SlideShare una empresa de Scribd logo
1 de 47
Descargar para leer sin conexión
Project Management
Part 2
Plan Schedule Management
“The process of establishing the policies,
procedures, and documentation for planning,
developing, managing, executing, and controlling
the project schedule.”
(PMBOK 6.1)
©2013 Project Management Institute A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition
Define Activities
“The process of identifying and documenting the
specific actions to be performed to produce the
project deliverables.”
(PMBOK 6.2)
Activities are usually derived from the lowest level of
the project WBS.
Project activities may also be called tasks, work
packages, “stories,” or other names.
©2013 Project Management Institute A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition
Document Activity Information
• Identify a single owner for each task
• Clearly define the output deliverables of each
project task
• Document key assumptions for all tasks
• Collect and store all task data
Activity Ownership
Ownership: Many owners = No owner
• Assign one, and only one, owner per task
• Owners plan, estimate, monitor and report task
data
• Owners are not necessarily „doers‟
Activity Staffing
In addition to the activity owner, determine all
contributors expected to participate in the
work.
Capture:
• Names
• Roles and skills
• Availability
Measurable Deliverables
• Owners specify the deliverable(s) for each lowest-level task
• Define the deliverables clearly
• Tasks with several deliverables may need further break down
• Determine measures and completion criteria
• Capture key assumptions
Project Milestones
In addition to activities, projects also contain milestones,
which are “moments in time” and have no (or almost
no) work or duration. Examples of milestones:
• Project start
• Project end
• Life cycle transitions or phase gates
• Significant events or decisions
• Links between projects
Also document all project milestones.
Sequence Activities
“The process of identifying and documenting relationships
among the project activities.”
(PMBOK 6.3)
• Dependency relationships generally follow work flow.
• Every identified activity must precede another activity (or
milestone).
• Every identified activity must follow another activity (or
milestone).
• Activity linkages are based on logic, not dates.
Determine and thoroughly document all project activity
dependencies.
©2013 Project Management Institute A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition
Finish-to-Start Dependencies
The predecessor activity must completed before the
successor activity can begin. This is by far the most common
linkage type.
For example:
When linking activities, always check for activities in between
that you may have missed, and add them to the WBS.
Install Electricity
Test Equipment
Start-to-Start Dependencies
Two (or more) activities in the project must start
simultaneously. For most projects, this dependency
type is not common.
For example:
Monitor test
Conduct test
Finish-to-Finish Dependencies
The finish of one (or more) project activities is constrained by
the completion of another activity. Also relatively rare, but
occurs when activity deliverables need to be used or combined
promptly because they will change (cool, dry, harden, etc.).
For example:
Set the support posts
Pour the concrete
Start-to-Finish Dependencies
This type of dependency is defined mostly for symmetry.
There are few, if any, cases best modeled using it in
typical projects.
For example:
Go live with new system
Operate the legacy system
Dependency Leads and Lags
Leads provide overlap dependencies. Leads often occur
in “compressed” schedules.
Design Application
Note: The visibility of logical work flow is concealed.
Lead = 2 weeks
Write Software
2.3-8
Lags are a delay in a dependency.
Paint the first coat
Lag = 1 day
Paint the second coat
Sequencing Continuity
Ensure that all activities (and milestones) are part of a
continuous workflow that extends back to the project
start and forward to the project end.
• Most linkages are finish-to-start (default for tools).
• Avoid most use of “fixed date” logic.
• Find and fix all workflow gaps.
Visit Customers
Analyze Data
Specify Product
S
E
Missing dependency
Project Estimation Terms
Effort: Total personal time spent working on
a activity
Duration: Workdays required to complete a
activity
Calendar time: Total number of days on the calendar
to complete a activity
Estimate Activity Durations
