Vision and Scope Document

10/12/2007
Ho Chi Minh National University – International University
Instructor: Phan Viet Hoang



                   Date              October 10th , 2007
                   Version           1.0
                   Status            Baseline
                   Author            Team TiHonMumMim(Group 6)
                   Reviewer          Team TiHonMumMim(Group 6)
                   Documenter        Nguyen Duc Quan




                       Team member              Signature

                   Nguyen Duc Quan

                   Le Vu Hoang

                   Tran Minh Phung

                   Phan Duy Tan

                   Huynh Da Thuc
Final Document



                                                             Table of Contents
Introduction ..................................................................................................................................................... 13
Development team & OURS project ................................................................................................................ 13
Problem Statement .......................................................................................................................................... 15
   Project background ...................................................................................................................................... 15
   Key users ...................................................................................................................................................... 15
   Stakeholders ................................................................................................................................................ 16
   Assumptions & Constraints of Online University Registration System ......................................................... 17
Vision of Solution ............................................................................................................................................. 17
   Vision statement .......................................................................................................................................... 17
   Scope ........................................................................................................................................................... 18
   List of features ............................................................................................................................................. 18
   List of features will not be developed .......................................................................................................... 18
Business Plan & SRS Document ....................................................................................................................... 20
STATEMENT OF WORK ..................................................................................................................................... 21
RESOURCE LIST ................................................................................................................................................ 24
   Human ......................................................................................................................................................... 24
   Software ...................................................................................................................................................... 24
   Hardware ..................................................................................................................................................... 24
ESTIMATION .................................................................................................................................................... 25
   Huynh Da Thuc estimation ........................................................................................................................... 25
   Phan Duy Tan estimation ............................................................................................................................. 28
   Tran Minh Phung estimation ....................................................................................................................... 31
   Nguyen Duc Quan estimation ...................................................................................................................... 34
   Le Vu Hoang estimation ............................................................................................................................... 37
   Estimation Summary .................................................................................................................................... 39
SCHEDULE ........................................................................................................................................................ 43
   Task list ........................................................................................................................................................ 43

                                                                                  2
Final Document

   Gantt chart (reference) ................................................................................................................................ 45
RISK PLAN ........................................................................................................................................................ 46
DISCUSSION SUMMARY ................................................................................................................................... 48
   Project background ...................................................................................................................................... 48
       Purpose of project ................................................................................................................................... 48
       Scope of project ....................................................................................................................................... 49
   Perspectives ................................................................................................................................................. 51
       Who will use the system? ........................................................................................................................ 51
       Who can provide needs about the system? ............................................................................................. 51
   Project objectives ........................................................................................................................................ 52
       Know business rules ................................................................................................................................. 52
       System information and/or diagrams ...................................................................................................... 52
       Assumptions and dependencies .............................................................................................................. 54
       Design and implementation constraint .................................................................................................... 54
   Risks ............................................................................................................................................................. 54
   Known future enhancements ...................................................................................................................... 55
   References ................................................................................................................................................... 55
   Open, unresolved issues ............................................................................................................................. 55
SOFTWARE REQUIREMENT SPECIFICATION ..................................................................................................... 56
   USE CASE SPECIFICATION ............................................................................................................................. 56
       Log in and Log out .................................................................................................................................... 56
       Manage Department Information ............................................................................................................ 58
       Manage Lecturer Information .................................................................................................................. 60
       Manage Student Information................................................................................................................... 63
       Manage Course Offering .......................................................................................................................... 66
       Manage Financial Activities ...................................................................................................................... 69
       View Academic History ............................................................................................................................ 71
       Register Course ........................................................................................................................................ 72
       Manage Course Catalogue ....................................................................................................................... 74
       Manage User Account .............................................................................................................................. 77
                                                                                   3
Final Document

       Appendix .................................................................................................................................................. 80
   FUNCTIONAL REQUIREMENT ....................................................................................................................... 82
   NON-FUNCTIONAL REQUIREMENT .............................................................................................................. 86
       Performance: ........................................................................................................................................... 86
       Reliability: ................................................................................................................................................ 86
       Availability: .............................................................................................................................................. 86
       Efficiency:................................................................................................................................................. 86
       Supportability: ......................................................................................................................................... 86
       Integrity: .................................................................................................................................................. 86
       Portability: ............................................................................................................................................... 86
       Flexibility: ................................................................................................................................................. 87
INSPECTION REPORT ........................................................................................................................................ 88
GLOSSARY ........................................................................................................................................................ 89
   Introduction ................................................................................................................................................. 89
   Definitions.................................................................................................................................................... 89
       OURS ........................................................................................................................................................ 89
       Academic staff ......................................................................................................................................... 89
       Finance staff ............................................................................................................................................. 89
       Department ............................................................................................................................................. 89
       Faculty...................................................................................................................................................... 89
       Curriculum ............................................................................................................................................... 89
       Subject ..................................................................................................................................................... 89
       Course Offering ........................................................................................................................................ 90
       Prerequisite.............................................................................................................................................. 90
       Course Catalog ......................................................................................................................................... 90
       Lecturer .................................................................................................................................................... 90
       Student .................................................................................................................................................... 90
       Student priority ........................................................................................................................................ 90
       Discount rate............................................................................................................................................ 90
       Grade ....................................................................................................................................................... 90
                                                                                  4
Final Document

        Schedule .................................................................................................................................................. 90
        Tuition fee ................................................................................................................................................ 90
        Credit ....................................................................................................................................................... 90
        Academic duration ................................................................................................................................... 90
        Academic year.......................................................................................................................................... 91
Testing Plan & Test case Document ................................................................................................................. 93
A-      Test Plan .................................................................................................................................................. 94
Introduction ..................................................................................................................................................... 94
     Purpose ........................................................................................................................................................ 94
     Scope ........................................................................................................................................................... 94
     References ................................................................................................................................................... 94
Review requirement and Design ...................................................................................................................... 94
     Review system architecture ......................................................................................................................... 95
Features to be tested ....................................................................................................................................... 97
Features not to be tested ................................................................................................................................ 98
Approach ......................................................................................................................................................... 99
     Kind of test ................................................................................................................................................... 99
        Data and Database Integrity Testing ........................................................................................................ 99
        System testing.......................................................................................................................................... 99
        Performance Testing .............................................................................................................................. 100
        Load Testing ........................................................................................................................................... 100
        Stress Testing ......................................................................................................................................... 100
        Volume Testing ...................................................................................................................................... 100
     Test Strategy .............................................................................................................................................. 100
        Checklist of unit test .............................................................................................................................. 100
        Unit testing ............................................................................................................................................ 101
        Smoke test ............................................................................................................................................. 101
        Test Automation .................................................................................................................................... 101
        Data and Database Integrity Testing ...................................................................................................... 102
        System Testing ....................................................................................................................................... 102
                                                                                    5
Final Document

        Performance Testing .............................................................................................................................. 103
        Load Testing ........................................................................................................................................... 104
        Stress Testing ......................................................................................................................................... 105
        Volume Testing ...................................................................................................................................... 106
Suspension criteria and resumption requirements ........................................................................................ 107
     Suspension criteria..................................................................................................................................... 107
     Resumption requirements ......................................................................................................................... 107
Environmental Needs .................................................................................................................................... 108
     Tools .......................................................................................................................................................... 108
     Software .................................................................................................................................................... 108
     Hardware ................................................................................................................................................... 109
Schedule ........................................................................................................................................................ 109
Acceptance criteria ........................................................................................................................................ 110
Resources ...................................................................................................................................................... 110
B-      Test Case ................................................................................................................................................ 113
Unit testing .................................................................................................................................................... 113
Test Cases of Log in and Log out Use Case ..................................................................................................... 115
     User logs in successfully with valid username and password .................................................................... 115
     Fail to login the system when providing invalid username ........................................................................ 115
     Fail to login the system when providing username or password containing special character(s).............. 115
     Fail to login the system when providing valid username and invalid password ......................................... 116
     Fail to login the system when providing empty username ........................................................................ 116
     Fail to login the system when providing valid username and empty password ......................................... 117
     User account is locked after failing to log in 3 times .................................................................................. 117
     User logs in the system using an account is being used by another user................................................... 118
     User logs in the system using an account is being locked .......................................................................... 118
     Change password successfully ................................................................................................................... 118
     Fail to change password when old or new or confirmed password is empty ............................................ 119
     Fail to change password when old password is incorrect .......................................................................... 119
     Recover the password successfully ............................................................................................................ 120
                                                                                    6
Final Document

   Fail to reset password when inputting wrong answer for the security question ....................................... 120
   Fail to reset password when inputting answer containing special character(s) for the security question . 121
   Fail to reset password when inputting empty answer for the security question ....................................... 122
Test Cases of Manage Department Information Use case ............................................................................. 122
   Add a department with valid information successfully .............................................................................. 122
   Fail to add a department with name that already exists in the system ..................................................... 123
   Fail to add a department when one or some or all fields are empty ......................................................... 123
   Fail to add a department when inputting special character(s) to one or some or all fields ....................... 124
   Update a department with valid information successfully ........................................................................ 125
   Fail to update a department with name that already exists in the system ................................................ 125
   Fail to update a department when one or some or all fields are empty .................................................... 126
   Fail to update a department when inputting special character(s) to one or some or all fields .................. 127
   Update cancel ............................................................................................................................................ 127
   Delete a department .................................................................................................................................. 128
   Delete cancel ............................................................................................................................................. 128
Test Cases of Manage Lecturer Information use case.................................................................................... 129
   Add a lecturer with valid information successfully .................................................................................... 129
   Fail to add a department when one or some or all fields are empty ......................................................... 129
   Fail to add a lecturer when inputting special character(s) to one or some or all fields.............................. 130
   Look for a lecturer...................................................................................................................................... 131
   Update a lecturer with valid information successfully ............................................................................... 131
   Fail to update a lecturer when one or some or all fields are empty .......................................................... 133
   Fail to update a lecturer information when inputting special character(s) to one or some or all fields .... 133
   Update cancel ............................................................................................................................................ 134
   Delete a lecturer ........................................................................................................................................ 135
   Delete cancel ............................................................................................................................................. 135
Test Cases of Manage Student Information Use Case ................................................................................... 136
   Add a student with valid information successfully..................................................................................... 136
   Fail to add a student when one or some or all fields are empty ................................................................ 136
   Fail to add a student when inputting special character(s) to one or some or all fields .............................. 137
                                                                               7
Final Document

   Search student by student ID or/and by student name ............................................................................. 138
   Fail to search student by student ID or/and by student name when providing invalid student ID or/and
   student name ............................................................................................................................................. 138
   Fail to search student by student ID or/and by student name when providing empty student ID or/and
   student name ............................................................................................................................................. 139
   Search student by faculty and academic duration ..................................................................................... 139
   Search student by academic year, semester, and course .......................................................................... 141
   Update a student with valid information successfully ............................................................................... 141
   Fail to update a student when one or some or all fields are empty ........................................................... 142
   Fail to update a student when inputting special character(s) to one or some or all fields ........................ 142
   Update is canceled ..................................................................................................................................... 143
   Delete a student ........................................................................................................................................ 144
   Delete is canceled ...................................................................................................................................... 144
Test Cases of Manage Course Offering Use Case ........................................................................................... 145
   Create list of courses offering successfully ................................................................................................ 145
   Update the list of course offering .............................................................................................................. 145
   Cancel during the Create list of course offering operation ........................................................................ 146
   Cancel during the Update list of course offering operation ....................................................................... 147
   Fail to create an empty list of course offering ........................................................................................... 147
   Update list of course offering while there’s no list of course offering for specific faculty ......................... 148
Test Cases of Manage Financial Activities Use Case ...................................................................................... 150
   View tuition fee by student ID or/and by student name............................................................................ 150
   Fail to view tuition fee by student ID or/and by student name when providing invalid student ID or/and
   student name ............................................................................................................................................. 150
   Fail to view tuition fee by student ID or/and by student name when providing empty student ID or/and
   student name ............................................................................................................................................. 151
   View tuition fee by faculty or/and by academic duration .......................................................................... 151
   View tuition fee by academic year, semester, and course ......................................................................... 152
   Update tuition fee status of a student ....................................................................................................... 152
Test Cases of View Academic History Use Case ............................................................................................. 153
   View academic history successfully ........................................................................................................... 153
                                                                8
Final Document

