SlideShare una empresa de Scribd logo
1 de 33
THE ROAD (137 km) AND THE BRIDGES
REHABILITATION DE LA R.R. N°8
BOSSANGOA – BOZOUM
BOSSANGOA
BOZOUM
OUHAM BAC
EXISTING BRIDGES - DESCRIPTION
REHABILITATION DE LA R.R. N°8
BOSSANGOA – BOZOUM
STEEL GIRDERS
TIMBER
DECKING
STONE MASONRY
ABUTMENTS
• THERE ARE 20 BRIDGES ON THE BOSSANGOA-BOZOUM ROAD
• THE CONSTRUCTION METHOD IS THE SAME FOR ALL THE
BRIDGES: TIMBER DECKING ON 4 STEEL GIRDERS WITH STONE
MASONRY ABUTMENTS
EXISTING BRIDGES - CONSERVATION STATE
• TIMBER DECKING
– ON THE BOSSANGOA SIDE, THE TIMBER DECKING IS STILL
IN POSITION, BUT GENERALLY IN POOR CONDITION.
– ON THE BOZOUM SIDE THE ORIGINAL DECKING HAS
COLLAPSED AND HAS BEEN REPLACED BY WOODEN
BRANCHES.
• STEEL GIRDERS
– THE CONDITION IS GOOD.
• MASONRY ABUTMENTS
– THE CONSERVATION IS GENERALLY GOOD, EXCEPT FOR 7
BRIDGES WITH CRACKS THAT REQUIRE REINFORCING.
REHABILITATION DE LA R.R. N°8
BOSSANGOA – BOZOUM
EXISTING BRIDGES - CONSERVATION STATE
PONT N° 16 (BOSSANGOA SIDE) – THE TIMBER DECKING
REHABILITATION DE LA R.R. N°8
BOSSANGOA – BOZOUM
EXISTING BRIDGES - CONSERVATION STATE
PONT N° 17 (BOSSANGOA SIDE) – THE TIMBER DECKING
REHABILITATION DE LA R.R. N°8
BOSSANGOA – BOZOUM
EXISTING BRIDGES - CONSERVATION STATE
PONT N° 19 (BOSSANGOA SIDE) – THE TIMBER DECKING
REHABILITATION DE LA R.R. N°8
BOSSANGOA – BOZOUM
EXISTING BRIDGES - CONSERVATION STATE
PONT N° 8 (BOZOUM SIDE) – THE TIMBER DECKING
REHABILITATION DE LA R.R. N°8
BOSSANGOA – BOZOUM
EXISTING BRIDGES - CONSERVATION STATE
PONT N° 10 (BOZOUM SIDE) – THE TIMBER DECKING
REHABILITATION DE LA R.R. N°8
BOSSANGOA – BOZOUM
EXISTING BRIDGES - CONSERVATION STATE
PONT N° 12 (BOZOUM SIDE) – THE TIMBER DECKING
REHABILITATION DE LA R.R. N°8
BOSSANGOA – BOZOUM
EXISTING BRIDGES - CONSERVATION STATE
PONT N° 20 (BOZOUM SIDE) – THE STEEL GIRDERS
REHABILITATION DE LA R.R. N°8
BOSSANGOA – BOZOUM
EXISTING BRIDGES - CONSERVATION STATE
PONT N° 4 (BOZOUM SIDE) – THE STEEL GIRDERS
REHABILITATION DE LA R.R. N°8
BOSSANGOA – BOZOUM
EXISTING BRIDGES - CONSERVATION STATE
PONT N° 7 (BOZOUM SIDE) – THE STEEL GIRDERS
REHABILITATION DE LA R.R. N°8
BOSSANGOA – BOZOUM
EXISTING BRIDGES - CONSERVATION STATE
