SlideShare una empresa de Scribd logo
1 de 16
Descargar para leer sin conexión
Project developers for Oil Terminals,
SPM/CBM/FSO and Maritime Operations
page 2
Contracting Strategies
for
Terminal Construction
Contracting Strategies for Terminal Construction
Choosing the way to contract the design and construction for a tank terminal
construction project is a decision of which the influence on the project is often
underestimated. The contracting strategy has a large and early impact on the
execution and organization of the project. The choice influences the price, the risk
and the duration of the project. And it determines the required level of pre-contract
engineering. To guarantee efficient and fast early stages of the project, it is essential
that the decision for a contracting strategy is taken early in the project.
There are many ways to contract the construction of a tank terminal. This
presentation describes the advantages and disadvantages of the various available
options.
page 3
How to contract engineering, procurement & construction of a
tank terminal project
Client managed construction
When the client wished to manage everything himself
• Managed by the project organization of the client
• Typically a high number of contracts with different kinds of suppliers
page 4
Client
Contractor
Engineer
Equipment Material
Package
unit
Consultant
This requires large resources and expertise from the client.
There are many alternative solutions.
EPC – Single contract
Engineering, Procurement & Construction
• E, P & C by one main contractor
• Single contract based delivery of the complete
scope of a project, typically with guarantees for the
operational functionality of the installation.
• The required pre-contract engineering, often called
FEED (Front-End Engineering Design), can be
limited to a conceptual functionality design.
• The main contractor typically engineers and
constructs a large part of the project themselves
• The main contractor procures the other parts of the
project from suppliers and sub-contractors
page 5
EPC
Contractor
Client
Sub
Contractors
Suppliers
Engineer
Package Unit approach
Multiple EPC contracts
• Functional or geographical clearly separated
packages of work, each contracted in an
EPC manner.
• Could be 2, 3 or a high number of packages.
• Introduces interfaces between the
packages, both technical and organizational.
• The interfaces require more detailed pre-
contract engineering (FEED’s).
• Requires coordination by the client between
the contractors of each package.
page 6
Client
Package 2Package 1 Package 3
Engineer
Suppliers Suppliers Suppliers
EPC Contract formats
Lump-sum Turn-key
• The contractor will deliver a
functional construction (just
turn the key) for a single,
fixed all inclusive price
(lump-sum).
• Functionality and delivery
date are contractually
guaranteed, often with
penalties if not met.
• The client has essentially no
influence on the detail design
or construction of the project.
• The risk for overruns in time
and budget are on the
shoulders of the contractor .
page 7
Design and Construct
• The contractor will first
deliver the design, often for a
fixed fee. This design is to be
approved by the client.
• Based on the design and
agreed unit rates, the
contractor will calculate a
fixed fee and delivery date
for the construction.
• The client has a strong
influence on the detail design
of the project..
• The risk for schedule and
budget are on the shoulder
of both parties.
Unit Rates
• The contract consists of a
price list of all units
(supplies, manhours) to be
delivered by the contractor.
• The contractor will invoice
based on actually procured
supplies and spent
manhours.
• The client has a strong
influence on the detail design
and the construction of the
project..
• The risk for schedule and
budget are on the shoulder
of the client..
Most common contract forms
For tank terminals, The most commonly chosen contracting strategies are:
• EPC, lump-sum turn-key
• Package units, design and construct
Other strategies might however fit certain client-project combinations better.
page 8
The contracting processes compared
EPC Lump-sum Turn-key
1. Define location and required functionality of the
terminal.
2. Contract an engineering company to make a
FEED. This FEED can be limited to a
functional, conceptual design.
3. Do a pre-qualification to determine the short-list
of potential EPC contractors.
