SlideShare una empresa de Scribd logo
1 de 10
Cost Estimation Cost Budgetting Work Authorization
Cost Estimating The cost estimate is prepared as follows: The types of estimate required is determined from the RFP, RFQ or other requestor. The estimating method(s) appropriate to the type of estimate, the program phase and information available are selected. The estimating team is formed, briefed on the estimate requirements and statement of work. Estimates are prepared using a “Basis of Estimate” (BOE) Form, and collected by the “estimate manager” – usually the proposal manager before contract award, and project manager afterwards.  Usually these estimates are expressed in a mixture of labour hours and dollars. The BOE forms are compiled, summarized, and submitted to the “Pricing” or “control accounting” function for the application of all additional Elements of Cost (EOC). If prepared for a proposal, “Profit” is applied to yield the proposal “priced estimate”.  Otherwise, this forms the basis for the program budget.
Types of Cost Estimates
Estimating Methods Similar approaches as used for schedule estimating Expert judgment  Analogous Parametric Probabilistic Estimates include both internal estimates and quotes from suppliers and sub-contractor Take care to subject external estimates to the same level of scrutiny as internal
Kicking off the Estimate Team  Preparing an estimate is “a project within a project”, with the following steps: The “estimate manager” – possibly marketing or business development for proposal, project manager after contract award – performs an initial review of the required RFP/SOW. Depending on the level of estimate required and complexity of work, manager pulls together “estimating” team of “experts”  Team performs review and estimates on BOE sheets, often supplemented by completion of a SOW compliance matrix for their aspects
Typical Basis-of-Estimate (BOE) Format 674-2435 Specific reference to proposal, contract or purchase order number WBS reference:  estimates are usually done at the lowest level of WBS definition available at the time of the estimate Occasionally, BOE’s may be done by functional group rather than WBS in order to provide clear accountability for the estimate, however, this is not preferred Estimator’s certification, and approval by related functional management Assures “ownership” of estimates by those who will need to support them Summary of the work being estimated, as well as applicable specifications Estimate methods used Estimates by task, activity or deliverable, broken out into impacted functions Allows for use in early resource planning Allows follow-up comparison to actuals to assess estimate accuracy Estimate assumptions May be derived from the SOW/RFP compliance matrix, but should be on the BOE in order to provide a “standalone” reference
Turning the Estimate into a Contract Price The estimates developed on the various Basis of Estimate forms are collected and added together – this gives the total labour, material and other costs exclusively associated with completing the project (ie. the “Direct Costs”) However, when deciding what price to charge the customer, these costs must be supplemented by the other “Elements of Cost” “Indirect Costs” – the “cost of doing business” Profit – the “charge” for the “added value” delivered
Elements of Cost ,[object Object]
Work conducted by dedicated program team
Material purchased to build program equipment and deliverables

Más contenido relacionado

La actualidad más candente

Cost baseline and cost budget
Cost baseline and cost budgetCost baseline and cost budget
Cost baseline and cost budgetMudassir Iqbal
 
Introduction to cost management & control in construction projects
Introduction to cost management & control in construction projectsIntroduction to cost management & control in construction projects
Introduction to cost management & control in construction projectsEssam Lotffy, PMP®, CCP®
 
Project planning and scheduling
Project planning and schedulingProject planning and scheduling
Project planning and schedulingadeel hamid
 
Project Management Definitions
Project Management DefinitionsProject Management Definitions
Project Management DefinitionsTURKI , PMP
 
Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...Shabaz Khan
 
Project management : Project Monitoring and Control by iFour Technolab Pvt. Ltd.
Project management : Project Monitoring and Control by iFour Technolab Pvt. Ltd.Project management : Project Monitoring and Control by iFour Technolab Pvt. Ltd.
Project management : Project Monitoring and Control by iFour Technolab Pvt. Ltd.iFour Institute - Sustainable Learning
 
TGE Project Controls
TGE Project ControlsTGE Project Controls
TGE Project ControlsDavid Mathews
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueChris Carson
 
Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...ijtsrd
 
Planning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessPlanning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessAlberto Sanchez
 
How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2Abdelhay Ghanem
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time AnalysisFarhan Moosa
 

La actualidad más candente (20)

Cost baseline and cost budget
Cost baseline and cost budgetCost baseline and cost budget
Cost baseline and cost budget
 
Introduction to cost management & control in construction projects
Introduction to cost management & control in construction projectsIntroduction to cost management & control in construction projects
Introduction to cost management & control in construction projects
 
Project planning and scheduling
Project planning and schedulingProject planning and scheduling
Project planning and scheduling
 
Project Management Definitions
Project Management DefinitionsProject Management Definitions
Project Management Definitions
 
Construction Management - New Trends
Construction Management - New TrendsConstruction Management - New Trends
Construction Management - New Trends
 
Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...
 
