A Study on Identification of Risks at Various Phases of Road
Construction
Vishal Shelar1, Asst. Prof Shruti Wadalkar2
1PG student, Dept. of Civil Engineering, Dr. D.Y Patil Institute of Technology, Pune, MH, India
2Asst. Professor, Dept. of Civil Engineering, Dr.D.Y Patil Institute of Technology, Pune, MH, India
---------------------------------------------------------------------------------***-------------------------------------------------------------------------------
Abstract— Risk is nothing but the difficulties occurring in the
completion of the project in such a way that causes delay of
the project, increase in the cost of project, quality of the work
etc. For a road construction projects it is very important to
mitigate the risks for the completion of the project without
any failure. In order to mitigate the risk factors we have to
first identify the risk which are causing a greater impact and
then take the steps to overcome the losses caused by them. It
is important to rank the risks which will give us priority of the
risk mitigation program. To do the ranking one needs to do it
logically by methods such as various indices, Analytical
Hierarchy Processes, fuzzy logics etc. Better way is to do it by
different methods and check if the result occurred is relatively
same or not, if it’s same then ranking or priority that needs to
be given is verified. In this paper risk ranking is done and
mitigation measures are suggested.
Keywords— Risk management, Road construction, Risk
Ranking, Relative Importance Index
1. INTRODUCTION
A risk may be a potential problem which might occur or
might not.
Risk contains following terms:
- Risk includes future happenings
- Risk concerns about change in mind, opinion,
actions, places, etc.
- Risk is a choice and the uncertainty that choice
entails.
Whereas risk management can be defined on the following
terms:
- Identify possible risks; recognize things which can
go wrong.
- Asses each risks on the basis of probability of its
occurrence and its impact.
- Rank the risks by probability and impact, Impact
may be very low, moderate and very high.
- Initiate a mitigation plan to manage those risks
having high impact and high probability.
As a developing nation our country is building a huge
network of roads all over the country for the better
transportation which will help in growth of manufacturing
industry indirectly creating more jobs and development of
Indian economy. For a better road network it should be
kept in mind that there will be very complex uncertainties
lying at each and every stage. Road construction has
number of activities which are beyond our control. There
are various ways to find the uncertainties and their
probabilities in order to mitigate the risks involved in the
construction process. There are several different tools and
techniques which have already been developed. However,
there is a gap between risk management techniques and
their practical application by contractor.
In our country there is a need to study the risks which
occur consistently and need a plan to counter attack. First
of all it is needed to prioritize the risks to mitigate them
effectively.
2. OBJECTIVE
Objective of the study is to identify which risk during
typical phases of the construction are needed to give an
importance and start mitigation practices immediately to
reduce its severity. The main objectives of this research is
to rank out the identified common Risks at various stages
of Road Construction Projects in Maharashtra state of
INDIA, as well as to study the preventive and remedial
steps to avoid or to minimize the number of Risks in Road
construction and mitigation measures also to save the time
and cost.
3. Data Collection
Risk involved at every stage is recognized in terms of
problem statement or hazard. Risks were studied and
observed on the basis of literature review and
questionnaires which were distributed in the n number of
field experts. A criterion for respondents was of minimum
10 years of experience. In all the questionnaires were
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 07 Issue: 03 | Mar 2020 www.irjet.net p-ISSN: 2395-0072
© 2020, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 2991
distributed to 120 field experts, out of which 90
questionnaires were received.
3.1 Expert opinion
While distributing the questionnaires, stakeholders were
projected. All the stakeholders from contractor, site
engineer, project manager and owner were taken into
consideration. Questionnaire was formulated on 5-point
Likert scale from 1 to 5 ratings representing as Very Low,
Low, Moderate, High and Very High respectively.
3.2 Types of Respondents:
From the total experts 10% of respondents were owners,
20% project managers, 10% senior site engineers, 15%
junior site engineers, 25% contractors, 10 % supervisors,
10% teaching individuals.
3.3 Experience of Field Experts:
Among the total respondents 40% of the respondents have
10 to 20 years of experience, 20% of respondents have 7 to
10 years of experience, 30 % of respondents have 5 to 7
years of experience and 10 % of respondents have below 5
years of experience.
4. Data Analysis:
For the ranking of risks two methods Relative Importance
Index and Geometric mean Method was used. The details of
these methods are as follows:
4.1 Relative Importance Index
Also for Comparison Relative Importance Index (RII) by
following formula, was also adopted.
∑
Where,
w: Weighting given to each factor by respondents and its
ranges from 1-5
x: Frequency of the response given by each individual
A: Highest weight (i.e. 5 here)
N: Total no. of respondents
Suppose impact value given by 3 respondents were 5, 5
respondents gave value of 2 and 2 repondents gave value of
4 on a 1-5 point likert scale. The RII will be
RII = 0.66
4.2 Geometric Mean-AHP
The geometric mean of a data set {x1, x2… xn} is given by:
GM = √ or (x1.x2….xn)(1/n)
For example, in a set of four numbers {1, 2, 3, 4},
the product of 1 X 2 X 3 X 4 is 24, and the geometric mean
is the fourth root of 24, or 2.213. The exponent on the left
side is equivalent to the taking nth root.
From the calculation Ranking of the risks was given on the
basis of Geometric Mean and RII. It was observed that both
the method showed the similar ranking. This confirmed
that Ranking is done accurately. Next step is to determine
the weight of each factor. Weights are determined by
applying AHP technique. First a pair wise comparison
matrix is design. A pair wise comparison matrix, square
matrix, compares the important of one alternative over
that.
After calculating all the weights ranking was given as per
the smallest value of sum of weights.
STAGE – I : Initial stage (Concept Stage)
Risks R01 R02 R03 R04 R05
R01 1.00 0.96 0.69 0.94 0.91
R02 1.04 1.00 0.72 0.98 0.95
R03 1.45 1.39 1.00 1.37 1.32
R04 1.06 1.02 0.73 1.00 0.97
R05 1.10 1.05 0.76 1.03 1.00
∑ 5.65 5.41 3.90 5.33 5.15
Rank: 5 4 1 3 2
Table 4.1 Sample Clculations of AHP
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 07 Issue: 03 | Mar 2020 www.irjet.net p-ISSN: 2395-0072
© 2020, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 2992
5. RESULT & DISCUSSION
Sr.
No.
Description of Main Risks likely to
occur
AHP
Factor
RII
STAGE – I : Initial stage (Concept Stage)
1
Feasibility w.r.t. specific area where the
project is proposed
5.65 0.44
2
Constructability of Project concept not
in line w.r.t. Design & Engineering
capabilities in your Organization
5.41 0.46
3
Lack of Clarity about legal framework
and restriction under which Project is
to be implemented
3.90 0.66
4
Uncertainty about Political policy
changes adversely affecting the project
at the later stages of Execution
5.33 0.47
5
Rejection of proposal by concerned
authority
5.15 0.49
STAGE – II : Fund Raising and Financial Stability
6
Delay due to budget approvals from
concerned authority
3.21 0.68
7
Various permissions to be obtained
from Authorities are not clearly
identified
4.85 0.42
8 Mobilization of finance 4.18 0.50
9
Lack of clarity in specifications and cost
estimates
4.11 0.52
Sr.
No.
Description of Main
Risks likely to occur
AHP
Factor
RII
STAGE – III : Tendering and Contracting of Project
10
Non-availability of
correct details of scope of
work without any
ambiguity along with
necessary drawings
5.50 0.50
11