PONT N° 4 (BOZOUM SIDE) – THE ABUTMENTS
REHABILITATION DE LA R.R. N°8
BOSSANGOA – BOZOUM
EXISTING BRIDGES - CONSERVATION STATE
PONT N° 16 (BOSSANGOA SIDE) – THE ABUTMENTS
REHABILITATION DE LA R.R. N°8
BOSSANGOA – BOZOUM
EXISTING BRIDGES - CONSERVATION STATE
PONT N° 20 (BOZOUM SIDE) – THE ABUTMENTS
REHABILITATION DE LA R.R. N°8
BOSSANGOA – BOZOUM
EXISTING BRIDGES - CONSERVATION STATE
PONT N° 3 (BOZOUM SIDE) – THE ABUTMENTS
REHABILITATION DE LA R.R. N°8
BOSSANGOA – BOZOUM
EXISTING BRIDGES - CONSERVATION STATE
PONT N° 18 (BOSSANGOA SIDE) – THE ABUTMENTS
REHABILITATION DE LA R.R. N°8
BOSSANGOA – BOZOUM
THE DESIGN
• GOAL OF THE DESIGN:
– REOPEN THE ROAD AND THE BRIDGES TO TRAFFIC IN A
SAFE, FAST AND COST-EFFECTIVE WAY. WE HAVE TRIED
TO CONSERVATE AND REUSE TO THE MAXIMUM THE
EXISTING BRIDGES, IDENTIFYING THE ALLOWABLE LOAD
OF THE STRUCTURES AND REINFORCEING THEM WHERE
NEEDED.
• METHOD OF WORK:
– FOR ALL THE BRIDGES WE HAVE CONDUCTED A
STRUCTURAL ANALYSIS WITH COMPUTER FINITE ELEMENT
MODELS TO DEFINE THE MAXIMUM LOAD THAT THE
BRIDGES CAN SUPPORT AND THEREFORE THE ALLOWABLE
LOAD OF THE ROAD. THE CALCULATIONS HAVE BEEN DONE
ACCORDING TO EUROCODES AND AASHTO “STANDARD
SPECIFICATIONS FOR HIGHWAY BRIDGES”.
REHABILITATION DE LA R.R. N°8
BOSSANGOA – BOZOUM
THE DESIGN – THE STRUCTURAL ANALYSIS
• DESIGN LOAD:
(FROM AMERICAN AASHTO CODES)
• THE MATERIALS:
– TIMBER: MUKULUNGU
– STEEL: ? FOR THE EXISTING GIRDERS WE HAVE NO
INFORMATION ON THE GRADE OF THE STEEL AND ITS
RESISTANCE. WE HAVE CONSERVATIVELY ASSUMED THAT
THE GIRDERS ARE MADE OF S235 STEEL (yielding strength
= 235 MPa) WHICH IS THE LOWEST OF THE 3 COMMERCIAL
STEEL GRADES (235, 275 O 355 MPa)
REHABILITATION DE LA R.R. N°8
BOSSANGOA – BOZOUM
THE DESIGN – THE STRUCTURAL ANALYSIS
REHABILITATION DE LA R.R. N°8
BOSSANGOA – BOZOUM
FINITE ELEMENT MODEL (2D) FINITE ELEMENT MODEL (3D)
BENDING MOMENT CALCULATED DEFLECTION
MAXIMUM
CALCULATED
DEFLECTION
THE DESIGN – CONCLUSIONS
• REPLACE THE TIMBER DECKING FOR ALL BRIDGES
• REINFORCE THE ABUTMENTS OF 7 BRIDGES
• MAINTAIN THE STEEL GIRDERS FOR ALL BRIDGES
EXCEPT BRIDGE N° 18 WHICH HAS A LOWER LOAD
CAPACITY: 2 NEW GIRDERS WILL BE ADDED FOR
THIS BRIDGE.
