SlideShare una empresa de Scribd logo
1 de 18
Descargar para leer sin conexión
QUALITY CHECKLIST FOR SITE WORKS
SURVEYING AND SETTING OUT
Name of the Customer: Date:
Project Name: Project ID:
Name of the Contractor: Location:
Drawing Ref. No.: Quantity:
Sl.No. Description YES NO NA
1 Is contour/ survey plan available?
2
3
4
5
Comments:
Contractor's Rep.: Client Rep.: Lemcon Rep.:
Establishment of Co-ordination points, MAIN GRID LINES,
CENTRE LINES in both directions, block levels, spot level etc.
Is it as per Drawings?
Check for set back are they as per the norms of local authority
approval drawing?
Check whether there is any variation in the actual marking and
whether it is recorded/ reported?
LOCATION of INDIVIDUAL STRUCTURAL ELEMENTS like
Column footings, columns, location of pile, etc.,
Are they as per Drawings?
CORRECTIVE ACTION PROPOSED- Item wise.
If 'No' is marked, please specify reasons and thereafter corrective action proposed.
(Add additional sheets, if necessary)
ARCHITECTURAL STRUCTURL INTERIOR SERVICES & UTILITY
CL : 01CL : 01
QUALITY CHECKLIST FOR SITE WORKS
EARTH WORK/ BACKFILLING
Name of the Customer: Date:
Project Name: Project ID:
Name of the Contractor: Location:
Drawing Ref. No.: Quantity:
Sl.No. Description YES NO NA
1 Is format CL: 01 for Surveying complied with?
2
3
4 Is adequate shoring, strutting done?
5 Check for DEWATERING. Is it O.K.?
6 Is the excavation done up-to the level as per drawing.
A. NATURAL EXISTING GROUND LEVEL :
B. FOUNDING LEVEL :
C. DEPTH OF EXCAVATION :
BACKFILLING
1 Is the earth used for filling as per specification?
2
3
Contractor's Rep.: Client Rep.: Lemcon Rep.:
Whether suitable arrangements for re-routing the service lines
done?
Is the LAYOUT, ALIGNMENT and SIZE of Excavation marked
on the ground as per drawings?
Check for the approved method of compaction, ie. (Roller, plate
compactor, etc.,)
Whether Proctor compaction test carried out satisfactorily as
per the requirement?
CORRECTIVE ACTION PROPOSED- Item wise.
If 'No' is marked, please specify reasons and thereafter corrective action proposed.
ARCHITECTURAL STRUCTURAL SITE
DEVELOPMENT
SERVICES & UTILITY
CL : 02CL : 02
$
$
QUALITY CHECKLIST FOR SITE WORKS
CONCRETE POUR CARD
Name of the Customer: Date:
Project Name: Project ID:
Name of the Contractor: Location:
Drawing Ref. No.: Grade & Quantity :
Sl.No. Description YES NO NA
A. FORM WORK:
1 Level
2 Plumb
3 Cutouts
B. Reinforcement:
1 As per bar bending schedule
2 Dowel bars
3 Links
4 Binding/ Welding
C. Services:
1 Position
2 Size
3 Trimming bars
D. General
1 Embedments
2 Water proofing
3 Construction Joint
E. Sampling:
1 Mix as per design :
2 No. of sample & Identity
Comments:
Contractor's Rep.: Client Rep.: Lemcon Rep.:
IF 'YES', THEN SITE ENGINEER SHALL TAKE SUITABLE CORRECTIVE ACTION in consultation with
PRT/ AST/ PRM AND RECHECK .
CORRECTIVE ACTION PROPOSED- Item wise.
If 'No' is marked, please specify reasons and thereafter corrective action proposed.
(Add additional sheets, if necessary)
ARCHITECTURAL STRUCTURAL INTERIOR SERVICES & UTILITY
CL : 03CL : 03
QUALITY CHECKLIST FOR SITE WORKS
WATER PROOFING
Name of the Customer: Date:
Project Name: Project ID:
Name of the Contractor: Location:
Drawing Ref. No.: Quantity:
Sl.No. Description YES NO NA
1
2 Check for surface preparation. Is it o.k.?
3 Check for Plastering before coating. Is it o.k.?
4 Check for coating of chemical. Is it o.k.?
5 Check for Plastering after coating. Is it o.k.?
6 Check for fixing of nozzles and spacing. Is it o.k.?
7 Check for grouting. Is it o.k.?
8 Check for brickbatcoba thickness & slopes.
9 Check for curing. Is it o.k.?
Comments:
Contractor's Rep.: Client Rep.: Lemcon Rep.:
Whether approved / specified materials used as per
specification?
CORRECTIVE ACTION PROPOSED- Item wise.
If 'No' is marked, please specify reasons and thereafter corrective action proposed.
(Add additional sheets, if necessary)
ARCHITECTURAL STRUCTURAL INTERIOR SERVICES & UTILITY
1. Raft slab 2. Retaining wall 3. Toilet sunken 4. Terrace
CL : 04CL : 04
QUALITY CHECKLIST FOR SITE WORKS
EXTERNAL & PARTITION WALL/ RR MASONRY
Name of the Customer: Date:
Project Name: Project ID:
Name of the Contractor: Location:
Drawing Ref. No.: Quantity:
Sl.No. Description YES NO NA
Thickness
1
2 Check for placing reinforcement RC bands as per specification.
3
4
INTERIOR - (PARTITION / WALL PANELLING FRAME WORK)
1 Type of Partitions/ Frame etc.,
Frame work materials used.
a) Aluminum frames
b) Timber frames
c) G.I /M.S frames
2
3 Height of Partition.
b) Half height
4
5
6
Comments:
Contractor's Rep.: Client Rep.: Lemcon Rep.:
Check for ALIGNMENT & LOCATION of wall. Is it as per
drawing?
Check for MORTAR MIX PROPORTION is ok?
Check for SIZES OF OPENINGS for Doors & Windows? /
Any other sevices.
AC duct, Cable tray, chilled water pipe, etc.
If it is wooden partition, check for Anti-termite/ wood borer
preventing treatment provided?
Whether the frame work sufficiently anchored in the floor & true
ceiling?
Check provisions made in the frame work for fixing conduits for
electrical, Data lines etc., as per drawings.
Check for approved make of finishing materials as per
specification.
CORRECTIVE ACTION PROPOSED- Item wise.
If 'No' is marked, please specify reasons and thereafter corrective action proposed.
(Add additional sheets, if necessary)
:
ARCHITECTURAL STRUCTURAL INTERIOR SERVICES & UTILITY
9. Glazed
Hollow
1. Brick 2. Solid Block 4. R . R 5. C. R
10. Others6. Aerocon Block 7. Gypsum
3. Hollow Block
8. Wooden
CL : 05CL : 05
QUALITY CHECKLIST FOR SITE WORKS
PLASTERING/ PAINTING
Name of the Customer: Date:
Project Name: Project ID:
Name of the Contractor: Location:
Drawing Ref. No.: Quantity:
Sl.No. Description YES NO NA
1
2
3
4
PAINTING
1
DURING & AFTER PAINTING
1
2 Check for Number of Coats.
Comments:
Contractor's Rep.: Client Rep.: Lemcon Rep.:
Check for COMPLETION OF PRECEDING ACTIVITIES like
fixing of service Conduits, Water Supply & sanitation lines, etc.
Whether chicken mesh, Corner beads used as per
specifications?
Check for MORTAR MIX PROPORTION & Check for Surface of
mortar mixing and addition of water profing compond if required.
Check for THICKNESS & NUMBER OF COATS of Plaster and
required finish for further activities.
PRIOR TO PAINTING
Check whether approved make & shade are used?
Check for APPLICATION of paint. Is it uniform?
CORRECTIVE ACTION PROPOSED- Item wise.
If 'No' is marked, please specify reasons and thereafter corrective action proposed.
(Add additional sheets, if necessary)
ARCHITECTURAL STRUCTURAL INTERIOR SERVICES & UTILITY
CL : 06CL : 06
QUALITY CHECKLIST FOR SITE WORKS
JOINERIES - (FIXING DOORS/ WINDOWS/ VENTILATOR)
Name of the Customer: Date:
Project Name: Project ID:
Name of the Contractor: Location:
Drawing Ref. No.: Quantity:
Sl.No. Description YES NO NA
1 Whether specified material and approved sample are used?
2
3
4 Check for fixing and grouting of frames with hold fasts. Is it o.k.?
5 Check whether architrave is specified for door frames?
6
7 Locks/ Latches
8 Handle
9 Weather stripping / Stoppers
Comments:
Contractor's Rep.: Client Rep.: Lemcon Rep.:
Check for the correct size of frames/ shutters as per drawing. Is
it o.k?
Check for the proper primer painting, powder coating, Anodizing
coating and other finishes to frames before fixing. Is it o.k.?
Check vision panel, door closers, floor spring, Access card ,
whether provision made.
CORRECTIVE ACTION PROPOSED- Item wise.
If 'No' is marked, please specify reasons and thereafter corrective action proposed.
(Add additional sheets, if necessary)
ARCHITECTURAL STRUCTURAL INTERIOR SERVICES & UTILITY
CL : 07CL : 07
QUALITY CHECKLIST FOR SITE WORKS
FLOORING/ DADOING
Name of the Customer:
Project Name:
Name of the Contractor:
Drawing Ref. No.:
Sl.No. Description
I Prior to Tiling:
1
2
3
4
5
6
7
LAYING PAVER BLOCKS
1 All pipe line/ Conduiting/ Sleeve work completed.
2 Check formation level ie. Bottom of sand bedding
3 Check thickness, shape, colour, pattern of paver blocks.
Comments:
Contractor's Rep.: Client Rep.: Lemcon Rep.:
Check for COMPLETION OF PRECEDING ACTIVITIES like
fixing of Door, Frames, Partitions, etc.
A. Check for Provision of Service Conduits, junction Boxes,
plumbing, etc.
Is the SAMPLE OF TILES approved?.
Check for MORTAR MIX/ ADHESIVE PROPORTION. Is it as
specified?
Check for THICKNESS OF MORTAR BED. Is it o.k?
Check for PATTERN OF LAYING. Is it ok?
Check for TOP LEVEL. Is it o.k?
CORRECTIVE ACTION PROPOSED- Item wise.
If 'No' is marked, please specify reasons and thereafter corrective action proposed.
(Add additional sheets, if necessary)
ARCHITECTURAL INTERIOR
1. Ceramic tile 2. Vitrified tile 3. Marble
5. Cement based tile 6. Mosaic
DADOINGFLOORING SKIRTING
7. Paver block
CL : 08CL : 08
FOR SITE WORKS
ADOING
Date:
Project ID:
Location:
Quantity:
YES NO NA
Lemcon Rep.:
orrective action proposed.
4. Granite
8. Others
EXTERNAL CLADDING
7. Paver block
QUALITY CHECKLIST FOR SITE WORKS
INTERIOR (FALSECEILING)
Name of the Customer: Date:
Project Name: Project ID:
Name of the Contractor: Location:
Drawing Ref. No.: Quantity:
Description YES NO NA
1 Check the type of falseceiling as per specification.
2
3
4
5
6
Comments:
Contractor's Rep.: Client Rep.: Lemcon Rep.:
Sl.N
o.
If it is Grid type, Check whether grids are marked as per
drawing so as to locate the service points.
Check whether the frame work and hanger rods are as per
specification.
Before fixing/ laying of boards check all service works such as
electrical, AC ducting, fire alarm, sprinkler, speakers, smoke
detector, heat detector, etc, Whether cutout/ opening provided.
Check for any cornices, trap door provision as per the drawing.
Check for painting of ceiling ( If it is board) - is it as per
specification.
CORRECTIVE ACTION PROPOSED- Item wise.
If 'No' is marked, please specify reasons and thereafter corrective action proposed.
(Add additional sheets, if necessary)
ARCHITECTURAL STRUCTURAL INTERIOR SERVICES & UTILITY
CL : 09CL : 09
QUALITY CHECKLIST FOR SITE WORKS
ROAD & DRAINS WORKS
Name of the Customer: Date:
Project Name: Project ID:
Name of the Contractor: Location:
Drawing Ref. No.: Quantity:
Sl.No. Description YES NO NA
PREPARATION OF SUBGRADE
1
SAND - GRAVEL MIX FOR ROAD WORK.
1 Check the formation of subgrade with specified camber.
2
3
W.B.M:
1 Check for proper grading of aggregates.
2
3
4
5
6
ASPHALT/ BT FOR ROAD WORKS
2 Check Whether tack coat application is done properly.
3 Check for Uniform spread thickness of premix. Is it o.k.?
4
Drain work:
1 Marking layout line level of R.C.C drain.
2 Making R.C.C. drain all as per drawing in line, level & slope.
Comments:
PREPARATION OF SUBGRADE to specified lines and Camber.
Check for Cleaning and Making up of Soft spots & other
irregularities.
Check for spreading in layers as specified and watering has
been done on prior to the required proctor density to the
required compaction.
Check for finished surfaces, compacted thickness, camber,
gradient lines and slope. Are they acceptable?
Check for Underground trenches / Hume pipes / Drain crossing /
road crossing LAYOUTS, GRADES & CROSS - SECTIONS OF
COMPACTED SUBGRADE prior to spreading of aggregates.
Check for UNIFORM SPREAD THICKNESS of Aggregates.
Check for DRY ROLLING, using proper road roller.
Check for WET ROLLING of Aggregates and COMPACTION.
Check for FINISHED SURFACES, COMPACTED THICKNESS,
CAMBER, LINES AND SLOPE.Are they acceptable?
Check for finished surfaces,compacted thickness. gradient lines
and slope: Are they acceptable.
CORRECTIVE ACTION PROPOSED- Item wise.
If 'No' is marked, please specify reasons and thereafter corrective action proposed.
(Add additional sheets, if necessary)
SERVICES & UTILITY
CL : 10CL : 10
Sl.No. Description YES NO NA
CL : 10CL : 10
Contractor's Rep.: Client Rep.: Lemcon Rep.:
QUALITY CHECKLIST FOR SITE WORKS
Name of the Customer: Date:
Project Name: Project ID:
Name of the Contractor: Location:
Drawing Ref. No.: Quantity:
Sl.No. Description YES NO NA
1 Check the setting out is line with drawing/ layout
2
3 Check the type of finish :
a) Laminate
b) Veneer with melamine polish
c) ACP
4
INTERIOR (STORAGE UNIT)
1
b) 1200 mm height
c) 2100/ 2400 mm height
2
3
4 Check is it modular/ Custorm built.
1
2
3
4 Check type of skirting.
5 Check location of switch boxes, is it ok?
INTERIOR (FURNISHING WORKS)
1
2 Check whether chair is of specified make colour and shade.
INTERIOR - (FURNITURES/ STORAGE UNIT/ PARTITION/ PANELLING/ FURNISHING
WORKS)
Check the provisions are made for such as pencil drawer, Key
board drawer, storage units attached with the table.
Check the Approved make and thickness of materials as per
specifications and drawings.
Type of storage unit:
a) 750 mm Low height
Check the Hardware such as lock, hinges, handles are provided
with as per specifications / drawings.
Check the plywood thickness, finishing of material whether with
Laminate or Veneer.
Check type of internal frame work (work/ Aluminium box
sections)
Check type of partition (Fully solid/ Fully glazed/ combination of
glass and opaque)
Check before fixing of plywood electrical civil access, other
services consul
Check whether the carpet is of specified make colour and
shade.
ARCHITECTURAL STRUCTURAL INTERIOR SERVICES & UTILITY
CL : 11CL : 11
Sl.No. Description YES NO NA
CL : 11CL : 11
3
4 Check about etching designs in glass partition.
Comments:
Contractor's Rep.: Client Rep.: Lemcon Rep.:
Check the Fabric Pinup board.Is the fabric, colour, size of board
as per drawing / Specification.
CORRECTIVE ACTION PROPOSED- Item wise.
If 'No' is marked, please specify reasons and thereafter corrective action proposed.
(Add additional sheets, if necessary)
QUALITY CHECKLIST FOR SITE WORKS
PLUMBING & SANITARY/ SANITARY FIXTURES
Name of the Customer:
Project Name:
Name of the Contractor:
Drawing Ref. No.:
Sl.No. Description
Water supply:
1
2
3
4
5
Sewer Line:
1
2
3
4
5 Whether leak tests conducted?
SANITARY FIXTURES & FITTINGS
1
Comments:
Contractor's Rep.: Client Rep.: Lemcon Rep.:
Check whether all pipe joints and method of jointing are done as
per specification and conforming to relevant IS codes and
standards.
Whether the samples of pipes and fittings are as per approved
specification?
Whether the concealed pipe lines are painted and protected as
per the specification?
Whether connected pipe lines and fittings are satisfactorily
tested for leaks before covering?
Ceiling suspended lines adequately supported by suitable dia of
rod/ anchor fastener with suitable spacing.
Check the approved pipes are used for the sewer lines. Is it
o.k.?
Check for the levels and alignment of sewer line as per
drawing / specifications. Is it o.k.?
Check whether the jointing of pipes are as per specifications/
drawing. Is it o.k.?
Check whether for the inspection chambers are at the correct
location shape and to the correct invert level as per drawings/
specifications.
Whether the fixtures are fixed in correct position and level as per
the drawings/ specifications?
ARCHITECTURAL STRUCTURAL INTERIOR
CL : 12CL : 12
FOR SITE WORKS
ANITARY FIXTURES
Date:
Project ID:
Location:
Quantity:
YES NO NA
Lemcon Rep.:
INTERIOR SERVICES & UTILITY
C.R. Narayana Rao
Architects & Engineers
Rev.1 dtd. 13.01.2006
17 of 18
QUALITY CHECKLIST FOR SITE WORKS
ELECTRICAL INSTALLATION WORKS
Name of the Customer: Date:
Project Name: Project ID:
Name of the Contractor: Location:
Drawing Ref. No.: Quantity:
The following Indian Standard Codes are adopted for Installing the equipments at site
Sl. No. Description YES NO NA
I.S No.
1 CODE OF PRACTICES
2 732/1989 - Code of Practice for Electrical wiring installation.
3
4
5
6
7
Comments:
Contractor's Rep.: Client Rep.: Lemcon Rep.:
8884/1976 - Code of Practice for the installation of electric bell
and call system.
10028 Part 1 1985 - Code of Practice for selection installation and
maintenance of transformers Part 2 Installation.
10118 Part 3 1982 - Code of Practice for selection, installation
and maintenance of switchgear and control gear Part 3-
Installation.
5613 Part 2 Selection 1 1985 - Code of Practice for design
installation and maintenance of overhead power lines Part 2 lines
upto and including 11KV section 1 Installation.
1255 (1983) - Code of Practice for Installation and Maintenance
of Power Cables upto and inlcuding 33 KV rating.
CORRECTIVE ACTION PROPOSED- Item wise.
If 'No' is marked, please specify reasons and thereafter corrective action proposed.
(Add additional sheets, if necessary)
CL : 13CL : 13
SERVICES & UTILITY
C.R. Narayana Rao
Architects & Engineers
Rev. 0 dtd. 13.01.2006
18 of 18
QUALITY CHECKLIST FOR SITE WORKS
FABRICATION WORK
Name of the Customer: Date:
Project Name: Project ID:
Name of the Contractor: Location:
Drawing Ref. No.: Quantity:
Sl. No. Description YES NO NA
BEFORE FABRICATION:
Check for the following PRECEDING ACTIVITIES:
1
2 Approval obtained for the fabrication drawing
3 Check for the approved welding rods used
4
AFTER FABRICATION:
1 Material section used as per drawing.
2 Whether welding length as per drawing.
3
4 Fabricated material is ready for sand blasting
Comments:
Contractor's Rep.: Client Rep.: Lemcon Rep.:
Check for the quality of materials / Test certificates of
materials submitted.
Check for fabrication material free from mud stains/ other
materials.
Whether all the interconnection section welded/ holes drilled
to assemble other members.
CORRECTIVE ACTION PROPOSED- Item wise.
If 'No' is marked, please specify reasons and thereafter corrective action proposed.
(Add additional sheets, if necessary)
CL : 14CL : 14
ARCHITECTURAL STRUCTURAL INTERIOR SERVICES & UTILITY