Properly prequalified
contractors participating
in the competitive
bidding process is not
assured
5.49 0.50
12
Availability of
Professional Consultant
for Designing and Project
monitoring at Client’s
4.53 0.62
side is not established
13
Various permissions to
be obtained from
Authorities are not
clearly identified
4.06 0.72
14
The environmental
Impact Assessment is not
available or clearances to
be obtained as per
provisions of the Law are
not made clear
5.92 0.46
STAGE – IV : Project Planning
15
Site is not made available
to contractor with
suitable access without
encumbrances
5.22 0.46
16
Basic layout designs are
not available and
detailed drawing is not
approved in time
4.13 0.55
17
Government’s decision
on technical issues not
available in time
5.91 0.44
18
Mechanism for Dispute
settlement in case of
claims is not clearly
established
5.44 0.46
19
Time constraint for
project is not fixed
initially & varies
according to government
policies
4.70 0.52
Sr.
No.
Description of Main
Risks likely to occur
AHP
Factor
RII
STAGE – V : Contract
Execution, Monitoring
and Control
20
Construction
equipment
maintenance issues
5.06 0.57
21
Land acquisition
necessary for Project is
not complete or not
available
4.90 0.60
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 07 Issue: 03 | Mar 2020 www.irjet.net p-ISSN: 2395-0072
© 2020, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 2993
22
Changes in client’s design
are not clear and
matching, cost and time
changes are not agreed
4.98 0.58
23
Suspension of Work due
to reasons under Client’s
control is not properly
understood
5.62 0.51
24
Lack of safety precautions
resulting into serious
accidents
4.55 0.66
STAGE – VI : Finishing
Work and Closure of
Project
25
Non Settlement dispute
about reasons of delays
and time extension
needed to complete the
project
6.24 0.60
26
Delays in settlement of
pending claims and
contract closer with final
payments.
6.27 0.59
27
Support of local and state
level bodies in smooth
functioning of the
infrastructure assets, is
not available
6.25 0.59
28
Support of law and order
authority for the
maintaining peace and
smooth working is not
provided
6.66 0.56
29
Cost overruns of
maintenance expenses
reducing the income
margins for the
contractor
6.21 0.62
30 Delay in payment 4.79 0.80
6. MITIGATION MEASURES
All the risks in the respective Life Cycle Phases are
ranked as per the weights and further used for
providing mitigation measures.
Stage of
Project Life
Cycle
Risk
Description
Recommendations
as Mitigation
Measures
STAGE – I
: Initial
stage
(Concept
Stage)
Lack of
Clarity
about legal
framework
and
restriction
under
which
Project is to
be
implemente
d.
To provide an
enabling legal &
statutory
framework.
Provide consent
when required
for significant
legal or
regulatory
decisions. The
tender
documents
should be spcific
by the
government and
documents
should be made
available to
various
implementing
agencies for use.
Maintain
perception of
current and
emerging laws,
and regulations
affecting project
to assess their
impact on the
organization’s
business.
STAGE –
II : Fund
Raising
and
Financial
Stability
Delay due
to budget
approvals
from
concerned
authority
Detailed
estimation and
secured sources
of financing
should be made
available. Clear
indications about
the amount of
expenditure with
financial
constraints
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 07 Issue: 03 | Mar 2020 www.irjet.net p-ISSN: 2395-0072
© 2020, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 2994
should be given
to spending
agencies at the
start of the
budget
preparation
process. A
“fundamental
program” within
the budget
should be
arranged and
higher priority
given to this
program during
budget
execution.
STAGE –
III :
Tenderin
g and
Contracti
ng of
Project
Various
permissions
to be
obtained
from
Authorities
are not
clearly
identified
It is must to have
a management
collabrations in
place to deal
with the Tender
Process, thus
ensuring the
legitimacy are
studied and that
possesion of the
process is
assigned.
STAGE –
IV :
Project
Planning
Basic layout
designs are
not
available
and
detailed
drawing is
not
approved in
time
Designated
consultancies
should be hired
for the specific
work of making
designs and
drawings of
pavement.
Authorities
regarding timely
approval should
be audited on
fixed time
intervals. Online
approvals should
be made
mandatory to
keep this in a
legal framework
to eliminate
issues like
corruption from
the system.
STAGE –
V :
Contract
Executio
n,
Monitori
ng and
Control
Lack of
safety
precautions
resulting
into serious
accidents
Safety of workers
and officials
working on the
project should be
given high
priority so as to
boost their
confidence. This
will ensure them
with secure
working
environment and
will also increase
their work
efficiency.
Recognition
Initiative about
"The Minimum
Wages Act,
1948", "The
Building and
Other
Constructions
Workers’
(Regulation of
Employment and
Conditions of
Service) Act,
1996" Should be
conducted.
STAGE –
VI :
Finishing
Work
and
Closure
of
Delay in
payment.
Have necessary
clauses in
contract for
compensation.
Agree payment
terms in advance
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 07 Issue: 03 | Mar 2020 www.irjet.net p-ISSN: 2395-0072
© 2020, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 2995
Project to control cash
flow
management at
the source.
Invoicing
correctly &
promptly.
Chasing payment
immediately
when it becomes
overdue.
Create incentive
for prompt
payment.
Assess accrued
interest charges
beginning on the
first day the
payment
becomes late.
Make sure this
policy is clearly
stated in
contract.
CONCLUSIONS
The research was carried out throughout the life cycle of the
project and hence it included all types of risks that can be
encountered in the whole life of project. All the risks in all
the stages were given points based on the expert’s views
and with the help of these the criticality of the risks were
found out. This will help to concentrate on specific risks at
proper stages. Then the various ways were found out to
mitigate these risks which will help to take the appropriate
measures so as to avoid the losses.
As per the findings and inferences arrived at as indicated
above, further analysis and verification can be carried out
with the help of qualitative as well as quantitative
assessment. With the help of quantitative assessment, the
cost impact of each of the risks can be found out. And after
adopting the above mitigation measures, its effect on the
cost impact can be found out.
ACKNOWLEDGEMENT
I am truly grateful to my guide Prof. Shruti wadalkar
Madam, Department of Civil Engineering, that she believed
in this research and she have my most sincere appreciation
for her valuable time, sustained guidance and useful
suggestions, which helped me in completing the work, in
time, Also would like to express thanks to past researchers
for the successful completion of this work.
REFERENCES
1] Mr. N. V. Patil, Dr. P. G. Gaikwad (July 2015) “Risk
Management In Road Construction” International Journal of
Modern Trends in Engineering and Reaserch; e-ISSN
No.:2349-9745
2] Katkar M.B., Dr.Khandekar S.D (June 2015) ”Study of risk
management for National Highway Project” International
Research Journal of Engineering and Technology (IRJET)e-
ISSN: 2395 -0056
3] Rinaj Pathan, Prof. Dr. S. S. Pimplikar (Feb 2013) “Risk
Assessment of BOT Road Projects” IOSR Journal of
Mechanical and Civil Engineering (IOSR-JMCE) e-ISSN:
2278-1684Volume 5, Issue 3), PP 40-59
4] SatishKamane, SandipMahadik.(2014), “Risk
Management in Construction Industry”, IOSR Journal of
Mechanical and Civil Engineering (IOSR-JMCE) ISSN: 2278-
1684, PP: 59-65.
5] KinnareshPatel(2013), “A study on risk assessment and
its management in India”, American Journal of Civil
Engineering, doi: 10.11648/j.ajce.20130102.13.
6] Patel AnkitMahendra, Jayeshkumar R. Pitroda, J. J.
Bhavsar (October 2013) “A Study of Risk Management
Techniques for Construction Projects in Developing
Countries”International Journal of Innovative Technology
and Exploring Engineering (IJITEE) ISSN: 2278-3075,
Volume-3, Issue-5, October 2013
7] Sharmila Mane, Dr. S.S.Pimplikar (August 2013). “Risk
Assessment of BOT Projects”. International Journal of
Computational Engineering Research||Vol, 03||Issue, 8||

