Structuring a PMO with the Help of Front-End Loading and the PMBOK® Guide

                                      Ivo M. Michalick Vasconcelos, Vale
                                         Paulo Penna de Moraes, Vale


                                                     Abstract

A thorough and effective management process is a critical success factor for any kind of project. This is even truer
in capital projects, which usually have a development phase that is critical and mandatory before the project gets
formal approval.

This paper describes the task of structuring a project management office (PMO) in the logistics projects department
(responsible for developing ports and railroads capital projects) of a large and multinational mining company. This
PMO is in charge of supporting the development phase (front-end) of capital projects of different sizes and
complexities, based on a stage-gated process inspired by the front-end loading (FEL) approach and with the help of
best practices proposed in the A Guide to the Project Management Body of Knowledge (PMBOK® Guide—Fourth
Edition).

Introduction

Capital projects, due to their size and strategic importance, tend to have a high impact on the companies that perform
them. In the context of this paper, capital projects are ones that:

     •   Provide a capacity increment in an integrated logistics chain;
     •   Require board approval for moving to the construction phase; and
     •   Have a deep impact (social and economical, direct and indirect) in the geographical area where they are
         deployed.

This paper describes the task of structuring a project management office (PMO) in the logistics projects department
(responsible for developing ports and railroads capital projects) of a large and multinational mining company. This
PMO is in charge of supporting the development phase (front-end) of capital projects of different sizes and
complexities, based on a stage gated process inspired by the front-end loading (FEL) approach and with the help of
best practices proposed in the A Guide to the Project Management Body of Knowledge (PMBOK® Guide—Fourth
Edition) (Project Management Institute [PMI], 2008).

 The PMO has the following main features:

     -   A project management methodology that matches a corporate process based on FEL and the best practices
          from the PMBOK® Guide—Fourth Edition (PMI, 2008).

     -   A project categorization system that allows tailoring the methodology to a specific project, identifying key
          deliverables and processes to be used for each type of project.

     -   An integrated risk management process that spans the overall project life cycle.

     -   A project governance system that handles project initiation and termination, project priorities, and scope
          changes.

Each feature will be presented in the following sections.




                     ©2010 Ivo M. Michalick Vasconcelos, Paulo Penna de Moraes            1
               Originally published as part of Proceedings PMI Global Congress 2010 – Milan, Italy
The Project Management Methodology

Several studies on capital projects, such as Nissen (2003), have shown that the success in implementing competitive
projects is based on four factors: project team, technology, value-improving techniques (VIPs), and FEL. Among
them, FEL is considered the most crucial factor for project success.

According to Barshop (2003), “Front-end loading (FEL) is a process by which a company translates its marketing
and technology opportunities into capital projects. The objective is to align project objectives with the business need
and to develop the most efficient process design and execution plan to achieve the project objectives” (p. 17).

         The company developed a corporate methodology based on a FEL process that divides the development
phase into three different stages (Exhibit 1).


              Initiate              Gate 1               Gate 2               Gate 3                  Start up


                         Business            Trade-off            Execution            Construction              Operation
                         Analysis            analysis             Planning




                                        Development phase
                                                                                                 Rework




                                                                                                                 Proceed




                                                                                                 Cancel



                             Exhibit 1. Capital Project Life Cycle with Gate Reviews


Each phase ends with a gate review, which works as a clear transition point, where the project, after being examined,
is either allowed to move to the next phase, return for a better definition or canceled. For each FEL stage, a set of
deliverables is defined, and in the beginning of each stage, its planning is reviewed. This process is inspired by the
“rolling wave planning” concept proposed in the PMBOK® Guide—Fourth Edition (PMI, 2008, p.46 ).

                                      The Project Categorization System
The company has a corporate process that defines a complete set of deliverables for each FEL stage, and that set is
mandatory for projects above a certain capital expenditure (CAPEX) value. However, the PMO is also in charge of
supporting projects with CAPEX below that threshold, so in order to tailor the corporate process for such projects a
categorization system has been defined. This system goes beyond the CAPEX value and onsidering questions such
as the following:

    •    Is the project Greenfield (new, undeveloped site), Brownfield (to be developed on an already developed
         site), or both?
    •    What is the level of environmental permitting required?
    •    Will the project demand fast tracking?

