schedule margin using monte carlo simulation Glen Alleman
 
Building A Credible Measurement Baseline
Building A Credible Measurement BaselineBuilding A Credible Measurement Baseline
Building A Credible Measurement BaselineGlen Alleman
 
TGE Project Controls
TGE Project ControlsTGE Project Controls
TGE Project ControlsDavid Mathews
 
IRJET- Value Management
IRJET- Value ManagementIRJET- Value Management
IRJET- Value ManagementIRJET Journal
 
Julie Rampello Maximo workshop IMC 2013 presentation
Julie Rampello Maximo workshop IMC 2013 presentationJulie Rampello Maximo workshop IMC 2013 presentation
Julie Rampello Maximo workshop IMC 2013 presentationProjetech
 
Project controls
Project controlsProject controls
Project controlsAshok Kumar
 
Project Cost.pdf
Project Cost.pdfProject Cost.pdf
Project Cost.pdf341741357
 
EVMS with Technical Performance Measures
EVMS with Technical Performance MeasuresEVMS with Technical Performance Measures
EVMS with Technical Performance MeasuresGlen Alleman
 
What Does Done Look Like?
What Does Done Look Like?What Does Done Look Like?
What Does Done Look Like?Glen Alleman
 
Agile Project Management Procedures
Agile Project Management ProceduresAgile Project Management Procedures
Agile Project Management ProceduresGlen Alleman
 
EVMS for Commercial projects
EVMS for Commercial projectsEVMS for Commercial projects
EVMS for Commercial projectsGlen Alleman
 
Six ½ Day Sessions on the Road To Becoming a CAM
Six ½ Day Sessions on the Road To Becoming a CAMSix ½ Day Sessions on the Road To Becoming a CAM
Six ½ Day Sessions on the Road To Becoming a CAMGlen Alleman
 
A credible pmb is the window to program
A credible pmb is the window to programA credible pmb is the window to program
A credible pmb is the window to programGlen Alleman
 
Estimating Cost & Time.ppt
Estimating Cost & Time.pptEstimating Cost & Time.ppt
Estimating Cost & Time.ppt341741357
 
Schedule analysis what could possibly go wrong - Oracle Primavera Collaborat...
Schedule analysis what could possibly go wrong  - Oracle Primavera Collaborat...Schedule analysis what could possibly go wrong  - Oracle Primavera Collaborat...
Schedule analysis what could possibly go wrong - Oracle Primavera Collaborat...p6academy
 

La actualidad más candente (20)

Study of Probability Distributions of Cpi and Spi in Earned Value Analysis
Study of Probability Distributions of Cpi and Spi in Earned Value AnalysisStudy of Probability Distributions of Cpi and Spi in Earned Value Analysis
Study of Probability Distributions of Cpi and Spi in Earned Value Analysis
 
Establishing schedule margin using monte carlo simulation
Establishing schedule margin using monte carlo simulation Establishing schedule margin using monte carlo simulation
Establishing schedule margin using monte carlo simulation
 
Building A Credible Measurement Baseline
Building A Credible Measurement BaselineBuilding A Credible Measurement Baseline
Building A Credible Measurement Baseline
 
TGE Project Controls
TGE Project ControlsTGE Project Controls
TGE Project Controls
 
Agile EVMS
Agile EVMSAgile EVMS
Agile EVMS
 
Control techniques
Control techniquesControl techniques
Control techniques
 
IRJET- Value Management
IRJET- Value ManagementIRJET- Value Management
IRJET- Value Management
 
Julie Rampello Maximo workshop IMC 2013 presentation
Julie Rampello Maximo workshop IMC 2013 presentationJulie Rampello Maximo workshop IMC 2013 presentation
Julie Rampello Maximo workshop IMC 2013 presentation
 
Project controls
Project controlsProject controls
Project controls
 
Software Estimation Checklist
Software Estimation ChecklistSoftware Estimation Checklist
Software Estimation Checklist
 
Project Cost.pdf
Project Cost.pdfProject Cost.pdf
Project Cost.pdf
 
EVMS with Technical Performance Measures
EVMS with Technical Performance MeasuresEVMS with Technical Performance Measures
EVMS with Technical Performance Measures
 
What Does Done Look Like?
What Does Done Look Like?What Does Done Look Like?
What Does Done Look Like?
 