Más contenido relacionado

La actualidad más candente

Construction Site Monitoring and Predictive Analysis Using Artificial Neural ...
Construction Site Monitoring and Predictive Analysis Using Artificial Neural ...Construction Site Monitoring and Predictive Analysis Using Artificial Neural ...
Construction Site Monitoring and Predictive Analysis Using Artificial Neural ...IJSRED
 
IRJET - A Study on Identification of Risks at Various Phases of Road Construc...
IRJET - A Study on Identification of Risks at Various Phases of Road Construc...IRJET - A Study on Identification of Risks at Various Phases of Road Construc...
IRJET - A Study on Identification of Risks at Various Phases of Road Construc...IRJET Journal
 
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...IRJET Journal
 
A Study on Risk Assessment in Construction Projects
A Study on Risk Assessment in Construction ProjectsA Study on Risk Assessment in Construction Projects
A Study on Risk Assessment in Construction ProjectsIJMER
 
Risk Management in High Rise Construction Projects: A Review
Risk Management in High Rise Construction Projects: A ReviewRisk Management in High Rise Construction Projects: A Review
Risk Management in High Rise Construction Projects: A ReviewA Makwana
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentIJERD Editor
 
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTSEFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTSvivatechijri
 
Establishing risk management factors for construction projects in iraq
Establishing risk management factors for construction projects in iraqEstablishing risk management factors for construction projects in iraq
Establishing risk management factors for construction projects in iraqIAEME Publication
 
RISK LEVEL ASSESSMENT ON ROAD CONSTRUCTION’S CONTRACTORS USING CULTURAL – PRO...
RISK LEVEL ASSESSMENT ON ROAD CONSTRUCTION’S CONTRACTORS USING CULTURAL – PRO...RISK LEVEL ASSESSMENT ON ROAD CONSTRUCTION’S CONTRACTORS USING CULTURAL – PRO...
RISK LEVEL ASSESSMENT ON ROAD CONSTRUCTION’S CONTRACTORS USING CULTURAL – PRO...IAEME Publication
 