“The process of estimating the number of work
periods needed to complete individual activities
with estimated resources.” (PMBOK 6.5)
– Initial duration estimates relate to project time
management.
– Calendar duration estimates include both workdays
and non-workdays
– Effort (resource) estimates relate to project cost,
and are measured in “person hours” or similar units.
Effort and duration estimates must be consistent.
©2013 Project Management Institute A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition
Initial Duration Estimates
Initial project estimates are:
• Best provided by task owners
• Based on activity details:
•Duration estimates are based on history
•Effort assessments are based on staffing assumptions
Project Estimates
Estimates
Project
Information
Activity
Information
Assumptions
Estimating Process
Archived
Metrics
Activity Estimates
Project
Specifics
People and
Teams
Non-Project
Factors
Good estimates take into account:
• History base
• Project specifics
• People and team variables
• Non-project factors
History
Base
Duration
Estimates
Calendar
Time
Effort
Estimates
3-Point Estimates
TIME
tpteto
1% 50% 99%
0 tm
te
tp tm4
6
to
to = “Optimistic” estimate
tm = “Most likely” estimate
tp = “Pessimistic” estimate
te = “Expected” estimate
3-point estimates originated with
“PERT” (Program Evaluation and
Review Technique), and can help
account for risk.
Activity Information Database
WBS
Code
Task
Owner
Completion
Criteria
Task
Name
Duration
Estimate
Task information such as this may be documented in a project
scheduling tool, in a spreadsheet, a notebook, or a file cabinet...
3.2 ABC XYZNo testing
errors
Write
Software
15 days
2.3-2
“The process of analyzing activity sequences, durations,
resource requirements, and schedule constraints to
create the project schedule model.” (PMBoK 6.6)
Initial schedules are based on bottom-up analysis of
workflow, not on arbitrary date targets.
Formats:
• Network or precedence diagrams emphasize logical relationships.
• Bar or Gantt diagrams display timing.
Develop Schedule
©2013 Project Management Institute A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition
©2013 Project Management Institute A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition
©2013 Project Management Institute A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition
Create Network Diagrams
2.5
Develop
Test Plan
7 d
2.4
Document
System
5 d
2.3
Design
System
15 d
3.1
Build
Hardware
10 d
3.2
Write
Software
8 d
3.4
Assemble
Prototype
18 d
. . .
. . .
Initial network precedence diagrams can use sticky
notes and penciled arrows to show the project as
sequences of defined activities and milestones.
Create Bar or Gantt Charts
©2013 Project Management Institute A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition
Analyze Project Critical Path (Critical
Path Method—CPM)
= Critical path task
• A Critical Path (CP) network path with the longest duration.
• Any CP activity slip will delay the project.
• To shorten the schedule, you must shorten the CP.
• CP focuses management analysis and tracking.
2.3-14
= Non-critical path task
Start End
Critical Path Analysis
• The project critical path (or paths) is the longest, and
least flexible, path through the network.
• To determine:
• Calculate the early schedule using forward path analysis.
• Calculate the late schedule using backward path analysis.
• The calculated difference between Late and Early
schedules = Float, or Slack.
• Non-critical tasks have a positive float, showing
flexibility.
• Critical tasks have no (or negative) float.
2.3-13
CPM Example
Work Days
Task C (5 days)
Start End
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Task A (5 days)
Task B (10 days)
2.3-15
ES= EF=
Task A
DUR=5 FI=
LS= LF=
ES=1 EF=1
Start
DUR=0 FI=
LS= LF=
ES= EF=
Task B
DUR=10 FI=
LS= LF=
ES= EF=
End
DUR=0 FI=
LS= LF=
ES= EF=
Task C
DUR=5 FI=
LS= LF=
1 5 6 15
1 5
15 15
15 15
6 15
11 15
1 5
1 1
0
10
0 0
0
Plan Human Resource Management
“The process of identifying and documenting
project roles, responsibilities, required skills,
reporting relationships, and creating a staffing
management plan.” (PMBOK 9.1)
Develop:
• Updated staffing roster (from project initiation)
• Responsibility analysis
• Strategy for managing resources
©2013 Project Management Institute A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition
Roles and Responsibilities
©2013 Project Management Institute A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition
Delegating Responsibility
Ownership: Many owners = No owner
• Assign one, and only one, owner for each defined
project activity.
• Owners plan, initially estimate, monitor, and report on
activities.
• Owners are not necessarily “doers.”
Analyze Responsibilities
Responsibility Assignment Matrix (RAM) in RACI format
Activities
Staff
Hawkeye Margaret Trapper Radar TBA
Activity
1.1.1
A R C R
Activity
1.1.2
C A
Activity
1.2.1
R A C RRR
Activity
1.2.2
C R R A
RACI Matrix Definitions
Define “RACI” roles for project work for each
defined activity:
• R: Responsible (Contributor, does work)
• A: Accountable (Owner—one “A” per activity)
• C: Consulted (Approvers, decision makers)
• I: Informed (Receives information)
Include a “TBA” column in a RACI analysis to track
staffing or other unmet needs.
Estimates for Staffing
When estimating effort, consider:
• Skills and experience of staff
• Availability
• Competing priorities
• Number of hours per day for project work
• Interruptions
• Team communications and meetings
• Geographic separation
• Other work factors
Consider Non-Project Factors
• Holidays and paid time off
• Scheduled vacations
• Off-site meetings
• Other responsibilities
• Equipment downtime
• Scheduled sick leave
• …
Assess Resource Timing
2.4-4
March 7 March 14 March 21 March 28 April 4 . . .
Hawkeye Pierce 20 23 45 25 3
B. J. Hunnicut 4 4 4 4 4
Charles Winchester 12 12 12 12 12
Radar O’Reilly 80 80 90 168 70
Margaret Hoolihan 26 26 26 26 26
Example using a spreadsheet:
Using the project workflow analysis, “stack up” all effort estimates to determine
staffing overcommitments.
Project management scheduling tools may be useful for complex projects.
Resource histograms can be generated If staffing and activity data are accurately
entered.
Resource Histogram Example
©2013 Project Management Institute A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition
Estimate Other Resources
• Contract staffing
• Materials
• Equipment
• Travel
• Services required
• Other direct project expenses
Plan Cost Management
“The process that establishes the policies,
procedures, and documentation for planning,
managing, executing, and controlling project
costs.” (PMBOK 7.1)
©2013 Project Management Institute A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition
Estimate Costs
“The process of developing an approximation of
the monetary resources needed to complete
project activities.” (PMBOK 7.2)
Use the quantities estimated for each identified
resource (hours, days, kilograms, pages, scheduled
trips, etc.) to calculate the cost for each to the
project.
©2013 Project Management Institute A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition
Activity Cost Estimates
Includes the cost of staff effort assessed for each activity as
part of duration analysis, plus:
• Outsourcing costs (Contract fees, Potential penalties…)
• Hardware and other equipment purchases
• Charges for use of shared or rented equipment
• Supplies and required components
• Software acquisition and licenses
• Communications: Audio, Video, Computer networking
• Services: Shipping costs, Duplicating, Printing, etc.
• Travel expenses
• Other direct expenses
Types of Cost Estimates
• Rough Order of Magnitude (ROM) estimates
– Made without any detailed engineering data
– May use past experience
– Accuracy ± (25-75)% within the scope of the project
• Plan (or budgetary) estimates
– Prepared from initial plans
– Based on WBS
– Accuracy ± (10-25)%
• Definitive (or detailed) estimates
– Prepared from well-defined engineering data, vendor quotes, unit
prices, etc.
– Based on analysis of specific WBS low-level activities
– Accuracy ± (5-10)%
Determine Budget
“The process of aggregating the estimated costs of
individual activities or work packages to establish
an authorized cost baseline.” (PMBOK 7.3)
Sum all estimated costs required for each project
activity to determine the overall bottom-up
assessed cost of the project.
©2013 Project Management Institute A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition
Overall Project Budget
An overall bottom-up project budget includes:
• Costs estimated for every defined project activity
• Any additional direct expenses that will be carried
by the project (overhead, etc.)
• All management cost reserve or contingency
funding allocated to the project
For tracking and analysis, all costs may be
apportioned to lowest-level WBS activities.
Thank You
hkbhadraa@gmail.com