REHABILITATION DE LA R.R. N°8
BOSSANGOA – BOZOUM
THE DESIGN – REPLACEMENT OF THE DECKING
REHABILITATION DE LA R.R. N°8
BOSSANGOA – BOZOUM
MUKULUNGU TIMBER
FOR TRANSVERSE
MADRIERS AND
LONGITUDINAL
ELEMENTS: RESISTANT
AND DURABLE
THE DESIGN – REPLACEMENT OF THE DECKING
REHABILITATION DE LA R.R. N°8
BOSSANGOA – BOZOUM
CLOSER MADRIERS (25 cm
INSTEAD OF 30 cm) TO
INCREASE RESISTANCE
AND SAFETY OF
PEDESTRIANS
RECONSTRUCTION OF
THE SAFETY POSTS ON
EACH SIDE OF THE
ABUTMENTS TO ENSURE
THAT VEHICLES TRAVEL
ON THE CENTER OF THE
BRIDGE
THE DESIGN – REPLACEMENT OF THE DECKING
REHABILITATION DE LA R.R. N°8
BOSSANGOA – BOZOUM
RUNNING SURFACE MADE WITH
8 cm MADRIERS INSTEAD OF 3
cm PLANKS TO INCREASE
DURABILITY
THE DESIGN – REPLACEMENT OF THE DECKING
REHABILITATION DE LA R.R. N°8
BOSSANGOA – BOZOUM
LAG SCREWS INSTEAD OF
NAILS TO INCREASE
DURABILITY
RUNNING SURFACE MADE WITH
8 cm MADRIERS INSTEAD OF 3
cm PLANKS TO INCREASE
DURABILITY
REHABILITATION DE LA R.R. N°8
BOSSANGOA – BOZOUM
THE DESIGN – REINFORCEMENT OF THE ABUTMENTS
• SIMPLE AND EFFECTIVE REINFORCEMENT
TECHNIQUES (FOR EXAMPLE CONCRETE
COATING) HAVE BEEN CHOSEN FOR THE
ABUTMENTS
EXAMPLE OF THE REINFORCEMENT FOR
BRIDGES 1, 2, 14 AND 20:
REHABILITATION DE LA R.R. N°8
BOSSANGOA – BOZOUM
THE DESIGN – ALLOWABLE LOAD
• THE CALCULATIONS HAVE SHOWN THAT, ASSUMING A STEEL
RESISTANCE OF 235 MPa, ALL OF THE BRIDGES (EXCEPT ONE) CAN
SUPPORT AN AXLE LOAD OF AT LEAST 100 kN (10 tons)
• THE EXCEPTION IS BRIDGE n° 18 (pk 32.5) WHICH CAN SUPPORT AN
AXLE LOAD OF JUST 70 kN (7 tons)
• THEREFORE, BRIDGE N° 18 WILL BE REINFORCED BY ADDING 2 NEW
GIRDERS BESIDES THE EXISTING ONES, INCREASING ITS LOAD
CAPACITY TO 100 kN (10 tons).
• TO ACCOUNT FOR POSSIBLE OVERLOADED TRUCKS, WE WILL
CONSIDER AN ADDITIONAL 15% SAFETY FACTOR, THEREFORE THE
ALLOWABLE AXLE LOAD ON THE ROAD WILL BE:
85 kN (8.5 tons)
REHABILITATION DE LA R.R. N°8
BOSSANGOA – BOZOUM
BRIDGE n° 18 – REINFORCEMENT
• TWO NEW GIRDERS WILL BE ADDED BESIDES THE
EXISTING ONES, INCREASING THE LOAD CAPACITY
REHABILITATION DE LA R.R. N°8
BOSSANGOA – BOZOUM
TEST LOADS – DURING CONSTRUCTION
• DURING CONSTRUCTION IT WILL BE IMPORTANT TO
CHECK THAT THE BENDING RESISTANCE OF THE