                     ©2010 Ivo M. Michalick Vasconcelos, Paulo Penna de Moraes            2
               Originally published as part of Proceedings PMI Global Congress 2010 – Milan, Italy
•    Will the project require land acquisition? At what level?
    •    Will the project interfere with communities or wildlife?
    •    Is this a port/railroad/ or both project?
    •    What is the perceived degree of risk for the project?

All these questions must be answered by the project team as part of the project initiation process. Based on the
answers, the project can be classified as simple, medium, large, or mega.

A mega project must adhere to all methodology requirements (including independent evaluation at the end of FEL 2
and FEL 3) and provide all deliverables, whereas a simple project demands a smaller set of deliverables, and can
have an internal evaluation at the end of each phase. For instance, for large and mega projects, a quantitative risk
analysis is a mandatory deliverable for the FEL 3 stage, and it is optional for simple and medium projects (but all
projects must perform at least a qualitative risk analysis during FEL 3).

Regardless of their category, all projects need to have an approved project development plan (PDP) before they are
authorized to proceed; all projects are monitored based on this plan, which is reviewed at the beginning of each new
stage. In addition, all projects must produce a project execution plan (PEP) at the end of FEL 3. This plan will guide
the execution of the next stage (construction).

                                The Integrated Risk Management Process
 The corporate process defines risk as the measure of the uncertainties in the assumptions adopted in the different
disciplines of a project, in view of the project’s main objectives: schedule, budget (CAPEX), and return on
investment (ROI). A risk may be a threat (negative impact on one or more objectives) or an opportunity (positive
impact on one or more objectives). Notice that the definition of risk has a strong quantitative component. At the end
of a development phase, the main project risks must have been evaluated and assigned a quantitative impact on the
schedule and the CAPEX.

The level of risk analysis detail is compatible with each FEL stage (Exhibit 2).




                           Exhibit 2. Level of Detail of Risk Analysis at Each FEL Stage

Risk Management at the FEL 1 Stage

At this stage risk, management is broken down into two stages. The first one identifies fatal flaws in the
environment, land acquisition, communities, and engineering. The second stage identifies fatal flaws in economic
analysis and tries to identify uncertainties in relevant economic variables.




                     ©2010 Ivo M. Michalick Vasconcelos, Paulo Penna de Moraes            3
               Originally published as part of Proceedings PMI Global Congress 2010 – Milan, Italy
Risk Management at the FEL 2 Stage

At the FEL 2 stage, a process is defined for supporting the selection of the best alternatives (site location,
technological process, etc.) for the project. A qualitative risk analysis follows the conclusion of the conceptual
engineering studies of all alternatives to support the decision process that will select the best alternative for the
project.

Risk Management at the FEL 3 Stage

At the FEL 3 stage, risk analysis is broken down in two main processes.

    •    Quantitative risk analysis is based on Monte Carlo simulation. It evaluates the chances of meeting the main
         project objectives, especially CAPEX and schedule. This is a two-stage process, namely:

              o     Stage 1: It comprises only risk identification in the environment, land acquisition, human
                    resources, communities, safety and security, engineering, and planning. This is usually performed
                    halfway through FEL 3.
              o     Stage 2 comprises a review of the risks identified in stage 1. It identifies risks in engineering and
                    planning, quantitative analysis, and development of a risk management plan. This is usually
                    performed closer to the end of FEL 3.

    •    Hazard and operability analysis (HazOp) is a structured technique for qualitative analysis developed in
         order to identify operational problems in project processes that can compromise or jeopardize capacity,
         productivity, and/or safety. This analysis is usually performed upon completion of engineering basic
         design.

                                        The Project Governance System

In order to be included in the portfolio of projects monitored by the PMO, a project must undergo a project
authorization process based in the initiation process group as described in the PMBOK® Guide—Fourth Edition
(PMI, 2008). The PMO manager receives a project charter proposal and submits it for internal analysis of the
engineering area. If and when the project charter is approved, a project code is created for the corresponding project
and a project manager is designated. The project manager’s first order of business is to gather a core project team
and start developing a PDP for the corresponding FEL stage upon which the project is received.

Change requests are managed based on the processes described in the Practice Standard for Project Configuration
Management (PMI, 2007) and shown in Exhibit 3.




                        ©2010 Ivo M. Michalick Vasconcelos, Paulo Penna de Moraes            4
                  Originally published as part of Proceedings PMI Global Congress 2010 – Milan, Italy
Exhibit 3. Change Control Process According to PMI (2007, p. 17)

If a project is approved to proceed after a FEL 3 gate review, it is transferred to a different structure to go to the
construction phase. Depending on the project size, a projectized structure is created for it. It is common that team
members from the development phase continue with the project during the construction phase.

