SlideShare una empresa de Scribd logo
1 de 89
Descargar para leer sin conexión
Administrasi Kontrak
(1.Kontrak)
CAYA CEOLANG SALJANA TEKNIK YANG
SANGAT PINTEL DAN MENGUACAI
PELHITUNGAN KONTLUKSI.
APA GUNANYA PENGETAHUAN TENTANG
KONTLAK, ITU KHAN ULUSANNYA AHLI
HUKUM.
PENANGGUNG JAWAB TEKNIK
ASPEK LEGAL DAN ADMINISTRASI KONTRAK
Kontrak
Konstruksi
Administrasi
Kontrak
Klaim
Konstruksi
Garner (2004) “Contract is an agreement between two or more
parties creating obligations that are enforceable or otherwise
recognizable at law”
Martin and Law (2006) “Contract is a legally binding agreement.
Agreement arises as a result of “offer and acceptance”, but a number
of other requirements must be satisfied for an agreement to be legally
binding”.
(Bryan A.Garner (2004): “Black’s Law Dictionary”, Thomson West)
(Elizabeth A Martin and Jonathan Law (2006): “Oxford Dictionary of Law”,
Oxford University Press)
Chow (2006) “Contract is a legally binding agreement formed when
one party accepts an offer made by another and which fulfills the
conditions”
(Chow Kok Fong (2006):” Construction Contracts Dictionary”, Sweet & Maxwell Asia)
John Adriaanse (2007) “A variety of factors makes a construction
contract different from most other types of contracts. These include
the length of the project, its complexity, its size and the fact that the
price agreed and the amount of work done may change as it
proceeds
John Adriaanse (2007): “Construction Contract Law”
ADMINISTRASI KONTRAK:
Administrasi Kontrak bukan hanya melaksanakan
pekerjaan administrasi dari suatu kontrak
melainkan adalah ”cara mengelola kontrak”.
The Contract for Construction: The Contractor to
“CONSTRUCT” in accordance with the Contract
and The Employer to “PAY” for them”. It describes
comprehensively what the`works are, and how
payment is to be made.
Pekerjaan administrasi kontrak sudah harus dimulai
jauh sebelum kontrak ditandatangani, oleh
pengguna jasa maupun penyedia jasa:
© Sarwono Hardjomuljadi
FIDIC CC for Works of Civil Engineering Construction 4th edition
(1987)
FIDIC CC for Works of Civil Engineering Construction 3rd edition
(1977)
FIDIC CC for Works of Civil Engineering Construction 2nd edition
(1969)
FIDIC CC for Works of Civil Engineering Construction 1st edition
(1957)
General Condition of Contract ICE 3rd edition
(1945)
th
FIDIC CC for Construction 1st edition
(1999)
FIDIC CC for Construction MDB Harmonised Edition
(2006)
 Which contract to be used
STRAIGHT
FORWARD PROJECT
EMPLOYER
DESIGN
CONTRACTOR DESIGN
Plant and/or high unforeseen risks
Fixed price - lump sum
Little employer involvement
No major unforeseen risks
no
no
no
DISCUSS IN DETAIL
Employer’s requirements
with the Contractor, and
negotiate a modified FIDIC
contract
no
yes
yes
yes
Maintenance
yes
yes
no
© Sarwono Hardjomuljadi
Berdasarkan cara pembayaran:
Lumpsum Contract
Lumpsum Contract adalah kontrak pengadaan jasa
pelaksanaan konstruksi atas penyelesaian seluruh pekerjaan
dalam batas waktu tertentu, dengan jumlah harga pasti dan
tetap, dan resiko yang mungkin terjadi dalam proses
penyelesaian pekerjaan sepenuhnya ditanggung penyedia
jasa.
Unit Price Contract
Unit Price Contract adalah kontrak pengadaan jasa
pelaksanaan konstruksi atas penyelesaian seluruh pekerjaan
dalam batas waktu tertentu berdasarkan harga satuan untuk
setiap satuan/unsur pekerjaan dengan spesifikasi teknis
tertentu, yang kuantitas pekerjaannya masih bersifat
perkiraan sementara, sedangkan pembayarannya didasarkan
pada hasil pengukuran bersama atas kuantitas pekerjaan
yang telah dilaksanakan oleh penyedia jasa.
© Sarwono Hardjomuljadi
FIDIC GCC for Works of Civil
Engineering Construction
2nd edition (July 1969)
Clause 5: Extent of Contract.
5. The contract comprises the
construction………….everything whether of a temporary or
permanent nature required in and for such construction
completion and maintenance so far as the necessity for providing
the same is specified in or reasonably to be inferred from the
Contract.
© Sarwono Hardjomuljadi
Case:
During the execution of Saguling Hydro Electric Power
Plant Project, in the employer’s opinion, the additional
slope protection by full column adhesive rock-bolt was
inferred as necessary due to the excavation shape and the
extent of weathered rock. In the contractor’s opinion, the
full column adhesive rock bolt was not specified in the
contract.
The different interpretation encouraged the contractor to
submit their claim which finally became disputes between
two parties and proofed that the ambiguities of wording
may lead to disputes.
FIDIC GCC for Works of Civil Engineering Construction 3rd edition
(March 1977) [1]
Clause 8: Contractor’s General Responsibilities.
(1) The Contractor shall, subject to the provision of the
Contract……………….whether of a temporary or permanent nature, required in
and for such execution and maintenance, so far as the necessity for providing the
same is specified in or reasonably to be inferred from the Contract.
(2) The Contractor shall take full responsibility……………….provided that the
Contractor shall not be responsible, except as may be expressly provided in the
Contract, for the design or specification of the Permanent Works, or of the
design or specification of any Temporary Works prepared by the Engineer.
© Sarwono Hardjomuljadi
Case:
During the execution of Cirata Hydro Electric Power Plant
Project under the Clause 5 which then became Clause 8 in
the 3rd edition (as an improvement to make it more fair
and balanced), the contractor was not responsible for the
temporary works which design and specification were not
prepared by the contractor but the engineer.
A different interpretation again occurred. The engineer
rejected to issue the payment for the bridge strengthening
required for the mobilization of contractor’s plant. The
bridge was actually the temporary facilities provided by
the employer and was done by other contractor
(infrastructure contractor). It was designed as temporary
bridge by the former contractor (not the engineer) and the
engineer considered that during the tender stage the
bridge condition should be checked by the contractor and
become the contractor responsibility as a part of working
method. It then became a dispute after a lengthy
discussion without conclusion.
FIDIC GCC for Works of Civil Engineering Construction 4thedition
(1987 amended 1992)
Clause 8.1: Contractor’s General Responsibilities
8.1 The Contractor shall, with due care and diligence, design (to the
extent provided for by the Contract), execute and complete the
Works………….whether of a temporary or permanent nature, required in and for
such design, execution, completion and remedying of any defects, so far as the
necessity for providing the same is specified in or is reasonably to be inferred
from the Contract.
Clause 8.2: Site Operations and Method of Construction
8.2 The contractor shall take full responsibility…………….Provided that
the Contractor shall not be responsible (except as stated hereunder or as may
be otherwise agreed) for the design or specification of Permanent Works, or
for the design or specification of any Temporary Works not prepared by
the Contractor.
© Sarwono Hardjomuljadi
Case:
During the execution of Renun Hydro Electric Power
Plant Project, the extent of Clause 5 (2nd edition) and
Clause 8 (3rd edition) then became 8.1 and 8.2 in the
4th edition were means to reduce the dispute possibility.
Under these clauses, contractor was only responsible for
the design or specification prepared by himself but
irresponsible for the design and specification prepared
by other parties.
FIDIC GCC for Construction 1st edition (1999)
Clause 4.1: Contractor’s General Obligations
4.1 The Contractor shall design (to the extent specified in the
Contract), execute and complete the Works in accordance with the
Contract and with the Engineer’s Instruction, and shall remedy any
defects in the Works.
The Contractor shall be responsible for the adequacy, stability and
safety of all Site operations and of all methods of construction. Except to the
extent specified in the Contract, the Contractor (i) shall be responsible for
all Contractor’s Documents, Temporary Works, and such design of each
item of Plant and Materials as is required for the item to be in
accordance with the Contract, and (ii) shall not otherwise be
responsible for the design or specification of the Permanent Works.
© Sarwono Hardjomuljadi
The above clause is the final revision which clarifies
contractor’s responsibilities. Contractor is responsible for
the design of all contractor’s documents, temporary
works, the design of plant and material as is required for
the item to be in accordance with the Contract, and the
contractor will be irresponsible for the design and
specification of permanent works, means that everything
not mentioned in the contract is not the contractor’s
responsibility.
1 + 2 = 3
Persyaratan teknis memastikan spesifikasi
yang harus dipenuhi, Siapapun yang akan
mempunyai pendapat yang sama untuk
capaian yang diinginkan.
1 + 2 = 3 atau 1 + 2 = ?
Persyaratan umum kontrak.memuat persyaratan yang
bisa ditafsirkan berbeda oleh para pihak.
MODIFIED CONDITIONS OF CONTRACT BY THE EMPLOYER
Employer’s Reason : To avoid the Contract’s Cost Overrun
WON BY EMPLOYERWON BY CONTRACTOR
CONTRACT PRICE NOT INCREASE
POSSIBLY BAD QUALITY
DELAY IN OPERATION OF THE PREMISES
FOR REVENUE
INCREASE OF CONTRACT PRICE
IMPACT TO THE EMPLOYER
POSSIBLY PROJECT
COMPLETION DELAY
CLAIMS
© Sarwono Hardjomuljadi
KASUS KONTRAK KONSTRUKSI
(Interpretasi Kontrak)
2000.01.01
Commencement Date
Scheduled Starting date of
contractor’s activity and Possession
of Site [Clause 2.1] refer to Sub-
Clause 8.3 [Programme]
2000.03.01
2000.03.01 2000.04.012000.03.20
Actual Possession of site [Clause 2.1],
(3 stages) without disruption to the
contractor’s activities
Actual start of
contractor’s activity
2000.05.01
Employer’s barrier for Clause 20:
1. Payment of Performance Security
2. Right to Claim if suffer delay
start of contractor’s
activity
© Sarwono Hardjomuljadi
Kontraktor melaksanakan beberapa item pekerjaan pada proyek
jalan bebas hambatan sesuai spesifikasi dan gambar, tetapi karena
kuantitas pekerjaan sudah mencapai volume yang ada dalam BOQ
untuk pekerjaan tersebut, misalnya item pekerjaan galian struktur,
kontraktor memutuskan untuk menghentikan pekerjaan
Padahal jika pekerjaan ini tidak terselesaikan terlebih dahulu maka
banyak item pekerjaan lain yang tidak dapat dimulai
pelaksanaannya misalnya grade preparation, common
embankment. Dalam klausul kontrak disebutkan bahwa kuantitas
pekerjaan yang ada dalam BoQ adalah pekiraan dan tidak dapat
digunakan sebagai kuantitas aktual dan benar (GCC 14.1.c).
Hal yang harus diperhatikan: Hirarki dokumen tender, unit price atau lumpsum,
perintah perubahan
Setelah melakukan rekayasa lapangan pada masa mobilisasi bersama
dengan Enjinir dan PPK, disimpulkan bahwa terdapat pekerjaan major
yang pay itemnya tidak termasuk dalam BOQ misalnya Galian Batu
pada tebing dimana pada tahap desain diidentifikasi sebagai Galian
Biasa. Jika pekerjaan tersebut tidak dilaksanakan, maka pekerjaan
lain yang merupakan critical path seperti penyiapan drainase dan
penyiapan badan jalan untuk pelebaran tidak dapat dimulai.
Penambahan biaya yang cukup besar menyulitkan pengguna jasa
dalam mengambil keputusan.
Karena tidak adanya kepastian dalam proses dan persetujuan VO
maka kontraktor memutuskan untuk menghentikan pekerjaan yang
pasti akan mengakibatkan keterlambatan proyek secara keseluruhan.
Hal yang harus diperhatikan: status penandatanganan kontrak, value enjiniring
Setelah melakukan rekayasa lapangan pada masa mobilisasi bersama
dengan Enjinir dan PPK, disimpulkan bahwa terdapat pekerjaan major
yang pay itemnya tidak termasuk dalam BOQ misalnya Galian Batu
pada tebing dimana pada tahap desain diidentifikasi sebagai Galian
Biasa. Jika pekerjaan tersebut tidak dilaksanakan, maka pekerjaan
lain yang merupakan critical path seperti penyiapan drainase dan
penyiapan badan jalan untuk pelebaran tidak dapat dimulai.
Penambahan biaya yang cukup besar menyulitkan pengguna jasa
dalam mengambil keputusan.
Karena tidak adanya kepastian dalam proses dan persetujuan VO
maka kontraktor memutuskan untuk menghentikan pekerjaan yang
pasti akan mengakibatkan keterlambatan proyek secara keseluruhan.
Hal yang harus diperhatikan: status penandatanganan kontrak, value enjiniring
Kontraktor telah melaksanakan item pekerjaan masonry wall
sesuai dengan gambar tetapi memutuskan untuk
menghentikan pekerjaan tersebut karena ada item pekerjaan
lanjutan seperti filter material for backfilling tidak masuk
dalam BoQ. Kontraktor meminta adanya VO kepada Enjinir
yang diteruskan kepada PPK untuk memasukkan pay item
baru. Sebagaimana diketahui, persyaratan kontrak GCC 3.1
menyebutkan bahwa Enjinir harus mendapatkan persetujuan
