SlideShare una empresa de Scribd logo
1 de 9
Descargar para leer sin conexión
International Journal of Engineering Research and Development
e-ISSN: 2278-067X, p-ISSN: 2278-800X, www.ijerd.com
Volume 2, Issue 10 (August 2012), PP. 35-43


     Lean Manufacturing and Productivity Improvement in Coal
                        Mining Industry
                                 Er. Manoj Ade1, Dr. V.S.Deshpande2
                                                   1
                                                  Western Coalfields limited
                                              2
                                               Principal RKNEC, Nagpur India



Abstract—The economic reforms- Liberalization, Privatization, Globalization, (LPG) started in 1991 in India. The main
objective of the government was to achieve high economic growth and industrialize the nation for the well-being of
Indian citizens. Thus Indian market became Global and open market. Coal industry was not an exception to these
phenomena of globalization. The improvement in productivity has become need of coal industry to take the competitive
advantage of global marketing. Productivity improvement through Lean manufacturing means optimization and co-
ordination of the input resources to minimize the wastes to reduce total production cost. This can be achieved by Lean
thinking (to identify and eliminate wastes) and Lean Manufacturing (to improve efficiency and effectiveness of
equipment). In this paper researcher has applied lean manufacturing concept in order to increase productivity of coal
mining. By application of lean tools the Overall Human Effectiveness is analyzed which is converted into productive
output to increase the productivity and develop an overview of the conceptual framework of lean manufacturing practices
to minimize the production cost of mining.

Keywords––Lean thinking, Lean Manufacturing, Lean production, wastes, Overall Human Effectiveness.

                                             I.         INTRODUCTION
          Henry Ford is known as “Father of the Management”, continued his focus on waste minimization while developing
his mass assembly manufacturing system and work standardization. While standardizing the work, each activity is analyzed
on the basis of desirable activity or undesirable activity. All the desirable activities are known as value added activity and
undesirable activities are known as wastes. Thus work standardization has become the basis of Lean thinking.
          Lean thinking is an approach to achieving manufacturing excellence based upon the continued value addition and
elimination of waste. Lean thinking is a set of methodologies for maximizing value of an item or feature for which a
customer is willing to pay. All other items aspects are deemed waste. Figure-1
                                                   Team Based
                                                   continuous
                                                  improvement

                                 Lean thinking               Lean Production
                               maximizing value             improve efficiency
                                and minimizing                of value added
                                    waste.                       activities

                                                     Lean
                                                  Manufacturing


          Lean production and Lean maintenance- utilizes techniques and principles that improve efficiencies of value,
product development, operations, suppliers and customers relations that requires less human effort, less space, less relations
that requires less human effort, less space, less capital and less time to make products with fewer defects compared with the
previous system of mass production. Lean maintenance- Maintenance works that is to be carried out by application of
TPM, 5S, Kanban and Andon with less waste, less human effort, less maintenance space, less investment in tools, less
inventory, and in less time.
          TPM is a lean tool to optimize the effectiveness of equipment and tooling. It is total Employee Involvement, to
create a culture where operators develop ownership of their equipment, and become full partners with Maintenance,
Engineering and Management to assure equipment operates properly everyday.
          Lean Manufacturing – Lean Manufacturing is a way to eliminate waste and improve efficiency in a
manufacturing environment. Lean manufacturing was successfully implemented by Toyota in his factory hence named as
Toyota production. 1 Taiichi Ohno identified wastes as - Elimination of waste is the goal of Lean. Toyota defined three types
of waste-

                                                             35
Lean Manufacturing and Productivity Improvement in Coal Mining Industry

    1)    Muri – Muri focuses on the preparation and planning of the process or what can be avoided proactively by design.
    2)    Mura- Mura focuses on implementation and the elimination of fluctuation at the scheduling or operations level
          such as quality and volume.
     3) Muda- Muda is after the process is in place and is dealt with reactively. Taiichi Ohno identified seven types of
          wastes in operational working. These are-
          1) Overproduction – Production ahead of demand.
          2) Transportation- Moving products that are not actually required to perform the processing
          3) Waiting- Waiting for the next production step.
          4) Inventory- All components, work-in-progress and finished product not being processed.
          5) Motion People or equipment moving or walking more than is required to perform the processing.
          6) Over processing – Due to poor tool or product design creating activity.
          7) Defects- The effort involved in inspecting for and fixing defects.
          Lean manufacturing is the production of coal using less of everything compared to traditional mass production:
less waste, human effort, manufacturing space, investment in tools, inventory, and engineering time to develop a new
product.
          The term “Lean” as 4 Womack and his colleagues define it denotes a system that utilizes less, in term of all
inputs, to create the same outputs as those created end customer. The Lean Manufacturing discipline is to work in every
facet of the value stream by eliminating waste in order to reduce cost, generate capital, bring in more sales and remain
competitive in a growing global market. This business philosophy goes by different names. Agile manufacturing, just-in-
time manufacturing, synchronous manufacturing, world-class manufacturing and continuous flow are all terms that are used
in parallel with Lean Manufacturing. So the resounding principle of Lean Manufacturing is to reduce cost through
continuous improvement that will eventually reduce the cost of services and products thus growing more profits.
Lean manufacturing as a technique of productivity improvement – Lean Manufacturing in mining is the production of
coal using less of everything compared to traditional mass production: less waste, human effort, manufacturing space,
investment in tools, inventory, and engineering time to develop a new product.
          Productivity improvement through Lean manufacturing means optimization and co-ordination of the input
resources to minimize the wastes. Improvement in productivity has become need of any industry to take competitive
advantage in the Global market to satisfy the customer at minimum cost. Figure-2




                                   II.       PROBLEM IDENTIFICATION
        In search of a critical problem, the identified problems have been categorized according to the capability of group
members , the involvement of the management and other external agencies, in three categories, i.e.,
        „A‟ category problem – Minimum involvement of other departments in solving them.
       „B‟ category problem – Involvement of the other department is a necessity.
       „C‟ category problem – Management sanction may be needed in implementing the solution.
1.1 IDENTIFICATION OF WASTES:- Table-1
            WASTES/PROBLEMS                                                                         CATEGORY OF
                                                                                                    THE PROBLEM

            a)        Coal seam height thin and thick which is very difficult to excavate, and
            the need of coal does not permit to leave it un-mined.                                          C

            b)        Coal spillage and re-handling of the spilled coal.
                                                                                                            A
            c)        Overall Equipment Effectiveness (OEE)                                                 B

            d)        Pumping system in under ground mine.                                                  B

            e)        Bottleneck (under ground bunker) of the coal transportation system.
                                                                                                            C



                                                            36
Lean Manufacturing and Productivity Improvement in Coal Mining Industry

             f)        Proper tool bit profile during re-sharpening process.                                   A

             g)        Human energy loss due to heavy working conditions                                       C


1)   Lean Production Beliefs- People are an organizations‟ most important asset. The way in which we value those people,
     are our competitive advantage. Keeping them safe and providing excellent working conditions help to show this value.
     While going through the balance sheet of CIL the expenditure on remuneration is nearly 44% of the major six
     expenditures. It is the most vital and critical area to optimize for better output. Manpower is to be effectively used for
     increase of production. Figure-3 Bar Chart

                           2000000

                           1500000

                           1000000                                                             Amt. Lacs

                            500000

                                  0




                                                            Table-2


                      Description in CIL Balance Sheet (AR page no.117)        Rs.x (00000)
                     Remuneration                                                       1821104

                     Stores and spares                                                  523145

                     Contractual expenses                                               458003

                     Over Burdon Removal                                                261847

                     Internal coal consumption                                          234129

                     social overhead                                                    227012


                                                    Figure – 4 Parato Chart

                     1.2
                       1
                     0.8
                     0.6
                     0.4
                     0.2
                       0                                                                        Series 1




                                             III.       METHODOLOGY
Standardization of Work
          Defined as the sequence of job tasks that must be performed by an operator to efficiently and effectively perform a
given job function The persons engaged for coal preparation and coal production are considered as a cell. The working of


                                                              37
Lean Manufacturing and Productivity Improvement in Coal Mining Industry

the cell is dependent on one another and operations are performed sequentially. These operations are to be optimized for
better output.
           Each workman has to carry additional weight of gum boot, helmet, belt and cap lamp, along with his tools and
tackles (that is not standardized hence weight not taken into consideration) to perform their duty in underground mine. A
person has spent his energy in carrying the material and becomes less efficient.
As per the ergonomics principle-
     1) As per book “Motion and Time Study Design and Measurement of Work” by 3Ralph M. Barnes, in chapter
           ‘Factors affecting degree of Fatigue’- A person can work with an energy expenditure up to 5 calories per
           minutes over an 8 hour day without going into “oxygen debt”. On a task that does not tax a person beyond this
           level, no rest period would be needed. If the work is more demanding physically than the 5 Calories/min then rest
           periods should be introduced.
     2) Calculation of rest period -Then total rest required can then be computed from the formula:-
           R = T(K-S) / (K-1.5)
R= Rest required in minutes
T=Total working time
K=Average Kcal/min of type of work (heavy/low)
For heavy physical work K ranging from 7.5-10 Kcal/min, avg.= 8.75 Kcal/min
For light physical work K ranging from 2.5-5 Kcal/min, avg.= 3.75 Kcal/min
S= Standard Kcal/min = 5 Kcal/min
Working in mine and walking on upstairs and downstairs comes under heavy category.
Therefore we will take value of K= 8.75 Kcal/min.
If worker does not take rest it will result into fatigue which causes low work output, deteriorated performance, accidents or
absenteeism from the duties.
The mine chosen for study- Saoner Mine no. 1 in Nagpur Area. It is 45 Kms from Nagpur, having working of Bord and
Pillar method of mining.
In a mine of incline gradient of 1:4.5 and coal seam is 130M below the ground level and the nearest working face is nearly
2KM from the incline at low inline gradient of 1:20-1:30.