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...IRJET Journal
 
Critical Factors Influencing to Management Risk in Construction Projects
Critical Factors Influencing to Management Risk in Construction ProjectsCritical Factors Influencing to Management Risk in Construction Projects
Critical Factors Influencing to Management Risk in Construction Projectstheijes
 
Study and Need of Risk Management for Construction Projects
Study and Need of Risk Management for Construction ProjectsStudy and Need of Risk Management for Construction Projects
Study and Need of Risk Management for Construction ProjectsIRJET Journal
 
2.11 risk management 1
2.11 risk management 12.11 risk management 1
2.11 risk management 1reddvise
 
Risk Severity Framework for a BOT Highway Project
Risk Severity Framework for a BOT Highway ProjectRisk Severity Framework for a BOT Highway Project
Risk Severity Framework for a BOT Highway ProjectIOSRJMCE
 
The Identification of Risks and its Criticality in the Nigeria Construction I...
The Identification of Risks and its Criticality in the Nigeria Construction I...The Identification of Risks and its Criticality in the Nigeria Construction I...
The Identification of Risks and its Criticality in the Nigeria Construction I...Dr. Amarjeet Singh
 
Ijirt100070 paper
Ijirt100070 paperIjirt100070 paper
Ijirt100070 paperMolay Reja
 
risk management: a better approach
risk management: a better approachrisk management: a better approach
risk management: a better approachMadhumanti Samaddar
 
Software Project Risk Management Practice in Oman
Software Project Risk Management Practice in OmanSoftware Project Risk Management Practice in Oman
Software Project Risk Management Practice in OmanEECJOURNAL
 

La actualidad más candente (20)

Construction Site Monitoring and Predictive Analysis Using Artificial Neural ...
Construction Site Monitoring and Predictive Analysis Using Artificial Neural ...Construction Site Monitoring and Predictive Analysis Using Artificial Neural ...
Construction Site Monitoring and Predictive Analysis Using Artificial Neural ...
 
IRJET - A Study on Identification of Risks at Various Phases of Road Construc...
IRJET - A Study on Identification of Risks at Various Phases of Road Construc...IRJET - A Study on Identification of Risks at Various Phases of Road Construc...
IRJET - A Study on Identification of Risks at Various Phases of Road Construc...
 
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...
 
A Study on Risk Assessment in Construction Projects
A Study on Risk Assessment in Construction ProjectsA Study on Risk Assessment in Construction Projects
A Study on Risk Assessment in Construction Projects
 
Risk Management in High Rise Construction Projects: A Review
Risk Management in High Rise Construction Projects: A ReviewRisk Management in High Rise Construction Projects: A Review
Risk Management in High Rise Construction Projects: A Review
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
 
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTSEFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
 
Establishing risk management factors for construction projects in iraq
Establishing risk management factors for construction projects in iraqEstablishing risk management factors for construction projects in iraq
Establishing risk management factors for construction projects in iraq
 
RISK LEVEL ASSESSMENT ON ROAD CONSTRUCTION’S CONTRACTORS USING CULTURAL – PRO...
RISK LEVEL ASSESSMENT ON ROAD CONSTRUCTION’S CONTRACTORS USING CULTURAL – PRO...RISK LEVEL ASSESSMENT ON ROAD CONSTRUCTION’S CONTRACTORS USING CULTURAL – PRO...
RISK LEVEL ASSESSMENT ON ROAD CONSTRUCTION’S CONTRACTORS USING CULTURAL – PRO...
 
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
 
Project risk management
Project risk managementProject risk management
Project risk management
 
QUALITATIVE RISK ASSESSMENT AND MITIGATION MEASURES FOR REAL ESTATE PROJECTS ...
QUALITATIVE RISK ASSESSMENT AND MITIGATION MEASURES FOR REAL ESTATE PROJECTS ...QUALITATIVE RISK ASSESSMENT AND MITIGATION MEASURES FOR REAL ESTATE PROJECTS ...
QUALITATIVE RISK ASSESSMENT AND MITIGATION MEASURES FOR REAL ESTATE PROJECTS ...
 
Critical Factors Influencing to Management Risk in Construction Projects
Critical Factors Influencing to Management Risk in Construction ProjectsCritical Factors Influencing to Management Risk in Construction Projects
Critical Factors Influencing to Management Risk in Construction Projects
 
Study and Need of Risk Management for Construction Projects
Study and Need of Risk Management for Construction ProjectsStudy and Need of Risk Management for Construction Projects
Study and Need of Risk Management for Construction Projects
 
2.11 risk management 1
2.11 risk management 12.11 risk management 1
2.11 risk management 1
 
Risk Severity Framework for a BOT Highway Project
Risk Severity Framework for a BOT Highway ProjectRisk Severity Framework for a BOT Highway Project
Risk Severity Framework for a BOT Highway Project
 
The Identification of Risks and its Criticality in the Nigeria Construction I...
The Identification of Risks and its Criticality in the Nigeria Construction I...The Identification of Risks and its Criticality in the Nigeria Construction I...
The Identification of Risks and its Criticality in the Nigeria Construction I...
 