Agile Project Management Procedures
Agile Project Management ProceduresAgile Project Management Procedures
Agile Project Management Procedures
 
EVMS for Commercial projects
EVMS for Commercial projectsEVMS for Commercial projects
EVMS for Commercial projects
 
Six ½ Day Sessions on the Road To Becoming a CAM
Six ½ Day Sessions on the Road To Becoming a CAMSix ½ Day Sessions on the Road To Becoming a CAM
Six ½ Day Sessions on the Road To Becoming a CAM
 
Project Management System-SharePoint Apps by Adapt
Project Management System-SharePoint Apps by AdaptProject Management System-SharePoint Apps by Adapt
Project Management System-SharePoint Apps by Adapt
 
A credible pmb is the window to program
A credible pmb is the window to programA credible pmb is the window to program
A credible pmb is the window to program
 
Estimating Cost & Time.ppt
Estimating Cost & Time.pptEstimating Cost & Time.ppt
Estimating Cost & Time.ppt
 
Schedule analysis what could possibly go wrong - Oracle Primavera Collaborat...
Schedule analysis what could possibly go wrong  - Oracle Primavera Collaborat...Schedule analysis what could possibly go wrong  - Oracle Primavera Collaborat...
Schedule analysis what could possibly go wrong - Oracle Primavera Collaborat...
 

Similar a Beyond CPI and SPI

Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineGlen Alleman
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineGlen Alleman
 
Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value ManagementGlen Alleman
 
The integrated master plan and integrated master schedule
The integrated master plan and integrated master scheduleThe integrated master plan and integrated master schedule
The integrated master plan and integrated master scheduleGlen Alleman
 
Using Technical Performance Progress
Using Technical Performance ProgressUsing Technical Performance Progress
Using Technical Performance ProgressGlen Alleman
 
Making Agile Development work in Government Contracting
Making Agile Development work in Government ContractingMaking Agile Development work in Government Contracting
Making Agile Development work in Government ContractingGlen Alleman
 
Creating Credible Plans, Integrating Reporting and Control Systems - Part 2
Creating Credible Plans, Integrating Reporting and Control Systems - Part 2Creating Credible Plans, Integrating Reporting and Control Systems - Part 2
Creating Credible Plans, Integrating Reporting and Control Systems - Part 2Glen Alleman
 
Measurement News Webinar
Measurement News WebinarMeasurement News Webinar
Measurement News WebinarGlen Alleman
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan DevelopmentGlen Alleman
 
Informing Program Performance with Technical Performance Measures (TPMs)
Informing Program Performance with Technical Performance Measures (TPMs)Informing Program Performance with Technical Performance Measures (TPMs)
Informing Program Performance with Technical Performance Measures (TPMs)Glen Alleman
 
Building a Credible Performance Measurement Baseline (PM Journal)
Building a Credible Performance Measurement Baseline (PM Journal)Building a Credible Performance Measurement Baseline (PM Journal)
Building a Credible Performance Measurement Baseline (PM Journal)Glen Alleman
 
Earned Value Managed Services
Earned Value Managed ServicesEarned Value Managed Services
Earned Value Managed ServicesGlen Alleman
 
Earned Value Management Essentials
Earned Value Management EssentialsEarned Value Management Essentials
Earned Value Management EssentialsGlen Alleman
 
Earned Value Management Essentials
Earned Value Management EssentialsEarned Value Management Essentials
Earned Value Management EssentialsGlen Alleman
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-controleidalin95
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement BaselineGlen Alleman
 
Project management
Project managementProject management
Project managementAhmed Said
 
Big data meets evm (submitted)
Big data meets evm (submitted)Big data meets evm (submitted)
Big data meets evm (submitted)Glen Alleman
 
Integrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value ManagementIntegrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value ManagementGlen Alleman
 
Agile Project Management Meets Earned Value Management
Agile Project Management Meets Earned Value ManagementAgile Project Management Meets Earned Value Management
Agile Project Management Meets Earned Value ManagementGlen Alleman
 

Similar a Beyond CPI and SPI (20)

Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value Management
 
The integrated master plan and integrated master schedule
The integrated master plan and integrated master scheduleThe integrated master plan and integrated master schedule
The integrated master plan and integrated master schedule
 
Using Technical Performance Progress
Using Technical Performance ProgressUsing Technical Performance Progress
Using Technical Performance Progress
 
Making Agile Development work in Government Contracting
Making Agile Development work in Government ContractingMaking Agile Development work in Government Contracting
Making Agile Development work in Government Contracting
 
Creating Credible Plans, Integrating Reporting and Control Systems - Part 2
Creating Credible Plans, Integrating Reporting and Control Systems - Part 2Creating Credible Plans, Integrating Reporting and Control Systems - Part 2
Creating Credible Plans, Integrating Reporting and Control Systems - Part 2
 