   View all course have taken history............................................................................................................. 153
   View by specific year and semester. .......................................................................................................... 154
   View by passed and failed status. .............................................................................................................. 154
Test Cases of Register Course Use Case ......................................................................................................... 155
   Fail to register more than 30 credits .......................................................................................................... 155
   Fail to register less than 15 credits ............................................................................................................ 155
   Register for courses successfully................................................................................................................ 156
   Update the existing schedule successfully ................................................................................................. 157
Test Cases of Manage Course Catalogue Use Case ........................................................................................ 157
   Add new course to course catalogue successfully ..................................................................................... 157
   Fail to add a course when one or some or all fields are empty .................................................................. 158
   Fail to add a course when inputting special character(s) ........................................................................... 159
   Search for course by ID or Name ............................................................................................................... 159
   Fail to search for course by ID or Name when inputting invalid ID and/or Name ...................................... 160
   Fail to search for course by ID or Name when inputting empty ID and/or empty Name ........................... 160
   Update course with valid information successfully.................................................................................... 161
   Fail to update a course when one or some or all fields are empty ............................................................ 161
   Fail to update a course when inputting special character(s) ...................................................................... 162
   Update operation is canceled .................................................................................................................... 163
   Delete a course .......................................................................................................................................... 163
   Delete operation is canceled ..................................................................................................................... 163
Test Cases of Manage User Account Use Case ............................................................................................... 164
   Create a new user account successfully ..................................................................................................... 164
   Fail to create a new user account when the username that user has provided existing in the system
   already ....................................................................................................................................................... 164
   Fail to create a new user account when inputting empty username ......................................................... 165
   Fail to create a new user account when the inputs containing special character(s) .................................. 166
   Search for account by username ............................................................................................................... 166
   Fail to search for account by empty username .......................................................................................... 167
   Fail to search for account by username that does not exist in the system ................................................ 167
                                                                                 9
Final Document

     Fail to search for account by username containing special characters(s) .................................................. 167
     Update an account ..................................................................................................................................... 168
     Update operation is canceled .................................................................................................................... 168
     Delete an account ...................................................................................................................................... 169
     Delete operation is canceled ..................................................................................................................... 169
Test Cases of Non-functional requirement testing ........................................................................................ 170
     Switch from Vietnamese to English ........................................................................................................... 170
     Switch from English to Vietnamese ........................................................................................................... 170
     Load testing with 15 requests at the same time ........................................................................................ 170
     Load testing with 25 requests at the same time ........................................................................................ 171
C-      Appendix ................................................................................................................................................ 171
D-      Inspection Checklist ............................................................................................................................... 173
The following checklist items apply to the test plan. ..................................................................................... 173
The following checklist items apply to the test cases: ................................................................................... 173
Testing demo ................................................................................................................................................. 176
Unit testing .................................................................................................................................................... 177
Functional requirement testing ..................................................................................................................... 177
Test Cases of Log in and Log out Use Case ..................................................................................................... 177
     User logs in successfully with valid username and password .................................................................... 177
     Fail to login the system when providing invalid username ........................................................................ 178
     Fail to login the system when providing username or password containing special character(s).............. 178
     Fail to login the system when providing valid username and invalid password ......................................... 179
     Fail to login the system when providing empty username ........................................................................ 179
     Fail to login the system when providing valid username and empty password ......................................... 179
     User account is locked after failing to log in 3 times .................................................................................. 180
     User logs in the system using an account is being used by another user................................................... 180
     User logs in the system using an account is being locked .......................................................................... 181
     Change password successfully ................................................................................................................... 181
     Fail to change password when old or new or confirmed password is empty ............................................ 182
     Fail to change password when old password is incorrect .......................................................................... 182
                                                                                10
Final Document

   Recover the password successfully ............................................................................................................ 183
   Fail to reset password when inputting wrong answer for the security question ....................................... 183
   Fail to reset password when inputting answer containing special character(s) for security question ....... 184
   Fail to reset password when inputting empty answer for the security question ....................................... 184
Test Cases of Manage Course Offering Use Case ........................................................................................... 185
   Create list of courses offering successfully ................................................................................................ 185
   Update the list of course offering .............................................................................................................. 186
   Cancel during the Create list of course offering operation ........................................................................ 186
   Cancel during the Update list of course offering operation ....................................................................... 187
   Fail to create an empty list of course offering ........................................................................................... 188
   Update list of course offering while there’s no list of course offering for specific faculty ......................... 188
Test Cases of Manage Department Information Use case ............................................................................. 189
   Add a department with valid information successfully .............................................................................. 189
   Fail to add a department with name that already exists in the system ..................................................... 189
   Fail to add a department when one or some or all fields are empty ......................................................... 190
   Fail to add a department when inputting special character(s) to one or some or all fields ....................... 191
   Update a department with valid information successfully ........................................................................ 191
   Fail to update a department with name that already exists in the system ................................................ 192
   Fail to update a department when one or some or all fields are empty .................................................... 193
   Fail to update a department when inputting special character(s) to one or some or all fields .................. 193
   Update cancel ............................................................................................................................................ 194
   Delete a department .................................................................................................................................. 194
   Delete cancel ............................................................................................................................................. 195
Test Cases of Register Course Use Case ......................................................................................................... 195
   Fail to register more than 30 credits .......................................................................................................... 195
   Fail to register less than 15 credits ............................................................................................................ 196
   Register for courses successfully................................................................................................................ 196
   Update the existing schedule successfully ................................................................................................. 198
Non-functional requirement testing .............................................................................................................. 198
Test Cases of Non-functional requirement testing ........................................................................................ 198
                                                                              11
Final Document

   Switch from Vietnamese to English ........................................................................................................... 198
   Switch from English to Vietnamese ........................................................................................................... 199
   Load testing with 15 requests at the same time ........................................................................................ 199
   Load testing with 25 requests at the same time ........................................................................................ 199
System architecture introduction .................................................................................................................. 200
How to download & install tools .................................................................................................................... 201
How to install OURS ....................................................................................................................................... 205
How to run OURS ........................................................................................................................................... 207
How to setup and run tests of OURS ............................................................................................................. 208
How to use OURS ........................................................................................................................................... 209
Login and Logout ........................................................................................................................................... 209
Register Course .............................................................................................................................................. 209
View Academic History .................................................................................................................................. 209
Manage Department Information ................................................................................................................. 210
Manage Student Information ........................................................................................................................ 210
Manage Course Offering ................................................................................................................................ 211
Manage Lecturer Information ........................................................................................................................ 212
Manage Financial Activities ........................................................................................................................... 213
Manage Course Catalogue ............................................................................................................................. 214
Manage User Account ................................................................................................................................... 214




                                                                               12
Final Document




Introduction
  This is the Vision and Scope document of OURS project. Like any other Vision and Scope
  document, this document will cover the problem and vision statement including project
  background, list of users, stakeholders, candidate risks, assumptions & constraints, and project
  scope. In addition, the document will also cover the part of development team introduction.



Development team & OURS project
  TiHonMumMim is a small software development team set up in 2007 by 5 students of
  International University. The structure of the team includes 3 software engineers, 1 system &
  networking engineer, and 1 team leader.

  Our business goal is to be a leading company in IT. And our slogan is “Computing, consulting,
  and programming professionally” (CC&PP).

  For more information about our team:
  Email: TiHonMumMim@yahoo.com
  Blog: http://360.yahoo.com/TiHonMumMim




                                               13
Final Document


   We are assigned to build Online University Registration System (OURS). The internal
   development team structure and roles on OURS project:

                                          OURS project



                                          Team leader




                  Documenter     Tester                 Coder      Integrator




                      Business      System           System          UI
                      Analyst       Analyst          Designer     Designer



   TEAM LEADER : Responsible for all project management.
   DOCUMENTER : Responsible for documentation from other members’ according to the RUP
   document standard.
   BUSINESS ANALYST : Capture and analyze user requirements.
   SYSTEM ANALYST : Analyze system requirements.
   SYSTEM DESIGNER : Design the internal structure and operations of system.
   UI DESIGNER : Design user interface for the system.
   CODER: Responsible for implementing the system.
   INTEGRATOR : Integrate the system components.
   TESTER : Responsible for testing activities.



  Team member           ID                  Email                        Main roles
Tran Minh Phung     090401096     toyohiko1507@yahoo.com        Tester, Integrator
Le Vu Hoang         090401019    smallwildcat_86@yahoo.com      System Designer, Coder
Huynh Da Thuc       090401121        runnfire@yahoo.com         Tester, UI Designer
Phan Duy Tan        090401044      kingduytan@yahoo.com         System Analyst, Coder
Nguyen Duc Quan     090401038       duc.quan@yahoo.com          Team leader, Business
                                                                Analyst, Documenter



                                                14
Final Document




Problem Statement

     Project background
        There is a widespread agreement that the policy in course registration is very complicated,
costly, take-time, and inconvenient to both students and university. This is due the fact that at the
beginning of each semester, the university has to pause or delay some activities to spend time for
course registration of students. Some staffs have to prepare for offering courses list (including
selecting courses and inviting lecturers …), print it out, and deliver the registration form to each
student. After around one week, all students’ registration form will be returned. And the staffs
have to input students’ registration information to Excel files. They also have to check manually
whether the registration form of each student is legal or not basing on some conditions such as
prerequisite course, maximum and minimum number of credits allowed to register … If there is
anything wrong or students want to add or drop the courses, everything in the above process has
to be restarted. And sometimes some papers are lost when documents are moved from one place
to another place; both students and university have to spend time for retrieving necessary
information and approve it. However, it is impossible to do that in some cases.
        In addition, calculating tuition fee for students, managing students’ academic history… are
also thorny issues. Mistakes can occur anytime when financial office‘s staffs use calculator or
Microsoft excel to calculate tuition fee.
Students’ transcript management is also another issue. When students want to have transcript to
see their academic history, they have to wait at least two weeks to receive it from academic affair.
        Those are some typical examples for the inconvenience and complication of the current
course registration policy. They lead the university to the decision of building Online Course
Registration System to improve effectiveness, reduce time and cost in course registration process.




   Key users
   STUDENT: use the system to register for course or view academic history.
   ADMINISTRATOR: Manage the system after it is built and the authentication mechanism of the
   system.

                                                 15
Final Document


ACADEMIC AFFAIR STAFF: use the system to manage department and faculty, lecturer, student,
course catalogue, list of course offering information.
FINANCIAL OFFICE STAFF: use the system to monitor financial activities related to course
registration.


Stakeholders
STUDENT: use the system to register for course or view academic history.
ADMINISTRATOR : Manage the system after it is built.
ACADEMIC AFFAIR STAFF: use the system to manage school, lecturer-professor, and
ADMINISTRATOR : Manage the system after it is built and the authentication mechanism of the
system.
LECTURER: They could give ideas or comment on the solution for the system’s development
and improvement.
FINANCIAL OFFICE MANAGER : They also manage the investment of university for the system
development.
FINANCIAL OFFICE STAFF: use the system to monitor financial activities related to course
registration.
DEVELOPMENT TEAM : include all software engineers, business analysts, system analysts, system
designers, implementers, testers, QA, and project manager… They are tasked to build the
system.



     List of Risks

          All team members need preparation time for midterm, final exam, and other
          subjects.
          Phung, Thuc, and Hoang take pre-thesis course.
          Lack of experiences in software project management, especially in testing,
          verification, validation, risks management and changes management exists in the
          Team.
          No substitution if any team member cannot continue to contribute to the project.
          Applying the project again from the beginning could take development team more
          time.
          Development time is limited in 2 months only. Therefore the pressure is really high.

                                           16
Final Document


              Development team cannot deliver the components when reviewed. Development
              team could deliver components of unacceptably low quality, and time must be
              added to improve quality.
              Developing extra functionalities that are not required will extends the schedule.
              Low motivation and moral reduce productivity.
              Team member needs extra time to learn unfamiliar tools or techniques.
              Conflicts among team members’ ideas results in poor performances, more meeting,
              and extra rework.
              People’s assignments do not match their strengths.
              Components developed separately cannot be integrated easily, requiring redesign
              and rework.
              Detail reporting could take more development time.




Assumptions & Constraints of Online University Registration System
           The system will be applied for universities using credit system like International
           University.
           The registration information of students is processed by academic affair. And only
           academic affair has right to manage and process the registration information.
           Development team will use J2EE architecture to develop system.
           Policy for tuition fee payment is using cash and it is managed by financial office.
           Development team must have at least one 2-hour meeting per week.
           Development time 2 months and 10 days (from 01/10/2007 to 20/12/2008)
           Development team must produce the first build before review 3 (05/12/2007).
           Each team member must work at least 15 hours per week.




Vision of Solution


     Vision statement
As the head of information systems for International University team are tasked with developing a
new Online Course Registration System. The new system will allow students to access the system
during registration time to register for courses, add or drop the registered courses, check tuition
                                                17
Final Document


fee, and review their academic history. Academic affair can use the system as a mean to manage
information of schools, classes, professors, students and offering courses. Financial office will use
the system to monitor financial activities. The system provides a better solution and policy for
course registration in International University. It reduces much time, cost, and resources required
in processing registration information of students.


     Scope
To be noticed on the scope of the system that this system is an Online University Registration
System. It is not a university management system which is much larger than the system we try to
build. It is only a part of the university management system. Therefore, we have to pay attention
on building applications supporting students to do registration, academic affairs to manage
information related to students’ courses registration, and financial office to mange financial
activities.