Ijirt100070 paper
Ijirt100070 paperIjirt100070 paper
Ijirt100070 paper
 
risk management: a better approach
risk management: a better approachrisk management: a better approach
risk management: a better approach
 
Software Project Risk Management Practice in Oman
Software Project Risk Management Practice in OmanSoftware Project Risk Management Practice in Oman
Software Project Risk Management Practice in Oman
 

Similar a IRJET - A Study on Identification of Risks at Various Phases of Road Construction

Risk Management Appraisal - A tool for successful Infrastructure project
Risk Management Appraisal - A tool for successful Infrastructure projectRisk Management Appraisal - A tool for successful Infrastructure project
Risk Management Appraisal - A tool for successful Infrastructure projectIRJET Journal
 
IRJET-Qualitative Risk Analysis for Construction Projects
IRJET-Qualitative Risk Analysis for Construction ProjectsIRJET-Qualitative Risk Analysis for Construction Projects
IRJET-Qualitative Risk Analysis for Construction ProjectsIRJET Journal
 
Risk Management In High Rise Construction Projects
Risk Management In High Rise Construction ProjectsRisk Management In High Rise Construction Projects
Risk Management In High Rise Construction ProjectsIRJET Journal
 
Risk Management Methodologies in Construction Industries
Risk Management Methodologies in Construction IndustriesRisk Management Methodologies in Construction Industries
Risk Management Methodologies in Construction IndustriesIRJET Journal
 
Episode 25 : Project Risk Management
Episode 25 :  Project Risk ManagementEpisode 25 :  Project Risk Management
Episode 25 : Project Risk ManagementSAJJAD KHUDHUR ABBAS
 
IRJET- Risk Management using Primavera Software for Residential Sector
IRJET-  	  Risk Management using Primavera Software for Residential SectorIRJET-  	  Risk Management using Primavera Software for Residential Sector
IRJET- Risk Management using Primavera Software for Residential SectorIRJET Journal
 
IRJET- Improving Labour Productivity in Construction Industries
IRJET- Improving Labour Productivity in Construction IndustriesIRJET- Improving Labour Productivity in Construction Industries
IRJET- Improving Labour Productivity in Construction IndustriesIRJET Journal
 
A Qualitative approach for analysing Causes and Effects of Construction Risks
A Qualitative approach for analysing Causes and Effects of Construction RisksA Qualitative approach for analysing Causes and Effects of Construction Risks
A Qualitative approach for analysing Causes and Effects of Construction RisksIRJET Journal
 
IRJET - Risk Allocation in Public Private Partnership Projects in Kerala
IRJET - Risk Allocation in Public Private Partnership Projects in KeralaIRJET - Risk Allocation in Public Private Partnership Projects in Kerala
IRJET - Risk Allocation in Public Private Partnership Projects in KeralaIRJET Journal
 
Risk management plan
Risk management planRisk management plan
Risk management planKashif Mastan
 
13 chapter 4
13 chapter 413 chapter 4
13 chapter 4Ubah Esse
 
IRJET- Study and Analysis of Risk Management Strategies in Construction P...
IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...
IRJET- Study and Analysis of Risk Management Strategies in Construction P...IRJET Journal
 
Risk and Its Management in the Kuwait Construction Industry |2020
Risk and Its Management in the Kuwait Construction Industry |2020 Risk and Its Management in the Kuwait Construction Industry |2020
Risk and Its Management in the Kuwait Construction Industry |2020 Taju Abdulaziz
 
For Ch -6 == Risk Monitoring & Controlling.pptx
For Ch -6 == Risk Monitoring & Controlling.pptxFor Ch -6 == Risk Monitoring & Controlling.pptx
For Ch -6 == Risk Monitoring & Controlling.pptxAbhinavRJ1
 
Road User Attitudes towards Safety Initiatives in Kuwait
Road User Attitudes towards Safety Initiatives in KuwaitRoad User Attitudes towards Safety Initiatives in Kuwait
Road User Attitudes towards Safety Initiatives in KuwaitIJMER
 
IRJET- Risk Management in Construction: A Literature Review
IRJET- Risk Management in Construction: A Literature ReviewIRJET- Risk Management in Construction: A Literature Review
IRJET- Risk Management in Construction: A Literature ReviewIRJET Journal
 
IRJET- A Review Paper on Risk Management using Primavera for Residential ...
IRJET-  	  A Review Paper on Risk Management using Primavera for Residential ...IRJET-  	  A Review Paper on Risk Management using Primavera for Residential ...
IRJET- A Review Paper on Risk Management using Primavera for Residential ...IRJET Journal
 
PRMG195 - Rsik Management Case Study.pdf
PRMG195 - Rsik Management Case Study.pdfPRMG195 - Rsik Management Case Study.pdf
PRMG195 - Rsik Management Case Study.pdfmohamed Ismail
 
Risk Management in Railway Projects
Risk Management in Railway ProjectsRisk Management in Railway Projects
Risk Management in Railway ProjectsIRJET Journal
 

Similar a IRJET - A Study on Identification of Risks at Various Phases of Road Construction (20)

Risk Management Appraisal - A tool for successful Infrastructure project
Risk Management Appraisal - A tool for successful Infrastructure projectRisk Management Appraisal - A tool for successful Infrastructure project
Risk Management Appraisal - A tool for successful Infrastructure project
 
IRJET-Qualitative Risk Analysis for Construction Projects
IRJET-Qualitative Risk Analysis for Construction ProjectsIRJET-Qualitative Risk Analysis for Construction Projects
IRJET-Qualitative Risk Analysis for Construction Projects
 
Risk Management In High Rise Construction Projects
Risk Management In High Rise Construction ProjectsRisk Management In High Rise Construction Projects
Risk Management In High Rise Construction Projects
 
Risk Management Methodologies in Construction Industries
Risk Management Methodologies in Construction IndustriesRisk Management Methodologies in Construction Industries
Risk Management Methodologies in Construction Industries
 
Episode 25 : Project Risk Management
Episode 25 :  Project Risk ManagementEpisode 25 :  Project Risk Management
Episode 25 : Project Risk Management
 
IRJET- Risk Management using Primavera Software for Residential Sector
IRJET-  	  Risk Management using Primavera Software for Residential SectorIRJET-  	  Risk Management using Primavera Software for Residential Sector
IRJET- Risk Management using Primavera Software for Residential Sector
 
IRJET- Improving Labour Productivity in Construction Industries
IRJET- Improving Labour Productivity in Construction IndustriesIRJET- Improving Labour Productivity in Construction Industries
IRJET- Improving Labour Productivity in Construction Industries
 