Project cost management
Project cost managementProject cost management
Project cost management
 
Cost Control Process for Construction
Cost Control Process for ConstructionCost Control Process for Construction
Cost Control Process for Construction
 
Project management : Project Monitoring and Control by iFour Technolab Pvt. Ltd.
Project management : Project Monitoring and Control by iFour Technolab Pvt. Ltd.Project management : Project Monitoring and Control by iFour Technolab Pvt. Ltd.
Project management : Project Monitoring and Control by iFour Technolab Pvt. Ltd.
 
ACH 216 Lecture 06 (Pre Construction Planning)
ACH 216 Lecture 06 (Pre Construction Planning)ACH 216 Lecture 06 (Pre Construction Planning)
ACH 216 Lecture 06 (Pre Construction Planning)
 
TGE Project Controls
TGE Project ControlsTGE Project Controls
TGE Project Controls
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned Value
 
Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...
 
Planning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessPlanning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning Process
 
How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2
 
Project control
Project controlProject control
Project control
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time Analysis
 
Extension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed IbarhimExtension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed Ibarhim
 
Project Schedule Management
Project Schedule ManagementProject Schedule Management
Project Schedule Management
 
Cost management
Cost managementCost management
Cost management
 

Similar a 3 pm3 c_2-%20estimating%20costs

con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptsheryl90
 
con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptsheryl90
 
Quality metrics in project management
Quality metrics in project managementQuality metrics in project management
Quality metrics in project managementselinasimpson1601
 
Cost management
Cost managementCost management
Cost managementshkadry
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1reddvise
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost managementImran Jamil
 
Software Project Cost Management and estimation
Software Project Cost Management and estimationSoftware Project Cost Management and estimation
Software Project Cost Management and estimationssuser9d62d6
 
CPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdfCPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdfDejeneTsegaye6
 
CPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdfCPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdfDejeneTsegaye6
 
Project Budget.pptx.ppt
Project Budget.pptx.pptProject Budget.pptx.ppt
Project Budget.pptx.pptDejeneTsegaye6
 
Estimation guidelines and templates
Estimation guidelines and templatesEstimation guidelines and templates
Estimation guidelines and templatesHoa PN Thaycacac
 
Preparing cost estimation
Preparing cost estimationPreparing cost estimation
Preparing cost estimationSomashekar S.M
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updatedShraddha PMP
 
L03 integration management
L03 integration managementL03 integration management
L03 integration managementAsa Chan
 
PMP Training - 04 project integration management
PMP Training - 04 project integration managementPMP Training - 04 project integration management
PMP Training - 04 project integration managementejlp12
 

Similar a 3 pm3 c_2-%20estimating%20costs (20)

con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.ppt
 
con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.ppt
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Quality metrics in project management
Quality metrics in project managementQuality metrics in project management
Quality metrics in project management
 
Cost management
Cost managementCost management
Cost management
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
 
Software Project Cost Management and estimation
Software Project Cost Management and estimationSoftware Project Cost Management and estimation
Software Project Cost Management and estimation
 
CPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdfCPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdf
 
CPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdfCPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdf
 
4. project cost management
4. project cost management4. project cost management
4. project cost management
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Project Budget.pptx.ppt
Project Budget.pptx.pptProject Budget.pptx.ppt
Project Budget.pptx.ppt
 
Construction Cost Control
Construction Cost ControlConstruction Cost Control
Construction Cost Control
 
Estimation guidelines and templates
Estimation guidelines and templatesEstimation guidelines and templates
Estimation guidelines and templates
 
Preparing cost estimation
Preparing cost estimationPreparing cost estimation
Preparing cost estimation
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updated
 
L03 integration management
L03 integration managementL03 integration management
L03 integration management
 
Chap005
Chap005Chap005
Chap005
 
PMP Training - 04 project integration management
PMP Training - 04 project integration managementPMP Training - 04 project integration management
PMP Training - 04 project integration management
 

Más de harwoodr

3 pm3 t_we%20-%20setting%20up%20the%20control%20account%20structure
3 pm3 t_we%20-%20setting%20up%20the%20control%20account%20structure3 pm3 t_we%20-%20setting%20up%20the%20control%20account%20structure
3 pm3 t_we%20-%20setting%20up%20the%20control%20account%20structureharwoodr
 
3 pm3 t_we%20-%20creating%20the%20schedule%20network
3 pm3 t_we%20-%20creating%20the%20schedule%20network3 pm3 t_we%20-%20creating%20the%20schedule%20network
3 pm3 t_we%20-%20creating%20the%20schedule%20networkharwoodr
 
3 pm3 t_we%20-%20creating%20a%20schedule%20that%20works
3 pm3 t_we%20-%20creating%20a%20schedule%20that%20works3 pm3 t_we%20-%20creating%20a%20schedule%20that%20works
3 pm3 t_we%20-%20creating%20a%20schedule%20that%20worksharwoodr
 