dari Pengguna Jasa sebelum dapat melakukan Variasi
Kontrak.
Kontraktor mengingatkan bahwa meninggalkan pekerjaan
tersebut tanpa kepastian akan membahayakan pada
konstruksi yang ada.
Hal yang harus diperhatikan: keadaan darurat, klaim
Dalam gambar design Kontraktor diminta untuk melaksanakan pekerjaan borepile
dimana elevasi pile tip yang telah ditentukan berada 10 meter dibawah lapisan
tanah keras atau batu. Karena diperkirakan akan menjadi kendala maka pada saat
tender alat borepile menjadi salah satu kriteria evaluasi. Pada saat pelaksanaan
pekerjaan Kontraktor pemenang menyatakan tidak sanggup melakukan
pengeboran pada lapisan keras dan menghentikan pekerjaan di atas lapisan keras
tersebut dan meminta kepada Enjinir agar dapat menerima kondisi lapangan
dengan membuat justifikasi teknis yang melampirkan data boring baru yang
menunjukkan ada perbedaan klasifikasi lapisan keras disertai perhitungan
perkuatan pondasi dengan penambahan jumlah dan perubahan konfigurasi
borepile. Berdasarkan hasil evaluasi dengan mempertimbangan kondisi lapangan
dan pengalaman dilokasi lain, Enjinir menolak permintaan kontraktor dan
menginstruksikan untuk melanjutkan pengeboran sampai kedalaman yang tertera
pada gambar. Kontraktor tidak mengikuti instruksi Enjinir dan melanjutkan
pekerjaan pengecoran borepile pada kedalaman diatas tanah keras dan
melakukan perubahan konfigurasi atas dasar instruksi langsung dari Pengguna
Jasa walaupun Justifikasi Teknis belum disetujui Enjinir.
Hal yang harus diperhatikan: pemahaman kontrak, klaim
Kontraktor memberikan sebagian pekerjaan kepada beberapa
subkontraktor lokal atas permintaan informal Daerah untuk
pemberdayaan pengusaha lokal tanpa melaporkan ke pada Enjinir
untuk mengerjakan pekerjaan critical path seperti masonry wall,
side ditch dan box culvert, ternyata dalam pelaksanaannya
pekerjaan-pekerjaan tersebut kemajuan (progress) nya sangat
terlambat.
Karena hal tersebut pekerjaan yang akan dilakukan Kontraktor
Utama menjadi terhambat.
Kontraktor berdasarkan persyaratan kontrak mengajukan revisi
program. Setelah dilakukan evaluasi terlihat bahwa secara realistis
program tersebut tidak akan dapat dilakukan tanpa perpanjangan
waktu.
Hal yang harus diperhatikan: subkontraktor, lintasan kritis, EOT.
AKHIR SESI 1:
Administrasi Kontrak
(2.Administrasi)
Administrasi Kontrak
Definisi:
 Seni untuk mengelola semua aspek dari implementasi
proyek.
 Pemahaman dan penggunaan aturan kontrak –siapa
melakukan apa, bilamana dan bagaimana.
SHM
Kontrak
 Kesepakatan antara 2 pihak dengan tanggung
jawab masing-masing.
 Penawaran dari satu pihak disetujui oleh pihak
lainnya.
SHMSHM
Para Pihak dalam Kontrak
 Kontrak adalah antara Pengguna Jasa dan
Kontraktor.
 Pengguna Jasa dapat mendelegasikan sebahagian
kwenangannya kepada “EnjinIr” untuk melaksanakan
Administrasi Kontrak.
 Enjinir adalah agen dari Pengguna Jasa.
 Kontrak mendefinisikan peran Enjinir dan mengatur
bagaimana para pihak harus berinteraksi.
SHMSHM
Hubungan para pihak dalam Kontrak
Pengguna Jasa
Enjinir
Kontraktor
Penandatangan Kontrak
Tidak ada kontrak atau
perjanjian
Perjanjian untuk memberikan
Layanan Profesional
Notes:
Kontrak Konstruksi menempatkan Enjinir di anatara
Pengguna Jasa dan Kontraktor/
SHM
Bagaimana mendapatkan
Kontrak
Penyiapan Pelelangan
 Desain and Dokumen Lelang
Proses Pelelangan
 Undangan lelang (pra/pasca kualifikasi)
 Penyampaian penawaran
 Evaluasi penawaran (kualitas dan harga)
 Catatan: QCBS (Quality-Cost Based Selection)
 Surat Penunjukan
SHMSHM
Penerbitan
Dokumen
Lelang
Penyampaian
Dokumen
Penawaran
Penerbitan
Surat
Penunjukan
Tanggal
Mulainya
Pekarjaan
Penerbitan
Berita Acara
Serah Teima 1
Penerbitan
Berita Acara
Serah Teima 2
Masa Penyiapan
Penawaran
Masa Evalusai
Penawaran
Penerbitan Jaminan
Pelaksanaan
Masa
Pelaksanaan
Pekerjaan
Masa
Pemberitahuan
Cacat Mutu
Pengembalian
Jaminan
Pelaksanaan
(Akhir Kontrak)
Tahapan Pelelangan hingga Penyelesaian Pekerjaan
SHM
Penyiapan Kontrak
 Penyiapan dan penandatanganan kontrak (para
pihak)
 Jaminan Pelaksanaan (Kontraktor)
SHMSHMSHM
Dokumen Kontrak
 Perjanjian Kontrak
 Surat Penunjukan
 Dokumen Penawaran
 Persyaratan Khusus Kontrak Bagian A (Data Kontrak)
 Persyaratan Khusus Kontrak Bagian B
 Persyaratan Umum Kontrak
 Spesifikasi Khusus
 Spesifikasi Umum
 Gambar-gambar
 Daftar-daftar (BOQ, dsb.)
 Dokumen-dokumen terkait lainnya
SHMSHMSHMSHM
Persyaratan Umum Kontrak
 Aturan yang disepakati untuk pelaksanaan
Adfministrasi Kontrak
 Menetapkan peran dan tanggung jawab para pihak
dalam kontrak, antara Pengguna Jasa dan
Kontraktor.
 Dilengkapi dengan Persyaratan Khusus.
SHMSHMSHMSHMSHM
Apa yang diharapkan dari
Persyaratan Umum Kontrak ?:
 Adil dan Berimbang
 Jelas, rasional dan mudah dipahami
 Menyeluruh dan luwes
 Teruji dengan rekam jejak yang baik
 Independen
 Dikenal dan diakui
FIDIC Conditions of Contract memenuhi semua hal di
atas.
SHMSHMSHMSHMSHM
FIDIC
 FIDIC adalah Federasi Internasional Konsultan
Enjiniring didirikan pada tahun 1913.(Fédération
Internationale des Ingénieurs-Conseils)
 FIDIC beranggotakan lebih dari 80 negara di dunia.
 Tujuan– meningkatkan profesionalisme dari
anggotanya dan menyebarluaskan informasi.
SHMSHMSHMSHMSHMSHM
Peran Pengguna Jasa
Menurut kontrak:
 Memberikan penguasaan lahan
 Membantu Kontraktor dalam mendapatkan izin,
lisensi dsb.
 Menjamin kerjasama antar personil dan kontraktor
lain yang bekerja untuk Pengguna Jasa.
 Menyiapkan bukti ketersediaan anggaran.
 Menyampaikan pemberitahuan klaim Pengguna
Jasa.
SHMSHMSHMSHMSHMSHM
Peran Pengguna Jasa
Dua tanggung jawab utama:
 Menunjuk dan mendelegasikan kepada Enjinir.
 Membayar kepada Kontraktor dengan jumlah
yang ditetapkan oleh Enjinir.
Pengguna Jasa mempunyai banyak tanggung
jawab lain dalam pelaksanaan proyek- tetapi ini
berada di luar kontrak.
SHMSHMSHMSHMSHMSHMSHM
Peran Enjinir
 Enjinir adalah seseorang yang ditunjuk untuk
bertindak untuk dan atas nama Pengguna Jasa.
 Kontrak menetapkan tugas Enjinir dengan
pembatasan, sesuai dengan surat
penunjukkannya.
SHMSHMSHMSHMSHMSHMSHMSHM
Peran Enjinir
 Kewenangan
 Kebebasan
 Keterampilan
 Penetapan
 Instruksi
 Pendelegasian
 Penggantian
SHMSHMSHMSHMSHMSHMSHMSHMSHM
Peran Enjinir
Enjinir harus mendapat persetujuan spesifik dari
Pengguna Jasasebelum mengambil tindakan dalam
hal:
 Menyetujui atau menetapkan tambahan biaya.
 Menyetujui suatu perpanjangan waktu.
 Menginstruksikan Variasi, kecuali:
 Dalam keadaan darurat
 Jika variasi akan menambah nilai
kontrak dengan jumlah lebih kecil
dari persentasi yang dinyatakan
dalam kontrak.
SHMSHMSHMSHMSHMSHMSHMSHMSHM
Peran Kontraktor
 Melaksanakan dan menyelesaikan pekerjaan
sesuai dengan Kontrak dan sesuai dengan
Instruksi Enjinir dan harus memperbaiki cacat
mutu dalam Pekerjaan.
 Menyiapkan semua yang dibutuhkan untuk
pelaksanaan dan penyelesaian.
 Bertanggung Jawab atas Penjagaan Pekerjaan.
 Bertanggung Jawab atas keselamatan kerja dan
pengamanan lingkungan.
 Tugas-tugas terkait pelaksanaan konstruksi.
SHMSHMSHMSHMSHMSHMSHMSHMSHM
Peran Kontraktor
 Tugas terkait pelaksanaan konstruksi
 Desain sesuai kebutuhan
 Menentukan metode pelaksanaan konstruksi.
 Menata batas-batas kerja
 Melaksanakan QC dan QA
 Melaporkan “adverse physical conditions” etc.
 Bertanggung jawab atas peralatannya.
 Menjaga kebersihan lapangan, memelihara akses.
 Menyiapkan “as-built drawings”
 Memperbaiki cacat mutu
SHMSHMSHMSHMSHMSHMSHMSHMSHM
Peran Kontraktor
Persyaratan Administratif:
 Menyiapkan Jaminan Pelaksanaan (atas biaya
Kontraktor) dan menyampaikannya kepada
Pengguna Jasa.
 Mengasuransikan sesuai dengan ketentuan
kontrak.
 Menyimpan semua catatan sebagai pendukung
proses pembayaran.
 Menyiapkan dan menyampaikan Laporan
Kemajuan Pekerjaan Bulanan
SHMSHMSHMSHMSHMSHMSHMSHMSHMSHM
Peran Kontraktor
Kuasa Kontraktor
 Kontraktor harus menunjuk kuasanya (General
Superintendent) dan memberikan semua
kewenangan yang dibutuhkan untuk bertindak
untuk dan atas nama Kontraktor.
 Kuasa Kontraktor harus berkedudukan di
“lapangan”
SHMSHMSHMSHMSHMSHMSHMSHMSHMSHM
Peran Kontraktor
Sub – Kontraktor
 Kontraktor tidak boleh mensubkontrakkan
keseluruhan pekerjaan.
 Kontraktor membutuhkan izin dari Enjinir untuk
mensub-kontrakkan sebagian pekerjaannya.
 Semua persyaratan yang berlaku bagi kontraktor
harus juga berlaku untuk Sub-Kontraktor.
SHMSHMSHMSHMSHMSHMSHMSHMSHMSHM
UNIVERSITAS ATMA JAYA YOGYAKARTA
18 – 19 Februari 2011
Variasi atas Kontrak
Variasi kontrak mengizinkan perubahan atas
pekerjaan yang dikontrakkan.
Meliputi:
 Pekerjaan Tambah
 Revisi atas pekerjaan desain – mutu, jenis,
kuantitas, dsb.
 Revisi atas waktu penyelesaian
(perpanjangan waktu)
SHMSHMSHMSHMSHMSHMSHMSHMSHMSHM
Perpanjangan Waktu
 Enjinir dapat memberikan perpanjangan
waktu penyelesaian sehubungan dengan
adanya perintah variasi.
 Jika Kontraktor beranggapan bahwa
kejadian-kejadian menyebabkan kontraktor
berhak mendapatkan suatu perpanjangan
waktu, ia harus menyampaikan
pemberitahuan kepadaa Enjinir.
SHMSHMSHMSHMSHMSHMSHMSHMSHMSHM
Ganti Rugi akibat keterlambatan
 Jika Kontraktor gagal menyelesaikan kontrak dalam
jangka waktu yang ditentukan pada dokumen
kontrak atau tanggal lain sebagai akibat adanya
perpanjangan waktu Kontraktor harus membayar
ganti rugi akibat keterlambatan.
 Jumlah dan batasan dari ganti rugi akibat
keterlambatan dinyatakan dalam Data Kontrak.
SHMSHMSHMSHMSHMSHMSHMSHMSHMSHM
Klaim oleh Kontraktor
 Kontraktor harus menyampaikan pemberitahuan
(sesuai jangka waktu yang ditetapkan dalam
kontrak) kepada Enjinir jika ia beranggapan berhak
untuk mendapatkan tambahan pembayaran atau
perpanjangan waktu.
 Kontraktor harus menyimpan catan-catatan untuk
mendukung penyampaian klaim.
 Persyaratan Umum Kontrak menetapkan batasan
waktu untuk penyampaian klaim dan tangapan.
SHMSHMSHMSHMSHMSHMSHMSHMSHMSHM
Waktu Penyelesaian
 Waktu penyelesaian dinyatakan dalam Data
Kontrak (x hari kalender)
 Waktu penyelesaian dihitung dari tanggal
mulainya pelaksanaan (commencement date).
 Tanggal mulainya pelaksanaan adalah setelah
diterbitkannya Instruksi Enjinir (dan telah diterima
oleh kontraktor) untuk mulai bekerja (instruksi
enjinir diterbitkan setelah dipenuhinya beberapa
persyaratan).
SHMSHMSHMSHMSHMSHMSHMSHMSHMSHMSHM
Program Pelaksanaan
 Kontraktor harus menyampaikan program rinci kepada
Enjinir dalam jangka waktu 28 hari setelah
pemberitahuan mulainya pekerjaan (Klausula 8).
 Kontraktor harus memulai pekerjaan sesuai dengan
program pelaksanaannya.
 Jika kemajuan pekerjaan aktual tidak komnsisten
dengan program pelaksanaan kontraktor harus
menyampaikan program revisi.
SHMSHMSHMSHMSHMSHMSHMSHMSHMSHMSHM
Tingkat Kemajuan Pekerjaan
Jika suatu saat:
 Kemajuan pekerjaan terlalu lambat untuk
menyelesaikan pekerjaan dalam waktu penyelesaian
sesuai kontrak,atau
 Kemajuan pekerjaan berada di belakang program
yang berlaku saat ini.
Kontraktor harus menyampaikan program revisi
menunjukkan bagaimana kemajuan pekerjaan dapat
diakselerasi dan penyelesaian dapat dicapai.
SHMSHMSHMSHMSHMSHMSHMSHMSHMSHMSHM
Kegagalan untuk melanjutkan
pekerjaan
 Kegagalan berlanjut dan tidak terjamin untuk
melanjutkan pekerjaan sesuai dengan program
kerjanya dapat dianggap sebagai pelanggaran
kontrak.
 Sesuai Klausula 15.2, Kontraktor tanpa alasan yang
wajar, gagal untuk melanjutkan pekerjaan sesuai
dengan Klausula 8, maka Penghentian Kontrak
dimungkinkan.
SHMSHMSHMSHMSHMSHMSHMSHMSHMSHMSHM
Dokumentasi
 Nilai dan pentingnya dokumen yang baik tidak
perlu dibesar-besarkan.
 Penyimpanan catatan-catatan yang jelas dan
akurat harus menanamkan sebagai kebiasaan
bagi semua staff di lapangan.
SHMSHMSHMSHMSHMSHMSHMSHMSHMSHMSHM
Dokumentasi
 Dokumentasi lapangan seringkali merupakan
masukan yang paling berharga dalam
penyelesaian sengketa dan klaim.
 Dokumentasi termasuk:
 Catatan Harian, Instruksi Lapangan /
Permohonan.
 Penyampaian catatan-catatan
 Data pendukung (pengukuran, pengetesan dsb)
untuk Interim Payment Certificate (IPC)
 Pengiriman pemberitahuan, tagihan, jadwal dsb.,
SHMSHMSHMSHMSHMSHMSHMSHMSHMSHMSHM
Mutu
 Aspek terpenting untuk kesuksesan suatu proyek
adalah MUTU.
 Mutu pekerjaan adalah tanggung jawab kontraktor.
 Mutu dapat dicapai dengan menggunakan metode
kerja yang baik dengan sumber daya yang
memadai dan kesesuaian dengan Rencana Mutu
Terpadu.
SHMSHMSHMSHMSHMSHMSHMSHMSHMSHMSHM
Mutu
 QC dab QA harus dapat memperlihatkan bahwa
semua pekerjaan sesuai dengan persyaratan
standar mutu.
 The Enjinir harus melaksanakan pengecekan mutu
hingga ia puas bahwa pekerjaan memperlihatkan
kesesuaian dengan persyaratan kontrak.
SHMSHMSHMSHMSHMSHMSHMSHMSHMSHMSHM
Manajemen Mutu
Manajemen Mutu Kontraktor:
 Kontraktor, sebagai perusahaan, harus mempunyai
kebijakan yang jelas dalam hal mutu, dengan
dukungan dari atas.
 Kontraktor harus menominasikan Manajer Mutu di
lapangan.
 Manajer Mutu harus bebas dari GS.
SHMSHMSHMSHMSHMSHMSHMSHMSHMSHMSHM
Korupsi dan Praktek kecurangan
FIDIC GCC for Construction, MDB Harmonised
