Project Costing
             Hitesh Gupta
              11/09/2012
Direct Costs                           Indirect Costs
Can be identified specifically with a       Incurred for common or joint objectives &
particular sponsored project                can’t be identified readily & specifically
                                            with a particular sponsored project
E.g if company produces artisan
furniture, cost of wood & cost of
craftsperson
                                            Can be controlled by efficient
                                            engineering, proficient staff, construction
Can be controlled by good supervision and
                                            time, etc
job control



                                            Costs like
                                            advertising, depreciation, general supplies
Includes Direct labour, Repair labour,
                                            for firm, accounting services, Office
Operating costs of equipments, Supplies,
                                            Payroll and expense, Property taxes etc
Permanent materials, Subcontract costs
Dealing with Contingency items for cost estimation
Occurrence:

•May or May not occur

Contingency Exposure

•Minor to Maximum amount,
•Can’t be estimated

Dealing :

• Should be computed & listed separately but not in actual estimates
• Markup decided if max cost explained to contractor




Minimizing effect :

•If specifications contain: force-majeure (e.g., war, strike etc) unforeseen condition (e.g.
Irregular final rock surface) clauses
•Builders All-Risk Insurance
Dealing with Escalation items for cost estimation

Increase in cost during construction

• Project risks may escalate more than reasonable estimation
• Consists of total project labour costs and permanent material costs




Labour Costs

•Unescalated labour costs * % increase in labour cost ( reviewing labour contracts,
reviewing trends in particular craft, overall wage increase throughout country etc)




Material Costs

• Minor costs as quotations will be firm for life of project.
•Escalation in material be determined after receipt
•Computation performed same as labour
Relevance of making cash flows for cost estimation
Cash Forecast prepared:

•To establish capital requirements – For purchasing
construction P&M, insurance, etc

•To estimate interest expense - Interest on capital invested

•To analyze, & select investment projects where expected returns
extend beyond 1 year.

• To gauge time to completion (more time = more overheads)

• To estimate initial investment/cost required
Relevance of calculating cost of promoter’s
           funds in final estimate


Loan/Debt Requirement
   •Future interest payments



Cost of Capital –
   •Opportunity Cost


Employer’s Cost
   •For future pricing/tariffs



Risk involved Project
Process followed for selecting method of
                  excavation
     Examining                                    Explanation

Nature of subsoil       affect type of machine used and the necessity of soil protection.


Size of excavation      affect type of machine used & method to excavate.


Scale of work           large volume of excavation may involve complicated phasing
                        arrangement & work planning


Ground water            affect degree of protection (watertight sheet piling or dewatering
condition               may required.)

Surrounding condition   impose certain restrictions and precautions (eg. diversion of
                        government drain, or underpinning work to nearby building
                        foundation)
Deciding Mark-Up
Project Characteristics
    • Size, Cash flow, Location etc

Company’s Characteristics
   • Past Profit, Current Workload, Experience etc

Economic Environment
   • Labour availability, Tax, Economy etc

Project Documentation
    • Type of Contract, Completeness of documents,
    •Pre-qualification, number of competitors etc.


                             Refinement Required

Across-the-Board Markup vs Differential Markup
    • Mark-up should be allocated to each cost

Cash flow-based model to calculate Mark-Up
   • Mark-Up (Percent) = (PV of disbursements/PV of receipts) -1 (*100)
Costs involved in different forms of Guarantees

Bid bond or tender bond
•Bid bonds are usually issued for 1% to 5%


Performance bond
•After tender is accepted
•Replace bid bond
•10% to 20% contract amount



Retention bond
• Client may withhold 5%-10% of contract amount



Payment guarantee
•Ensures payment to contractor
Insurance policies available for covering Contractor’s Risk

Employers Liability Insurance (EL)
• Aagainst liability for injury or disease to employees
Third party or Public Liability Insurance (PL) -
•Someone suffering loss not party to insurance contract.
•Depends on amount & scope of works

Contract Works Insurance (CW) -
•Covers costs of losses and damages of works undertaken
•e.g. flooding a completed property or burning down a newly built house.


Professional Indemnity Insurance (PI) -
• Covers incorrect design of part of works
•e.g. drainage system.