Cellular manufacturing- it is one of the cornerstones when one wants to become Lean. A cell consists of persons,
equipment and workstations that are arranged in order to improve the productivity. Arranging people and equipment into
cells has great advantage in terms of achieving Lean goals. One of the advantages of cells is the one-piece flow concept.
In mines there are three districts of working, in each districts there are two cellular groups are deployed for coal preparation.
Each cellular group of 10 persons is consists of- comprising of Mining Sardar, Driller 3, Dresser 2, Carrier 2, Pump operator
1 and Machine operator 1.
Time analysis of one cellular group is noted.
Total time = Unavoidable time + Available time
Unavoidable time=(Preparation time+In/out travelling time+normalization time)
 Available time = (working time+ idle time+ tiffin time)
Corresponding time is represented in bar diagram. The total availability of workers in % is calculated.

Activities Analysis of A Cellular Group During Working Figure-5

                                                                                                           Prep.

                 operator                                                                                  Inw. Tr.
                   Carrier
                    Driller                                                                                Idle
                  Dresser
               Pump Opt.                                                                                   tiffin
              Mining Sard.
                                                                                                           Working
                              0%         20%           40%          60%           80%        100%

Table – 3 Time Study Prior to Installation of Man Rider

           Person/       Mining     Pump     Dri-   Dri-     Dri-   Dre-   Dre-                         M.        Total
            Activity     Sardar      optr     1      2        3       1     2      Carrier   S.Firer   Optr.
           Prepration      32         30     34     34       32      31     34       40        38       37        342
            Inmove         40         38     40     37       41      39     38       40        42       40        395
           Outmove         43         41     42     41       40      42     40       40        44       42        415
           Normalize       43         41     42     40       42      42     40       42        44       42        420


                                                               38
Lean Manufacturing and Productivity Improvement in Coal Mining Industry

           Unavoid.        158       150      158   152    155     154    152       162     168       161     1570
            Lunch           30        30       30    30     30     30     30         30     30         30     300
              Idle         111       136       65    68     73     135    136       140     130        81     1075
            tot.idle       141       166       95    98    103     165    166       170     160       111     1375
           Working         181       164      227   230    222     161    162       148     152       208     1855

Summary of Time Study
                                                                                            Available Working
                            Total time                           Unavoidable time
                                                                                                   time

                      480 mins*10=4800 mins                         1570 mins                     3230 mins
                                                                     32.71%                        67.29%

Human energy calculation
On the basis of ergonomics principles to obtain optimum condition two criteria have to be satisfied:
    i) Energy expenditure should not average more than 5 Kcal/min
    ii) Work should continue at a rate exceeding 5 Kcal/min for an optimum length of time after which rest should be
         taken.

  Data Table No. 4: AVERAGE WEIGHT CARRIED BY A WORKMAN (Director General of Mines Safety Approved)
          DISCRIPTION         I KG/PAIR          II            III          IV             V         AVERAGE
         WEIGHT                              KG/PAIR        KG/PAIR      KG/PAIR       KG/PAIR
         GUM BOOT            2.020          2.010          2.040        2.030         2.025          2.025
         NO.5
         GUM BOOT            2.090          2.100          2.110        2.100         2.100          2.100
         NO.6
         GUM BOOT            2.170          2.190          2.180        2.200         2.180          2.180
         NO.7
         GUM BOOT            2.220          2.230          2.230        2.240         2.230          2.230
         NO.8
         GUM BOOT            2.250          2.250          2.260        2.260         2.255          2.255
         NO.9
                                    AVERAGE WEIGHT OF BOOT                                           2.158
         HALMET              0.280          0.275          0.280        0.280         0.285          0.280
         CAP LAMP TEE        2.390          2.400          2.380        2.390         2.390          2.390
         TYPE
         CAP LAMP            2.330          2.340          2.350        2.340         2.340          2.340
         OLDHAM
         BELT                0.250          0.260          0.260        0.255         0.245          0.250
         TOTAL AVERAGE WEIGHT CARRIED                                                                5.078 KG
Work that is expected from a normal worker is @ 5Kcal/min.
Working for 8x60 = 480 min./day = 480 Min/day x 5 cal/min = 2400 cal/day.
Data Table No. 5:- ENERGY CALCULATION
Energy spent in just reaching to and fro from the pit is calculated by website(by calories calculator on website www.pro
health.com, //www.runners web.com / ).

     Person      Age       Weight.       Height.    Down    To & fro        Up        Carry        Total      Balance
     Name                                           Move                    move      Access.      energy     energy
                                                                                                   spent
     Laxman      39        166           69         107     105             284       373          869        1531
     Sharad      44        154           68         99      97              264       246          706        1694
     Rahim       43        156           66         100     99              267       351          817        1583
     Nathoo      53        178           72         114     113             305       400          932        1468
     Bandoo      57        148           66         95      94              254       332          775        1625
     Jitendra    44        152           68         98      96              260       341          795        1605
     Mohan       34        144           64         92      91              247       323          753        1647
     Yadav       37        168           65         108     106             288       77           579        1821
     Babloo      55        180           66         116     114             308       404          942        1458
     Mukesh      48        188           69         121     119             322       422          984        1416

                                                             39
Lean Manufacturing and Productivity Improvement in Coal Mining Industry

     Total                                                                                                   15848

     Total work Calories                    Unavoidable calories                   Available Working Calories
     2400 cal/day*10 person                 8152 cal                               15848 Calories/cell
     = 24000 cal/cell
                                           33.96%                               66.04%
Nearly 34% of the energy is being spent to just reach up to the working face by a normal man at 120BPM @ 5 kal/ min.
Need of this wasted 800 Kcal/person is to be converted into productive output.

                                  IV.       DATA ANALYSIS AND RESULTS
         Overall human Effectiveness (OHE) is a measure of the overall capacity utilization of workmen of that cellular
group. OHE can be broken down into:

1.   Availability
           How much time has to be given to the worker to normalize after travelling inwards and outwards of the mine with
accessories (average weight 5.078Kg) and tools and tackles in heavy working conditions.
From table- the total time taken by ten persons is (inwards movement = 395mins and outwards movement = 415 mins) 810
mins.
Average time taken by a person to move inward and outwards = 810/10
=81 mins.
Calculating Rest period for a person for 81 minutes travelling inwards and outwards in mine (which is considered as heavy
working condition)
           R = T(K-S) / (K-1.5)
R= Rest required in minutes
T=Total working time
K=Average Kcal/min of type of work (heavy/low)
For heavy physical work K ranging from 7.5-10 Kcal/min, avg.= 8.75 Kcal/min
For light physical work K ranging from 2.5-5 Kcal/min, avg.= 3.75 Kcal/min
S= Standard Kcal/min = 5 Kcal/min
= 81(8.75 – 5.00) / (8.75 – 1.50)
= 41.89 minutes needed by a worker to normalize (recover from Oxygen debt) himself. Nearly 42 minutes time is waste
from the total time available and it is treated as non value added activity, due care must be taken to minimize this time and
increase the worker in productive outputs.

2.   Performance efficiency
          The machine‟s actual throughput when it is operating compared to its designed maximum capacity or the
maximum it could produce based on continuous processing.
In our case availability is 67.29% and performance efficiency is 66%, then the OHE would be:

          Availability x Performance Efficiency = OHE
           67.29 % x         66%                    = 44.41%
          The Overall Human Effectiveness is 44.41% in manual mining system. While going through the balance sheet of
CIL the expenditure on remuneration is nearly 44% of the major six expenditures. It is the most vital and critical area to
optimize for better output. Need of effective and efficient use of manpower is to increase the production and narrow the gap
of demand supply for nation‟s development. Data collected for manual working with OHE 44.41%, the drilling time / face
comes to 57.67 min obtained from 31 days record for four faces/day & production of that shift and trying to find relationship
among them. V-2 is dependent variable on V-1 drilling time, V-3 availability and V-4 balance human energy. Pearson
Correlation prior to man rider system is as below:- Table-6
                                                           Correlations


                                                V1                   V2               V3                   V4
                                                                            **
                  Pearson Correlation            1                  -.672            -.254               -.545**
     V1              Sig. (2-tailed)                                 .000            .168                 .002
                           N                    31                    31              31                   31
                                                      **                                   **
                  Pearson Correlation         -.672                   1             .575                  .688**
     V2              Sig. (2-tailed)           .000                                  .001                 .000
                           N                    31                    31              31                   31
                                                                           **
                  Pearson Correlation          -.254                .575               1                  .259
     V3
                     Sig. (2-tailed)           .168                  .001                                 .159

                                                               40
Lean Manufacturing and Productivity Improvement in Coal Mining Industry

                              N                       31                  31                     31                 31
                                                            **                  **
                  Pearson Correlation               -.545                .688                 .259                   1
      V4             Sig. (2-tailed)                 .002                .000                 .159
                              N                       31                  31                     31                 31
                                    **. Correlation is significant at the 0.01 level (2-tailed).


