Research Inventy: International Journal Of Engineering And Science
Vol.3, Issue 6 (Aug 2013), PP 01-06
Issn(e): 2278-4721, Issn(p):2319-6483, Www.Researchinventy.Com
1
Cost and Time Performance of Construction Projects under The
Due Process Reform In Nigeria
¹ADE-OJO, Comfort Olubunmi, ²BABALOLA, Anthony Ayo.
¹Department of Quantity Surveying, The Federal Polytechnic, Ado-Ekiti. Nigeria.
²Department of Quantity Surveying, The Federal Polytechnic, Ado-Ekiti. Nigeria.
ABSTRACT: The Due process policy is a product of the Fderal government public procurement reform of
1999. The policy was meant to be an anticorruption device aimed at ensuring probity, transparency,
accountability in the procurement of public goods and services. The need for the reform is long overdue.
However, in order to assess the implementation of the Due process policy in procurement of construction
projects, the study took a survey study of construction projects awarded and executed in federal higher
educational institutions in the southwest Nigeria. The study revealed that although cost overrun on such
projects was at 19% due to the lump sum nature of the due process reform, time overrun was at the rate of
108%. Financial capability of the client followed by prompt payment were identified respectively for timely
completion while delayed payment has the highest contribution to time overrun at 36%. Financial incapability
of the contractor has significant contribution to delay in completion of the projects. The study observed that the
contracts were awarded on short contract duration, it concluded that the excessive time overrun on such
projects is not good for the construction industry in Nigeria as it does not only erode the contractor’s profit, it
also deprives the client from having his project as at when due. It therefore suggested that there is need to
ensure that realistic contract periods are quoted and that the federal government should endeavor to assess the
success of the reform so far in order to address the grey areas.
KEY WORDS: Due Process, cost overrun, time overrun, performance, prequalification.
I. INTRODUCTION
The Federal Government of Nigeria in 1999 adopted the use of competitive bidding as a means of
procuring public goods and services. The development came on the heels of the economic reform going on in
the country as it became imperative that to achieve sanity in the public sector procurement, there was need for a
procurement reform. The Budget Monitoring and Implementation Unit (BMPIU) was set up for the monitoring
and implementation of the procurement reform which is being referred to as the Due Process certification
(Ezenwa, 2004[1]; Wahab, 2006[2]). This is referred to as the Bureau for Public Procurement in the
Procurement Act of 2007.
The due process reform in the procurement of construction project in Nigeria is in response to the
unguarded and uncoordinated way in which public projects were awarded. Considering the fact that the
government is the largest consumer of the construction industry product, its procurement policies directly
impacts on the activity of the industry. This is so much the case of a developing economy like Nigeria. In order
to provide a sane and guarded means of procuring public project, the guidelines are stringently interwoven with
lots of bureaucratic intervention. To combat fraud and unreasonably high rates of procurement of public works
in Nigeria, the Federal Government introduced competitive bidding as a procurement method emphasized by the
Due Process reform.
The crux of the Due Process reform is to get the lowest responsive and responsible bidder, one who
takes into proper consideration the pros and cons of the project if the contract is won. However, researches have
shown that contractors are more concerned with “being the lowest bidder” rather than “the responsive and
responsible bidder”, assuming the “All Goes According to Plan” (AGPA) and not the “What Happens If ”
(WHIF) as proposed by Flanagan and Norman (1997[3]). In view of these, achieving reasonable performance of
construction projects in terms of time and cost cannot be guaranteed which is not good for the health of the
construction industry. Consequently, the research question therefore is; „what is the level of performance of
construction projects since the implementation of the Due Process reform for the award of public contract for
goods and services in Nigeria including those for construction works‟, what are the factors that influence the
performance of construction projects under the due process reform and what are those factors that mitigate
effective performance of such projects?.
Cost And Time Performance Of …
2
II. PUBLIC PROCUREMENT REFORM
Public procurement systems across the globe began to receive attention not too long ago. Before the
April 11, (9th
) International Anti-Corruption Conference held in Abidjan in 1998 which stimulated a new look
at procurement in many Countries of the world, procurement was seen as an insignificant part of an
administrative function. Wittig (1999[4]) believes that the reviews of public procurement systems in the
developed countries in recent times were geared towards improving its efficiency and generating savings in
government spending. The United States in 1994, procurement reform of South Africa in 1997 and in 1998, the
United Kingdom‟s call for efficiency in Civil Government led to its public sector reform. The series of
economic reforms embarked upon by the Obasanjo led administration starting form 1999 gave birth to the
public procurement act in Nigeria which was signed into law on the 4th
of June 2007 (Okereke –Onyeri,
2008[5]).
2.1 Procurement Reform In Nigeria
Before the reestablishment of the democratic rule in 1999, the public sector procurement system in
Nigeria had witnessed years of economic mismanagement and corruption under the successive military regimes
(USAID, 2001a[6]) such as the abandonment of the initial Structural Adjustment Reforms of 1986 by the year
1992 resulting into years of slow and stagnated growth, inflation and increased poverty in Nigeria (USAID,
2001b[7]). In 1999, the Obasanjo led Administration took discreet steps to check the excesses of the previous
administrations, combat corruption and build public confidence (USAID, 2001b). This was the beginning of the
Procurement Reform in Nigeria and the implementation of the Due Process certification in the procurement of
public goods and services is one of the cardinal strategies of the economic reform (Wahab, 2006[2]). The
Procurement Act of June, 2007 was enacted to provide a legal and operational frame work for proper
implementation of the Due Process reform. The Procurement Act as stated „shall apply to the procurement of
goods, works and services carried out by the Federal government of Nigeria and all its entities that derives at
least 35% of its fund from the Federal government‟ (Okereke-Onyeri, 2008[5]). The Bureau for Public
Procurement is expected to among other things ensure the application of fair, competitive, transparent and value
for money standards.
2.2 THE “DUE PROCESS” REFORM
Adedeji (2004[8]) noted that the public sector as the largest client of the construction industry in
Nigeria is badly reputed for poor financial probity. The “Due Process Reform” came as an anti-corruption
device to entrench the ideals of public procurement systems using the “Due process certification” in the award
of contracts for public projects in Nigeria. Collusion between parties to public contracts and acceptance of
gratuities from bidding contractors in the award of such contracts has greatly affected the decision-making and
executive processes of Nigeria resulting in Legal, Administrative and Economic costs to the Country (Wittig,
1999[4]; Abdullahi, 2004[9] and Esenwa, 2004[1]). The enactment of the due process policy by the Federal
government of Nigeria was in line with the World Trade Organization‟s (WTO) Government Procurement
Agreement (GPA). The GPA is supported by the World Bank based on the United Nations Committee on
International Trade Law (UNCITRAL) model for public procurement. The “Due Process” reform of the Federal
Republic of Nigeria is as contained in the “New Policy Guidelines for Procurement and Award of contracts in
Government ministries/parastatals- Ref no FI5775 of 27th
June 2001 and the Treasury Circular no ASA55/001
of 30th
October, 2001 on “Due Process Certification of contracts (Abdulahi,2004[9]). The BMPIU established
for proper implementation of the Due process certification of contracts transformed into the Bureau for Public
Procurement with the signing into law the 2007 Public Procurement Act.
Contractor‟s prequalification is one of the focal points of the procurement reform. The provision of the
Due Process certification states that public contracts be awarded within specific thresholds as follows; Contracts
below N1m, Contracts above N1m but below N50m and Contracts of N50m and above (BMPIU, 2005[10]).
Abdullahi (2004 [9]) observed that contracts above N10m shall be given notice for 6 weeks while contracts
above this threshold will require two- stage certification: Pre-qualification with a minimum of 2 weeks and
bidding period of 6 weeks. The lowest price/best evaluated bid shall be awarded the contract.
2.3 PREQUALIFICATION
Waara and Brochner (2006[11]) identified prequalification as the only possible way of protecting the
capable and established firms with the client getting a more economical job. It ensures that invitation to bid is
only given to the firms who have adequate capabilities and resources to execute the project (Gale, 2006[12]).
The effective implementation of competitive bidding is dependent on Contractor‟s prequalification as this, if
adequately implemented, serves to prevent fronting and window dressing by incompetent and corrupt
Cost And Time Performance Of …
3
contractors. The different government circulars on the implementation of the Due Process Certification
as summarized by Esenwa (2004[1]) pointed out that the call for pre-qualification is one of the major criteria for
the certification of any public projects awarded. Going by the Inter-America Development Banks report
(1997[13]); prequalification depends on the “ability of the potential contractors to carry out the works in
satisfactory manner”. The criteria for pre-qualification stated in the report include Past experience and results in
similar projects, Contractor‟s personnel and equipment available, Financial capability of the contractor, Other
contracts presently being undertaken, Any litigation or Arbitration from previous contracts in the last five years.
The 2007 Procurement Act also stipulates professional and technical qualifications, financial capability,
equipment and adequate personnel to execute the contract (Ibrahim, 2008[14]).
III. RESEARCH METHODOLOGY:
The research consists of a survey of Due process projects carried out in Federal higher educational
institutions in South-western Nigeria which are directly funded by the federal government. The study considered