Más contenido relacionado

La actualidad más candente

Old definition of project management
Old definition of project managementOld definition of project management
Old definition of project managementArlen Mark
 
6. Schedule Management
6. Schedule Management6. Schedule Management
6. Schedule ManagementSanjay Rajpoot
 
MS Project Presentation
MS Project PresentationMS Project Presentation
MS Project PresentationKhem Singh
 
Work breakdown structure ppt
Work breakdown structure pptWork breakdown structure ppt
Work breakdown structure pptnazi2020
 
Project Management Toolkit - Presentation
Project Management Toolkit - PresentationProject Management Toolkit - Presentation
Project Management Toolkit - PresentationHassan Rizwan
 
SLeahy - Unit 5 Assignment - IT599-01
SLeahy - Unit 5 Assignment - IT599-01SLeahy - Unit 5 Assignment - IT599-01
SLeahy - Unit 5 Assignment - IT599-01Steven Leahy
 
Project management
Project managementProject management
Project managementtwilight89
 
Project time management
Project time managementProject time management
Project time managementJivan Nepali
 
project planning-estimation
project planning-estimationproject planning-estimation
project planning-estimationReetesh Gupta
 
Projects2016_Franks_PreparingFortheParty-Project Close
Projects2016_Franks_PreparingFortheParty-Project CloseProjects2016_Franks_PreparingFortheParty-Project Close
Projects2016_Franks_PreparingFortheParty-Project CloseBarbara Franks
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Schedulingsslovepk
 
Project management planning
Project management planningProject management planning
Project management planningAlvin Niere
 
10 key features of microsoft project plan (mpp)
10 key features of microsoft project plan (mpp)10 key features of microsoft project plan (mpp)
10 key features of microsoft project plan (mpp)Sridhar Srinivas, PMP, CSM
 

La actualidad más candente (20)

Old definition of project management
Old definition of project managementOld definition of project management
Old definition of project management
 
6. Schedule Management
6. Schedule Management6. Schedule Management
6. Schedule Management
 
MS Project Presentation
MS Project PresentationMS Project Presentation
MS Project Presentation
 
Excel Project Management
Excel Project ManagementExcel Project Management
Excel Project Management
 
Project Planning
Project PlanningProject Planning
Project Planning
 
Work breakdown structure ppt
Work breakdown structure pptWork breakdown structure ppt
Work breakdown structure ppt
 
Project Management Toolkit - Presentation
Project Management Toolkit - PresentationProject Management Toolkit - Presentation
Project Management Toolkit - Presentation
 
SLeahy - Unit 5 Assignment - IT599-01
SLeahy - Unit 5 Assignment - IT599-01SLeahy - Unit 5 Assignment - IT599-01
SLeahy - Unit 5 Assignment - IT599-01
 
Project Planning Scheduling
Project Planning SchedulingProject Planning Scheduling
Project Planning Scheduling
 
project management
project managementproject management
project management
 
Project management
Project managementProject management
Project management
 
Project time management
Project time managementProject time management
Project time management
 
Project termination
Project terminationProject termination
Project termination
 
project planning-estimation
project planning-estimationproject planning-estimation
project planning-estimation
 
Project time management
Project time managementProject time management
Project time management
 
Projects2016_Franks_PreparingFortheParty-Project Close
Projects2016_Franks_PreparingFortheParty-Project CloseProjects2016_Franks_PreparingFortheParty-Project Close
Projects2016_Franks_PreparingFortheParty-Project Close
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Scheduling
 
Chapter 4
Chapter 4Chapter 4
Chapter 4
 
Project management planning
Project management planningProject management planning
Project management planning
 
10 key features of microsoft project plan (mpp)
10 key features of microsoft project plan (mpp)10 key features of microsoft project plan (mpp)
10 key features of microsoft project plan (mpp)
 

Destacado

Gamification
GamificationGamification
Gamificationhkbhadraa
 
Internet of things
Internet of thingsInternet of things
Internet of thingshkbhadraa
 
Big data Lambda Architecture - Batch Layer Hands On
Big data Lambda Architecture - Batch Layer Hands OnBig data Lambda Architecture - Batch Layer Hands On
Big data Lambda Architecture - Batch Layer Hands Onhkbhadraa
 
Big data lambda architecture - Streaming Layer Hands On
Big data lambda architecture - Streaming Layer Hands OnBig data lambda architecture - Streaming Layer Hands On
Big data lambda architecture - Streaming Layer Hands Onhkbhadraa
 
IBM Bluemix Cloud Platform Application Development with Eclipse IDE
IBM Bluemix Cloud Platform Application Development with Eclipse IDEIBM Bluemix Cloud Platform Application Development with Eclipse IDE
IBM Bluemix Cloud Platform Application Development with Eclipse IDEhkbhadraa
 