MANUAL OPERATIONS- Table-7
                                                        Model Summary

     Model            R                 R Square                 Adjusted R Square                 Std. Error of the Estimate
                          a
       1            .856                   .733                          .703                                2.519
                                          a. Predictors: (Constant), V-4, V-3, V-1

                                                  Figure-6 MAN RIDER SYSTEM




3.   Providing of man riding system for Manpower transportation
           When manpower is transported by mechanized mode at faster speed and nearer to the working face it offers less
travelling time, more energetic manpower availability, increases the effective working time for production and more
availability to operate the equipments. Consequently there will be increase in production and increase in productivity. It will
increase the attendance/ presence of workers and reduction in medical bills. Pay back of investment can be easily justified,
therefore it is to be installed in each and every mine

4.   Over all Human Effectiveness after mechanized transportation
           In a mine of incline gradient of 1:4.5 and coal seam is 130M below the ground level and the nearest working face
is nearly 2KM from the incline at low inline gradient of 1:20-1:30.

5.    Increased Availability
          The man rider can transport the manpower irrespective of the inclination and gradient. For the same parameters
@1.5-1.7 m/sec speed man can move to and fro in 45min. and there will be net saving of 35 minutes.
The energetic manpower available in mine for production and the 42 minutes time required to normalize the body will also
be saved which a person avails during his working.
 There will be net time saving = Travelling time saved + normalizing time = 35min +42min =77 min. saved/ person/day
                       Mining.      Pump                      Dri-    Dre- Dre-                             M.    Total
    Person/Activity    Sardar        optr    Dri-1   Dri-2     3        1        2     Carrier S.Firer Optr. Time
  Prepration                 30          36     32      33      34       32       32       38        42      36    345
  (In+walk)move              24          24     25      26      24       25       26       26        24      24    248
  (Out+walk)move             25          26     24      25      26       24       25       26        25      26    252
  Normalize                   8           8       8      8       8        8        8         8         8      8     80
 Unavoid.                      87            94        89         92       92         89    91         98      99         94    925
 Lunch                         30            30        30         30       30         30    30         30      30         30    300
 Idle                         115           142        68         64       75        132   128        135     130         82   1071
 tot.idle                     145           172        98         94      105        162   158        165     160        112   1371
 Working                      248           214      293         294      283        229   231        217     221        274   2504

                                                                    41
Lean Manufacturing and Productivity Improvement in Coal Mining Industry

Table-8

6. Summary of Time Study            Table-9
  Total time                                  Unavoidable time                                Available Working time

 480 mins*10=4800 mins                        925 mins                                        3875 mins

                                              80.72%                                          80.72%


7. Performance efficiency Table-10
The total energy consumed in carrying the accessories by ten persons is given below:-
     1. The total expected work @ 5 Kcal/min is 2400 Kcal in eight hour working.
     2. (4 www.healthyforum.com,www.prohealth.com/ //www.runners web.com / ).
       NAME           AGE            WT        Height in      To & Fro         Carry                        Total        ENERGY
                                    (lbs )     Inches            walk          Access.                     Energy        BALANCE
                                                                energy         Energy                       spent


  Manohar            38             136           65                86                  75                161          2239
  Kunal              44             147           66                93                  81                174          2226
  Tirath             42             123           69                78                  68                146          2254
  Mustaque           53             165           68                104                 91                195          2205
  Prabhakar          59             141           66                89                  78                167          2233
  Deepak             57             151           65                95                  83                195          2205
  Lallan             34             165           68                104                 91                195          2205
  Sudhir             54             180           70                114                 99                213          2187
  Ayodhya            52             191           72                121                 105               226          2174
  Chandu             58             171           73                108                 94                202          2198
                                                                                                                       22126

            Total work Calories                        Unavoidable calories                          Available Working Calories

           2400 cal/day*10 person
                                                              1874 cal/cell                                22126 Calories/cell
              = 24000 cal/cell

                                                                 7.80%                                          92.20%

          After installation of man rider system there is increase of 13.43% in human availability from 67.29% to 80.72%
and increase of 26.2% in human efficiency. Overall Human Effectiveness after man rider system is

          Availability x Performance Efficiency = OHE
         80.72 % x         92.20%              = 74.42%
          From above comparison it is clear that by providing mechanized transportation there is increase of 30.01% in
Overall Human Effectiveness. Data collected for manual working with OHE 74.42%, the drilling time / face comes to
48.85 min obtained from 31 days record for four faces/day & production of that shift and trying to find relationship among
them. V-6 is dependent variable on V-5 drilling time, V-7 availability and V-8 balance human energy. Pearson Correlation
prior to man rider system is as below:- Table-11
                                                   Correlations
                                                       V5                     V6                V7                       V8
                                                                                   **                 **
                    Pearson Correlation                 1                 -.801               -.603                   -.600**
    V5                 Sig. (2-tailed)                                        .000             .000                     .000
                             N                         31                     31                31                       31
                                                            **                                       **
                    Pearson Correlation             -.801                      1              .705                     .794**
    V6                 Sig. (2-tailed)                 .000                                    .000                     .000
                             N                         31                     31                31                       31
                                                            **                     **
                    Pearson Correlation             -.603                 .705                   1                     .566**
    V7
                       Sig. (2-tailed)                 .000                   .000                                      .001

                                                                  42
Lean Manufacturing and Productivity Improvement in Coal Mining Industry

                                      N                        31                 31                 31                      31
                                                                    **                  **                 **
                           Pearson Correlation              -.600                .794               .566                      1
        V8                     Sig. (2-tailed)                 .000              .000               .001
                                      N                        31                 31                 31                      31
**. Correlation is significant at the 0.01 level (2-tailed).Increase in correlation coefficient of availability balance
energy and (-)drilling time there is increases in production of 16.77%.



 Model Summary Table12


       Model                     R                   R Square                  Adjusted R Square                Std. Error of the Estimate

                                      a
             1                 .906                     .821                             .802                             1.938

                                            a. Predictors: (Constant), V8, V7, V5
 8.    Analysis
            In above table- after man riding system associated variables V-5 to V-8 analyzed. V-6 is the dependent variable
 that is production and V-7 availability in mine, V-8 balance human energy & V-5 is drill time of the faces has been analyzed
 for their correlation. It is observed that drilling time is showing negative coefficient which indicates inverse relationship.
 Drilling time Pearson correlation is stronger than the availability and human energy. Lesser the face drilling time the more
 will be the production. Among balance human energy and availability in mine, balance human energy is the more
 contributing factor in perspective of production.
            We have compared the data of production with independent variables availability of manpower, balance human
 energy and face drilling time, which shows significant relationship with production output. After man riding system there is
 increase in production with linear correlation. Man rider system is to be provided to achieve better productivity for better
 utilization of reducing manpower to cater the energy needs of the country.

 9.      Tangible benefits
          Improved morale of the employees and better quality of life.
          Absenteeism rate has decreased and better mine management.
          Medically challenged persons also goes to mine.
          Indirect cost involved reduced fatigue, accidents and medical expenses.
          As the working is cellular and each activity is dependent on one another the waiting time is minimized and can
             move together.

                                                         V.              CONCLUSION
            In manual operation human energy coefficient was more correlated with the production. After man rider
 installation Availability (13.43%) and human efficiency (26.2%) increase contributes in increase in (16.77%) production.
            Lean philosophy is the only way for reduction of waste and improve effectiveness of the resources to compete the
 world. Identification of wastes is a continuous and never ending process, with the application and implementation of lean
 production the coal can be produced with highest quality at cheaper rate.
            It is clear that global competition demands the effective implementation of lean tools in coal industry and more
 research is needed on application of lean tools in the process industry.

                                                               REFERENCES
      [1].       Taichi Ohno “Toyota Production System”
      [2].       Groover M.P. Automation, Production Systems and Computer Integrated system, Prentice Hall, New Jersey.
      [3].       Ralph M. Barnes “ Motion and time study Design and measurement of work” Wiley India Edition
      [4].       Womack James P, Daniel T Jones ; „The Machine that Changed the world. „The story of lean production and lean thinking;
                 banish Waste‟ and „Create wealth in your organization.‟
      [5].       Journal AUG 11, of Indian institution of Industrial Engineering „Lean manufacturing‟ by N.C. Dutta.
      [6].       Int. J. Logistics Systems and Management, Vol. 6, No. 3, 2010 Lean mining: principles for modelling and improving processes of
                 mineral value chains J.G. Steinberg* and G. De Tomi
      [7].       SPSS statistical analysis tool to analyze the data collected.

 Web References
      [1].       Web sites of Coal India „www.coalindia.nic.in‟.
      [2].       Lean manufacturing related web sites
      [3].       www.6 sigma.com
      [4].       www.healthyforum.com,www.prohealth.com/ //www.runners web.com / ).