construction projects awarded and undertaken under the Due Process reform from 2001 to 2006 since the
reform actually took effect in 2001. The field work included the use of structured questionnaire that comprised
of two parts; section A and B. The first aspect was to obtain secondary data on Due Process projects awarded /
executed from 2001 to 2006 to determine the contactors project performance. The second aspect was used to
assess the factors that affected the performance of the Due Process projects. The limitations to the study
included the lack of archival data on construction activities in Nigeria. In order to achieve the aim of the study,
project documents in the selected institutions were collated for the purpose of data analysis. To ensure the
validity of the data collected, two questionnaires were given out for each specific project, one to the contractor
and the other to the client‟s representative. The sample consisted of all the fourteen (14) higher educational
institutions funded by the Federal Government in the south-western geopolitical zone of Nigeria. A total number
of 48 questionnaires were returned for 24 projects representing two per project. However, only 40
questionnaires representing 20 (83%) sample projects were good for analysis. Data on construction projects
were available in 12 (86%) out of the 14 higher educational institutions in the study area while data available in
the other two institutions were on the procurement of goods and services. Section A considered contractual
information on the Due Process projects related to the award, bid quotations, contract duration, final contract
sum (for projects completed) while section B covered specific project information and risk factors associated
with each project under consideration which were administered on the participants identified above. The
Resident Due Process personnel within the institutions were contacted for specific project information and
Contractors for the awarded projects under the scope of the study. Secondary data collated on the initial
and final contract sums and duration for individual project were analyzed to determine the rate of cost overrun
and delay experienced on each project. The level of cost and time overrun were determined by calculating the
mean differences and the rates of increase above the initial contract figures for each of the projects.
IV. RESULTS AND DISCUSSIONS
Table 1: Cost and Time performance of sample projects
Final contract sum
(N Millions)
Initial contract sum
(N Millions)
Rate of
increase
%
Final contract
duration
( Months)
Initial contract
duration
( Months)
Rate of
increase
%
45,000,000 42,230,000 0.0656 7 10 0.4286
15,428,434 13,854,734 0.1136 6 6 0.0000
36,000,000 26,000,000 0.3846 6 30 4.0000
65,944,606 49,944,606 0.3204 11 30 1.7273
12,324,000 8,984,000 0.3718 2 18 8.0000
34,062,225 27,698,375 0.2298 4 4 0.0000
12,890,650 12,776,993 0.0089 6.5 6.5 0.0000
12,000,000 12,000,000 0.0000 3 3 0.0000
24,000,000 22,000,000 0.0909 6 12 1.0000
26,800,000 25,000,000 0.0720 8 20 1.5000
55,156,733 44,156,733 0.2491 7.3 13 0.7808
15,642,000 14,784,000 0.0580 14 24 0.7143
7,142,250 5,334,105 0.3390 3 5 0.6667
14,825,250 13,500,000 0.0982 6 6 0.0000
377,216,148 318,263,546 0.1852 90 188 1.08
Cost And Time Performance Of …
4
Due to the lump sum nature of the Due process contract, the rate of cost overrun is minimal; 0.19, (Table 1).
This implies that project performance in terms of cost under the “Due process” is about 81%. This is not without
tradeoffs in respect of completion time and quality of the completed project as contractors are made to bear the
burden of any extra cost for the project as usual for lump sum contracts. This is not so much a plus to the Due
process reform because it erodes the contractor‟s profit and morale. On the other hand, time overrun is
experienced at the rate of 1.08 i.e. twice the initial contract period. The implication is that the contract periods
were exceeded by 108% of the expected contract duration.
Table 2: Factors responsible for timely completion
In Table 2, the financial capability of the client ranked highest as a factor for timely completion of the
projects with 30%, while accurate design and prompt payment were second with 23% each. The financial
capability of the contractor, favorable weather and adequate site condition do not have any significant effect on
the timely completion of the projects with 8% each. This suggests that the projects completed to time enjoyed
prompt payment with little or no design problems. The result shows that although the financial capability of the
contractor is one of the requirements for prequalification, it does not have effect on the completion period of the
project.
Table 3: Factors responsible for delay in completion
Design error, inflation and construction related problems were next with 16%, estimating error and client related
problems came third in the list (8%). Subcontractor/supplier had 3% contribution to project delay under the due
process reform. Financial incapability of the client did not arise with zero percent.
Table 4: Contract period (months)
Response %
Accurate design 23
Prompt payment 23
Financial capability of client 30
Financial capability of contractor 8
Favorable site condition 8
Favorable weather 8
Subcontractor/Supplier 0
Total 100
Factors № %
Design error 6 24
Site condition 3 12
Delay in payment. 9 36
Financial incapability of client 0 0
Financial incapability of contractor 6 24
Subcontractor /supplier 1 4
Total 25 100
Average
contract period
(months)
№ %
3.5 11 61
8.5 5 28
11.5 2 11
21.5 0 0
27.5 0 0
33.5 0 0
Total 18 100
Cost And Time Performance Of …
5
In table 4, 61% of the sample projects have contract periods within 1 to 6 months with an average
period of 3½ months while contracts with 7-12 and 13-18 months duration have 28% and 11% respectively. A
larger percentage of the due process projects were awarded on short contract period. The longest duration for
11% of the projects is between 13 to 18months with an average of 1year contract period.
Table 5: Number of completed projects
In Table 5, only 61% of the sample projects have been completed. Delayed payment (24%) was identified as
being highly responsible for time overrun (Table 3).
Table 6: Number of projects completed on time
Table 6 revealed that a greater percentage, 64% of the projects completed were subject to time overrun. This is a
confirmation of the result in table 1. Out of the 61% completed projects, only 36% were completed to time. This
implies that 64% of such projects were subject to time overrun while 39% of the projects were yet to be
completed.
V. CONCLUSION AND SUGGESTIONS
Construction projects under the Due process reform were awarded to pre-qualified contractors. Sixty-
one percent of the projects have short contract duration while the longest contract period falls below 18 months.
Only 36% of the (61%) completed projects were completed on time which implies that 64% of the Due Process
projects experienced time overrun (TABLE 5) at 108%. The financial capability of the client (31%), accurate
design and prompt payment (23%) were responsible for timely completion, (TABLE 2) while delay in payment
has the highest contribution to untimely completion of the projects as shown in TABLE 3. Design error,
inflation, construction related problems and financial incapability of the contractor has the second highest
contribution to untimely completion.
In the light of the above, the following suggestions are made:
1. Since the projects are awarded to pre-qualified contractors but mostly on short contract duration, it
should be ensured that contract duration quoted are realistic and strictly adhered to in order to avoid time
overrun.
2. The Due Process contracts are lump sum contracts and the ability of the contractor to access bank
loan is very poor due to the inflation rate and high interest rate. Therefore, the economy should be stabilized
to provide a leveled playground for contractors while bidding competitively. Contractors should be
financially empowered to finance construction projects to eliminate delay arising from late payment.
3. Lastly, the Federal Government should endeavor to assess the success of the reform so far in order to
address the grey areas.
REFERENCES
[1] Esenwa, O. F Jr. (2004) – “Project Procurement Method in Due process on How to Execute Capital Projects Effectively” Technical
meeting of the Department of Physical Planning and Development. Abuja.
[2] Wahab, K.A. (2006) – Federal Government Economic Reforms, Human Development and Due Process. Proceedings of the 1st
Annual
Lecture of the School of Environmental Technology, Federal University of Technology, Akure.
[3] Flanagan, R. & Norman, G. (1997) – Putting risk into perspective. Risk Management and Construction. London. Oxford.
[4] Wittig, A.W. (1999) – Building Value through Public Procurement: A Focus on Africa. Proceedings of the 9th
International Anti-
Corruption Conference. Geneva, Switzerland, available on-line at /www.transparency.or/iacc/9th
-iacc/papers/day2/ws2/d2ws2-
www.wittig.html/#eval. (accessed 19th
October, 2005).
[5] Okereke-Onyeri, F. A. (2008) – The Procurement Act”. Proceedings of the workshop of the Nigerian Institute of Quantity Surveyors
Lagos, Nigeria.
Response № %
Projects completed 11 61
Projects not completed 7 39
Total 18 100
Response № %
projects completed on time 4 36
projects not completed on time 7 64
Total 11 100
Cost And Time Performance Of …
6
[6] USAID, (2001a) - Nigeria -FY 2001. Program Description and Activity Data Sheet, available online at www–
usaid.Gov/pubs/bj2001/afr/index.html (accessed19th October, 2005).
[7] USAID, (2001b) -
Economic Management and Capacity Building {EMCAP}, available online at www –
usaid.Gov/pubs/bj2001/afr/ng/620-010.x/s (accessed19th October, 2005).
[8] Adedeji, A. (2004) - Challenges facing indigenous contracting firms. Independent Newspapers Ltd. Lagos, available online at
http/www.independentng.com.(accessed August, 2004)
[9] Abdullahi, I. (2004) –“Utilization of 2004 Capital Appropriations and Due Process Certification by BMPIU”. Meeting of the Directors
of Physical Planning Unit of Federal Universities and Inter-University Centers, Abuja, Nigeria.
[10] BMPIU (2005)- The ABC of the contract Due Process Policy. A manual on public procurement reform programme in Nigeria. State
House, Abuja, Nigeria.
[11] Waara, F. & Borchner, J. (2006) - A non price criteria for contractor selection. Journal of construction Engineering and
Management., 132(8), 797-804.
[12] Gale, T. (2006) – Construction: Securing a specialty contractor. Thompson Corporation. Retrieved February 20th
, 2006 from
www.refereceforbusiness.com/small/Co-Di/Construction.Intal
[13] Intr-American Development Bank(1997)- Comparative study on Government Procurement- Free Trade Area of the Americas.
Washington D.C. (accessed 26th
)
[14] Ibrahim A. D, (2008) – A critique of the operational philosophy and mechanism of the Public Procurement Act 2007: Construction
industry perspective. Proceedings the Biennial conference of the Nigerian Institute of Quantity Surveyors’ Kaduna, Nigeria.