Setup 3 Node Kafka Cluster on AWS - Hands On
Setup 3 Node Kafka Cluster on AWS - Hands OnSetup 3 Node Kafka Cluster on AWS - Hands On
Setup 3 Node Kafka Cluster on AWS - Hands Onhkbhadraa
 
Hadoop BIG Data - Fraud Detection with Real-Time Analytics
Hadoop BIG Data - Fraud Detection with Real-Time AnalyticsHadoop BIG Data - Fraud Detection with Real-Time Analytics
Hadoop BIG Data - Fraud Detection with Real-Time Analyticshkbhadraa
 

Destacado (7)

Gamification
GamificationGamification
Gamification
 
Internet of things
Internet of thingsInternet of things
Internet of things
 
Big data Lambda Architecture - Batch Layer Hands On
Big data Lambda Architecture - Batch Layer Hands OnBig data Lambda Architecture - Batch Layer Hands On
Big data Lambda Architecture - Batch Layer Hands On
 
Big data lambda architecture - Streaming Layer Hands On
Big data lambda architecture - Streaming Layer Hands OnBig data lambda architecture - Streaming Layer Hands On
Big data lambda architecture - Streaming Layer Hands On
 
IBM Bluemix Cloud Platform Application Development with Eclipse IDE
IBM Bluemix Cloud Platform Application Development with Eclipse IDEIBM Bluemix Cloud Platform Application Development with Eclipse IDE
IBM Bluemix Cloud Platform Application Development with Eclipse IDE
 
Setup 3 Node Kafka Cluster on AWS - Hands On
Setup 3 Node Kafka Cluster on AWS - Hands OnSetup 3 Node Kafka Cluster on AWS - Hands On
Setup 3 Node Kafka Cluster on AWS - Hands On
 
Hadoop BIG Data - Fraud Detection with Real-Time Analytics
Hadoop BIG Data - Fraud Detection with Real-Time AnalyticsHadoop BIG Data - Fraud Detection with Real-Time Analytics
Hadoop BIG Data - Fraud Detection with Real-Time Analytics
 

Similar a Project management part 2

Similar a Project management part 2 (20)

Day 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptxDay 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptx
 
Chapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapterChapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapter
 
Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)
 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Management
 
Session 8 4th edition PMP
Session 8 4th edition PMPSession 8 4th edition PMP
Session 8 4th edition PMP
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
PMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptxPMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptx
 
Microsot project basics
Microsot project basicsMicrosot project basics
Microsot project basics
 
3- Project Time Management.ppt
3- Project Time Management.ppt3- Project Time Management.ppt
3- Project Time Management.ppt
 
HM 418 2e hcpm05 (1)
HM 418 2e hcpm05 (1)HM 418 2e hcpm05 (1)
HM 418 2e hcpm05 (1)
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
SPM_UNIT-2.pptx
SPM_UNIT-2.pptxSPM_UNIT-2.pptx
SPM_UNIT-2.pptx
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Pm chapter 5...
Pm chapter 5...Pm chapter 5...
Pm chapter 5...
 
Primavara
PrimavaraPrimavara
Primavara
 
Project Management.pptx
 Project  Management.pptx Project  Management.pptx
Project Management.pptx
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule Development
 
Gantt Charts.ppt
Gantt Charts.pptGantt Charts.ppt
Gantt Charts.ppt
 

Último

Safety T fire missions army field Artillery
Safety T fire missions army field ArtillerySafety T fire missions army field Artillery
Safety T fire missions army field ArtilleryKennethSwanberg
 
Beyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentBeyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentNimot Muili
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptxAss.Prof. Dr. Mogeeb Mosleh
 
Marketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docxMarketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docxssuserf63bd7
 
The Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard BrownThe Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard BrownSandaliGurusinghe2
 
digital Human resource management presentation.pdf
digital Human resource management presentation.pdfdigital Human resource management presentation.pdf
digital Human resource management presentation.pdfArtiSrivastava23
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxalinstan901
 
Leaders enhance communication by actively listening, providing constructive f...
Leaders enhance communication by actively listening, providing constructive f...Leaders enhance communication by actively listening, providing constructive f...
Leaders enhance communication by actively listening, providing constructive f...Ram V Chary
 
How Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptxHow Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptxAaron Stannard
 
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime SiliguriSiliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siligurimeghakumariji156
 
