LEAN SIX SIGMA BLACK BELT PROJECT STORYBOARD
CITY OF SAN ANTONIO |TASK ORDER & INVOICING PROCESS TIMING
MARCH 24, 2016
JESSICA M. SHIRLEY-SAENZ
PROJECT CONTROL MANAGER | TRANSPORTATION & CAPITAL IMPROVEMENTS DEPARTMENT
TABLEOFCONTENTS
DEFINE
Project Charter | Tools
KEYWORDS 4
EXECUTIVE SUMMARY 3
DMAIC METHODOLOGY 5
MEASURE
Data Collection | Baseline Measures | Tools
ANALYZE
Root Cause Analysis | Tools
IMPROVE
Solutions| Implementation Plan | Charts | Tools
CONTROL
Control & Monitoring Plans | Next Steps | Lessons Learned
APPENDIX 23
TASKORDER&INVOICINGTIMING
EXECUTIVE SUMMARY
Construction ManagementProblem Statement
Project Control
ComplianceBusiness Case
In April 2014, the City received complaints from on-call task order Contractors regarding how
long it takes to receive payment for completing work on street maintenance projects.
Contractors alleged that payments were taking longer than it use to, up to 30 or more days to
receive. Consequently, if payments are delayed, Contractors and their subcontractors are not
paid. If continued, Contractors would no longer bid on City projects which would delay the
completion of street maintenance projects city-wide. If street maintenance projects are not
completed this will negatively impact and potentially compromise the City’s infrastructure -
namely, its safety, transportation conveniences and accessibility.
Project Results
Graphical Display of ImprovementRoot Cause Analysis
Identified delays in efficiently processing task order payments was significantly attributed to:
▪ Payments Rejected for Incorrect Quantities – Due to inconsistent, redundant and non-
transparent documentation of approved quantities.
▪ Delayed and Combined Payment Requests (Invoicing) – Due to invoices being
submitted long after project completion, an additional review was being required to verify
quantities.
Solutions Implemented
▪ Implemented a tolerance threshold for quantity yield calculations to reduce number of rejects
for disputed quantity amounts
▪ Implemented new daily quantity process to centralize and standardize the documentation of
daily quantities information
▪ Updated the payment workflow so City can invoice on behalf of Contractor to improve
timeliness and eliminate the additional review of quantities
▪ Increased overall number of payments processed monthly for street maintenance
task orders from an average of 97 payment requests to 116 payment requests
▪ Reduced the overall number of rejected payments for disputed quantity amounts
from an average of 17 rejects to 12 rejects
▪ Reduced the overall percentage of rejected payments for disputed quantity amounts
from 58% ($21.6 million) to 42% ($15 million)
KEYWORDS
Lean Six Sigma Black Belt Project Storyboard
Task Order & Invoicing Process Timing
Construction Management
Responsible for the review and approval of task orders
and invoices; and creation as well as closure of Task
Order Purchase Orders in the City’s financial system (i.e.
SAP).
City Fiscal Accountant
Project Control
Compliance
Contracts
Fiscal
Responsible for inspecting the work Contractors perform
to ensure consistency with contract drawings and
specification. Inspects the work as acceptable, documents
construction quantities and approves payment.
City Inspector
Consists of City’s Project Manager (PM) (customarily, an
Engineer) and Project Team. Oversees the work
Contractors perform, is consistent with the contract
drawings and specifications, affirms the completed work as
acceptable, submits task orders and approves payment.
City Project Team
Responsible to perform construction work as defined by
the contract drawings and specifications.
Contractor
Is a PRIMELink form used by the Contractor or City to bill
(i.e. invoice) on behalf of the Contractor for work
completed.
Payment Request
Is a hosted enterprise capital improvements project portal
system. It manages the electronic routing and storage of
capital project documents such as Task Orders, Invoices,
Payment data and all other associated project documents
(i.e. change orders, contracts, plans, RFIs, submittals,
etc…).
PRIMELink System
Quantities refer to the itemized list of work, materials and
any cost related items supplied by the contractor in order
to complete the requested work. Actual billable quantities
are verified by a City Inspector and included in the
Payment Request so the Contractor is paid for those
items.
Quantities
Is a PRIMELink form used by the City to authorize work
consistent with the scope of the contract and within the
existing contract dollar authorization. It is needed to
create a Purchase Order (PO) for work to be completed.
Task Order
Transportation and Capital Improvements Department
(TCI) oversees and directs the development and
maintenance of the publicly owned infrastructure of the
City of San Antonio.
TCI
DEFINE
PROJECT CHARTER
Construction ManagementProblem Statement
Project Control
Compliance
Contracts
Goal Statement
Scope In/Out
Problem Statement
Timeline
Team Members
Business Case & Benefits
On-call task order Contractors are complaining about how long it takes to receive
payment after completing work on street maintenance projects. The average standard
processing time is 13 days, if all of the quantities are correct and scope of work is pre-
approved prior to the start of work.
POSITION PERSON
Executive Sponsor Mike Frisbie, TCI Director
Project Champion(s) Anthony Chukwudolue, TCI Streets Asst. Director
Debbie Racca-Sittre, TCI Support Services Asst. Director
Razi Hosseini, TCI Project Delivery Asst. Director
The goal is to increase the number of payment requests processed by decreasing the
number of rejected invoices for disputed quantity amounts by 10% or more by the end
of 4th Quarter in FY 2015 (September 2015) .
In Scope: Street Maintenance City Construction Task Order Contracts, Process Steps
(Including Task Order, Payment & Associating Processes), System Upgrades
Out of Scope: Street Maintenance Utility (Electric, Gas or Sewer) Work Task Orders
Improved timeliness of payment requests to Contractors will result in more timely
payments to Subcontractors and restore Contractors’ confidence with the City’s invoicing
process (as more reliable). Which will translate to Contractors wanting to continue to
bid on City street maintenance projects; and, allow the City to release funds that would
otherwise remain encumbered delaying completion of other projects.
PHASE PLANNED ACTUAL
Define April 28, 2014 April 28, 2014
Measure May 19, 2014 May 26, 2014
Analyze July 24, 2014 July 24, 2014
Improve August 25, 2014 *April 2, 2015
Control September 1, 2014 *August 3, 2015
*Project delays attributed to:
(1) Team awaiting for completion
of FY 2015 budget to buy
laptops needed for TCI
inspectors to complete the new
daily quantity log in the field.
(2) Team awaiting start of new
Street Maintenance Task Order
contracts.
POSITION PERSON
Project Manager Jessica M. Shirley-Saenz
Core Team Members Contractors
Fiscal
PRIMELink Manager
TCI Streets Engineering Project Teams
TCI Inspectors
DEFINE
SIPOC
Key Take Away: The scope of this project begins with the planning of the task order and includes when the work is
initiated up through inspection of the work, ending with the payment for the work completed.
S I P O C
Supplier Input Process Output Customer
Work Planning  Agreed Upon Project Scope Planning Payment Contractor
Contractor  Defined Project Limits Initial Phase of Task Order  Completed Project Work
(City) Project Team  Estimated Quantities Define Project Scope & Quantities  Inspected Work
(City) Inspector  Completion of Work  Agreed Upon Quantities
Work Task Creation  Inspection of Work Creation
Contractor  Quantity Verification Task Order (Authorization/Approval of
Work)(City) Project Team
Work Completion
(Contractor) Work Crew Execution
(Contractor) Superintendent Work Completion
CUSTOMER REQUIREMENTS
(City) Inspector Inspection & Quantity Verification
Payment Timely & Consistent Payment
(Contractor) Fiscal Rep Payment Transparency
(Contractor) Superintendent Payment Request Creation Improved Communication
(City) Project Team Payment Request Approval
(City) Inspector
Close-Out Close-Out
(Contractor) Fiscal Rep Project Completion
(City) Project Team Coordination of Final Payment
(City) Inspector Final Task Order Completion
DEFINE
VOICE OF THE CUSTOMER
Construction ManagementProblem Statement
Project Control
Compliance
Contracts
Fiscal
Customer Comment Gathering More Understanding Customer Requirement
“It takes forever to receive payment for work I
complete”
Contractor not receiving payments timely Payments should be processed within 13 days
or less
“I can’t invoice because the task order isn’t even
processed yet”
Contractor completes work prior to task
order being processed
Require the task order must be processed
prior to work start
“I don’t submit invoices anymore because they just
get rejected”
Contractor stop submitting payments because
payments are rejected for incorrect quantities
Quantities are documented and accessible
daily and agreed upon daily
“I’d be happy if I could just get paid for the work
quantities we do agree upon, we can work out the
ones we disagree with later”
Once the payment request is submitted the
Contractor nor the City can modify or
remove quantity pay items; one disputed item
out of a list of many will hold up an entire
Payment Request
Should have ability to generate an Payment
Request with approved quantities only and
pend disputing quantities until resolved
“I have to wait for quantities and when I do get
them I have to hunt through emails or call
inspector for quantities”
City Inspector documents quantities on
various manual logs and provides quantities
manually to the City’s ProjectTeam and
Contractor through email or by phone
Establish a consistent and standard process to
document and provide quantity information
to City staff and Contractor
Key Take Away: Project needs to address the documentation process of a project’s daily quantities. Specifically, the
standardization, accessibility and consistency. Standardization of this process will help identify and rectify quantity errors in a
more timely manner which will help reduce the number of rejected payments and in turn increase the number of timely
payments made.
MEASURE
DATA COLLECTION PLAN
Measure Data Type Operational Definition Stratification Factors Sampling Notes Who and How
Total Number of
Task Orders
Continuous Street Maintenance City Task Orders not
rejected . All task orders with a “Complete”
status.
By Contractor
By Purchase Order Line
Sample includes every task order
processed in *Fiscal Years 2012
through 2015.
Project Lead retrieve from
PRIMELink
Administrator/PRIMELink
Total Number of
Payments Processed
Continuous Street Maintenance City Payment Requests not
rejected . All Payment Requests with a
Payment Date.
By Contractor
By Purchase Order Line
Sample includes every payment
request processed in *Fiscal
Years 2012 through 2015.
Project Lead retrieve from
PRIMELink
Administrator/PRIMELink
Timeliness of
Payments Processed
Continuous Number of days to process payment.
calculated by taking the difference between
Payment Request creation date and payment
date. List of payments processed within 30
days.
By Contractor
By Payment Date
By Day Ranges [5 days,
10 days, 15 days, 30 days
and 30 days+]
Sample includes every payment
request processed in *Fiscal
Years 2012 through 2015.
Project Lead retrieve from
PRIMELink
Administrator/PRIMELink
Total Number of
Payments Rejected
Continuous Street Maintenance City Payment Requests
rejected. All payment requests with a
“Rejected” status.
By Contractor
By Reject Date
Sample includes every rejected
payment request in *Fiscal Years
2012 through 2015.
Project Lead retrieve from
PRIMELink
Administrator/PRIMELink
Reject Types Discrete List of reasons for rejects. None Sample includes feedback
retrieved from the contractor
(with largest volume) and city
staff approvers (inspectors,
project team & fiscal)
Project Lead retrieve from
interviews document top
reasons and tally
Total Number of
Rejected Payments
by Reject Reason
Continuous Street Maintenance City Payment Requests
rejected by the identified reasons retrieved
from sampling above.
By Reject Reason Sample includes every rejected
payment request processed in
*Fiscal Years 2012 through 2015.
Project Lead from
PRIMELink
Administrator/PRIMELink
Key Take Away: Project lead is responsible for all data collection – team and subject matter experts (SMEs) made the
appropriate adjustments to provide and/or make themselves available to accommodate the request for information.
*Fiscal Year = October 1st – September 30th
 Task order Street Maintenance payment requests
processed between October 2012 to June 2014 (1,531
Payment Requests valued at $69.3 million) was analyzed
to understand within how many days are these payment
requests being processed.
 It is City’s policy that vendors (i.e. Contractors) be paid by
the City within 30 days of the date a correct Payment
Request is submitted for work performed for the City.
The TCI department’s overall average payment processing
time is 11 days.
 Pareto shows that 95% of the Street Maintenance
payment requests processed between October 2012 to
June 2014 were processed within 30 days; and, less than