4. Define the contract format, incl. the contractor
guarantees, HSE requirements etc.
5. Issue a Request for Proposal (RfP) consisting
of the contract and the FEED to the short-listed
contractors
6. Evaluate the bids and negotiate and award the
contract.
page 9
Package Units, Design and Construct
1. Define location and required functionality of the
terminal.
2. Contract an engineering company to make a
FEED. This FEED should be a basic design
that defines the technical interfaces between
packages..
3. Do for each package a pre-qualification to
determine the short-list of potential contractors.
4. Define the contract format(s), incl. the
contractor guarantees, HSE requirements etc.
And define the interface management
procedure.
5. Issue for each package a Request for Proposal
(RfP) consisting of the contract and the
relevant part of the FEED to the short-listed
contractors
6. Evaluate the bids and negotiate and award the
contracts.
EPC lump-sum turn-key
Advantages
• Total project costs “fixed” in early stage
• All liability by the main contractor
• Small project team required by client
• Only functional design required up-front
• Mainly applicable for ‘greenfield’ projects
Disadvantages
• High project costs (risk factor added by Contractor)
• Almost no influence on the project by the Client
• Up-front engineering not sufficient for environmental permit application
page 10
Package units, design and construct
Advantages
• Most of the liabilities by the contractors
• Potential for negotiating low project costs
• LImited amount of engineering required before contracting
• Detailed influence on the design by the Client
• Makes good use of expert knowledge from contractors
Disadvantages
• Late availability of ‘fixed’ contracted project costs
• Large project team required by client
• Interfaces between contractors need to be engineered and managed by Client
page 11
EPC management (EPCm)
Engineering, Procurement & Construction
management
• Engineering and management of Procurement and
Construction typically by an engineering firm but could
also be two or even three separate companies.
• The contract with the EPCm company(ies) can be lump-
sum or based on unit rates or a combination of both.
• Contracts with contractors and suppliers directly with
client but managed by EPCm engineers. The
contracting strategy is to be agreed between client and
EPCm engineers.
page 12
EPCm
Engineers
Client
ContractorsSuppliers
For large and/or complex (brown field) projects
EPCm
Advantages
• Potential for lower project costs
• Much influence on project by Client
• Quality determined earliest by choice of contractor/supplier
• Flexibility to change/adapt during design
• Fits ‘brown field’ projects well
Disadvantages
• More engineering hours
• Large project team required
• Late availability of final contracted project costs
• risk for overruns of initial budget and schedule
page 13
How to make the contracting decision?
Questions to ask yourself
• Do you want to be fast? EPC
• Do you want detailed influence on the quality of construction? Design & construct
• Is your project large and complex EPCm
• Do you want a low risk for budget over-run? Lump-sum, Turn-key
• Do you have your own, large project organization? Package units
• Do you want detailed influence on the design? EPCm
• Do you have limited experience in constructing a terminal? EPC
• Do you want guarantees on the functionality of the terminal EPC
• Do you want to negotiate yourself for the lowest price? package units
page 14
Do you find this confusing? Engage Riverlake Solutions!
Management contacts
page 15
Jan Thijs Maatman
MSc. Mining and Petroleum Engineering
Since 1999 experience in contracting oil & gas
maatman@riverlakesolutions.com
Mobile +31 650 12 84 21
Erik van Sliedregt
MSc. Mechanical Engineering
Since 1998 experience in marine contracting construction
and production mangement
sliedregt@riverlakesolutions.com
Mobile +31 650 12 84 20
Wilbert Versteeg
Master of Business Sience
Since 1996 experience in marine contracting oil & gas
versteeg@riverlakesolutions.com
Mobile +31 650 12 84 22
Feiko Jager
MSc. Maritime Technology
Since 1987 experience in oil terminal and maritime
logistics
jager@riverlakesolutions.com
Mobile +31 613 02 50 86
page 16
Office Contact
Sales Office
Parklaan 46
3016 BC Rotterdam, The Netherlands
Tel: +31 10 436 54 30
Fax: +31 10 225 06 89
Head Office
26, rue du Mont-Blanc
1201 Geneva, CH
www.riverlakesolutions.com