Tools and Temporary Works Insurance (TTW)


All Risk Insurance (AR) -
Covers all other losses
Points of major differences of cost calculations that occurred between
             joint venture partners of Sierra Tunnel Project

               (Cost for New Machinery Vs Used P&M)

Plant and Machinery
    •Net charge would reduce


Maintenance
    •Cost more to maintain used machinery


Estimated Production
    •Decrease


Interest cost
     •Decrease as there is no purchase


Excavation cost
   •Increase
Relevance of Project Accounting understanding in Project Costing

              With reference to IAS 7 (statement of cash flows)

Developing the Budget

    •Identifying Cost Accounts (interest charges, rental expenses, taxes, etc.)
    •Developing a Schedule of Cost Accounts
    •Making a Forecast Estimate

Monitoring Budget Implementation - Cash Flow Status Report

    •Provides a summary for monitoring the cash inflows and outflows.
    •Manager will be able to perceive if budget is being closely implemented
    • If cash inflow coming from the client is timely and sufficient.


Evaluating Financial Reports

    •Disclose fund adequacy or inadequacy
    •Negative results would prompt contractor to thresh-out matter with client before
    proceeding with project
Relevance of ABC costing for Infrastructure development business



                  Projects use ABC costing in some form
Provides a Clear Understanding of Processes
    • provide better understanding of processes performed
    • how processes react to different inputs & variables.

Assign Cost to Activities

    • Identify activities & assign costs to them
    • Identify cost drivers associated with activities
    • Assign costs to projects (by cost driver rate * volume of cost driver units
    consumed by project)

Technique adopted for project budgets

    • Identify sources of cost-drivers/project costs
    • Help in indentifying control measures
Thanks

Más contenido relacionado

La actualidad más candente

Reduction of cost in construction
Reduction of cost in constructionReduction of cost in construction
Reduction of cost in constructionSaravana murthy
 
Bba ii cost and management accounting u 3.3 contract costing
Bba ii cost and management accounting u 3.3 contract costingBba ii cost and management accounting u 3.3 contract costing
Bba ii cost and management accounting u 3.3 contract costingRai University
 
10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation StepsSHAZEBALIKHAN1
 
COST ANALYSIS (Brief overview)
COST ANALYSIS (Brief overview)COST ANALYSIS (Brief overview)
COST ANALYSIS (Brief overview)Archit Aditya
 
Key Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionKey Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionWaleed Liaqat
 
Job,batch and contract costing
Job,batch and contract costingJob,batch and contract costing
Job,batch and contract costingCollen Mahambo
 
Project Management 5 Cost Management
Project Management 5 Cost ManagementProject Management 5 Cost Management
Project Management 5 Cost Managementgrmkslideshare
 
Sample cost control training proposal
Sample cost control training proposalSample cost control training proposal
Sample cost control training proposalSadegh Yazdani
 
Contract costing, BCOM (HONS)
Contract costing, BCOM (HONS)Contract costing, BCOM (HONS)
Contract costing, BCOM (HONS)AmarnathRana1
 
Cost management in Buildings
Cost management in BuildingsCost management in Buildings
Cost management in BuildingsJIT KUMAR GUPTA
 

La actualidad más candente (19)

Contract Costing
Contract CostingContract Costing
Contract Costing
 
Reduction of cost in construction
Reduction of cost in constructionReduction of cost in construction
Reduction of cost in construction
 
Bba ii cost and management accounting u 3.3 contract costing
Bba ii cost and management accounting u 3.3 contract costingBba ii cost and management accounting u 3.3 contract costing
Bba ii cost and management accounting u 3.3 contract costing
 
10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps
 
COST ANALYSIS (Brief overview)
COST ANALYSIS (Brief overview)COST ANALYSIS (Brief overview)
COST ANALYSIS (Brief overview)
 
PMP Session 3
PMP Session 3PMP Session 3
PMP Session 3
 
Key Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionKey Components of Cost Estimation in construction
Key Components of Cost Estimation in construction
 
Contract costing
Contract costingContract costing
Contract costing
 
Cost estimation techniques
Cost estimation techniquesCost estimation techniques
Cost estimation techniques
 
Contract costing
Contract costingContract costing
Contract costing
 
Job,batch and contract costing
Job,batch and contract costingJob,batch and contract costing
Job,batch and contract costing
 
cost-estimation-tutorial
cost-estimation-tutorialcost-estimation-tutorial
cost-estimation-tutorial
 
Project Management 5 Cost Management
Project Management 5 Cost ManagementProject Management 5 Cost Management
Project Management 5 Cost Management
 
Questions in notes
Questions in notesQuestions in notes
Questions in notes
 
Preparation of boq
Preparation of boqPreparation of boq
Preparation of boq
 
Sample cost control training proposal
Sample cost control training proposalSample cost control training proposal
Sample cost control training proposal
 