Edition mempunyai klausula untuk mencegah
korupsi (Klausula 15.6)
Jika Pengguna Jasa menetapkan bahwa
Kontraktor terlibat korupsi, kecurangan, kolusi
atau praktek pemaksaan maka Pengguna Jasa
dapat menghentikan hubungan kerja dengan
Kontraktor.
SHMSHMSHMSHMSHMSHMSHMSHMSHMSHMSHM
Akhir Sesi 2
SHMSHMSHMSHMSHMSHMSHMSHMSHMSHMSHM
Administrasi Kontrak
(3.Klaim dan Penyelesaian
Sengketa Konstruksi)
Hardjomuljadi et al (2006) [17] “Klaim
adalah suatu tindakan seseorang untuk
meminta sesuatu, dimana hak seseorang
tersebut telah hilang sebelumnya, karena
yang bersangkutan beranggapan
mempunyai hak untuk mendapatkannya
kembali”.
Garner (2004) [16] “A demand for money,
property, or a legal remedy to which one
asserts a right”
Martin and Law (2006) [18] “Claim is A
demand for a remedy or ascertain of a
right, especially the right to take a
particular case to court”
CLAIM
© Dr.Sarwono Hardjomuljadi
Hanvey (2005) [19]“ One of the most
common issues impacting construction
projects is inadequate or incomplete
design documents”
Fisk (2003) [21] “Differing site conditions is the one of the most
misunderstood of all contract provisions, and the one that is
frequently the cause of large contractor claims for additional work
and change orders”.
Arditi and Patel (1989) [20]
“ Most of the typical claims are caused by
factors differing site conditions”.
Barrie & Paulson (1992) [22] “Changed
conditions when the actual physical
conditions or other jobsite condition prove
different from those foreseeable from the
plans and specifications”
CLAIM
© Dr.Sarwono Hardjomuljadi
MODIFIED CONDITIONS OF CONTRACT BY THE EMPLOYER
Employer’s Reason : To avoid the Contract’s Cost Overrun
WON BY EMPLOYERWON BY CONTRACTOR
CONTRACT PRICE NOT INCREASE
POSSIBLY BAD QUALITY
DELAY IN OPERATION OF THE PREMISES
FOR REVENUE
INCREASE OF CONTRACT PRICE
IMPACT TO THE EMPLOYER
POSSIBLY PROJECT
COMPLETION DELAY
CLAIMS
© Sarwono Hardjomuljadi
(The action of demanding something, which one lost
before hand, because of one’s right to recover it).
Hardjomuljadi et al (2006)
Gambaran sederhana adalah
seseorang yang
mempergunakan jasa
angkutan udara akan
menyerahkan bagasinya
kepada perusahaan
penerbangan untuk
selanjutnya mengklaim
kembali bagasinya (baggage
claim) pada saat sampai
ditempat tujuan penerbangan
© Dr. Sarwono Hardjomuljadi
Contractual Claims
Klaim konstruksi di mana kontraktor secara nyata
memang berhak di bayar dengan cara reimbursement
dan secasra jelas mermpunyai dasar legal yang
tercantum dalam kontrak seperti misalnya klaim
upc.
Non-Contractual Claims
Klaim konsatruklsui yang cara penyelesaiannya
secara spesifik tidak diretapkan dalam kontrak,
misalnya klaim, karena perubahan nilai tukar., ex
gratia claims.
© Dr. Sarwono Hardjomuljadi
EMPLOYER’S CLAIM
FIDIC MDB 2010 Clause 2.5
Employer’s Claims
If the Employer considers himself to be entitled to any payment under
any Clause of these Conditions or otherwise in connection with the
Contract, and/or to any extension of the Defects Notification Period, the
Employer or the Engineer shall give notice and particulars to the
Contractor. However, notice is not required for payments due under Sub-
Clause 4.19 [Electricity, Water and Gas], under Sub-Clause 4.20
[Employer’s Equipment and Free-Issue Materials], or for other services
requested by the Contractor.
The notice shall be given as soon as practicable, of the event or
circumstances giving rise to the claim. A notice relating to any extension
of the Defects Notification Period shall be given before the expiry of
such period.
FIDIC MDB 20 Clause 2.5 Employer’s Claims
If the Employer considers himself to be entitled to any payment under any
Clause of these Conditions or otherwise in connection with the Contract,
and/or to any extension of the Defects Notification Period, the Employer or
the Engineer shall give notice and particulars to the Contractor. However,
notice is not required for payments due under Sub-Clause 4.19 [Electricity,
Water and Gas], under Sub-Clause 4.20 [Employer’s Equipment and Free-
Issue Materials], or for other services requested by the Contractor.
The notice shall be given as soon as practicable and no longer than 28
days after the Employer became aware, or should have become
aware, of the event or circumstances giving rise to the claim. A notice
relating to any extension of the Defects Notification Period shall be given
before the expiry of such period.
CONTRACTOR’S CLAIM
Clause 20
Claims, Disputes and Arbitration
20.1
Contractor’s Claims
If the Contractor considers himself to be entitled to any extension of
the Time for Completion and/or any additional payment, under any
Clause of these Conditions or otherwise in connection with the
Contract, the Contractor shall give notice to the Engineer, describing
the event or circumstance giving rise to the claim. The notice shall be
given as soon as practicable, and not later than 28 days after the
Contractor became aware, or should have become aware, of the event
or circumstance.
- Hak kontraktor untuk mengajukan klaim EOT & Additional Payment
- Pembeitahuan atas kemungkinan klaim dan batas waktu penyampaiannya.
© Dr. Sarwono Hardjomuljadi
The Contractor shall keep such contemporary records as may be
necessary to substantiate any claim, either on the Site or at another
location acceptable to the Engineer. Without admitting the Employer’s
liability, the Engineer may, after receiving any notice under this Sub-
Clause, monitor the record-keeping and/or instruct the Contractor to keep
further contemporary records. The Contractor shall permit the
Engineer to inspect all these records, and shall (if instructed) submit
copies to the Engineer.
Clause 20
Claims, Disputes and Arbitration
20.1
Contractor’s Claims
- Tentang catatan lengkap (contemporary record).
- Hak Enjinir untuk memeriksa catatan
Each Payment Certificate shall include such additional payment for any
claim as have been reasonably substantiated as due under the relevant
provision of the Contract.
Unless and until the particulars supplied are sufficient to substantiate the
whole of the claim, the Contractor shall only be entitled to payment for
such part of the claim as he has been able to substantiate.
Clause 20
Claims, Disputes and Arbitration
20.1
Contractor’s Claims
- Setiap BA Pembayaran harus termasuk tambahan biaya klaim, dalam hal
belum dapat disetujui, diberi tanda bintang.
20.2
Appointment of the Dispute Board
Disputes shall be referred to a DB for decision in accordance with
Sub-Clause 20.4[Obtaining Dispute Board’s Decision]. The Parties
shall appoint a DB by the date stated in the Contract Data.
The DB shall comprise, as stated in the Contract Data, either one or
three suitablyqualified persons (“the members”), each of whom shall
be fluent in the language forcommunication defined in the Contract
and shall be a professional experienced in thetype of construction
involved in the Works and with the interpretation of
contractualdocuments. If the number is not so stated and the Parties
do not agree otherwise, the DB shall comprise three persons.
- Tentang Penunjukan Dewan Sengketa
Clauses requiring notice by the Contractor (1)
1.8 Care and Supply of Documents
1.9 Delayed Drawings or Instructions
1.13 Compliance with Laws
2.1 Right of Access to the Site
3.4 Replacement of the Engineer
4.3 Contractor’s Representative
4.4 Subcontractors
4.7 Setting Out
4.12 Unforeseeable Physical Conditions
4.16 Transport of Goods
4.20 Employer’s Equipment and Free-Issue Materials
4.21 Progress Reports
4.24 Fossils
Clauses requiring notice by the Contractor (2)
5.2 Objection to Nomination
7.3 Inspection
7.4 Testing
8.3 Programme
8.4 Extension of Time for Completion
8.9 Consequences of Suspension
8.11 Prolonged Suspension
9.1 Contractor’s Obligations [Tests on Completion]
9.2 Delayed Tests
10.1 Taking Over of the Works and Sections
10.2 Taking Over of Parts of the Works
10.3 Interference with Tests on Completion
12.1 Works to be Measured
Clauses requiring notice by the Contractor (3)
12.4 Omissions
13.1 Right to Vary
13.7 Adjustments for Changes in Legislation
16.1 Contractor’s Entitlement to Suspend Work
16.2 Termination by Contractor
17.4 Consequences of Employer’s Risks
17.5 Intellectual and Industrial Property Rights
18.1 General Requirements for Insurances
18.2 Insurance for Works and Contractor’s Equipment
19.2 Notice of Force Majeure
19.3 Duty to Minimise Delay
19.6 Optional Termination, Payment and Release
19.7 Release from Performance
20.1 Contractor’s Claims
20.4 Obtaining Dispute Board’s Decision
Mobile +62 811 844 903
eMail sarwonohm2@yahoo.co.id
The Dispute Resolution Board Foundation
19550 International Blvd. South, Suite 314 ; Seattle, WA 98188 USA
Tel 206-878-3336 ; Facsimile 206-878-3338 ; Toll-free USA 888-523-5208
eMail: info@drb.org ; website: www.drb.org
Dr. Sarwono Hardjomuljadi
Country Representative for Indonesia
Bab I Ketentuan Umum Pasal 1 Butir 10
Alternatif Penyelesaian sengketa adalah lembaga penyelesaian sengketa atau beda
pendapat melalui prosedur yang disepakati para pihak, yaitu penyelesaian di luar
pengadilan dengan cara konsultasi, negosiasi, konsiliasi, atau penilaian ahli.
Bab II Alternatif Penyelesaian Sengketa PAsal 6 Butir 1
Sengketa atau beda pendapat perdata dapat diselesaikan oleh para pihak melalui
alternatif penyelesaian sengketa yang didasarkan pada itikad baik dengan
mengesampingkan penyelesaian secara litigasi di Pengadilan Negeri.
Bab II Alternatif Penyelesaian Sengketa PAsal 6 Butir 7
Kesepakatan penyelesaian sengketa atau beda pendapat secara tertulis adalah final dan
mengikat para pihak untuk dilaksanakan dengan itikad baik serta wajib didaftarkan di
Pengadilan negeri dalam waktu paling lama 30 hari sejak tanggal penandatanganan.
Catatan:
Undang-undang ini mengatur penyelesaian sengketa yang secara tegas mencantumkan
dalam perjanjian kontraknya bahwa semua sengketa atau beda pendapat yang timbul
atau mungkin timbul dari hubungan hukum tersebut akan diselesaikan dengan cara
arbitrase atau melalui alternatif penyelesaian sengketa.
Related Regulation in Indonesia
Undang-undang No. 30 / 1999
Re: Arbitrase dan Alternatif Penyelesaian Sengketa
Related Regulation
FIDIC Conditions of Contract for Construction MDB Harmonised Ed. 2010
Clause 20 Claims, Disputes and Arbitration
Clause 20 Point 2 Appointment of the Dispute Board
The DB shall comprise, as stated in the Contract Data, either one or three
suitably qualified persons (“the members”), each of whom shall be fluent in the
language for communication defined in the Contract and shall be a professional
experienced in the type of construction involved in the Works and with the
interpretation of contractual documents. If the number is not so stated and the
Parties do not agree otherwise, the DB shall comprise three persons.
If the parties have not jointly appointed the DB 21 days before the date stated
in the Contract Data and the DB is comprise three persons, each Party shall
nominate one member for the approval of the other Party. The first two
members shall recommend and the Parties shall agree upon the third member,
who shall act as chairman.
Clause 20 Point 2 Appointment of the Dispute Board
The DB shall comprise, as stated in the Appendix to Tender, either one or
three suitably qualified persons (“the members”), If the number is not so
stated and the Parties do not agree otherwise, the DAB shall comprise three
p[ersons.
.
If the DAB is to comprise three persons, each Party shall nominate one
member for the approval of the other Party. The Parties shall consult both
these members and shall agree upon the third member, who shall be
appointed to act as chairman.
Related Regulation
FIDIC Conditions of Contract for Plant and Design Bulid 1999
Clause 20 Claims, Disputes and Arbitration
Related Regulation
FIDIC Conditions of Contract for EPC/Turnkey 1999
Clause 20 Claims, Disputes and Arbitration
Clause 20 Point 2 Appointment of the Dispute Board
The DB shall comprise, as stated in the Particular Conditions, either one or
three suitably qualified persons (“the members”), If the number is not so
stated and the Parties do not agree otherwise, the DAB shall comprise three
persons.
.
If the DAB is to comprise three persons, each Party shall nominate one
member for the approval of the other Party. The Parties shall consult both
these members and shall agree upon the third member, who shall be
appointed to act as chairman.
DB/DRB/
DAB
84 days
(Clause 20.4 Para 4)
84 days
(Clause 20.4 Para
5)Fail to
decide
Commence
of Arbitration
Decision
Agree
d
Notice of
Dissatisfication to
other Party
Final and
binding
Disagreed
© Sarwono Hardjomuljadi
Amicable
Setlement
Yes
28 days
(Clause 20.4 Para 5)
28 days
(Clause 20.4 Para 5)
56 days
(Clause 20.5 Para 1)
No
Clause 20,
Claims, Disputes and
Arbitration
TERIMA KASIH
AKHIR SESI 3:

Más contenido relacionado

La actualidad más candente

Aspek hukum perjanjian sewa menyewa
Aspek hukum perjanjian sewa menyewaAspek hukum perjanjian sewa menyewa
Aspek hukum perjanjian sewa menyewa
Leks&Co
 
107028040 rapat-persiapan-pelaksanaan-kontrak-pcm
107028040 rapat-persiapan-pelaksanaan-kontrak-pcm107028040 rapat-persiapan-pelaksanaan-kontrak-pcm
107028040 rapat-persiapan-pelaksanaan-kontrak-pcm
Bintek
 
fbb8a_3._PERSIAPAN_PELAKSANAAN_PEKERJAAN.PPT
fbb8a_3._PERSIAPAN_PELAKSANAAN_PEKERJAAN.PPTfbb8a_3._PERSIAPAN_PELAKSANAAN_PEKERJAAN.PPT
fbb8a_3._PERSIAPAN_PELAKSANAAN_PEKERJAAN.PPT
ArDiAn719274
 
Construction law basics 1103041
Construction law basics 1103041Construction law basics 1103041
Construction law basics 1103041
Dan Schleck
 

La actualidad más candente (20)

Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract forms
 
PCM Contoh Paparan Presentasi.ppt
PCM Contoh Paparan Presentasi.pptPCM Contoh Paparan Presentasi.ppt
PCM Contoh Paparan Presentasi.ppt
 
PENGENDALIAN KONTRAK JASA KONSTRUKSI (UP DATE).pdf
PENGENDALIAN KONTRAK JASA KONSTRUKSI (UP DATE).pdfPENGENDALIAN KONTRAK JASA KONSTRUKSI (UP DATE).pdf
PENGENDALIAN KONTRAK JASA KONSTRUKSI (UP DATE).pdf
 
Manajemen proyek konstruksi
Manajemen proyek konstruksiManajemen proyek konstruksi
Manajemen proyek konstruksi
 
Perjanjian pekerjaan pembangunan proyek (building work) (Beli Perjanjian, Hub...
Perjanjian pekerjaan pembangunan proyek (building work) (Beli Perjanjian, Hub...Perjanjian pekerjaan pembangunan proyek (building work) (Beli Perjanjian, Hub...
Perjanjian pekerjaan pembangunan proyek (building work) (Beli Perjanjian, Hub...
 
Legal Drafting
Legal DraftingLegal Drafting
Legal Drafting
 
Aspek hukum perjanjian sewa menyewa
Aspek hukum perjanjian sewa menyewaAspek hukum perjanjian sewa menyewa
Aspek hukum perjanjian sewa menyewa
 
Construction contract
Construction contractConstruction contract
Construction contract
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
 
Perencanaan teknis bangunan gedung ppt
Perencanaan teknis bangunan gedung pptPerencanaan teknis bangunan gedung ppt
Perencanaan teknis bangunan gedung ppt
 
Fidic
FidicFidic
Fidic
 
Types of contract
Types of contractTypes of contract
Types of contract
 
107028040 rapat-persiapan-pelaksanaan-kontrak-pcm
107028040 rapat-persiapan-pelaksanaan-kontrak-pcm107028040 rapat-persiapan-pelaksanaan-kontrak-pcm
107028040 rapat-persiapan-pelaksanaan-kontrak-pcm
 
Draft surat perjanjian kontrak kerja
Draft surat perjanjian kontrak kerjaDraft surat perjanjian kontrak kerja
Draft surat perjanjian kontrak kerja
 
fbb8a_3._PERSIAPAN_PELAKSANAAN_PEKERJAAN.PPT
fbb8a_3._PERSIAPAN_PELAKSANAAN_PEKERJAAN.PPTfbb8a_3._PERSIAPAN_PELAKSANAAN_PEKERJAAN.PPT
fbb8a_3._PERSIAPAN_PELAKSANAAN_PEKERJAAN.PPT
 
Civil Quantity Survey and Estimation
Civil Quantity Survey and EstimationCivil Quantity Survey and Estimation
Civil Quantity Survey and Estimation
 
Construction law basics 1103041
Construction law basics 1103041Construction law basics 1103041
Construction law basics 1103041
 
PERJANJIAN KREDIT MODAL KERJA
PERJANJIAN KREDIT MODAL KERJAPERJANJIAN KREDIT MODAL KERJA
PERJANJIAN KREDIT MODAL KERJA
 
Hukum Jaminan
Hukum JaminanHukum Jaminan
Hukum Jaminan
 
#FIDIC Understanding Basics# By SN Panigrahi
#FIDIC Understanding Basics# By SN Panigrahi#FIDIC Understanding Basics# By SN Panigrahi
#FIDIC Understanding Basics# By SN Panigrahi
 

Destacado

2.kontrak konsultan pengawas
2.kontrak konsultan pengawas2.kontrak konsultan pengawas
2.kontrak konsultan pengawas
Leo Agus
 
Presentasi softskill
Presentasi softskillPresentasi softskill
Presentasi softskill
benn_beckmen
 
Lampiran VI Swakelola (PERPRES 54 TAHUN 2010)
Lampiran VI Swakelola (PERPRES 54 TAHUN 2010)Lampiran VI Swakelola (PERPRES 54 TAHUN 2010)
Lampiran VI Swakelola (PERPRES 54 TAHUN 2010)
Trust Tour And Travel
 
makalah Pajak penghasilan pasal 21
makalah Pajak penghasilan pasal 21makalah Pajak penghasilan pasal 21
makalah Pajak penghasilan pasal 21
Fitri Bersahabat
 
Ringkasan materi-sak-etap
Ringkasan materi-sak-etapRingkasan materi-sak-etap
Ringkasan materi-sak-etap
heri baskoro
 
6. biaya penggunaan modal kerja (cost of capital)
6. biaya penggunaan modal kerja (cost of capital)6. biaya penggunaan modal kerja (cost of capital)
6. biaya penggunaan modal kerja (cost of capital)
SEPTIANA RAHAYUNINGTIAS
 
5 2 pelaksanaan swakelola
5 2 pelaksanaan swakelola5 2 pelaksanaan swakelola
5 2 pelaksanaan swakelola
Joy Irman
 

Destacado (20)

Contract review
Contract reviewContract review
Contract review
 
Kontrak
KontrakKontrak
Kontrak
 
Elemen elemen kontrak
Elemen elemen kontrak Elemen elemen kontrak
Elemen elemen kontrak
 
2.kontrak konsultan pengawas
2.kontrak konsultan pengawas2.kontrak konsultan pengawas
2.kontrak konsultan pengawas
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006
 
Presentasi softskill
Presentasi softskillPresentasi softskill
Presentasi softskill
 
Working Capital
Working CapitalWorking Capital
Working Capital
 
36 contoh desain pamflet dan brosur jasa keuangan finansial dan investasi
36 contoh desain pamflet dan brosur jasa keuangan finansial dan investasi36 contoh desain pamflet dan brosur jasa keuangan finansial dan investasi
36 contoh desain pamflet dan brosur jasa keuangan finansial dan investasi
 
Lampiran VI Swakelola (PERPRES 54 TAHUN 2010)
Lampiran VI Swakelola (PERPRES 54 TAHUN 2010)Lampiran VI Swakelola (PERPRES 54 TAHUN 2010)
Lampiran VI Swakelola (PERPRES 54 TAHUN 2010)
 
makalah Pajak penghasilan pasal 21
makalah Pajak penghasilan pasal 21makalah Pajak penghasilan pasal 21
makalah Pajak penghasilan pasal 21
 
Ringkasan materi-sak-etap
Ringkasan materi-sak-etapRingkasan materi-sak-etap
Ringkasan materi-sak-etap
 
Akuntansi & penyusunan lkd
Akuntansi & penyusunan lkdAkuntansi & penyusunan lkd
Akuntansi & penyusunan lkd
 
Bab vii ketentuan imbalan jasa versi iai
Bab vii ketentuan imbalan jasa versi iaiBab vii ketentuan imbalan jasa versi iai
Bab vii ketentuan imbalan jasa versi iai
 
Manajemen Bank Umum
Manajemen Bank UmumManajemen Bank Umum
Manajemen Bank Umum
 
6. biaya penggunaan modal kerja (cost of capital)
6. biaya penggunaan modal kerja (cost of capital)6. biaya penggunaan modal kerja (cost of capital)
6. biaya penggunaan modal kerja (cost of capital)
 
Manajemen Bank Umum
Manajemen Bank UmumManajemen Bank Umum
Manajemen Bank Umum
 
Manajemen Bank Umum 2015210412
Manajemen Bank Umum 2015210412Manajemen Bank Umum 2015210412
Manajemen Bank Umum 2015210412
 
Klasifikasi bidang layanan non konstruksi 2015
Klasifikasi bidang layanan non konstruksi 2015Klasifikasi bidang layanan non konstruksi 2015
Klasifikasi bidang layanan non konstruksi 2015
 
Hukum kontrak
Hukum kontrakHukum kontrak
Hukum kontrak
 
5 2 pelaksanaan swakelola
5 2 pelaksanaan swakelola5 2 pelaksanaan swakelola
5 2 pelaksanaan swakelola
 

Similar a Materi fidic pjt non kecil yogya 2016

Similar a Materi fidic pjt non kecil yogya 2016 (20)

Prinsip Konstruksi.pptx
Prinsip Konstruksi.pptxPrinsip Konstruksi.pptx
Prinsip Konstruksi.pptx
 
1831a_Dokumen_Kontrak_2020.pdf
1831a_Dokumen_Kontrak_2020.pdf1831a_Dokumen_Kontrak_2020.pdf
1831a_Dokumen_Kontrak_2020.pdf
 
Sistem Administrasi Proyek 3
Sistem Administrasi Proyek 3Sistem Administrasi Proyek 3
Sistem Administrasi Proyek 3
 
c6bab_BT_Dokumen_Kontrak-2.pdf
c6bab_BT_Dokumen_Kontrak-2.pdfc6bab_BT_Dokumen_Kontrak-2.pdf
c6bab_BT_Dokumen_Kontrak-2.pdf
 
Refrensi
RefrensiRefrensi
Refrensi
 
11906451.ppt
11906451.ppt11906451.ppt
11906451.ppt
 
Tgs mk2 arbi ardli-17.1003.222.01.0669-kls b
Tgs mk2 arbi ardli-17.1003.222.01.0669-kls bTgs mk2 arbi ardli-17.1003.222.01.0669-kls b
Tgs mk2 arbi ardli-17.1003.222.01.0669-kls b
 
Kontrak konruksi presentasi
Kontrak konruksi presentasiKontrak konruksi presentasi
Kontrak konruksi presentasi
 
Type of Procurement Contract _Training "PROCUREMENT Contract & Biding EVALUAT...
Type of Procurement Contract _Training "PROCUREMENT Contract & Biding EVALUAT...Type of Procurement Contract _Training "PROCUREMENT Contract & Biding EVALUAT...
Type of Procurement Contract _Training "PROCUREMENT Contract & Biding EVALUAT...
 