5% of the payment requests took more than 30 days to
process.
BASELINE MEASURE
Payment RequestTimeliness
36% 34%
18%
7%
5%
DATA SUMMARY
Key Take Away: Average processing time for task order
Street Maintenance payment requests is 13 days. Data
shows that 95% of Street Maintenance payment requests
when submitted with no issues were processed within 30
days.
Baseline
Oct. 2012 - June 2014
BASELINE MEASURE
Payment Rejects
 Task order Street Maintenance payment requests rejected
between October 2012 to June 2014 (322 valued at $21.6
million) was analyzed to understand the volume and
reasons for rejected payment requests.
 The Pareto shows that that payment requests were
rejected for Disputed Amounts (83%) followed by Utility
related disputes (14%) and Budget Adjustment (3%).
DATA SUMMARY
Key Take Away: Rejected payment requests delay
payments made to the Contractor. Baseline data
shows Street Maintenance payment requests are
rejected more often for disputed amounts than any
other reject reason. Team planned on gathering
additional information from process experts to help
identify what is causing the amounts to be disputed.
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
0
50
100
150
200
250
300
Disputed Amount Utility Budget Adjustment
NumberofRejects
83%
14%
3%
Baseline
Oct. 2012 - June 2014
ANALYZE
FISHBONE DIAGRAM
TOOLS
REPORTING
CITY PROCESS
PAYMENTS
CITY PROCESS
TASK ORDERS
CITY STAFF
CONTRACTOR
NoTransparency
[For Quantities]
Inconsistent Documentation
Work Completed or Initiated
Prior toTask Order
Approval Sequencing
[Contractor Not Aware of Utility Rejects]
Task Order Not Processed
Rejected Payments
Quantity Discrepancies
Lack of Connectivity
to PRIMELink in
the Field
Tracking & Report Duplication
[Inspector, Project Team & Vendor Separately
Track]
Delayed Communication
Untimely Payment Request Submissions
Combining Payment Requests
Delayed
Processing
of Payment
Requests
(Payments to
Contractors)
No Standardization
[For Quantities]
Limited Accessibility
[For Quantities]
Inconsistent Material “Ticket”
Submissions
Delayed Utility Approvals
KeyTake Away: Root Cause Analysis will focus on Daily Quantity documentation/reporting process and Payment Process.
Why are Payment Requests
rejected for disputed
amounts?
-Contractor quantities included in
Payment Request do not match
City’s verified quantities
-Why? Verified daily quantities
information is not easily accessible
or consistently provided to confirm
quantities are correct
-Why? Documentation and delivery
of daily quantities varies by City
Inspector
- Why? There currently is no
standard documentation and
reporting process for daily
quantities
ANALYZE
HYPOTHESISTESTING RESULTS
Possible X Root Cause Hypothesis HypothesisTest Results
Payment Request
Time Period
Processing of Street Maintenance Task Order
Payment Requests takes longer than it used to
One-Sample Sign False
Task Order
Time Period
Processing of Street Maintenance Task Order
takes longer than it used to
One-Sample Test False
Rejects
There are more payment request rejects than there
used to be
One-Sample Sign True
Reject Types
Number of rejects seems to be higher for certain
reject reasons
Mood’s Median True
KeyTake Away: Hypothesis tests confirmed that rejected payments was a key area of focus.
ONE SIGN HYPOTHESISTEST
Hypothesis: Total payment processing time is taking longer than it use to.
Key Take Away: There was no significant change in total payment processing time. However, since “payment processing time” was a “critical X” and
identified by the Contractor’s as a significant issue, the team decided they needed to complete some further analysis. The team discovered the data retrieved
from PRIMELink did not capture the time expended from the Contractor with-holding and not submitting Payment Requests in PRIMELink to avoid Payment
Requests from being rejected. If the with-holding days were accounted for then the total payment processing time would have reflected as taking longer than
it use to. With this, the team then focused on what was causing the Contractor to not to enter payment requests in PRIMELink .
 Team looked at the current
payment processing time and
compared it to the historical
target.
 P-value less than 0.05, so team
rejected the null hypothesis (Ho).
 Result - Total payment processing
isn’t taking longer than it use to,
i.e. there is no significant change
in total payment processing time.
DATA SUMMARY
ONE SIGN HYPOTHESISTEST
Hypothesis: There are more payment request rejects than there use to be.
Key Take Away: There are more payment request rejects than there use to be. There was a total of 146 rejects in FY 2013 and 227 rejects in FY 2014.
Improvement focused on the rejected Payment Requests. More specifically, why they are being rejected and how we can reduce the number of rejects to
increase the number of payments .
 Team looked at the historical
reject volume and compared it to
the historical target.
 P-value is greater than 0.05, so
team failed to reject the null
hypothesis (Ho).
 Result - There are more payment
request rejects than there use to
be.
DATA SUMMARY
0
5
10
15
20
25
30
NumberofRejects
Run Chart
MOOD’S MEDIAN TEST
Hypothesis: Number of rejects seems to be higher for certain reject reasons
Key Take Away: Mood’s Median test confirmed there is a significant difference in the number of rejects for certain reject reasons. Data reflects that
Payment Request rejects are largely attributed to disputed amounts. Team focused on identifying root causes and solutions on how to reduce rejects for
disputed amounts.
 Team met with staff and
Contractor to retrieve
information on reasons why
Payment Requests are rejected
and compared it to the reject data
retrieved from PRIMELink.
 P-value less than 0.05, so team
rejected the null hypothesis (Ho).
 Result: There is a significant
difference in the number of
rejects for certain reject reasons.
DATA SUMMARY
IMPROVE
IMPACT & EFFORT MATRIX Impact Effort Matrix
Objective: Increase Overall Number of Invoices Processed On-Time
Sponsor: TCI Project Delivery, Streets and Support Services Asst. Directors
Stakeholder: Contractor
High Impact
Hard Easy
Low Impact
1. Update PRIMELink workflows to optimize the sequencing
of task order and payment request approval steps (i.e.
adding the City as a Payment Request submitter and
enabling the copy furnish feature to include Contractor
on rejected items).
2. Facilitate the exchange of i-pads for laptop computers so
Inspectors can document quantities in the field.
3. Implement a tolerance threshold for yield calculations to
minimize quantities rejections for minor quantity
threshold discrepancies.
4. Create an inspector quantity log in PRIMELink to allow
inspector to log and track quantities and allow all
authorized users (including the Contractor) to view
quantities.
5. Document and implement a new quantity authorization
process which will entail the documentation,
acknowledgement and agreement of approved quantities.
6. Change invoicing process such that the City will create
and initiate the Payment Request on behalf of the
Contractor based on approved documented quantities.
1
2
34
5
6
Key Take Away: Leveraging the low/high impact quadrant, the team was able to prioritize the implementation of the solutions.
Implementing “quick wins” first and gradually all of the rest the solutions as follows: 3, 1, 2, 4, 5 and 6.
IMPROVE
INNOVATIONTRANSFER OPPORTUNITIES
PROCESS IMPROVEMENT
[Innovation/Addition/Change/Removal]
PROCESS BENEFITS IMPACTED ENTITY
[Area/Department/Business Unit]
Update task order PRIMELink workflow (i.e. enabled the copy
furnish feature to include Contractor on rejected task orders)
• Expedites action needed on rejected task orders
• Reduces time needed to process task order so payment
requests can be submitted
• Contractor
• Streets Engineering ProjectTeam
Update payment request PRIMELink workflow (i.e. added the
City as a Payment Request submitter)
• Provides Contractor option to continue to invoice or permit
the City to invoice on their behalf
• Contractor
• Fiscal
Implemented 5% tolerance threshold for quantity yield
calculations
• Minimize and eliminate the unnecessary rejection of payment
requests due to quantity discrepancies
• Contractor
• Inspector
Established connectivity to PRIMELink for Inspectors in the field
(i.e. facilitated the purchase and exchange of i-pads for laptops
for all TCI Inspectors)
• Inspectors able to remotely access PRIMElink and shared drives
in the field
• Allow for near real time data entry of daily quantities, reports
and approvals
• Promote documentation standardization (i.e. provide a
centralized and easily accessible way to report)
• Eliminated the need for inspectors to drive to and from a
service center to upload data, thus allowing more time to be
spent in the field
• Inspector
Implemented new daily quantity log documentation and
reporting process
• Improved transparency and communication
• Report standardization
• Reduce payment requests for incorrect quantities
• Contractor
• Inspector
•Streets Engineering ProjectTeam
Implemented City initiated payment request (invoicing) process • Ensures timely and consistent payments based on approved quantities • Contractor
• Fiscal
IMPROVE
BEFORE & AFTER PAYMENT REQUEST REJECTS
Key Take Away: Implemented solutions
decreased total number of payments rejected
for disputed quantity amounts by 17%
achieving the project goal of decreasing the
number of rejects for disputed quantity
amounts by 10% or better.
Fiscal Year
Oct. 1 – Sept. 30
42% [ $15.1M]
REJECTED
58% [ $21.6M]
REJECTED
Mean: 15.10
0
5
10
15
20
25
30
RunChart:Data
Run Chart
IMPROVE
RISK MANAGEMENT
Key Take Away: For each identified risk, leveraged training, visual management/procedural guides, system and/or procedural
controls where needed to mitigate risks and proactively elevate issues.
CONTROL
MONITORING & RESPONSE PLAN
MONITORING PLAN
MEASURE
INPUT/OUTPUT/
PROCESS
TRIGGER MEASURES MEASURMENT METHOD
CHECKING
FREQUENCY
WHO MEASURES
Daily Quantities Timing Input Daily Quantity Log must be completed within 48
hours; No later than Tuesdays End of Day
Time Stamp When Log is Completed Daily Inspector
Supervisor
Daily Quantities Discrepancies Output Zero quantity discrepancies prior to invoicing
date (within two weeks of quantities being posted)
Time Stamp When Log is Completed Daily Contractor
Total Payment Requests Timing Process No greater than 15 days (Upper Control Limit) Time Stamp from When Payment Request
is Submitted to When Payment Request is
Paid
Monthly Fiscal Accountant
Total Number of Rejects Process No greater than 27 rejects (Upper Control Limit) Total Number of Rejects By Vendor for
Disputed Amount
Monthly Performance
Management Team
RESPONSE PLAN
DAMAGE CONTROL PROCESS ADJUSTMENT EFFECTIVENESS ASSESSMENT CONTINOUS IMPROVEMENT
Daily Quantity Discrepancies Report any quantity discrepancies to the Inspector to
either correct the discrepancy or agree to not include
in Invoice until discrepancy can be corrected
Determine if discrepancy attributed to typo or
missing documentation Project Team to verify
quantities daily
Project Team to verify once material tickets are
received to what is reflected on daily quantity log,
verify daily entry
Corrected Daily Quantity Log Inspector to either (a) correct quantity on the
appropriate daily quantity log (only if the log has not
already been pulled for invoicing) or (b) create new
daily log and reflect the corrected difference
Project Team and Inspector to review Daily
Quantity Summary Report to monitor quantity
and dollar balances
Project Team through review of balances can as
necessary submit appropriate budget adjustment to
elevate delays in invoicing; Inspector can know when
quantities are not within or exceeding specifications.
Unable to Process Payment
Request Due to Insufficient
Funds
Report funding insufficiency to Project Manager so
that a budget adjustment can be completed.
Project Team will run the summary daily quantity
report to monitor potential over runs.
Project Team and Inspector working together to help
proactively elevate the need for last minute
adjustments at time of invoice rather complete
adjustments sooner.
Rejected Payment Requests Fiscal Accountant to work with Contractor and/or
Project Team on correction needed. If quantity
related, work with Inspector to correct accordingly.
PRIMELink report regarding number of rejects
and payment timing will be evaluated monthly.
Team to review control charts to help trigger
additional investigation of causes and as needed
adjustments to control limits.
Key Take Away: Team devised a monitoring and response plan to help sustain improvements and know how identify as well as
handle issues should they arise.
IMPROVE
RACI MATRIX
TASK FREQUENCY DUE DATE
Responsibility Approver Consulted Informed
The person responsible for
producing the deliverable
and/or completing the task.
The person accountable for
the deliverable.
The person or persons that
must be consulted before a
decision can be made.
The person or persons that
must be informed of any
decision that has been made.
Complete Daily Quantity Usage
Record
Daily
Within 48 hours; No Later
than Tuesdays End of Day
Inspector Inspector Supervisor Project Manager/Team