Measurement News Webinar
Measurement News WebinarMeasurement News Webinar
Measurement News Webinar
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan Development
 
Informing Program Performance with Technical Performance Measures (TPMs)
Informing Program Performance with Technical Performance Measures (TPMs)Informing Program Performance with Technical Performance Measures (TPMs)
Informing Program Performance with Technical Performance Measures (TPMs)
 
Building a Credible Performance Measurement Baseline (PM Journal)
Building a Credible Performance Measurement Baseline (PM Journal)Building a Credible Performance Measurement Baseline (PM Journal)
Building a Credible Performance Measurement Baseline (PM Journal)
 
Earned Value Managed Services
Earned Value Managed ServicesEarned Value Managed Services
Earned Value Managed Services
 
Earned Value Management Essentials
Earned Value Management EssentialsEarned Value Management Essentials
Earned Value Management Essentials
 
Earned Value Management Essentials
Earned Value Management EssentialsEarned Value Management Essentials
Earned Value Management Essentials
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-control
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement Baseline
 
Project management
Project managementProject management
Project management
 
Big data meets evm (submitted)
Big data meets evm (submitted)Big data meets evm (submitted)
Big data meets evm (submitted)
 
Integrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value ManagementIntegrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value Management
 
Agile Project Management Meets Earned Value Management
Agile Project Management Meets Earned Value ManagementAgile Project Management Meets Earned Value Management
Agile Project Management Meets Earned Value Management
 

Más de Glen Alleman

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planningGlen Alleman
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project SuccessGlen Alleman
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMGlen Alleman
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk managementGlen Alleman
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk ManagementGlen Alleman
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Glen Alleman
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringGlen Alleman
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideGlen Alleman
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by StepGlen Alleman
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)Glen Alleman
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possibleGlen Alleman
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic AbundanceGlen Alleman
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planningGlen Alleman
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for AgileGlen Alleman
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaGlen Alleman
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure RolloutGlen Alleman
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan DevelopmentGlen Alleman
 
Project Management Theory
Project Management TheoryProject Management Theory
Project Management TheoryGlen Alleman
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesGlen Alleman
 
Seven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project managerSeven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project managerGlen Alleman
 

Más de Glen Alleman (20)

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPM
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by Step
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic Abundance
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan Development
 
Project Management Theory
Project Management TheoryProject Management Theory
Project Management Theory
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and Practices
 
Seven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project managerSeven Habits of a Highly Effective agile project manager
Seven Habits of a Highly Effective agile project manager
 

Último

04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptxHampshireHUG
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024The Digital Insurer
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonetsnaman860154
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking MenDelhi Call girls
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityPrincipled Technologies
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsJoaquim Jorge
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...Martijn de Jong
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfsudhanshuwaghmare1
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Scriptwesley chun
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxKatpro Technologies
 
CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Servicegiselly40
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...Neo4j
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)Gabriella Davis
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdfhans926745
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slidespraypatel2
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxMalak Abu Hammad
 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEarley Information Science
 
Real Time Object Detection Using Open CV
Real Time Object Detection Using Open CVReal Time Object Detection Using Open CV
Real Time Object Detection Using Open CVKhem
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationSafe Software
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024Rafal Los
 

Último (20)

04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonets
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivity
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and Myths
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdf
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Script
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
 
CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Service
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slides
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptx
 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
 
Real Time Object Detection Using Open CV
Real Time Object Detection Using Open CVReal Time Object Detection Using Open CV
Real Time Object Detection Using Open CV
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 