Contoh Perjanjian Pembukaan Lahan Persawahan (Beli Perjanjian, Hub: 081188872...
Contoh Perjanjian Pembukaan Lahan Persawahan (Beli Perjanjian, Hub: 081188872...Contoh Perjanjian Pembukaan Lahan Persawahan (Beli Perjanjian, Hub: 081188872...
Contoh Perjanjian Pembukaan Lahan Persawahan (Beli Perjanjian, Hub: 081188872...
 
11906451.ppt
11906451.ppt11906451.ppt
11906451.ppt
 
4dokumen-kontrak.ppt
4dokumen-kontrak.ppt4dokumen-kontrak.ppt
4dokumen-kontrak.ppt
 
Contoh Perjanjian Kontraktor Pengeboran Terbaru (Beli Perjanjian, Hub: 081188...
Contoh Perjanjian Kontraktor Pengeboran Terbaru (Beli Perjanjian, Hub: 081188...Contoh Perjanjian Kontraktor Pengeboran Terbaru (Beli Perjanjian, Hub: 081188...
Contoh Perjanjian Kontraktor Pengeboran Terbaru (Beli Perjanjian, Hub: 081188...
 
Syarat Syarat Umum Kontrak.pdf
Syarat Syarat Umum Kontrak.pdfSyarat Syarat Umum Kontrak.pdf
Syarat Syarat Umum Kontrak.pdf
 
Kontrak kerjasama
Kontrak kerjasamaKontrak kerjasama
Kontrak kerjasama
 
Tugas manajemen konstruksi ii mohamad bayu prawiratama
Tugas manajemen konstruksi ii mohamad bayu prawiratamaTugas manajemen konstruksi ii mohamad bayu prawiratama
Tugas manajemen konstruksi ii mohamad bayu prawiratama
 
TOT Bidang Gedung Bagi Guru SMK di Kota Malang Propinsi Jawa Timur
TOT Bidang Gedung Bagi Guru SMK di Kota Malang Propinsi Jawa TimurTOT Bidang Gedung Bagi Guru SMK di Kota Malang Propinsi Jawa Timur
TOT Bidang Gedung Bagi Guru SMK di Kota Malang Propinsi Jawa Timur
 
03_Modul_PEMAHAMAN DOKUMEN KONTRAK KERJA KONSTRUKSI_SSUK_SSKK.pdf
03_Modul_PEMAHAMAN DOKUMEN KONTRAK KERJA KONSTRUKSI_SSUK_SSKK.pdf03_Modul_PEMAHAMAN DOKUMEN KONTRAK KERJA KONSTRUKSI_SSUK_SSKK.pdf
03_Modul_PEMAHAMAN DOKUMEN KONTRAK KERJA KONSTRUKSI_SSUK_SSKK.pdf
 
Perjanjian Konstruksi Pembangunan Gudang dan Container Yard Terbaru (Beli Per...
Perjanjian Konstruksi Pembangunan Gudang dan Container Yard Terbaru (Beli Per...Perjanjian Konstruksi Pembangunan Gudang dan Container Yard Terbaru (Beli Per...
Perjanjian Konstruksi Pembangunan Gudang dan Container Yard Terbaru (Beli Per...
 
Tugas3 _M Maulana Al Muki_,Manajemen Konstruksi II
Tugas3 _M Maulana Al Muki_,Manajemen Konstruksi IITugas3 _M Maulana Al Muki_,Manajemen Konstruksi II
Tugas3 _M Maulana Al Muki_,Manajemen Konstruksi II
 

Último

MAteri:Penggunaan fungsi pada pemrograman c++
MAteri:Penggunaan fungsi pada pemrograman c++MAteri:Penggunaan fungsi pada pemrograman c++
MAteri:Penggunaan fungsi pada pemrograman c++
FujiAdam
 
10.-Programable-Logic-Controller (1).ppt
10.-Programable-Logic-Controller (1).ppt10.-Programable-Logic-Controller (1).ppt
10.-Programable-Logic-Controller (1).ppt
taniaalda710
 
2024.02.26 - Pra-Rakor Tol IKN 3A-2 - R2 V2.pptx
2024.02.26 - Pra-Rakor Tol IKN 3A-2 - R2 V2.pptx2024.02.26 - Pra-Rakor Tol IKN 3A-2 - R2 V2.pptx
2024.02.26 - Pra-Rakor Tol IKN 3A-2 - R2 V2.pptx
EnginerMine
 
SOAL UJIAN SKKhhhhhhjjjjjjjjjjjjjjjj.pptx
SOAL UJIAN SKKhhhhhhjjjjjjjjjjjjjjjj.pptxSOAL UJIAN SKKhhhhhhjjjjjjjjjjjjjjjj.pptx
SOAL UJIAN SKKhhhhhhjjjjjjjjjjjjjjjj.pptx
FahrizalTriPrasetyo
 
Manajer Lapangan Pelaksanaan Pekerjaan Gedung - Endy Aitya.pptx
Manajer Lapangan Pelaksanaan Pekerjaan Gedung - Endy Aitya.pptxManajer Lapangan Pelaksanaan Pekerjaan Gedung - Endy Aitya.pptx
Manajer Lapangan Pelaksanaan Pekerjaan Gedung - Endy Aitya.pptx
arifyudianto3
 
Abortion Pills In Doha // QATAR (+966572737505 ) Get Cytotec
Abortion Pills In Doha // QATAR (+966572737505 ) Get CytotecAbortion Pills In Doha // QATAR (+966572737505 ) Get Cytotec
Abortion Pills In Doha // QATAR (+966572737505 ) Get Cytotec
Abortion pills in Riyadh +966572737505 get cytotec
 

Último (14)

sample for Flow Chart Permintaan Spare Part
sample for Flow Chart Permintaan Spare Partsample for Flow Chart Permintaan Spare Part
sample for Flow Chart Permintaan Spare Part
 
MAteri:Penggunaan fungsi pada pemrograman c++
MAteri:Penggunaan fungsi pada pemrograman c++MAteri:Penggunaan fungsi pada pemrograman c++
MAteri:Penggunaan fungsi pada pemrograman c++
 
10.-Programable-Logic-Controller (1).ppt
10.-Programable-Logic-Controller (1).ppt10.-Programable-Logic-Controller (1).ppt
10.-Programable-Logic-Controller (1).ppt
 
Presentasi gedung jenjang 6 - Isman Kurniawan.ppt
Presentasi gedung jenjang 6 - Isman Kurniawan.pptPresentasi gedung jenjang 6 - Isman Kurniawan.ppt
Presentasi gedung jenjang 6 - Isman Kurniawan.ppt
 
BAB_3_Teorema superposisi_thevenin_norton (1).ppt
BAB_3_Teorema superposisi_thevenin_norton (1).pptBAB_3_Teorema superposisi_thevenin_norton (1).ppt
BAB_3_Teorema superposisi_thevenin_norton (1).ppt
 
Laporan Tinjauan Manajemen HSE/Laporan HSE Triwulanpptx
Laporan Tinjauan Manajemen HSE/Laporan HSE TriwulanpptxLaporan Tinjauan Manajemen HSE/Laporan HSE Triwulanpptx
Laporan Tinjauan Manajemen HSE/Laporan HSE Triwulanpptx
 
2024.02.26 - Pra-Rakor Tol IKN 3A-2 - R2 V2.pptx
2024.02.26 - Pra-Rakor Tol IKN 3A-2 - R2 V2.pptx2024.02.26 - Pra-Rakor Tol IKN 3A-2 - R2 V2.pptx
2024.02.26 - Pra-Rakor Tol IKN 3A-2 - R2 V2.pptx
 
SOAL UJIAN SKKhhhhhhjjjjjjjjjjjjjjjj.pptx
SOAL UJIAN SKKhhhhhhjjjjjjjjjjjjjjjj.pptxSOAL UJIAN SKKhhhhhhjjjjjjjjjjjjjjjj.pptx
SOAL UJIAN SKKhhhhhhjjjjjjjjjjjjjjjj.pptx
 
TEKNIS TES TULIS REKRUTMEN PAMSIMAS 2024.pdf
TEKNIS TES TULIS REKRUTMEN PAMSIMAS 2024.pdfTEKNIS TES TULIS REKRUTMEN PAMSIMAS 2024.pdf
TEKNIS TES TULIS REKRUTMEN PAMSIMAS 2024.pdf
 
Manajer Lapangan Pelaksanaan Pekerjaan Gedung - Endy Aitya.pptx
Manajer Lapangan Pelaksanaan Pekerjaan Gedung - Endy Aitya.pptxManajer Lapangan Pelaksanaan Pekerjaan Gedung - Endy Aitya.pptx
Manajer Lapangan Pelaksanaan Pekerjaan Gedung - Endy Aitya.pptx
 
Abortion Pills In Doha // QATAR (+966572737505 ) Get Cytotec
Abortion Pills In Doha // QATAR (+966572737505 ) Get CytotecAbortion Pills In Doha // QATAR (+966572737505 ) Get Cytotec
Abortion Pills In Doha // QATAR (+966572737505 ) Get Cytotec
 
Materi Asesi SKK Manajer Pelaksana SPAM- jenjang 6.pptx
Materi Asesi SKK Manajer Pelaksana SPAM- jenjang 6.pptxMateri Asesi SKK Manajer Pelaksana SPAM- jenjang 6.pptx
Materi Asesi SKK Manajer Pelaksana SPAM- jenjang 6.pptx
 
Strategi Pengembangan Agribisnis di Indonesia
Strategi Pengembangan Agribisnis di IndonesiaStrategi Pengembangan Agribisnis di Indonesia
Strategi Pengembangan Agribisnis di Indonesia
 
Manual Desain Perkerasan jalan 2017 FINAL.pptx
Manual Desain Perkerasan jalan 2017 FINAL.pptxManual Desain Perkerasan jalan 2017 FINAL.pptx
Manual Desain Perkerasan jalan 2017 FINAL.pptx
 