Más contenido relacionado

Similar a Research Inventy : International Journal of Engineering and Science

An empirical analysis of the obstacles derailing procurement
An empirical analysis of the obstacles derailing procurementAn empirical analysis of the obstacles derailing procurement
An empirical analysis of the obstacles derailing procurementAlexander Decker
 
Effect of Fiscal Responsibility Act on Budgeting and Accountability Practice ...
Effect of Fiscal Responsibility Act on Budgeting and Accountability Practice ...Effect of Fiscal Responsibility Act on Budgeting and Accountability Practice ...
Effect of Fiscal Responsibility Act on Budgeting and Accountability Practice ...ijtsrd
 
Influence of performance contract on public service delivery in kenya study ...
Influence of performance contract on public service delivery in kenya  study ...Influence of performance contract on public service delivery in kenya  study ...
Influence of performance contract on public service delivery in kenya study ...Alexander Decker
 
Effects of Government Procurement on Prompt Tendering and Supply of Goods: A...
	Effects of Government Procurement on Prompt Tendering and Supply of Goods: A...	Effects of Government Procurement on Prompt Tendering and Supply of Goods: A...
Effects of Government Procurement on Prompt Tendering and Supply of Goods: A...inventionjournals
 
Effects of ghana’s current public procurement regime on the operations of val...
Effects of ghana’s current public procurement regime on the operations of val...Effects of ghana’s current public procurement regime on the operations of val...
Effects of ghana’s current public procurement regime on the operations of val...Alexander Decker
 
Presentation on theme.docx
Presentation on theme.docxPresentation on theme.docx
Presentation on theme.docxkayerencaole1
 
Public- Private Partnership (Ppp) As Catalyst for Sustainable Infrasstructura...
Public- Private Partnership (Ppp) As Catalyst for Sustainable Infrasstructura...Public- Private Partnership (Ppp) As Catalyst for Sustainable Infrasstructura...
Public- Private Partnership (Ppp) As Catalyst for Sustainable Infrasstructura...inventionjournals
 
Rabiu m shuaib nura jibo
Rabiu m shuaib nura jiboRabiu m shuaib nura jibo
Rabiu m shuaib nura jiboDr. Paul Davis
 
ASSESSING THE RELEVANCE OF QUANTITY SURVEYORS IN PUBLIC PRIVATE PARTNERSHIP I...
ASSESSING THE RELEVANCE OF QUANTITY SURVEYORS IN PUBLIC PRIVATE PARTNERSHIP I...ASSESSING THE RELEVANCE OF QUANTITY SURVEYORS IN PUBLIC PRIVATE PARTNERSHIP I...
ASSESSING THE RELEVANCE OF QUANTITY SURVEYORS IN PUBLIC PRIVATE PARTNERSHIP I...Audrey Britton
 
General Provisions of RA 9184
General Provisions of RA 9184General Provisions of RA 9184
General Provisions of RA 9184Emily Marundan
 
OVERVIEW OF PUBLIC PROCUREMENT UNDER THE PUBLIC PROCUREMENT[23058430092159162...
OVERVIEW OF PUBLIC PROCUREMENT UNDER THE PUBLIC PROCUREMENT[23058430092159162...OVERVIEW OF PUBLIC PROCUREMENT UNDER THE PUBLIC PROCUREMENT[23058430092159162...
OVERVIEW OF PUBLIC PROCUREMENT UNDER THE PUBLIC PROCUREMENT[23058430092159162...UbongAkpekong1
 
Place of Power Sector in Public-Private Partnership: A Veritable Tool to Prom...
Place of Power Sector in Public-Private Partnership: A Veritable Tool to Prom...Place of Power Sector in Public-Private Partnership: A Veritable Tool to Prom...
Place of Power Sector in Public-Private Partnership: A Veritable Tool to Prom...IJMERJOURNAL
 