Beyond CPI and SPI

  • 1. Beyond CPI/SPI Forecasting the Corrective Actions Needed to Keep the Program GREEN Glen Alleman and Tom Coonce The Situation We’re a Program Controls Manager on ACAT1 and ACAT2 programs using DCMA Validated Earned Value Management, with monthly reporting of CPI and SPI along with the other variables in the IPMR (DI-MGMT-81861). Our government Program Manager is using our IPMR information to assess the performance of our program, along with CDRL submittals, and other performance documentation. These measures are used to provide the visibility to program performance, the Estimate At Completion, and Estimate to Complete for the program. The Risk Register is not a submittal, nor the reporting of Measures of Effectiveness, Measures of Performance, Technical Performance Measures, and Key Performance Parameters as part of the submittal for Earned Value Management.  Root Cause Analysis of the situation  Known missing processes and data The Protagonist The Program Manager is a key participant. In the EV community we think of ourselves as the ones providing the information to help manage the program, there are other participants in the effort to increase the probability of program success. These participants start with Systems Engineers. The Program Controls staff are the planners, scorekeepers, and advisors to those performing the work.` The Imbalance The use of Earned Value may be necessary, but it is far from sufficient to plan, measure, and control the performance of the program to increase the probability of success. There are several core reasons for this gap in the ability of Earned Value:  While EAI 748-C states in the open page that Earned Value should Objectively assess accomplishments at the work performance level, there is no guidance on exactly how to do that.
  • 2.  As well in §3.8 of EAI-748-C, it says, Earned value is a direct measurement of the quantity of work accomplished. The quality and technical content of work performed is controlled by other processes. Earned value is computed based on the budget assigned to the completed work scope.  The units of measure in Earned Value are dollars. So the meaning of Schedule Variance (SV) in the IPMR is not defined without looking at the Integrated Master Schedule (IMS). Knowing where to look is also not defined in any of the IPMR fields. The imbalance is obvious everywhere. From OTB’s to Nunn McCurdy’s, to simple cost and schedule overruns. Add to that, the less than acceptable technical performance of many of our programs, the imbalance is we can’t show up on time, using the money we’ve been given, and have some acceptable probability that the thing we’re producing will actually work as planned. The source of the imbalance starts when we measure our progress to plan with the “Gold Card” CPI and SPI that is not based on measures associated with the technical performance of the product, the effectiveness of that product in the “mission space,” and the compliance with the Key Performance Parameters needed to assure the outcome will be useful to those paying for the program. As well, when we forecast the future performance of the program in the absence of the risks to that future performance we are not being credible. Finally when we make any forecast (an estimate of the future) in the absence of the statistical behavior of the past performance and the statistical performance of the future performance (risk is an uncertainty that is statistically based), then the credibility of our numbers is suspect.  Specific assessment of RCA on ACAT1’s  Traceability to missing parts in the policy and practice Aiming for Balance We must start by recognizing that Earned Value, the BCWP part of Earned Value, must be informed by more than the passage of time and consumption of resources. The Control Account Managers assessment of Physical Percent Complete is not sufficient. Tangible Evidence – as 748 says Objective assessment of the accomplishments at the work performance level. But more is needed. Measures of Performance, Measures of Effectiveness, Technical Performance Measures and their Quantified Backup Data, and the Key Performance Parameters all contribute to informing BCWP. These attributes – each a random variable – are related in the following manner:
  • 3. The result of this picture is that the Integrated Master Plan (IMP) needs to be the framework for our credible Earned Value Management System. It’s the IMP – built by Systems Engineering – where the MOE’s, MOP’s, KPP’s, TPM’s, and Risks live. The Integrated Master Schedule shows the sequence of work traceable to the IMP. This vertical traceability is called out in DI-MGMT-81861, starting in §3.7.1.3.  How do we connect the dots  What are the units of measure for informing BCWP  What are some scenarios for doing this – TPMs, MOEs, MOPs, Risk adjusted everything The Recommended Solution  Put the Integrated Master Plan (IMP) back in the mandatory category with a DID for ACAT1’s – the IMP is the framework for assessing the increasing maturity of the deliverables. Measuring progress toward those deliverables in the IMS is necessary but is far from sufficient. CPI/SPI, later starts, late finishes, labor absorption are all valuable. But without an assessment of the Effectiveness and Performance of the produces products and services, being on time, and on budget, doesn’t mean the delivered outcomes actual work for the end user.  Update the DOD IMP/IMS Preparation and Use Guide, from V0.9 to V1.O, and show through examples how to make the connections between MOE,
  • 4. MOP, TPM, KPP, and risk as the mechanisms for informing of BCWP to represent Physical Percent Complete in the IMS.  Develop EAC and ETC forecasts based on sound statistical analysis using ARIMA (Autoregressive Integrated Moving Average) – Box-Jenkins, using historical data from Format 1 in the EVMS database.  Use this statistical data to calculate EAC and ETC  Start thinking more like a Systems Engineer and less like a cost and schele analyst – can we recognize what Done looks like in units of measure meaningful to the decisions makers. These units start with Effectiveness and Performance and include Risk Retirement, Technical Performance and the array of …illities associated with program success.  Require the Risk Register to be submitted and reviewed at IBR and undergo a review quarterly at least and monthly at best.  Require a risk adjusted EAC instead of a Management EAC