Contract costing, BCOM (HONS)
Contract costing, BCOM (HONS)Contract costing, BCOM (HONS)
Contract costing, BCOM (HONS)
 
Cost management in Buildings
Cost management in BuildingsCost management in Buildings
Cost management in Buildings
 
Contract costing
Contract costingContract costing
Contract costing
 

Destacado

Oracle Project Costing - How to resolve Transaction Import Error
Oracle Project Costing - How to resolve Transaction Import ErrorOracle Project Costing - How to resolve Transaction Import Error
Oracle Project Costing - How to resolve Transaction Import Errorgoelrajesh
 
Day1 1410-1455-pearl2-vijaysane-131009043034-phpapp02
Day1 1410-1455-pearl2-vijaysane-131009043034-phpapp02Day1 1410-1455-pearl2-vijaysane-131009043034-phpapp02
Day1 1410-1455-pearl2-vijaysane-131009043034-phpapp02PMI_IREP_TP
 
The Time is Now - Beyond Budgeting in the Enterprise
The Time is Now - Beyond Budgeting in the EnterpriseThe Time is Now - Beyond Budgeting in the Enterprise
The Time is Now - Beyond Budgeting in the EnterpriseIntel Security
 
Translating Points to Dollars
Translating Points to Dollars Translating Points to Dollars
Translating Points to Dollars Brent Barton
 
E-Business Suite 1 | Jeannie Dobney | Oracle Project Management for Users of ...
E-Business Suite 1 | Jeannie Dobney | Oracle Project Management for Users of ...E-Business Suite 1 | Jeannie Dobney | Oracle Project Management for Users of ...
E-Business Suite 1 | Jeannie Dobney | Oracle Project Management for Users of ...InSync2011
 
Forecast it - Agile in distributed teams - AgilityLab
Forecast it - Agile in distributed teams - AgilityLabForecast it - Agile in distributed teams - AgilityLab
Forecast it - Agile in distributed teams - AgilityLabDennis Kayser
 
R12.2.2 oracle projects cost break down structure overview
R12.2.2 oracle projects cost break down structure overviewR12.2.2 oracle projects cost break down structure overview
R12.2.2 oracle projects cost break down structure overviewMatthew Bezuidenhout
 
Composting process and organic fertilizers production
Composting process and organic fertilizers productionComposting process and organic fertilizers production
Composting process and organic fertilizers productionSuhardiyoto Haryadi
 
Oracle R12.1.3 Costing Overview
Oracle R12.1.3 Costing OverviewOracle R12.1.3 Costing Overview
Oracle R12.1.3 Costing OverviewPritesh Mogane
 
Business opportunity bio fertilizer plant
Business opportunity   bio fertilizer plantBusiness opportunity   bio fertilizer plant
Business opportunity bio fertilizer plantvaibhavtuls
 
How to Start Organic Farming Business (Cultivation of Mushroom, Crop, Cotton,...
How to Start Organic Farming Business (Cultivation of Mushroom, Crop, Cotton,...How to Start Organic Farming Business (Cultivation of Mushroom, Crop, Cotton,...
How to Start Organic Farming Business (Cultivation of Mushroom, Crop, Cotton,...Ajjay Kumar Gupta
 
Oracle Fixed assets ivas
Oracle Fixed assets ivasOracle Fixed assets ivas
Oracle Fixed assets ivasAli Ibrahim
 
Track Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementBaroness PM
 
Production of Biofertilizers and Organic Farming - Food and Agriculture
Production of Biofertilizers and Organic Farming - Food and AgricultureProduction of Biofertilizers and Organic Farming - Food and Agriculture
Production of Biofertilizers and Organic Farming - Food and AgricultureAjjay Kumar Gupta
 

Destacado (20)

Oracle Project Costing - How to resolve Transaction Import Error
Oracle Project Costing - How to resolve Transaction Import ErrorOracle Project Costing - How to resolve Transaction Import Error
Oracle Project Costing - How to resolve Transaction Import Error
 
Day1 1410-1455-pearl2-vijaysane-131009043034-phpapp02
Day1 1410-1455-pearl2-vijaysane-131009043034-phpapp02Day1 1410-1455-pearl2-vijaysane-131009043034-phpapp02
Day1 1410-1455-pearl2-vijaysane-131009043034-phpapp02
 
The Time is Now - Beyond Budgeting in the Enterprise
The Time is Now - Beyond Budgeting in the EnterpriseThe Time is Now - Beyond Budgeting in the Enterprise
The Time is Now - Beyond Budgeting in the Enterprise
 
Translating Points to Dollars
Translating Points to Dollars Translating Points to Dollars
Translating Points to Dollars
 
E-Business Suite 1 | Jeannie Dobney | Oracle Project Management for Users of ...
E-Business Suite 1 | Jeannie Dobney | Oracle Project Management for Users of ...E-Business Suite 1 | Jeannie Dobney | Oracle Project Management for Users of ...
E-Business Suite 1 | Jeannie Dobney | Oracle Project Management for Users of ...
 