Considering that at the end of FEL 3, the project moves to a different structure within the department, a formal
transfer term must be signed between the involved parties and after the FEL 3 gate review. Periodically, an
executive panel is published internally, with an executive view of the PMO portfolio and all projects main
milestones.

                                                     Conclusion
We described how a PMO focused in the development of capital projects has been structured based on existing
processes, tools, and techniques within the company. The resulting methodology adheres both to the FEL approach
and to the best practices as proposed in the PMBOK® Guide—Fourth Edition (PMI, 2008).

All this work was performed while the project pipeline was kept active, with projects entering and leaving the
portfolio. The governance system survived the bumps generated by the economical crisis of 2008–2009 (the
Brazilian PIB (Gross Domestic Product) decreased by 0.2% in 2009) (PRNewswire, 2010 ¶1) and has been very
efficient now, when the economy, at least in the mining sector, is strongly recovering.

We believe that the four features described in this paper (a project management methodology, a project
categorization system, an integrated risk management process, and a project governance system) can be
used/adapted by other organizations that handle capital projects as a starting point for implementing their own PMO
and achieving more effective results in their capital projects.

                                                     References
Barshop, P. (2003, December 22). Best practice pays off. European Chemical News 79 ( 2081), 16–17.
Nissen, R. A. (2003). VIPs: Who are they and what can they do for us? Retrieved March 10. 2010, from
         http://www.nwccc.org/upload/nissen.pdf
PRI Newswire (2010, 11 March) Brazil's GDP Down 0.2% in 2009, Demonstrating Resilience Amidst Global
         Economic Crisis Retrived from http://www.prnewswire.com/news-releases/brazils-gdp-down-02-in-2009-
         demonstrating-resilience-amidst-global-economic-crisis-87374637.html


                      ©2010 Ivo M. Michalick Vasconcelos, Paulo Penna de Moraes            5
                Originally published as part of Proceedings PMI Global Congress 2010 – Milan, Italy
Project Management Institute. (2007). Practice standard for project configuration management. Newtown Square,
         PA: Project Management Institute.
Project Management Institute. (2008). A guide to the project management body of knowledge (PMBOK® Guide) (4th
         ed.). Newtown Square, PA: Project Management Institute.




                    ©2010 Ivo M. Michalick Vasconcelos, Paulo Penna de Moraes            6
              Originally published as part of Proceedings PMI Global Congress 2010 – Milan, Italy

Más contenido relacionado

Más de Ivo M Michalick Vasconcelos, PMP, PMI-SP, CPCC

"Utilização prática de métodos de seleção e priorização de projetos alinhados...
"Utilização prática de métodos de seleção e priorização de projetos alinhados..."Utilização prática de métodos de seleção e priorização de projetos alinhados...
"Utilização prática de métodos de seleção e priorização de projetos alinhados...Ivo M Michalick Vasconcelos, PMP, PMI-SP, CPCC
 

Más de Ivo M Michalick Vasconcelos, PMP, PMI-SP, CPCC (14)

Desafios lencioni-out16
Desafios lencioni-out16Desafios lencioni-out16
Desafios lencioni-out16
 
Agilidade Emocional, competência essencial para profissionais de projetos
Agilidade Emocional, competência essencial para profissionais de projetosAgilidade Emocional, competência essencial para profissionais de projetos
Agilidade Emocional, competência essencial para profissionais de projetos
 
Leadership & Emotional Intelligence: Two Sides of the Same Coin
Leadership & Emotional Intelligence: Two Sides of the Same CoinLeadership & Emotional Intelligence: Two Sides of the Same Coin
Leadership & Emotional Intelligence: Two Sides of the Same Coin
 
Você sabe decidir?
Você sabe decidir?Você sabe decidir?
Você sabe decidir?
 
Liderança de Equipes de Projetos
Liderança de Equipes de ProjetosLiderança de Equipes de Projetos
Liderança de Equipes de Projetos
 
"Utilização prática de métodos de seleção e priorização de projetos alinhados...
"Utilização prática de métodos de seleção e priorização de projetos alinhados..."Utilização prática de métodos de seleção e priorização de projetos alinhados...
"Utilização prática de métodos de seleção e priorização de projetos alinhados...
 