3 pm3 t_we%20-%20adding%20resources%20to%20the%20schedule
3 pm3 t_we%20-%20adding%20resources%20to%20the%20schedule3 pm3 t_we%20-%20adding%20resources%20to%20the%20schedule
3 pm3 t_we%20-%20adding%20resources%20to%20the%20scheduleharwoodr
 
3 pm3 t_4%20-%20schedule%20development
3 pm3 t_4%20-%20schedule%20development3 pm3 t_4%20-%20schedule%20development
3 pm3 t_4%20-%20schedule%20developmentharwoodr
 
3 pm3 t_3%20-%20activity%20resource%20estimating
3 pm3 t_3%20-%20activity%20resource%20estimating3 pm3 t_3%20-%20activity%20resource%20estimating
3 pm3 t_3%20-%20activity%20resource%20estimatingharwoodr
 
3 pm3 t_2%20-%20activity%20duration%20estimating
3 pm3 t_2%20-%20activity%20duration%20estimating3 pm3 t_2%20-%20activity%20duration%20estimating
3 pm3 t_2%20-%20activity%20duration%20estimatingharwoodr
 
3 pm3 t_1%20-%20activity%20sequencing
3 pm3 t_1%20-%20activity%20sequencing3 pm3 t_1%20-%20activity%20sequencing
3 pm3 t_1%20-%20activity%20sequencingharwoodr
 
3 pm3 c_5%20-%20work%20authorization
3 pm3 c_5%20-%20work%20authorization3 pm3 c_5%20-%20work%20authorization
3 pm3 c_5%20-%20work%20authorizationharwoodr
 
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budgetharwoodr
 
3 pm3 c_3%20-%20the%20program%20budget
3 pm3 c_3%20-%20the%20program%20budget3 pm3 c_3%20-%20the%20program%20budget
3 pm3 c_3%20-%20the%20program%20budgetharwoodr
 
3 pm3 c_1%20-%20developing%20the%20cost%20plan
3 pm3 c_1%20-%20developing%20the%20cost%20plan3 pm3 c_1%20-%20developing%20the%20cost%20plan
3 pm3 c_1%20-%20developing%20the%20cost%20planharwoodr
 

Más de harwoodr (13)

3 pm3 t_we%20-%20setting%20up%20the%20control%20account%20structure
3 pm3 t_we%20-%20setting%20up%20the%20control%20account%20structure3 pm3 t_we%20-%20setting%20up%20the%20control%20account%20structure
3 pm3 t_we%20-%20setting%20up%20the%20control%20account%20structure
 
3 pm3 t_we%20-%20creating%20the%20schedule%20network
3 pm3 t_we%20-%20creating%20the%20schedule%20network3 pm3 t_we%20-%20creating%20the%20schedule%20network
3 pm3 t_we%20-%20creating%20the%20schedule%20network
 
3 pm3 t_we%20-%20creating%20a%20schedule%20that%20works
3 pm3 t_we%20-%20creating%20a%20schedule%20that%20works3 pm3 t_we%20-%20creating%20a%20schedule%20that%20works
3 pm3 t_we%20-%20creating%20a%20schedule%20that%20works
 
3 pm3 t_we%20-%20adding%20resources%20to%20the%20schedule
3 pm3 t_we%20-%20adding%20resources%20to%20the%20schedule3 pm3 t_we%20-%20adding%20resources%20to%20the%20schedule
3 pm3 t_we%20-%20adding%20resources%20to%20the%20schedule
 
3 pm3 t_4%20-%20schedule%20development
3 pm3 t_4%20-%20schedule%20development3 pm3 t_4%20-%20schedule%20development
3 pm3 t_4%20-%20schedule%20development
 
3 pm3 t_3%20-%20activity%20resource%20estimating
3 pm3 t_3%20-%20activity%20resource%20estimating3 pm3 t_3%20-%20activity%20resource%20estimating
3 pm3 t_3%20-%20activity%20resource%20estimating
 
3 pm3 t_2%20-%20activity%20duration%20estimating
3 pm3 t_2%20-%20activity%20duration%20estimating3 pm3 t_2%20-%20activity%20duration%20estimating
3 pm3 t_2%20-%20activity%20duration%20estimating
 
3 pm3 t_1%20-%20activity%20sequencing
3 pm3 t_1%20-%20activity%20sequencing3 pm3 t_1%20-%20activity%20sequencing
3 pm3 t_1%20-%20activity%20sequencing
 
3 pm3 c_5%20-%20work%20authorization
3 pm3 c_5%20-%20work%20authorization3 pm3 c_5%20-%20work%20authorization
3 pm3 c_5%20-%20work%20authorization
 