A Qualitative approach for analysing Causes and Effects of Construction Risks
A Qualitative approach for analysing Causes and Effects of Construction RisksA Qualitative approach for analysing Causes and Effects of Construction Risks
A Qualitative approach for analysing Causes and Effects of Construction Risks
 
IRJET - Risk Allocation in Public Private Partnership Projects in Kerala
IRJET - Risk Allocation in Public Private Partnership Projects in KeralaIRJET - Risk Allocation in Public Private Partnership Projects in Kerala
IRJET - Risk Allocation in Public Private Partnership Projects in Kerala
 
Risk management plan
Risk management planRisk management plan
Risk management plan
 
13 chapter 4
13 chapter 413 chapter 4
13 chapter 4
 
IJET-V2I6P23
IJET-V2I6P23IJET-V2I6P23
IJET-V2I6P23
 
IRJET- Study and Analysis of Risk Management Strategies in Construction P...
IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...
IRJET- Study and Analysis of Risk Management Strategies in Construction P...
 
Risk and Its Management in the Kuwait Construction Industry |2020
Risk and Its Management in the Kuwait Construction Industry |2020 Risk and Its Management in the Kuwait Construction Industry |2020
Risk and Its Management in the Kuwait Construction Industry |2020
 
For Ch -6 == Risk Monitoring & Controlling.pptx
For Ch -6 == Risk Monitoring & Controlling.pptxFor Ch -6 == Risk Monitoring & Controlling.pptx
For Ch -6 == Risk Monitoring & Controlling.pptx
 
Road User Attitudes towards Safety Initiatives in Kuwait
Road User Attitudes towards Safety Initiatives in KuwaitRoad User Attitudes towards Safety Initiatives in Kuwait
Road User Attitudes towards Safety Initiatives in Kuwait
 
IRJET- Risk Management in Construction: A Literature Review
IRJET- Risk Management in Construction: A Literature ReviewIRJET- Risk Management in Construction: A Literature Review
IRJET- Risk Management in Construction: A Literature Review
 
IRJET- A Review Paper on Risk Management using Primavera for Residential ...
IRJET-  	  A Review Paper on Risk Management using Primavera for Residential ...IRJET-  	  A Review Paper on Risk Management using Primavera for Residential ...
IRJET- A Review Paper on Risk Management using Primavera for Residential ...
 
PRMG195 - Rsik Management Case Study.pdf
PRMG195 - Rsik Management Case Study.pdfPRMG195 - Rsik Management Case Study.pdf
PRMG195 - Rsik Management Case Study.pdf
 
Risk Management in Railway Projects
Risk Management in Railway ProjectsRisk Management in Railway Projects
Risk Management in Railway Projects
 

Más de IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

Más de IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Último

VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdfSuman Jyoti
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756dollysharma2066
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Arindam Chakraborty, Ph.D., P.E. (CA, TX)
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptMsecMca
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringmulugeta48
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfRagavanV2
 

Último (20)

VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdf
 

IRJET - A Study on Identification of Risks at Various Phases of Road Construction