Construction Management
Manager
Run Daily Quantity Usage Reports
Weekly or As
Needed
Wednesdays End of Day Inspector Supervisor
Construction
Management Manager
Project Manager/Team
Project Delivery Assistant
Director
Review Daily Quantity Usage Reports
Weekly or As
Needed
Wednesdays End of Day Project Manager/Team
Streets Engineering
Manager
Inspector Supervisor Streets Assistant Director
Validate Daily Quantities
Weekly or As
Needed
Wednesdays End of Day Contractor Contractor Owner Project Manager/Team Streets Assistant Director
Communicate Daily Quantity
Discrepancies
As Needed
Within 2 Weeks of Quantities
being Posted
Contractor Contractor Owner Project Manager/Team Streets Assistant Director
Complete Daily Quantity Discrepancy
Revisions
As Needed
Within 2 Weeks of Quantities
being Posted or PM Team
Notification
Inspector Inspector Supervisor Project Manager/Team Contractor
Consolidation of Daily Quantities (for
City Issued Payment Requests)
Monthly or As
Needed
First Wednesdays of Month or
within 48 Hours of Receiving
PM Team Notification
Fiscal Accountant Capital Fiscal Manager Project Manager/Team Contractor
Consolidation of Daily Quantities (for
Vendor Payment Requests)
Monthly or As
Needed
Contractor Contractor Owner Project Manager/Team Streets Assistant Director
Creation & Submission of Payment
Requests
Monthly or As
Needed
First Fridays of Month or
within 48 Hours of Receiving
PM Team Notification
Fiscal Accountant Capital Fiscal Manager Project Manager/Team Contractor
Notification of Overruns Daily As Needed Project Manager/Team
Streets Engineering
Manager
Inspector Supervisor Streets Assistant Director
Creation & Submission Task Orders
(for Overruns or Project Close-Out)
Daily As Needed Project Manager/Team
Streets Engineering
Manager
Inspector Supervisor Streets Assistant Director
Updating Major Changes to Standard
Operating Procedures Document
As Needed As Needed
Performance
Management Team
Inspector Supervisor Project Manager/Team
Project Delivery & Steets
Assistant Director
CONTROL
CONTROL CHART
Key Take Away: Team is continuing to work on causes of variation and control limits. The control charts will be a key part
of TCI’s on-going monitoring of the process in identifying ways to improve and address issues. As a result, of the immediate
success of the 6-month pilot and overwhelming positive response from Contractors following the pilot, TCI has begun
rolling-out the new Daily Quantity Log and Payment Request process for all Street Maintenance Improvement construction
contracts and eventually all TCI managed construction contracts.
PAYMENT REQUESTS
Avg. Process Timing Trigger = 15 Days or Greater
[Upper Control Limit = 16]
16.49
Mean CL: 12.875
9.26
0
5
10
15
20
25
Individuals:Data
Individuals Control Chart
Data UCL CL (Mean) LCL
26.76
15.1025641
3.44
0
5
10
15
20
25
30
C:Data
C (Count) Control Chart
Rejects Data UCL CL (Mean) LCL
REJECTS
No. Rejects Trigger = 20 Rejects or Greater
[Upper Control Limit = 27 Rejects]
NEXT STEPS
Black Belt Project Storyboard
Task Order & Invoicing Process Improvement
EXTEND SUSTAIN
COLLABORATE IMPROVE
Roll out daily inspection
quantity and invoicing process
for all other capital
construction contracts.
IMPROVEMENT
Coordinate with local utilities to
have them begin utilizing new
daily inspection quantity and
invoicing process for utility
work on City projects.
Continue to retrieve feedback
from process owner, staff and
contractors. Follow through
and review monitor and control
plans.
Continue quarterly meeting
with process owners and users
to access process progress,
identify ways to improve and
address any associated issues.
LESSONS LEARNED
Lessons
Learned
Lean Six Sigma methodology is not just
applicable to manufacturing operations it can
be applied in Municipal business functions and
services.
Lean Six Sigma methodology has provided a
roadmap to not only implement but sustain
improvements .
Data does matter – performance and its
established triggers are essential in maintaining
efficient and effective delivery of
services/deliverables.
Lean Six Sigma Methodology
Having a clear and consistent communication plan is
key in sustaining success and ensuring issues are
addressed accordingly. Communication helps fosters
better collaboration and a greater awareness of the
team’s overall goal and responsibilities.
Communication
Lack of standardized, documented and agreed
upon policies/processes leads to variability which
results in inconsistency, additional work and
potentially costly processing delays.
Creating uniform policies and procedures helps
reduce confusion and improves communication
for City staff and among Contractors.
Information regarding policies and procedures
should be accessible and easy to understand both
for Contractors and City staff.
Standardized Processes
With out the involvement through the project and
buy-in of the process owner of the improved
process the realized improvements can not be
sustained. Simply, “if its not important to the boss
its not important to staff.”
Ownership
APPENDIX
Lean Six Sigma Black Belt Project Storyboard
Task Order & Invoicing Process Timing
TASKORDER&INVOICINGTIMING
STAKEHOLDER ANALYSIS
Key Take Away: There was no resistance to the process improvement and all appropriate key stakeholders were included as
part of the team.
TASKORDER&INVOICETIMING
AS-IS PROCESS MAPS
Key Take Away: Understanding the Task Order and associated Payment
Process was instrumental in identifying areas of focus and has provided City staff
a renewed and visible perspective of the entire process.
TASKORDER&INVOICINGTIMING
FIVE (5)WHY’S
Why are Payment Requests rejected?
Why ?: Contractor quantities included in Payment Request do not
match City’s verified quantities.
Why ?: Verified daily quantities information is not easily accessible or
consistently provided to confirm quantities are correct.
Why?: Documentation and delivery of daily quantities information
varies by City Inspector.
Why?: There currently is no standard documentation and reporting
process for daily quantities.
Key Take Away: Payment Requests rejected for disputed quantities is attributable to the lack of a defined process
and impacts the Contractor, City Project Team and City Inspector.
Expedite
Project Delivery
and Completion
of Infrastructure
Projects
City-Wide
City Staff
Contractor
City
Processes
Reporting &
Tools
MATCHING X &Y MEASURES
Key Take Away: X’s that impact Y (Expedited project delivery and completion
of Infrastructure Projects city-wide) are as follows: City Staff (includes Project
Team and Inspector), Contractor, City’s Processes and reporting/tools.
X1 X2 X3 X4 Y
City Staff
Communication
Report Duplication
Contractor
Communication
Consistency
City Processes
Standardization
Documentation
Reporting &
Tools
Equipment
Transparency
Standardization
Accessibility
Expedite
Project
Delivery and
Completion of
Infrastructure
Projects City-
Wide
TASKORDER&INVOICINGTIMING
8 WASTES CHECK SHEET
Process Area: Daily Quantity Process
Waste Definition Level Description of Issues
D Defects
Information, products and services that are incomplete
or inaccurate
High
Inconsistent documentation of daily project quantities
makes it difficult to research, verify and approve quantities;
instances of incorrect quantities more likely
O Overproduction
Making more of something - making it earlier or faster-
than it's needed
High
Redundant and non-transparent documentation (i.e.
quantities documented in emails and various manual logs by
Contractor, Project Team and Inspectors)
W Waiting
Waiting for information, equipment, materials, parts or
people
Medium
Daily quantities information is not centralized and easily
assessable (i.e. project team and vendor have to await for
information to be sent by Inspector )
N Non-Utilized Talent
Not properly utilizing people's experience, skills,
knowledge or creativity
Medium
Inspectors are unable to leverage PRIMELink in the field
consistently which forces inspectors to track and
communicate manually requiring additional time as a
opposed to documenting information in the system for all
to access
T Transportation
Unnecessary movement of materials, information or
equipment
High
Inspectors not able to document daily quantities in field so
Inspectors manually track and transfer information to
various logs and emails the same information
I Inventory
Accumulation of parts, information, applications, etc.
beyond what is required by the customer
High
Since there is no daily log in PRIMELink Inspectors manually
track quantities in the field and for most they wait until the
end of the week or several days so they have to update
manual logs and provide updates once
M Motion
Any movement by people that is not of value to the
customer
Medium
Project team, vendor and inspector have to search through
manual logs and emails to verify quantities to approve or
reject payment requests
E
Extra-
Processing
Any steps that do not add value in the eyes of the
customer
Medium
Project team, vendor and inspector each track quantities
on their own separate logs same information
TASKORDER&INVOICINGTIMING
COMMUNICATION PLAN
Stakeholder Group Objectives/Actions Desired Message Delivery Method Timing
Executives (Project Champions)
Inform of project findings, create buy-in
and ownership
Results of analysis and hypothesis
tests; solutions selected
Share at Regular
Scheduled Executive Meeting
Within1 Week
Construction Management & Street
Engineering Supervisors
Inform of project findings, install
confidence in team and process
changes
Results of analysis and hypothesis
tests; solutions selected
Schedule Meeting Within 2 Weeks
Construction Management
Inspectors
Inform of project findings, create buy-in
and ownership, participate in pilot & roll-
out
Pilot results, training and
implementation plan
Schedule Meeting Within 3 Weeks
Street Engineering Project Manager
& Project Team Members
Inform of project findings, create buy-in
and ownership, participate in pilot & roll-
out
Pilot results, training and
implementation plan
Schedule Meeting Within 3 Weeks
Fiscal
Purchase new laptops , inform of project
findings, create buy-in and ownership,
participate in pilot & roll-out
Purchasing new hardware,
execution dates, training and
implementation plan
Email
After Executive and
Manager Approval
Vendors
Inform of project findings, create buy-in
and ownership, participate in pilot & roll-
out
Pilot results, training and
implementation plan
Schedule Meeting Within 3 Weeks
Key Take Away: Adhering to Communication Plan was instrumental in making sure the team and its project champions were
informed on what was happening with the project and anticipated due dates.
TASKORDER&INVOICINGTIMING
IMPLEMENTATION PLAN Plan Do Check Act
Action Responsible Due Date
Plan
Complete Test Task Order and Payment Request Work Flow Changes PRIMELink Manager 07/12/2014
Procure (32) Windows-based Laptops ProjectTeam Leader, Fiscal, Information Technology 11/14/2014
Design Inspector Daily Quantity Log in PRIMELink PRIMELink Manager 12/15/2014
Design Daily Quantity Log Detailed & Summary PRIMELink Reports PRIMELink Manager 12/15/2014
Design Payment Request Detailed & Summary PRIMELink Reports PRIMELink Manager 12/15/2014
Facilitate Exchange I-pads for Laptops ProjectTeam Leader, Fiscal, Construction Management 04/02/2015
Do
Create Inspector Daily Quantity Log in PRIMELink PRIMELink Manager 01/15/2015
Create Daily Quantity Log Detailed & Summary Reports in PRIMELink PRIMELink Manager 02/15/2015
Create Payment Request Detailed and Summary Reports in PRIMELink PRIMELink Manager 02/15/2015
Document Procedures,Visual Management Guide and Control Plan for
Inspector Daily Quantity Log and Payment Process
ProjectTeam Leader 04/15/2015
Train PRIMELink Helpdesk, Inspectors, ProjectTeam, Fiscal & Contractor ProjectTeam Leader, PRIMELink Manager 05/08/2015
Check
Deploy Pilot [Test Process & New Changes in PRIMELink with (1)
[Willing and Able Contractor]
PRIMELink Manager 06/26/2015
Monitor Inspector Daily Quantity Log Completion, Payment Process
Timing and RejectVolume for Team
ProjectTeam Leader 07/26/2015
Act
Made Adjustments to Daily Quantity Log and Payment Process Based on
Pilot
ProjectTeam Leader, Construction Management Inspectors, Street
Engineering ProjectTeam, Fiscal
08/03/2015
Roll Out New Daily Quantity Log and Payment Process for All Other
Street Maintenance Construction Contracts
ProjectTeam Leader, Construction Management Inspectors, Street
Engineering ProjectTeam, Fiscal
09/01/2015
Key Take Away: Implementation Plan was used to organize key tasks and provide the team an overview of what is to be completed and the
team’s role in tasks to be completed.
TASKORDER&INVOICINGTIMING
CONTROL CHART
5
1
2
2
2
2
5 5 5
12.88
9.26
16.49
9.00
10.00
11.00
12.00
13.00
14.00
15.00
16.00
17.00
18.00
19.00
20.00
21.00
22.00Individuals:Data
1.36
0.00
4.44
-1.00
0.00
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
MR:Data
Key Take Away: The I-MR-R chart turned out to be the visual tool to review payment processing time. Team has both a cumulative monthly and
daily chart to illustrate the process’s progress and any variation. The Upper Control Limit and Response Plan trigger is 16 days.
I-MR Chart | Monthly Payment ProcessingTime