Más contenido relacionado

La actualidad más candente

GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1
GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1
GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1
Charles S. Maggio
 
Effective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryEffective Engineering Management in EPC Industry
Effective Engineering Management in EPC Industry
PMI Chennai Chapter
 

La actualidad más candente (19)

GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1
GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1
GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1
 
Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...
Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...
Risk Assessment, Mitigation And Management In Epc Projects With Case Study By...
 
EPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A ComparisonEPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A Comparison
 
Nec3 introduction
Nec3 introductionNec3 introduction
Nec3 introduction
 
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...
 
Epc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promoEpc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promo
 
Why EPC
Why EPCWhy EPC
Why EPC
 
EPC Business Model
EPC Business ModelEPC Business Model
EPC Business Model
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016
 
Construction Futures Wales - NEC Contracts Overview Workshop
Construction Futures Wales  - NEC Contracts Overview WorkshopConstruction Futures Wales  - NEC Contracts Overview Workshop
Construction Futures Wales - NEC Contracts Overview Workshop
 
EPC Contracts – Negotiation, Administration and Risk Management
EPC Contracts – Negotiation, Administration and Risk ManagementEPC Contracts – Negotiation, Administration and Risk Management
EPC Contracts – Negotiation, Administration and Risk Management
 
Design-Build: The Owner’s Role in Successful Outcomes
Design-Build: The Owner’s Role in Successful OutcomesDesign-Build: The Owner’s Role in Successful Outcomes
Design-Build: The Owner’s Role in Successful Outcomes
 
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
 
Contract administration iowa AGC
Contract administration iowa AGCContract administration iowa AGC
Contract administration iowa AGC
 
Assessment of Risks in International EPC Projects Reference Current Global Ec...
Assessment of Risks in International EPC Projects Reference Current Global Ec...Assessment of Risks in International EPC Projects Reference Current Global Ec...
Assessment of Risks in International EPC Projects Reference Current Global Ec...
 
Design build risks and rewards for public owner
Design build risks and rewards for public ownerDesign build risks and rewards for public owner
Design build risks and rewards for public owner
 
Time cost trade off
Time cost trade offTime cost trade off
Time cost trade off
 
Claim Presentation Rev 03 FINAL
Claim Presentation Rev 03 FINALClaim Presentation Rev 03 FINAL
Claim Presentation Rev 03 FINAL
 
Effective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryEffective Engineering Management in EPC Industry
Effective Engineering Management in EPC Industry
 

Similar a Contracting strategies for_terminal_construction

1._pmc_2019_day_1_project_initiation_and_planning_final.pptx
1._pmc_2019_day_1_project_initiation_and_planning_final.pptx1._pmc_2019_day_1_project_initiation_and_planning_final.pptx
1._pmc_2019_day_1_project_initiation_and_planning_final.pptx
sheryl90
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentation
Timun Loh
 

Similar a Contracting strategies for_terminal_construction (20)

TURNKEY PROJECT.pptx
TURNKEY PROJECT.pptxTURNKEY PROJECT.pptx
TURNKEY PROJECT.pptx
 
TOPIC2.pdf
TOPIC2.pdfTOPIC2.pdf
TOPIC2.pdf
 
Contract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment StructureContract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment Structure
 
Preparation of boq
Preparation of boqPreparation of boq
Preparation of boq
 
Professional Practice
Professional PracticeProfessional Practice
Professional Practice
 
ARTSCAPE_Introduction
ARTSCAPE_IntroductionARTSCAPE_Introduction
ARTSCAPE_Introduction
 
PP1 - Presentation Slides
PP1 - Presentation Slides PP1 - Presentation Slides
PP1 - Presentation Slides
 
Mepl presentation
Mepl presentationMepl presentation
Mepl presentation
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignment
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignment
 
Early contractor involvement (eci) procurement approach spm talk 2016
Early contractor involvement (eci) procurement approach   spm talk 2016Early contractor involvement (eci) procurement approach   spm talk 2016
Early contractor involvement (eci) procurement approach spm talk 2016
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION
 
1._pmc_2019_day_1_project_initiation_and_planning_final.pptx
1._pmc_2019_day_1_project_initiation_and_planning_final.pptx1._pmc_2019_day_1_project_initiation_and_planning_final.pptx
1._pmc_2019_day_1_project_initiation_and_planning_final.pptx
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentation
 
Contracts 2
Contracts 2Contracts 2
Contracts 2
 
Time cost trade off with primavera (real case)
Time cost trade off with primavera (real case)Time cost trade off with primavera (real case)
Time cost trade off with primavera (real case)
 
Beyond Engineering: EPC Lessons learnt from a Lenders' Technical and Environm...
Beyond Engineering: EPC Lessons learnt from a Lenders' Technical and Environm...Beyond Engineering: EPC Lessons learnt from a Lenders' Technical and Environm...
Beyond Engineering: EPC Lessons learnt from a Lenders' Technical and Environm...
 