     List of features
           User login and log out
           View Academic History
           Register for course
           Manage Department Information
           Manage Student Information
           Manage Courses Offering
           Manage Course Catalogue
           Manage Lecturer Information
           Manage Financial Activities
           Manage User Account

     List of features will not be developed
           Pay tuition fee (billing system)
           Access the system as professor or lecturer




                                                 18
Final Document




Business Plan &
               SRS Document

11/9/2007
Ho Chi Minh National University – International University
Instructor: Phan Viet Hoang

Group 6
                   Date                 November 9th , 2007
                   Version              1.0
                   Status               Baseline
                   Author               Team TiHonMumMim
                   Reviewer             Team TiHonMumMim
                   Documenter           Nguyen Duc Quan


                       Team member                  Signature

                   Nguyen Duc Quan

                   Le Vu Hoang

                   Tran Minh Phung

                   Phan Duy Tan

                   Huynh Da Thuc




                                   19
Final Document



Business Plan & SRS Document




                20
Final Document


STATEMENT OF WORK
As the head of information systems for International University, our team is tasked with developing
a new Online Course Registration System.
       The system will allow students to access the system during registration time to register for
       courses, add or drop the registered courses, check tuition fee, and review their academic
       history.
       The academic affair staffs will use the system as a mean to manage information of
       departments, faculties, students and offering courses.
       The system also supports financial office staffs in monitoring financial activities.
The features of the systems can be summarized as the following table:

Group of users              Features OURS provides
All Users                   Login and Log out
Academic Affair Staffs      Manage Department
                            Information
                            Manage Lecturer Information
                            Manage Course Catalogue
                            Manage Student Information
                            Manage Courses Offering
Financial Office Staffs     Manage Financial Activities
Students                    View Academic History
                            Register for courses
Administrator               Manage User Account



Our team is going to develop the system using Rational Unified Process with use-case driven. It
includes four phases (inception, elaboration, construction, and transition). And in each phase, we
will go through 6 workflows only (Management, Requirement, Analysis, Design, Implementation,
and Testing). In fact, all 6 workflows will be done iteratively in each phase. However, attention level
of ours team on each workflow in different phases is different. In particular,

Inception: It can be referred as Initial phase. In this phase we will review the initial system request
from customer, do feasibility study, define the vision and scope of the new system, and the initial
project plan.




                                                  21
Final Document


Elaboration: It can be referred as planning & requirement phase. In this phase we will pay
attention on detail plan which includes risk plan, estimation, and detail schedule. We also capture
& analyze most of requirements to define the system and analyze its behaviors.

Construction: It can be referred as executing, monitoring, and controlling phase which includes 3
main parts: system design, system implementation, and testing.

Transition: It can be referred as closing phase. In this phase, we will complete and improve the
system, and performance acceptance test to prepare for delivering the system to the stakeholders.



     Inception                 Elaboration                Construction             Transition



In order to complete the system development, our team will complete the vision and scope
document, project plan and 6 primary development models which are key products of each phase.




           [Use-case driven]
                                              Design
                                              Model
    Use case           Analysis                                  Implementation         Test
     Model              Model                                        Model             Model
                                             Deployment
                                               Model




Vision and Scope document: It provides a vision of current problem and solution for the problem.
It also defines what will be developed and what will not be developed. It is done in Inception phase.

Project plan: It is a business plan. It includes statements of works, project estimation, schedule,
and risk plan. It is also done in Inception phase.

Use case model: It is a group of use-case package, which includes one or some related use-cases.
And each use case will contain related users’ needs, goals, tasks, processes…, and resources

                                                  22
Final Document


involved to it together. It is created after users and stakeholders’ requirements are captured by
business analysts. The most important document included in use case model is use-cases
specification document. Use-case model will be done in Inception & Elaboration phases.

Analysis model: It contains use-cases and theirs realization which includes domain study, analysis
classes and objects, interactions and behaviors of the system. It also defines the design constraints,
test plan and test cases for the system. Analysis model is mainly done in Elaboration phase.

Design model: It includes system design specifications that define the system architecture and
detail design of components, database, graphical user interface, and the constraints for
implementation. Design model is done in Construction phase.

Deployment model: It defines how we can deploy the system so that it can run on server(s).
However, we intent to develop the system running on one server only, not distributed on many
server. Therefore, we will not pay much attention on deployment model. This model will be done in
Construction phase.

Implementation model: It defines the way we transfer from logical system architecture into
physical system architecture; test components (unit testing) and integrate them together in order
to form a unique system that satisfies users and stakeholders’ needs.

Test model: It includes many checklists and test cases that are planned and designed in previous
phases. It also requires all defects or errors to be recorded in defects and errors reports. It is done
in Construction phase.

The detail of each workflows and models will be presented in detail schedule, and the plan for each
phase.

Development team will use web-base and J2EE technologies to develop the system.




                                                  23
Final Document


RESOURCE LIST

Human
   Team member                  Main roles                           Responsibilities
   Tran Minh Phung       Tester, Integrator       Integrate, test components, builds, and system
   Le Vu Hoang           System Designer, Coder   Design components, system and implement
                                                  components
   Huynh Da Thuc         Tester, UI Designer      Design graphical user interface, and test components,
                                                  builds, and system
   Phan Duy Tan          System Analyst, Coder    Analyze system and implement front end of the
                                                  system
   Nguyen Duc Quan       Team leader, Business    Monitor, control the project; analyze requirements
                         Analyst, Documenter      and system behaviors; and do documentation



Software
  Documentation tool        Microsoft word 2007
  Scheduling tool           Microsoft project 2007
  IDE                       Netbean 6.0
  Web Server                Glassfish server 2.0
                            Photoshop CS2
  Design tool
                            Microsoft Express Web Designer
  JDK                       JDK 6.0
  DBMS                      MySQL 5.0
  Browser                   Internet Explorer 6.0, 7.0
                            Firefox, Opera
  Operating system          Windows XP, Vista, Linux

Hardware
  Client        3 laptops
                2 desktops
  Server        Reuse one 24/7 available desktop to simulate the server for testing
                and deployment




                                                  24
Final Document


ESTIMATION

Huynh Da Thuc estimation
Name : Huynh Da Thuc                          Date: 11/09/2007                                    Estimation form ///
Goal statement: To estimate the time to develop prototype for customer A and B                                            Unit: days
Category                   x     goal tasks             x quality tasks            waiting time            project overhead
No.                       Task                    Est    Del1    Del2     Del3     Del4   Total                      Assumption
Initial
  1       Write team introduction                   3        1                                4
                                                                                                   The system request is quite complex than initial
  2       Review system request                     4        2      1       -4                3    review
                                                                                                   The key user and stakeholder varies and
  3       Identify User and Stakeholder             4       -4      3                         3    changes
          Gather user and stakeholder
                                                    2        3      5       -5                5    Difficult in getting appointment and interview
  4       ideas
  5       Write Project background                  2      0.5     0.5                        3
  6       Write Vision statement                    1        2      3                         6
  7       Write Scope statement                     2       -1      1                         2    The scope is quite simple
  8       Identify risks and assumption             2      0.5                              2.5
                                                                                                   The document should be review again and
  9       Complete vision and scope                 1      0.5     0.5                        2    check any existing error
 10       Team Review                               3       -1                                2    Team gather late and far distance
 11       Review 1                                  3      0.5     0.5                        4
Planning
  1       Complete statements of works              2        1                                3    Statement of works is more complex
                                                                                                   Risk varies and should be coherent between
  2       Plan for risk                             4        1      -1                        4    the team members
  3       WBS                                       2        3      -1         1              5
  4       Estimation & assumption                   1      0.5     0.5                        2    Idea should be coherent
  5       Schedule                                0.5      0.5      1                         2
                                                                                                   The document is long and complex, need more
  6       Discussion summary                        2        3      1                         7    time to review
  7       Analyze initial requirement               2        2      2                         6
          Understand stakeholder & user
  8       needs                                     1        1      -2         2              2
  9       Complete glossary                         2        1      1                         4    The glossary should be exact and complete
 10       Login use case                            1        1      -2         3              3
 11       Manage faculty use case                 1.5                                         2
 12       Manage lecturer use case                  1        1      1                         3    The use case should be reviewed many times
 13       Manage student use case                 0.5               2                         3    The use case should be reviewed many times
 14       Manage courses offering                   2        1      1                         4    The use case should be reviewed many times
 15       View academic history                     2        2      1                         5
                                                                          25
Final Document


16   Register courses use case          3     1   1         1    6
17   Manage financial activities        3     2   -3        1    3   Financial activities are quite complex
     Complete functional
18   requirement                        1     1   -4        4    2
     Complete non-functional
19   requirements                       2     1                  3
20   Define the system                  1     1   3         1    6   Team should consider carefully this part
     Manage the scope of the
21   system                             2     1   1         1    5
                                                                     Requirement is complex and should be
22   Complete SRS                       1     1   1              3   reviewed more
23   SRS inspection                    0.5        1              2
24   Test Plan                         1.5    1                  3
25   Test case                          2     1                  3
26   Detail WBS                         2                        2
27   Re-estimation & assumption        1.4    1                  2
28   Detail Schedule                   1.5                       2
29   Team review                        1     2                  3
30   Review 2                           2                        2
Executing
 1   Define candidate architecture     1.5                       2
 2   Refine the architecture            1     1                  2   Refinement should last for more session
 3   Analyze behaviors                  2                        2
 4   Complete analysis model            2     1                  3
     Complete design model &
 5   system architecture                1     1   1              3   The architecture grows rapidly
 6   Design GUI                         2     1                  3
 7   Design database                   1.5                       2
 8   Design persistence layer           2     1                  3
 9   Design business logic layer       1.5                       2
10   Design presentation layer         1.5    1                  3
11   Design test case                   2                        2
     Complete Implementation
12   model                              1     1                  2
     Complete Implementation
13   guidelines & code conventions      2                        2
14   Produce Integration build plan     1                        1
15   Review OOAD                        1                        1
16   Create file structure of system    1                        1
17   Implement GUI                     10                       10
18   Implement database                 9     2                 11   No experience in using MySQL
19   Implement persistence layer       11                       11

                                                       26
Final Document


20    Implement business logic layer   9                      9
21    Implement presentation layer     9                      9
      Review code & update
22    changes                          2    1                 3   Fixing bugs and updates encounter difficulty
23    Integrated build                 2                      2
24    Do integration test              1    1                 2
25    Test build                       1    1                 2
26    Test system                      2    1                 3   System should be tested well
                                                                  Inspection meeting should be established
                                                                  between this duration to ensure the report is
27    Complete test report             6    2                 8   defection-free and coherent
28    Rework                           4    2                 6
29    Team review & evaluation         1    1                 2
30    Review 3                         1    2                 3
Closing
                                                                  Need coherence and re-check logic
  1   Complete source code             6    2   4            12   functionality
  2   Complete User Manual             3    2   1        1    7   User manual must be in detail
  3   Do acceptance test               3    1   1             5   Acceptance test is brand new to team
  4   Team review & evaluation         2                      2
  5   Complete all documents           2    2   3             7
  6   Review 4                         2                      2




                                                    27
Final Document


Phan Duy Tan estimation

Name : Phan Duy Tan                       Date: 11/09/2007                                    Estimation form ///


Goal statement: To estimate the time to develop prototype for customer A and B                                          Unit: days


Category                   x     goal tasks           x quality tasks          waiting time                project overhead

No.
                          Task                 Est.    Del1    Del2     Del3   Del4   Total                         Assumption

Initial
  1       Write team introduction               0.5      0.5                              1      discuss
  2       Review system request                 0.5      0.5                              1      additional requirement
  3       Identify User and stakeholder          1         1      1                       3      Interview
                                                                                                 2 members do not know requirements provides
          Login use case                         4        -2                              2
  4                                                                                              last year

  5       Write Project background               1         1                              2      Spend time to understand current problem
  6       Write Vision statement                0.5      0.5                              1      review
  7       Write Scope statement                 0.5      0.5                              1      review
  8       Identify risks and assumption          3        -1      2                       4      cannot find all risk and assumption
                                                                                                 All parts of Vision and Scope document have to
          Complete vision and scope             0.5      0.5                              1
  9                                                                                              be finished
 10       Team Review                                                                     1
 11       Review 1                              0.5                                     0.5
Planning
  1       Complete statements of works          0.5                                     0.5
  2       Plan for risk                          6         4      -1                      9      Need a lot of meeting to identify mitigation plan
  3       WBS                                   0.5                                     0.5
  4       Estimation & assumption                1                                        1
  5       Schedule                              0.5                                     0.5
  6       Discussion summary                     1                                        1
  7       Analyze initial requirement            2         1                              3      Review
          Understand stake holder &
  8       user needs                             2                                        2
  9       Complete glossary                     0.5      0.5                              1      Double-check term definitions
 10       Login use case                         1                                        1
 11       Manage faculty use case                1                                        1
 12       Manage lecturer use case               1                                        1
 13       Manage student use case                2                                        2