Más contenido relacionado

La actualidad más candente

Problem solving tools 112411
Problem solving tools 112411Problem solving tools 112411
Problem solving tools 112411Khriztel NaTsu
 
Lean Six Sigma Green Belt Project No-Show Rate Reduction
Lean Six Sigma Green Belt Project No-Show Rate ReductionLean Six Sigma Green Belt Project No-Show Rate Reduction
Lean Six Sigma Green Belt Project No-Show Rate ReductionJohn W. McAfee, MHA, PMP, FACHE
 
Project Storyboard: Reducing Cycle Time for Bid Tab Creation by 33%
Project Storyboard: Reducing Cycle Time for Bid Tab Creationby 33%Project Storyboard: Reducing Cycle Time for Bid Tab Creationby 33%
Project Storyboard: Reducing Cycle Time for Bid Tab Creation by 33%GoLeanSixSigma.com
 
6 sigma-process-mapping-1233778357447980-3
6 sigma-process-mapping-1233778357447980-36 sigma-process-mapping-1233778357447980-3
6 sigma-process-mapping-1233778357447980-3jseets
 
Lean, Six Sigma, ToC using DMAIC - Measure phase
Lean, Six Sigma, ToC using DMAIC - Measure phase Lean, Six Sigma, ToC using DMAIC - Measure phase
Lean, Six Sigma, ToC using DMAIC - Measure phase Simon Misiewicz
 
Lean six sigma black belt project by iftakhar
Lean six sigma black belt project   by iftakharLean six sigma black belt project   by iftakhar
Lean six sigma black belt project by iftakharMohammad IFTAKHAR
 
Analyze phase lean six sigma tollgate template
Analyze phase   lean six sigma tollgate templateAnalyze phase   lean six sigma tollgate template
Analyze phase lean six sigma tollgate templateSteven Bonacorsi
 
Black Belt Project Storyboard Template Example
Black Belt Project Storyboard Template ExampleBlack Belt Project Storyboard Template Example
Black Belt Project Storyboard Template ExampleGoLeanSixSigma.com
 
Lean six sigma tollgate checklists
Lean six sigma tollgate checklistsLean six sigma tollgate checklists
Lean six sigma tollgate checklistsSteven Bonacorsi
 
Service revamp lean six sigma black belt project
Service revamp lean six sigma black belt projectService revamp lean six sigma black belt project
Service revamp lean six sigma black belt projectSumit K Jha
 
Hoshin Kanri: Creating a Strategy Deployment Plan That Gets Results
Hoshin Kanri: Creating a Strategy Deployment Plan That Gets Results Hoshin Kanri: Creating a Strategy Deployment Plan That Gets Results
Hoshin Kanri: Creating a Strategy Deployment Plan That Gets Results TKMG, Inc.
 
Value Stream Mapping in Office & Service Setttings
Value Stream Mapping in Office & Service SetttingsValue Stream Mapping in Office & Service Setttings
Value Stream Mapping in Office & Service SetttingsTKMG, Inc.
 

La actualidad más candente (20)

Problem solving tools 112411
Problem solving tools 112411Problem solving tools 112411
Problem solving tools 112411
 
Lean Six Sigma Green Belt Project No-Show Rate Reduction
Lean Six Sigma Green Belt Project No-Show Rate ReductionLean Six Sigma Green Belt Project No-Show Rate Reduction
Lean Six Sigma Green Belt Project No-Show Rate Reduction
 
Project Storyboard: Reducing Cycle Time for Bid Tab Creation by 33%
Project Storyboard: Reducing Cycle Time for Bid Tab Creationby 33%Project Storyboard: Reducing Cycle Time for Bid Tab Creationby 33%
Project Storyboard: Reducing Cycle Time for Bid Tab Creation by 33%
 
6 sigma-process-mapping-1233778357447980-3
6 sigma-process-mapping-1233778357447980-36 sigma-process-mapping-1233778357447980-3
6 sigma-process-mapping-1233778357447980-3
 
Dmaic
DmaicDmaic
Dmaic
 
Lean, Six Sigma, ToC using DMAIC - Measure phase
Lean, Six Sigma, ToC using DMAIC - Measure phase Lean, Six Sigma, ToC using DMAIC - Measure phase
Lean, Six Sigma, ToC using DMAIC - Measure phase
 
Lean six sigma black belt project by iftakhar
Lean six sigma black belt project   by iftakharLean six sigma black belt project   by iftakhar
Lean six sigma black belt project by iftakhar
 
Analyze phase lean six sigma tollgate template
Analyze phase   lean six sigma tollgate templateAnalyze phase   lean six sigma tollgate template
Analyze phase lean six sigma tollgate template
 
Six sigma-black-belt-project-sample
Six sigma-black-belt-project-sampleSix sigma-black-belt-project-sample
Six sigma-black-belt-project-sample
 
LeanKaizenTraining
LeanKaizenTrainingLeanKaizenTraining
LeanKaizenTraining
 
Lean Six Sigma Projects
Lean Six Sigma ProjectsLean Six Sigma Projects
Lean Six Sigma Projects
 
Black Belt Project Storyboard Template Example
Black Belt Project Storyboard Template ExampleBlack Belt Project Storyboard Template Example
Black Belt Project Storyboard Template Example
 
Six Sigma Sample Project
Six Sigma Sample ProjectSix Sigma Sample Project
Six Sigma Sample Project
 
Lean six sigma tollgate checklists
Lean six sigma tollgate checklistsLean six sigma tollgate checklists
Lean six sigma tollgate checklists
 
Extension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed IbarhimExtension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed Ibarhim
 
Service revamp lean six sigma black belt project
Service revamp lean six sigma black belt projectService revamp lean six sigma black belt project
Service revamp lean six sigma black belt project
 
Hoshin Kanri: Creating a Strategy Deployment Plan That Gets Results
Hoshin Kanri: Creating a Strategy Deployment Plan That Gets Results Hoshin Kanri: Creating a Strategy Deployment Plan That Gets Results
Hoshin Kanri: Creating a Strategy Deployment Plan That Gets Results
 
Dmaic
DmaicDmaic
Dmaic
 
Value Stream Mapping in Office & Service Setttings
Value Stream Mapping in Office & Service SetttingsValue Stream Mapping in Office & Service Setttings
Value Stream Mapping in Office & Service Setttings
 
Value Stream Mapping in the Office
Value Stream Mapping in the Office Value Stream Mapping in the Office
Value Stream Mapping in the Office
 

Similar a How The City of San Antonio Increased Payments For Street Maintenance Using Lean Six Sigma

Construction Process Proposal PowerPoint Presentation Slides
Construction Process Proposal PowerPoint Presentation SlidesConstruction Process Proposal PowerPoint Presentation Slides
Construction Process Proposal PowerPoint Presentation SlidesSlideTeam
 
CV waqar Azeem QS
CV waqar Azeem QSCV waqar Azeem QS
CV waqar Azeem QSWAQAR AZEEM
 
Payment claim process for large contracts
Payment claim process for large contractsPayment claim process for large contracts
Payment claim process for large contractsJohn Lowry
 
Payment claim process for large contracts
Payment claim process for large contractsPayment claim process for large contracts
Payment claim process for large contractsJohn Lowry
 
CASE STUDY 1 Alternative Water Supply Gordon Rivers, the city manage.pdf
CASE STUDY 1 Alternative Water Supply Gordon Rivers, the city manage.pdfCASE STUDY 1 Alternative Water Supply Gordon Rivers, the city manage.pdf
CASE STUDY 1 Alternative Water Supply Gordon Rivers, the city manage.pdfrahulfancycorner21
 
FMA - 2_CM651_Group.pptx
FMA - 2_CM651_Group.pptxFMA - 2_CM651_Group.pptx
FMA - 2_CM651_Group.pptxArJayTambaoan
 
Siddhant Singh Parmar-new resume (17.02.2016).compressed
Siddhant Singh Parmar-new resume (17.02.2016).compressedSiddhant Singh Parmar-new resume (17.02.2016).compressed
Siddhant Singh Parmar-new resume (17.02.2016).compressedsiddhant singh parmar
 
Project Management Control
Project Management ControlProject Management Control
Project Management ControlVinay Mangrulkar
 
Item # 11 - PPT Auustin Hwy/Lower Broadway Improvement Project RFQ
Item # 11 - PPT Auustin Hwy/Lower Broadway Improvement Project RFQItem # 11 - PPT Auustin Hwy/Lower Broadway Improvement Project RFQ
Item # 11 - PPT Auustin Hwy/Lower Broadway Improvement Project RFQahcitycouncil
 
Improve Your Outcomes on Cost Type Contracts
Improve Your Outcomes on Cost Type ContractsImprove Your Outcomes on Cost Type Contracts
Improve Your Outcomes on Cost Type ContractsUnanet
 
SUMMER INTERNSHIP REPORT FOR 3RD YEAR STUDENT
SUMMER INTERNSHIP REPORT FOR 3RD YEAR STUDENT SUMMER INTERNSHIP REPORT FOR 3RD YEAR STUDENT
SUMMER INTERNSHIP REPORT FOR 3RD YEAR STUDENT Irfan Quraishi
 
Project plan and charter
Project plan and charterProject plan and charter
Project plan and charterkecia26
 
MANAGEMENT OF PROJECTS IN LOCAL GOVERNMENT
MANAGEMENT OF PROJECTS IN LOCAL GOVERNMENTMANAGEMENT OF PROJECTS IN LOCAL GOVERNMENT
MANAGEMENT OF PROJECTS IN LOCAL GOVERNMENTTaiwo Okuselu
 

Similar a How The City of San Antonio Increased Payments For Street Maintenance Using Lean Six Sigma (20)

Van herrera cv
Van herrera   cvVan herrera   cv
Van herrera cv
 
Kiran H K 17-06-2016
Kiran H K 17-06-2016Kiran H K 17-06-2016
Kiran H K 17-06-2016
 
CV Shreenivash Chandra
CV Shreenivash ChandraCV Shreenivash Chandra
CV Shreenivash Chandra
 
Construction Process Proposal PowerPoint Presentation Slides
Construction Process Proposal PowerPoint Presentation SlidesConstruction Process Proposal PowerPoint Presentation Slides
Construction Process Proposal PowerPoint Presentation Slides
 
CV waqar Azeem QS
CV waqar Azeem QSCV waqar Azeem QS
CV waqar Azeem QS
 
Payment claim process for large contracts
Payment claim process for large contractsPayment claim process for large contracts
Payment claim process for large contracts
 
Payment claim process for large contracts
Payment claim process for large contractsPayment claim process for large contracts
Payment claim process for large contracts
 
CV SHIRISH 1-1-2015
CV SHIRISH 1-1-2015CV SHIRISH 1-1-2015
CV SHIRISH 1-1-2015
 
CV Shehzad SQS
CV Shehzad SQSCV Shehzad SQS
CV Shehzad SQS
 
CASE STUDY 1 Alternative Water Supply Gordon Rivers, the city manage.pdf
CASE STUDY 1 Alternative Water Supply Gordon Rivers, the city manage.pdfCASE STUDY 1 Alternative Water Supply Gordon Rivers, the city manage.pdf
CASE STUDY 1 Alternative Water Supply Gordon Rivers, the city manage.pdf
 
FMA - 2_CM651_Group.pptx
FMA - 2_CM651_Group.pptxFMA - 2_CM651_Group.pptx
FMA - 2_CM651_Group.pptx
 
Siddhant Singh Parmar-new resume (17.02.2016).compressed
Siddhant Singh Parmar-new resume (17.02.2016).compressedSiddhant Singh Parmar-new resume (17.02.2016).compressed
Siddhant Singh Parmar-new resume (17.02.2016).compressed
 
Project Management Control
Project Management ControlProject Management Control
Project Management Control
 