O Gerenciamento de Projetos de Software Desenvolvidos à Luz das Metodologias ...
O Gerenciamento de Projetos de Software Desenvolvidos à Luz das Metodologias ...O Gerenciamento de Projetos de Software Desenvolvidos à Luz das Metodologias ...
O Gerenciamento de Projetos de Software Desenvolvidos à Luz das Metodologias ...
 
O Processo de Desenvolvimento de uma Célula Operacional do SIVAM
O Processo de Desenvolvimento de uma Célula Operacional do SIVAMO Processo de Desenvolvimento de uma Célula Operacional do SIVAM
O Processo de Desenvolvimento de uma Célula Operacional do SIVAM
 
Managing Change in Software Development Projects with a Virtual CCB
Managing Change in Software Development Projects with a Virtual CCBManaging Change in Software Development Projects with a Virtual CCB
Managing Change in Software Development Projects with a Virtual CCB
 
Aperfeiçoando o gerenciamento de projetos em uma instituição de P&D
Aperfeiçoando o gerenciamento de projetos em uma instituição de P&DAperfeiçoando o gerenciamento de projetos em uma instituição de P&D
Aperfeiçoando o gerenciamento de projetos em uma instituição de P&D
 
Gerenciamento de Tempo em Ambientes de Múltiplos Projetos
Gerenciamento de Tempo em Ambientes de Múltiplos ProjetosGerenciamento de Tempo em Ambientes de Múltiplos Projetos
Gerenciamento de Tempo em Ambientes de Múltiplos Projetos
 
Negociação ivo michalick - ago12
Negociação   ivo michalick - ago12Negociação   ivo michalick - ago12
Negociação ivo michalick - ago12
 
Motivation ivo michalick - 03-24-2012
Motivation   ivo michalick - 03-24-2012Motivation   ivo michalick - 03-24-2012
Motivation ivo michalick - 03-24-2012
 
Competencias ivo - mar13
Competencias   ivo - mar13Competencias   ivo - mar13
Competencias ivo - mar13
 

Último

Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
Best Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaBest Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaShree Krishna Exports
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communicationskarancommunications
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfPaul Menig
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...Any kyc Account
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Roland Driesen
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...amitlee9823
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLSeo
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayNZSG
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Centuryrwgiffor
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Delhi Call girls
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Lviv Startup Club
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...Aggregage
 
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 DelhiCall Girls in Delhi
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 

Último (20)

Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
Best Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaBest Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in India
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communications
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdf
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
 