Más contenido relacionado

La actualidad más candente

Building maintenance
Building maintenance Building maintenance
Building maintenance Janki Patel
 
Quality Management In Construction
Quality Management In ConstructionQuality Management In Construction
Quality Management In ConstructionIsidro Sid Calayag
 
Estimation and costing of a commercial building
Estimation and costing of a commercial buildingEstimation and costing of a commercial building
Estimation and costing of a commercial buildinglckr117
 
Resume - Zubair Khan - Civil QC Inspector
Resume - Zubair Khan - Civil QC InspectorResume - Zubair Khan - Civil QC Inspector
Resume - Zubair Khan - Civil QC InspectorM.ZUBAIR KHAN
 
Formats for struct audit report
Formats for struct audit reportFormats for struct audit report
Formats for struct audit reportstructaudit
 
Insepction and quality control
Insepction and quality controlInsepction and quality control
Insepction and quality controlSOURAV4798
 
Specification writting civil construction
Specification writting civil constructionSpecification writting civil construction
Specification writting civil constructiondiasawada12345
 
Stages in Construction
Stages in Construction Stages in Construction
Stages in Construction Mereia Kali
 
Unit-4_Specification
Unit-4_SpecificationUnit-4_Specification
Unit-4_SpecificationAkash Bharti
 
Ms for-mechanical-piping-system-installation-work
Ms for-mechanical-piping-system-installation-workMs for-mechanical-piping-system-installation-work
Ms for-mechanical-piping-system-installation-workthanhuce
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management Rajat Nainwal
 
Quantity surveying drawing FNBE 2014
Quantity surveying drawing FNBE 2014Quantity surveying drawing FNBE 2014
Quantity surveying drawing FNBE 2014Felix Vong
 