                                                                          43

Más contenido relacionado

Destacado

Reduced Order Observer (DGO) based State Variable Design of Two Loop Lateral ...
Reduced Order Observer (DGO) based State Variable Design of Two Loop Lateral ...Reduced Order Observer (DGO) based State Variable Design of Two Loop Lateral ...
Reduced Order Observer (DGO) based State Variable Design of Two Loop Lateral ...IJERD Editor
 
Power System Damping Oscillations in Smib with Pss-Fuzzy Upfc Controller
Power System Damping Oscillations in Smib with Pss-Fuzzy Upfc ControllerPower System Damping Oscillations in Smib with Pss-Fuzzy Upfc Controller
Power System Damping Oscillations in Smib with Pss-Fuzzy Upfc ControllerIJERD Editor
 
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...IJERD Editor
 
International Journal of Engineering Research and Development (IJERD)
 International Journal of Engineering Research and Development (IJERD) International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)IJERD Editor
 
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...IJERD Editor
 
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...IJERD Editor
 
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...IJERD Editor
 
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...IJERD Editor
 
A grain of gold will gild a great surface, but not so much as a grain of wisdom
A grain of gold will gild a great surface, but not so much as a grain of wisdomA grain of gold will gild a great surface, but not so much as a grain of wisdom
A grain of gold will gild a great surface, but not so much as a grain of wisdomRhea Myers
 
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...IJERD Editor
 
Love don't get everything, it's true; what it don't get I can't use.
Love don't get everything, it's true; what it don't get I can't use.Love don't get everything, it's true; what it don't get I can't use.
Love don't get everything, it's true; what it don't get I can't use.Rhea Myers
 
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...IJERD Editor
 
Temporal and geographical variation of geo-hydrological risk to the populatio...
Temporal and geographical variation of geo-hydrological risk to the populatio...Temporal and geographical variation of geo-hydrological risk to the populatio...
Temporal and geographical variation of geo-hydrological risk to the populatio...Global Risk Forum GRFDavos
 
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...IJERD Editor
 
GT IBR 2012 - focus on: mainland China
GT IBR 2012 - focus on: mainland ChinaGT IBR 2012 - focus on: mainland China
GT IBR 2012 - focus on: mainland ChinaGrant Thornton
 
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...IJERD Editor
 
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...IJERD Editor
 
Reduced Order Observer (DGO) based State Variable Design of Two Loop Lateral ...
Reduced Order Observer (DGO) based State Variable Design of Two Loop Lateral ...Reduced Order Observer (DGO) based State Variable Design of Two Loop Lateral ...
Reduced Order Observer (DGO) based State Variable Design of Two Loop Lateral ...IJERD Editor
 
Sines no clube dos 14 mil - Cargo
Sines no clube dos 14 mil - CargoSines no clube dos 14 mil - Cargo
Sines no clube dos 14 mil - CargoCláudio Carneiro
 

Destacado (20)

Reduced Order Observer (DGO) based State Variable Design of Two Loop Lateral ...
Reduced Order Observer (DGO) based State Variable Design of Two Loop Lateral ...Reduced Order Observer (DGO) based State Variable Design of Two Loop Lateral ...
Reduced Order Observer (DGO) based State Variable Design of Two Loop Lateral ...
 
Power System Damping Oscillations in Smib with Pss-Fuzzy Upfc Controller
Power System Damping Oscillations in Smib with Pss-Fuzzy Upfc ControllerPower System Damping Oscillations in Smib with Pss-Fuzzy Upfc Controller
Power System Damping Oscillations in Smib with Pss-Fuzzy Upfc Controller
 
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
 
International Journal of Engineering Research and Development (IJERD)
 International Journal of Engineering Research and Development (IJERD) International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)
 
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
 
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
 
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
 
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
 
A grain of gold will gild a great surface, but not so much as a grain of wisdom
A grain of gold will gild a great surface, but not so much as a grain of wisdomA grain of gold will gild a great surface, but not so much as a grain of wisdom
A grain of gold will gild a great surface, but not so much as a grain of wisdom
 
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
 
Love don't get everything, it's true; what it don't get I can't use.
Love don't get everything, it's true; what it don't get I can't use.Love don't get everything, it's true; what it don't get I can't use.
Love don't get everything, it's true; what it don't get I can't use.
 
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
 
Temporal and geographical variation of geo-hydrological risk to the populatio...
Temporal and geographical variation of geo-hydrological risk to the populatio...Temporal and geographical variation of geo-hydrological risk to the populatio...
Temporal and geographical variation of geo-hydrological risk to the populatio...
 
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
 
GT IBR 2012 - focus on: mainland China
GT IBR 2012 - focus on: mainland ChinaGT IBR 2012 - focus on: mainland China
GT IBR 2012 - focus on: mainland China
 
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
 
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
 
Reduced Order Observer (DGO) based State Variable Design of Two Loop Lateral ...
Reduced Order Observer (DGO) based State Variable Design of Two Loop Lateral ...Reduced Order Observer (DGO) based State Variable Design of Two Loop Lateral ...
Reduced Order Observer (DGO) based State Variable Design of Two Loop Lateral ...
 
Relatrio final - IEVA
Relatrio final - IEVARelatrio final - IEVA
Relatrio final - IEVA
 
Sines no clube dos 14 mil - Cargo
Sines no clube dos 14 mil - CargoSines no clube dos 14 mil - Cargo
Sines no clube dos 14 mil - Cargo
 

Similar a IJERD (www.ijerd.com) International Journal of Engineering Research and Development

Lean Manufacturing Cost Cutting Methods
Lean Manufacturing   Cost Cutting MethodsLean Manufacturing   Cost Cutting Methods
Lean Manufacturing Cost Cutting MethodsExerciseLeanLLC
 
IRJET- Implementing Lean Manufacturing Principle in Fabrication Process- A...
IRJET- 	  Implementing Lean Manufacturing Principle in Fabrication Process- A...IRJET- 	  Implementing Lean Manufacturing Principle in Fabrication Process- A...
IRJET- Implementing Lean Manufacturing Principle in Fabrication Process- A...IRJET Journal
 
Implementation of Lean Manufacturing System for Successful Production System ...
Implementation of Lean Manufacturing System for Successful Production System ...Implementation of Lean Manufacturing System for Successful Production System ...
Implementation of Lean Manufacturing System for Successful Production System ...IJERA Editor
 
Lean Tools and resulting ROI 2015
Lean Tools and resulting ROI 2015Lean Tools and resulting ROI 2015
Lean Tools and resulting ROI 2015Bill Bearnson
 
Improvement of Productivity Using Value Stream Mapping
Improvement of Productivity Using Value Stream MappingImprovement of Productivity Using Value Stream Mapping
Improvement of Productivity Using Value Stream Mappingijsrd.com
 
Project report on inventory management prakirn gupta
Project report on inventory management    prakirn guptaProject report on inventory management    prakirn gupta
Project report on inventory management prakirn guptaNITTO DENKO INDIA PVT. LTD
 
1.introduction of production and operations management
1.introduction of production and operations management1.introduction of production and operations management
1.introduction of production and operations managementAkash Bakshi
 
Implementation of Lean Manufacturing Principles in Foundries
Implementation of Lean Manufacturing Principles in FoundriesImplementation of Lean Manufacturing Principles in Foundries
Implementation of Lean Manufacturing Principles in FoundriesIJMER
 
Kaizen Implementation to reduce “No-Stock” in Stores
Kaizen Implementation to reduce “No-Stock” in StoresKaizen Implementation to reduce “No-Stock” in Stores
Kaizen Implementation to reduce “No-Stock” in StoresIRJET Journal
 
The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...
The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...
The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...ijsrd.com
 
Some aspects of Production and Operations Management
Some aspects of Production and Operations ManagementSome aspects of Production and Operations Management
Some aspects of Production and Operations ManagementMinalBhandari2
 
Production & Operation Management EPILOGUE[1]
Production & Operation Management EPILOGUE[1]Production & Operation Management EPILOGUE[1]
Production & Operation Management EPILOGUE[1]Hariharan Ponnusamy
 
Chapter 3 JIT, Value Added and Waste .docx
Chapter 3 JIT, Value Added and Waste            .docxChapter 3 JIT, Value Added and Waste            .docx
Chapter 3 JIT, Value Added and Waste .docxadkinspaige22
 

Similar a IJERD (www.ijerd.com) International Journal of Engineering Research and Development (20)

Lean outlook
Lean outlookLean outlook
Lean outlook
 
Wcm
WcmWcm
Wcm
 
Lean manufacturing report
Lean manufacturing reportLean manufacturing report
Lean manufacturing report
 
Lean Manufacturing Cost Cutting Methods
Lean Manufacturing   Cost Cutting MethodsLean Manufacturing   Cost Cutting Methods
Lean Manufacturing Cost Cutting Methods
 
D04942231
D04942231D04942231
D04942231
 
IRJET- Implementing Lean Manufacturing Principle in Fabrication Process- A...
IRJET- 	  Implementing Lean Manufacturing Principle in Fabrication Process- A...IRJET- 	  Implementing Lean Manufacturing Principle in Fabrication Process- A...
IRJET- Implementing Lean Manufacturing Principle in Fabrication Process- A...
 
E04712935
E04712935E04712935
E04712935
 
Implementation of Lean Manufacturing System for Successful Production System ...
Implementation of Lean Manufacturing System for Successful Production System ...Implementation of Lean Manufacturing System for Successful Production System ...
Implementation of Lean Manufacturing System for Successful Production System ...
 
LEAN
LEANLEAN
LEAN
 
Lean Tools and resulting ROI 2015
Lean Tools and resulting ROI 2015Lean Tools and resulting ROI 2015
Lean Tools and resulting ROI 2015
 
Improvement of Productivity Using Value Stream Mapping
Improvement of Productivity Using Value Stream MappingImprovement of Productivity Using Value Stream Mapping
Improvement of Productivity Using Value Stream Mapping
 
Project report on inventory management prakirn gupta
Project report on inventory management    prakirn guptaProject report on inventory management    prakirn gupta
Project report on inventory management prakirn gupta
 
1.introduction of production and operations management
1.introduction of production and operations management1.introduction of production and operations management
1.introduction of production and operations management
 
Implementation of Lean Manufacturing Principles in Foundries
Implementation of Lean Manufacturing Principles in FoundriesImplementation of Lean Manufacturing Principles in Foundries
Implementation of Lean Manufacturing Principles in Foundries
 
Hugh Jones. Carbon Footprinting Competitive Advantage?
Hugh Jones. Carbon Footprinting Competitive Advantage?Hugh Jones. Carbon Footprinting Competitive Advantage?
Hugh Jones. Carbon Footprinting Competitive Advantage?
 
Kaizen Implementation to reduce “No-Stock” in Stores
Kaizen Implementation to reduce “No-Stock” in StoresKaizen Implementation to reduce “No-Stock” in Stores
Kaizen Implementation to reduce “No-Stock” in Stores
 
The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...
The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...
The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...
 