Monitoring intensity-and-procurement-performance-emprical-evidence-from-elgey...
Monitoring intensity-and-procurement-performance-emprical-evidence-from-elgey...Monitoring intensity-and-procurement-performance-emprical-evidence-from-elgey...
Monitoring intensity-and-procurement-performance-emprical-evidence-from-elgey...oircjournals
 
Monitoring intensity-and-procurement-performance-emprical-evidence-from-elgey...
Monitoring intensity-and-procurement-performance-emprical-evidence-from-elgey...Monitoring intensity-and-procurement-performance-emprical-evidence-from-elgey...
Monitoring intensity-and-procurement-performance-emprical-evidence-from-elgey...oircjournals
 
procurement planning.pdf
procurement planning.pdfprocurement planning.pdf
procurement planning.pdfRawlings Bello
 
Quantity Surveyor’s Impact: A Panacea to achieving Critical Success Factors i...
Quantity Surveyor’s Impact: A Panacea to achieving Critical Success Factors i...Quantity Surveyor’s Impact: A Panacea to achieving Critical Success Factors i...
Quantity Surveyor’s Impact: A Panacea to achieving Critical Success Factors i...inventionjournals
 

Similar a Research Inventy : International Journal of Engineering and Science (20)

An empirical analysis of the obstacles derailing procurement
An empirical analysis of the obstacles derailing procurementAn empirical analysis of the obstacles derailing procurement
An empirical analysis of the obstacles derailing procurement
 
RICHAMPONG 2
RICHAMPONG 2RICHAMPONG 2
RICHAMPONG 2
 
Effect of Fiscal Responsibility Act on Budgeting and Accountability Practice ...
Effect of Fiscal Responsibility Act on Budgeting and Accountability Practice ...Effect of Fiscal Responsibility Act on Budgeting and Accountability Practice ...
Effect of Fiscal Responsibility Act on Budgeting and Accountability Practice ...
 
Influence of performance contract on public service delivery in kenya study ...
Influence of performance contract on public service delivery in kenya  study ...Influence of performance contract on public service delivery in kenya  study ...
Influence of performance contract on public service delivery in kenya study ...
 
Effects of Government Procurement on Prompt Tendering and Supply of Goods: A...
	Effects of Government Procurement on Prompt Tendering and Supply of Goods: A...	Effects of Government Procurement on Prompt Tendering and Supply of Goods: A...
Effects of Government Procurement on Prompt Tendering and Supply of Goods: A...
 
Effects of ghana’s current public procurement regime on the operations of val...
Effects of ghana’s current public procurement regime on the operations of val...Effects of ghana’s current public procurement regime on the operations of val...
Effects of ghana’s current public procurement regime on the operations of val...
 
Presentation on theme.docx
Presentation on theme.docxPresentation on theme.docx
Presentation on theme.docx
 
Public- Private Partnership (Ppp) As Catalyst for Sustainable Infrasstructura...
Public- Private Partnership (Ppp) As Catalyst for Sustainable Infrasstructura...Public- Private Partnership (Ppp) As Catalyst for Sustainable Infrasstructura...
Public- Private Partnership (Ppp) As Catalyst for Sustainable Infrasstructura...
 
Rabiu m shuaib nura jibo
Rabiu m shuaib nura jiboRabiu m shuaib nura jibo
Rabiu m shuaib nura jibo
 
ASSESSING THE RELEVANCE OF QUANTITY SURVEYORS IN PUBLIC PRIVATE PARTNERSHIP I...
ASSESSING THE RELEVANCE OF QUANTITY SURVEYORS IN PUBLIC PRIVATE PARTNERSHIP I...ASSESSING THE RELEVANCE OF QUANTITY SURVEYORS IN PUBLIC PRIVATE PARTNERSHIP I...
ASSESSING THE RELEVANCE OF QUANTITY SURVEYORS IN PUBLIC PRIVATE PARTNERSHIP I...
 
General Provisions of RA 9184
General Provisions of RA 9184General Provisions of RA 9184
General Provisions of RA 9184
 
Factors affecting effective
Factors affecting effectiveFactors affecting effective
Factors affecting effective
 
Procurement process
Procurement processProcurement process
Procurement process
 
OVERVIEW OF PUBLIC PROCUREMENT UNDER THE PUBLIC PROCUREMENT[23058430092159162...
OVERVIEW OF PUBLIC PROCUREMENT UNDER THE PUBLIC PROCUREMENT[23058430092159162...OVERVIEW OF PUBLIC PROCUREMENT UNDER THE PUBLIC PROCUREMENT[23058430092159162...
OVERVIEW OF PUBLIC PROCUREMENT UNDER THE PUBLIC PROCUREMENT[23058430092159162...
 
Place of Power Sector in Public-Private Partnership: A Veritable Tool to Prom...
Place of Power Sector in Public-Private Partnership: A Veritable Tool to Prom...Place of Power Sector in Public-Private Partnership: A Veritable Tool to Prom...
Place of Power Sector in Public-Private Partnership: A Veritable Tool to Prom...
 
Monitoring intensity-and-procurement-performance-emprical-evidence-from-elgey...
Monitoring intensity-and-procurement-performance-emprical-evidence-from-elgey...Monitoring intensity-and-procurement-performance-emprical-evidence-from-elgey...
Monitoring intensity-and-procurement-performance-emprical-evidence-from-elgey...
 
Monitoring intensity-and-procurement-performance-emprical-evidence-from-elgey...
Monitoring intensity-and-procurement-performance-emprical-evidence-from-elgey...Monitoring intensity-and-procurement-performance-emprical-evidence-from-elgey...
Monitoring intensity-and-procurement-performance-emprical-evidence-from-elgey...
 
procurement planning.pdf
procurement planning.pdfprocurement planning.pdf
procurement planning.pdf
 
Quantity Surveyor’s Impact: A Panacea to achieving Critical Success Factors i...
Quantity Surveyor’s Impact: A Panacea to achieving Critical Success Factors i...Quantity Surveyor’s Impact: A Panacea to achieving Critical Success Factors i...
Quantity Surveyor’s Impact: A Panacea to achieving Critical Success Factors i...
 
Rethinking Public Procurement System in Nigeria: The E-Procurement Option (A ...
Rethinking Public Procurement System in Nigeria: The E-Procurement Option (A ...Rethinking Public Procurement System in Nigeria: The E-Procurement Option (A ...
Rethinking Public Procurement System in Nigeria: The E-Procurement Option (A ...
 

Más de inventy

Experimental Investigation of a Household Refrigerator Using Evaporative-Cool...
Experimental Investigation of a Household Refrigerator Using Evaporative-Cool...Experimental Investigation of a Household Refrigerator Using Evaporative-Cool...
Experimental Investigation of a Household Refrigerator Using Evaporative-Cool...inventy
 
Copper Strip Corrossion Test in Various Aviation Fuels
Copper Strip Corrossion Test in Various Aviation FuelsCopper Strip Corrossion Test in Various Aviation Fuels
Copper Strip Corrossion Test in Various Aviation Fuelsinventy
 
Additional Conservation Laws for Two-Velocity Hydrodynamics Equations with th...
Additional Conservation Laws for Two-Velocity Hydrodynamics Equations with th...Additional Conservation Laws for Two-Velocity Hydrodynamics Equations with th...
Additional Conservation Laws for Two-Velocity Hydrodynamics Equations with th...inventy
 
Comparative Study of the Quality of Life, Quality of Work Life and Organisati...
Comparative Study of the Quality of Life, Quality of Work Life and Organisati...Comparative Study of the Quality of Life, Quality of Work Life and Organisati...
Comparative Study of the Quality of Life, Quality of Work Life and Organisati...inventy
 
A Study of Automated Decision Making Systems
A Study of Automated Decision Making SystemsA Study of Automated Decision Making Systems
A Study of Automated Decision Making Systemsinventy
 