Fixed assets-set-up
Fixed assets-set-upFixed assets-set-up
Fixed assets-set-up
 
Oracle fixed assets
Oracle fixed assetsOracle fixed assets
Oracle fixed assets
 
Forecast it - Agile in distributed teams - AgilityLab
Forecast it - Agile in distributed teams - AgilityLabForecast it - Agile in distributed teams - AgilityLab
Forecast it - Agile in distributed teams - AgilityLab
 
Organic fertilizers
Organic fertilizersOrganic fertilizers
Organic fertilizers
 
Compost, oganic matter
Compost, oganic matterCompost, oganic matter
Compost, oganic matter
 
R12.2.2 oracle projects cost break down structure overview
R12.2.2 oracle projects cost break down structure overviewR12.2.2 oracle projects cost break down structure overview
R12.2.2 oracle projects cost break down structure overview
 
Organic Fertilizer
Organic FertilizerOrganic Fertilizer
Organic Fertilizer
 
Composting process and organic fertilizers production
Composting process and organic fertilizers productionComposting process and organic fertilizers production
Composting process and organic fertilizers production
 
Oracle R12.1.3 Costing Overview
Oracle R12.1.3 Costing OverviewOracle R12.1.3 Costing Overview
Oracle R12.1.3 Costing Overview
 
Business opportunity bio fertilizer plant
Business opportunity   bio fertilizer plantBusiness opportunity   bio fertilizer plant
Business opportunity bio fertilizer plant
 
How to Start Organic Farming Business (Cultivation of Mushroom, Crop, Cotton,...
How to Start Organic Farming Business (Cultivation of Mushroom, Crop, Cotton,...How to Start Organic Farming Business (Cultivation of Mushroom, Crop, Cotton,...
How to Start Organic Farming Business (Cultivation of Mushroom, Crop, Cotton,...
 
Oracle Fixed assets ivas
Oracle Fixed assets ivasOracle Fixed assets ivas
Oracle Fixed assets ivas
 
Track Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value Management
 
Production of Biofertilizers and Organic Farming - Food and Agriculture
Production of Biofertilizers and Organic Farming - Food and AgricultureProduction of Biofertilizers and Organic Farming - Food and Agriculture
Production of Biofertilizers and Organic Farming - Food and Agriculture
 
Organic fertilizers
Organic fertilizersOrganic fertilizers
Organic fertilizers
 

Similar a Pmc hitesh

Economic consideration
Economic considerationEconomic consideration
Economic considerationMalavika M R
 
Charging of Engineering Services.pptx
Charging of Engineering Services.pptxCharging of Engineering Services.pptx
Charging of Engineering Services.pptxLovelynCosicol
 
Quantity Survey and Estimation basic terms
Quantity Survey and Estimation basic termsQuantity Survey and Estimation basic terms
Quantity Survey and Estimation basic termsmeghajain275
 
Turnkey implementation of distribution projects
Turnkey implementation of distribution projectsTurnkey implementation of distribution projects
Turnkey implementation of distribution projectsD.Pawan Kumar
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost ManagementBhuWan Khadka
 
Renewable Energy Feed-in Tarriff presentation
Renewable Energy Feed-in Tarriff presentationRenewable Energy Feed-in Tarriff presentation
Renewable Energy Feed-in Tarriff presentationJerry Sakala
 
Software Project Cost Management and estimation
Software Project Cost Management and estimationSoftware Project Cost Management and estimation
Software Project Cost Management and estimationssuser9d62d6
 
con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptsheryl90
 
con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptsheryl90
 
Procurement Strategies: A Seminar
Procurement Strategies: A SeminarProcurement Strategies: A Seminar
Procurement Strategies: A SeminarPang Khai Shuen
 

Similar a Pmc hitesh (20)

Economic consideration
Economic considerationEconomic consideration
Economic consideration
 
Charging of Engineering Services.pptx
Charging of Engineering Services.pptxCharging of Engineering Services.pptx
Charging of Engineering Services.pptx
 