Govind_Bio
Govind_BioGovind_Bio
Govind_Bio
 
Item # 11 - PPT Auustin Hwy/Lower Broadway Improvement Project RFQ
Item # 11 - PPT Auustin Hwy/Lower Broadway Improvement Project RFQItem # 11 - PPT Auustin Hwy/Lower Broadway Improvement Project RFQ
Item # 11 - PPT Auustin Hwy/Lower Broadway Improvement Project RFQ
 
Improve Your Outcomes on Cost Type Contracts
Improve Your Outcomes on Cost Type ContractsImprove Your Outcomes on Cost Type Contracts
Improve Your Outcomes on Cost Type Contracts
 
SUMMER INTERNSHIP REPORT FOR 3RD YEAR STUDENT
SUMMER INTERNSHIP REPORT FOR 3RD YEAR STUDENT SUMMER INTERNSHIP REPORT FOR 3RD YEAR STUDENT
SUMMER INTERNSHIP REPORT FOR 3RD YEAR STUDENT
 
Mohannad Al Twait-CV1
Mohannad Al Twait-CV1Mohannad Al Twait-CV1
Mohannad Al Twait-CV1
 
Project plan and charter
Project plan and charterProject plan and charter
Project plan and charter
 
MANAGEMENT OF PROJECTS IN LOCAL GOVERNMENT
MANAGEMENT OF PROJECTS IN LOCAL GOVERNMENTMANAGEMENT OF PROJECTS IN LOCAL GOVERNMENT
MANAGEMENT OF PROJECTS IN LOCAL GOVERNMENT
 

Más de GoLeanSixSigma.com

Webinar: Process Improvement in Government Using Lean Six Sigma
Webinar: Process Improvement in Government Using Lean Six SigmaWebinar: Process Improvement in Government Using Lean Six Sigma
Webinar: Process Improvement in Government Using Lean Six SigmaGoLeanSixSigma.com
 
Webinar: How to Create Predictable Cash Flow With Lean Six Sigma Projects
Webinar: How to Create Predictable Cash Flow With Lean Six Sigma ProjectsWebinar: How to Create Predictable Cash Flow With Lean Six Sigma Projects
Webinar: How to Create Predictable Cash Flow With Lean Six Sigma ProjectsGoLeanSixSigma.com
 
Webinar: How Soldiers Receive 100% Funding for Lean Six Sigma Certification
Webinar: How Soldiers Receive 100% Funding for Lean Six Sigma CertificationWebinar: How Soldiers Receive 100% Funding for Lean Six Sigma Certification
Webinar: How Soldiers Receive 100% Funding for Lean Six Sigma CertificationGoLeanSixSigma.com
 
Webinar: 10 Tips for a Standout Lean Six Sigma Green Belt Project
Webinar: 10 Tips for a Standout Lean Six Sigma Green Belt ProjectWebinar: 10 Tips for a Standout Lean Six Sigma Green Belt Project
Webinar: 10 Tips for a Standout Lean Six Sigma Green Belt ProjectGoLeanSixSigma.com
 
Webinar: How Army Soldiers Can Advance Their Careers With Green Belt Training...
Webinar: How Army Soldiers Can Advance Their Careers With Green Belt Training...Webinar: How Army Soldiers Can Advance Their Careers With Green Belt Training...
Webinar: How Army Soldiers Can Advance Their Careers With Green Belt Training...GoLeanSixSigma.com
 
Webinar: Going Remote - How Process Improvement Teams Collaborate Virtually
Webinar: Going Remote - How Process Improvement Teams Collaborate VirtuallyWebinar: Going Remote - How Process Improvement Teams Collaborate Virtually
Webinar: Going Remote - How Process Improvement Teams Collaborate VirtuallyGoLeanSixSigma.com
 
How to Request Army Credentialing Assistance on ArmyIgnited.com
How to Request Army Credentialing Assistance on ArmyIgnited.comHow to Request Army Credentialing Assistance on ArmyIgnited.com
How to Request Army Credentialing Assistance on ArmyIgnited.comGoLeanSixSigma.com
 
Webinar: Remote Learning - How to Successfully Switch Lean Six Sigma Training...
Webinar: Remote Learning - How to Successfully Switch Lean Six Sigma Training...Webinar: Remote Learning - How to Successfully Switch Lean Six Sigma Training...
Webinar: Remote Learning - How to Successfully Switch Lean Six Sigma Training...GoLeanSixSigma.com
 
Webinar: How Tax Preparers & Accountants Can Increase Their Profitability Usi...
Webinar: How Tax Preparers & Accountants Can Increase Their Profitability Usi...Webinar: How Tax Preparers & Accountants Can Increase Their Profitability Usi...
Webinar: How Tax Preparers & Accountants Can Increase Their Profitability Usi...GoLeanSixSigma.com
 
Webinar: Remote Learning - How to Brainstorm Lean Six Sigma Improvement Ideas
Webinar: Remote Learning - How to Brainstorm Lean Six Sigma Improvement IdeasWebinar: Remote Learning - How to Brainstorm Lean Six Sigma Improvement Ideas
Webinar: Remote Learning - How to Brainstorm Lean Six Sigma Improvement IdeasGoLeanSixSigma.com
 
Webinar: How to Facilitate Successful Virtual Kaizen Events
Webinar: How to Facilitate Successful Virtual Kaizen EventsWebinar: How to Facilitate Successful Virtual Kaizen Events
Webinar: How to Facilitate Successful Virtual Kaizen EventsGoLeanSixSigma.com
 
Webinar: Online Green Belt Workshop Information Session
Webinar: Online Green Belt Workshop Information SessionWebinar: Online Green Belt Workshop Information Session
Webinar: Online Green Belt Workshop Information SessionGoLeanSixSigma.com
 
Webinar: Online Green Belt Information Session
Webinar: Online Green Belt Information SessionWebinar: Online Green Belt Information Session
Webinar: Online Green Belt Information SessionGoLeanSixSigma.com
 
Webinar: Going Virtual - How to Coach Problem Solvers on A3s
Webinar: Going Virtual - How to Coach Problem Solvers on A3sWebinar: Going Virtual - How to Coach Problem Solvers on A3s
Webinar: Going Virtual - How to Coach Problem Solvers on A3sGoLeanSixSigma.com
 
Webinar: How to Manage Your Project to Completion Using the Project Builder
Webinar: How to Manage Your Project to Completion Using the Project BuilderWebinar: How to Manage Your Project to Completion Using the Project Builder
Webinar: How to Manage Your Project to Completion Using the Project BuilderGoLeanSixSigma.com
 
Webinar: DMAIC: Common Challenges & How to Overcome Them
Webinar: DMAIC: Common Challenges & How to Overcome ThemWebinar: DMAIC: Common Challenges & How to Overcome Them
Webinar: DMAIC: Common Challenges & How to Overcome ThemGoLeanSixSigma.com
 
WEBINAR: How to Deploy Lean Six Sigma in Your Organization
WEBINAR: How to Deploy Lean Six Sigma in Your OrganizationWEBINAR: How to Deploy Lean Six Sigma in Your Organization
WEBINAR: How to Deploy Lean Six Sigma in Your OrganizationGoLeanSixSigma.com
 
WEBINAR: Introduction to Process Management
WEBINAR: Introduction to Process ManagementWEBINAR: Introduction to Process Management
WEBINAR: Introduction to Process ManagementGoLeanSixSigma.com
 
Webinar: How to Use a Fishbone Diagram (Encore!)
Webinar: How to Use a Fishbone Diagram (Encore!)Webinar: How to Use a Fishbone Diagram (Encore!)
Webinar: How to Use a Fishbone Diagram (Encore!)GoLeanSixSigma.com
 
WEBINAR: Introduction to Value Stream Mapping
WEBINAR: Introduction to Value Stream MappingWEBINAR: Introduction to Value Stream Mapping
WEBINAR: Introduction to Value Stream MappingGoLeanSixSigma.com
 

Más de GoLeanSixSigma.com (20)

Webinar: Process Improvement in Government Using Lean Six Sigma
Webinar: Process Improvement in Government Using Lean Six SigmaWebinar: Process Improvement in Government Using Lean Six Sigma
Webinar: Process Improvement in Government Using Lean Six Sigma
 
Webinar: How to Create Predictable Cash Flow With Lean Six Sigma Projects
Webinar: How to Create Predictable Cash Flow With Lean Six Sigma ProjectsWebinar: How to Create Predictable Cash Flow With Lean Six Sigma Projects
Webinar: How to Create Predictable Cash Flow With Lean Six Sigma Projects
 
Webinar: How Soldiers Receive 100% Funding for Lean Six Sigma Certification
Webinar: How Soldiers Receive 100% Funding for Lean Six Sigma CertificationWebinar: How Soldiers Receive 100% Funding for Lean Six Sigma Certification
Webinar: How Soldiers Receive 100% Funding for Lean Six Sigma Certification
 
Webinar: 10 Tips for a Standout Lean Six Sigma Green Belt Project
Webinar: 10 Tips for a Standout Lean Six Sigma Green Belt ProjectWebinar: 10 Tips for a Standout Lean Six Sigma Green Belt Project
Webinar: 10 Tips for a Standout Lean Six Sigma Green Belt Project
 
Webinar: How Army Soldiers Can Advance Their Careers With Green Belt Training...
Webinar: How Army Soldiers Can Advance Their Careers With Green Belt Training...Webinar: How Army Soldiers Can Advance Their Careers With Green Belt Training...
Webinar: How Army Soldiers Can Advance Their Careers With Green Belt Training...
 
Webinar: Going Remote - How Process Improvement Teams Collaborate Virtually
Webinar: Going Remote - How Process Improvement Teams Collaborate VirtuallyWebinar: Going Remote - How Process Improvement Teams Collaborate Virtually
Webinar: Going Remote - How Process Improvement Teams Collaborate Virtually
 
How to Request Army Credentialing Assistance on ArmyIgnited.com
How to Request Army Credentialing Assistance on ArmyIgnited.comHow to Request Army Credentialing Assistance on ArmyIgnited.com
How to Request Army Credentialing Assistance on ArmyIgnited.com
 
Webinar: Remote Learning - How to Successfully Switch Lean Six Sigma Training...
Webinar: Remote Learning - How to Successfully Switch Lean Six Sigma Training...Webinar: Remote Learning - How to Successfully Switch Lean Six Sigma Training...
Webinar: Remote Learning - How to Successfully Switch Lean Six Sigma Training...
 
Webinar: How Tax Preparers & Accountants Can Increase Their Profitability Usi...
Webinar: How Tax Preparers & Accountants Can Increase Their Profitability Usi...Webinar: How Tax Preparers & Accountants Can Increase Their Profitability Usi...
Webinar: How Tax Preparers & Accountants Can Increase Their Profitability Usi...
 
Webinar: Remote Learning - How to Brainstorm Lean Six Sigma Improvement Ideas
Webinar: Remote Learning - How to Brainstorm Lean Six Sigma Improvement IdeasWebinar: Remote Learning - How to Brainstorm Lean Six Sigma Improvement Ideas
Webinar: Remote Learning - How to Brainstorm Lean Six Sigma Improvement Ideas
 
Webinar: How to Facilitate Successful Virtual Kaizen Events
Webinar: How to Facilitate Successful Virtual Kaizen EventsWebinar: How to Facilitate Successful Virtual Kaizen Events
Webinar: How to Facilitate Successful Virtual Kaizen Events
 
Webinar: Online Green Belt Workshop Information Session
Webinar: Online Green Belt Workshop Information SessionWebinar: Online Green Belt Workshop Information Session
Webinar: Online Green Belt Workshop Information Session
 
Webinar: Online Green Belt Information Session
Webinar: Online Green Belt Information SessionWebinar: Online Green Belt Information Session
Webinar: Online Green Belt Information Session
 
Webinar: Going Virtual - How to Coach Problem Solvers on A3s
Webinar: Going Virtual - How to Coach Problem Solvers on A3sWebinar: Going Virtual - How to Coach Problem Solvers on A3s
Webinar: Going Virtual - How to Coach Problem Solvers on A3s
 
Webinar: How to Manage Your Project to Completion Using the Project Builder
Webinar: How to Manage Your Project to Completion Using the Project BuilderWebinar: How to Manage Your Project to Completion Using the Project Builder
Webinar: How to Manage Your Project to Completion Using the Project Builder
 
Webinar: DMAIC: Common Challenges & How to Overcome Them
Webinar: DMAIC: Common Challenges & How to Overcome ThemWebinar: DMAIC: Common Challenges & How to Overcome Them
Webinar: DMAIC: Common Challenges & How to Overcome Them
 
WEBINAR: How to Deploy Lean Six Sigma in Your Organization
WEBINAR: How to Deploy Lean Six Sigma in Your OrganizationWEBINAR: How to Deploy Lean Six Sigma in Your Organization
WEBINAR: How to Deploy Lean Six Sigma in Your Organization
 
WEBINAR: Introduction to Process Management
WEBINAR: Introduction to Process ManagementWEBINAR: Introduction to Process Management
WEBINAR: Introduction to Process Management
 
Webinar: How to Use a Fishbone Diagram (Encore!)
Webinar: How to Use a Fishbone Diagram (Encore!)Webinar: How to Use a Fishbone Diagram (Encore!)
Webinar: How to Use a Fishbone Diagram (Encore!)
 