Crystallization of L-Glutamic Acid: Mechanism of Heterogeneous β -Form Nuclea...
Crystallization of L-Glutamic Acid: Mechanism of Heterogeneous β -Form Nuclea...Crystallization of L-Glutamic Acid: Mechanism of Heterogeneous β -Form Nuclea...
Crystallization of L-Glutamic Acid: Mechanism of Heterogeneous β -Form Nuclea...inventy
 
Evaluation of Damage by the Reliability of the Traction Test on Polymer Test ...
Evaluation of Damage by the Reliability of the Traction Test on Polymer Test ...Evaluation of Damage by the Reliability of the Traction Test on Polymer Test ...
Evaluation of Damage by the Reliability of the Traction Test on Polymer Test ...inventy
 
Application of Kennelly’model of Running Performances to Elite Endurance Runn...
Application of Kennelly’model of Running Performances to Elite Endurance Runn...Application of Kennelly’model of Running Performances to Elite Endurance Runn...
Application of Kennelly’model of Running Performances to Elite Endurance Runn...inventy
 
Development and Application of a Failure Monitoring System by Using the Vibra...
Development and Application of a Failure Monitoring System by Using the Vibra...Development and Application of a Failure Monitoring System by Using the Vibra...
Development and Application of a Failure Monitoring System by Using the Vibra...inventy
 
The Management of Protected Areas in Serengeti Ecosystem: A Case Study of Iko...
The Management of Protected Areas in Serengeti Ecosystem: A Case Study of Iko...The Management of Protected Areas in Serengeti Ecosystem: A Case Study of Iko...
The Management of Protected Areas in Serengeti Ecosystem: A Case Study of Iko...inventy
 
Size distribution and biometric relationships of little tunny Euthynnus allet...
Size distribution and biometric relationships of little tunny Euthynnus allet...Size distribution and biometric relationships of little tunny Euthynnus allet...
Size distribution and biometric relationships of little tunny Euthynnus allet...inventy
 
Removal of Chromium (VI) From Aqueous Solutions Using Discarded Solanum Tuber...
Removal of Chromium (VI) From Aqueous Solutions Using Discarded Solanum Tuber...Removal of Chromium (VI) From Aqueous Solutions Using Discarded Solanum Tuber...
Removal of Chromium (VI) From Aqueous Solutions Using Discarded Solanum Tuber...inventy
 
Effect of Various External and Internal Factors on the Carrier Mobility in n-...
Effect of Various External and Internal Factors on the Carrier Mobility in n-...Effect of Various External and Internal Factors on the Carrier Mobility in n-...
Effect of Various External and Internal Factors on the Carrier Mobility in n-...inventy
 
Transient flow analysis for horizontal axial upper-wind turbine
Transient flow analysis for horizontal axial upper-wind turbineTransient flow analysis for horizontal axial upper-wind turbine
Transient flow analysis for horizontal axial upper-wind turbineinventy
 
Choice of Numerical Integration Method for Wind Time History Analysis of Tall...
Choice of Numerical Integration Method for Wind Time History Analysis of Tall...Choice of Numerical Integration Method for Wind Time History Analysis of Tall...
Choice of Numerical Integration Method for Wind Time History Analysis of Tall...inventy
 
Impacts of Demand Side Management on System Reliability Evaluation
Impacts of Demand Side Management on System Reliability EvaluationImpacts of Demand Side Management on System Reliability Evaluation
Impacts of Demand Side Management on System Reliability Evaluationinventy
 
Reliability Evaluation of Riyadh System Incorporating Renewable Generation
Reliability Evaluation of Riyadh System Incorporating Renewable GenerationReliability Evaluation of Riyadh System Incorporating Renewable Generation
Reliability Evaluation of Riyadh System Incorporating Renewable Generationinventy
 
The effect of reduced pressure acetylene plasma treatment on physical charact...
The effect of reduced pressure acetylene plasma treatment on physical charact...The effect of reduced pressure acetylene plasma treatment on physical charact...
The effect of reduced pressure acetylene plasma treatment on physical charact...inventy
 
Experimental Investigation of Mini Cooler cum Freezer
Experimental Investigation of Mini Cooler cum FreezerExperimental Investigation of Mini Cooler cum Freezer
Experimental Investigation of Mini Cooler cum Freezerinventy
 
Growth and Magnetic properties of MnGeP2 thin films
Growth and Magnetic properties of MnGeP2 thin filmsGrowth and Magnetic properties of MnGeP2 thin films
Growth and Magnetic properties of MnGeP2 thin filmsinventy
 

Más de inventy (20)

Experimental Investigation of a Household Refrigerator Using Evaporative-Cool...
Experimental Investigation of a Household Refrigerator Using Evaporative-Cool...Experimental Investigation of a Household Refrigerator Using Evaporative-Cool...
Experimental Investigation of a Household Refrigerator Using Evaporative-Cool...
 
Copper Strip Corrossion Test in Various Aviation Fuels
Copper Strip Corrossion Test in Various Aviation FuelsCopper Strip Corrossion Test in Various Aviation Fuels
Copper Strip Corrossion Test in Various Aviation Fuels
 
Additional Conservation Laws for Two-Velocity Hydrodynamics Equations with th...
Additional Conservation Laws for Two-Velocity Hydrodynamics Equations with th...Additional Conservation Laws for Two-Velocity Hydrodynamics Equations with th...
Additional Conservation Laws for Two-Velocity Hydrodynamics Equations with th...
 
Comparative Study of the Quality of Life, Quality of Work Life and Organisati...
Comparative Study of the Quality of Life, Quality of Work Life and Organisati...Comparative Study of the Quality of Life, Quality of Work Life and Organisati...
Comparative Study of the Quality of Life, Quality of Work Life and Organisati...
 
A Study of Automated Decision Making Systems
A Study of Automated Decision Making SystemsA Study of Automated Decision Making Systems
A Study of Automated Decision Making Systems
 
Crystallization of L-Glutamic Acid: Mechanism of Heterogeneous β -Form Nuclea...
Crystallization of L-Glutamic Acid: Mechanism of Heterogeneous β -Form Nuclea...Crystallization of L-Glutamic Acid: Mechanism of Heterogeneous β -Form Nuclea...
Crystallization of L-Glutamic Acid: Mechanism of Heterogeneous β -Form Nuclea...
 
Evaluation of Damage by the Reliability of the Traction Test on Polymer Test ...
Evaluation of Damage by the Reliability of the Traction Test on Polymer Test ...Evaluation of Damage by the Reliability of the Traction Test on Polymer Test ...
Evaluation of Damage by the Reliability of the Traction Test on Polymer Test ...
 
Application of Kennelly’model of Running Performances to Elite Endurance Runn...
Application of Kennelly’model of Running Performances to Elite Endurance Runn...Application of Kennelly’model of Running Performances to Elite Endurance Runn...
Application of Kennelly’model of Running Performances to Elite Endurance Runn...
 
Development and Application of a Failure Monitoring System by Using the Vibra...
Development and Application of a Failure Monitoring System by Using the Vibra...Development and Application of a Failure Monitoring System by Using the Vibra...
Development and Application of a Failure Monitoring System by Using the Vibra...
 
The Management of Protected Areas in Serengeti Ecosystem: A Case Study of Iko...
The Management of Protected Areas in Serengeti Ecosystem: A Case Study of Iko...The Management of Protected Areas in Serengeti Ecosystem: A Case Study of Iko...
The Management of Protected Areas in Serengeti Ecosystem: A Case Study of Iko...
 
Size distribution and biometric relationships of little tunny Euthynnus allet...
Size distribution and biometric relationships of little tunny Euthynnus allet...Size distribution and biometric relationships of little tunny Euthynnus allet...
Size distribution and biometric relationships of little tunny Euthynnus allet...
 