Questions in notes
Questions in notesQuestions in notes
Questions in notes
 
Questions in notes
Questions in notesQuestions in notes
Questions in notes
 
EstimatesPresentation.pptx
EstimatesPresentation.pptxEstimatesPresentation.pptx
EstimatesPresentation.pptx
 
Quantity Survey and Estimation basic terms
Quantity Survey and Estimation basic termsQuantity Survey and Estimation basic terms
Quantity Survey and Estimation basic terms
 
Project Cost Management for IEM talk on 13 January 2018.
Project Cost Management  for IEM talk on 13 January 2018.Project Cost Management  for IEM talk on 13 January 2018.
Project Cost Management for IEM talk on 13 January 2018.
 
Project cost management
Project cost management Project cost management
Project cost management
 
Contract costing
Contract costingContract costing
Contract costing
 
Total-Project-Cost.pptx
Total-Project-Cost.pptxTotal-Project-Cost.pptx
Total-Project-Cost.pptx
 
Turnkey implementation of distribution projects
Turnkey implementation of distribution projectsTurnkey implementation of distribution projects
Turnkey implementation of distribution projects
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost Management
 
Aiab089228
Aiab089228Aiab089228
Aiab089228
 
Renewable Energy Feed-in Tarriff presentation
Renewable Energy Feed-in Tarriff presentationRenewable Energy Feed-in Tarriff presentation
Renewable Energy Feed-in Tarriff presentation
 
Software Project Cost Management and estimation
Software Project Cost Management and estimationSoftware Project Cost Management and estimation
Software Project Cost Management and estimation
 
ESTIMATING.pdf
ESTIMATING.pdfESTIMATING.pdf
ESTIMATING.pdf
 
con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.ppt
 
con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.ppt
 
uap doc 207-208
uap doc 207-208uap doc 207-208
uap doc 207-208
 
Procurement Strategies: A Seminar
Procurement Strategies: A SeminarProcurement Strategies: A Seminar
Procurement Strategies: A Seminar
 

Último

GOODSANDSERVICETAX IN INDIAN ECONOMY IMPACT
GOODSANDSERVICETAX IN INDIAN ECONOMY IMPACTGOODSANDSERVICETAX IN INDIAN ECONOMY IMPACT
GOODSANDSERVICETAX IN INDIAN ECONOMY IMPACTharshitverma1762
 
Amil Baba In Pakistan amil baba in Lahore amil baba in Islamabad amil baba in...
Amil Baba In Pakistan amil baba in Lahore amil baba in Islamabad amil baba in...Amil Baba In Pakistan amil baba in Lahore amil baba in Islamabad amil baba in...
Amil Baba In Pakistan amil baba in Lahore amil baba in Islamabad amil baba in...amilabibi1
 
Managing Finances in a Small Business (yes).pdf
Managing Finances  in a Small Business (yes).pdfManaging Finances  in a Small Business (yes).pdf
Managing Finances in a Small Business (yes).pdfmar yame
 
NO1 Certified Ilam kala Jadu Specialist Expert In Bahawalpur, Sargodha, Sialk...
NO1 Certified Ilam kala Jadu Specialist Expert In Bahawalpur, Sargodha, Sialk...NO1 Certified Ilam kala Jadu Specialist Expert In Bahawalpur, Sargodha, Sialk...
NO1 Certified Ilam kala Jadu Specialist Expert In Bahawalpur, Sargodha, Sialk...Amil Baba Dawood bangali
 
Classical Theory of Macroeconomics by Adam Smith
Classical Theory of Macroeconomics by Adam SmithClassical Theory of Macroeconomics by Adam Smith
Classical Theory of Macroeconomics by Adam SmithAdamYassin2
 
《加拿大本地办假证-寻找办理Dalhousie毕业证和达尔豪斯大学毕业证书的中介代理》
《加拿大本地办假证-寻找办理Dalhousie毕业证和达尔豪斯大学毕业证书的中介代理》《加拿大本地办假证-寻找办理Dalhousie毕业证和达尔豪斯大学毕业证书的中介代理》
《加拿大本地办假证-寻找办理Dalhousie毕业证和达尔豪斯大学毕业证书的中介代理》rnrncn29
 
Economics, Commerce and Trade Management: An International Journal (ECTIJ)
Economics, Commerce and Trade Management: An International Journal (ECTIJ)Economics, Commerce and Trade Management: An International Journal (ECTIJ)
Economics, Commerce and Trade Management: An International Journal (ECTIJ)ECTIJ
 