Some aspects of Production and Operations Management
Some aspects of Production and Operations ManagementSome aspects of Production and Operations Management
Some aspects of Production and Operations Management
 
Production & Operation Management EPILOGUE[1]
Production & Operation Management EPILOGUE[1]Production & Operation Management EPILOGUE[1]
Production & Operation Management EPILOGUE[1]
 
Chapter 3 JIT, Value Added and Waste .docx
Chapter 3 JIT, Value Added and Waste            .docxChapter 3 JIT, Value Added and Waste            .docx
Chapter 3 JIT, Value Added and Waste .docx
 

Más de IJERD Editor

A Novel Method for Prevention of Bandwidth Distributed Denial of Service Attacks
A Novel Method for Prevention of Bandwidth Distributed Denial of Service AttacksA Novel Method for Prevention of Bandwidth Distributed Denial of Service Attacks
A Novel Method for Prevention of Bandwidth Distributed Denial of Service AttacksIJERD Editor
 
MEMS MICROPHONE INTERFACE
MEMS MICROPHONE INTERFACEMEMS MICROPHONE INTERFACE
MEMS MICROPHONE INTERFACEIJERD Editor
 
Influence of tensile behaviour of slab on the structural Behaviour of shear c...
Influence of tensile behaviour of slab on the structural Behaviour of shear c...Influence of tensile behaviour of slab on the structural Behaviour of shear c...
Influence of tensile behaviour of slab on the structural Behaviour of shear c...IJERD Editor
 
Gold prospecting using Remote Sensing ‘A case study of Sudan’
Gold prospecting using Remote Sensing ‘A case study of Sudan’Gold prospecting using Remote Sensing ‘A case study of Sudan’
Gold prospecting using Remote Sensing ‘A case study of Sudan’IJERD Editor
 
Reducing Corrosion Rate by Welding Design
Reducing Corrosion Rate by Welding DesignReducing Corrosion Rate by Welding Design
Reducing Corrosion Rate by Welding DesignIJERD Editor
 
Router 1X3 – RTL Design and Verification
Router 1X3 – RTL Design and VerificationRouter 1X3 – RTL Design and Verification
Router 1X3 – RTL Design and VerificationIJERD Editor
 
Active Power Exchange in Distributed Power-Flow Controller (DPFC) At Third Ha...
Active Power Exchange in Distributed Power-Flow Controller (DPFC) At Third Ha...Active Power Exchange in Distributed Power-Flow Controller (DPFC) At Third Ha...
Active Power Exchange in Distributed Power-Flow Controller (DPFC) At Third Ha...IJERD Editor
 
Mitigation of Voltage Sag/Swell with Fuzzy Control Reduced Rating DVR
Mitigation of Voltage Sag/Swell with Fuzzy Control Reduced Rating DVRMitigation of Voltage Sag/Swell with Fuzzy Control Reduced Rating DVR
Mitigation of Voltage Sag/Swell with Fuzzy Control Reduced Rating DVRIJERD Editor
 
Study on the Fused Deposition Modelling In Additive Manufacturing
Study on the Fused Deposition Modelling In Additive ManufacturingStudy on the Fused Deposition Modelling In Additive Manufacturing
Study on the Fused Deposition Modelling In Additive ManufacturingIJERD Editor
 
Spyware triggering system by particular string value
Spyware triggering system by particular string valueSpyware triggering system by particular string value
Spyware triggering system by particular string valueIJERD Editor
 
A Blind Steganalysis on JPEG Gray Level Image Based on Statistical Features a...
A Blind Steganalysis on JPEG Gray Level Image Based on Statistical Features a...A Blind Steganalysis on JPEG Gray Level Image Based on Statistical Features a...
A Blind Steganalysis on JPEG Gray Level Image Based on Statistical Features a...IJERD Editor
 
Secure Image Transmission for Cloud Storage System Using Hybrid Scheme
Secure Image Transmission for Cloud Storage System Using Hybrid SchemeSecure Image Transmission for Cloud Storage System Using Hybrid Scheme
Secure Image Transmission for Cloud Storage System Using Hybrid SchemeIJERD Editor
 
Application of Buckley-Leverett Equation in Modeling the Radius of Invasion i...
Application of Buckley-Leverett Equation in Modeling the Radius of Invasion i...Application of Buckley-Leverett Equation in Modeling the Radius of Invasion i...
Application of Buckley-Leverett Equation in Modeling the Radius of Invasion i...IJERD Editor
 
Gesture Gaming on the World Wide Web Using an Ordinary Web Camera
Gesture Gaming on the World Wide Web Using an Ordinary Web CameraGesture Gaming on the World Wide Web Using an Ordinary Web Camera
Gesture Gaming on the World Wide Web Using an Ordinary Web CameraIJERD Editor
 
Hardware Analysis of Resonant Frequency Converter Using Isolated Circuits And...
Hardware Analysis of Resonant Frequency Converter Using Isolated Circuits And...Hardware Analysis of Resonant Frequency Converter Using Isolated Circuits And...
Hardware Analysis of Resonant Frequency Converter Using Isolated Circuits And...IJERD Editor
 
Simulated Analysis of Resonant Frequency Converter Using Different Tank Circu...
Simulated Analysis of Resonant Frequency Converter Using Different Tank Circu...Simulated Analysis of Resonant Frequency Converter Using Different Tank Circu...
Simulated Analysis of Resonant Frequency Converter Using Different Tank Circu...IJERD Editor
 
Moon-bounce: A Boon for VHF Dxing
Moon-bounce: A Boon for VHF DxingMoon-bounce: A Boon for VHF Dxing
Moon-bounce: A Boon for VHF DxingIJERD Editor
 
“MS-Extractor: An Innovative Approach to Extract Microsatellites on „Y‟ Chrom...
“MS-Extractor: An Innovative Approach to Extract Microsatellites on „Y‟ Chrom...“MS-Extractor: An Innovative Approach to Extract Microsatellites on „Y‟ Chrom...
“MS-Extractor: An Innovative Approach to Extract Microsatellites on „Y‟ Chrom...IJERD Editor
 
Importance of Measurements in Smart Grid
Importance of Measurements in Smart GridImportance of Measurements in Smart Grid
Importance of Measurements in Smart GridIJERD Editor
 
Study of Macro level Properties of SCC using GGBS and Lime stone powder
Study of Macro level Properties of SCC using GGBS and Lime stone powderStudy of Macro level Properties of SCC using GGBS and Lime stone powder
Study of Macro level Properties of SCC using GGBS and Lime stone powderIJERD Editor
 

Más de IJERD Editor (20)

A Novel Method for Prevention of Bandwidth Distributed Denial of Service Attacks
A Novel Method for Prevention of Bandwidth Distributed Denial of Service AttacksA Novel Method for Prevention of Bandwidth Distributed Denial of Service Attacks
A Novel Method for Prevention of Bandwidth Distributed Denial of Service Attacks
 
MEMS MICROPHONE INTERFACE
MEMS MICROPHONE INTERFACEMEMS MICROPHONE INTERFACE
MEMS MICROPHONE INTERFACE
 
Influence of tensile behaviour of slab on the structural Behaviour of shear c...
Influence of tensile behaviour of slab on the structural Behaviour of shear c...Influence of tensile behaviour of slab on the structural Behaviour of shear c...
Influence of tensile behaviour of slab on the structural Behaviour of shear c...
 
Gold prospecting using Remote Sensing ‘A case study of Sudan’
Gold prospecting using Remote Sensing ‘A case study of Sudan’Gold prospecting using Remote Sensing ‘A case study of Sudan’
Gold prospecting using Remote Sensing ‘A case study of Sudan’
 
Reducing Corrosion Rate by Welding Design
Reducing Corrosion Rate by Welding DesignReducing Corrosion Rate by Welding Design
Reducing Corrosion Rate by Welding Design
 
Router 1X3 – RTL Design and Verification
Router 1X3 – RTL Design and VerificationRouter 1X3 – RTL Design and Verification
Router 1X3 – RTL Design and Verification
 
Active Power Exchange in Distributed Power-Flow Controller (DPFC) At Third Ha...
Active Power Exchange in Distributed Power-Flow Controller (DPFC) At Third Ha...Active Power Exchange in Distributed Power-Flow Controller (DPFC) At Third Ha...
Active Power Exchange in Distributed Power-Flow Controller (DPFC) At Third Ha...
 
Mitigation of Voltage Sag/Swell with Fuzzy Control Reduced Rating DVR
Mitigation of Voltage Sag/Swell with Fuzzy Control Reduced Rating DVRMitigation of Voltage Sag/Swell with Fuzzy Control Reduced Rating DVR
Mitigation of Voltage Sag/Swell with Fuzzy Control Reduced Rating DVR
 
Study on the Fused Deposition Modelling In Additive Manufacturing
Study on the Fused Deposition Modelling In Additive ManufacturingStudy on the Fused Deposition Modelling In Additive Manufacturing
Study on the Fused Deposition Modelling In Additive Manufacturing
 
Spyware triggering system by particular string value
Spyware triggering system by particular string valueSpyware triggering system by particular string value
Spyware triggering system by particular string value
 
A Blind Steganalysis on JPEG Gray Level Image Based on Statistical Features a...
A Blind Steganalysis on JPEG Gray Level Image Based on Statistical Features a...A Blind Steganalysis on JPEG Gray Level Image Based on Statistical Features a...
A Blind Steganalysis on JPEG Gray Level Image Based on Statistical Features a...
 