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 

Structuring a PMO with the Help of Front End Loading and the PMBOK® Guide

  • 1. Structuring a PMO with the Help of Front-End Loading and the PMBOK® Guide Ivo M. Michalick Vasconcelos, Vale Paulo Penna de Moraes, Vale Abstract A thorough and effective management process is a critical success factor for any kind of project. This is even truer in capital projects, which usually have a development phase that is critical and mandatory before the project gets formal approval. This paper describes the task of structuring a project management office (PMO) in the logistics projects department (responsible for developing ports and railroads capital projects) of a large and multinational mining company. This PMO is in charge of supporting the development phase (front-end) of capital projects of different sizes and complexities, based on a stage-gated process inspired by the front-end loading (FEL) approach and with the help of best practices proposed in the A Guide to the Project Management Body of Knowledge (PMBOK® Guide—Fourth Edition). Introduction Capital projects, due to their size and strategic importance, tend to have a high impact on the companies that perform them. In the context of this paper, capital projects are ones that: • Provide a capacity increment in an integrated logistics chain; • Require board approval for moving to the construction phase; and • Have a deep impact (social and economical, direct and indirect) in the geographical area where they are deployed. This paper describes the task of structuring a project management office (PMO) in the logistics projects department (responsible for developing ports and railroads capital projects) of a large and multinational mining company. This PMO is in charge of supporting the development phase (front-end) of capital projects of different sizes and complexities, based on a stage gated process inspired by the front-end loading (FEL) approach and with the help of best practices proposed in the A Guide to the Project Management Body of Knowledge (PMBOK® Guide—Fourth Edition) (Project Management Institute [PMI], 2008). The PMO has the following main features: - A project management methodology that matches a corporate process based on FEL and the best practices from the PMBOK® Guide—Fourth Edition (PMI, 2008). - A project categorization system that allows tailoring the methodology to a specific project, identifying key deliverables and processes to be used for each type of project. - An integrated risk management process that spans the overall project life cycle. - A project governance system that handles project initiation and termination, project priorities, and scope changes. Each feature will be presented in the following sections. ©2010 Ivo M. Michalick Vasconcelos, Paulo Penna de Moraes 1 Originally published as part of Proceedings PMI Global Congress 2010 – Milan, Italy
  • 2. The Project Management Methodology Several studies on capital projects, such as Nissen (2003), have shown that the success in implementing competitive projects is based on four factors: project team, technology, value-improving techniques (VIPs), and FEL. Among them, FEL is considered the most crucial factor for project success. According to Barshop (2003), “Front-end loading (FEL) is a process by which a company translates its marketing and technology opportunities into capital projects. The objective is to align project objectives with the business need and to develop the most efficient process design and execution plan to achieve the project objectives” (p. 17). The company developed a corporate methodology based on a FEL process that divides the development phase into three different stages (Exhibit 1). Initiate Gate 1 Gate 2 Gate 3 Start up Business Trade-off Execution Construction Operation Analysis analysis Planning Development phase Rework Proceed Cancel Exhibit 1. Capital Project Life Cycle with Gate Reviews Each phase ends with a gate review, which works as a clear transition point, where the project, after being examined, is either allowed to move to the next phase, return for a better definition or canceled. For each FEL stage, a set of deliverables is defined, and in the beginning of each stage, its planning is reviewed. This process is inspired by the “rolling wave planning” concept proposed in the PMBOK® Guide—Fourth Edition (PMI, 2008, p.46 ). The Project Categorization System The company has a corporate process that defines a complete set of deliverables for each FEL stage, and that set is mandatory for projects above a certain capital expenditure (CAPEX) value. However, the PMO is also in charge of supporting projects with CAPEX below that threshold, so in order to tailor the corporate process for such projects a categorization system has been defined. This system goes beyond the CAPEX value and onsidering questions such as the following: • Is the project Greenfield (new, undeveloped site), Brownfield (to be developed on an already developed site), or both? • What is the level of environmental permitting required? • Will the project demand fast tracking? ©2010 Ivo M. Michalick Vasconcelos, Paulo Penna de Moraes 2 Originally published as part of Proceedings PMI Global Congress 2010 – Milan, Italy
  • 3. Will the project require land acquisition? At what level? • Will the project interfere with communities or wildlife? • Is this a port/railroad/ or both project? • What is the perceived degree of risk for the project? All these questions must be answered by the project team as part of the project initiation process. Based on the answers, the project can be classified as simple, medium, large, or mega. A mega project must adhere to all methodology requirements (including independent evaluation at the end of FEL 2 and FEL 3) and provide all deliverables, whereas a simple project demands a smaller set of deliverables, and can have an internal evaluation at the end of each phase. For instance, for large and mega projects, a quantitative risk analysis is a mandatory deliverable for the FEL 3 stage, and it is optional for simple and medium projects (but all projects must perform at least a qualitative risk analysis during FEL 3). Regardless of their category, all projects need to have an approved project development plan (PDP) before they are authorized to proceed; all projects are monitored based on this plan, which is reviewed at the beginning of each new stage. In addition, all projects must produce a project execution plan (PEP) at the end of FEL 3. This plan will guide the execution of the next stage (construction). The Integrated Risk