Stock Market Brief Deck for 4/24/24 .pdf
Stock Market Brief Deck for 4/24/24 .pdfStock Market Brief Deck for 4/24/24 .pdf
Stock Market Brief Deck for 4/24/24 .pdfMichael Silva
 
call girls in Nand Nagri (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in  Nand Nagri (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in  Nand Nagri (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Nand Nagri (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
fca-bsps-decision-letter-redacted (1).pdf
fca-bsps-decision-letter-redacted (1).pdffca-bsps-decision-letter-redacted (1).pdf
fca-bsps-decision-letter-redacted (1).pdfHenry Tapper
 
government_intervention_in_business_ownership[1].pdf
government_intervention_in_business_ownership[1].pdfgovernment_intervention_in_business_ownership[1].pdf
government_intervention_in_business_ownership[1].pdfshaunmashale756
 
Tenets of Physiocracy History of Economic
Tenets of Physiocracy History of EconomicTenets of Physiocracy History of Economic
Tenets of Physiocracy History of Economiccinemoviesu
 
The Core Functions of the Bangko Sentral ng Pilipinas
The Core Functions of the Bangko Sentral ng PilipinasThe Core Functions of the Bangko Sentral ng Pilipinas
The Core Functions of the Bangko Sentral ng PilipinasCherylouCamus
 
2024 Q1 Crypto Industry Report | CoinGecko
2024 Q1 Crypto Industry Report | CoinGecko2024 Q1 Crypto Industry Report | CoinGecko
2024 Q1 Crypto Industry Report | CoinGeckoCoinGecko
 
Governor Olli Rehn: Dialling back monetary restraint
Governor Olli Rehn: Dialling back monetary restraintGovernor Olli Rehn: Dialling back monetary restraint
Governor Olli Rehn: Dialling back monetary restraintSuomen Pankki
 
(办理学位证)美国加州州立大学东湾分校毕业证成绩单原版一比一
(办理学位证)美国加州州立大学东湾分校毕业证成绩单原版一比一(办理学位证)美国加州州立大学东湾分校毕业证成绩单原版一比一
(办理学位证)美国加州州立大学东湾分校毕业证成绩单原版一比一S SDS
 
Bladex 1Q24 Earning Results Presentation
Bladex 1Q24 Earning Results PresentationBladex 1Q24 Earning Results Presentation
Bladex 1Q24 Earning Results PresentationBladex
 

Último (20)

GOODSANDSERVICETAX IN INDIAN ECONOMY IMPACT
GOODSANDSERVICETAX IN INDIAN ECONOMY IMPACTGOODSANDSERVICETAX IN INDIAN ECONOMY IMPACT
GOODSANDSERVICETAX IN INDIAN ECONOMY IMPACT
 
Amil Baba In Pakistan amil baba in Lahore amil baba in Islamabad amil baba in...
Amil Baba In Pakistan amil baba in Lahore amil baba in Islamabad amil baba in...Amil Baba In Pakistan amil baba in Lahore amil baba in Islamabad amil baba in...
Amil Baba In Pakistan amil baba in Lahore amil baba in Islamabad amil baba in...
 
Managing Finances in a Small Business (yes).pdf
Managing Finances  in a Small Business (yes).pdfManaging Finances  in a Small Business (yes).pdf
Managing Finances in a Small Business (yes).pdf
 
NO1 Certified Ilam kala Jadu Specialist Expert In Bahawalpur, Sargodha, Sialk...
NO1 Certified Ilam kala Jadu Specialist Expert In Bahawalpur, Sargodha, Sialk...NO1 Certified Ilam kala Jadu Specialist Expert In Bahawalpur, Sargodha, Sialk...
NO1 Certified Ilam kala Jadu Specialist Expert In Bahawalpur, Sargodha, Sialk...
 