WEBINAR: Introduction to Value Stream Mapping
WEBINAR: Introduction to Value Stream MappingWEBINAR: Introduction to Value Stream Mapping
WEBINAR: Introduction to Value Stream Mapping
 

Último

MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLSeo
 
Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1kcpayne
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756dollysharma2066
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...Aggregage
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdfRenandantas16
 
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...amitlee9823
 
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...rajveerescorts2022
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsP&CO
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangaloreamitlee9823
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLBAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLkapoorjyoti4444
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxpriyanshujha201
 
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...allensay1
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Centuryrwgiffor
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 
John Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfJohn Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfAmzadHosen3
 

Último (20)

MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 
Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
 
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
 
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLBAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
 
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
John Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfJohn Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdf
 

How The City of San Antonio Increased Payments For Street Maintenance Using Lean Six Sigma

  • 1. LEAN SIX SIGMA BLACK BELT PROJECT STORYBOARD CITY OF SAN ANTONIO |TASK ORDER & INVOICING PROCESS TIMING MARCH 24, 2016 JESSICA M. SHIRLEY-SAENZ PROJECT CONTROL MANAGER | TRANSPORTATION & CAPITAL IMPROVEMENTS DEPARTMENT
  • 2. TABLEOFCONTENTS DEFINE Project Charter | Tools KEYWORDS 4 EXECUTIVE SUMMARY 3 DMAIC METHODOLOGY 5 MEASURE Data Collection | Baseline Measures | Tools ANALYZE Root Cause Analysis | Tools IMPROVE Solutions| Implementation Plan | Charts | Tools CONTROL Control & Monitoring Plans | Next Steps | Lessons Learned APPENDIX 23
  • 3. TASKORDER&INVOICINGTIMING EXECUTIVE SUMMARY Construction ManagementProblem Statement Project Control ComplianceBusiness Case In April 2014, the City received complaints from on-call task order Contractors regarding how long it takes to receive payment for completing work on street maintenance projects. Contractors alleged that payments were taking longer than it use to, up to 30 or more days to receive. Consequently, if payments are delayed, Contractors and their subcontractors are not paid. If continued, Contractors would no longer bid on City projects which would delay the completion of street maintenance projects city-wide. If street maintenance projects are not completed this will negatively impact and potentially compromise the City’s infrastructure - namely, its safety, transportation conveniences and accessibility. Project Results Graphical Display of ImprovementRoot Cause Analysis Identified delays in efficiently processing task order payments was significantly attributed to: ▪ Payments Rejected for Incorrect Quantities – Due to inconsistent, redundant and non- transparent documentation of approved quantities. ▪ Delayed and Combined Payment Requests (Invoicing) – Due to invoices being submitted long after project completion, an additional review was being required to verify quantities. Solutions Implemented ▪ Implemented a tolerance threshold for quantity yield calculations to reduce number of rejects for disputed quantity amounts ▪ Implemented new daily quantity process to centralize and standardize the documentation of daily quantities information ▪ Updated the payment workflow so City can invoice on behalf of Contractor to improve timeliness and eliminate the additional review of quantities ▪ Increased overall number of payments processed monthly for street maintenance task orders from an average of 97 payment requests to 116 payment requests ▪ Reduced the overall number of rejected payments for disputed quantity amounts from an average of 17 rejects to 12 rejects ▪ Reduced the overall percentage of rejected payments for disputed quantity amounts from 58% ($21.6 million) to 42% ($15 million)
  • 4. KEYWORDS Lean Six Sigma Black Belt Project Storyboard Task Order & Invoicing Process Timing Construction Management Responsible for the review and approval of task orders and invoices; and creation as well as closure of Task Order Purchase Orders in the City’s financial system (i.e. SAP). City Fiscal Accountant Project Control Compliance Contracts Fiscal Responsible for inspecting the work Contractors perform to ensure consistency with contract drawings and specification. Inspects the work as acceptable, documents construction quantities and approves payment. City Inspector Consists of City’s Project Manager (PM) (customarily, an Engineer) and Project Team. Oversees the work Contractors perform, is consistent with the contract drawings and specifications, affirms the completed work as acceptable, submits task orders and approves payment. City Project Team Responsible to perform construction work as defined by the contract drawings and specifications. Contractor Is a PRIMELink form used by the Contractor or City to bill (i.e. invoice) on behalf of the Contractor for work completed. Payment Request Is a hosted enterprise capital improvements project portal system. It manages the electronic routing and storage of capital project documents such as Task Orders, Invoices, Payment data and all other associated project documents (i.e. change orders, contracts, plans, RFIs, submittals, etc…). PRIMELink System Quantities refer to the itemized list of work, materials and any cost related items supplied by the contractor in order to complete the requested work. Actual billable quantities are verified by a City Inspector and included in the Payment Request so the Contractor is paid for those items. Quantities Is a PRIMELink form used by the City to authorize work consistent with the scope of the contract and within the existing contract dollar authorization. It is needed to create a Purchase Order (PO) for work to be completed. Task Order Transportation and Capital Improvements Department (TCI) oversees and directs the development and maintenance of the publicly owned infrastructure of the City of San Antonio. TCI
  • 5. DEFINE PROJECT CHARTER Construction ManagementProblem Statement Project Control Compliance Contracts Goal Statement Scope In/Out Problem Statement Timeline Team Members Business Case & Benefits On-call task order Contractors are complaining about how long it takes to receive payment after completing work on street maintenance projects. The average standard processing time is 13 days, if all of the quantities are correct and scope of work is pre- approved prior to the start of work. POSITION PERSON Executive Sponsor Mike Frisbie, TCI Director Project Champion(s) Anthony Chukwudolue, TCI Streets Asst. Director Debbie Racca-Sittre, TCI Support Services Asst. Director Razi Hosseini, TCI Project Delivery Asst. Director The goal is to increase the number of payment requests processed by decreasing the number of rejected invoices for disputed quantity amounts by 10% or more by the end of 4th Quarter in FY 2015 (September 2015) . In Scope: Street Maintenance City Construction Task Order Contracts, Process Steps (Including Task Order, Payment & Associating Processes), System Upgrades Out of Scope: Street Maintenance Utility (Electric, Gas or Sewer) Work Task Orders Improved timeliness of payment requests to Contractors will result in more timely payments to Subcontractors and restore Contractors’ confidence with the City’s invoicing process (as more reliable). Which will translate to Contractors wanting to continue to bid on City street maintenance projects; and, allow the City to release funds that would otherwise remain encumbered delaying completion of other projects. PHASE PLANNED ACTUAL Define April 28, 2014 April 28, 2014 Measure May 19, 2014 May 26, 2014 Analyze July 24, 2014 July 24, 2014 Improve August 25, 2014 *April 2, 2015 Control September 1, 2014 *August 3, 2015 *Project delays attributed to: (1) Team awaiting for completion of FY 2015 budget to buy laptops needed for TCI inspectors to complete the new daily quantity log in the field. (2) Team awaiting start of new Street Maintenance Task Order contracts. POSITION PERSON Project Manager Jessica M. Shirley-Saenz Core Team Members Contractors Fiscal PRIMELink Manager TCI Streets Engineering Project Teams TCI Inspectors
  • 6. DEFINE SIPOC Key Take Away: The scope of this project begins with the planning of the task order and includes when the work is initiated up through inspection of the work, ending with the payment for the work completed. S I P O C Supplier Input Process Output Customer Work Planning  Agreed Upon Project Scope Planning Payment Contractor Contractor  Defined Project Limits Initial Phase of Task Order  Completed Project Work (City) Project Team  Estimated Quantities Define Project Scope & Quantities  Inspected Work (City) Inspector  Completion of Work  Agreed Upon Quantities Work Task Creation  Inspection of Work Creation Contractor  Quantity Verification Task Order (Authorization/Approval of Work)(City) Project Team Work Completion (Contractor) Work Crew Execution (Contractor) Superintendent Work Completion CUSTOMER REQUIREMENTS (City) Inspector Inspection & Quantity Verification Payment Timely & Consistent Payment (Contractor) Fiscal Rep Payment Transparency (Contractor) Superintendent Payment Request Creation Improved Communication (City) Project Team Payment Request Approval (City) Inspector Close-Out Close-Out (Contractor) Fiscal Rep Project Completion (City) Project Team Coordination of Final Payment (City) Inspector Final Task Order Completion
  • 7. DEFINE VOICE OF THE CUSTOMER Construction ManagementProblem Statement Project Control Compliance Contracts Fiscal Customer Comment Gathering More Understanding Customer Requirement “It takes forever to receive payment for work I complete” Contractor not receiving payments timely Payments should be processed within 13 days or less “I can’t invoice because the task order isn’t even processed yet” Contractor completes work prior to task order being processed Require the task order must be processed prior to work start “I don’t submit invoices anymore because they just get rejected” Contractor stop submitting payments because payments are rejected for incorrect quantities Quantities are documented and accessible daily and agreed upon daily “I’d be happy if I could just get paid for the work quantities we do agree upon, we can work out the ones we disagree with later” Once the payment request is submitted the Contractor nor the City can modify or remove quantity pay items; one disputed item out of a list of many will hold up an entire Payment Request Should have ability to generate an Payment Request with approved quantities only and pend disputing quantities until resolved “I have to wait for quantities and when I do get them I have to hunt through emails or call inspector for quantities” City Inspector documents quantities on various manual logs and provides quantities manually to the City’s ProjectTeam and Contractor through email or by phone Establish a consistent and standard process to document and provide quantity information to City staff and Contractor Key Take Away: Project needs to address the documentation process of a project’s daily quantities. Specifically, the standardization, accessibility and consistency. Standardization of this process will help identify and rectify quantity errors in a more timely manner which will help reduce the number of rejected payments and in turn increase the number of timely payments made.
  • 8. MEASURE DATA COLLECTION PLAN Measure Data Type Operational Definition Stratification Factors Sampling Notes Who and How Total Number of Task Orders Continuous Street Maintenance City Task Orders not rejected . All task orders with a “Complete” status. By Contractor By Purchase Order Line Sample includes every task order processed in *Fiscal Years 2012 through 2015. Project Lead retrieve from PRIMELink Administrator/PRIMELink Total Number of Payments Processed Continuous Street Maintenance City Payment Requests not rejected . All Payment Requests with a Payment Date. By Contractor By Purchase Order Line Sample includes every payment request processed in *Fiscal Years 2012 through 2015. Project Lead retrieve from PRIMELink Administrator/PRIMELink Timeliness of Payments Processed Continuous Number of days to process payment. calculated by taking the difference between Payment Request creation date and payment date. List of payments processed within 30 days. By Contractor By Payment Date By Day Ranges [5 days, 10 days, 15 days, 30 days and 30 days+] Sample includes every payment request processed in *Fiscal Years 2012 through 2015. Project Lead retrieve from PRIMELink Administrator/PRIMELink Total Number of Payments Rejected Continuous Street Maintenance City Payment Requests rejected. All payment requests with a “Rejected” status. By Contractor By Reject Date Sample includes every rejected payment request in *Fiscal Years 2012 through 2015. Project Lead retrieve from PRIMELink Administrator/PRIMELink Reject Types Discrete List of reasons for rejects. None Sample includes feedback retrieved from the contractor (with largest volume) and city staff approvers (inspectors, project team & fiscal) Project Lead retrieve from interviews document top reasons and tally Total Number of Rejected Payments by Reject Reason Continuous Street Maintenance City Payment Requests rejected by the identified reasons retrieved from sampling above. By Reject Reason Sample includes every rejected payment request processed in *Fiscal Years 2012 through 2015. Project Lead from PRIMELink Administrator/PRIMELink Key Take Away: Project lead is responsible for all data collection – team and subject matter experts (SMEs) made the appropriate adjustments to provide and/or make themselves available to accommodate the request for information. *Fiscal Year = October 1st – September 30th