                                                                        28
Final Document


                                                                  There are many solutions in solving problem of
     Manage courses offering            4     -1   1          4   course offering management. It is difficult to
14                                                                choose one
15   View academic history              1                     1
16   Register courses use case          4     -1              3   Team brainstorming
17   Manage financial activities        2     -1              1   only simple activities
     Complete functional
18   requirement                        3                     3
     Complete non-functional
19   requirements                       3                     3
20   Define the system                  2     1               3   Review
     Manage the scope of the
21   system                             2                     2
22   Complete SRS                       1     1               2   Use cases are written in details
23   SRS inspection                     1                     1
24   Test Plan                          2     1               3   No experience
25   Test case                          2     1               3   Review
26   Detail WBS                        0.5                  0.5
27   Re-estimation & assumption        0.5   0.5              1   Under-estimate tasks
28   Detail Schedule                   0.5                  0.5
29   Team review                        1                     1
30   Review 2                           1                     1
Executing
 1   Define candidate architecture      3     2               5   J2EE architecture is complex
 2   Refine the architecture            1     1               2   J2EE architecture is complex
 3   Analyze behaviors                  1                     1
 4   Complete analysis model            1                     1
     Complete design model &
 5   system architecture                2     1               3   Review
 6   Design GUI                         1                     1
 7   Design database                    2                     2
 8   Design persistence layer           1                     1
 9   Design business logic layer        1                     1
10   Design presentation layer          1                     1
11   Design test case                   2     1               3   test case document
     Complete Implementation
12   model                              2                     2
     Complete Implementation
13   guidelines & code conventions     0.5                  0.5
14   Produce Integration build plan    0.5                    1
15   Review OOAD                       0.5   0.5              1   Debate
16   Create file structure of system   0.5   0.5              1   Packaging

                                                       29
Final Document

                                                                     Tan has a lot of experience in implementing
17    Implement GUI                     6    -1   -1        1    5   GUI
18    Implement database                4    4    2         1   11   First time using MySQL
19    Implement persistence layer       9                        9
20    Implement business logic layer   10                       10
21    Implement presentation layer      6    1                   7   Environment integration
      Review code & update
22    changes                           1                        1
23    Integrate build                   1                        1
24    Do integration test               2    -1                  1   No experience
25    Test build                        2                        2
26    Test system                       2                        2
27    Complete test report              3    2                   5   Fix new defects
28    Rework                            3                        3
29    Team review & evaluation          1                        1
30    Review 3                          1                        1
Closing
  1   Complete source code             10    -1   -1             8   use IDE
  2   Complete User Manual              6    -1                  5   Thuc has a very good writing skill
  3   Do acceptance test                3                        3
  4   Team review & evaluation          1                        1
  5   Complete all documents            3                        3
  6   Review 4                          1                        1




                                                       30
Final Document


Tran Minh Phung estimation

Name : Tran Minh Phung                        Date: 11/09/2007                                       Estimation form ///


Goal statement: To estimate the time to develop prototype for customer A and B                                             Unit: days


Category                   x     goal tasks            x quality tasks            waiting time              project overhead


No.                       Task                  Est     Del1     Del2    Del3     Del4    Total                       Assumption

Initial
  1       Write team introduction                  2      0.5     0.5                            3             Understanding the problems
  2       Review system request                    2        1     0.5     0.5                    4
  3       Identify User and Stakeholder            2      0.5     0.5                            3


          Gather user and stakeholder
                                                   3        1       1                            5              Use all existed documents
          ideas
  4
  5       Write Project background                 1        1                 2                  4
  6       Write Vision statement                   3        1       1     0.5      0.5           6
  7       Write Scope statement                    4        1       2                            7
  8       Identify risks and assumption            1      0.5     0.5         1                  3
  9       Complete vision and scope                1      0.5     0.5                            2             Have enough all information
 10       Team Review                              1                                             1
 11       Review 1                                 1                                             1
Planning

                                                                                                         Vision and Scope documents is baseline
  1       Complete statements of works             1      0.5     0.5                            2

                                                                                                        Candidate risks must be listed out already
  2       Plan for risk                            3        2       1         1                  5
  3       WBS                                      4      0.5     0.5         1                  6
  4       Estimation & assumption                1.5              0.5                            2
  5       Schedule                                 2        1                                    3
  6       Discussion summary                       6        1                                    7
  7       Analyze initial requirement              2                                             2
          Understand stake holder &
  8       user needs                               1        1       1                            3
  9       Complete glossary                        4        1     0.5     0.5                    5
 10       Login use case                           3      0.5     0.5                            4

                                                                         31
Final Document


11   Manage faculty use case           2    0.5   0.5             3
12   Manage lecturer use case          3    0.5   0.5             4
13   Manage student use case           3     1                    4
14   Manage courses offering           3     1                    4
15   View academic history             4     1     1              6
16   Register courses use case         4     1     1         1    7
17   Manage financial activities       1    0.5                   2
     Complete functional
18   requirement                       1                          1
     Complete non-functional
19   requirements                      3     1                    4
20   Define the system                 7    0.5   0.5             8
     Manage the scope of the
21   system                            8     1     2             11
22   Complete SRS                      1                          1
23   SRS inspection                    1                          1
24   Test Plan                         2     1                    3
25   Test case                         2     1                    3
26   Detail WBS                        2                          2
27   Re-estimation & assumption        1                          1
28   Detail Schedule                   1                          1
29   Team review                       1                          1
30   Review 2                          1                          1
Executing
 1   Define candidate architecture     1     1                    2
 2   Refine the architecture           1                          1
 3   Analyze behaviors                 1                          1
 4   Complete analysis model           2                          2
     Complete design model &
 5   system architecture               2                          2
 6   Design GUI                        1     1                    2
 7   Design database                   1     1                    2
 8   Design persistence layer          1     1                    2
 9   Design business logic layer      1.5   0.5                   2
10   Design presentation layer        1.5   0.5                   2
11   Design test case                 1.5   0.5                   2
     Complete Implementation
12   model                             2                          2
     Complete Implementation
13   guidelines & code conventions     1                          1
14   Produce Integration build plan    2                          2
15   Review OOAD                       1                          1
                                                        32
Final Document


16    Create file structure of system   1.5   0.5                   2
17    Implement GUI                     10     2                   12
18    Implement database                 8    1.5   0.5            10
19    Implement persistence layer        9    0.5   0.5            10
20    Implement business logic layer     8    0.5   0.5        1   10
21    Implement presentation layer       7     2     1             10
      Review code & update
22    changes                            1     1                    2
23    Integrate build                    1     1                    2
24    Do integration test                1     1                    2
25    Test build                         1    0.5   0.5             2
26    Test system                        3                          3
27    Complete test report               6     2     1              9
28    Rework                             5     2                    7
29    Team review & evaluation           1     1                    2
30    Review 3                           1                          1
Closing
  1   Complete source code              10     1     1         1   13
  2   Complete User Manual               6     1     1              8
  3   Do acceptance test                 4     2                    6
  4   Team review & evaluation           1     2                    3
  5   Complete all documents             4     3     1              8
  6   Review 4                           1                          1




                                                          33
Final Document


Nguyen Duc Quan estimation

Name :Nguyen Duc Quan                         Date: 11/09/2007                                        Estimation form ///


Goal statement: To estimate the time to develop prototype for customer A and B                                               Unit: days


Category                   x     goal tasks            x quality tasks             waiting time               project overhead


No.                       Task                  Est     Del1     Del2    Del3      Del4    Total                        Assumption

Initial
  1       Write team introduction                  1        2      -1                             2
  2       Review system request                    1        1                                     2
  3       Identify User and Stakeholder            2        1      -1                             2


          Gather user and stakeholder                                                                  Use existing requirements provided last year,
                                                   1                                              1
          ideas                                                                                        additional requirements
  4
  5       Write Project background                 1                                              1
  6       Write Vision statement                   1                                              1
  7       Write Scope statement                    1                                              1

                                                                                                       this task must be done along the summary
                                                                                                       task
  8       Identify risks and assumption            4        2       2         -2                  6
  9       Complete vision and scope              0.5      0.5                                     1    must do informal review
 10       Team Review                              1                                              1
 11       Review 1                                 1                                              1
Planning
  1       Complete statements of works           0.5      0.5                                     1

                                                                                                       lack of experience in risk mitigation
  2       Plan for risk                            8        2       1         -2              11
  3       WBS                                      1                                              1
  4       Estimation & assumption                  1                                              1
  5       Schedule                                 1                                              1

                                                                                                       must be more detail than vision and scope
  6       Discussion summary                       1      0.5     0.5                             2
  7       Analyze initial requirement              1        1                                     2
          Understand stake holder &
  8       user needs                               2                                              2

                                                                         34
Final Document


 9   Complete glossary               2                       2


10   Login use case                  3    -1                 2   Login is a popular function
11   Manage faculty use case         2    1                  3
12   Manage lecturer use case        2    1                  3
13   Manage student use case         2    1                  3
14   Manage courses offering         2    1                  3   3 members are familiar with old requirements
15   View academic history           2    1                  3
16   Register courses use case       2    1                  3
17   Manage financial activities     2    1                  3
     Complete functional
18   requirement                     1    1    1             3
     Complete non-functional
19   requirements                    1    1    1             3
20   Define the system               1    1    1             3


                                                                 Must perform scope management during the
                                                                 requirement phase
     Manage the scope of the
21   system                          6    2    1        1   10
22   Complete SRS                    1                       1
23   SRS inspection                  1                       1
24   Test Plan                       1    1                  2
25   Test case                       1    1                  2
26   Detail WBS                      1                       1
27   Re-estimation & assumption      1                       1
28   Detail Schedule                 1                       1
29   Team review                     1                       1
30   Review 2                        1                       1
Executing
 1   Define candidate architecture   2    1                  3
 2   Refine the architecture         1                       1
 3   Analyze behaviors               1                       1
 4   Complete analysis model         1                       1
     Complete design model &
 5   system architecture             1                       1
 6   Design GUI                      1    1                  2
 7   Design database                 1                       1
 8   Design persistence layer        1                       1
 9   Design business logic layer     1                       1
10   Design presentation layer       1                       1

                                                   35
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents
All  Documents

Más contenido relacionado

La actualidad más candente

(Springer optimization and its applications 37) eligius m.t. hendrix, boglárk...
(Springer optimization and its applications 37) eligius m.t. hendrix, boglárk...(Springer optimization and its applications 37) eligius m.t. hendrix, boglárk...
(Springer optimization and its applications 37) eligius m.t. hendrix, boglárk...
ssuserfa7e73
 
Ppdg Robust File Replication
Ppdg Robust File ReplicationPpdg Robust File Replication
Ppdg Robust File Replication
guest0dc8a2
 
Cloud Computing Security (Final Year Project) by Pavlos Stefanis
Cloud Computing Security (Final Year Project) by Pavlos StefanisCloud Computing Security (Final Year Project) by Pavlos Stefanis
Cloud Computing Security (Final Year Project) by Pavlos Stefanis
Pavlos Stefanis
 
Video and Storytelling
Video and StorytellingVideo and Storytelling
Video and Storytelling
E-Mediat
 
Stair climbing hand truck
Stair climbing hand truckStair climbing hand truck
Stair climbing hand truck
Shiyas Basheer
 
Instructor utilities guide
Instructor utilities guideInstructor utilities guide
Instructor utilities guide
apaezgonzal
 

La actualidad más candente (17)

Creating A Business Advantage With Offshore Resources
Creating A Business Advantage With Offshore ResourcesCreating A Business Advantage With Offshore Resources
Creating A Business Advantage With Offshore Resources
 
(Springer optimization and its applications 37) eligius m.t. hendrix, boglárk...
(Springer optimization and its applications 37) eligius m.t. hendrix, boglárk...(Springer optimization and its applications 37) eligius m.t. hendrix, boglárk...
(Springer optimization and its applications 37) eligius m.t. hendrix, boglárk...
 
Ppdg Robust File Replication
Ppdg Robust File ReplicationPpdg Robust File Replication
Ppdg Robust File Replication
 
Sentrifugo 3.2 User Guide
Sentrifugo 3.2  User GuideSentrifugo 3.2  User Guide
Sentrifugo 3.2 User Guide
 
Sentrifugo 3.1.1 User Guide
Sentrifugo 3.1.1 User GuideSentrifugo 3.1.1 User Guide
Sentrifugo 3.1.1 User Guide
 
Sentrifugo 3.1 User Guide
Sentrifugo 3.1 User GuideSentrifugo 3.1 User Guide
Sentrifugo 3.1 User Guide
 
Sentrifugo HRMS 3.0 - User Guide
Sentrifugo HRMS 3.0 - User GuideSentrifugo HRMS 3.0 - User Guide
Sentrifugo HRMS 3.0 - User Guide
 
Caulobacter crescentus Surface Adherence As A Developmental Process A Ph D T...
Caulobacter crescentus Surface Adherence As A Developmental Process  A Ph D T...Caulobacter crescentus Surface Adherence As A Developmental Process  A Ph D T...
Caulobacter crescentus Surface Adherence As A Developmental Process A Ph D T...
 