MUKULUNGU TIMBER ISN’T LOWER THAN THE VALUE
CONSIDERED IN THE DESIGN (30 MPa)
• SIMPLE RESISTANCE TESTS WILL HAVE TO BE MADE ON
THE TIMBER MADRIERS
REHABILITATION DE LA R.R. N°8
BOSSANGOA – BOZOUM
TEST LOADS – DURING CONSTRUCTION
• TEST LOADS ON THE TIMBER MADRIERS
REHABILITATION DE LA R.R. N°8
BOSSANGOA – BOZOUM
TEST LOADS – AFTER CONSTRUCTION
• AFTER CONSTRUCTION IT WILL BE IMPORTANT TO CHECK THAT THE
RESPONSE OF THE BRIDGE CORRESPONDS TO THE EXPECTED
PERFORMANCE.
• LOAD TESTS WILL BE MADE ON THE BRIDGES TO CHECK THAT THE REAL
DEFLECTION CORRESPONDS TO THE CALCULATED DEFLECTION. A TRUCK
WITH THE SAME WEIGHT AS THE DESIGN LOAD WILL STAY ON THE BRIDGE
WITH THE AXLE PLACED IN MIDSPAN, AND THE MAXIMUM DEFLECTION WILL
BE MEASURED WITH A DIAL GAUGE.
REHABILITATION DE LA R.R. N°8
BOSSANGOA – BOZOUM
MAINTENANCE AND MONITORING
IN ORDER TO ENSURE THE DURABILITY OF THE BRIDGES IT IS NECESSARY TO
REGULARLY MAINTAIN AND MONITOR THEM.
• TIMBER RUNNING SURFACE: IT IS ONE OF THE MOST EXPOSED PARTS TO WEAR
AND DEGRADATION, AND SHOULD BE CHECKED EVERY 4 MONTHS TO IDENTIFY
DAMAGED PARTS THAT SHOULD BE REPLACED.
• TRANSVERSE MADRIERS: THE TRANSVERSE MADRIERS SHOULD BE INSPECTED
EVERY 4 MONTHS TO FIND DAMAGED OR BROKEN ELEMENTS THAT SHOULD BE
IMMEDIATELY REPLACED.
• TIMBER CONNECTIONS: THE CONNECTIONS BETWEEN THE TIMBER ELEMENTS
ARE PARTICULARLY SENSITIVE TO VIBRATIONS AND TRAFFIC. THEY SHOULD BE
CHECKED EVERY 4 MONTHS; THEY SHOULD BE TIGHTENED WHEN NECESSARY,
AND REPLACED IMMEDIATELY IF FOUND TO BE MISSING.
• SAFETY POSTS: THE SAFETY POSTS ON THE ABUTMENTS ARE ESSENTIAL FOR
THE SAFETY OF THE BRIDGES: THEY SHOULD BE CHECKED EVERY 2 MONTHS
AND IMMEDIATELY REPLACED IF BROKEN.
• ABUTMENTS: ABUTMENTS SHOULD BE CHECKED REGULARLY FOR CRACKS,
DISPLACED STONES, SCOUR ON FOUNDATIONS, ETC. AND APPROPRIATE
RECONSTRUCTION/REINFORCEMENT SHOULD BE DONE. A COMPLETE
INSPECTION SHOULD BE DONE EVERY SIX MONTHS.
• VEGETATION: VEGETATION SHOULD BE CLEARED FROM THE BRIDGE
ANNUALLY. VEGETATION SHOULD ALSO CAREFULLY BE REMOVED FROM THE
ABUTMENTS WITHOUT DAMAGING THE MASONRY.
REHABILITATION DE LA R.R. N°8
BOSSANGOA – BOZOUM
THANKYOU
FOR YOUR ATTENTION