  • 9.  Task order Street Maintenance payment requests processed between October 2012 to June 2014 (1,531 Payment Requests valued at $69.3 million) was analyzed to understand within how many days are these payment requests being processed.  It is City’s policy that vendors (i.e. Contractors) be paid by the City within 30 days of the date a correct Payment Request is submitted for work performed for the City. The TCI department’s overall average payment processing time is 11 days.  Pareto shows that 95% of the Street Maintenance payment requests processed between October 2012 to June 2014 were processed within 30 days; and, less than 5% of the payment requests took more than 30 days to process. BASELINE MEASURE Payment RequestTimeliness 36% 34% 18% 7% 5% DATA SUMMARY Key Take Away: Average processing time for task order Street Maintenance payment requests is 13 days. Data shows that 95% of Street Maintenance payment requests when submitted with no issues were processed within 30 days. Baseline Oct. 2012 - June 2014
  • 10. BASELINE MEASURE Payment Rejects  Task order Street Maintenance payment requests rejected between October 2012 to June 2014 (322 valued at $21.6 million) was analyzed to understand the volume and reasons for rejected payment requests.  The Pareto shows that that payment requests were rejected for Disputed Amounts (83%) followed by Utility related disputes (14%) and Budget Adjustment (3%). DATA SUMMARY Key Take Away: Rejected payment requests delay payments made to the Contractor. Baseline data shows Street Maintenance payment requests are rejected more often for disputed amounts than any other reject reason. Team planned on gathering additional information from process experts to help identify what is causing the amounts to be disputed. 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 0 50 100 150 200 250 300 Disputed Amount Utility Budget Adjustment NumberofRejects 83% 14% 3% Baseline Oct. 2012 - June 2014
  • 11. ANALYZE FISHBONE DIAGRAM TOOLS REPORTING CITY PROCESS PAYMENTS CITY PROCESS TASK ORDERS CITY STAFF CONTRACTOR NoTransparency [For Quantities] Inconsistent Documentation Work Completed or Initiated Prior toTask Order Approval Sequencing [Contractor Not Aware of Utility Rejects] Task Order Not Processed Rejected Payments Quantity Discrepancies Lack of Connectivity to PRIMELink in the Field Tracking & Report Duplication [Inspector, Project Team & Vendor Separately Track] Delayed Communication Untimely Payment Request Submissions Combining Payment Requests Delayed Processing of Payment Requests (Payments to Contractors) No Standardization [For Quantities] Limited Accessibility [For Quantities] Inconsistent Material “Ticket” Submissions Delayed Utility Approvals KeyTake Away: Root Cause Analysis will focus on Daily Quantity documentation/reporting process and Payment Process. Why are Payment Requests rejected for disputed amounts? -Contractor quantities included in Payment Request do not match City’s verified quantities -Why? Verified daily quantities information is not easily accessible or consistently provided to confirm quantities are correct -Why? Documentation and delivery of daily quantities varies by City Inspector - Why? There currently is no standard documentation and reporting process for daily quantities
  • 12. ANALYZE HYPOTHESISTESTING RESULTS Possible X Root Cause Hypothesis HypothesisTest Results Payment Request Time Period Processing of Street Maintenance Task Order Payment Requests takes longer than it used to One-Sample Sign False Task Order Time Period Processing of Street Maintenance Task Order takes longer than it used to One-Sample Test False Rejects There are more payment request rejects than there used to be One-Sample Sign True Reject Types Number of rejects seems to be higher for certain reject reasons Mood’s Median True KeyTake Away: Hypothesis tests confirmed that rejected payments was a key area of focus.
  • 13. ONE SIGN HYPOTHESISTEST Hypothesis: Total payment processing time is taking longer than it use to. Key Take Away: There was no significant change in total payment processing time. However, since “payment processing time” was a “critical X” and identified by the Contractor’s as a significant issue, the team decided they needed to complete some further analysis. The team discovered the data retrieved from PRIMELink did not capture the time expended from the Contractor with-holding and not submitting Payment Requests in PRIMELink to avoid Payment Requests from being rejected. If the with-holding days were accounted for then the total payment processing time would have reflected as taking longer than it use to. With this, the team then focused on what was causing the Contractor to not to enter payment requests in PRIMELink .  Team looked at the current payment processing time and compared it to the historical target.  P-value less than 0.05, so team rejected the null hypothesis (Ho).  Result - Total payment processing isn’t taking longer than it use to, i.e. there is no significant change in total payment processing time. DATA SUMMARY
  • 14. ONE SIGN HYPOTHESISTEST Hypothesis: There are more payment request rejects than there use to be. Key Take Away: There are more payment request rejects than there use to be. There was a total of 146 rejects in FY 2013 and 227 rejects in FY 2014. Improvement focused on the rejected Payment Requests. More specifically, why they are being rejected and how we can reduce the number of rejects to increase the number of payments .  Team looked at the historical reject volume and compared it to the historical target.  P-value is greater than 0.05, so team failed to reject the null hypothesis (Ho).  Result - There are more payment request rejects than there use to be. DATA SUMMARY 0 5 10 15 20 25 30 NumberofRejects Run Chart
  • 15. MOOD’S MEDIAN TEST Hypothesis: Number of rejects seems to be higher for certain reject reasons Key Take Away: Mood’s Median test confirmed there is a significant difference in the number of rejects for certain reject reasons. Data reflects that Payment Request rejects are largely attributed to disputed amounts. Team focused on identifying root causes and solutions on how to reduce rejects for disputed amounts.  Team met with staff and Contractor to retrieve information on reasons why Payment Requests are rejected and compared it to the reject data retrieved from PRIMELink.  P-value less than 0.05, so team rejected the null hypothesis (Ho).  Result: There is a significant difference in the number of rejects for certain reject reasons. DATA SUMMARY
  • 16. IMPROVE IMPACT & EFFORT MATRIX Impact Effort Matrix Objective: Increase Overall Number of Invoices Processed On-Time Sponsor: TCI Project Delivery, Streets and Support Services Asst. Directors Stakeholder: Contractor High Impact Hard Easy Low Impact 1. Update PRIMELink workflows to optimize the sequencing of task order and payment request approval steps (i.e. adding the City as a Payment Request submitter and enabling the copy furnish feature to include Contractor on rejected items). 2. Facilitate the exchange of i-pads for laptop computers so Inspectors can document quantities in the field. 3. Implement a tolerance threshold for yield calculations to minimize quantities rejections for minor quantity threshold discrepancies. 4. Create an inspector quantity log in PRIMELink to allow inspector to log and track quantities and allow all authorized users (including the Contractor) to view quantities. 5. Document and implement a new quantity authorization process which will entail the documentation, acknowledgement and agreement of approved quantities. 6. Change invoicing process such that the City will create and initiate the Payment Request on behalf of the Contractor based on approved documented quantities. 1 2 34 5 6 Key Take Away: Leveraging the low/high impact quadrant, the team was able to prioritize the implementation of the solutions. Implementing “quick wins” first and gradually all of the rest the solutions as follows: 3, 1, 2, 4, 5 and 6.
  • 17. IMPROVE INNOVATIONTRANSFER OPPORTUNITIES PROCESS IMPROVEMENT [Innovation/Addition/Change/Removal] PROCESS BENEFITS IMPACTED ENTITY [Area/Department/Business Unit] Update task order PRIMELink workflow (i.e. enabled the copy furnish feature to include Contractor on rejected task orders) • Expedites action needed on rejected task orders • Reduces time needed to process task order so payment requests can be submitted • Contractor • Streets Engineering ProjectTeam Update payment request PRIMELink workflow (i.e. added the City as a Payment Request submitter) • Provides Contractor option to continue to invoice or permit the City to invoice on their behalf • Contractor • Fiscal Implemented 5% tolerance threshold for quantity yield calculations • Minimize and eliminate the unnecessary rejection of payment requests due to quantity discrepancies • Contractor • Inspector Established connectivity to PRIMELink for Inspectors in the field (i.e. facilitated the purchase and exchange of i-pads for laptops for all TCI Inspectors) • Inspectors able to remotely access PRIMElink and shared drives in the field • Allow for near real time data entry of daily quantities, reports and approvals • Promote documentation standardization (i.e. provide a centralized and easily accessible way to report) • Eliminated the need for inspectors to drive to and from a service center to upload data, thus allowing more time to be spent in the field • Inspector Implemented new daily quantity log documentation and reporting process • Improved transparency and communication • Report standardization • Reduce payment requests for incorrect quantities • Contractor • Inspector •Streets Engineering ProjectTeam Implemented City initiated payment request (invoicing) process • Ensures timely and consistent payments based on approved quantities • Contractor • Fiscal
  • 18. IMPROVE BEFORE & AFTER PAYMENT REQUEST REJECTS Key Take Away: Implemented solutions decreased total number of payments rejected for disputed quantity amounts by 17% achieving the project goal of decreasing the number of rejects for disputed quantity amounts by 10% or better. Fiscal Year Oct. 1 – Sept. 30 42% [ $15.1M] REJECTED 58% [ $21.6M] REJECTED Mean: 15.10 0 5 10 15 20 25 30 RunChart:Data Run Chart
  • 19. IMPROVE RISK MANAGEMENT Key Take Away: For each identified risk, leveraged training, visual management/procedural guides, system and/or procedural controls where needed to mitigate risks and proactively elevate issues.
  • 20. CONTROL MONITORING & RESPONSE PLAN MONITORING PLAN MEASURE INPUT/OUTPUT/ PROCESS TRIGGER MEASURES MEASURMENT METHOD CHECKING FREQUENCY WHO MEASURES Daily Quantities Timing Input Daily Quantity Log must be completed within 48 hours; No later than Tuesdays End of Day Time Stamp When Log is Completed Daily Inspector Supervisor Daily Quantities Discrepancies Output Zero quantity discrepancies prior to invoicing date (within two weeks of quantities being posted) Time Stamp When Log is Completed Daily Contractor Total Payment Requests Timing Process No greater than 15 days (Upper Control Limit) Time Stamp from When Payment Request is Submitted to When Payment Request is Paid Monthly Fiscal Accountant Total Number of Rejects Process No greater than 27 rejects (Upper Control Limit) Total Number of Rejects By Vendor for Disputed Amount Monthly Performance Management Team RESPONSE PLAN DAMAGE CONTROL PROCESS ADJUSTMENT EFFECTIVENESS ASSESSMENT CONTINOUS IMPROVEMENT Daily Quantity Discrepancies Report any quantity discrepancies to the Inspector to either correct the discrepancy or agree to not include in Invoice until discrepancy can be corrected Determine if discrepancy attributed to typo or missing documentation Project Team to verify quantities daily Project Team to verify once material tickets are received to what is reflected on daily quantity log, verify daily entry Corrected Daily Quantity Log Inspector to either (a) correct quantity on the appropriate daily quantity log (only if the log has not already been pulled for invoicing) or (b) create new daily log and reflect the corrected difference Project Team and Inspector to review Daily Quantity Summary Report to monitor quantity and dollar balances Project Team through review of balances can as necessary submit appropriate budget adjustment to elevate delays in invoicing; Inspector can know when quantities are not within or exceeding specifications. Unable to Process Payment Request Due to Insufficient Funds Report funding insufficiency to Project Manager so that a budget adjustment can be completed. Project Team will run the summary daily quantity report to monitor potential over runs. Project Team and Inspector working together to help proactively elevate the need for last minute adjustments at time of invoice rather complete adjustments sooner. Rejected Payment Requests Fiscal Accountant to work with Contractor and/or Project Team on correction needed. If quantity related, work with Inspector to correct accordingly. PRIMELink report regarding number of rejects and payment timing will be evaluated monthly. Team to review control charts to help trigger additional investigation of causes and as needed adjustments to control limits. Key Take Away: Team devised a monitoring and response plan to help sustain improvements and know how identify as well as handle issues should they arise.