Secure Image Transmission for Cloud Storage System Using Hybrid Scheme
Secure Image Transmission for Cloud Storage System Using Hybrid SchemeSecure Image Transmission for Cloud Storage System Using Hybrid Scheme
Secure Image Transmission for Cloud Storage System Using Hybrid Scheme
 
Application of Buckley-Leverett Equation in Modeling the Radius of Invasion i...
Application of Buckley-Leverett Equation in Modeling the Radius of Invasion i...Application of Buckley-Leverett Equation in Modeling the Radius of Invasion i...
Application of Buckley-Leverett Equation in Modeling the Radius of Invasion i...
 
Gesture Gaming on the World Wide Web Using an Ordinary Web Camera
Gesture Gaming on the World Wide Web Using an Ordinary Web CameraGesture Gaming on the World Wide Web Using an Ordinary Web Camera
Gesture Gaming on the World Wide Web Using an Ordinary Web Camera
 
Hardware Analysis of Resonant Frequency Converter Using Isolated Circuits And...
Hardware Analysis of Resonant Frequency Converter Using Isolated Circuits And...Hardware Analysis of Resonant Frequency Converter Using Isolated Circuits And...
Hardware Analysis of Resonant Frequency Converter Using Isolated Circuits And...
 
Simulated Analysis of Resonant Frequency Converter Using Different Tank Circu...
Simulated Analysis of Resonant Frequency Converter Using Different Tank Circu...Simulated Analysis of Resonant Frequency Converter Using Different Tank Circu...
Simulated Analysis of Resonant Frequency Converter Using Different Tank Circu...
 
Moon-bounce: A Boon for VHF Dxing
Moon-bounce: A Boon for VHF DxingMoon-bounce: A Boon for VHF Dxing
Moon-bounce: A Boon for VHF Dxing
 
“MS-Extractor: An Innovative Approach to Extract Microsatellites on „Y‟ Chrom...
“MS-Extractor: An Innovative Approach to Extract Microsatellites on „Y‟ Chrom...“MS-Extractor: An Innovative Approach to Extract Microsatellites on „Y‟ Chrom...
“MS-Extractor: An Innovative Approach to Extract Microsatellites on „Y‟ Chrom...
 
Importance of Measurements in Smart Grid
Importance of Measurements in Smart GridImportance of Measurements in Smart Grid
Importance of Measurements in Smart Grid
 
Study of Macro level Properties of SCC using GGBS and Lime stone powder
Study of Macro level Properties of SCC using GGBS and Lime stone powderStudy of Macro level Properties of SCC using GGBS and Lime stone powder
Study of Macro level Properties of SCC using GGBS and Lime stone powder
 

Último

VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Roomdivyansh0kumar0
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024christinemoorman
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyEthan lee
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...noida100girls
 
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdfCatalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdfOrient Homes
 
RE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechRE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechNewman George Leech
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communicationskarancommunications
 
Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.Eni
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayNZSG
 
Socio-economic-Impact-of-business-consumers-suppliers-and.pptx
Socio-economic-Impact-of-business-consumers-suppliers-and.pptxSocio-economic-Impact-of-business-consumers-suppliers-and.pptx
Socio-economic-Impact-of-business-consumers-suppliers-and.pptxtrishalcan8
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurSuhani Kapoor
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in managementchhavia330
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLSeo
 
DEPED Work From Home WORKWEEK-PLAN.docx
DEPED Work From Home  WORKWEEK-PLAN.docxDEPED Work From Home  WORKWEEK-PLAN.docx
DEPED Work From Home WORKWEEK-PLAN.docxRodelinaLaud
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 

Último (20)

Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
 
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdfCatalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
 
RE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechRE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman Leech
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communications
 
Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.
 
Best Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting PartnershipBest Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting Partnership
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
Socio-economic-Impact-of-business-consumers-suppliers-and.pptx
Socio-economic-Impact-of-business-consumers-suppliers-and.pptxSocio-economic-Impact-of-business-consumers-suppliers-and.pptx
Socio-economic-Impact-of-business-consumers-suppliers-and.pptx
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
 
KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in management
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 
DEPED Work From Home WORKWEEK-PLAN.docx
DEPED Work From Home  WORKWEEK-PLAN.docxDEPED Work From Home  WORKWEEK-PLAN.docx
DEPED Work From Home WORKWEEK-PLAN.docx
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 

IJERD (www.ijerd.com) International Journal of Engineering Research and Development