Materi fidic pjt non kecil yogya 2016

  • 2. CAYA CEOLANG SALJANA TEKNIK YANG SANGAT PINTEL DAN MENGUACAI PELHITUNGAN KONTLUKSI. APA GUNANYA PENGETAHUAN TENTANG KONTLAK, ITU KHAN ULUSANNYA AHLI HUKUM. PENANGGUNG JAWAB TEKNIK
  • 3. ASPEK LEGAL DAN ADMINISTRASI KONTRAK Kontrak Konstruksi Administrasi Kontrak Klaim Konstruksi
  • 4. Garner (2004) “Contract is an agreement between two or more parties creating obligations that are enforceable or otherwise recognizable at law” Martin and Law (2006) “Contract is a legally binding agreement. Agreement arises as a result of “offer and acceptance”, but a number of other requirements must be satisfied for an agreement to be legally binding”. (Bryan A.Garner (2004): “Black’s Law Dictionary”, Thomson West) (Elizabeth A Martin and Jonathan Law (2006): “Oxford Dictionary of Law”, Oxford University Press)
  • 5. Chow (2006) “Contract is a legally binding agreement formed when one party accepts an offer made by another and which fulfills the conditions” (Chow Kok Fong (2006):” Construction Contracts Dictionary”, Sweet & Maxwell Asia) John Adriaanse (2007) “A variety of factors makes a construction contract different from most other types of contracts. These include the length of the project, its complexity, its size and the fact that the price agreed and the amount of work done may change as it proceeds John Adriaanse (2007): “Construction Contract Law”
  • 6. ADMINISTRASI KONTRAK: Administrasi Kontrak bukan hanya melaksanakan pekerjaan administrasi dari suatu kontrak melainkan adalah ”cara mengelola kontrak”. The Contract for Construction: The Contractor to “CONSTRUCT” in accordance with the Contract and The Employer to “PAY” for them”. It describes comprehensively what the`works are, and how payment is to be made. Pekerjaan administrasi kontrak sudah harus dimulai jauh sebelum kontrak ditandatangani, oleh pengguna jasa maupun penyedia jasa: © Sarwono Hardjomuljadi
  • 7. FIDIC CC for Works of Civil Engineering Construction 4th edition (1987) FIDIC CC for Works of Civil Engineering Construction 3rd edition (1977) FIDIC CC for Works of Civil Engineering Construction 2nd edition (1969) FIDIC CC for Works of Civil Engineering Construction 1st edition (1957) General Condition of Contract ICE 3rd edition (1945) th FIDIC CC for Construction 1st edition (1999) FIDIC CC for Construction MDB Harmonised Edition (2006)
  • 8.  Which contract to be used STRAIGHT FORWARD PROJECT EMPLOYER DESIGN CONTRACTOR DESIGN Plant and/or high unforeseen risks Fixed price - lump sum Little employer involvement No major unforeseen risks no no no DISCUSS IN DETAIL Employer’s requirements with the Contractor, and negotiate a modified FIDIC contract no yes yes yes Maintenance yes yes no © Sarwono Hardjomuljadi
  • 9. Berdasarkan cara pembayaran: Lumpsum Contract Lumpsum Contract adalah kontrak pengadaan jasa pelaksanaan konstruksi atas penyelesaian seluruh pekerjaan dalam batas waktu tertentu, dengan jumlah harga pasti dan tetap, dan resiko yang mungkin terjadi dalam proses penyelesaian pekerjaan sepenuhnya ditanggung penyedia jasa. Unit Price Contract Unit Price Contract adalah kontrak pengadaan jasa pelaksanaan konstruksi atas penyelesaian seluruh pekerjaan dalam batas waktu tertentu berdasarkan harga satuan untuk setiap satuan/unsur pekerjaan dengan spesifikasi teknis tertentu, yang kuantitas pekerjaannya masih bersifat perkiraan sementara, sedangkan pembayarannya didasarkan pada hasil pengukuran bersama atas kuantitas pekerjaan yang telah dilaksanakan oleh penyedia jasa. © Sarwono Hardjomuljadi
  • 10. FIDIC GCC for Works of Civil Engineering Construction 2nd edition (July 1969) Clause 5: Extent of Contract. 5. The contract comprises the construction………….everything whether of a temporary or permanent nature required in and for such construction completion and maintenance so far as the necessity for providing the same is specified in or reasonably to be inferred from the Contract. © Sarwono Hardjomuljadi
  • 11. Case: During the execution of Saguling Hydro Electric Power Plant Project, in the employer’s opinion, the additional slope protection by full column adhesive rock-bolt was inferred as necessary due to the excavation shape and the extent of weathered rock. In the contractor’s opinion, the full column adhesive rock bolt was not specified in the contract. The different interpretation encouraged the contractor to submit their claim which finally became disputes between two parties and proofed that the ambiguities of wording may lead to disputes.
  • 12. FIDIC GCC for Works of Civil Engineering Construction 3rd edition (March 1977) [1] Clause 8: Contractor’s General Responsibilities. (1) The Contractor shall, subject to the provision of the Contract……………….whether of a temporary or permanent nature, required in and for such execution and maintenance, so far as the necessity for providing the same is specified in or reasonably to be inferred from the Contract. (2) The Contractor shall take full responsibility……………….provided that the Contractor shall not be responsible, except as may be expressly provided in the Contract, for the design or specification of the Permanent Works, or of the design or specification of any Temporary Works prepared by the Engineer. © Sarwono Hardjomuljadi
  • 13. Case: During the execution of Cirata Hydro Electric Power Plant Project under the Clause 5 which then became Clause 8 in the 3rd edition (as an improvement to make it more fair and balanced), the contractor was not responsible for the temporary works which design and specification were not prepared by the contractor but the engineer. A different interpretation again occurred. The engineer rejected to issue the payment for the bridge strengthening required for the mobilization of contractor’s plant. The bridge was actually the temporary facilities provided by the employer and was done by other contractor (infrastructure contractor). It was designed as temporary bridge by the former contractor (not the engineer) and the engineer considered that during the tender stage the bridge condition should be checked by the contractor and become the contractor responsibility as a part of working method. It then became a dispute after a lengthy discussion without conclusion.
  • 14. FIDIC GCC for Works of Civil Engineering Construction 4thedition (1987 amended 1992) Clause 8.1: Contractor’s General Responsibilities 8.1 The Contractor shall, with due care and diligence, design (to the extent provided for by the Contract), execute and complete the Works………….whether of a temporary or permanent nature, required in and for such design, execution, completion and remedying of any defects, so far as the necessity for providing the same is specified in or is reasonably to be inferred from the Contract. Clause 8.2: Site Operations and Method of Construction 8.2 The contractor shall take full responsibility…………….Provided that the Contractor shall not be responsible (except as stated hereunder or as may be otherwise agreed) for the design or specification of Permanent Works, or for the design or specification of any Temporary Works not prepared by the Contractor. © Sarwono Hardjomuljadi
  • 15. Case: During the execution of Renun Hydro Electric Power Plant Project, the extent of Clause 5 (2nd edition) and Clause 8 (3rd edition) then became 8.1 and 8.2 in the 4th edition were means to reduce the dispute possibility. Under these clauses, contractor was only responsible for the design or specification prepared by himself but irresponsible for the design and specification prepared by other parties.
  • 16. FIDIC GCC for Construction 1st edition (1999) Clause 4.1: Contractor’s General Obligations 4.1 The Contractor shall design (to the extent specified in the Contract), execute and complete the Works in accordance with the Contract and with the Engineer’s Instruction, and shall remedy any defects in the Works. The Contractor shall be responsible for the adequacy, stability and safety of all Site operations and of all methods of construction. Except to the extent specified in the Contract, the Contractor (i) shall be responsible for all Contractor’s Documents, Temporary Works, and such design of each item of Plant and Materials as is required for the item to be in accordance with the Contract, and (ii) shall not otherwise be responsible for the design or specification of the Permanent Works. © Sarwono Hardjomuljadi
  • 17. The above clause is the final revision which clarifies contractor’s responsibilities. Contractor is responsible for the design of all contractor’s documents, temporary works, the design of plant and material as is required for the item to be in accordance with the Contract, and the contractor will be irresponsible for the design and specification of permanent works, means that everything not mentioned in the contract is not the contractor’s responsibility.
  • 18. 1 + 2 = 3 Persyaratan teknis memastikan spesifikasi yang harus dipenuhi, Siapapun yang akan mempunyai pendapat yang sama untuk capaian yang diinginkan. 1 + 2 = 3 atau 1 + 2 = ? Persyaratan umum kontrak.memuat persyaratan yang bisa ditafsirkan berbeda oleh para pihak.
  • 19. MODIFIED CONDITIONS OF CONTRACT BY THE EMPLOYER Employer’s Reason : To avoid the Contract’s Cost Overrun WON BY EMPLOYERWON BY CONTRACTOR CONTRACT PRICE NOT INCREASE POSSIBLY BAD QUALITY DELAY IN OPERATION OF THE PREMISES FOR REVENUE INCREASE OF CONTRACT PRICE IMPACT TO THE EMPLOYER POSSIBLY PROJECT COMPLETION DELAY CLAIMS © Sarwono Hardjomuljadi
  • 21. 2000.01.01 Commencement Date Scheduled Starting date of contractor’s activity and Possession of Site [Clause 2.1] refer to Sub- Clause 8.3 [Programme] 2000.03.01 2000.03.01 2000.04.012000.03.20 Actual Possession of site [Clause 2.1], (3 stages) without disruption to the contractor’s activities Actual start of contractor’s activity 2000.05.01 Employer’s barrier for Clause 20: 1. Payment of Performance Security 2. Right to Claim if suffer delay start of contractor’s activity © Sarwono Hardjomuljadi
  • 22. Kontraktor melaksanakan beberapa item pekerjaan pada proyek jalan bebas hambatan sesuai spesifikasi dan gambar, tetapi karena kuantitas pekerjaan sudah mencapai volume yang ada dalam BOQ untuk pekerjaan tersebut, misalnya item pekerjaan galian struktur, kontraktor memutuskan untuk menghentikan pekerjaan Padahal jika pekerjaan ini tidak terselesaikan terlebih dahulu maka banyak item pekerjaan lain yang tidak dapat dimulai pelaksanaannya misalnya grade preparation, common embankment. Dalam klausul kontrak disebutkan bahwa kuantitas pekerjaan yang ada dalam BoQ adalah pekiraan dan tidak dapat digunakan sebagai kuantitas aktual dan benar (GCC 14.1.c). Hal yang harus diperhatikan: Hirarki dokumen tender, unit price atau lumpsum, perintah perubahan
  • 23. Setelah melakukan rekayasa lapangan pada masa mobilisasi bersama dengan Enjinir dan PPK, disimpulkan bahwa terdapat pekerjaan major yang pay itemnya tidak termasuk dalam BOQ misalnya Galian Batu pada tebing dimana pada tahap desain diidentifikasi sebagai Galian Biasa. Jika pekerjaan tersebut tidak dilaksanakan, maka pekerjaan lain yang merupakan critical path seperti penyiapan drainase dan penyiapan badan jalan untuk pelebaran tidak dapat dimulai. Penambahan biaya yang cukup besar menyulitkan pengguna jasa dalam mengambil keputusan. Karena tidak adanya kepastian dalam proses dan persetujuan VO maka kontraktor memutuskan untuk menghentikan pekerjaan yang pasti akan mengakibatkan keterlambatan proyek secara keseluruhan. Hal yang harus diperhatikan: status penandatanganan kontrak, value enjiniring
  • 24. Setelah melakukan rekayasa lapangan pada masa mobilisasi bersama dengan Enjinir dan PPK, disimpulkan bahwa terdapat pekerjaan major yang pay itemnya tidak termasuk dalam BOQ misalnya Galian Batu pada tebing dimana pada tahap desain diidentifikasi sebagai Galian Biasa. Jika pekerjaan tersebut tidak dilaksanakan, maka pekerjaan lain yang merupakan critical path seperti penyiapan drainase dan penyiapan badan jalan untuk pelebaran tidak dapat dimulai. Penambahan biaya yang cukup besar menyulitkan pengguna jasa dalam mengambil keputusan. Karena tidak adanya kepastian dalam proses dan persetujuan VO maka kontraktor memutuskan untuk menghentikan pekerjaan yang pasti akan mengakibatkan keterlambatan proyek secara keseluruhan. Hal yang harus diperhatikan: status penandatanganan kontrak, value enjiniring
  • 25. Kontraktor telah melaksanakan item pekerjaan masonry wall sesuai dengan gambar tetapi memutuskan untuk menghentikan pekerjaan tersebut karena ada item pekerjaan lanjutan seperti filter material for backfilling tidak masuk dalam BoQ. Kontraktor meminta adanya VO kepada Enjinir yang diteruskan kepada PPK untuk memasukkan pay item baru. Sebagaimana diketahui, persyaratan kontrak GCC 3.1 menyebutkan bahwa Enjinir harus mendapatkan persetujuan dari Pengguna Jasa sebelum dapat melakukan Variasi Kontrak. Kontraktor mengingatkan bahwa meninggalkan pekerjaan tersebut tanpa kepastian akan membahayakan pada konstruksi yang ada. Hal yang harus diperhatikan: keadaan darurat, klaim