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professionalW.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professionalWilliam (Bill) H. Bender, FCSI
 
internship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamrainternship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamraAllTops
 
International Ocean Transportation p.pdf
International Ocean Transportation p.pdfInternational Ocean Transportation p.pdf
International Ocean Transportation p.pdfAlejandromexEspino
 
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot ModelGautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot ModelNitya salvi
 

Último (16)

Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTECAbortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
 
Safety T fire missions army field Artillery
Safety T fire missions army field ArtillerySafety T fire missions army field Artillery
Safety T fire missions army field Artillery
 
Beyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentBeyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable development
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptx
 
Marketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docxMarketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docx
 
The Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard BrownThe Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard Brown
 
digital Human resource management presentation.pdf
digital Human resource management presentation.pdfdigital Human resource management presentation.pdf
digital Human resource management presentation.pdf
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptx
 
Leaders enhance communication by actively listening, providing constructive f...
Leaders enhance communication by actively listening, providing constructive f...Leaders enhance communication by actively listening, providing constructive f...
Leaders enhance communication by actively listening, providing constructive f...
 
How Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptxHow Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptx
 
Intro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptxIntro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptx
 
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime SiliguriSiliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
 
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professionalW.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
 
internship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamrainternship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamra
 
International Ocean Transportation p.pdf
International Ocean Transportation p.pdfInternational Ocean Transportation p.pdf
International Ocean Transportation p.pdf
 
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot ModelGautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
 