Más contenido relacionado

La actualidad más candente

Pile foundation power point ptesentation
Pile foundation power point ptesentationPile foundation power point ptesentation
Pile foundation power point ptesentationMohammad zuha
 
Presentation 1 drilling rigs
Presentation 1 drilling rigsPresentation 1 drilling rigs
Presentation 1 drilling rigsAli Trichelli
 
Embankment dam civil 5 th sem upload
Embankment dam civil 5 th sem uploadEmbankment dam civil 5 th sem upload
Embankment dam civil 5 th sem uploadMeet Soni
 
Analysis and Design Aspects of Support Measures of Main Caverns of Karuma Hyd...
Analysis and Design Aspects of Support Measures of Main Caverns of Karuma Hyd...Analysis and Design Aspects of Support Measures of Main Caverns of Karuma Hyd...
Analysis and Design Aspects of Support Measures of Main Caverns of Karuma Hyd...IOSRJMCE
 
Combine piled raft foundation (cprf)_Er.Karan Chauhan
Combine piled raft foundation (cprf)_Er.Karan ChauhanCombine piled raft foundation (cprf)_Er.Karan Chauhan
Combine piled raft foundation (cprf)_Er.Karan ChauhanEr.Karan Chauhan
 
General & geotechnical considerations for pile design
General & geotechnical considerations for pile designGeneral & geotechnical considerations for pile design
General & geotechnical considerations for pile designRizwan Khurram
 
Design of earth dam at gorukallu
Design of earth dam at gorukalluDesign of earth dam at gorukallu
Design of earth dam at gorukallurohinibjn
 
DRILLED SHAFT CAPACITY IN COMPRESSION
DRILLED SHAFT CAPACITY IN COMPRESSION DRILLED SHAFT CAPACITY IN COMPRESSION
DRILLED SHAFT CAPACITY IN COMPRESSION SNC-Lavalin
 
Abhishek and tarachand stone columns an over view
Abhishek and tarachand stone columns an over viewAbhishek and tarachand stone columns an over view
Abhishek and tarachand stone columns an over viewTarachand Veeragattapu
 
19100309 offshore-platform-design
19100309 offshore-platform-design19100309 offshore-platform-design
19100309 offshore-platform-designOFFSHORE VN
 

La actualidad más candente (20)

Pile foundation power point ptesentation
Pile foundation power point ptesentationPile foundation power point ptesentation
Pile foundation power point ptesentation
 
9429
94299429
9429
 
Earthen Dams
Earthen DamsEarthen Dams
Earthen Dams
 
Dam engineering i 5
Dam engineering i 5Dam engineering i 5
Dam engineering i 5
 
Dam engineering i 2
Dam engineering i 2Dam engineering i 2
Dam engineering i 2
 
Diversion headworks
Diversion headworksDiversion headworks
Diversion headworks
 
Arch and Buttress Dams
Arch and Buttress DamsArch and Buttress Dams
Arch and Buttress Dams
 
Presentation 1 drilling rigs
Presentation 1 drilling rigsPresentation 1 drilling rigs
Presentation 1 drilling rigs
 
Embankment dam civil 5 th sem upload
Embankment dam civil 5 th sem uploadEmbankment dam civil 5 th sem upload
Embankment dam civil 5 th sem upload
 
Analysis and Design Aspects of Support Measures of Main Caverns of Karuma Hyd...
Analysis and Design Aspects of Support Measures of Main Caverns of Karuma Hyd...Analysis and Design Aspects of Support Measures of Main Caverns of Karuma Hyd...
Analysis and Design Aspects of Support Measures of Main Caverns of Karuma Hyd...
 
4410 8
4410 84410 8
4410 8
 
Combine piled raft foundation (cprf)_Er.Karan Chauhan
Combine piled raft foundation (cprf)_Er.Karan ChauhanCombine piled raft foundation (cprf)_Er.Karan Chauhan
Combine piled raft foundation (cprf)_Er.Karan Chauhan
 
Embankment lecture 2
Embankment lecture 2Embankment lecture 2
Embankment lecture 2
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 
Reservoir Dam Safety
Reservoir Dam SafetyReservoir Dam Safety
Reservoir Dam Safety
 
General & geotechnical considerations for pile design
General & geotechnical considerations for pile designGeneral & geotechnical considerations for pile design
General & geotechnical considerations for pile design
 
Design of earth dam at gorukallu
Design of earth dam at gorukalluDesign of earth dam at gorukallu
Design of earth dam at gorukallu
 