Removal of Chromium (VI) From Aqueous Solutions Using Discarded Solanum Tuber...
Removal of Chromium (VI) From Aqueous Solutions Using Discarded Solanum Tuber...Removal of Chromium (VI) From Aqueous Solutions Using Discarded Solanum Tuber...
Removal of Chromium (VI) From Aqueous Solutions Using Discarded Solanum Tuber...
 
Effect of Various External and Internal Factors on the Carrier Mobility in n-...
Effect of Various External and Internal Factors on the Carrier Mobility in n-...Effect of Various External and Internal Factors on the Carrier Mobility in n-...
Effect of Various External and Internal Factors on the Carrier Mobility in n-...
 
Transient flow analysis for horizontal axial upper-wind turbine
Transient flow analysis for horizontal axial upper-wind turbineTransient flow analysis for horizontal axial upper-wind turbine
Transient flow analysis for horizontal axial upper-wind turbine
 
Choice of Numerical Integration Method for Wind Time History Analysis of Tall...
Choice of Numerical Integration Method for Wind Time History Analysis of Tall...Choice of Numerical Integration Method for Wind Time History Analysis of Tall...
Choice of Numerical Integration Method for Wind Time History Analysis of Tall...
 
Impacts of Demand Side Management on System Reliability Evaluation
Impacts of Demand Side Management on System Reliability EvaluationImpacts of Demand Side Management on System Reliability Evaluation
Impacts of Demand Side Management on System Reliability Evaluation
 
Reliability Evaluation of Riyadh System Incorporating Renewable Generation
Reliability Evaluation of Riyadh System Incorporating Renewable GenerationReliability Evaluation of Riyadh System Incorporating Renewable Generation
Reliability Evaluation of Riyadh System Incorporating Renewable Generation
 
The effect of reduced pressure acetylene plasma treatment on physical charact...
The effect of reduced pressure acetylene plasma treatment on physical charact...The effect of reduced pressure acetylene plasma treatment on physical charact...
The effect of reduced pressure acetylene plasma treatment on physical charact...
 
Experimental Investigation of Mini Cooler cum Freezer
Experimental Investigation of Mini Cooler cum FreezerExperimental Investigation of Mini Cooler cum Freezer
Experimental Investigation of Mini Cooler cum Freezer
 
Growth and Magnetic properties of MnGeP2 thin films
Growth and Magnetic properties of MnGeP2 thin filmsGrowth and Magnetic properties of MnGeP2 thin films
Growth and Magnetic properties of MnGeP2 thin films
 

Último

Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonAnna Loughnan Colquhoun
 
Deploy with confidence: VMware Cloud Foundation 5.1 on next gen Dell PowerEdg...
Deploy with confidence: VMware Cloud Foundation 5.1 on next gen Dell PowerEdg...Deploy with confidence: VMware Cloud Foundation 5.1 on next gen Dell PowerEdg...
Deploy with confidence: VMware Cloud Foundation 5.1 on next gen Dell PowerEdg...Principled Technologies
 
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data DiscoveryTrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data DiscoveryTrustArc
 
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin WoodPolkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin WoodJuan lago vázquez
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...Martijn de Jong
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?Igalia
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024The Digital Insurer
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Scriptwesley chun
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Miguel Araújo
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationRadu Cotescu
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FMESafe Software
 
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUnderstanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUK Journal
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024The Digital Insurer
 
Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024The Digital Insurer
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfsudhanshuwaghmare1
 
Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)wesley chun
 
Artificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : UncertaintyArtificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : UncertaintyKhushali Kathiriya
 
GenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdfGenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdflior mazor
 
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...apidays
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc
 

Último (20)

Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt Robison
 
Deploy with confidence: VMware Cloud Foundation 5.1 on next gen Dell PowerEdg...
Deploy with confidence: VMware Cloud Foundation 5.1 on next gen Dell PowerEdg...Deploy with confidence: VMware Cloud Foundation 5.1 on next gen Dell PowerEdg...
Deploy with confidence: VMware Cloud Foundation 5.1 on next gen Dell PowerEdg...
 
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data DiscoveryTrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
 
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin WoodPolkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Script
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
 
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUnderstanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
 
Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdf
 
Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)
 
Artificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : UncertaintyArtificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : Uncertainty
 
GenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdfGenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdf
 