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 07 Issue: 03 | Mar 2020 www.irjet.net p-ISSN: 2395-0072 © 2020, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 2990 A Study on Identification of Risks at Various Phases of Road Construction Vishal Shelar1, Asst. Prof Shruti Wadalkar2 1PG student, Dept. of Civil Engineering, Dr. D.Y Patil Institute of Technology, Pune, MH, India 2Asst. Professor, Dept. of Civil Engineering, Dr.D.Y Patil Institute of Technology, Pune, MH, India ---------------------------------------------------------------------------------***------------------------------------------------------------------------------- Abstract— Risk is nothing but the difficulties occurring in the completion of the project in such a way that causes delay of the project, increase in the cost of project, quality of the work etc. For a road construction projects it is very important to mitigate the risks for the completion of the project without any failure. In order to mitigate the risk factors we have to first identify the risk which are causing a greater impact and then take the steps to overcome the losses caused by them. It is important to rank the risks which will give us priority of the risk mitigation program. To do the ranking one needs to do it logically by methods such as various indices, Analytical Hierarchy Processes, fuzzy logics etc. Better way is to do it by different methods and check if the result occurred is relatively same or not, if it’s same then ranking or priority that needs to be given is verified. In this paper risk ranking is done and mitigation measures are suggested. Keywords— Risk management, Road construction, Risk Ranking, Relative Importance Index 1. INTRODUCTION A risk may be a potential problem which might occur or might not. Risk contains following terms: - Risk includes future happenings - Risk concerns about change in mind, opinion, actions, places, etc. - Risk is a choice and the uncertainty that choice entails. Whereas risk management can be defined on the following terms: - Identify possible risks; recognize things which can go wrong. - Asses each risks on the basis of probability of its occurrence and its impact. - Rank the risks by probability and impact, Impact may be very low, moderate and very high. - Initiate a mitigation plan to manage those risks having high impact and high probability. As a developing nation our country is building a huge network of roads all over the country for the better transportation which will help in growth of manufacturing industry indirectly creating more jobs and development of Indian economy. For a better road network it should be kept in mind that there will be very complex uncertainties lying at each and every stage. Road construction has number of activities which are beyond our control. There are various ways to find the uncertainties and their probabilities in order to mitigate the risks involved in the construction process. There are several different tools and techniques which have already been developed. However, there is a gap between risk management techniques and their practical application by contractor. In our country there is a need to study the risks which occur consistently and need a plan to counter attack. First of all it is needed to prioritize the risks to mitigate them effectively. 2. OBJECTIVE Objective of the study is to identify which risk during typical phases of the construction are needed to give an importance and start mitigation practices immediately to reduce its severity. The main objectives of this research is to rank out the identified common Risks at various stages of Road Construction Projects in Maharashtra state of INDIA, as well as to study the preventive and remedial steps to avoid or to minimize the number of Risks in Road construction and mitigation measures also to save the time and cost. 3. Data Collection Risk involved at every stage is recognized in terms of problem statement or hazard. Risks were studied and observed on the basis of literature review and questionnaires which were distributed in the n number of field experts. A criterion for respondents was of minimum 10 years of experience. In all the questionnaires were
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 07 Issue: 03 | Mar 2020 www.irjet.net p-ISSN: 2395-0072 © 2020, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 2991 distributed to 120 field experts, out of which 90 questionnaires were received. 3.1 Expert opinion While distributing the questionnaires, stakeholders were projected. All the stakeholders from contractor, site engineer, project manager and owner were taken into consideration. Questionnaire was formulated on 5-point Likert scale from 1 to 5 ratings representing as Very Low, Low, Moderate, High and Very High respectively. 3.2 Types of Respondents: From the total experts 10% of respondents were owners, 20% project managers, 10% senior site engineers, 15% junior site engineers, 25% contractors, 10 % supervisors, 10% teaching individuals. 3.3 Experience of Field Experts: Among the total respondents 40% of the respondents have 10 to 20 years of experience, 20% of respondents have 7 to 10 years of experience, 30 % of respondents have 5 to 7 years of experience and 10 % of respondents have below 5 years of experience. 4. Data Analysis: For the ranking of risks two methods Relative Importance Index and Geometric mean Method was used. The details of these methods are as follows: 4.1 Relative Importance Index Also for Comparison Relative Importance Index (RII) by following formula, was also adopted. ∑ Where, w: Weighting given to each factor by respondents and its ranges from 1-5 x: Frequency of the response given by each individual A: Highest weight (i.e. 5 here) N: Total no. of respondents Suppose impact value given by 3 respondents were 5, 5 respondents gave value of 2 and 2 repondents gave value of 4 on a 1-5 point likert scale. The RII will be RII = 0.66 4.2 Geometric Mean-AHP The geometric mean of a data set {x1, x2… xn} is given by: GM = √ or (x1.x2….xn)(1/n) For example, in a set of four numbers {1, 2, 3, 4}, the product of 1 X 2 X 3 X 4 is 24, and the geometric mean is the fourth root of 24, or 2.213. The exponent on the left side is equivalent to the taking nth root. From the calculation Ranking of the risks was given on the basis of Geometric Mean and RII. It was observed that both the method showed the similar ranking. This confirmed that Ranking is done accurately. Next step is to determine the weight of each factor. Weights are determined by applying AHP technique. First a pair wise comparison matrix is design. A pair wise comparison matrix, square matrix, compares the important of one alternative over that. After calculating all the weights ranking was given as per the smallest value of sum of weights. STAGE – I : Initial stage (Concept Stage) Risks R01 R02 R03 R04 R05 R01 1.00 0.96 0.69 0.94 0.91 R02 1.04 1.00 0.72 0.98 0.95 R03 1.45 1.39 1.00 1.37 1.32 R04 1.06 1.02 0.73 1.00 0.97 R05 1.10 1.05 0.76 1.03 1.00 ∑ 5.65 5.41 3.90 5.33 5.15 Rank: 5 4 1 3 2 Table 4.1 Sample Clculations of AHP