  • 26. Dalam gambar design Kontraktor diminta untuk melaksanakan pekerjaan borepile dimana elevasi pile tip yang telah ditentukan berada 10 meter dibawah lapisan tanah keras atau batu. Karena diperkirakan akan menjadi kendala maka pada saat tender alat borepile menjadi salah satu kriteria evaluasi. Pada saat pelaksanaan pekerjaan Kontraktor pemenang menyatakan tidak sanggup melakukan pengeboran pada lapisan keras dan menghentikan pekerjaan di atas lapisan keras tersebut dan meminta kepada Enjinir agar dapat menerima kondisi lapangan dengan membuat justifikasi teknis yang melampirkan data boring baru yang menunjukkan ada perbedaan klasifikasi lapisan keras disertai perhitungan perkuatan pondasi dengan penambahan jumlah dan perubahan konfigurasi borepile. Berdasarkan hasil evaluasi dengan mempertimbangan kondisi lapangan dan pengalaman dilokasi lain, Enjinir menolak permintaan kontraktor dan menginstruksikan untuk melanjutkan pengeboran sampai kedalaman yang tertera pada gambar. Kontraktor tidak mengikuti instruksi Enjinir dan melanjutkan pekerjaan pengecoran borepile pada kedalaman diatas tanah keras dan melakukan perubahan konfigurasi atas dasar instruksi langsung dari Pengguna Jasa walaupun Justifikasi Teknis belum disetujui Enjinir. Hal yang harus diperhatikan: pemahaman kontrak, klaim
  • 27. Kontraktor memberikan sebagian pekerjaan kepada beberapa subkontraktor lokal atas permintaan informal Daerah untuk pemberdayaan pengusaha lokal tanpa melaporkan ke pada Enjinir untuk mengerjakan pekerjaan critical path seperti masonry wall, side ditch dan box culvert, ternyata dalam pelaksanaannya pekerjaan-pekerjaan tersebut kemajuan (progress) nya sangat terlambat. Karena hal tersebut pekerjaan yang akan dilakukan Kontraktor Utama menjadi terhambat. Kontraktor berdasarkan persyaratan kontrak mengajukan revisi program. Setelah dilakukan evaluasi terlihat bahwa secara realistis program tersebut tidak akan dapat dilakukan tanpa perpanjangan waktu. Hal yang harus diperhatikan: subkontraktor, lintasan kritis, EOT.
  • 30. Administrasi Kontrak Definisi:  Seni untuk mengelola semua aspek dari implementasi proyek.  Pemahaman dan penggunaan aturan kontrak –siapa melakukan apa, bilamana dan bagaimana. SHM
  • 31. Kontrak  Kesepakatan antara 2 pihak dengan tanggung jawab masing-masing.  Penawaran dari satu pihak disetujui oleh pihak lainnya. SHMSHM
  • 32. Para Pihak dalam Kontrak  Kontrak adalah antara Pengguna Jasa dan Kontraktor.  Pengguna Jasa dapat mendelegasikan sebahagian kwenangannya kepada “EnjinIr” untuk melaksanakan Administrasi Kontrak.  Enjinir adalah agen dari Pengguna Jasa.  Kontrak mendefinisikan peran Enjinir dan mengatur bagaimana para pihak harus berinteraksi. SHMSHM
  • 33. Hubungan para pihak dalam Kontrak Pengguna Jasa Enjinir Kontraktor Penandatangan Kontrak Tidak ada kontrak atau perjanjian Perjanjian untuk memberikan Layanan Profesional Notes: Kontrak Konstruksi menempatkan Enjinir di anatara Pengguna Jasa dan Kontraktor/ SHM
  • 34. Bagaimana mendapatkan Kontrak Penyiapan Pelelangan  Desain and Dokumen Lelang Proses Pelelangan  Undangan lelang (pra/pasca kualifikasi)  Penyampaian penawaran  Evaluasi penawaran (kualitas dan harga)  Catatan: QCBS (Quality-Cost Based Selection)  Surat Penunjukan SHMSHM
  • 35. Penerbitan Dokumen Lelang Penyampaian Dokumen Penawaran Penerbitan Surat Penunjukan Tanggal Mulainya Pekarjaan Penerbitan Berita Acara Serah Teima 1 Penerbitan Berita Acara Serah Teima 2 Masa Penyiapan Penawaran Masa Evalusai Penawaran Penerbitan Jaminan Pelaksanaan Masa Pelaksanaan Pekerjaan Masa Pemberitahuan Cacat Mutu Pengembalian Jaminan Pelaksanaan (Akhir Kontrak) Tahapan Pelelangan hingga Penyelesaian Pekerjaan SHM
  • 36. Penyiapan Kontrak  Penyiapan dan penandatanganan kontrak (para pihak)  Jaminan Pelaksanaan (Kontraktor) SHMSHMSHM
  • 37. Dokumen Kontrak  Perjanjian Kontrak  Surat Penunjukan  Dokumen Penawaran  Persyaratan Khusus Kontrak Bagian A (Data Kontrak)  Persyaratan Khusus Kontrak Bagian B  Persyaratan Umum Kontrak  Spesifikasi Khusus  Spesifikasi Umum  Gambar-gambar  Daftar-daftar (BOQ, dsb.)  Dokumen-dokumen terkait lainnya SHMSHMSHMSHM
  • 38. Persyaratan Umum Kontrak  Aturan yang disepakati untuk pelaksanaan Adfministrasi Kontrak  Menetapkan peran dan tanggung jawab para pihak dalam kontrak, antara Pengguna Jasa dan Kontraktor.  Dilengkapi dengan Persyaratan Khusus. SHMSHMSHMSHMSHM
  • 39. Apa yang diharapkan dari Persyaratan Umum Kontrak ?:  Adil dan Berimbang  Jelas, rasional dan mudah dipahami  Menyeluruh dan luwes  Teruji dengan rekam jejak yang baik  Independen  Dikenal dan diakui FIDIC Conditions of Contract memenuhi semua hal di atas. SHMSHMSHMSHMSHM
  • 40. FIDIC  FIDIC adalah Federasi Internasional Konsultan Enjiniring didirikan pada tahun 1913.(Fédération Internationale des Ingénieurs-Conseils)  FIDIC beranggotakan lebih dari 80 negara di dunia.  Tujuan– meningkatkan profesionalisme dari anggotanya dan menyebarluaskan informasi. SHMSHMSHMSHMSHMSHM
  • 41. Peran Pengguna Jasa Menurut kontrak:  Memberikan penguasaan lahan  Membantu Kontraktor dalam mendapatkan izin, lisensi dsb.  Menjamin kerjasama antar personil dan kontraktor lain yang bekerja untuk Pengguna Jasa.  Menyiapkan bukti ketersediaan anggaran.  Menyampaikan pemberitahuan klaim Pengguna Jasa. SHMSHMSHMSHMSHMSHM
  • 42. Peran Pengguna Jasa Dua tanggung jawab utama:  Menunjuk dan mendelegasikan kepada Enjinir.  Membayar kepada Kontraktor dengan jumlah yang ditetapkan oleh Enjinir. Pengguna Jasa mempunyai banyak tanggung jawab lain dalam pelaksanaan proyek- tetapi ini berada di luar kontrak. SHMSHMSHMSHMSHMSHMSHM
  • 43. Peran Enjinir  Enjinir adalah seseorang yang ditunjuk untuk bertindak untuk dan atas nama Pengguna Jasa.  Kontrak menetapkan tugas Enjinir dengan pembatasan, sesuai dengan surat penunjukkannya. SHMSHMSHMSHMSHMSHMSHMSHM
  • 44. Peran Enjinir  Kewenangan  Kebebasan  Keterampilan  Penetapan  Instruksi  Pendelegasian  Penggantian SHMSHMSHMSHMSHMSHMSHMSHMSHM
  • 45. Peran Enjinir Enjinir harus mendapat persetujuan spesifik dari Pengguna Jasasebelum mengambil tindakan dalam hal:  Menyetujui atau menetapkan tambahan biaya.  Menyetujui suatu perpanjangan waktu.  Menginstruksikan Variasi, kecuali:  Dalam keadaan darurat  Jika variasi akan menambah nilai kontrak dengan jumlah lebih kecil dari persentasi yang dinyatakan dalam kontrak. SHMSHMSHMSHMSHMSHMSHMSHMSHM
  • 46. Peran Kontraktor  Melaksanakan dan menyelesaikan pekerjaan sesuai dengan Kontrak dan sesuai dengan Instruksi Enjinir dan harus memperbaiki cacat mutu dalam Pekerjaan.  Menyiapkan semua yang dibutuhkan untuk pelaksanaan dan penyelesaian.  Bertanggung Jawab atas Penjagaan Pekerjaan.  Bertanggung Jawab atas keselamatan kerja dan pengamanan lingkungan.  Tugas-tugas terkait pelaksanaan konstruksi. SHMSHMSHMSHMSHMSHMSHMSHMSHM
  • 47. Peran Kontraktor  Tugas terkait pelaksanaan konstruksi  Desain sesuai kebutuhan  Menentukan metode pelaksanaan konstruksi.  Menata batas-batas kerja  Melaksanakan QC dan QA  Melaporkan “adverse physical conditions” etc.  Bertanggung jawab atas peralatannya.  Menjaga kebersihan lapangan, memelihara akses.  Menyiapkan “as-built drawings”  Memperbaiki cacat mutu SHMSHMSHMSHMSHMSHMSHMSHMSHM
  • 48. Peran Kontraktor Persyaratan Administratif:  Menyiapkan Jaminan Pelaksanaan (atas biaya Kontraktor) dan menyampaikannya kepada Pengguna Jasa.  Mengasuransikan sesuai dengan ketentuan kontrak.  Menyimpan semua catatan sebagai pendukung proses pembayaran.  Menyiapkan dan menyampaikan Laporan Kemajuan Pekerjaan Bulanan SHMSHMSHMSHMSHMSHMSHMSHMSHMSHM
  • 49. Peran Kontraktor Kuasa Kontraktor  Kontraktor harus menunjuk kuasanya (General Superintendent) dan memberikan semua kewenangan yang dibutuhkan untuk bertindak untuk dan atas nama Kontraktor.  Kuasa Kontraktor harus berkedudukan di “lapangan” SHMSHMSHMSHMSHMSHMSHMSHMSHMSHM
  • 50. Peran Kontraktor Sub – Kontraktor  Kontraktor tidak boleh mensubkontrakkan keseluruhan pekerjaan.  Kontraktor membutuhkan izin dari Enjinir untuk mensub-kontrakkan sebagian pekerjaannya.  Semua persyaratan yang berlaku bagi kontraktor harus juga berlaku untuk Sub-Kontraktor. SHMSHMSHMSHMSHMSHMSHMSHMSHMSHM UNIVERSITAS ATMA JAYA YOGYAKARTA 18 – 19 Februari 2011
  • 51. Variasi atas Kontrak Variasi kontrak mengizinkan perubahan atas pekerjaan yang dikontrakkan. Meliputi:  Pekerjaan Tambah  Revisi atas pekerjaan desain – mutu, jenis, kuantitas, dsb.  Revisi atas waktu penyelesaian (perpanjangan waktu) SHMSHMSHMSHMSHMSHMSHMSHMSHMSHM
  • 52. Perpanjangan Waktu  Enjinir dapat memberikan perpanjangan waktu penyelesaian sehubungan dengan adanya perintah variasi.  Jika Kontraktor beranggapan bahwa kejadian-kejadian menyebabkan kontraktor berhak mendapatkan suatu perpanjangan waktu, ia harus menyampaikan pemberitahuan kepadaa Enjinir. SHMSHMSHMSHMSHMSHMSHMSHMSHMSHM
  • 53. Ganti Rugi akibat keterlambatan  Jika Kontraktor gagal menyelesaikan kontrak dalam jangka waktu yang ditentukan pada dokumen kontrak atau tanggal lain sebagai akibat adanya perpanjangan waktu Kontraktor harus membayar ganti rugi akibat keterlambatan.  Jumlah dan batasan dari ganti rugi akibat keterlambatan dinyatakan dalam Data Kontrak. SHMSHMSHMSHMSHMSHMSHMSHMSHMSHM
  • 54. Klaim oleh Kontraktor  Kontraktor harus menyampaikan pemberitahuan (sesuai jangka waktu yang ditetapkan dalam kontrak) kepada Enjinir jika ia beranggapan berhak untuk mendapatkan tambahan pembayaran atau perpanjangan waktu.  Kontraktor harus menyimpan catan-catatan untuk mendukung penyampaian klaim.  Persyaratan Umum Kontrak menetapkan batasan waktu untuk penyampaian klaim dan tangapan. SHMSHMSHMSHMSHMSHMSHMSHMSHMSHM
  • 55. Waktu Penyelesaian  Waktu penyelesaian dinyatakan dalam Data Kontrak (x hari kalender)  Waktu penyelesaian dihitung dari tanggal mulainya pelaksanaan (commencement date).  Tanggal mulainya pelaksanaan adalah setelah diterbitkannya Instruksi Enjinir (dan telah diterima oleh kontraktor) untuk mulai bekerja (instruksi enjinir diterbitkan setelah dipenuhinya beberapa persyaratan). SHMSHMSHMSHMSHMSHMSHMSHMSHMSHMSHM
  • 56. Program Pelaksanaan  Kontraktor harus menyampaikan program rinci kepada Enjinir dalam jangka waktu 28 hari setelah pemberitahuan mulainya pekerjaan (Klausula 8).  Kontraktor harus memulai pekerjaan sesuai dengan program pelaksanaannya.  Jika kemajuan pekerjaan aktual tidak komnsisten dengan program pelaksanaan kontraktor harus menyampaikan program revisi. SHMSHMSHMSHMSHMSHMSHMSHMSHMSHMSHM
  • 57. Tingkat Kemajuan Pekerjaan Jika suatu saat:  Kemajuan pekerjaan terlalu lambat untuk menyelesaikan pekerjaan dalam waktu penyelesaian sesuai kontrak,atau  Kemajuan pekerjaan berada di belakang program yang berlaku saat ini. Kontraktor harus menyampaikan program revisi menunjukkan bagaimana kemajuan pekerjaan dapat diakselerasi dan penyelesaian dapat dicapai. SHMSHMSHMSHMSHMSHMSHMSHMSHMSHMSHM
  • 58. Kegagalan untuk melanjutkan pekerjaan  Kegagalan berlanjut dan tidak terjamin untuk melanjutkan pekerjaan sesuai dengan program kerjanya dapat dianggap sebagai pelanggaran kontrak.  Sesuai Klausula 15.2, Kontraktor tanpa alasan yang wajar, gagal untuk melanjutkan pekerjaan sesuai dengan Klausula 8, maka Penghentian Kontrak dimungkinkan. SHMSHMSHMSHMSHMSHMSHMSHMSHMSHMSHM
  • 59. Dokumentasi  Nilai dan pentingnya dokumen yang baik tidak perlu dibesar-besarkan.  Penyimpanan catatan-catatan yang jelas dan akurat harus menanamkan sebagai kebiasaan bagi semua staff di lapangan. SHMSHMSHMSHMSHMSHMSHMSHMSHMSHMSHM
  • 60. Dokumentasi  Dokumentasi lapangan seringkali merupakan masukan yang paling berharga dalam penyelesaian sengketa dan klaim.  Dokumentasi termasuk:  Catatan Harian, Instruksi Lapangan / Permohonan.  Penyampaian catatan-catatan  Data pendukung (pengukuran, pengetesan dsb) untuk Interim Payment Certificate (IPC)  Pengiriman pemberitahuan, tagihan, jadwal dsb., SHMSHMSHMSHMSHMSHMSHMSHMSHMSHMSHM
  • 61. Mutu  Aspek terpenting untuk kesuksesan suatu proyek adalah MUTU.  Mutu pekerjaan adalah tanggung jawab kontraktor.  Mutu dapat dicapai dengan menggunakan metode kerja yang baik dengan sumber daya yang memadai dan kesesuaian dengan Rencana Mutu Terpadu. SHMSHMSHMSHMSHMSHMSHMSHMSHMSHMSHM
  • 62. Mutu  QC dab QA harus dapat memperlihatkan bahwa semua pekerjaan sesuai dengan persyaratan standar mutu.  The Enjinir harus melaksanakan pengecekan mutu hingga ia puas bahwa pekerjaan memperlihatkan kesesuaian dengan persyaratan kontrak. SHMSHMSHMSHMSHMSHMSHMSHMSHMSHMSHM
  • 63. Manajemen Mutu Manajemen Mutu Kontraktor:  Kontraktor, sebagai perusahaan, harus mempunyai kebijakan yang jelas dalam hal mutu, dengan dukungan dari atas.  Kontraktor harus menominasikan Manajer Mutu di lapangan.  Manajer Mutu harus bebas dari GS. SHMSHMSHMSHMSHMSHMSHMSHMSHMSHMSHM