Rebar arrangement and construction carryout
Rebar arrangement and construction carryoutRebar arrangement and construction carryout
Rebar arrangement and construction carryoutChhay Teng
 
Fabrication and Quality Control of structural steel
Fabrication and Quality Control of structural steelFabrication and Quality Control of structural steel
Fabrication and Quality Control of structural steelAhmed Allam
 
Classification of building based on occupancy and type of construction
Classification of building based on occupancy and type of constructionClassification of building based on occupancy and type of construction
Classification of building based on occupancy and type of constructionritubharti6
 
MEASUREMENT PDF
MEASUREMENT PDFMEASUREMENT PDF
MEASUREMENT PDFIDHAMUKI
 
Ashghal guide-qatar-sewerage-amp-drainage-design-manual
Ashghal guide-qatar-sewerage-amp-drainage-design-manualAshghal guide-qatar-sewerage-amp-drainage-design-manual
Ashghal guide-qatar-sewerage-amp-drainage-design-manualsyedfaisalali_50
 

La actualidad más candente (20)

Building maintenance
Building maintenance Building maintenance
Building maintenance
 
Quality Management In Construction
Quality Management In ConstructionQuality Management In Construction
Quality Management In Construction
 
Estimation and costing of a commercial building
Estimation and costing of a commercial buildingEstimation and costing of a commercial building
Estimation and costing of a commercial building
 
Resume - Zubair Khan - Civil QC Inspector
Resume - Zubair Khan - Civil QC InspectorResume - Zubair Khan - Civil QC Inspector
Resume - Zubair Khan - Civil QC Inspector
 
Formats for struct audit report
Formats for struct audit reportFormats for struct audit report
Formats for struct audit report
 
Qaqc in civil construction
Qaqc in civil constructionQaqc in civil construction
Qaqc in civil construction
 
Insepction and quality control
Insepction and quality controlInsepction and quality control
Insepction and quality control
 
Specification writting civil construction
Specification writting civil constructionSpecification writting civil construction
Specification writting civil construction
 
Stages in Construction
Stages in Construction Stages in Construction
Stages in Construction
 
Unit-4_Specification
Unit-4_SpecificationUnit-4_Specification
Unit-4_Specification
 
Ms for-mechanical-piping-system-installation-work
Ms for-mechanical-piping-system-installation-workMs for-mechanical-piping-system-installation-work
Ms for-mechanical-piping-system-installation-work
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management
 
Quantity surveying drawing FNBE 2014
Quantity surveying drawing FNBE 2014Quantity surveying drawing FNBE 2014
Quantity surveying drawing FNBE 2014
 
Rebar arrangement and construction carryout
Rebar arrangement and construction carryoutRebar arrangement and construction carryout
Rebar arrangement and construction carryout
 
Fabrication and Quality Control of structural steel
Fabrication and Quality Control of structural steelFabrication and Quality Control of structural steel
Fabrication and Quality Control of structural steel
 
Boq sample
Boq sampleBoq sample
Boq sample
 
Classification of building based on occupancy and type of construction
Classification of building based on occupancy and type of constructionClassification of building based on occupancy and type of construction
Classification of building based on occupancy and type of construction
 
MEASUREMENT PDF
MEASUREMENT PDFMEASUREMENT PDF
MEASUREMENT PDF
 
Ashghal guide-qatar-sewerage-amp-drainage-design-manual
Ashghal guide-qatar-sewerage-amp-drainage-design-manualAshghal guide-qatar-sewerage-amp-drainage-design-manual
Ashghal guide-qatar-sewerage-amp-drainage-design-manual
 
Module 3 - Construction quality and safety by Dr.Vinay Kumar B M
Module 3 - Construction quality and safety by Dr.Vinay Kumar B M Module 3 - Construction quality and safety by Dr.Vinay Kumar B M
Module 3 - Construction quality and safety by Dr.Vinay Kumar B M
 

Similar a 50727481 checklist-for-site-works

883-4-S10-P10S-CN12-RCC-SH-TYP-MF-04-1010_01
883-4-S10-P10S-CN12-RCC-SH-TYP-MF-04-1010_01883-4-S10-P10S-CN12-RCC-SH-TYP-MF-04-1010_01
883-4-S10-P10S-CN12-RCC-SH-TYP-MF-04-1010_01Sherif Azab
 
Cswip welding inspection notes and questions
Cswip welding inspection notes and questionsCswip welding inspection notes and questions
Cswip welding inspection notes and questionsKarthik Banari
 
Twi cswip welding inspection notes and questions
Twi cswip welding inspection notes and questionsTwi cswip welding inspection notes and questions
Twi cswip welding inspection notes and questionsThang Do Minh
 
01 architectural cycle 2 interactive
01 architectural   cycle 2 interactive01 architectural   cycle 2 interactive
01 architectural cycle 2 interactivesergencad sergencad
 
E9._Non-Conformity_Report_NCR.doc
E9._Non-Conformity_Report_NCR.docE9._Non-Conformity_Report_NCR.doc
E9._Non-Conformity_Report_NCR.docPeterIyere2
 
Cswip welding-inspection-notes-and-questions-1
Cswip welding-inspection-notes-and-questions-1Cswip welding-inspection-notes-and-questions-1
Cswip welding-inspection-notes-and-questions-1dhiaa ebadi
 
Multidispline Inspector - DEEPAK RAI
Multidispline Inspector - DEEPAK RAIMultidispline Inspector - DEEPAK RAI
Multidispline Inspector - DEEPAK RAIDeepak Rai
 
BALAJI RESUME. UPDATED
BALAJI RESUME. UPDATEDBALAJI RESUME. UPDATED
BALAJI RESUME. UPDATEDP. Balaji
 
Retail and Office building
Retail and Office buildingRetail and Office building
Retail and Office buildingJyoti Prashar
 
PROYECTO EN ILUSTRATOR
PROYECTO EN ILUSTRATORPROYECTO EN ILUSTRATOR
PROYECTO EN ILUSTRATORpanderistas17
 
At of modern building which create abvolated view
At of modern building which create abvolated viewAt of modern building which create abvolated view
At of modern building which create abvolated viewdreem073
 
Elements Of A Masonry Forensic Investigation Ryan Biggs
Elements Of A Masonry Forensic Investigation Ryan BiggsElements Of A Masonry Forensic Investigation Ryan Biggs
Elements Of A Masonry Forensic Investigation Ryan BiggsMartin Demarest
 
estimating and costing specification ppt -.pptx
estimating and costing  specification ppt -.pptxestimating and costing  specification ppt -.pptx
estimating and costing specification ppt -.pptxAshishJadhav655553
 
ASSET 11 STORM NETWORK DEC '14 ASSETS ON
ASSET 11 STORM NETWORK DEC '14 ASSETS ONASSET 11 STORM NETWORK DEC '14 ASSETS ON
ASSET 11 STORM NETWORK DEC '14 ASSETS ONNoel Carroll
 

Similar a 50727481 checklist-for-site-works (20)

111.pdf
111.pdf111.pdf
111.pdf
 
Ir extraco
Ir extracoIr extraco
Ir extraco
 
883-4-S10-P10S-CN12-RCC-SH-TYP-MF-04-1010_01
883-4-S10-P10S-CN12-RCC-SH-TYP-MF-04-1010_01883-4-S10-P10S-CN12-RCC-SH-TYP-MF-04-1010_01
883-4-S10-P10S-CN12-RCC-SH-TYP-MF-04-1010_01
 