PP1 assignment presentation slides
PP1 assignment presentation slidesPP1 assignment presentation slides
PP1 assignment presentation slides
 
Lecture 1.pptx
Lecture 1.pptxLecture 1.pptx
Lecture 1.pptx
 
PASBA 2010 presentation
PASBA 2010 presentationPASBA 2010 presentation
PASBA 2010 presentation
 

Más de drs. ing. George van Bommel MBE, BSc

Más de drs. ing. George van Bommel MBE, BSc (20)

haldor topsoe ammonia plant startup document
haldor topsoe ammonia plant startup documenthaldor topsoe ammonia plant startup document
haldor topsoe ammonia plant startup document
 
Project Development Handbook presentation
Project Development Handbook presentationProject Development Handbook presentation
Project Development Handbook presentation
 
La Luz Port Nautical Chart detailed information
La Luz Port Nautical Chart detailed informationLa Luz Port Nautical Chart detailed information
La Luz Port Nautical Chart detailed information
 
RivSol_article_2_-_Engineering_process.pdf
RivSol_article_2_-_Engineering_process.pdfRivSol_article_2_-_Engineering_process.pdf
RivSol_article_2_-_Engineering_process.pdf
 
bunker fuels ISO specs 8217 2010.pdf
bunker fuels ISO specs 8217 2010.pdfbunker fuels ISO specs 8217 2010.pdf
bunker fuels ISO specs 8217 2010.pdf
 
topsoe_ammonia_4_start_up_worlds_largest_ammonia_plant.pdf
topsoe_ammonia_4_start_up_worlds_largest_ammonia_plant.pdftopsoe_ammonia_4_start_up_worlds_largest_ammonia_plant.pdf
topsoe_ammonia_4_start_up_worlds_largest_ammonia_plant.pdf
 
Commissioning ammonia_plant Kaltim 2000.pdf
Commissioning ammonia_plant Kaltim 2000.pdfCommissioning ammonia_plant Kaltim 2000.pdf
Commissioning ammonia_plant Kaltim 2000.pdf
 
Large_Pellet_Plants.pdf
Large_Pellet_Plants.pdfLarge_Pellet_Plants.pdf
Large_Pellet_Plants.pdf
 
Bunker fuels iso specs 8217 2010
Bunker fuels iso specs 8217 2010Bunker fuels iso specs 8217 2010
Bunker fuels iso specs 8217 2010
 
Project development handbook rl website
Project development handbook rl websiteProject development handbook rl website
Project development handbook rl website
 
Contracting strategies for_terminal_construction
Contracting strategies for_terminal_constructionContracting strategies for_terminal_construction
Contracting strategies for_terminal_construction
 
Training program for_urea_engineers_july_by ukh
Training program for_urea_engineers_july_by ukhTraining program for_urea_engineers_july_by ukh
Training program for_urea_engineers_july_by ukh
 
VMT 11 - Artikel BioValGroup
VMT 11 - Artikel BioValGroupVMT 11 - Artikel BioValGroup
VMT 11 - Artikel BioValGroup
 
Fertilizer Product Quality GVB
Fertilizer Product Quality GVBFertilizer Product Quality GVB
Fertilizer Product Quality GVB
 
2012_07_UreaKnowHow.com_Van_Bommel_Dedusting_Technology
2012_07_UreaKnowHow.com_Van_Bommel_Dedusting_Technology 2012_07_UreaKnowHow.com_Van_Bommel_Dedusting_Technology
2012_07_UreaKnowHow.com_Van_Bommel_Dedusting_Technology
 
Pöyry is biocoal_a_bioenergy_game_changer
Pöyry is biocoal_a_bioenergy_game_changerPöyry is biocoal_a_bioenergy_game_changer
Pöyry is biocoal_a_bioenergy_game_changer
 