  • 64. Korupsi dan Praktek kecurangan FIDIC GCC for Construction, MDB Harmonised Edition mempunyai klausula untuk mencegah korupsi (Klausula 15.6) Jika Pengguna Jasa menetapkan bahwa Kontraktor terlibat korupsi, kecurangan, kolusi atau praktek pemaksaan maka Pengguna Jasa dapat menghentikan hubungan kerja dengan Kontraktor. SHMSHMSHMSHMSHMSHMSHMSHMSHMSHMSHM
  • 66. Administrasi Kontrak (3.Klaim dan Penyelesaian Sengketa Konstruksi)
  • 67. Hardjomuljadi et al (2006) [17] “Klaim adalah suatu tindakan seseorang untuk meminta sesuatu, dimana hak seseorang tersebut telah hilang sebelumnya, karena yang bersangkutan beranggapan mempunyai hak untuk mendapatkannya kembali”. Garner (2004) [16] “A demand for money, property, or a legal remedy to which one asserts a right” Martin and Law (2006) [18] “Claim is A demand for a remedy or ascertain of a right, especially the right to take a particular case to court” CLAIM © Dr.Sarwono Hardjomuljadi
  • 68. Hanvey (2005) [19]“ One of the most common issues impacting construction projects is inadequate or incomplete design documents” Fisk (2003) [21] “Differing site conditions is the one of the most misunderstood of all contract provisions, and the one that is frequently the cause of large contractor claims for additional work and change orders”. Arditi and Patel (1989) [20] “ Most of the typical claims are caused by factors differing site conditions”. Barrie & Paulson (1992) [22] “Changed conditions when the actual physical conditions or other jobsite condition prove different from those foreseeable from the plans and specifications” CLAIM © Dr.Sarwono Hardjomuljadi
  • 69. MODIFIED CONDITIONS OF CONTRACT BY THE EMPLOYER Employer’s Reason : To avoid the Contract’s Cost Overrun WON BY EMPLOYERWON BY CONTRACTOR CONTRACT PRICE NOT INCREASE POSSIBLY BAD QUALITY DELAY IN OPERATION OF THE PREMISES FOR REVENUE INCREASE OF CONTRACT PRICE IMPACT TO THE EMPLOYER POSSIBLY PROJECT COMPLETION DELAY CLAIMS © Sarwono Hardjomuljadi
  • 70. (The action of demanding something, which one lost before hand, because of one’s right to recover it). Hardjomuljadi et al (2006) Gambaran sederhana adalah seseorang yang mempergunakan jasa angkutan udara akan menyerahkan bagasinya kepada perusahaan penerbangan untuk selanjutnya mengklaim kembali bagasinya (baggage claim) pada saat sampai ditempat tujuan penerbangan © Dr. Sarwono Hardjomuljadi
  • 71. Contractual Claims Klaim konstruksi di mana kontraktor secara nyata memang berhak di bayar dengan cara reimbursement dan secasra jelas mermpunyai dasar legal yang tercantum dalam kontrak seperti misalnya klaim upc. Non-Contractual Claims Klaim konsatruklsui yang cara penyelesaiannya secara spesifik tidak diretapkan dalam kontrak, misalnya klaim, karena perubahan nilai tukar., ex gratia claims. © Dr. Sarwono Hardjomuljadi
  • 73. FIDIC MDB 2010 Clause 2.5 Employer’s Claims If the Employer considers himself to be entitled to any payment under any Clause of these Conditions or otherwise in connection with the Contract, and/or to any extension of the Defects Notification Period, the Employer or the Engineer shall give notice and particulars to the Contractor. However, notice is not required for payments due under Sub- Clause 4.19 [Electricity, Water and Gas], under Sub-Clause 4.20 [Employer’s Equipment and Free-Issue Materials], or for other services requested by the Contractor. The notice shall be given as soon as practicable, of the event or circumstances giving rise to the claim. A notice relating to any extension of the Defects Notification Period shall be given before the expiry of such period.
  • 74. FIDIC MDB 20 Clause 2.5 Employer’s Claims If the Employer considers himself to be entitled to any payment under any Clause of these Conditions or otherwise in connection with the Contract, and/or to any extension of the Defects Notification Period, the Employer or the Engineer shall give notice and particulars to the Contractor. However, notice is not required for payments due under Sub-Clause 4.19 [Electricity, Water and Gas], under Sub-Clause 4.20 [Employer’s Equipment and Free- Issue Materials], or for other services requested by the Contractor. The notice shall be given as soon as practicable and no longer than 28 days after the Employer became aware, or should have become aware, of the event or circumstances giving rise to the claim. A notice relating to any extension of the Defects Notification Period shall be given before the expiry of such period.
  • 76. Clause 20 Claims, Disputes and Arbitration 20.1 Contractor’s Claims If the Contractor considers himself to be entitled to any extension of the Time for Completion and/or any additional payment, under any Clause of these Conditions or otherwise in connection with the Contract, the Contractor shall give notice to the Engineer, describing the event or circumstance giving rise to the claim. The notice shall be given as soon as practicable, and not later than 28 days after the Contractor became aware, or should have become aware, of the event or circumstance. - Hak kontraktor untuk mengajukan klaim EOT & Additional Payment - Pembeitahuan atas kemungkinan klaim dan batas waktu penyampaiannya. © Dr. Sarwono Hardjomuljadi
  • 77. The Contractor shall keep such contemporary records as may be necessary to substantiate any claim, either on the Site or at another location acceptable to the Engineer. Without admitting the Employer’s liability, the Engineer may, after receiving any notice under this Sub- Clause, monitor the record-keeping and/or instruct the Contractor to keep further contemporary records. The Contractor shall permit the Engineer to inspect all these records, and shall (if instructed) submit copies to the Engineer. Clause 20 Claims, Disputes and Arbitration 20.1 Contractor’s Claims - Tentang catatan lengkap (contemporary record). - Hak Enjinir untuk memeriksa catatan
  • 78. Each Payment Certificate shall include such additional payment for any claim as have been reasonably substantiated as due under the relevant provision of the Contract. Unless and until the particulars supplied are sufficient to substantiate the whole of the claim, the Contractor shall only be entitled to payment for such part of the claim as he has been able to substantiate. Clause 20 Claims, Disputes and Arbitration 20.1 Contractor’s Claims - Setiap BA Pembayaran harus termasuk tambahan biaya klaim, dalam hal belum dapat disetujui, diberi tanda bintang.
  • 79. 20.2 Appointment of the Dispute Board Disputes shall be referred to a DB for decision in accordance with Sub-Clause 20.4[Obtaining Dispute Board’s Decision]. The Parties shall appoint a DB by the date stated in the Contract Data. The DB shall comprise, as stated in the Contract Data, either one or three suitablyqualified persons (“the members”), each of whom shall be fluent in the language forcommunication defined in the Contract and shall be a professional experienced in thetype of construction involved in the Works and with the interpretation of contractualdocuments. If the number is not so stated and the Parties do not agree otherwise, the DB shall comprise three persons. - Tentang Penunjukan Dewan Sengketa
  • 80. Clauses requiring notice by the Contractor (1) 1.8 Care and Supply of Documents 1.9 Delayed Drawings or Instructions 1.13 Compliance with Laws 2.1 Right of Access to the Site 3.4 Replacement of the Engineer 4.3 Contractor’s Representative 4.4 Subcontractors 4.7 Setting Out 4.12 Unforeseeable Physical Conditions 4.16 Transport of Goods 4.20 Employer’s Equipment and Free-Issue Materials 4.21 Progress Reports 4.24 Fossils
  • 81. Clauses requiring notice by the Contractor (2) 5.2 Objection to Nomination 7.3 Inspection 7.4 Testing 8.3 Programme 8.4 Extension of Time for Completion 8.9 Consequences of Suspension 8.11 Prolonged Suspension 9.1 Contractor’s Obligations [Tests on Completion] 9.2 Delayed Tests 10.1 Taking Over of the Works and Sections 10.2 Taking Over of Parts of the Works 10.3 Interference with Tests on Completion 12.1 Works to be Measured
  • 82. Clauses requiring notice by the Contractor (3) 12.4 Omissions 13.1 Right to Vary 13.7 Adjustments for Changes in Legislation 16.1 Contractor’s Entitlement to Suspend Work 16.2 Termination by Contractor 17.4 Consequences of Employer’s Risks 17.5 Intellectual and Industrial Property Rights 18.1 General Requirements for Insurances 18.2 Insurance for Works and Contractor’s Equipment 19.2 Notice of Force Majeure 19.3 Duty to Minimise Delay 19.6 Optional Termination, Payment and Release 19.7 Release from Performance 20.1 Contractor’s Claims 20.4 Obtaining Dispute Board’s Decision
  • 83. Mobile +62 811 844 903 eMail sarwonohm2@yahoo.co.id The Dispute Resolution Board Foundation 19550 International Blvd. South, Suite 314 ; Seattle, WA 98188 USA Tel 206-878-3336 ; Facsimile 206-878-3338 ; Toll-free USA 888-523-5208 eMail: info@drb.org ; website: www.drb.org Dr. Sarwono Hardjomuljadi Country Representative for Indonesia
  • 84. Bab I Ketentuan Umum Pasal 1 Butir 10 Alternatif Penyelesaian sengketa adalah lembaga penyelesaian sengketa atau beda pendapat melalui prosedur yang disepakati para pihak, yaitu penyelesaian di luar pengadilan dengan cara konsultasi, negosiasi, konsiliasi, atau penilaian ahli. Bab II Alternatif Penyelesaian Sengketa PAsal 6 Butir 1 Sengketa atau beda pendapat perdata dapat diselesaikan oleh para pihak melalui alternatif penyelesaian sengketa yang didasarkan pada itikad baik dengan mengesampingkan penyelesaian secara litigasi di Pengadilan Negeri. Bab II Alternatif Penyelesaian Sengketa PAsal 6 Butir 7 Kesepakatan penyelesaian sengketa atau beda pendapat secara tertulis adalah final dan mengikat para pihak untuk dilaksanakan dengan itikad baik serta wajib didaftarkan di Pengadilan negeri dalam waktu paling lama 30 hari sejak tanggal penandatanganan. Catatan: Undang-undang ini mengatur penyelesaian sengketa yang secara tegas mencantumkan dalam perjanjian kontraknya bahwa semua sengketa atau beda pendapat yang timbul atau mungkin timbul dari hubungan hukum tersebut akan diselesaikan dengan cara arbitrase atau melalui alternatif penyelesaian sengketa. Related Regulation in Indonesia Undang-undang No. 30 / 1999 Re: Arbitrase dan Alternatif Penyelesaian Sengketa
  • 85. Related Regulation FIDIC Conditions of Contract for Construction MDB Harmonised Ed. 2010 Clause 20 Claims, Disputes and Arbitration Clause 20 Point 2 Appointment of the Dispute Board The DB shall comprise, as stated in the Contract Data, either one or three suitably qualified persons (“the members”), each of whom shall be fluent in the language for communication defined in the Contract and shall be a professional experienced in the type of construction involved in the Works and with the interpretation of contractual documents. If the number is not so stated and the Parties do not agree otherwise, the DB shall comprise three persons. If the parties have not jointly appointed the DB 21 days before the date stated in the Contract Data and the DB is comprise three persons, each Party shall nominate one member for the approval of the other Party. The first two members shall recommend and the Parties shall agree upon the third member, who shall act as chairman.
  • 86. Clause 20 Point 2 Appointment of the Dispute Board The DB shall comprise, as stated in the Appendix to Tender, either one or three suitably qualified persons (“the members”), If the number is not so stated and the Parties do not agree otherwise, the DAB shall comprise three p[ersons. . If the DAB is to comprise three persons, each Party shall nominate one member for the approval of the other Party. The Parties shall consult both these members and shall agree upon the third member, who shall be appointed to act as chairman. Related Regulation FIDIC Conditions of Contract for Plant and Design Bulid 1999 Clause 20 Claims, Disputes and Arbitration
  • 87. Related Regulation FIDIC Conditions of Contract for EPC/Turnkey 1999 Clause 20 Claims, Disputes and Arbitration Clause 20 Point 2 Appointment of the Dispute Board The DB shall comprise, as stated in the Particular Conditions, either one or three suitably qualified persons (“the members”), If the number is not so stated and the Parties do not agree otherwise, the DAB shall comprise three persons. . If the DAB is to comprise three persons, each Party shall nominate one member for the approval of the other Party. The Parties shall consult both these members and shall agree upon the third member, who shall be appointed to act as chairman.
  • 88. DB/DRB/ DAB 84 days (Clause 20.4 Para 4) 84 days (Clause 20.4 Para 5)Fail to decide Commence of Arbitration Decision Agree d Notice of Dissatisfication to other Party Final and binding Disagreed © Sarwono Hardjomuljadi Amicable Setlement Yes 28 days (Clause 20.4 Para 5) 28 days (Clause 20.4 Para 5) 56 days (Clause 20.5 Para 1) No Clause 20, Claims, Disputes and Arbitration