Classical Theory of Macroeconomics by Adam Smith
Classical Theory of Macroeconomics by Adam SmithClassical Theory of Macroeconomics by Adam Smith
Classical Theory of Macroeconomics by Adam Smith
 
Q1 2024 Newsletter | Financial Synergies Wealth Advisors
Q1 2024 Newsletter | Financial Synergies Wealth AdvisorsQ1 2024 Newsletter | Financial Synergies Wealth Advisors
Q1 2024 Newsletter | Financial Synergies Wealth Advisors
 
《加拿大本地办假证-寻找办理Dalhousie毕业证和达尔豪斯大学毕业证书的中介代理》
《加拿大本地办假证-寻找办理Dalhousie毕业证和达尔豪斯大学毕业证书的中介代理》《加拿大本地办假证-寻找办理Dalhousie毕业证和达尔豪斯大学毕业证书的中介代理》
《加拿大本地办假证-寻找办理Dalhousie毕业证和达尔豪斯大学毕业证书的中介代理》
 
Economics, Commerce and Trade Management: An International Journal (ECTIJ)
Economics, Commerce and Trade Management: An International Journal (ECTIJ)Economics, Commerce and Trade Management: An International Journal (ECTIJ)
Economics, Commerce and Trade Management: An International Journal (ECTIJ)
 
Stock Market Brief Deck for 4/24/24 .pdf
Stock Market Brief Deck for 4/24/24 .pdfStock Market Brief Deck for 4/24/24 .pdf
Stock Market Brief Deck for 4/24/24 .pdf
 
call girls in Nand Nagri (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in  Nand Nagri (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in  Nand Nagri (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Nand Nagri (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
fca-bsps-decision-letter-redacted (1).pdf
fca-bsps-decision-letter-redacted (1).pdffca-bsps-decision-letter-redacted (1).pdf
fca-bsps-decision-letter-redacted (1).pdf
 
government_intervention_in_business_ownership[1].pdf
government_intervention_in_business_ownership[1].pdfgovernment_intervention_in_business_ownership[1].pdf
government_intervention_in_business_ownership[1].pdf
 
Monthly Economic Monitoring of Ukraine No 231, April 2024
Monthly Economic Monitoring of Ukraine No 231, April 2024Monthly Economic Monitoring of Ukraine No 231, April 2024
Monthly Economic Monitoring of Ukraine No 231, April 2024
 
🔝+919953056974 🔝young Delhi Escort service Pusa Road
🔝+919953056974 🔝young Delhi Escort service Pusa Road🔝+919953056974 🔝young Delhi Escort service Pusa Road
🔝+919953056974 🔝young Delhi Escort service Pusa Road
 
Tenets of Physiocracy History of Economic
Tenets of Physiocracy History of EconomicTenets of Physiocracy History of Economic
Tenets of Physiocracy History of Economic
 
The Core Functions of the Bangko Sentral ng Pilipinas
The Core Functions of the Bangko Sentral ng PilipinasThe Core Functions of the Bangko Sentral ng Pilipinas
The Core Functions of the Bangko Sentral ng Pilipinas
 
2024 Q1 Crypto Industry Report | CoinGecko
2024 Q1 Crypto Industry Report | CoinGecko2024 Q1 Crypto Industry Report | CoinGecko
2024 Q1 Crypto Industry Report | CoinGecko
 
Governor Olli Rehn: Dialling back monetary restraint
Governor Olli Rehn: Dialling back monetary restraintGovernor Olli Rehn: Dialling back monetary restraint
Governor Olli Rehn: Dialling back monetary restraint
 
(办理学位证)美国加州州立大学东湾分校毕业证成绩单原版一比一
(办理学位证)美国加州州立大学东湾分校毕业证成绩单原版一比一(办理学位证)美国加州州立大学东湾分校毕业证成绩单原版一比一
(办理学位证)美国加州州立大学东湾分校毕业证成绩单原版一比一
 
Bladex 1Q24 Earning Results Presentation
Bladex 1Q24 Earning Results PresentationBladex 1Q24 Earning Results Presentation
Bladex 1Q24 Earning Results Presentation
 