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 

Research Inventy : International Journal of Engineering and Science

  • 1. Research Inventy: International Journal Of Engineering And Science Vol.3, Issue 6 (Aug 2013), PP 01-06 Issn(e): 2278-4721, Issn(p):2319-6483, Www.Researchinventy.Com 1 Cost and Time Performance of Construction Projects under The Due Process Reform In Nigeria ¹ADE-OJO, Comfort Olubunmi, ²BABALOLA, Anthony Ayo. ¹Department of Quantity Surveying, The Federal Polytechnic, Ado-Ekiti. Nigeria. ²Department of Quantity Surveying, The Federal Polytechnic, Ado-Ekiti. Nigeria. ABSTRACT: The Due process policy is a product of the Fderal government public procurement reform of 1999. The policy was meant to be an anticorruption device aimed at ensuring probity, transparency, accountability in the procurement of public goods and services. The need for the reform is long overdue. However, in order to assess the implementation of the Due process policy in procurement of construction projects, the study took a survey study of construction projects awarded and executed in federal higher educational institutions in the southwest Nigeria. The study revealed that although cost overrun on such projects was at 19% due to the lump sum nature of the due process reform, time overrun was at the rate of 108%. Financial capability of the client followed by prompt payment were identified respectively for timely completion while delayed payment has the highest contribution to time overrun at 36%. Financial incapability of the contractor has significant contribution to delay in completion of the projects. The study observed that the contracts were awarded on short contract duration, it concluded that the excessive time overrun on such projects is not good for the construction industry in Nigeria as it does not only erode the contractor’s profit, it also deprives the client from having his project as at when due. It therefore suggested that there is need to ensure that realistic contract periods are quoted and that the federal government should endeavor to assess the success of the reform so far in order to address the grey areas. KEY WORDS: Due Process, cost overrun, time overrun, performance, prequalification. I. INTRODUCTION The Federal Government of Nigeria in 1999 adopted the use of competitive bidding as a means of procuring public goods and services. The development came on the heels of the economic reform going on in the country as it became imperative that to achieve sanity in the public sector procurement, there was need for a procurement reform. The Budget Monitoring and Implementation Unit (BMPIU) was set up for the monitoring and implementation of the procurement reform which is being referred to as the Due Process certification (Ezenwa, 2004[1]; Wahab, 2006[2]). This is referred to as the Bureau for Public Procurement in the Procurement Act of 2007. The due process reform in the procurement of construction project in Nigeria is in response to the unguarded and uncoordinated way in which public projects were awarded. Considering the fact that the government is the largest consumer of the construction industry product, its procurement policies directly impacts on the activity of the industry. This is so much the case of a developing economy like Nigeria. In order to provide a sane and guarded means of procuring public project, the guidelines are stringently interwoven with lots of bureaucratic intervention. To combat fraud and unreasonably high rates of procurement of public works in Nigeria, the Federal Government introduced competitive bidding as a procurement method emphasized by the Due Process reform. The crux of the Due Process reform is to get the lowest responsive and responsible bidder, one who takes into proper consideration the pros and cons of the project if the contract is won. However, researches have shown that contractors are more concerned with “being the lowest bidder” rather than “the responsive and responsible bidder”, assuming the “All Goes According to Plan” (AGPA) and not the “What Happens If ” (WHIF) as proposed by Flanagan and Norman (1997[3]). In view of these, achieving reasonable performance of construction projects in terms of time and cost cannot be guaranteed which is not good for the health of the construction industry. Consequently, the research question therefore is; „what is the level of performance of construction projects since the implementation of the Due Process reform for the award of public contract for goods and services in Nigeria including those for construction works‟, what are the factors that influence the performance of construction projects under the due process reform and what are those factors that mitigate effective performance of such projects?.
  • 2. Cost And Time Performance Of … 2 II. PUBLIC PROCUREMENT REFORM Public procurement systems across the globe began to receive attention not too long ago. Before the April 11, (9th ) International Anti-Corruption Conference held in Abidjan in 1998 which stimulated a new look at procurement in many Countries of the world, procurement was seen as an insignificant part of an administrative function. Wittig (1999[4]) believes that the reviews of public procurement systems in the developed countries in recent times were geared towards improving its efficiency and generating savings in government spending. The United States in 1994, procurement reform of South Africa in 1997 and in 1998, the United Kingdom‟s call for efficiency in Civil Government led to its public sector reform. The series of economic reforms embarked upon by the Obasanjo led administration starting form 1999 gave birth to the public procurement act in Nigeria which was signed into law on the 4th of June 2007 (Okereke –Onyeri, 2008[5]). 2.1 Procurement Reform In Nigeria Before the reestablishment of the democratic rule in 1999, the public sector procurement system in Nigeria had witnessed years of economic mismanagement and corruption under the successive military regimes (USAID, 2001a[6]) such as the abandonment of the initial Structural Adjustment Reforms of 1986 by the year 1992 resulting into years of slow and stagnated growth, inflation and increased poverty in Nigeria (USAID, 2001b[7]). In 1999, the Obasanjo led Administration took discreet steps to check the excesses of the previous administrations, combat corruption and build public confidence (USAID, 2001b). This was the beginning of the Procurement Reform in Nigeria and the implementation of the Due Process certification in the procurement of public goods and services is one of the cardinal strategies of the economic reform (Wahab, 2006[2]). The Procurement Act of June, 2007 was enacted to provide a legal and operational frame work for proper implementation of the Due Process reform. The Procurement Act as stated „shall apply to the procurement of goods, works and services carried out by the Federal government of Nigeria and all its entities that derives at least 35% of its fund from the Federal government‟ (Okereke-Onyeri, 2008[5]). The Bureau for Public Procurement is expected to among other things ensure the application of fair, competitive, transparent and value for money standards. 2.2 THE “DUE PROCESS” REFORM Adedeji (2004[8]) noted that the public sector as the largest client of the construction industry in Nigeria is badly reputed for poor financial probity. The “Due Process Reform” came as an anti-corruption device to entrench the ideals of public procurement systems using the “Due process certification” in the award of contracts for public projects in Nigeria. Collusion between parties to public contracts and acceptance of gratuities from bidding contractors in the award of such contracts has greatly affected the decision-making and executive processes of Nigeria resulting in Legal, Administrative and Economic costs to the Country (Wittig, 1999[4]; Abdullahi, 2004[9] and Esenwa, 2004[1]). The enactment of the due process policy by the Federal government of Nigeria was in line with the World Trade Organization‟s (WTO) Government Procurement Agreement (GPA). The GPA is supported by the World Bank based on the United Nations Committee on International Trade Law (UNCITRAL) model for public procurement. The “Due Process” reform of the Federal Republic of Nigeria is as contained in the “New Policy Guidelines for Procurement and Award of contracts in Government ministries/parastatals- Ref no FI5775 of 27th June 2001 and the Treasury Circular no ASA55/001 of 30th October, 2001 on “Due Process Certification of contracts (Abdulahi,2004[9]). The BMPIU established for proper implementation of the Due process certification of contracts transformed into the Bureau for Public Procurement with the signing into law the 2007 Public Procurement Act. Contractor‟s prequalification is one of the focal points of the procurement reform. The provision of the Due Process certification states that public contracts be awarded within specific thresholds as follows; Contracts below N1m, Contracts above N1m but below N50m and Contracts of N50m and above (BMPIU, 2005[10]). Abdullahi (2004 [9]) observed that contracts above N10m shall be given notice for 6 weeks while contracts above this threshold will require two- stage certification: Pre-qualification with a minimum of 2 weeks and bidding period of 6 weeks. The lowest price/best evaluated bid shall be awarded the contract. 2.3 PREQUALIFICATION Waara and Brochner (2006[11]) identified prequalification as the only possible way of protecting the capable and established firms with the client getting a more economical job. It ensures that invitation to bid is only given to the firms who have adequate capabilities and resources to execute the project (Gale, 2006[12]). The effective implementation of competitive bidding is dependent on Contractor‟s prequalification as this, if adequately implemented, serves to prevent fronting and window dressing by incompetent and corrupt