Iea bioenergy t32_torrefaction_review (overview of technologies)
Iea bioenergy t32_torrefaction_review (overview of technologies)Iea bioenergy t32_torrefaction_review (overview of technologies)
Iea bioenergy t32_torrefaction_review (overview of technologies)
 
Fertilizer manual (unido and ifdc)
Fertilizer manual (unido and ifdc)Fertilizer manual (unido and ifdc)
Fertilizer manual (unido and ifdc)
 
Biomass tar properties
Biomass tar propertiesBiomass tar properties
Biomass tar properties
 
Ash correlations on hhv
Ash correlations on hhvAsh correlations on hhv
Ash correlations on hhv
 

Último

notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
MsecMca
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
ankushspencer015
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Christo Ananth
 

Último (20)

notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 

Contracting strategies for_terminal_construction

  • 1. Project developers for Oil Terminals, SPM/CBM/FSO and Maritime Operations
  • 3. Contracting Strategies for Terminal Construction Choosing the way to contract the design and construction for a tank terminal construction project is a decision of which the influence on the project is often underestimated. The contracting strategy has a large and early impact on the execution and organization of the project. The choice influences the price, the risk and the duration of the project. And it determines the required level of pre-contract engineering. To guarantee efficient and fast early stages of the project, it is essential that the decision for a contracting strategy is taken early in the project. There are many ways to contract the construction of a tank terminal. This presentation describes the advantages and disadvantages of the various available options. page 3 How to contract engineering, procurement & construction of a tank terminal project
  • 4. Client managed construction When the client wished to manage everything himself • Managed by the project organization of the client • Typically a high number of contracts with different kinds of suppliers page 4 Client Contractor Engineer Equipment Material Package unit Consultant This requires large resources and expertise from the client. There are many alternative solutions.
  • 5. EPC – Single contract Engineering, Procurement & Construction • E, P & C by one main contractor • Single contract based delivery of the complete scope of a project, typically with guarantees for the operational functionality of the installation. • The required pre-contract engineering, often called FEED (Front-End Engineering Design), can be limited to a conceptual functionality design. • The main contractor typically engineers and constructs a large part of the project themselves • The main contractor procures the other parts of the project from suppliers and sub-contractors page 5 EPC Contractor Client Sub Contractors Suppliers Engineer
  • 6. Package Unit approach Multiple EPC contracts • Functional or geographical clearly separated packages of work, each contracted in an EPC manner. • Could be 2, 3 or a high number of packages. • Introduces interfaces between the packages, both technical and organizational. • The interfaces require more detailed pre- contract engineering (FEED’s). • Requires coordination by the client between the contractors of each package. page 6 Client Package 2Package 1 Package 3 Engineer Suppliers Suppliers Suppliers
  • 7. EPC Contract formats Lump-sum Turn-key • The contractor will deliver a functional construction (just turn the key) for a single, fixed all inclusive price (lump-sum). • Functionality and delivery date are contractually guaranteed, often with penalties if not met. • The client has essentially no influence on the detail design or construction of the project. • The risk for overruns in time and budget are on the shoulders of the contractor . page 7 Design and Construct • The contractor will first deliver the design, often for a fixed fee. This design is to be approved by the client. • Based on the design and agreed unit rates, the contractor will calculate a fixed fee and delivery date for the construction. • The client has a strong influence on the detail design of the project.. • The risk for schedule and budget are on the shoulder of both parties. Unit Rates • The contract consists of a price list of all units (supplies, manhours) to be delivered by the contractor. • The contractor will invoice based on actually procured supplies and spent manhours. • The client has a strong influence on the detail design and the construction of the project.. • The risk for schedule and budget are on the shoulder of the client..
  • 8. Most common contract forms For tank terminals, The most commonly chosen contracting strategies are: • EPC, lump-sum turn-key • Package units, design and construct Other strategies might however fit certain client-project combinations better. page 8