MANAGER.QAQC(MECHANICAL)
MANAGER.QAQC(MECHANICAL)MANAGER.QAQC(MECHANICAL)
MANAGER.QAQC(MECHANICAL)
 
MANAGER.QAQC(MECHANICAL)-1
MANAGER.QAQC(MECHANICAL)-1MANAGER.QAQC(MECHANICAL)-1
MANAGER.QAQC(MECHANICAL)-1
 
Cswip welding inspection notes and questions
Cswip welding inspection notes and questionsCswip welding inspection notes and questions
Cswip welding inspection notes and questions
 
Twi cswip welding inspection notes and questions
Twi cswip welding inspection notes and questionsTwi cswip welding inspection notes and questions
Twi cswip welding inspection notes and questions
 
01 architectural cycle 2 interactive
01 architectural   cycle 2 interactive01 architectural   cycle 2 interactive
01 architectural cycle 2 interactive
 
E9._Non-Conformity_Report_NCR.doc
E9._Non-Conformity_Report_NCR.docE9._Non-Conformity_Report_NCR.doc
E9._Non-Conformity_Report_NCR.doc
 
Cswip welding-inspection-notes-and-questions-1
Cswip welding-inspection-notes-and-questions-1Cswip welding-inspection-notes-and-questions-1
Cswip welding-inspection-notes-and-questions-1
 
Multidispline Inspector - DEEPAK RAI
Multidispline Inspector - DEEPAK RAIMultidispline Inspector - DEEPAK RAI
Multidispline Inspector - DEEPAK RAI
 
BALAJI RESUME. UPDATED
BALAJI RESUME. UPDATEDBALAJI RESUME. UPDATED
BALAJI RESUME. UPDATED
 
Retail and Office building
Retail and Office buildingRetail and Office building
Retail and Office building
 
Kumar KV
Kumar KVKumar KV
Kumar KV
 
PROYECTO EN ILUSTRATOR
PROYECTO EN ILUSTRATORPROYECTO EN ILUSTRATOR
PROYECTO EN ILUSTRATOR
 
At of modern building which create abvolated view
At of modern building which create abvolated viewAt of modern building which create abvolated view
At of modern building which create abvolated view
 
Elements Of A Masonry Forensic Investigation Ryan Biggs
Elements Of A Masonry Forensic Investigation Ryan BiggsElements Of A Masonry Forensic Investigation Ryan Biggs
Elements Of A Masonry Forensic Investigation Ryan Biggs
 
BGAS_RESUME_2-2
BGAS_RESUME_2-2BGAS_RESUME_2-2
BGAS_RESUME_2-2
 
estimating and costing specification ppt -.pptx
estimating and costing  specification ppt -.pptxestimating and costing  specification ppt -.pptx
estimating and costing specification ppt -.pptx
 
ASSET 11 STORM NETWORK DEC '14 ASSETS ON
ASSET 11 STORM NETWORK DEC '14 ASSETS ONASSET 11 STORM NETWORK DEC '14 ASSETS ON
ASSET 11 STORM NETWORK DEC '14 ASSETS ON
 

Más de imaduddin91

07 a80102 groundwaterdevelopmentandmanagement
07 a80102 groundwaterdevelopmentandmanagement07 a80102 groundwaterdevelopmentandmanagement
07 a80102 groundwaterdevelopmentandmanagementimaduddin91
 
Remotesensingandgisapplications
RemotesensingandgisapplicationsRemotesensingandgisapplications
Remotesensingandgisapplicationsimaduddin91
 
R05410107 advancedfoundationengineering
R05410107 advancedfoundationengineeringR05410107 advancedfoundationengineering
R05410107 advancedfoundationengineeringimaduddin91
 
07 a80101 advanced structural design
07 a80101 advanced structural design07 a80101 advanced structural design
07 a80101 advanced structural designimaduddin91
 
07 a70401 remotesensingandgisapplications
07 a70401 remotesensingandgisapplications07 a70401 remotesensingandgisapplications
07 a70401 remotesensingandgisapplicationsimaduddin91
 
07 a70102 finite element methods in civil engineering
07 a70102 finite element methods in civil engineering07 a70102 finite element methods in civil engineering
07 a70102 finite element methods in civil engineeringimaduddin91
 
R05410103 remotesensingandgisapplications
R05410103 remotesensingandgisapplicationsR05410103 remotesensingandgisapplications
R05410103 remotesensingandgisapplicationsimaduddin91
 
R05410102 finiteelementmethodsincivilengineering
R05410102 finiteelementmethodsincivilengineeringR05410102 finiteelementmethodsincivilengineering
R05410102 finiteelementmethodsincivilengineeringimaduddin91
 
07 a60105 estimatingandcosting
07 a60105 estimatingandcosting07 a60105 estimatingandcosting
07 a60105 estimatingandcostingimaduddin91
 
07 a82101 advanced structural design
07 a82101  advanced structural design07 a82101  advanced structural design
07 a82101 advanced structural designimaduddin91
 
07 a80106 pavementanalysisanddesign
07 a80106 pavementanalysisanddesign07 a80106 pavementanalysisanddesign
07 a80106 pavementanalysisanddesignimaduddin91
 
07 a80104 watershedmanagement
07 a80104 watershedmanagement07 a80104 watershedmanagement
07 a80104 watershedmanagementimaduddin91
 
07 a80102 groundwaterdevelopmentandmanagement
07 a80102 groundwaterdevelopmentandmanagement07 a80102 groundwaterdevelopmentandmanagement
07 a80102 groundwaterdevelopmentandmanagementimaduddin91
 
07 a70110 remotesensingandgisapplications
07 a70110 remotesensingandgisapplications07 a70110 remotesensingandgisapplications
07 a70110 remotesensingandgisapplicationsimaduddin91
 
07 a70107 waterresourcessystemplanningandmanagement
07 a70107 waterresourcessystemplanningandmanagement07 a70107 waterresourcessystemplanningandmanagement
07 a70107 waterresourcessystemplanningandmanagementimaduddin91
 
07 a70102 finite element methods in civil engineering
07 a70102  finite element methods in civil engineering07 a70102  finite element methods in civil engineering
07 a70102 finite element methods in civil engineeringimaduddin91
 
07 a60105 estimatingandcosting
07 a60105 estimatingandcosting07 a60105 estimatingandcosting
07 a60105 estimatingandcostingimaduddin91
 
Statistical metods
Statistical metodsStatistical metods
Statistical metodsimaduddin91
 
Sas language reference concepts
Sas language reference  conceptsSas language reference  concepts
Sas language reference conceptsimaduddin91
 

Más de imaduddin91 (20)

07 a80102 groundwaterdevelopmentandmanagement
07 a80102 groundwaterdevelopmentandmanagement07 a80102 groundwaterdevelopmentandmanagement
07 a80102 groundwaterdevelopmentandmanagement
 
Remotesensingandgisapplications
RemotesensingandgisapplicationsRemotesensingandgisapplications
Remotesensingandgisapplications
 
R05410107 advancedfoundationengineering
R05410107 advancedfoundationengineeringR05410107 advancedfoundationengineering
R05410107 advancedfoundationengineering
 
07 a80101 advanced structural design
07 a80101 advanced structural design07 a80101 advanced structural design
07 a80101 advanced structural design
 
07 a70401 remotesensingandgisapplications
07 a70401 remotesensingandgisapplications07 a70401 remotesensingandgisapplications
07 a70401 remotesensingandgisapplications
 