Cloud Computing Security (Final Year Project) by Pavlos Stefanis
Cloud Computing Security (Final Year Project) by Pavlos StefanisCloud Computing Security (Final Year Project) by Pavlos Stefanis
Cloud Computing Security (Final Year Project) by Pavlos Stefanis
 
Video and Storytelling
Video and StorytellingVideo and Storytelling
Video and Storytelling
 
Basic stats
Basic statsBasic stats
Basic stats
 
Extraction, separation, and bio transformation of natural plant derived compo...
Extraction, separation, and bio transformation of natural plant derived compo...Extraction, separation, and bio transformation of natural plant derived compo...
Extraction, separation, and bio transformation of natural plant derived compo...
 
Clancy95barriers geetal
Clancy95barriers geetalClancy95barriers geetal
Clancy95barriers geetal
 
Stair climbing hand truck
Stair climbing hand truckStair climbing hand truck
Stair climbing hand truck
 
Instructor utilities guide
Instructor utilities guideInstructor utilities guide
Instructor utilities guide
 
Vita Industry Survey 2010
Vita Industry Survey 2010Vita Industry Survey 2010
Vita Industry Survey 2010
 
.Final Project Complete
.Final Project Complete.Final Project Complete
.Final Project Complete
 

Similar a All Documents

Emergency Planning Independent Study 235.b
Emergency Planning  Independent Study 235.b  Emergency Planning  Independent Study 235.b
Emergency Planning Independent Study 235.b
MerrileeDelvalle969
 
Mandarin chinese curriculum
Mandarin chinese curriculumMandarin chinese curriculum
Mandarin chinese curriculum
cdcjr
 
Evaluation of the u.s. army asymmetric warfare adaptive leader program
Evaluation of the u.s. army asymmetric warfare adaptive leader programEvaluation of the u.s. army asymmetric warfare adaptive leader program
Evaluation of the u.s. army asymmetric warfare adaptive leader program
Mamuka Mchedlidze
 
Building special operations partnership in afghanistan and beyond
Building special operations partnership in afghanistan and beyondBuilding special operations partnership in afghanistan and beyond
Building special operations partnership in afghanistan and beyond
Mamuka Mchedlidze
 
Quick testprofessional book_preview
Quick testprofessional book_previewQuick testprofessional book_preview
Quick testprofessional book_preview
Saurabh Singh
 

Similar a All Documents (20)

Project Plan And Srs Final
Project Plan And Srs FinalProject Plan And Srs Final
Project Plan And Srs Final
 
Testing Plan Test Case
Testing Plan Test CaseTesting Plan Test Case
Testing Plan Test Case
 
Emergency Planning Independent Study 235.b
Emergency Planning  Independent Study 235.b  Emergency Planning  Independent Study 235.b
Emergency Planning Independent Study 235.b
 
Emergency planning independent study 235.b
Emergency planning  independent study 235.b  Emergency planning  independent study 235.b
Emergency planning independent study 235.b
 
Mandarin chinese curriculum
Mandarin chinese curriculumMandarin chinese curriculum
Mandarin chinese curriculum
 
25quickformativeassessments 130203063349-phpapp01
25quickformativeassessments 130203063349-phpapp0125quickformativeassessments 130203063349-phpapp01
25quickformativeassessments 130203063349-phpapp01
 
Evaluation of the u.s. army asymmetric warfare adaptive leader program
Evaluation of the u.s. army asymmetric warfare adaptive leader programEvaluation of the u.s. army asymmetric warfare adaptive leader program
Evaluation of the u.s. army asymmetric warfare adaptive leader program
 
K12 2011
K12 2011K12 2011
K12 2011
 
Rand rr2364
Rand rr2364Rand rr2364
Rand rr2364
 
Comparing Game Development on the Android and Windows Phone 7 Platforms.
Comparing Game Development on the Android and Windows Phone 7 Platforms.Comparing Game Development on the Android and Windows Phone 7 Platforms.
Comparing Game Development on the Android and Windows Phone 7 Platforms.
 
Factors affect taking charge at Vingroup Corporation
Factors affect taking charge at Vingroup CorporationFactors affect taking charge at Vingroup Corporation
Factors affect taking charge at Vingroup Corporation
 
Building special operations partnership in afghanistan and beyond
Building special operations partnership in afghanistan and beyondBuilding special operations partnership in afghanistan and beyond
Building special operations partnership in afghanistan and beyond
 
Publication: Space Debris: Applied Technologies and Policy Prescriptions
Publication: Space Debris: Applied Technologies and Policy PrescriptionsPublication: Space Debris: Applied Technologies and Policy Prescriptions
Publication: Space Debris: Applied Technologies and Policy Prescriptions
 
Rand rr3242 (1)
Rand rr3242 (1)Rand rr3242 (1)
Rand rr3242 (1)
 
Rand rr3242
Rand rr3242Rand rr3242
Rand rr3242
 
Ict in africa education fullreport
Ict in africa education fullreportIct in africa education fullreport
Ict in africa education fullreport
 
NYU Masters Thesis - 2009 (Thesis of the Year - Runner Up)
NYU Masters Thesis - 2009 (Thesis of the Year - Runner Up)NYU Masters Thesis - 2009 (Thesis of the Year - Runner Up)
NYU Masters Thesis - 2009 (Thesis of the Year - Runner Up)
 
Quick testprofessional book_preview
Quick testprofessional book_previewQuick testprofessional book_preview
Quick testprofessional book_preview
 
Fraser_William
Fraser_WilliamFraser_William
Fraser_William
 
Erpi admin 11123510[1] by иссам неязын issam hejazin
Erpi admin 11123510[1] by иссам неязын issam hejazinErpi admin 11123510[1] by иссам неязын issam hejazin
Erpi admin 11123510[1] by иссам неязын issam hejazin
 

Último

Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire business
panagenda
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Safe Software
 

Último (20)

EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWEREMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
 
GenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdfGenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdf
 
A Beginners Guide to Building a RAG App Using Open Source Milvus
A Beginners Guide to Building a RAG App Using Open Source MilvusA Beginners Guide to Building a RAG App Using Open Source Milvus
A Beginners Guide to Building a RAG App Using Open Source Milvus
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
 
Apidays Singapore 2024 - Scalable LLM APIs for AI and Generative AI Applicati...
Apidays Singapore 2024 - Scalable LLM APIs for AI and Generative AI Applicati...Apidays Singapore 2024 - Scalable LLM APIs for AI and Generative AI Applicati...
Apidays Singapore 2024 - Scalable LLM APIs for AI and Generative AI Applicati...
 
Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...
 
Artificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : UncertaintyArtificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : Uncertainty
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
 
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
AXA XL - Insurer Innovation Award Americas 2024
AXA XL - Insurer Innovation Award Americas 2024AXA XL - Insurer Innovation Award Americas 2024
AXA XL - Insurer Innovation Award Americas 2024
 
AWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of Terraform
 
Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire business
 
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
 
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...
 
Corporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptxCorporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptx
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdf
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
 
Apidays Singapore 2024 - Modernizing Securities Finance by Madhu Subbu
Apidays Singapore 2024 - Modernizing Securities Finance by Madhu SubbuApidays Singapore 2024 - Modernizing Securities Finance by Madhu Subbu
Apidays Singapore 2024 - Modernizing Securities Finance by Madhu Subbu
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 