  • 3. Cost And Time Performance Of … 3 contractors. The different government circulars on the implementation of the Due Process Certification as summarized by Esenwa (2004[1]) pointed out that the call for pre-qualification is one of the major criteria for the certification of any public projects awarded. Going by the Inter-America Development Banks report (1997[13]); prequalification depends on the “ability of the potential contractors to carry out the works in satisfactory manner”. The criteria for pre-qualification stated in the report include Past experience and results in similar projects, Contractor‟s personnel and equipment available, Financial capability of the contractor, Other contracts presently being undertaken, Any litigation or Arbitration from previous contracts in the last five years. The 2007 Procurement Act also stipulates professional and technical qualifications, financial capability, equipment and adequate personnel to execute the contract (Ibrahim, 2008[14]). III. RESEARCH METHODOLOGY: The research consists of a survey of Due process projects carried out in Federal higher educational institutions in South-western Nigeria which are directly funded by the federal government. The study considered construction projects awarded and undertaken under the Due Process reform from 2001 to 2006 since the reform actually took effect in 2001. The field work included the use of structured questionnaire that comprised of two parts; section A and B. The first aspect was to obtain secondary data on Due Process projects awarded / executed from 2001 to 2006 to determine the contactors project performance. The second aspect was used to assess the factors that affected the performance of the Due Process projects. The limitations to the study included the lack of archival data on construction activities in Nigeria. In order to achieve the aim of the study, project documents in the selected institutions were collated for the purpose of data analysis. To ensure the validity of the data collected, two questionnaires were given out for each specific project, one to the contractor and the other to the client‟s representative. The sample consisted of all the fourteen (14) higher educational institutions funded by the Federal Government in the south-western geopolitical zone of Nigeria. A total number of 48 questionnaires were returned for 24 projects representing two per project. However, only 40 questionnaires representing 20 (83%) sample projects were good for analysis. Data on construction projects were available in 12 (86%) out of the 14 higher educational institutions in the study area while data available in the other two institutions were on the procurement of goods and services. Section A considered contractual information on the Due Process projects related to the award, bid quotations, contract duration, final contract sum (for projects completed) while section B covered specific project information and risk factors associated with each project under consideration which were administered on the participants identified above. The Resident Due Process personnel within the institutions were contacted for specific project information and Contractors for the awarded projects under the scope of the study. Secondary data collated on the initial and final contract sums and duration for individual project were analyzed to determine the rate of cost overrun and delay experienced on each project. The level of cost and time overrun were determined by calculating the mean differences and the rates of increase above the initial contract figures for each of the projects. IV. RESULTS AND DISCUSSIONS Table 1: Cost and Time performance of sample projects Final contract sum (N Millions) Initial contract sum (N Millions) Rate of increase % Final contract duration ( Months) Initial contract duration ( Months) Rate of increase % 45,000,000 42,230,000 0.0656 7 10 0.4286 15,428,434 13,854,734 0.1136 6 6 0.0000 36,000,000 26,000,000 0.3846 6 30 4.0000 65,944,606 49,944,606 0.3204 11 30 1.7273 12,324,000 8,984,000 0.3718 2 18 8.0000 34,062,225 27,698,375 0.2298 4 4 0.0000 12,890,650 12,776,993 0.0089 6.5 6.5 0.0000 12,000,000 12,000,000 0.0000 3 3 0.0000 24,000,000 22,000,000 0.0909 6 12 1.0000 26,800,000 25,000,000 0.0720 8 20 1.5000 55,156,733 44,156,733 0.2491 7.3 13 0.7808 15,642,000 14,784,000 0.0580 14 24 0.7143 7,142,250 5,334,105 0.3390 3 5 0.6667 14,825,250 13,500,000 0.0982 6 6 0.0000 377,216,148 318,263,546 0.1852 90 188 1.08
  • 4. Cost And Time Performance Of … 4 Due to the lump sum nature of the Due process contract, the rate of cost overrun is minimal; 0.19, (Table 1). This implies that project performance in terms of cost under the “Due process” is about 81%. This is not without tradeoffs in respect of completion time and quality of the completed project as contractors are made to bear the burden of any extra cost for the project as usual for lump sum contracts. This is not so much a plus to the Due process reform because it erodes the contractor‟s profit and morale. On the other hand, time overrun is experienced at the rate of 1.08 i.e. twice the initial contract period. The implication is that the contract periods were exceeded by 108% of the expected contract duration. Table 2: Factors responsible for timely completion In Table 2, the financial capability of the client ranked highest as a factor for timely completion of the projects with 30%, while accurate design and prompt payment were second with 23% each. The financial capability of the contractor, favorable weather and adequate site condition do not have any significant effect on the timely completion of the projects with 8% each. This suggests that the projects completed to time enjoyed prompt payment with little or no design problems. The result shows that although the financial capability of the contractor is one of the requirements for prequalification, it does not have effect on the completion period of the project. Table 3: Factors responsible for delay in completion Design error, inflation and construction related problems were next with 16%, estimating error and client related problems came third in the list (8%). Subcontractor/supplier had 3% contribution to project delay under the due process reform. Financial incapability of the client did not arise with zero percent. Table 4: Contract period (months) Response % Accurate design 23 Prompt payment 23 Financial capability of client 30 Financial capability of contractor 8 Favorable site condition 8 Favorable weather 8 Subcontractor/Supplier 0 Total 100 Factors № % Design error 6 24 Site condition 3 12 Delay in payment. 9 36 Financial incapability of client 0 0 Financial incapability of contractor 6 24 Subcontractor /supplier 1 4 Total 25 100 Average contract period (months) № % 3.5 11 61 8.5 5 28 11.5 2 11 21.5 0 0 27.5 0 0 33.5 0 0 Total 18 100
  • 5. Cost And Time Performance Of … 5 In table 4, 61% of the sample projects have contract periods within 1 to 6 months with an average period of 3½ months while contracts with 7-12 and 13-18 months duration have 28% and 11% respectively. A larger percentage of the due process projects were awarded on short contract period. The longest duration for 11% of the projects is between 13 to 18months with an average of 1year contract period. Table 5: Number of completed projects In Table 5, only 61% of the sample projects have been completed. Delayed payment (24%) was identified as being highly responsible for time overrun (Table 3). Table 6: Number of projects completed on time Table 6 revealed that a greater percentage, 64% of the projects completed were subject to time overrun. This is a confirmation of the result in table 1. Out of the 61% completed projects, only 36% were completed to time. This implies that 64% of such projects were subject to time overrun while 39% of the projects were yet to be completed. V. CONCLUSION AND SUGGESTIONS Construction projects under the Due process reform were awarded to pre-qualified contractors. Sixty- one percent of the projects have short contract duration while the longest contract period falls below 18 months. Only 36% of the (61%) completed projects were completed on time which implies that 64% of the Due Process projects experienced time overrun (TABLE 5) at 108%. The financial capability of the client (31%), accurate design and prompt payment (23%) were responsible for timely completion, (TABLE 2) while delay in payment has the highest contribution to untimely completion of the projects as shown in TABLE 3. Design error, inflation, construction related problems and financial incapability of the contractor has the second highest contribution to untimely completion. In the light of the above, the following suggestions are made: 1. Since the projects are awarded to pre-qualified contractors but mostly on short contract duration, it should be ensured that contract duration quoted are realistic and strictly adhered to in order to avoid time overrun. 2. The Due Process contracts are lump sum contracts and the ability of the contractor to access bank loan is very poor due to the inflation rate and high interest rate. Therefore, the economy should be stabilized to provide a leveled playground for contractors while bidding competitively. Contractors should be financially empowered to finance construction projects to eliminate delay arising from late payment. 3. Lastly, the Federal Government should endeavor to assess the success of the reform so far in order to address the grey areas. REFERENCES [1] Esenwa, O. F Jr. (2004) – “Project Procurement Method in Due process on How to Execute Capital Projects Effectively” Technical meeting of the Department of Physical Planning and Development. Abuja. [2] Wahab, K.A. (2006) – Federal Government Economic Reforms, Human Development and Due Process. Proceedings of the 1st Annual Lecture of the School of Environmental Technology, Federal University of Technology, Akure. [3] Flanagan, R. & Norman, G. (1997) – Putting risk into perspective. Risk Management and Construction. London. Oxford. [4] Wittig, A.W. (1999) – Building Value through Public Procurement: A Focus on Africa. Proceedings of the 9th International Anti- Corruption Conference. Geneva, Switzerland, available on-line at /www.transparency.or/iacc/9th -iacc/papers/day2/ws2/d2ws2- www.wittig.html/#eval. (accessed 19th October, 2005). [5] Okereke-Onyeri, F. A. (2008) – The Procurement Act”. Proceedings of the workshop of the Nigerian Institute of Quantity Surveyors Lagos, Nigeria. Response № % Projects completed 11 61 Projects not completed 7 39 Total 18 100 Response № % projects completed on time 4 36 projects not completed on time 7 64 Total 11 100
  • 6. Cost And Time Performance Of … 6 [6] USAID, (2001a) - Nigeria -FY 2001. Program Description and Activity Data Sheet, available online at www– usaid.Gov/pubs/bj2001/afr/index.html (accessed19th October, 2005). [7] USAID, (2001b) - Economic Management and Capacity Building {EMCAP}, available online at www – usaid.Gov/pubs/bj2001/afr/ng/620-010.x/s (accessed19th October, 2005). [8] Adedeji, A. (2004) - Challenges facing indigenous contracting firms. Independent Newspapers Ltd. Lagos, available online at http/www.independentng.com.(accessed August, 2004) [9] Abdullahi, I. (2004) –“Utilization of 2004 Capital Appropriations and Due Process Certification by BMPIU”. Meeting of the Directors of Physical Planning Unit of Federal Universities and Inter-University Centers, Abuja, Nigeria. [10] BMPIU (2005)- The ABC of the contract Due Process Policy. A manual on public procurement reform programme in Nigeria. State House, Abuja, Nigeria. [11] Waara, F. & Borchner, J. (2006) - A non price criteria for contractor selection. Journal of construction Engineering and Management., 132(8), 797-804. [12] Gale, T. (2006) – Construction: Securing a specialty contractor. Thompson Corporation. Retrieved February 20th , 2006 from www.refereceforbusiness.com/small/Co-Di/Construction.Intal [13] Intr-American Development Bank(1997)- Comparative study on Government Procurement- Free Trade Area of the Americas. Washington D.C. (accessed 26th ) [14] Ibrahim A. D, (2008) – A critique of the operational philosophy and mechanism of the Public Procurement Act 2007: Construction industry perspective. Proceedings the Biennial conference of the Nigerian Institute of Quantity Surveyors’ Kaduna, Nigeria.