07 a70102 finite element methods in civil engineering
07 a70102 finite element methods in civil engineering07 a70102 finite element methods in civil engineering
07 a70102 finite element methods in civil engineering
 
R05410103 remotesensingandgisapplications
R05410103 remotesensingandgisapplicationsR05410103 remotesensingandgisapplications
R05410103 remotesensingandgisapplications
 
R05410102 finiteelementmethodsincivilengineering
R05410102 finiteelementmethodsincivilengineeringR05410102 finiteelementmethodsincivilengineering
R05410102 finiteelementmethodsincivilengineering
 
07 a60105 estimatingandcosting
07 a60105 estimatingandcosting07 a60105 estimatingandcosting
07 a60105 estimatingandcosting
 
07 a82101 advanced structural design
07 a82101  advanced structural design07 a82101  advanced structural design
07 a82101 advanced structural design
 
07 a80106 pavementanalysisanddesign
07 a80106 pavementanalysisanddesign07 a80106 pavementanalysisanddesign
07 a80106 pavementanalysisanddesign
 
07 a80104 watershedmanagement
07 a80104 watershedmanagement07 a80104 watershedmanagement
07 a80104 watershedmanagement
 
07 a80102 groundwaterdevelopmentandmanagement
07 a80102 groundwaterdevelopmentandmanagement07 a80102 groundwaterdevelopmentandmanagement
07 a80102 groundwaterdevelopmentandmanagement
 
07 a70110 remotesensingandgisapplications
07 a70110 remotesensingandgisapplications07 a70110 remotesensingandgisapplications
07 a70110 remotesensingandgisapplications
 
07 a70107 waterresourcessystemplanningandmanagement
07 a70107 waterresourcessystemplanningandmanagement07 a70107 waterresourcessystemplanningandmanagement
07 a70107 waterresourcessystemplanningandmanagement
 
07 a70102 finite element methods in civil engineering
07 a70102  finite element methods in civil engineering07 a70102  finite element methods in civil engineering
07 a70102 finite element methods in civil engineering
 
07 a60105 estimatingandcosting
07 a60105 estimatingandcosting07 a60105 estimatingandcosting
07 a60105 estimatingandcosting
 
Statistical metods
Statistical metodsStatistical metods
Statistical metods
 
Sas cheat
Sas cheatSas cheat
Sas cheat
 
Sas language reference concepts
Sas language reference  conceptsSas language reference  concepts
Sas language reference concepts
 