  • 1. International Journal of Engineering Research and Development e-ISSN: 2278-067X, p-ISSN: 2278-800X, www.ijerd.com Volume 2, Issue 10 (August 2012), PP. 35-43 Lean Manufacturing and Productivity Improvement in Coal Mining Industry Er. Manoj Ade1, Dr. V.S.Deshpande2 1 Western Coalfields limited 2 Principal RKNEC, Nagpur India Abstract—The economic reforms- Liberalization, Privatization, Globalization, (LPG) started in 1991 in India. The main objective of the government was to achieve high economic growth and industrialize the nation for the well-being of Indian citizens. Thus Indian market became Global and open market. Coal industry was not an exception to these phenomena of globalization. The improvement in productivity has become need of coal industry to take the competitive advantage of global marketing. Productivity improvement through Lean manufacturing means optimization and co- ordination of the input resources to minimize the wastes to reduce total production cost. This can be achieved by Lean thinking (to identify and eliminate wastes) and Lean Manufacturing (to improve efficiency and effectiveness of equipment). In this paper researcher has applied lean manufacturing concept in order to increase productivity of coal mining. By application of lean tools the Overall Human Effectiveness is analyzed which is converted into productive output to increase the productivity and develop an overview of the conceptual framework of lean manufacturing practices to minimize the production cost of mining. Keywords––Lean thinking, Lean Manufacturing, Lean production, wastes, Overall Human Effectiveness. I. INTRODUCTION Henry Ford is known as “Father of the Management”, continued his focus on waste minimization while developing his mass assembly manufacturing system and work standardization. While standardizing the work, each activity is analyzed on the basis of desirable activity or undesirable activity. All the desirable activities are known as value added activity and undesirable activities are known as wastes. Thus work standardization has become the basis of Lean thinking. Lean thinking is an approach to achieving manufacturing excellence based upon the continued value addition and elimination of waste. Lean thinking is a set of methodologies for maximizing value of an item or feature for which a customer is willing to pay. All other items aspects are deemed waste. Figure-1 Team Based continuous improvement Lean thinking Lean Production maximizing value improve efficiency and minimizing of value added waste. activities Lean Manufacturing Lean production and Lean maintenance- utilizes techniques and principles that improve efficiencies of value, product development, operations, suppliers and customers relations that requires less human effort, less space, less relations that requires less human effort, less space, less capital and less time to make products with fewer defects compared with the previous system of mass production. Lean maintenance- Maintenance works that is to be carried out by application of TPM, 5S, Kanban and Andon with less waste, less human effort, less maintenance space, less investment in tools, less inventory, and in less time. TPM is a lean tool to optimize the effectiveness of equipment and tooling. It is total Employee Involvement, to create a culture where operators develop ownership of their equipment, and become full partners with Maintenance, Engineering and Management to assure equipment operates properly everyday. Lean Manufacturing – Lean Manufacturing is a way to eliminate waste and improve efficiency in a manufacturing environment. Lean manufacturing was successfully implemented by Toyota in his factory hence named as Toyota production. 1 Taiichi Ohno identified wastes as - Elimination of waste is the goal of Lean. Toyota defined three types of waste- 35
  • 2. Lean Manufacturing and Productivity Improvement in Coal Mining Industry 1) Muri – Muri focuses on the preparation and planning of the process or what can be avoided proactively by design. 2) Mura- Mura focuses on implementation and the elimination of fluctuation at the scheduling or operations level such as quality and volume. 3) Muda- Muda is after the process is in place and is dealt with reactively. Taiichi Ohno identified seven types of wastes in operational working. These are- 1) Overproduction – Production ahead of demand. 2) Transportation- Moving products that are not actually required to perform the processing 3) Waiting- Waiting for the next production step. 4) Inventory- All components, work-in-progress and finished product not being processed. 5) Motion People or equipment moving or walking more than is required to perform the processing. 6) Over processing – Due to poor tool or product design creating activity. 7) Defects- The effort involved in inspecting for and fixing defects. Lean manufacturing is the production of coal using less of everything compared to traditional mass production: less waste, human effort, manufacturing space, investment in tools, inventory, and engineering time to develop a new product. The term “Lean” as 4 Womack and his colleagues define it denotes a system that utilizes less, in term of all inputs, to create the same outputs as those created end customer. The Lean Manufacturing discipline is to work in every facet of the value stream by eliminating waste in order to reduce cost, generate capital, bring in more sales and remain competitive in a growing global market. This business philosophy goes by different names. Agile manufacturing, just-in- time manufacturing, synchronous manufacturing, world-class manufacturing and continuous flow are all terms that are used in parallel with Lean Manufacturing. So the resounding principle of Lean Manufacturing is to reduce cost through continuous improvement that will eventually reduce the cost of services and products thus growing more profits. Lean manufacturing as a technique of productivity improvement – Lean Manufacturing in mining is the production of coal using less of everything compared to traditional mass production: less waste, human effort, manufacturing space, investment in tools, inventory, and engineering time to develop a new product. Productivity improvement through Lean manufacturing means optimization and co-ordination of the input resources to minimize the wastes. Improvement in productivity has become need of any industry to take competitive advantage in the Global market to satisfy the customer at minimum cost. Figure-2 II. PROBLEM IDENTIFICATION In search of a critical problem, the identified problems have been categorized according to the capability of group members , the involvement of the management and other external agencies, in three categories, i.e.,  „A‟ category problem – Minimum involvement of other departments in solving them.  „B‟ category problem – Involvement of the other department is a necessity.  „C‟ category problem – Management sanction may be needed in implementing the solution. 1.1 IDENTIFICATION OF WASTES:- Table-1 WASTES/PROBLEMS CATEGORY OF THE PROBLEM a) Coal seam height thin and thick which is very difficult to excavate, and the need of coal does not permit to leave it un-mined. C b) Coal spillage and re-handling of the spilled coal. A c) Overall Equipment Effectiveness (OEE) B d) Pumping system in under ground mine. B e) Bottleneck (under ground bunker) of the coal transportation system. C 36
  • 3. Lean Manufacturing and Productivity Improvement in Coal Mining Industry f) Proper tool bit profile during re-sharpening process. A g) Human energy loss due to heavy working conditions C 1) Lean Production Beliefs- People are an organizations‟ most important asset. The way in which we value those people, are our competitive advantage. Keeping them safe and providing excellent working conditions help to show this value. While going through the balance sheet of CIL the expenditure on remuneration is nearly 44% of the major six expenditures. It is the most vital and critical area to optimize for better output. Manpower is to be effectively used for increase of production. Figure-3 Bar Chart 2000000 1500000 1000000 Amt. Lacs 500000 0 Table-2 Description in CIL Balance Sheet (AR page no.117) Rs.x (00000) Remuneration 1821104 Stores and spares 523145 Contractual expenses 458003 Over Burdon Removal 261847 Internal coal consumption 234129 social overhead 227012 Figure – 4 Parato Chart 1.2 1 0.8 0.6 0.4 0.2 0 Series 1 III. METHODOLOGY Standardization of Work Defined as the sequence of job tasks that must be performed by an operator to efficiently and effectively perform a given job function The persons engaged for coal preparation and coal production are considered as a cell. The working of 37
  • 4. Lean Manufacturing and Productivity Improvement in Coal Mining Industry the cell is dependent on one another and operations are performed sequentially. These operations are to be optimized for better output. Each workman has to carry additional weight of gum boot, helmet, belt and cap lamp, along with his tools and tackles (that is not standardized hence weight not taken into consideration) to perform their duty in underground mine. A person has spent his energy in carrying the material and becomes less efficient. As per the ergonomics principle- 1) As per book “Motion and Time Study Design and Measurement of Work” by 3Ralph M. Barnes, in chapter ‘Factors affecting degree of Fatigue’- A person can work with an energy expenditure up to 5 calories per minutes over an 8 hour day without going into “oxygen debt”. On a task that does not tax a person beyond this level, no rest period would be needed. If the work is more demanding physically than the 5 Calories/min then rest periods should be introduced. 2) Calculation of rest period -Then total rest required can then be computed from the formula:- R = T(K-S) / (K-1.5) R= Rest required in minutes T=Total working time K=Average Kcal/min of type of work (heavy/low) For heavy physical work K ranging from 7.5-10 Kcal/min, avg.= 8.75 Kcal/min For light physical work K ranging from 2.5-5 Kcal/min, avg.= 3.75 Kcal/min S= Standard Kcal/min = 5 Kcal/min Working in mine and walking on upstairs and downstairs comes under heavy category. Therefore we will take value of K= 8.75 Kcal/min. If worker does not take rest it will result into fatigue which causes low work output, deteriorated performance, accidents or absenteeism from the duties. The mine chosen for study- Saoner Mine no. 1 in Nagpur Area. It is 45 Kms from Nagpur, having working of Bord and Pillar method of mining. In a mine of incline gradient of 1:4.5 and coal seam is 130M below the ground level and the nearest working face is nearly 2KM from the incline at low inline gradient of 1:20-1:30. Cellular manufacturing- it is one of the cornerstones when one wants to become Lean. A cell consists of persons, equipment and workstations that are arranged in order to improve the productivity. Arranging people and equipment into cells has great advantage in terms of achieving Lean goals. One of the advantages of cells is the one-piece flow concept. In mines there are three districts of working, in each districts there are two cellular groups are deployed for coal preparation. Each cellular group of 10 persons is consists of- comprising of Mining Sardar, Driller 3, Dresser 2, Carrier 2, Pump operator 1 and Machine operator 1. Time analysis of one cellular group is noted. Total time = Unavoidable time + Available time Unavoidable time=(Preparation time+In/out travelling time+normalization time) Available time = (working time+ idle time+ tiffin time) Corresponding time is represented in bar diagram. The total availability of workers in % is calculated. Activities Analysis of A Cellular Group During Working Figure-5 Prep. operator Inw. Tr. Carrier Driller Idle Dresser Pump Opt. tiffin Mining Sard. Working 0% 20% 40% 60% 80% 100% Table – 3 Time Study Prior to Installation of Man Rider Person/ Mining Pump Dri- Dri- Dri- Dre- Dre- M. Total Activity Sardar optr 1 2 3 1 2 Carrier S.Firer Optr. Prepration 32 30 34 34 32 31 34 40 38 37 342 Inmove 40 38 40 37 41 39 38 40 42 40 395 Outmove 43 41 42 41 40 42 40 40 44 42 415 Normalize 43 41 42 40 42 42 40 42 44 42 420 38