  • 9. The contracting processes compared EPC Lump-sum Turn-key 1. Define location and required functionality of the terminal. 2. Contract an engineering company to make a FEED. This FEED can be limited to a functional, conceptual design. 3. Do a pre-qualification to determine the short-list of potential EPC contractors. 4. Define the contract format, incl. the contractor guarantees, HSE requirements etc. 5. Issue a Request for Proposal (RfP) consisting of the contract and the FEED to the short-listed contractors 6. Evaluate the bids and negotiate and award the contract. page 9 Package Units, Design and Construct 1. Define location and required functionality of the terminal. 2. Contract an engineering company to make a FEED. This FEED should be a basic design that defines the technical interfaces between packages.. 3. Do for each package a pre-qualification to determine the short-list of potential contractors. 4. Define the contract format(s), incl. the contractor guarantees, HSE requirements etc. And define the interface management procedure. 5. Issue for each package a Request for Proposal (RfP) consisting of the contract and the relevant part of the FEED to the short-listed contractors 6. Evaluate the bids and negotiate and award the contracts.
  • 10. EPC lump-sum turn-key Advantages • Total project costs “fixed” in early stage • All liability by the main contractor • Small project team required by client • Only functional design required up-front • Mainly applicable for ‘greenfield’ projects Disadvantages • High project costs (risk factor added by Contractor) • Almost no influence on the project by the Client • Up-front engineering not sufficient for environmental permit application page 10
  • 11. Package units, design and construct Advantages • Most of the liabilities by the contractors • Potential for negotiating low project costs • LImited amount of engineering required before contracting • Detailed influence on the design by the Client • Makes good use of expert knowledge from contractors Disadvantages • Late availability of ‘fixed’ contracted project costs • Large project team required by client • Interfaces between contractors need to be engineered and managed by Client page 11
  • 12. EPC management (EPCm) Engineering, Procurement & Construction management • Engineering and management of Procurement and Construction typically by an engineering firm but could also be two or even three separate companies. • The contract with the EPCm company(ies) can be lump- sum or based on unit rates or a combination of both. • Contracts with contractors and suppliers directly with client but managed by EPCm engineers. The contracting strategy is to be agreed between client and EPCm engineers. page 12 EPCm Engineers Client ContractorsSuppliers For large and/or complex (brown field) projects
  • 13. EPCm Advantages • Potential for lower project costs • Much influence on project by Client • Quality determined earliest by choice of contractor/supplier • Flexibility to change/adapt during design • Fits ‘brown field’ projects well Disadvantages • More engineering hours • Large project team required • Late availability of final contracted project costs • risk for overruns of initial budget and schedule page 13
  • 14. How to make the contracting decision? Questions to ask yourself • Do you want to be fast? EPC • Do you want detailed influence on the quality of construction? Design & construct • Is your project large and complex EPCm • Do you want a low risk for budget over-run? Lump-sum, Turn-key • Do you have your own, large project organization? Package units • Do you want detailed influence on the design? EPCm • Do you have limited experience in constructing a terminal? EPC • Do you want guarantees on the functionality of the terminal EPC • Do you want to negotiate yourself for the lowest price? package units page 14 Do you find this confusing? Engage Riverlake Solutions!
  • 15. Management contacts page 15 Jan Thijs Maatman MSc. Mining and Petroleum Engineering Since 1999 experience in contracting oil & gas maatman@riverlakesolutions.com Mobile +31 650 12 84 21 Erik van Sliedregt MSc. Mechanical Engineering Since 1998 experience in marine contracting construction and production mangement sliedregt@riverlakesolutions.com Mobile +31 650 12 84 20 Wilbert Versteeg Master of Business Sience Since 1996 experience in marine contracting oil & gas versteeg@riverlakesolutions.com Mobile +31 650 12 84 22 Feiko Jager MSc. Maritime Technology Since 1987 experience in oil terminal and maritime logistics jager@riverlakesolutions.com Mobile +31 613 02 50 86
  • 16. page 16 Office Contact Sales Office Parklaan 46 3016 BC Rotterdam, The Netherlands Tel: +31 10 436 54 30 Fax: +31 10 225 06 89 Head Office 26, rue du Mont-Blanc 1201 Geneva, CH www.riverlakesolutions.com