50727481 checklist-for-site-works

  • 1. QUALITY CHECKLIST FOR SITE WORKS SURVEYING AND SETTING OUT Name of the Customer: Date: Project Name: Project ID: Name of the Contractor: Location: Drawing Ref. No.: Quantity: Sl.No. Description YES NO NA 1 Is contour/ survey plan available? 2 3 4 5 Comments: Contractor's Rep.: Client Rep.: Lemcon Rep.: Establishment of Co-ordination points, MAIN GRID LINES, CENTRE LINES in both directions, block levels, spot level etc. Is it as per Drawings? Check for set back are they as per the norms of local authority approval drawing? Check whether there is any variation in the actual marking and whether it is recorded/ reported? LOCATION of INDIVIDUAL STRUCTURAL ELEMENTS like Column footings, columns, location of pile, etc., Are they as per Drawings? CORRECTIVE ACTION PROPOSED- Item wise. If 'No' is marked, please specify reasons and thereafter corrective action proposed. (Add additional sheets, if necessary) ARCHITECTURAL STRUCTURL INTERIOR SERVICES & UTILITY CL : 01CL : 01
  • 2. QUALITY CHECKLIST FOR SITE WORKS EARTH WORK/ BACKFILLING Name of the Customer: Date: Project Name: Project ID: Name of the Contractor: Location: Drawing Ref. No.: Quantity: Sl.No. Description YES NO NA 1 Is format CL: 01 for Surveying complied with? 2 3 4 Is adequate shoring, strutting done? 5 Check for DEWATERING. Is it O.K.? 6 Is the excavation done up-to the level as per drawing. A. NATURAL EXISTING GROUND LEVEL : B. FOUNDING LEVEL : C. DEPTH OF EXCAVATION : BACKFILLING 1 Is the earth used for filling as per specification? 2 3 Contractor's Rep.: Client Rep.: Lemcon Rep.: Whether suitable arrangements for re-routing the service lines done? Is the LAYOUT, ALIGNMENT and SIZE of Excavation marked on the ground as per drawings? Check for the approved method of compaction, ie. (Roller, plate compactor, etc.,) Whether Proctor compaction test carried out satisfactorily as per the requirement? CORRECTIVE ACTION PROPOSED- Item wise. If 'No' is marked, please specify reasons and thereafter corrective action proposed. ARCHITECTURAL STRUCTURAL SITE DEVELOPMENT SERVICES & UTILITY CL : 02CL : 02 $ $
  • 3. QUALITY CHECKLIST FOR SITE WORKS CONCRETE POUR CARD Name of the Customer: Date: Project Name: Project ID: Name of the Contractor: Location: Drawing Ref. No.: Grade & Quantity : Sl.No. Description YES NO NA A. FORM WORK: 1 Level 2 Plumb 3 Cutouts B. Reinforcement: 1 As per bar bending schedule 2 Dowel bars 3 Links 4 Binding/ Welding C. Services: 1 Position 2 Size 3 Trimming bars D. General 1 Embedments 2 Water proofing 3 Construction Joint E. Sampling: 1 Mix as per design : 2 No. of sample & Identity Comments: Contractor's Rep.: Client Rep.: Lemcon Rep.: IF 'YES', THEN SITE ENGINEER SHALL TAKE SUITABLE CORRECTIVE ACTION in consultation with PRT/ AST/ PRM AND RECHECK . CORRECTIVE ACTION PROPOSED- Item wise. If 'No' is marked, please specify reasons and thereafter corrective action proposed. (Add additional sheets, if necessary) ARCHITECTURAL STRUCTURAL INTERIOR SERVICES & UTILITY CL : 03CL : 03
  • 4. QUALITY CHECKLIST FOR SITE WORKS WATER PROOFING Name of the Customer: Date: Project Name: Project ID: Name of the Contractor: Location: Drawing Ref. No.: Quantity: Sl.No. Description YES NO NA 1 2 Check for surface preparation. Is it o.k.? 3 Check for Plastering before coating. Is it o.k.? 4 Check for coating of chemical. Is it o.k.? 5 Check for Plastering after coating. Is it o.k.? 6 Check for fixing of nozzles and spacing. Is it o.k.? 7 Check for grouting. Is it o.k.? 8 Check for brickbatcoba thickness & slopes. 9 Check for curing. Is it o.k.? Comments: Contractor's Rep.: Client Rep.: Lemcon Rep.: Whether approved / specified materials used as per specification? CORRECTIVE ACTION PROPOSED- Item wise. If 'No' is marked, please specify reasons and thereafter corrective action proposed. (Add additional sheets, if necessary) ARCHITECTURAL STRUCTURAL INTERIOR SERVICES & UTILITY 1. Raft slab 2. Retaining wall 3. Toilet sunken 4. Terrace CL : 04CL : 04
  • 5. QUALITY CHECKLIST FOR SITE WORKS EXTERNAL & PARTITION WALL/ RR MASONRY Name of the Customer: Date: Project Name: Project ID: Name of the Contractor: Location: Drawing Ref. No.: Quantity: Sl.No. Description YES NO NA Thickness 1 2 Check for placing reinforcement RC bands as per specification. 3 4 INTERIOR - (PARTITION / WALL PANELLING FRAME WORK) 1 Type of Partitions/ Frame etc., Frame work materials used. a) Aluminum frames b) Timber frames c) G.I /M.S frames 2 3 Height of Partition. b) Half height 4 5 6 Comments: Contractor's Rep.: Client Rep.: Lemcon Rep.: Check for ALIGNMENT & LOCATION of wall. Is it as per drawing? Check for MORTAR MIX PROPORTION is ok? Check for SIZES OF OPENINGS for Doors & Windows? / Any other sevices. AC duct, Cable tray, chilled water pipe, etc. If it is wooden partition, check for Anti-termite/ wood borer preventing treatment provided? Whether the frame work sufficiently anchored in the floor & true ceiling? Check provisions made in the frame work for fixing conduits for electrical, Data lines etc., as per drawings. Check for approved make of finishing materials as per specification. CORRECTIVE ACTION PROPOSED- Item wise. If 'No' is marked, please specify reasons and thereafter corrective action proposed. (Add additional sheets, if necessary) : ARCHITECTURAL STRUCTURAL INTERIOR SERVICES & UTILITY 9. Glazed Hollow 1. Brick 2. Solid Block 4. R . R 5. C. R 10. Others6. Aerocon Block 7. Gypsum 3. Hollow Block 8. Wooden CL : 05CL : 05
  • 6. QUALITY CHECKLIST FOR SITE WORKS PLASTERING/ PAINTING Name of the Customer: Date: Project Name: Project ID: Name of the Contractor: Location: Drawing Ref. No.: Quantity: Sl.No. Description YES NO NA 1 2 3 4 PAINTING 1 DURING & AFTER PAINTING 1 2 Check for Number of Coats. Comments: Contractor's Rep.: Client Rep.: Lemcon Rep.: Check for COMPLETION OF PRECEDING ACTIVITIES like fixing of service Conduits, Water Supply & sanitation lines, etc. Whether chicken mesh, Corner beads used as per specifications? Check for MORTAR MIX PROPORTION & Check for Surface of mortar mixing and addition of water profing compond if required. Check for THICKNESS & NUMBER OF COATS of Plaster and required finish for further activities. PRIOR TO PAINTING Check whether approved make & shade are used? Check for APPLICATION of paint. Is it uniform? CORRECTIVE ACTION PROPOSED- Item wise. If 'No' is marked, please specify reasons and thereafter corrective action proposed. (Add additional sheets, if necessary) ARCHITECTURAL STRUCTURAL INTERIOR SERVICES & UTILITY CL : 06CL : 06
  • 7. QUALITY CHECKLIST FOR SITE WORKS JOINERIES - (FIXING DOORS/ WINDOWS/ VENTILATOR) Name of the Customer: Date: Project Name: Project ID: Name of the Contractor: Location: Drawing Ref. No.: Quantity: Sl.No. Description YES NO NA 1 Whether specified material and approved sample are used? 2 3 4 Check for fixing and grouting of frames with hold fasts. Is it o.k.? 5 Check whether architrave is specified for door frames? 6 7 Locks/ Latches 8 Handle 9 Weather stripping / Stoppers Comments: Contractor's Rep.: Client Rep.: Lemcon Rep.: Check for the correct size of frames/ shutters as per drawing. Is it o.k? Check for the proper primer painting, powder coating, Anodizing coating and other finishes to frames before fixing. Is it o.k.? Check vision panel, door closers, floor spring, Access card , whether provision made. CORRECTIVE ACTION PROPOSED- Item wise. If 'No' is marked, please specify reasons and thereafter corrective action proposed. (Add additional sheets, if necessary) ARCHITECTURAL STRUCTURAL INTERIOR SERVICES & UTILITY CL : 07CL : 07
  • 8. QUALITY CHECKLIST FOR SITE WORKS FLOORING/ DADOING Name of the Customer: Project Name: Name of the Contractor: Drawing Ref. No.: Sl.No. Description I Prior to Tiling: 1 2 3 4 5 6 7 LAYING PAVER BLOCKS 1 All pipe line/ Conduiting/ Sleeve work completed. 2 Check formation level ie. Bottom of sand bedding 3 Check thickness, shape, colour, pattern of paver blocks. Comments: Contractor's Rep.: Client Rep.: Lemcon Rep.: Check for COMPLETION OF PRECEDING ACTIVITIES like fixing of Door, Frames, Partitions, etc. A. Check for Provision of Service Conduits, junction Boxes, plumbing, etc. Is the SAMPLE OF TILES approved?. Check for MORTAR MIX/ ADHESIVE PROPORTION. Is it as specified? Check for THICKNESS OF MORTAR BED. Is it o.k? Check for PATTERN OF LAYING. Is it ok? Check for TOP LEVEL. Is it o.k? CORRECTIVE ACTION PROPOSED- Item wise. If 'No' is marked, please specify reasons and thereafter corrective action proposed. (Add additional sheets, if necessary) ARCHITECTURAL INTERIOR 1. Ceramic tile 2. Vitrified tile 3. Marble 5. Cement based tile 6. Mosaic DADOINGFLOORING SKIRTING 7. Paver block CL : 08CL : 08
  • 9. FOR SITE WORKS ADOING Date: Project ID: Location: Quantity: YES NO NA Lemcon Rep.: orrective action proposed. 4. Granite 8. Others EXTERNAL CLADDING 7. Paver block