  • 5. Lean Manufacturing and Productivity Improvement in Coal Mining Industry Unavoid. 158 150 158 152 155 154 152 162 168 161 1570 Lunch 30 30 30 30 30 30 30 30 30 30 300 Idle 111 136 65 68 73 135 136 140 130 81 1075 tot.idle 141 166 95 98 103 165 166 170 160 111 1375 Working 181 164 227 230 222 161 162 148 152 208 1855 Summary of Time Study Available Working Total time Unavoidable time time 480 mins*10=4800 mins 1570 mins 3230 mins 32.71% 67.29% Human energy calculation On the basis of ergonomics principles to obtain optimum condition two criteria have to be satisfied: i) Energy expenditure should not average more than 5 Kcal/min ii) Work should continue at a rate exceeding 5 Kcal/min for an optimum length of time after which rest should be taken. Data Table No. 4: AVERAGE WEIGHT CARRIED BY A WORKMAN (Director General of Mines Safety Approved) DISCRIPTION I KG/PAIR II III IV V AVERAGE WEIGHT KG/PAIR KG/PAIR KG/PAIR KG/PAIR GUM BOOT 2.020 2.010 2.040 2.030 2.025 2.025 NO.5 GUM BOOT 2.090 2.100 2.110 2.100 2.100 2.100 NO.6 GUM BOOT 2.170 2.190 2.180 2.200 2.180 2.180 NO.7 GUM BOOT 2.220 2.230 2.230 2.240 2.230 2.230 NO.8 GUM BOOT 2.250 2.250 2.260 2.260 2.255 2.255 NO.9 AVERAGE WEIGHT OF BOOT 2.158 HALMET 0.280 0.275 0.280 0.280 0.285 0.280 CAP LAMP TEE 2.390 2.400 2.380 2.390 2.390 2.390 TYPE CAP LAMP 2.330 2.340 2.350 2.340 2.340 2.340 OLDHAM BELT 0.250 0.260 0.260 0.255 0.245 0.250 TOTAL AVERAGE WEIGHT CARRIED 5.078 KG Work that is expected from a normal worker is @ 5Kcal/min. Working for 8x60 = 480 min./day = 480 Min/day x 5 cal/min = 2400 cal/day. Data Table No. 5:- ENERGY CALCULATION Energy spent in just reaching to and fro from the pit is calculated by website(by calories calculator on website www.pro health.com, //www.runners web.com / ). Person Age Weight. Height. Down To & fro Up Carry Total Balance Name Move move Access. energy energy spent Laxman 39 166 69 107 105 284 373 869 1531 Sharad 44 154 68 99 97 264 246 706 1694 Rahim 43 156 66 100 99 267 351 817 1583 Nathoo 53 178 72 114 113 305 400 932 1468 Bandoo 57 148 66 95 94 254 332 775 1625 Jitendra 44 152 68 98 96 260 341 795 1605 Mohan 34 144 64 92 91 247 323 753 1647 Yadav 37 168 65 108 106 288 77 579 1821 Babloo 55 180 66 116 114 308 404 942 1458 Mukesh 48 188 69 121 119 322 422 984 1416 39
  • 6. Lean Manufacturing and Productivity Improvement in Coal Mining Industry Total 15848 Total work Calories Unavoidable calories Available Working Calories 2400 cal/day*10 person 8152 cal 15848 Calories/cell = 24000 cal/cell 33.96% 66.04% Nearly 34% of the energy is being spent to just reach up to the working face by a normal man at 120BPM @ 5 kal/ min. Need of this wasted 800 Kcal/person is to be converted into productive output. IV. DATA ANALYSIS AND RESULTS Overall human Effectiveness (OHE) is a measure of the overall capacity utilization of workmen of that cellular group. OHE can be broken down into: 1. Availability How much time has to be given to the worker to normalize after travelling inwards and outwards of the mine with accessories (average weight 5.078Kg) and tools and tackles in heavy working conditions. From table- the total time taken by ten persons is (inwards movement = 395mins and outwards movement = 415 mins) 810 mins. Average time taken by a person to move inward and outwards = 810/10 =81 mins. Calculating Rest period for a person for 81 minutes travelling inwards and outwards in mine (which is considered as heavy working condition) R = T(K-S) / (K-1.5) R= Rest required in minutes T=Total working time K=Average Kcal/min of type of work (heavy/low) For heavy physical work K ranging from 7.5-10 Kcal/min, avg.= 8.75 Kcal/min For light physical work K ranging from 2.5-5 Kcal/min, avg.= 3.75 Kcal/min S= Standard Kcal/min = 5 Kcal/min = 81(8.75 – 5.00) / (8.75 – 1.50) = 41.89 minutes needed by a worker to normalize (recover from Oxygen debt) himself. Nearly 42 minutes time is waste from the total time available and it is treated as non value added activity, due care must be taken to minimize this time and increase the worker in productive outputs. 2. Performance efficiency The machine‟s actual throughput when it is operating compared to its designed maximum capacity or the maximum it could produce based on continuous processing. In our case availability is 67.29% and performance efficiency is 66%, then the OHE would be: Availability x Performance Efficiency = OHE 67.29 % x 66% = 44.41% The Overall Human Effectiveness is 44.41% in manual mining system. While going through the balance sheet of CIL the expenditure on remuneration is nearly 44% of the major six expenditures. It is the most vital and critical area to optimize for better output. Need of effective and efficient use of manpower is to increase the production and narrow the gap of demand supply for nation‟s development. Data collected for manual working with OHE 44.41%, the drilling time / face comes to 57.67 min obtained from 31 days record for four faces/day & production of that shift and trying to find relationship among them. V-2 is dependent variable on V-1 drilling time, V-3 availability and V-4 balance human energy. Pearson Correlation prior to man rider system is as below:- Table-6 Correlations V1 V2 V3 V4 ** Pearson Correlation 1 -.672 -.254 -.545** V1 Sig. (2-tailed) .000 .168 .002 N 31 31 31 31 ** ** Pearson Correlation -.672 1 .575 .688** V2 Sig. (2-tailed) .000 .001 .000 N 31 31 31 31 ** Pearson Correlation -.254 .575 1 .259 V3 Sig. (2-tailed) .168 .001 .159 40
  • 7. Lean Manufacturing and Productivity Improvement in Coal Mining Industry N 31 31 31 31 ** ** Pearson Correlation -.545 .688 .259 1 V4 Sig. (2-tailed) .002 .000 .159 N 31 31 31 31 **. Correlation is significant at the 0.01 level (2-tailed). MANUAL OPERATIONS- Table-7 Model Summary Model R R Square Adjusted R Square Std. Error of the Estimate a 1 .856 .733 .703 2.519 a. Predictors: (Constant), V-4, V-3, V-1 Figure-6 MAN RIDER SYSTEM 3. Providing of man riding system for Manpower transportation When manpower is transported by mechanized mode at faster speed and nearer to the working face it offers less travelling time, more energetic manpower availability, increases the effective working time for production and more availability to operate the equipments. Consequently there will be increase in production and increase in productivity. It will increase the attendance/ presence of workers and reduction in medical bills. Pay back of investment can be easily justified, therefore it is to be installed in each and every mine 4. Over all Human Effectiveness after mechanized transportation In a mine of incline gradient of 1:4.5 and coal seam is 130M below the ground level and the nearest working face is nearly 2KM from the incline at low inline gradient of 1:20-1:30. 5. Increased Availability The man rider can transport the manpower irrespective of the inclination and gradient. For the same parameters @1.5-1.7 m/sec speed man can move to and fro in 45min. and there will be net saving of 35 minutes. The energetic manpower available in mine for production and the 42 minutes time required to normalize the body will also be saved which a person avails during his working. There will be net time saving = Travelling time saved + normalizing time = 35min +42min =77 min. saved/ person/day Mining. Pump Dri- Dre- Dre- M. Total Person/Activity Sardar optr Dri-1 Dri-2 3 1 2 Carrier S.Firer Optr. Time Prepration 30 36 32 33 34 32 32 38 42 36 345 (In+walk)move 24 24 25 26 24 25 26 26 24 24 248 (Out+walk)move 25 26 24 25 26 24 25 26 25 26 252 Normalize 8 8 8 8 8 8 8 8 8 8 80 Unavoid. 87 94 89 92 92 89 91 98 99 94 925 Lunch 30 30 30 30 30 30 30 30 30 30 300 Idle 115 142 68 64 75 132 128 135 130 82 1071 tot.idle 145 172 98 94 105 162 158 165 160 112 1371 Working 248 214 293 294 283 229 231 217 221 274 2504 41
  • 8. Lean Manufacturing and Productivity Improvement in Coal Mining Industry Table-8 6. Summary of Time Study Table-9 Total time Unavoidable time Available Working time 480 mins*10=4800 mins 925 mins 3875 mins 80.72% 80.72% 7. Performance efficiency Table-10 The total energy consumed in carrying the accessories by ten persons is given below:- 1. The total expected work @ 5 Kcal/min is 2400 Kcal in eight hour working. 2. (4 www.healthyforum.com,www.prohealth.com/ //www.runners web.com / ). NAME AGE WT Height in To & Fro Carry Total ENERGY (lbs ) Inches walk Access. Energy BALANCE energy Energy spent Manohar 38 136 65 86 75 161 2239 Kunal 44 147 66 93 81 174 2226 Tirath 42 123 69 78 68 146 2254 Mustaque 53 165 68 104 91 195 2205 Prabhakar 59 141 66 89 78 167 2233 Deepak 57 151 65 95 83 195 2205 Lallan 34 165 68 104 91 195 2205 Sudhir 54 180 70 114 99 213 2187 Ayodhya 52 191 72 121 105 226 2174 Chandu 58 171 73 108 94 202 2198 22126 Total work Calories Unavoidable calories Available Working Calories 2400 cal/day*10 person 1874 cal/cell 22126 Calories/cell = 24000 cal/cell 7.80% 92.20% After installation of man rider system there is increase of 13.43% in human availability from 67.29% to 80.72% and increase of 26.2% in human efficiency. Overall Human Effectiveness after man rider system is Availability x Performance Efficiency = OHE 80.72 % x 92.20% = 74.42% From above comparison it is clear that by providing mechanized transportation there is increase of 30.01% in Overall Human Effectiveness. Data collected for manual working with OHE 74.42%, the drilling time / face comes to 48.85 min obtained from 31 days record for four faces/day & production of that shift and trying to find relationship among them. V-6 is dependent variable on V-5 drilling time, V-7 availability and V-8 balance human energy. Pearson Correlation prior to man rider system is as below:- Table-11 Correlations V5 V6 V7 V8 ** ** Pearson Correlation 1 -.801 -.603 -.600** V5 Sig. (2-tailed) .000 .000 .000 N 31 31 31 31 ** ** Pearson Correlation -.801 1 .705 .794** V6 Sig. (2-tailed) .000 .000 .000 N 31 31 31 31 ** ** Pearson Correlation -.603 .705 1 .566** V7 Sig. (2-tailed) .000 .000 .001 42
  • 9. Lean Manufacturing and Productivity Improvement in Coal Mining Industry N 31 31 31 31 ** ** ** Pearson Correlation -.600 .794 .566 1 V8 Sig. (2-tailed) .000 .000 .001 N 31 31 31 31 **. Correlation is significant at the 0.01 level (2-tailed).Increase in correlation coefficient of availability balance energy and (-)drilling time there is increases in production of 16.77%. Model Summary Table12 Model R R Square Adjusted R Square Std. Error of the Estimate a 1 .906 .821 .802 1.938 a. Predictors: (Constant), V8, V7, V5 8. Analysis In above table- after man riding system associated variables V-5 to V-8 analyzed. V-6 is the dependent variable that is production and V-7 availability in mine, V-8 balance human energy & V-5 is drill time of the faces has been analyzed for their correlation. It is observed that drilling time is showing negative coefficient which indicates inverse relationship. Drilling time Pearson correlation is stronger than the availability and human energy. Lesser the face drilling time the more will be the production. Among balance human energy and availability in mine, balance human energy is the more contributing factor in perspective of production. We have compared the data of production with independent variables availability of manpower, balance human energy and face drilling time, which shows significant relationship with production output. After man riding system there is increase in production with linear correlation. Man rider system is to be provided to achieve better productivity for better utilization of reducing manpower to cater the energy needs of the country. 9. Tangible benefits  Improved morale of the employees and better quality of life.  Absenteeism rate has decreased and better mine management.  Medically challenged persons also goes to mine.  Indirect cost involved reduced fatigue, accidents and medical expenses.  As the working is cellular and each activity is dependent on one another the waiting time is minimized and can move together. V. CONCLUSION In manual operation human energy coefficient was more correlated with the production. After man rider installation Availability (13.43%) and human efficiency (26.2%) increase contributes in increase in (16.77%) production. Lean philosophy is the only way for reduction of waste and improve effectiveness of the resources to compete the world. Identification of wastes is a continuous and never ending process, with the application and implementation of lean production the coal can be produced with highest quality at cheaper rate. It is clear that global competition demands the effective implementation of lean tools in coal industry and more research is needed on application of lean tools in the process industry. REFERENCES [1]. Taichi Ohno “Toyota Production System” [2]. Groover M.P. Automation, Production Systems and Computer Integrated system, Prentice Hall, New Jersey. [3]. Ralph M. Barnes “ Motion and time study Design and measurement of work” Wiley India Edition [4]. Womack James P, Daniel T Jones ; „The Machine that Changed the world. „The story of lean production and lean thinking; banish Waste‟ and „Create wealth in your organization.‟ [5]. Journal AUG 11, of Indian institution of Industrial Engineering „Lean manufacturing‟ by N.C. Dutta. [6]. Int. J. Logistics Systems and Management, Vol. 6, No. 3, 2010 Lean mining: principles for modelling and improving processes of mineral value chains J.G. Steinberg* and G. De Tomi [7]. SPSS statistical analysis tool to analyze the data collected. Web References [1]. Web sites of Coal India „www.coalindia.nic.in‟. [2]. Lean manufacturing related web sites [3]. www.6 sigma.com [4]. www.healthyforum.com,www.prohealth.com/ //www.runners web.com / ). 43