Management Process The corporate process defines risk as the measure of the uncertainties in the assumptions adopted in the different disciplines of a project, in view of the project’s main objectives: schedule, budget (CAPEX), and return on investment (ROI). A risk may be a threat (negative impact on one or more objectives) or an opportunity (positive impact on one or more objectives). Notice that the definition of risk has a strong quantitative component. At the end of a development phase, the main project risks must have been evaluated and assigned a quantitative impact on the schedule and the CAPEX. The level of risk analysis detail is compatible with each FEL stage (Exhibit 2). Exhibit 2. Level of Detail of Risk Analysis at Each FEL Stage Risk Management at the FEL 1 Stage At this stage risk, management is broken down into two stages. The first one identifies fatal flaws in the environment, land acquisition, communities, and engineering. The second stage identifies fatal flaws in economic analysis and tries to identify uncertainties in relevant economic variables. ©2010 Ivo M. Michalick Vasconcelos, Paulo Penna de Moraes 3 Originally published as part of Proceedings PMI Global Congress 2010 – Milan, Italy
  • 4. Risk Management at the FEL 2 Stage At the FEL 2 stage, a process is defined for supporting the selection of the best alternatives (site location, technological process, etc.) for the project. A qualitative risk analysis follows the conclusion of the conceptual engineering studies of all alternatives to support the decision process that will select the best alternative for the project. Risk Management at the FEL 3 Stage At the FEL 3 stage, risk analysis is broken down in two main processes. • Quantitative risk analysis is based on Monte Carlo simulation. It evaluates the chances of meeting the main project objectives, especially CAPEX and schedule. This is a two-stage process, namely: o Stage 1: It comprises only risk identification in the environment, land acquisition, human resources, communities, safety and security, engineering, and planning. This is usually performed halfway through FEL 3. o Stage 2 comprises a review of the risks identified in stage 1. It identifies risks in engineering and planning, quantitative analysis, and development of a risk management plan. This is usually performed closer to the end of FEL 3. • Hazard and operability analysis (HazOp) is a structured technique for qualitative analysis developed in order to identify operational problems in project processes that can compromise or jeopardize capacity, productivity, and/or safety. This analysis is usually performed upon completion of engineering basic design. The Project Governance System In order to be included in the portfolio of projects monitored by the PMO, a project must undergo a project authorization process based in the initiation process group as described in the PMBOK® Guide—Fourth Edition (PMI, 2008). The PMO manager receives a project charter proposal and submits it for internal analysis of the engineering area. If and when the project charter is approved, a project code is created for the corresponding project and a project manager is designated. The project manager’s first order of business is to gather a core project team and start developing a PDP for the corresponding FEL stage upon which the project is received. Change requests are managed based on the processes described in the Practice Standard for Project Configuration Management (PMI, 2007) and shown in Exhibit 3. ©2010 Ivo M. Michalick Vasconcelos, Paulo Penna de Moraes 4 Originally published as part of Proceedings PMI Global Congress 2010 – Milan, Italy
  • 5. Exhibit 3. Change Control Process According to PMI (2007, p. 17) If a project is approved to proceed after a FEL 3 gate review, it is transferred to a different structure to go to the construction phase. Depending on the project size, a projectized structure is created for it. It is common that team members from the development phase continue with the project during the construction phase. Considering that at the end of FEL 3, the project moves to a different structure within the department, a formal transfer term must be signed between the involved parties and after the FEL 3 gate review. Periodically, an executive panel is published internally, with an executive view of the PMO portfolio and all projects main milestones. Conclusion We described how a PMO focused in the development of capital projects has been structured based on existing processes, tools, and techniques within the company. The resulting methodology adheres both to the FEL approach and to the best practices as proposed in the PMBOK® Guide—Fourth Edition (PMI, 2008). All this work was performed while the project pipeline was kept active, with projects entering and leaving the portfolio. The governance system survived the bumps generated by the economical crisis of 2008–2009 (the Brazilian PIB (Gross Domestic Product) decreased by 0.2% in 2009) (PRNewswire, 2010 ¶1) and has been very efficient now, when the economy, at least in the mining sector, is strongly recovering. We believe that the four features described in this paper (a project management methodology, a project categorization system, an integrated risk management process, and a project governance system) can be used/adapted by other organizations that handle capital projects as a starting point for implementing their own PMO and achieving more effective results in their capital projects. References Barshop, P. (2003, December 22). Best practice pays off. European Chemical News 79 ( 2081), 16–17. Nissen, R. A. (2003). VIPs: Who are they and what can they do for us? Retrieved March 10. 2010, from http://www.nwccc.org/upload/nissen.pdf PRI Newswire (2010, 11 March) Brazil's GDP Down 0.2% in 2009, Demonstrating Resilience Amidst Global Economic Crisis Retrived from http://www.prnewswire.com/news-releases/brazils-gdp-down-02-in-2009- demonstrating-resilience-amidst-global-economic-crisis-87374637.html ©2010 Ivo M. Michalick Vasconcelos, Paulo Penna de Moraes 5 Originally published as part of Proceedings PMI Global Congress 2010 – Milan, Italy
  • 6. Project Management Institute. (2007). Practice standard for project configuration management. Newtown Square, PA: Project Management Institute. Project Management Institute. (2008). A guide to the project management body of knowledge (PMBOK® Guide) (4th ed.). Newtown Square, PA: Project Management Institute. ©2010 Ivo M. Michalick Vasconcelos, Paulo Penna de Moraes 6 Originally published as part of Proceedings PMI Global Congress 2010 – Milan, Italy