  • 21. IMPROVE RACI MATRIX TASK FREQUENCY DUE DATE Responsibility Approver Consulted Informed The person responsible for producing the deliverable and/or completing the task. The person accountable for the deliverable. The person or persons that must be consulted before a decision can be made. The person or persons that must be informed of any decision that has been made. Complete Daily Quantity Usage Record Daily Within 48 hours; No Later than Tuesdays End of Day Inspector Inspector Supervisor Project Manager/Team Construction Management Manager Run Daily Quantity Usage Reports Weekly or As Needed Wednesdays End of Day Inspector Supervisor Construction Management Manager Project Manager/Team Project Delivery Assistant Director Review Daily Quantity Usage Reports Weekly or As Needed Wednesdays End of Day Project Manager/Team Streets Engineering Manager Inspector Supervisor Streets Assistant Director Validate Daily Quantities Weekly or As Needed Wednesdays End of Day Contractor Contractor Owner Project Manager/Team Streets Assistant Director Communicate Daily Quantity Discrepancies As Needed Within 2 Weeks of Quantities being Posted Contractor Contractor Owner Project Manager/Team Streets Assistant Director Complete Daily Quantity Discrepancy Revisions As Needed Within 2 Weeks of Quantities being Posted or PM Team Notification Inspector Inspector Supervisor Project Manager/Team Contractor Consolidation of Daily Quantities (for City Issued Payment Requests) Monthly or As Needed First Wednesdays of Month or within 48 Hours of Receiving PM Team Notification Fiscal Accountant Capital Fiscal Manager Project Manager/Team Contractor Consolidation of Daily Quantities (for Vendor Payment Requests) Monthly or As Needed Contractor Contractor Owner Project Manager/Team Streets Assistant Director Creation & Submission of Payment Requests Monthly or As Needed First Fridays of Month or within 48 Hours of Receiving PM Team Notification Fiscal Accountant Capital Fiscal Manager Project Manager/Team Contractor Notification of Overruns Daily As Needed Project Manager/Team Streets Engineering Manager Inspector Supervisor Streets Assistant Director Creation & Submission Task Orders (for Overruns or Project Close-Out) Daily As Needed Project Manager/Team Streets Engineering Manager Inspector Supervisor Streets Assistant Director Updating Major Changes to Standard Operating Procedures Document As Needed As Needed Performance Management Team Inspector Supervisor Project Manager/Team Project Delivery & Steets Assistant Director
  • 22. CONTROL CONTROL CHART Key Take Away: Team is continuing to work on causes of variation and control limits. The control charts will be a key part of TCI’s on-going monitoring of the process in identifying ways to improve and address issues. As a result, of the immediate success of the 6-month pilot and overwhelming positive response from Contractors following the pilot, TCI has begun rolling-out the new Daily Quantity Log and Payment Request process for all Street Maintenance Improvement construction contracts and eventually all TCI managed construction contracts. PAYMENT REQUESTS Avg. Process Timing Trigger = 15 Days or Greater [Upper Control Limit = 16] 16.49 Mean CL: 12.875 9.26 0 5 10 15 20 25 Individuals:Data Individuals Control Chart Data UCL CL (Mean) LCL 26.76 15.1025641 3.44 0 5 10 15 20 25 30 C:Data C (Count) Control Chart Rejects Data UCL CL (Mean) LCL REJECTS No. Rejects Trigger = 20 Rejects or Greater [Upper Control Limit = 27 Rejects]
  • 23. NEXT STEPS Black Belt Project Storyboard Task Order & Invoicing Process Improvement EXTEND SUSTAIN COLLABORATE IMPROVE Roll out daily inspection quantity and invoicing process for all other capital construction contracts. IMPROVEMENT Coordinate with local utilities to have them begin utilizing new daily inspection quantity and invoicing process for utility work on City projects. Continue to retrieve feedback from process owner, staff and contractors. Follow through and review monitor and control plans. Continue quarterly meeting with process owners and users to access process progress, identify ways to improve and address any associated issues.
  • 24. LESSONS LEARNED Lessons Learned Lean Six Sigma methodology is not just applicable to manufacturing operations it can be applied in Municipal business functions and services. Lean Six Sigma methodology has provided a roadmap to not only implement but sustain improvements . Data does matter – performance and its established triggers are essential in maintaining efficient and effective delivery of services/deliverables. Lean Six Sigma Methodology Having a clear and consistent communication plan is key in sustaining success and ensuring issues are addressed accordingly. Communication helps fosters better collaboration and a greater awareness of the team’s overall goal and responsibilities. Communication Lack of standardized, documented and agreed upon policies/processes leads to variability which results in inconsistency, additional work and potentially costly processing delays. Creating uniform policies and procedures helps reduce confusion and improves communication for City staff and among Contractors. Information regarding policies and procedures should be accessible and easy to understand both for Contractors and City staff. Standardized Processes With out the involvement through the project and buy-in of the process owner of the improved process the realized improvements can not be sustained. Simply, “if its not important to the boss its not important to staff.” Ownership
  • 25. APPENDIX Lean Six Sigma Black Belt Project Storyboard Task Order & Invoicing Process Timing
  • 26. TASKORDER&INVOICINGTIMING STAKEHOLDER ANALYSIS Key Take Away: There was no resistance to the process improvement and all appropriate key stakeholders were included as part of the team.
  • 27. TASKORDER&INVOICETIMING AS-IS PROCESS MAPS Key Take Away: Understanding the Task Order and associated Payment Process was instrumental in identifying areas of focus and has provided City staff a renewed and visible perspective of the entire process.
  • 28. TASKORDER&INVOICINGTIMING FIVE (5)WHY’S Why are Payment Requests rejected? Why ?: Contractor quantities included in Payment Request do not match City’s verified quantities. Why ?: Verified daily quantities information is not easily accessible or consistently provided to confirm quantities are correct. Why?: Documentation and delivery of daily quantities information varies by City Inspector. Why?: There currently is no standard documentation and reporting process for daily quantities. Key Take Away: Payment Requests rejected for disputed quantities is attributable to the lack of a defined process and impacts the Contractor, City Project Team and City Inspector.
  • 29. Expedite Project Delivery and Completion of Infrastructure Projects City-Wide City Staff Contractor City Processes Reporting & Tools MATCHING X &Y MEASURES Key Take Away: X’s that impact Y (Expedited project delivery and completion of Infrastructure Projects city-wide) are as follows: City Staff (includes Project Team and Inspector), Contractor, City’s Processes and reporting/tools. X1 X2 X3 X4 Y City Staff Communication Report Duplication Contractor Communication Consistency City Processes Standardization Documentation Reporting & Tools Equipment Transparency Standardization Accessibility Expedite Project Delivery and Completion of Infrastructure Projects City- Wide
  • 30. TASKORDER&INVOICINGTIMING 8 WASTES CHECK SHEET Process Area: Daily Quantity Process Waste Definition Level Description of Issues D Defects Information, products and services that are incomplete or inaccurate High Inconsistent documentation of daily project quantities makes it difficult to research, verify and approve quantities; instances of incorrect quantities more likely O Overproduction Making more of something - making it earlier or faster- than it's needed High Redundant and non-transparent documentation (i.e. quantities documented in emails and various manual logs by Contractor, Project Team and Inspectors) W Waiting Waiting for information, equipment, materials, parts or people Medium Daily quantities information is not centralized and easily assessable (i.e. project team and vendor have to await for information to be sent by Inspector ) N Non-Utilized Talent Not properly utilizing people's experience, skills, knowledge or creativity Medium Inspectors are unable to leverage PRIMELink in the field consistently which forces inspectors to track and communicate manually requiring additional time as a opposed to documenting information in the system for all to access T Transportation Unnecessary movement of materials, information or equipment High Inspectors not able to document daily quantities in field so Inspectors manually track and transfer information to various logs and emails the same information I Inventory Accumulation of parts, information, applications, etc. beyond what is required by the customer High Since there is no daily log in PRIMELink Inspectors manually track quantities in the field and for most they wait until the end of the week or several days so they have to update manual logs and provide updates once M Motion Any movement by people that is not of value to the customer Medium Project team, vendor and inspector have to search through manual logs and emails to verify quantities to approve or reject payment requests E Extra- Processing Any steps that do not add value in the eyes of the customer Medium Project team, vendor and inspector each track quantities on their own separate logs same information
  • 31. TASKORDER&INVOICINGTIMING COMMUNICATION PLAN Stakeholder Group Objectives/Actions Desired Message Delivery Method Timing Executives (Project Champions) Inform of project findings, create buy-in and ownership Results of analysis and hypothesis tests; solutions selected Share at Regular Scheduled Executive Meeting Within1 Week Construction Management & Street Engineering Supervisors Inform of project findings, install confidence in team and process changes Results of analysis and hypothesis tests; solutions selected Schedule Meeting Within 2 Weeks Construction Management Inspectors Inform of project findings, create buy-in and ownership, participate in pilot & roll- out Pilot results, training and implementation plan Schedule Meeting Within 3 Weeks Street Engineering Project Manager & Project Team Members Inform of project findings, create buy-in and ownership, participate in pilot & roll- out Pilot results, training and implementation plan Schedule Meeting Within 3 Weeks Fiscal Purchase new laptops , inform of project findings, create buy-in and ownership, participate in pilot & roll-out Purchasing new hardware, execution dates, training and implementation plan Email After Executive and Manager Approval Vendors Inform of project findings, create buy-in and ownership, participate in pilot & roll- out Pilot results, training and implementation plan Schedule Meeting Within 3 Weeks Key Take Away: Adhering to Communication Plan was instrumental in making sure the team and its project champions were informed on what was happening with the project and anticipated due dates.
  • 32. TASKORDER&INVOICINGTIMING IMPLEMENTATION PLAN Plan Do Check Act Action Responsible Due Date Plan Complete Test Task Order and Payment Request Work Flow Changes PRIMELink Manager 07/12/2014 Procure (32) Windows-based Laptops ProjectTeam Leader, Fiscal, Information Technology 11/14/2014 Design Inspector Daily Quantity Log in PRIMELink PRIMELink Manager 12/15/2014 Design Daily Quantity Log Detailed & Summary PRIMELink Reports PRIMELink Manager 12/15/2014 Design Payment Request Detailed & Summary PRIMELink Reports PRIMELink Manager 12/15/2014 Facilitate Exchange I-pads for Laptops ProjectTeam Leader, Fiscal, Construction Management 04/02/2015 Do Create Inspector Daily Quantity Log in PRIMELink PRIMELink Manager 01/15/2015 Create Daily Quantity Log Detailed & Summary Reports in PRIMELink PRIMELink Manager 02/15/2015 Create Payment Request Detailed and Summary Reports in PRIMELink PRIMELink Manager 02/15/2015 Document Procedures,Visual Management Guide and Control Plan for Inspector Daily Quantity Log and Payment Process ProjectTeam Leader 04/15/2015 Train PRIMELink Helpdesk, Inspectors, ProjectTeam, Fiscal & Contractor ProjectTeam Leader, PRIMELink Manager 05/08/2015 Check Deploy Pilot [Test Process & New Changes in PRIMELink with (1) [Willing and Able Contractor] PRIMELink Manager 06/26/2015 Monitor Inspector Daily Quantity Log Completion, Payment Process Timing and RejectVolume for Team ProjectTeam Leader 07/26/2015 Act Made Adjustments to Daily Quantity Log and Payment Process Based on Pilot ProjectTeam Leader, Construction Management Inspectors, Street Engineering ProjectTeam, Fiscal 08/03/2015 Roll Out New Daily Quantity Log and Payment Process for All Other Street Maintenance Construction Contracts ProjectTeam Leader, Construction Management Inspectors, Street Engineering ProjectTeam, Fiscal 09/01/2015 Key Take Away: Implementation Plan was used to organize key tasks and provide the team an overview of what is to be completed and the team’s role in tasks to be completed.
  • 33. TASKORDER&INVOICINGTIMING CONTROL CHART 5 1 2 2 2 2 5 5 5 12.88 9.26 16.49 9.00 10.00 11.00 12.00 13.00 14.00 15.00 16.00 17.00 18.00 19.00 20.00 21.00 22.00Individuals:Data 1.36 0.00 4.44 -1.00 0.00 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 MR:Data Key Take Away: The I-MR-R chart turned out to be the visual tool to review payment processing time. Team has both a cumulative monthly and daily chart to illustrate the process’s progress and any variation. The Upper Control Limit and Response Plan trigger is 16 days. I-MR Chart | Monthly Payment ProcessingTime