  • 10. QUALITY CHECKLIST FOR SITE WORKS INTERIOR (FALSECEILING) Name of the Customer: Date: Project Name: Project ID: Name of the Contractor: Location: Drawing Ref. No.: Quantity: Description YES NO NA 1 Check the type of falseceiling as per specification. 2 3 4 5 6 Comments: Contractor's Rep.: Client Rep.: Lemcon Rep.: Sl.N o. If it is Grid type, Check whether grids are marked as per drawing so as to locate the service points. Check whether the frame work and hanger rods are as per specification. Before fixing/ laying of boards check all service works such as electrical, AC ducting, fire alarm, sprinkler, speakers, smoke detector, heat detector, etc, Whether cutout/ opening provided. Check for any cornices, trap door provision as per the drawing. Check for painting of ceiling ( If it is board) - is it as per specification. CORRECTIVE ACTION PROPOSED- Item wise. If 'No' is marked, please specify reasons and thereafter corrective action proposed. (Add additional sheets, if necessary) ARCHITECTURAL STRUCTURAL INTERIOR SERVICES & UTILITY CL : 09CL : 09
  • 11. QUALITY CHECKLIST FOR SITE WORKS ROAD & DRAINS WORKS Name of the Customer: Date: Project Name: Project ID: Name of the Contractor: Location: Drawing Ref. No.: Quantity: Sl.No. Description YES NO NA PREPARATION OF SUBGRADE 1 SAND - GRAVEL MIX FOR ROAD WORK. 1 Check the formation of subgrade with specified camber. 2 3 W.B.M: 1 Check for proper grading of aggregates. 2 3 4 5 6 ASPHALT/ BT FOR ROAD WORKS 2 Check Whether tack coat application is done properly. 3 Check for Uniform spread thickness of premix. Is it o.k.? 4 Drain work: 1 Marking layout line level of R.C.C drain. 2 Making R.C.C. drain all as per drawing in line, level & slope. Comments: PREPARATION OF SUBGRADE to specified lines and Camber. Check for Cleaning and Making up of Soft spots & other irregularities. Check for spreading in layers as specified and watering has been done on prior to the required proctor density to the required compaction. Check for finished surfaces, compacted thickness, camber, gradient lines and slope. Are they acceptable? Check for Underground trenches / Hume pipes / Drain crossing / road crossing LAYOUTS, GRADES & CROSS - SECTIONS OF COMPACTED SUBGRADE prior to spreading of aggregates. Check for UNIFORM SPREAD THICKNESS of Aggregates. Check for DRY ROLLING, using proper road roller. Check for WET ROLLING of Aggregates and COMPACTION. Check for FINISHED SURFACES, COMPACTED THICKNESS, CAMBER, LINES AND SLOPE.Are they acceptable? Check for finished surfaces,compacted thickness. gradient lines and slope: Are they acceptable. CORRECTIVE ACTION PROPOSED- Item wise. If 'No' is marked, please specify reasons and thereafter corrective action proposed. (Add additional sheets, if necessary) SERVICES & UTILITY CL : 10CL : 10
  • 12. Sl.No. Description YES NO NA CL : 10CL : 10 Contractor's Rep.: Client Rep.: Lemcon Rep.:
  • 13. QUALITY CHECKLIST FOR SITE WORKS Name of the Customer: Date: Project Name: Project ID: Name of the Contractor: Location: Drawing Ref. No.: Quantity: Sl.No. Description YES NO NA 1 Check the setting out is line with drawing/ layout 2 3 Check the type of finish : a) Laminate b) Veneer with melamine polish c) ACP 4 INTERIOR (STORAGE UNIT) 1 b) 1200 mm height c) 2100/ 2400 mm height 2 3 4 Check is it modular/ Custorm built. 1 2 3 4 Check type of skirting. 5 Check location of switch boxes, is it ok? INTERIOR (FURNISHING WORKS) 1 2 Check whether chair is of specified make colour and shade. INTERIOR - (FURNITURES/ STORAGE UNIT/ PARTITION/ PANELLING/ FURNISHING WORKS) Check the provisions are made for such as pencil drawer, Key board drawer, storage units attached with the table. Check the Approved make and thickness of materials as per specifications and drawings. Type of storage unit: a) 750 mm Low height Check the Hardware such as lock, hinges, handles are provided with as per specifications / drawings. Check the plywood thickness, finishing of material whether with Laminate or Veneer. Check type of internal frame work (work/ Aluminium box sections) Check type of partition (Fully solid/ Fully glazed/ combination of glass and opaque) Check before fixing of plywood electrical civil access, other services consul Check whether the carpet is of specified make colour and shade. ARCHITECTURAL STRUCTURAL INTERIOR SERVICES & UTILITY CL : 11CL : 11
  • 14. Sl.No. Description YES NO NA CL : 11CL : 11 3 4 Check about etching designs in glass partition. Comments: Contractor's Rep.: Client Rep.: Lemcon Rep.: Check the Fabric Pinup board.Is the fabric, colour, size of board as per drawing / Specification. CORRECTIVE ACTION PROPOSED- Item wise. If 'No' is marked, please specify reasons and thereafter corrective action proposed. (Add additional sheets, if necessary)
  • 15. QUALITY CHECKLIST FOR SITE WORKS PLUMBING & SANITARY/ SANITARY FIXTURES Name of the Customer: Project Name: Name of the Contractor: Drawing Ref. No.: Sl.No. Description Water supply: 1 2 3 4 5 Sewer Line: 1 2 3 4 5 Whether leak tests conducted? SANITARY FIXTURES & FITTINGS 1 Comments: Contractor's Rep.: Client Rep.: Lemcon Rep.: Check whether all pipe joints and method of jointing are done as per specification and conforming to relevant IS codes and standards. Whether the samples of pipes and fittings are as per approved specification? Whether the concealed pipe lines are painted and protected as per the specification? Whether connected pipe lines and fittings are satisfactorily tested for leaks before covering? Ceiling suspended lines adequately supported by suitable dia of rod/ anchor fastener with suitable spacing. Check the approved pipes are used for the sewer lines. Is it o.k.? Check for the levels and alignment of sewer line as per drawing / specifications. Is it o.k.? Check whether the jointing of pipes are as per specifications/ drawing. Is it o.k.? Check whether for the inspection chambers are at the correct location shape and to the correct invert level as per drawings/ specifications. Whether the fixtures are fixed in correct position and level as per the drawings/ specifications? ARCHITECTURAL STRUCTURAL INTERIOR CL : 12CL : 12
  • 16. FOR SITE WORKS ANITARY FIXTURES Date: Project ID: Location: Quantity: YES NO NA Lemcon Rep.: INTERIOR SERVICES & UTILITY
  • 17. C.R. Narayana Rao Architects & Engineers Rev.1 dtd. 13.01.2006 17 of 18 QUALITY CHECKLIST FOR SITE WORKS ELECTRICAL INSTALLATION WORKS Name of the Customer: Date: Project Name: Project ID: Name of the Contractor: Location: Drawing Ref. No.: Quantity: The following Indian Standard Codes are adopted for Installing the equipments at site Sl. No. Description YES NO NA I.S No. 1 CODE OF PRACTICES 2 732/1989 - Code of Practice for Electrical wiring installation. 3 4 5 6 7 Comments: Contractor's Rep.: Client Rep.: Lemcon Rep.: 8884/1976 - Code of Practice for the installation of electric bell and call system. 10028 Part 1 1985 - Code of Practice for selection installation and maintenance of transformers Part 2 Installation. 10118 Part 3 1982 - Code of Practice for selection, installation and maintenance of switchgear and control gear Part 3- Installation. 5613 Part 2 Selection 1 1985 - Code of Practice for design installation and maintenance of overhead power lines Part 2 lines upto and including 11KV section 1 Installation. 1255 (1983) - Code of Practice for Installation and Maintenance of Power Cables upto and inlcuding 33 KV rating. CORRECTIVE ACTION PROPOSED- Item wise. If 'No' is marked, please specify reasons and thereafter corrective action proposed. (Add additional sheets, if necessary) CL : 13CL : 13 SERVICES & UTILITY
  • 18. C.R. Narayana Rao Architects & Engineers Rev. 0 dtd. 13.01.2006 18 of 18 QUALITY CHECKLIST FOR SITE WORKS FABRICATION WORK Name of the Customer: Date: Project Name: Project ID: Name of the Contractor: Location: Drawing Ref. No.: Quantity: Sl. No. Description YES NO NA BEFORE FABRICATION: Check for the following PRECEDING ACTIVITIES: 1 2 Approval obtained for the fabrication drawing 3 Check for the approved welding rods used 4 AFTER FABRICATION: 1 Material section used as per drawing. 2 Whether welding length as per drawing. 3 4 Fabricated material is ready for sand blasting Comments: Contractor's Rep.: Client Rep.: Lemcon Rep.: Check for the quality of materials / Test certificates of materials submitted. Check for fabrication material free from mud stains/ other materials. Whether all the interconnection section welded/ holes drilled to assemble other members. CORRECTIVE ACTION PROPOSED- Item wise. If 'No' is marked, please specify reasons and thereafter corrective action proposed. (Add additional sheets, if necessary) CL : 14CL : 14 ARCHITECTURAL STRUCTURAL INTERIOR SERVICES & UTILITY