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget
 
3 pm3 c_3%20-%20the%20program%20budget
3 pm3 c_3%20-%20the%20program%20budget3 pm3 c_3%20-%20the%20program%20budget
3 pm3 c_3%20-%20the%20program%20budget
 
3 pm3 c_1%20-%20developing%20the%20cost%20plan
3 pm3 c_1%20-%20developing%20the%20cost%20plan3 pm3 c_1%20-%20developing%20the%20cost%20plan
3 pm3 c_1%20-%20developing%20the%20cost%20plan
 
PHP games
PHP gamesPHP games
PHP games
 

Último

🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘RTylerCroy
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking MenDelhi Call girls
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024The Digital Insurer
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...apidays
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...Martijn de Jong
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityPrincipled Technologies
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking MenDelhi Call girls
 
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUnderstanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUK Journal
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfEnterprise Knowledge
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024The Digital Insurer
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024The Digital Insurer
 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEarley Information Science
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsMaria Levchenko
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptxHampshireHUG
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxKatpro Technologies
 
CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Servicegiselly40
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking MenDelhi Call girls
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...Neo4j
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)Gabriella Davis
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Scriptwesley chun
 

Último (20)

🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivity
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUnderstanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024
 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed texts
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
 
CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Service
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Script
 

3 pm3 c_2-%20estimating%20costs

  • 1. Cost Estimation Cost Budgetting Work Authorization
  • 2. Cost Estimating The cost estimate is prepared as follows: The types of estimate required is determined from the RFP, RFQ or other requestor. The estimating method(s) appropriate to the type of estimate, the program phase and information available are selected. The estimating team is formed, briefed on the estimate requirements and statement of work. Estimates are prepared using a “Basis of Estimate” (BOE) Form, and collected by the “estimate manager” – usually the proposal manager before contract award, and project manager afterwards. Usually these estimates are expressed in a mixture of labour hours and dollars. The BOE forms are compiled, summarized, and submitted to the “Pricing” or “control accounting” function for the application of all additional Elements of Cost (EOC). If prepared for a proposal, “Profit” is applied to yield the proposal “priced estimate”. Otherwise, this forms the basis for the program budget.
  • 3. Types of Cost Estimates
  • 4. Estimating Methods Similar approaches as used for schedule estimating Expert judgment Analogous Parametric Probabilistic Estimates include both internal estimates and quotes from suppliers and sub-contractor Take care to subject external estimates to the same level of scrutiny as internal
  • 5. Kicking off the Estimate Team Preparing an estimate is “a project within a project”, with the following steps: The “estimate manager” – possibly marketing or business development for proposal, project manager after contract award – performs an initial review of the required RFP/SOW. Depending on the level of estimate required and complexity of work, manager pulls together “estimating” team of “experts” Team performs review and estimates on BOE sheets, often supplemented by completion of a SOW compliance matrix for their aspects
  • 6. Typical Basis-of-Estimate (BOE) Format 674-2435 Specific reference to proposal, contract or purchase order number WBS reference: estimates are usually done at the lowest level of WBS definition available at the time of the estimate Occasionally, BOE’s may be done by functional group rather than WBS in order to provide clear accountability for the estimate, however, this is not preferred Estimator’s certification, and approval by related functional management Assures “ownership” of estimates by those who will need to support them Summary of the work being estimated, as well as applicable specifications Estimate methods used Estimates by task, activity or deliverable, broken out into impacted functions Allows for use in early resource planning Allows follow-up comparison to actuals to assess estimate accuracy Estimate assumptions May be derived from the SOW/RFP compliance matrix, but should be on the BOE in order to provide a “standalone” reference
  • 7. Turning the Estimate into a Contract Price The estimates developed on the various Basis of Estimate forms are collected and added together – this gives the total labour, material and other costs exclusively associated with completing the project (ie. the “Direct Costs”) However, when deciding what price to charge the customer, these costs must be supplemented by the other “Elements of Cost” “Indirect Costs” – the “cost of doing business” Profit – the “charge” for the “added value” delivered
  • 8.
  • 9. Work conducted by dedicated program team
  • 10. Material purchased to build program equipment and deliverables
  • 11. Contract costs of sub-contracts performed for the program
  • 12. Indirect: (applied by “Pricing” function)The “cost of doing business” for the business as a whole must be paid for by its “revenue generating” activities. This is done by calculating and applying “Overhead” rates to the Direct costs. Examples:
  • 13. Total annual costs of secretarial, accounting, HS&E etc. staff divided by annual “direct” costs of all projects – rate applied against future project direct costs (eg. Add 50% to all direct labour hours)
  • 14. Total material handling costs (labour, facilities, equipment) applied as an overhead to direct material costs
  • 15.
  • 16.
  • 17. revise budget allocation and work authorization