All Documents

  • 1. Vision and Scope Document 10/12/2007 Ho Chi Minh National University – International University Instructor: Phan Viet Hoang Date October 10th , 2007 Version 1.0 Status Baseline Author Team TiHonMumMim(Group 6) Reviewer Team TiHonMumMim(Group 6) Documenter Nguyen Duc Quan Team member Signature Nguyen Duc Quan Le Vu Hoang Tran Minh Phung Phan Duy Tan Huynh Da Thuc
  • 2. Final Document Table of Contents Introduction ..................................................................................................................................................... 13 Development team & OURS project ................................................................................................................ 13 Problem Statement .......................................................................................................................................... 15 Project background ...................................................................................................................................... 15 Key users ...................................................................................................................................................... 15 Stakeholders ................................................................................................................................................ 16 Assumptions & Constraints of Online University Registration System ......................................................... 17 Vision of Solution ............................................................................................................................................. 17 Vision statement .......................................................................................................................................... 17 Scope ........................................................................................................................................................... 18 List of features ............................................................................................................................................. 18 List of features will not be developed .......................................................................................................... 18 Business Plan & SRS Document ....................................................................................................................... 20 STATEMENT OF WORK ..................................................................................................................................... 21 RESOURCE LIST ................................................................................................................................................ 24 Human ......................................................................................................................................................... 24 Software ...................................................................................................................................................... 24 Hardware ..................................................................................................................................................... 24 ESTIMATION .................................................................................................................................................... 25 Huynh Da Thuc estimation ........................................................................................................................... 25 Phan Duy Tan estimation ............................................................................................................................. 28 Tran Minh Phung estimation ....................................................................................................................... 31 Nguyen Duc Quan estimation ...................................................................................................................... 34 Le Vu Hoang estimation ............................................................................................................................... 37 Estimation Summary .................................................................................................................................... 39 SCHEDULE ........................................................................................................................................................ 43 Task list ........................................................................................................................................................ 43 2
  • 3. Final Document Gantt chart (reference) ................................................................................................................................ 45 RISK PLAN ........................................................................................................................................................ 46 DISCUSSION SUMMARY ................................................................................................................................... 48 Project background ...................................................................................................................................... 48 Purpose of project ................................................................................................................................... 48 Scope of project ....................................................................................................................................... 49 Perspectives ................................................................................................................................................. 51 Who will use the system? ........................................................................................................................ 51 Who can provide needs about the system? ............................................................................................. 51 Project objectives ........................................................................................................................................ 52 Know business rules ................................................................................................................................. 52 System information and/or diagrams ...................................................................................................... 52 Assumptions and dependencies .............................................................................................................. 54 Design and implementation constraint .................................................................................................... 54 Risks ............................................................................................................................................................. 54 Known future enhancements ...................................................................................................................... 55 References ................................................................................................................................................... 55 Open, unresolved issues ............................................................................................................................. 55 SOFTWARE REQUIREMENT SPECIFICATION ..................................................................................................... 56 USE CASE SPECIFICATION ............................................................................................................................. 56 Log in and Log out .................................................................................................................................... 56 Manage Department Information ............................................................................................................ 58 Manage Lecturer Information .................................................................................................................. 60 Manage Student Information................................................................................................................... 63 Manage Course Offering .......................................................................................................................... 66 Manage Financial Activities ...................................................................................................................... 69 View Academic History ............................................................................................................................ 71 Register Course ........................................................................................................................................ 72 Manage Course Catalogue ....................................................................................................................... 74 Manage User Account .............................................................................................................................. 77 3
  • 4. Final Document Appendix .................................................................................................................................................. 80 FUNCTIONAL REQUIREMENT ....................................................................................................................... 82 NON-FUNCTIONAL REQUIREMENT .............................................................................................................. 86 Performance: ........................................................................................................................................... 86 Reliability: ................................................................................................................................................ 86 Availability: .............................................................................................................................................. 86 Efficiency:................................................................................................................................................. 86 Supportability: ......................................................................................................................................... 86 Integrity: .................................................................................................................................................. 86 Portability: ............................................................................................................................................... 86 Flexibility: ................................................................................................................................................. 87 INSPECTION REPORT ........................................................................................................................................ 88 GLOSSARY ........................................................................................................................................................ 89 Introduction ................................................................................................................................................. 89 Definitions.................................................................................................................................................... 89 OURS ........................................................................................................................................................ 89 Academic staff ......................................................................................................................................... 89 Finance staff ............................................................................................................................................. 89 Department ............................................................................................................................................. 89 Faculty...................................................................................................................................................... 89 Curriculum ............................................................................................................................................... 89 Subject ..................................................................................................................................................... 89 Course Offering ........................................................................................................................................ 90 Prerequisite.............................................................................................................................................. 90 Course Catalog ......................................................................................................................................... 90 Lecturer .................................................................................................................................................... 90 Student .................................................................................................................................................... 90 Student priority ........................................................................................................................................ 90 Discount rate............................................................................................................................................ 90 Grade ....................................................................................................................................................... 90 4
  • 5. Final Document Schedule .................................................................................................................................................. 90 Tuition fee ................................................................................................................................................ 90 Credit ....................................................................................................................................................... 90 Academic duration ................................................................................................................................... 90 Academic year.......................................................................................................................................... 91 Testing Plan & Test case Document ................................................................................................................. 93 A- Test Plan .................................................................................................................................................. 94 Introduction ..................................................................................................................................................... 94 Purpose ........................................................................................................................................................ 94 Scope ........................................................................................................................................................... 94 References ................................................................................................................................................... 94 Review requirement and Design ...................................................................................................................... 94 Review system architecture ......................................................................................................................... 95 Features to be tested ....................................................................................................................................... 97 Features not to be tested ................................................................................................................................ 98 Approach ......................................................................................................................................................... 99 Kind of test ................................................................................................................................................... 99 Data and Database Integrity Testing ........................................................................................................ 99 System testing.......................................................................................................................................... 99 Performance Testing .............................................................................................................................. 100 Load Testing ........................................................................................................................................... 100 Stress Testing ......................................................................................................................................... 100 Volume Testing ...................................................................................................................................... 100 Test Strategy .............................................................................................................................................. 100 Checklist of unit test .............................................................................................................................. 100 Unit testing ............................................................................................................................................ 101 Smoke test ............................................................................................................................................. 101 Test Automation .................................................................................................................................... 101 Data and Database Integrity Testing ...................................................................................................... 102 System Testing ....................................................................................................................................... 102 5
  • 6. Final Document Performance Testing .............................................................................................................................. 103 Load Testing ........................................................................................................................................... 104 Stress Testing ......................................................................................................................................... 105 Volume Testing ...................................................................................................................................... 106 Suspension criteria and resumption requirements ........................................................................................ 107 Suspension criteria..................................................................................................................................... 107 Resumption requirements ......................................................................................................................... 107 Environmental Needs .................................................................................................................................... 108 Tools .......................................................................................................................................................... 108 Software .................................................................................................................................................... 108 Hardware ................................................................................................................................................... 109 Schedule ........................................................................................................................................................ 109 Acceptance criteria ........................................................................................................................................ 110 Resources ...................................................................................................................................................... 110 B- Test Case ................................................................................................................................................ 113 Unit testing .................................................................................................................................................... 113 Test Cases of Log in and Log out Use Case ..................................................................................................... 115 User logs in successfully with valid username and password .................................................................... 115 Fail to login the system when providing invalid username ........................................................................ 115 Fail to login the system when providing username or password containing special character(s).............. 115 Fail to login the system when providing valid username and invalid password ......................................... 116 Fail to login the system when providing empty username ........................................................................ 116 Fail to login the system when providing valid username and empty password ......................................... 117 User account is locked after failing to log in 3 times .................................................................................. 117 User logs in the system using an account is being used by another user................................................... 118 User logs in the system using an account is being locked .......................................................................... 118 Change password successfully ................................................................................................................... 118 Fail to change password when old or new or confirmed password is empty ............................................ 119 Fail to change password when old password is incorrect .......................................................................... 119 Recover the password successfully ............................................................................................................ 120 6
  • 7. Final Document Fail to reset password when inputting wrong answer for the security question ....................................... 120 Fail to reset password when inputting answer containing special character(s) for the security question . 121 Fail to reset password when inputting empty answer for the security question ....................................... 122 Test Cases of Manage Department Information Use case ............................................................................. 122 Add a department with valid information successfully .............................................................................. 122 Fail to add a department with name that already exists in the system ..................................................... 123 Fail to add a department when one or some or all fields are empty ......................................................... 123 Fail to add a department when inputting special character(s) to one or some or all fields ....................... 124 Update a department with valid information successfully ........................................................................ 125 Fail to update a department with name that already exists in the system ................................................ 125 Fail to update a department when one or some or all fields are empty .................................................... 126 Fail to update a department when inputting special character(s) to one or some or all fields .................. 127 Update cancel ............................................................................................................................................ 127 Delete a department .................................................................................................................................. 128 Delete cancel ............................................................................................................................................. 128 Test Cases of Manage Lecturer Information use case.................................................................................... 129 Add a lecturer with valid information successfully .................................................................................... 129 Fail to add a department when one or some or all fields are empty ......................................................... 129 Fail to add a lecturer when inputting special character(s) to one or some or all fields.............................. 130 Look for a lecturer...................................................................................................................................... 131 Update a lecturer with valid information successfully ............................................................................... 131 Fail to update a lecturer when one or some or all fields are empty .......................................................... 133 Fail to update a lecturer information when inputting special character(s) to one or some or all fields .... 133 Update cancel ............................................................................................................................................ 134 Delete a lecturer ........................................................................................................................................ 135 Delete cancel ............................................................................................................................................. 135 Test Cases of Manage Student Information Use Case ................................................................................... 136 Add a student with valid information successfully..................................................................................... 136 Fail to add a student when one or some or all fields are empty ................................................................ 136 Fail to add a student when inputting special character(s) to one or some or all fields .............................. 137 7