Project management part 2

  • 2. Plan Schedule Management “The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.” (PMBOK 6.1) ©2013 Project Management Institute A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition
  • 3. Define Activities “The process of identifying and documenting the specific actions to be performed to produce the project deliverables.” (PMBOK 6.2) Activities are usually derived from the lowest level of the project WBS. Project activities may also be called tasks, work packages, “stories,” or other names. ©2013 Project Management Institute A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition
  • 4. Document Activity Information • Identify a single owner for each task • Clearly define the output deliverables of each project task • Document key assumptions for all tasks • Collect and store all task data
  • 5. Activity Ownership Ownership: Many owners = No owner • Assign one, and only one, owner per task • Owners plan, estimate, monitor and report task data • Owners are not necessarily „doers‟
  • 6. Activity Staffing In addition to the activity owner, determine all contributors expected to participate in the work. Capture: • Names • Roles and skills • Availability
  • 7. Measurable Deliverables • Owners specify the deliverable(s) for each lowest-level task • Define the deliverables clearly • Tasks with several deliverables may need further break down • Determine measures and completion criteria • Capture key assumptions
  • 8. Project Milestones In addition to activities, projects also contain milestones, which are “moments in time” and have no (or almost no) work or duration. Examples of milestones: • Project start • Project end • Life cycle transitions or phase gates • Significant events or decisions • Links between projects Also document all project milestones.
  • 9. Sequence Activities “The process of identifying and documenting relationships among the project activities.” (PMBOK 6.3) • Dependency relationships generally follow work flow. • Every identified activity must precede another activity (or milestone). • Every identified activity must follow another activity (or milestone). • Activity linkages are based on logic, not dates. Determine and thoroughly document all project activity dependencies. ©2013 Project Management Institute A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition
  • 10. Finish-to-Start Dependencies The predecessor activity must completed before the successor activity can begin. This is by far the most common linkage type. For example: When linking activities, always check for activities in between that you may have missed, and add them to the WBS. Install Electricity Test Equipment
  • 11. Start-to-Start Dependencies Two (or more) activities in the project must start simultaneously. For most projects, this dependency type is not common. For example: Monitor test Conduct test
  • 12. Finish-to-Finish Dependencies The finish of one (or more) project activities is constrained by the completion of another activity. Also relatively rare, but occurs when activity deliverables need to be used or combined promptly because they will change (cool, dry, harden, etc.). For example: Set the support posts Pour the concrete
  • 13. Start-to-Finish Dependencies This type of dependency is defined mostly for symmetry. There are few, if any, cases best modeled using it in typical projects. For example: Go live with new system Operate the legacy system
  • 14. Dependency Leads and Lags Leads provide overlap dependencies. Leads often occur in “compressed” schedules. Design Application Note: The visibility of logical work flow is concealed. Lead = 2 weeks Write Software 2.3-8 Lags are a delay in a dependency. Paint the first coat Lag = 1 day Paint the second coat
  • 15. Sequencing Continuity Ensure that all activities (and milestones) are part of a continuous workflow that extends back to the project start and forward to the project end. • Most linkages are finish-to-start (default for tools). • Avoid most use of “fixed date” logic. • Find and fix all workflow gaps. Visit Customers Analyze Data Specify Product S E Missing dependency
  • 16. Project Estimation Terms Effort: Total personal time spent working on a activity Duration: Workdays required to complete a activity Calendar time: Total number of days on the calendar to complete a activity
  • 17. Estimate Activity Durations “The process of estimating the number of work periods needed to complete individual activities with estimated resources.” (PMBOK 6.5) – Initial duration estimates relate to project time management. – Calendar duration estimates include both workdays and non-workdays – Effort (resource) estimates relate to project cost, and are measured in “person hours” or similar units. Effort and duration estimates must be consistent. ©2013 Project Management Institute A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition
  • 18. Initial Duration Estimates Initial project estimates are: • Best provided by task owners • Based on activity details: •Duration estimates are based on history •Effort assessments are based on staffing assumptions
  • 20. Activity Estimates Project Specifics People and Teams Non-Project Factors Good estimates take into account: • History base • Project specifics • People and team variables • Non-project factors History Base Duration Estimates Calendar Time Effort Estimates
  • 21. 3-Point Estimates TIME tpteto 1% 50% 99% 0 tm te tp tm4 6 to to = “Optimistic” estimate tm = “Most likely” estimate tp = “Pessimistic” estimate te = “Expected” estimate 3-point estimates originated with “PERT” (Program Evaluation and Review Technique), and can help account for risk.
  • 22. Activity Information Database WBS Code Task Owner Completion Criteria Task Name Duration Estimate Task information such as this may be documented in a project scheduling tool, in a spreadsheet, a notebook, or a file cabinet... 3.2 ABC XYZNo testing errors Write Software 15 days
  • 23. 2.3-2 “The process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model.” (PMBoK 6.6) Initial schedules are based on bottom-up analysis of workflow, not on arbitrary date targets. Formats: • Network or precedence diagrams emphasize logical relationships. • Bar or Gantt diagrams display timing. Develop Schedule ©2013 Project Management Institute A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition
  • 24. ©2013 Project Management Institute A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition
  • 25. ©2013 Project Management Institute A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition
  • 26. Create Network Diagrams 2.5 Develop Test Plan 7 d 2.4 Document System 5 d 2.3 Design System 15 d 3.1 Build Hardware 10 d 3.2 Write Software 8 d 3.4 Assemble Prototype 18 d . . . . . . Initial network precedence diagrams can use sticky notes and penciled arrows to show the project as sequences of defined activities and milestones.
  • 27. Create Bar or Gantt Charts ©2013 Project Management Institute A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition
  • 28. Analyze Project Critical Path (Critical Path Method—CPM) = Critical path task • A Critical Path (CP) network path with the longest duration. • Any CP activity slip will delay the project. • To shorten the schedule, you must shorten the CP. • CP focuses management analysis and tracking. 2.3-14 = Non-critical path task Start End
  • 29. Critical Path Analysis • The project critical path (or paths) is the longest, and least flexible, path through the network. • To determine: • Calculate the early schedule using forward path analysis. • Calculate the late schedule using backward path analysis. • The calculated difference between Late and Early schedules = Float, or Slack. • Non-critical tasks have a positive float, showing flexibility. • Critical tasks have no (or negative) float. 2.3-13
  • 30. CPM Example Work Days Task C (5 days) Start End 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Task A (5 days) Task B (10 days) 2.3-15 ES= EF= Task A DUR=5 FI= LS= LF= ES=1 EF=1 Start DUR=0 FI= LS= LF= ES= EF= Task B DUR=10 FI= LS= LF= ES= EF= End DUR=0 FI= LS= LF= ES= EF= Task C DUR=5 FI= LS= LF= 1 5 6 15 1 5 15 15 15 15 6 15 11 15 1 5 1 1 0 10 0 0 0
  • 31. Plan Human Resource Management “The process of identifying and documenting project roles, responsibilities, required skills, reporting relationships, and creating a staffing management plan.” (PMBOK 9.1) Develop: • Updated staffing roster (from project initiation) • Responsibility analysis • Strategy for managing resources ©2013 Project Management Institute A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition
  • 32. Roles and Responsibilities ©2013 Project Management Institute A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition
  • 33. Delegating Responsibility Ownership: Many owners = No owner • Assign one, and only one, owner for each defined project activity. • Owners plan, initially estimate, monitor, and report on activities. • Owners are not necessarily “doers.”
  • 34. Analyze Responsibilities Responsibility Assignment Matrix (RAM) in RACI format Activities Staff Hawkeye Margaret Trapper Radar TBA Activity 1.1.1 A R C R Activity 1.1.2 C A Activity 1.2.1 R A C RRR Activity 1.2.2 C R R A
  • 35. RACI Matrix Definitions Define “RACI” roles for project work for each defined activity: • R: Responsible (Contributor, does work) • A: Accountable (Owner—one “A” per activity) • C: Consulted (Approvers, decision makers) • I: Informed (Receives information) Include a “TBA” column in a RACI analysis to track staffing or other unmet needs.
  • 36. Estimates for Staffing When estimating effort, consider: • Skills and experience of staff • Availability • Competing priorities • Number of hours per day for project work • Interruptions • Team communications and meetings • Geographic separation • Other work factors
  • 37. Consider Non-Project Factors • Holidays and paid time off • Scheduled vacations • Off-site meetings • Other responsibilities • Equipment downtime • Scheduled sick leave • …
  • 38. Assess Resource Timing 2.4-4 March 7 March 14 March 21 March 28 April 4 . . . Hawkeye Pierce 20 23 45 25 3 B. J. Hunnicut 4 4 4 4 4 Charles Winchester 12 12 12 12 12 Radar O’Reilly 80 80 90 168 70 Margaret Hoolihan 26 26 26 26 26 Example using a spreadsheet: Using the project workflow analysis, “stack up” all effort estimates to determine staffing overcommitments. Project management scheduling tools may be useful for complex projects. Resource histograms can be generated If staffing and activity data are accurately entered.
  • 39. Resource Histogram Example ©2013 Project Management Institute A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition
  • 40. Estimate Other Resources • Contract staffing • Materials • Equipment • Travel • Services required • Other direct project expenses
  • 41. Plan Cost Management “The process that establishes the policies, procedures, and documentation for planning, managing, executing, and controlling project costs.” (PMBOK 7.1) ©2013 Project Management Institute A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition
  • 42. Estimate Costs “The process of developing an approximation of the monetary resources needed to complete project activities.” (PMBOK 7.2) Use the quantities estimated for each identified resource (hours, days, kilograms, pages, scheduled trips, etc.) to calculate the cost for each to the project. ©2013 Project Management Institute A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition
  • 43. Activity Cost Estimates Includes the cost of staff effort assessed for each activity as part of duration analysis, plus: • Outsourcing costs (Contract fees, Potential penalties…) • Hardware and other equipment purchases • Charges for use of shared or rented equipment • Supplies and required components • Software acquisition and licenses • Communications: Audio, Video, Computer networking • Services: Shipping costs, Duplicating, Printing, etc. • Travel expenses • Other direct expenses
  • 44. Types of Cost Estimates • Rough Order of Magnitude (ROM) estimates – Made without any detailed engineering data – May use past experience – Accuracy ± (25-75)% within the scope of the project • Plan (or budgetary) estimates – Prepared from initial plans – Based on WBS – Accuracy ± (10-25)% • Definitive (or detailed) estimates – Prepared from well-defined engineering data, vendor quotes, unit prices, etc. – Based on analysis of specific WBS low-level activities – Accuracy ± (5-10)%
  • 45. Determine Budget “The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline.” (PMBOK 7.3) Sum all estimated costs required for each project activity to determine the overall bottom-up assessed cost of the project. ©2013 Project Management Institute A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition
  • 46. Overall Project Budget An overall bottom-up project budget includes: • Costs estimated for every defined project activity • Any additional direct expenses that will be carried by the project (overhead, etc.) • All management cost reserve or contingency funding allocated to the project For tracking and analysis, all costs may be apportioned to lowest-level WBS activities.