Pmc hitesh

  • 1. Project Costing Hitesh Gupta 11/09/2012
  • 2. Direct Costs Indirect Costs Can be identified specifically with a Incurred for common or joint objectives & particular sponsored project can’t be identified readily & specifically with a particular sponsored project E.g if company produces artisan furniture, cost of wood & cost of craftsperson Can be controlled by efficient engineering, proficient staff, construction Can be controlled by good supervision and time, etc job control Costs like advertising, depreciation, general supplies Includes Direct labour, Repair labour, for firm, accounting services, Office Operating costs of equipments, Supplies, Payroll and expense, Property taxes etc Permanent materials, Subcontract costs
  • 3. Dealing with Contingency items for cost estimation Occurrence: •May or May not occur Contingency Exposure •Minor to Maximum amount, •Can’t be estimated Dealing : • Should be computed & listed separately but not in actual estimates • Markup decided if max cost explained to contractor Minimizing effect : •If specifications contain: force-majeure (e.g., war, strike etc) unforeseen condition (e.g. Irregular final rock surface) clauses •Builders All-Risk Insurance
  • 4. Dealing with Escalation items for cost estimation Increase in cost during construction • Project risks may escalate more than reasonable estimation • Consists of total project labour costs and permanent material costs Labour Costs •Unescalated labour costs * % increase in labour cost ( reviewing labour contracts, reviewing trends in particular craft, overall wage increase throughout country etc) Material Costs • Minor costs as quotations will be firm for life of project. •Escalation in material be determined after receipt •Computation performed same as labour
  • 5. Relevance of making cash flows for cost estimation Cash Forecast prepared: •To establish capital requirements – For purchasing construction P&M, insurance, etc •To estimate interest expense - Interest on capital invested •To analyze, & select investment projects where expected returns extend beyond 1 year. • To gauge time to completion (more time = more overheads) • To estimate initial investment/cost required
  • 6. Relevance of calculating cost of promoter’s funds in final estimate Loan/Debt Requirement •Future interest payments Cost of Capital – •Opportunity Cost Employer’s Cost •For future pricing/tariffs Risk involved Project
  • 7. Process followed for selecting method of excavation Examining Explanation Nature of subsoil affect type of machine used and the necessity of soil protection. Size of excavation affect type of machine used & method to excavate. Scale of work large volume of excavation may involve complicated phasing arrangement & work planning Ground water affect degree of protection (watertight sheet piling or dewatering condition may required.) Surrounding condition impose certain restrictions and precautions (eg. diversion of government drain, or underpinning work to nearby building foundation)
  • 8. Deciding Mark-Up Project Characteristics • Size, Cash flow, Location etc Company’s Characteristics • Past Profit, Current Workload, Experience etc Economic Environment • Labour availability, Tax, Economy etc Project Documentation • Type of Contract, Completeness of documents, •Pre-qualification, number of competitors etc. Refinement Required Across-the-Board Markup vs Differential Markup • Mark-up should be allocated to each cost Cash flow-based model to calculate Mark-Up • Mark-Up (Percent) = (PV of disbursements/PV of receipts) -1 (*100)
  • 9. Costs involved in different forms of Guarantees Bid bond or tender bond •Bid bonds are usually issued for 1% to 5% Performance bond •After tender is accepted •Replace bid bond •10% to 20% contract amount Retention bond • Client may withhold 5%-10% of contract amount Payment guarantee •Ensures payment to contractor
  • 10. Insurance policies available for covering Contractor’s Risk Employers Liability Insurance (EL) • Aagainst liability for injury or disease to employees Third party or Public Liability Insurance (PL) - •Someone suffering loss not party to insurance contract. •Depends on amount & scope of works Contract Works Insurance (CW) - •Covers costs of losses and damages of works undertaken •e.g. flooding a completed property or burning down a newly built house. Professional Indemnity Insurance (PI) - • Covers incorrect design of part of works •e.g. drainage system. Tools and Temporary Works Insurance (TTW) All Risk Insurance (AR) - Covers all other losses
  • 11. Points of major differences of cost calculations that occurred between joint venture partners of Sierra Tunnel Project (Cost for New Machinery Vs Used P&M) Plant and Machinery •Net charge would reduce Maintenance •Cost more to maintain used machinery Estimated Production •Decrease Interest cost •Decrease as there is no purchase Excavation cost •Increase
  • 12. Relevance of Project Accounting understanding in Project Costing With reference to IAS 7 (statement of cash flows) Developing the Budget •Identifying Cost Accounts (interest charges, rental expenses, taxes, etc.) •Developing a Schedule of Cost Accounts •Making a Forecast Estimate Monitoring Budget Implementation - Cash Flow Status Report •Provides a summary for monitoring the cash inflows and outflows. •Manager will be able to perceive if budget is being closely implemented • If cash inflow coming from the client is timely and sufficient. Evaluating Financial Reports •Disclose fund adequacy or inadequacy •Negative results would prompt contractor to thresh-out matter with client before proceeding with project
  • 13. Relevance of ABC costing for Infrastructure development business Projects use ABC costing in some form Provides a Clear Understanding of Processes • provide better understanding of processes performed • how processes react to different inputs & variables. Assign Cost to Activities • Identify activities & assign costs to them • Identify cost drivers associated with activities • Assign costs to projects (by cost driver rate * volume of cost driver units consumed by project) Technique adopted for project budgets • Identify sources of cost-drivers/project costs • Help in indentifying control measures

Notas del editor

  1. 3rd party :Damages caused to neighbouring buildings.