  • 8. Final Document Search student by student ID or/and by student name ............................................................................. 138 Fail to search student by student ID or/and by student name when providing invalid student ID or/and student name ............................................................................................................................................. 138 Fail to search student by student ID or/and by student name when providing empty student ID or/and student name ............................................................................................................................................. 139 Search student by faculty and academic duration ..................................................................................... 139 Search student by academic year, semester, and course .......................................................................... 141 Update a student with valid information successfully ............................................................................... 141 Fail to update a student when one or some or all fields are empty ........................................................... 142 Fail to update a student when inputting special character(s) to one or some or all fields ........................ 142 Update is canceled ..................................................................................................................................... 143 Delete a student ........................................................................................................................................ 144 Delete is canceled ...................................................................................................................................... 144 Test Cases of Manage Course Offering Use Case ........................................................................................... 145 Create list of courses offering successfully ................................................................................................ 145 Update the list of course offering .............................................................................................................. 145 Cancel during the Create list of course offering operation ........................................................................ 146 Cancel during the Update list of course offering operation ....................................................................... 147 Fail to create an empty list of course offering ........................................................................................... 147 Update list of course offering while there’s no list of course offering for specific faculty ......................... 148 Test Cases of Manage Financial Activities Use Case ...................................................................................... 150 View tuition fee by student ID or/and by student name............................................................................ 150 Fail to view tuition fee by student ID or/and by student name when providing invalid student ID or/and student name ............................................................................................................................................. 150 Fail to view tuition fee by student ID or/and by student name when providing empty student ID or/and student name ............................................................................................................................................. 151 View tuition fee by faculty or/and by academic duration .......................................................................... 151 View tuition fee by academic year, semester, and course ......................................................................... 152 Update tuition fee status of a student ....................................................................................................... 152 Test Cases of View Academic History Use Case ............................................................................................. 153 View academic history successfully ........................................................................................................... 153 8
  • 9. Final Document View all course have taken history............................................................................................................. 153 View by specific year and semester. .......................................................................................................... 154 View by passed and failed status. .............................................................................................................. 154 Test Cases of Register Course Use Case ......................................................................................................... 155 Fail to register more than 30 credits .......................................................................................................... 155 Fail to register less than 15 credits ............................................................................................................ 155 Register for courses successfully................................................................................................................ 156 Update the existing schedule successfully ................................................................................................. 157 Test Cases of Manage Course Catalogue Use Case ........................................................................................ 157 Add new course to course catalogue successfully ..................................................................................... 157 Fail to add a course when one or some or all fields are empty .................................................................. 158 Fail to add a course when inputting special character(s) ........................................................................... 159 Search for course by ID or Name ............................................................................................................... 159 Fail to search for course by ID or Name when inputting invalid ID and/or Name ...................................... 160 Fail to search for course by ID or Name when inputting empty ID and/or empty Name ........................... 160 Update course with valid information successfully.................................................................................... 161 Fail to update a course when one or some or all fields are empty ............................................................ 161 Fail to update a course when inputting special character(s) ...................................................................... 162 Update operation is canceled .................................................................................................................... 163 Delete a course .......................................................................................................................................... 163 Delete operation is canceled ..................................................................................................................... 163 Test Cases of Manage User Account Use Case ............................................................................................... 164 Create a new user account successfully ..................................................................................................... 164 Fail to create a new user account when the username that user has provided existing in the system already ....................................................................................................................................................... 164 Fail to create a new user account when inputting empty username ......................................................... 165 Fail to create a new user account when the inputs containing special character(s) .................................. 166 Search for account by username ............................................................................................................... 166 Fail to search for account by empty username .......................................................................................... 167 Fail to search for account by username that does not exist in the system ................................................ 167 9
  • 10. Final Document Fail to search for account by username containing special characters(s) .................................................. 167 Update an account ..................................................................................................................................... 168 Update operation is canceled .................................................................................................................... 168 Delete an account ...................................................................................................................................... 169 Delete operation is canceled ..................................................................................................................... 169 Test Cases of Non-functional requirement testing ........................................................................................ 170 Switch from Vietnamese to English ........................................................................................................... 170 Switch from English to Vietnamese ........................................................................................................... 170 Load testing with 15 requests at the same time ........................................................................................ 170 Load testing with 25 requests at the same time ........................................................................................ 171 C- Appendix ................................................................................................................................................ 171 D- Inspection Checklist ............................................................................................................................... 173 The following checklist items apply to the test plan. ..................................................................................... 173 The following checklist items apply to the test cases: ................................................................................... 173 Testing demo ................................................................................................................................................. 176 Unit testing .................................................................................................................................................... 177 Functional requirement testing ..................................................................................................................... 177 Test Cases of Log in and Log out Use Case ..................................................................................................... 177 User logs in successfully with valid username and password .................................................................... 177 Fail to login the system when providing invalid username ........................................................................ 178 Fail to login the system when providing username or password containing special character(s).............. 178 Fail to login the system when providing valid username and invalid password ......................................... 179 Fail to login the system when providing empty username ........................................................................ 179 Fail to login the system when providing valid username and empty password ......................................... 179 User account is locked after failing to log in 3 times .................................................................................. 180 User logs in the system using an account is being used by another user................................................... 180 User logs in the system using an account is being locked .......................................................................... 181 Change password successfully ................................................................................................................... 181 Fail to change password when old or new or confirmed password is empty ............................................ 182 Fail to change password when old password is incorrect .......................................................................... 182 10
  • 11. Final Document Recover the password successfully ............................................................................................................ 183 Fail to reset password when inputting wrong answer for the security question ....................................... 183 Fail to reset password when inputting answer containing special character(s) for security question ....... 184 Fail to reset password when inputting empty answer for the security question ....................................... 184 Test Cases of Manage Course Offering Use Case ........................................................................................... 185 Create list of courses offering successfully ................................................................................................ 185 Update the list of course offering .............................................................................................................. 186 Cancel during the Create list of course offering operation ........................................................................ 186 Cancel during the Update list of course offering operation ....................................................................... 187 Fail to create an empty list of course offering ........................................................................................... 188 Update list of course offering while there’s no list of course offering for specific faculty ......................... 188 Test Cases of Manage Department Information Use case ............................................................................. 189 Add a department with valid information successfully .............................................................................. 189 Fail to add a department with name that already exists in the system ..................................................... 189 Fail to add a department when one or some or all fields are empty ......................................................... 190 Fail to add a department when inputting special character(s) to one or some or all fields ....................... 191 Update a department with valid information successfully ........................................................................ 191 Fail to update a department with name that already exists in the system ................................................ 192 Fail to update a department when one or some or all fields are empty .................................................... 193 Fail to update a department when inputting special character(s) to one or some or all fields .................. 193 Update cancel ............................................................................................................................................ 194 Delete a department .................................................................................................................................. 194 Delete cancel ............................................................................................................................................. 195 Test Cases of Register Course Use Case ......................................................................................................... 195 Fail to register more than 30 credits .......................................................................................................... 195 Fail to register less than 15 credits ............................................................................................................ 196 Register for courses successfully................................................................................................................ 196 Update the existing schedule successfully ................................................................................................. 198 Non-functional requirement testing .............................................................................................................. 198 Test Cases of Non-functional requirement testing ........................................................................................ 198 11
  • 12. Final Document Switch from Vietnamese to English ........................................................................................................... 198 Switch from English to Vietnamese ........................................................................................................... 199 Load testing with 15 requests at the same time ........................................................................................ 199 Load testing with 25 requests at the same time ........................................................................................ 199 System architecture introduction .................................................................................................................. 200 How to download & install tools .................................................................................................................... 201 How to install OURS ....................................................................................................................................... 205 How to run OURS ........................................................................................................................................... 207 How to setup and run tests of OURS ............................................................................................................. 208 How to use OURS ........................................................................................................................................... 209 Login and Logout ........................................................................................................................................... 209 Register Course .............................................................................................................................................. 209 View Academic History .................................................................................................................................. 209 Manage Department Information ................................................................................................................. 210 Manage Student Information ........................................................................................................................ 210 Manage Course Offering ................................................................................................................................ 211 Manage Lecturer Information ........................................................................................................................ 212 Manage Financial Activities ........................................................................................................................... 213 Manage Course Catalogue ............................................................................................................................. 214 Manage User Account ................................................................................................................................... 214 12
  • 13. Final Document Introduction This is the Vision and Scope document of OURS project. Like any other Vision and Scope document, this document will cover the problem and vision statement including project background, list of users, stakeholders, candidate risks, assumptions & constraints, and project scope. In addition, the document will also cover the part of development team introduction. Development team & OURS project TiHonMumMim is a small software development team set up in 2007 by 5 students of International University. The structure of the team includes 3 software engineers, 1 system & networking engineer, and 1 team leader. Our business goal is to be a leading company in IT. And our slogan is “Computing, consulting, and programming professionally” (CC&PP). For more information about our team: Email: TiHonMumMim@yahoo.com Blog: http://360.yahoo.com/TiHonMumMim 13
  • 14. Final Document We are assigned to build Online University Registration System (OURS). The internal development team structure and roles on OURS project: OURS project Team leader Documenter Tester Coder Integrator Business System System UI Analyst Analyst Designer Designer TEAM LEADER : Responsible for all project management. DOCUMENTER : Responsible for documentation from other members’ according to the RUP document standard. BUSINESS ANALYST : Capture and analyze user requirements. SYSTEM ANALYST : Analyze system requirements. SYSTEM DESIGNER : Design the internal structure and operations of system. UI DESIGNER : Design user interface for the system. CODER: Responsible for implementing the system. INTEGRATOR : Integrate the system components. TESTER : Responsible for testing activities. Team member ID Email Main roles Tran Minh Phung 090401096 toyohiko1507@yahoo.com Tester, Integrator Le Vu Hoang 090401019 smallwildcat_86@yahoo.com System Designer, Coder Huynh Da Thuc 090401121 runnfire@yahoo.com Tester, UI Designer Phan Duy Tan 090401044 kingduytan@yahoo.com System Analyst, Coder Nguyen Duc Quan 090401038 duc.quan@yahoo.com Team leader, Business Analyst, Documenter 14
  • 15. Final Document Problem Statement Project background There is a widespread agreement that the policy in course registration is very complicated, costly, take-time, and inconvenient to both students and university. This is due the fact that at the beginning of each semester, the university has to pause or delay some activities to spend time for course registration of students. Some staffs have to prepare for offering courses list (including selecting courses and inviting lecturers …), print it out, and deliver the registration form to each student. After around one week, all students’ registration form will be returned. And the staffs have to input students’ registration information to Excel files. They also have to check manually whether the registration form of each student is legal or not basing on some conditions such as prerequisite course, maximum and minimum number of credits allowed to register … If there is anything wrong or students want to add or drop the courses, everything in the above process has to be restarted. And sometimes some papers are lost when documents are moved from one place to another place; both students and university have to spend time for retrieving necessary information and approve it. However, it is impossible to do that in some cases. In addition, calculating tuition fee for students, managing students’ academic history… are also thorny issues. Mistakes can occur anytime when financial office‘s staffs use calculator or Microsoft excel to calculate tuition fee. Students’ transcript management is also another issue. When students want to have transcript to see their academic history, they have to wait at least two weeks to receive it from academic affair. Those are some typical examples for the inconvenience and complication of the current course registration policy. They lead the university to the decision of building Online Course Registration System to improve effectiveness, reduce time and cost in course registration process. Key users STUDENT: use the system to register for course or view academic history. ADMINISTRATOR: Manage the system after it is built and the authentication mechanism of the system. 15