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 07 Issue: 03 | Mar 2020 www.irjet.net p-ISSN: 2395-0072 © 2020, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 2992 5. RESULT & DISCUSSION Sr. No. Description of Main Risks likely to occur AHP Factor RII STAGE – I : Initial stage (Concept Stage) 1 Feasibility w.r.t. specific area where the project is proposed 5.65 0.44 2 Constructability of Project concept not in line w.r.t. Design & Engineering capabilities in your Organization 5.41 0.46 3 Lack of Clarity about legal framework and restriction under which Project is to be implemented 3.90 0.66 4 Uncertainty about Political policy changes adversely affecting the project at the later stages of Execution 5.33 0.47 5 Rejection of proposal by concerned authority 5.15 0.49 STAGE – II : Fund Raising and Financial Stability 6 Delay due to budget approvals from concerned authority 3.21 0.68 7 Various permissions to be obtained from Authorities are not clearly identified 4.85 0.42 8 Mobilization of finance 4.18 0.50 9 Lack of clarity in specifications and cost estimates 4.11 0.52 Sr. No. Description of Main Risks likely to occur AHP Factor RII STAGE – III : Tendering and Contracting of Project 10 Non-availability of correct details of scope of work without any ambiguity along with necessary drawings 5.50 0.50 11 Properly prequalified contractors participating in the competitive bidding process is not assured 5.49 0.50 12 Availability of Professional Consultant for Designing and Project monitoring at Client’s 4.53 0.62 side is not established 13 Various permissions to be obtained from Authorities are not clearly identified 4.06 0.72 14 The environmental Impact Assessment is not available or clearances to be obtained as per provisions of the Law are not made clear 5.92 0.46 STAGE – IV : Project Planning 15 Site is not made available to contractor with suitable access without encumbrances 5.22 0.46 16 Basic layout designs are not available and detailed drawing is not approved in time 4.13 0.55 17 Government’s decision on technical issues not available in time 5.91 0.44 18 Mechanism for Dispute settlement in case of claims is not clearly established 5.44 0.46 19 Time constraint for project is not fixed initially & varies according to government policies 4.70 0.52 Sr. No. Description of Main Risks likely to occur AHP Factor RII STAGE – V : Contract Execution, Monitoring and Control 20 Construction equipment maintenance issues 5.06 0.57 21 Land acquisition necessary for Project is not complete or not available 4.90 0.60
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 07 Issue: 03 | Mar 2020 www.irjet.net p-ISSN: 2395-0072 © 2020, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 2993 22 Changes in client’s design are not clear and matching, cost and time changes are not agreed 4.98 0.58 23 Suspension of Work due to reasons under Client’s control is not properly understood 5.62 0.51 24 Lack of safety precautions resulting into serious accidents 4.55 0.66 STAGE – VI : Finishing Work and Closure of Project 25 Non Settlement dispute about reasons of delays and time extension needed to complete the project 6.24 0.60 26 Delays in settlement of pending claims and contract closer with final payments. 6.27 0.59 27 Support of local and state level bodies in smooth functioning of the infrastructure assets, is not available 6.25 0.59 28 Support of law and order authority for the maintaining peace and smooth working is not provided 6.66 0.56 29 Cost overruns of maintenance expenses reducing the income margins for the contractor 6.21 0.62 30 Delay in payment 4.79 0.80 6. MITIGATION MEASURES All the risks in the respective Life Cycle Phases are ranked as per the weights and further used for providing mitigation measures. Stage of Project Life Cycle Risk Description Recommendations as Mitigation Measures STAGE – I : Initial stage (Concept Stage) Lack of Clarity about legal framework and restriction under which Project is to be implemente d. To provide an enabling legal & statutory framework. Provide consent when required for significant legal or regulatory decisions. The tender documents should be spcific by the government and documents should be made available to various implementing agencies for use. Maintain perception of current and emerging laws, and regulations affecting project to assess their impact on the organization’s business. STAGE – II : Fund Raising and Financial Stability Delay due to budget approvals from concerned authority Detailed estimation and secured sources of financing should be made available. Clear indications about the amount of expenditure with financial constraints
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 07 Issue: 03 | Mar 2020 www.irjet.net p-ISSN: 2395-0072 © 2020, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 2994 should be given to spending agencies at the start of the budget preparation process. A “fundamental program” within the budget should be arranged and higher priority given to this program during budget execution. STAGE – III : Tenderin g and Contracti ng of Project Various permissions to be obtained from Authorities are not clearly identified It is must to have a management collabrations in place to deal with the Tender Process, thus ensuring the legitimacy are studied and that possesion of the process is assigned. STAGE – IV : Project Planning Basic layout designs are not available and detailed drawing is not approved in time Designated consultancies should be hired for the specific work of making designs and drawings of pavement. Authorities regarding timely approval should be audited on fixed time intervals. Online approvals should be made mandatory to keep this in a legal framework to eliminate issues like corruption from the system. STAGE – V : Contract Executio n, Monitori ng and Control Lack of safety precautions resulting into serious accidents Safety of workers and officials working on the project should be given high priority so as to boost their confidence. This will ensure them with secure working environment and will also increase their work efficiency. Recognition Initiative about "The Minimum Wages Act, 1948", "The Building and Other Constructions Workers’ (Regulation of Employment and Conditions of Service) Act, 1996" Should be conducted. STAGE – VI : Finishing Work and Closure of Delay in payment. Have necessary clauses in contract for compensation. Agree payment terms in advance
  • 6. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 07 Issue: 03 | Mar 2020 www.irjet.net p-ISSN: 2395-0072 © 2020, IRJET | Impact Factor value: 7.34 | ISO 9001:2008 Certified Journal | Page 2995 Project to control cash flow management at the source. Invoicing correctly & promptly. Chasing payment immediately when it becomes overdue. Create incentive for prompt payment. Assess accrued interest charges beginning on the first day the payment becomes late. Make sure this policy is clearly stated in contract. CONCLUSIONS The research was carried out throughout the life cycle of the project and hence it included all types of risks that can be encountered in the whole life of project. All the risks in all the stages were given points based on the expert’s views and with the help of these the criticality of the risks were found out. This will help to concentrate on specific risks at proper stages. Then the various ways were found out to mitigate these risks which will help to take the appropriate measures so as to avoid the losses. As per the findings and inferences arrived at as indicated above, further analysis and verification can be carried out with the help of qualitative as well as quantitative assessment. With the help of quantitative assessment, the cost impact of each of the risks can be found out. And after adopting the above mitigation measures, its effect on the cost impact can be found out. ACKNOWLEDGEMENT I am truly grateful to my guide Prof. Shruti wadalkar Madam, Department of Civil Engineering, that she believed in this research and she have my most sincere appreciation for her valuable time, sustained guidance and useful suggestions, which helped me in completing the work, in time, Also would like to express thanks to past researchers for the successful completion of this work. REFERENCES 1] Mr. N. V. Patil, Dr. P. G. Gaikwad (July 2015) “Risk Management In Road Construction” International Journal of Modern Trends in Engineering and Reaserch; e-ISSN No.:2349-9745 2] Katkar M.B., Dr.Khandekar S.D (June 2015) ”Study of risk management for National Highway Project” International Research Journal of Engineering and Technology (IRJET)e- ISSN: 2395 -0056 3] Rinaj Pathan, Prof. Dr. S. S. Pimplikar (Feb 2013) “Risk Assessment of BOT Road Projects” IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE) e-ISSN: 2278-1684Volume 5, Issue 3), PP 40-59 4] SatishKamane, SandipMahadik.(2014), “Risk Management in Construction Industry”, IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE) ISSN: 2278- 1684, PP: 59-65. 5] KinnareshPatel(2013), “A study on risk assessment and its management in India”, American Journal of Civil Engineering, doi: 10.11648/j.ajce.20130102.13. 6] Patel AnkitMahendra, Jayeshkumar R. Pitroda, J. J. Bhavsar (October 2013) “A Study of Risk Management Techniques for Construction Projects in Developing Countries”International Journal of Innovative Technology and Exploring Engineering (IJITEE) ISSN: 2278-3075, Volume-3, Issue-5, October 2013 7] Sharmila Mane, Dr. S.S.Pimplikar (August 2013). “Risk Assessment of BOT Projects”. International Journal of Computational Engineering Research||Vol, 03||Issue, 8||