  • 16. Final Document ACADEMIC AFFAIR STAFF: use the system to manage department and faculty, lecturer, student, course catalogue, list of course offering information. FINANCIAL OFFICE STAFF: use the system to monitor financial activities related to course registration. Stakeholders STUDENT: use the system to register for course or view academic history. ADMINISTRATOR : Manage the system after it is built. ACADEMIC AFFAIR STAFF: use the system to manage school, lecturer-professor, and ADMINISTRATOR : Manage the system after it is built and the authentication mechanism of the system. LECTURER: They could give ideas or comment on the solution for the system’s development and improvement. FINANCIAL OFFICE MANAGER : They also manage the investment of university for the system development. FINANCIAL OFFICE STAFF: use the system to monitor financial activities related to course registration. DEVELOPMENT TEAM : include all software engineers, business analysts, system analysts, system designers, implementers, testers, QA, and project manager… They are tasked to build the system. List of Risks All team members need preparation time for midterm, final exam, and other subjects. Phung, Thuc, and Hoang take pre-thesis course. Lack of experiences in software project management, especially in testing, verification, validation, risks management and changes management exists in the Team. No substitution if any team member cannot continue to contribute to the project. Applying the project again from the beginning could take development team more time. Development time is limited in 2 months only. Therefore the pressure is really high. 16
  • 17. Final Document Development team cannot deliver the components when reviewed. Development team could deliver components of unacceptably low quality, and time must be added to improve quality. Developing extra functionalities that are not required will extends the schedule. Low motivation and moral reduce productivity. Team member needs extra time to learn unfamiliar tools or techniques. Conflicts among team members’ ideas results in poor performances, more meeting, and extra rework. People’s assignments do not match their strengths. Components developed separately cannot be integrated easily, requiring redesign and rework. Detail reporting could take more development time. Assumptions & Constraints of Online University Registration System The system will be applied for universities using credit system like International University. The registration information of students is processed by academic affair. And only academic affair has right to manage and process the registration information. Development team will use J2EE architecture to develop system. Policy for tuition fee payment is using cash and it is managed by financial office. Development team must have at least one 2-hour meeting per week. Development time 2 months and 10 days (from 01/10/2007 to 20/12/2008) Development team must produce the first build before review 3 (05/12/2007). Each team member must work at least 15 hours per week. Vision of Solution Vision statement As the head of information systems for International University team are tasked with developing a new Online Course Registration System. The new system will allow students to access the system during registration time to register for courses, add or drop the registered courses, check tuition 17
  • 18. Final Document fee, and review their academic history. Academic affair can use the system as a mean to manage information of schools, classes, professors, students and offering courses. Financial office will use the system to monitor financial activities. The system provides a better solution and policy for course registration in International University. It reduces much time, cost, and resources required in processing registration information of students. Scope To be noticed on the scope of the system that this system is an Online University Registration System. It is not a university management system which is much larger than the system we try to build. It is only a part of the university management system. Therefore, we have to pay attention on building applications supporting students to do registration, academic affairs to manage information related to students’ courses registration, and financial office to mange financial activities. List of features User login and log out View Academic History Register for course Manage Department Information Manage Student Information Manage Courses Offering Manage Course Catalogue Manage Lecturer Information Manage Financial Activities Manage User Account List of features will not be developed Pay tuition fee (billing system) Access the system as professor or lecturer 18
  • 19. Final Document Business Plan & SRS Document 11/9/2007 Ho Chi Minh National University – International University Instructor: Phan Viet Hoang Group 6 Date November 9th , 2007 Version 1.0 Status Baseline Author Team TiHonMumMim Reviewer Team TiHonMumMim Documenter Nguyen Duc Quan Team member Signature Nguyen Duc Quan Le Vu Hoang Tran Minh Phung Phan Duy Tan Huynh Da Thuc 19
  • 20. Final Document Business Plan & SRS Document 20
  • 21. Final Document STATEMENT OF WORK As the head of information systems for International University, our team is tasked with developing a new Online Course Registration System. The system will allow students to access the system during registration time to register for courses, add or drop the registered courses, check tuition fee, and review their academic history. The academic affair staffs will use the system as a mean to manage information of departments, faculties, students and offering courses. The system also supports financial office staffs in monitoring financial activities. The features of the systems can be summarized as the following table: Group of users Features OURS provides All Users Login and Log out Academic Affair Staffs Manage Department Information Manage Lecturer Information Manage Course Catalogue Manage Student Information Manage Courses Offering Financial Office Staffs Manage Financial Activities Students View Academic History Register for courses Administrator Manage User Account Our team is going to develop the system using Rational Unified Process with use-case driven. It includes four phases (inception, elaboration, construction, and transition). And in each phase, we will go through 6 workflows only (Management, Requirement, Analysis, Design, Implementation, and Testing). In fact, all 6 workflows will be done iteratively in each phase. However, attention level of ours team on each workflow in different phases is different. In particular, Inception: It can be referred as Initial phase. In this phase we will review the initial system request from customer, do feasibility study, define the vision and scope of the new system, and the initial project plan. 21
  • 22. Final Document Elaboration: It can be referred as planning & requirement phase. In this phase we will pay attention on detail plan which includes risk plan, estimation, and detail schedule. We also capture & analyze most of requirements to define the system and analyze its behaviors. Construction: It can be referred as executing, monitoring, and controlling phase which includes 3 main parts: system design, system implementation, and testing. Transition: It can be referred as closing phase. In this phase, we will complete and improve the system, and performance acceptance test to prepare for delivering the system to the stakeholders. Inception Elaboration Construction Transition In order to complete the system development, our team will complete the vision and scope document, project plan and 6 primary development models which are key products of each phase. [Use-case driven] Design Model Use case Analysis Implementation Test Model Model Model Model Deployment Model Vision and Scope document: It provides a vision of current problem and solution for the problem. It also defines what will be developed and what will not be developed. It is done in Inception phase. Project plan: It is a business plan. It includes statements of works, project estimation, schedule, and risk plan. It is also done in Inception phase. Use case model: It is a group of use-case package, which includes one or some related use-cases. And each use case will contain related users’ needs, goals, tasks, processes…, and resources 22
  • 23. Final Document involved to it together. It is created after users and stakeholders’ requirements are captured by business analysts. The most important document included in use case model is use-cases specification document. Use-case model will be done in Inception & Elaboration phases. Analysis model: It contains use-cases and theirs realization which includes domain study, analysis classes and objects, interactions and behaviors of the system. It also defines the design constraints, test plan and test cases for the system. Analysis model is mainly done in Elaboration phase. Design model: It includes system design specifications that define the system architecture and detail design of components, database, graphical user interface, and the constraints for implementation. Design model is done in Construction phase. Deployment model: It defines how we can deploy the system so that it can run on server(s). However, we intent to develop the system running on one server only, not distributed on many server. Therefore, we will not pay much attention on deployment model. This model will be done in Construction phase. Implementation model: It defines the way we transfer from logical system architecture into physical system architecture; test components (unit testing) and integrate them together in order to form a unique system that satisfies users and stakeholders’ needs. Test model: It includes many checklists and test cases that are planned and designed in previous phases. It also requires all defects or errors to be recorded in defects and errors reports. It is done in Construction phase. The detail of each workflows and models will be presented in detail schedule, and the plan for each phase. Development team will use web-base and J2EE technologies to develop the system. 23
  • 24. Final Document RESOURCE LIST Human Team member Main roles Responsibilities Tran Minh Phung Tester, Integrator Integrate, test components, builds, and system Le Vu Hoang System Designer, Coder Design components, system and implement components Huynh Da Thuc Tester, UI Designer Design graphical user interface, and test components, builds, and system Phan Duy Tan System Analyst, Coder Analyze system and implement front end of the system Nguyen Duc Quan Team leader, Business Monitor, control the project; analyze requirements Analyst, Documenter and system behaviors; and do documentation Software Documentation tool Microsoft word 2007 Scheduling tool Microsoft project 2007 IDE Netbean 6.0 Web Server Glassfish server 2.0 Photoshop CS2 Design tool Microsoft Express Web Designer JDK JDK 6.0 DBMS MySQL 5.0 Browser Internet Explorer 6.0, 7.0 Firefox, Opera Operating system Windows XP, Vista, Linux Hardware Client 3 laptops 2 desktops Server Reuse one 24/7 available desktop to simulate the server for testing and deployment 24
  • 25. Final Document ESTIMATION Huynh Da Thuc estimation Name : Huynh Da Thuc Date: 11/09/2007 Estimation form /// Goal statement: To estimate the time to develop prototype for customer A and B Unit: days Category x goal tasks x quality tasks waiting time project overhead No. Task Est Del1 Del2 Del3 Del4 Total Assumption Initial 1 Write team introduction 3 1 4 The system request is quite complex than initial 2 Review system request 4 2 1 -4 3 review The key user and stakeholder varies and 3 Identify User and Stakeholder 4 -4 3 3 changes Gather user and stakeholder 2 3 5 -5 5 Difficult in getting appointment and interview 4 ideas 5 Write Project background 2 0.5 0.5 3 6 Write Vision statement 1 2 3 6 7 Write Scope statement 2 -1 1 2 The scope is quite simple 8 Identify risks and assumption 2 0.5 2.5 The document should be review again and 9 Complete vision and scope 1 0.5 0.5 2 check any existing error 10 Team Review 3 -1 2 Team gather late and far distance 11 Review 1 3 0.5 0.5 4 Planning 1 Complete statements of works 2 1 3 Statement of works is more complex Risk varies and should be coherent between 2 Plan for risk 4 1 -1 4 the team members 3 WBS 2 3 -1 1 5 4 Estimation & assumption 1 0.5 0.5 2 Idea should be coherent 5 Schedule 0.5 0.5 1 2 The document is long and complex, need more 6 Discussion summary 2 3 1 7 time to review 7 Analyze initial requirement 2 2 2 6 Understand stakeholder & user 8 needs 1 1 -2 2 2 9 Complete glossary 2 1 1 4 The glossary should be exact and complete 10 Login use case 1 1 -2 3 3 11 Manage faculty use case 1.5 2 12 Manage lecturer use case 1 1 1 3 The use case should be reviewed many times 13 Manage student use case 0.5 2 3 The use case should be reviewed many times 14 Manage courses offering 2 1 1 4 The use case should be reviewed many times 15 View academic history 2 2 1 5 25
  • 26. Final Document 16 Register courses use case 3 1 1 1 6 17 Manage financial activities 3 2 -3 1 3 Financial activities are quite complex Complete functional 18 requirement 1 1 -4 4 2 Complete non-functional 19 requirements 2 1 3 20 Define the system 1 1 3 1 6 Team should consider carefully this part Manage the scope of the 21 system 2 1 1 1 5 Requirement is complex and should be 22 Complete SRS 1 1 1 3 reviewed more 23 SRS inspection 0.5 1 2 24 Test Plan 1.5 1 3 25 Test case 2 1 3 26 Detail WBS 2 2 27 Re-estimation & assumption 1.4 1 2 28 Detail Schedule 1.5 2 29 Team review 1 2 3 30 Review 2 2 2 Executing 1 Define candidate architecture 1.5 2 2 Refine the architecture 1 1 2 Refinement should last for more session 3 Analyze behaviors 2 2 4 Complete analysis model 2 1 3 Complete design model & 5 system architecture 1 1 1 3 The architecture grows rapidly 6 Design GUI 2 1 3 7 Design database 1.5 2 8 Design persistence layer 2 1 3 9 Design business logic layer 1.5 2 10 Design presentation layer 1.5 1 3 11 Design test case 2 2 Complete Implementation 12 model 1 1 2 Complete Implementation 13 guidelines & code conventions 2 2 14 Produce Integration build plan 1 1 15 Review OOAD 1 1 16 Create file structure of system 1 1 17 Implement GUI 10 10 18 Implement database 9 2 11 No experience in using MySQL 19 Implement persistence layer 11 11 26
  • 27. Final Document 20 Implement business logic layer 9 9 21 Implement presentation layer 9 9 Review code & update 22 changes 2 1 3 Fixing bugs and updates encounter difficulty 23 Integrated build 2 2 24 Do integration test 1 1 2 25 Test build 1 1 2 26 Test system 2 1 3 System should be tested well Inspection meeting should be established between this duration to ensure the report is 27 Complete test report 6 2 8 defection-free and coherent 28 Rework 4 2 6 29 Team review & evaluation 1 1 2 30 Review 3 1 2 3 Closing Need coherence and re-check logic 1 Complete source code 6 2 4 12 functionality 2 Complete User Manual 3 2 1 1 7 User manual must be in detail 3 Do acceptance test 3 1 1 5 Acceptance test is brand new to team 4 Team review & evaluation 2 2 5 Complete all documents 2 2 3 7 6 Review 4 2 2 27
  • 28. Final Document Phan Duy Tan estimation Name : Phan Duy Tan Date: 11/09/2007 Estimation form /// Goal statement: To estimate the time to develop prototype for customer A and B Unit: days Category x goal tasks x quality tasks waiting time project overhead No. Task Est. Del1 Del2 Del3 Del4 Total Assumption Initial 1 Write team introduction 0.5 0.5 1 discuss 2 Review system request 0.5 0.5 1 additional requirement 3 Identify User and stakeholder 1 1 1 3 Interview 2 members do not know requirements provides Login use case 4 -2 2 4 last year 5 Write Project background 1 1 2 Spend time to understand current problem 6 Write Vision statement 0.5 0.5 1 review 7 Write Scope statement 0.5 0.5 1 review 8 Identify risks and assumption 3 -1 2 4 cannot find all risk and assumption All parts of Vision and Scope document have to Complete vision and scope 0.5 0.5 1 9 be finished 10 Team Review 1 11 Review 1 0.5 0.5 Planning 1 Complete statements of works 0.5 0.5 2 Plan for risk 6 4 -1 9 Need a lot of meeting to identify mitigation plan 3 WBS 0.5 0.5 4 Estimation & assumption 1 1 5 Schedule 0.5 0.5 6 Discussion summary 1 1 7 Analyze initial requirement 2 1 3 Review Understand stake holder & 8 user needs 2 2 9 Complete glossary 0.5 0.5 1 Double-check term definitions 10 Login use case 1 1 11 Manage faculty use case 1 1 12 Manage lecturer use case 1 1 13 Manage student use case 2 2 28
  • 29. Final Document There are many solutions in solving problem of Manage courses offering 4 -1 1 4 course offering management. It is difficult to 14 choose one 15 View academic history 1 1 16 Register courses use case 4 -1 3 Team brainstorming 17 Manage financial activities 2 -1 1 only simple activities Complete functional 18 requirement 3 3 Complete non-functional 19 requirements 3 3 20 Define the system 2 1 3 Review Manage the scope of the 21 system 2 2 22 Complete SRS 1 1 2 Use cases are written in details 23 SRS inspection 1 1 24 Test Plan 2 1 3 No experience 25 Test case 2 1 3 Review 26 Detail WBS 0.5 0.5 27 Re-estimation & assumption 0.5 0.5 1 Under-estimate tasks 28 Detail Schedule 0.5 0.5 29 Team review 1 1 30 Review 2 1 1 Executing 1 Define candidate architecture 3 2 5 J2EE architecture is complex 2 Refine the architecture 1 1 2 J2EE architecture is complex 3 Analyze behaviors 1 1 4 Complete analysis model 1 1 Complete design model & 5 system architecture 2 1 3 Review 6 Design GUI 1 1 7 Design database 2 2 8 Design persistence layer 1 1 9 Design business logic layer 1 1 10 Design presentation layer 1 1 11 Design test case 2 1 3 test case document Complete Implementation 12 model 2 2 Complete Implementation 13 guidelines & code conventions 0.5 0.5 14 Produce Integration build plan 0.5 1 15 Review OOAD 0.5 0.5 1 Debate 16 Create file structure of system 0.5 0.5 1 Packaging 29
  • 30. Final Document Tan has a lot of experience in implementing 17 Implement GUI 6 -1 -1 1 5 GUI 18 Implement database 4 4 2 1 11 First time using MySQL 19 Implement persistence layer 9 9 20 Implement business logic layer 10 10 21 Implement presentation layer 6 1 7 Environment integration Review code & update 22 changes 1 1 23 Integrate build 1 1 24 Do integration test 2 -1 1 No experience 25 Test build 2 2 26 Test system 2 2 27 Complete test report 3 2 5 Fix new defects 28 Rework 3 3 29 Team review & evaluation 1 1 30 Review 3 1 1 Closing 1 Complete source code 10 -1 -1 8 use IDE 2 Complete User Manual 6 -1 5 Thuc has a very good writing skill 3 Do acceptance test 3 3 4 Team review & evaluation 1 1 5 Complete all documents 3 3 6 Review 4 1 1 30
  • 31. Final Document Tran Minh Phung estimation Name : Tran Minh Phung Date: 11/09/2007 Estimation form /// Goal statement: To estimate the time to develop prototype for customer A and B Unit: days Category x goal tasks x quality tasks waiting time project overhead No. Task Est Del1 Del2 Del3 Del4 Total Assumption Initial 1 Write team introduction 2 0.5 0.5 3 Understanding the problems 2 Review system request 2 1 0.5 0.5 4 3 Identify User and Stakeholder 2 0.5 0.5 3 Gather user and stakeholder 3 1 1 5 Use all existed documents ideas 4 5 Write Project background 1 1 2 4 6 Write Vision statement 3 1 1 0.5 0.5 6 7 Write Scope statement 4 1 2 7 8 Identify risks and assumption 1 0.5 0.5 1 3 9 Complete vision and scope 1 0.5 0.5 2 Have enough all information 10 Team Review 1 1 11 Review 1 1 1 Planning Vision and Scope documents is baseline 1 Complete statements of works 1 0.5 0.5 2 Candidate risks must be listed out already 2 Plan for risk 3 2 1 1 5 3 WBS 4 0.5 0.5 1 6 4 Estimation & assumption 1.5 0.5 2 5 Schedule 2 1 3 6 Discussion summary 6 1 7 7 Analyze initial requirement 2 2 Understand stake holder & 8 user needs 1 1 1 3 9 Complete glossary 4 1 0.5 0.5 5 10 Login use case 3 0.5 0.5 4 31
  • 32. Final Document 11 Manage faculty use case 2 0.5 0.5 3 12 Manage lecturer use case 3 0.5 0.5 4 13 Manage student use case 3 1 4 14 Manage courses offering 3 1 4 15 View academic history 4 1 1 6 16 Register courses use case 4 1 1 1 7 17 Manage financial activities 1 0.5 2 Complete functional 18 requirement 1 1 Complete non-functional 19 requirements 3 1 4 20 Define the system 7 0.5 0.5 8 Manage the scope of the 21 system 8 1 2 11 22 Complete SRS 1 1 23 SRS inspection 1 1 24 Test Plan 2 1 3 25 Test case 2 1 3 26 Detail WBS 2 2 27 Re-estimation & assumption 1 1 28 Detail Schedule 1 1 29 Team review 1 1 30 Review 2 1 1 Executing 1 Define candidate architecture 1 1 2 2 Refine the architecture 1 1 3 Analyze behaviors 1 1 4 Complete analysis model 2 2 Complete design model & 5 system architecture 2 2 6 Design GUI 1 1 2 7 Design database 1 1 2 8 Design persistence layer 1 1 2 9 Design business logic layer 1.5 0.5 2 10 Design presentation layer 1.5 0.5 2 11 Design test case 1.5 0.5 2 Complete Implementation 12 model 2 2 Complete Implementation 13 guidelines & code conventions 1 1 14 Produce Integration build plan 2 2 15 Review OOAD 1 1 32
  • 33. Final Document 16 Create file structure of system 1.5 0.5 2 17 Implement GUI 10 2 12 18 Implement database 8 1.5 0.5 10 19 Implement persistence layer 9 0.5 0.5 10 20 Implement business logic layer 8 0.5 0.5 1 10 21 Implement presentation layer 7 2 1 10 Review code & update 22 changes 1 1 2 23 Integrate build 1 1 2 24 Do integration test 1 1 2 25 Test build 1 0.5 0.5 2 26 Test system 3 3 27 Complete test report 6 2 1 9 28 Rework 5 2 7 29 Team review & evaluation 1 1 2 30 Review 3 1 1 Closing 1 Complete source code 10 1 1 1 13 2 Complete User Manual 6 1 1 8 3 Do acceptance test 4 2 6 4 Team review & evaluation 1 2 3 5 Complete all documents 4 3 1 8 6 Review 4 1 1 33
  • 34. Final Document Nguyen Duc Quan estimation Name :Nguyen Duc Quan Date: 11/09/2007 Estimation form /// Goal statement: To estimate the time to develop prototype for customer A and B Unit: days Category x goal tasks x quality tasks waiting time project overhead No. Task Est Del1 Del2 Del3 Del4 Total Assumption Initial 1 Write team introduction 1 2 -1 2 2 Review system request 1 1 2 3 Identify User and Stakeholder 2 1 -1 2 Gather user and stakeholder Use existing requirements provided last year, 1 1 ideas additional requirements 4 5 Write Project background 1 1 6 Write Vision statement 1 1 7 Write Scope statement 1 1 this task must be done along the summary task 8 Identify risks and assumption 4 2 2 -2 6 9 Complete vision and scope 0.5 0.5 1 must do informal review 10 Team Review 1 1 11 Review 1 1 1 Planning 1 Complete statements of works 0.5 0.5 1 lack of experience in risk mitigation 2 Plan for risk 8 2 1 -2 11 3 WBS 1 1 4 Estimation & assumption 1 1 5 Schedule 1 1 must be more detail than vision and scope 6 Discussion summary 1 0.5 0.5 2 7 Analyze initial requirement 1 1 2 Understand stake holder & 8 user needs 2 2 34
  • 35. Final Document 9 Complete glossary 2 2 10 Login use case 3 -1 2 Login is a popular function 11 Manage faculty use case 2 1 3 12 Manage lecturer use case 2 1 3 13 Manage student use case 2 1 3 14 Manage courses offering 2 1 3 3 members are familiar with old requirements 15 View academic history 2 1 3 16 Register courses use case 2 1 3 17 Manage financial activities 2 1 3 Complete functional 18 requirement 1 1 1 3 Complete non-functional 19 requirements 1 1 1 3 20 Define the system 1 1 1 3 Must perform scope management during the requirement phase Manage the scope of the 21 system 6 2 1 1 10 22 Complete SRS 1 1 23 SRS inspection 1 1 24 Test Plan 1 1 2 25 Test case 1 1 2 26 Detail WBS 1 1 27 Re-estimation & assumption 1 1 28 Detail Schedule 1 1 29 Team review 1 1 30 Review 2 1 1 Executing 1 Define candidate architecture 2 1 3 2 Refine the architecture 1 1 3 Analyze behaviors 1 1 4 Complete analysis model 1 1 Complete design model & 5 system architecture 1 1 6 Design GUI 1 1 2 7 Design database 1 1 8 Design persistence layer 1 1 9 Design business logic layer 1 1 10 Design presentation layer 1 1 35