DRILLED SHAFT CAPACITY IN COMPRESSION
DRILLED SHAFT CAPACITY IN COMPRESSION DRILLED SHAFT CAPACITY IN COMPRESSION
DRILLED SHAFT CAPACITY IN COMPRESSION
 
Abhishek and tarachand stone columns an over view
Abhishek and tarachand stone columns an over viewAbhishek and tarachand stone columns an over view
Abhishek and tarachand stone columns an over view
 
19100309 offshore-platform-design
19100309 offshore-platform-design19100309 offshore-platform-design
19100309 offshore-platform-design
 

Destacado

Infrastructure Needs: North Dakota’s County, Township, & Tribal Roads & Bridg...
Infrastructure Needs: North Dakota’s County, Township, & Tribal Roads & Bridg...Infrastructure Needs: North Dakota’s County, Township, & Tribal Roads & Bridg...
Infrastructure Needs: North Dakota’s County, Township, & Tribal Roads & Bridg...UGPTI
 
Munger rail cum road bridge
Munger rail cum road bridgeMunger rail cum road bridge
Munger rail cum road bridgejaiveer singh
 
A Study on Development of Live Load Model for Passenger Vehicles-only Bridges
A Study on Development of Live Load Model for Passenger Vehicles-only Bridges A Study on Development of Live Load Model for Passenger Vehicles-only Bridges
A Study on Development of Live Load Model for Passenger Vehicles-only Bridges Hyeok Jin Choi
 
Designing the highway 2
Designing the highway 2Designing the highway 2
Designing the highway 2Rron de Guzman
 
summer Internship report L&T_ Bihar museum_Patna
summer Internship report L&T_ Bihar museum_Patnasummer Internship report L&T_ Bihar museum_Patna
summer Internship report L&T_ Bihar museum_Patnakishore1192
 
Fnl grade separators
Fnl grade separatorsFnl grade separators
Fnl grade separatorsarkalpana
 
Concrete Repair: Bridges and Tunnels--Epoxies
Concrete Repair: Bridges and Tunnels--Epoxies Concrete Repair: Bridges and Tunnels--Epoxies
Concrete Repair: Bridges and Tunnels--Epoxies jbors
 
An introduction to civil engineering
An introduction  to civil engineeringAn introduction  to civil engineering
An introduction to civil engineeringBhanu Pratap
 
Basics of bridge construction
Basics of bridge constructionBasics of bridge construction
Basics of bridge constructionsymphonyjo
 
Bridge
Bridge Bridge
Bridge illpa
 
Highway Engineering topics
Highway Engineering topicsHighway Engineering topics
Highway Engineering topicsShubham Sadh
 
Introduction to Civil Engineering
Introduction to Civil Engineering Introduction to Civil Engineering
Introduction to Civil Engineering Umer Farooq
 
Bridge engineering
Bridge engineeringBridge engineering
Bridge engineeringHalcrow
 
PPT On Bridge Construction
PPT On Bridge ConstructionPPT On Bridge Construction
PPT On Bridge ConstructionRobin Nirwal
 
LinkedIn SlideShare: Knowledge, Well-Presented
LinkedIn SlideShare: Knowledge, Well-PresentedLinkedIn SlideShare: Knowledge, Well-Presented
LinkedIn SlideShare: Knowledge, Well-PresentedSlideShare
 

Destacado (17)

Piano Bridge
Piano BridgePiano Bridge
Piano Bridge
 
Infrastructure Needs: North Dakota’s County, Township, & Tribal Roads & Bridg...
Infrastructure Needs: North Dakota’s County, Township, & Tribal Roads & Bridg...Infrastructure Needs: North Dakota’s County, Township, & Tribal Roads & Bridg...
Infrastructure Needs: North Dakota’s County, Township, & Tribal Roads & Bridg...
 
Munger rail cum road bridge
Munger rail cum road bridgeMunger rail cum road bridge
Munger rail cum road bridge
 
A Study on Development of Live Load Model for Passenger Vehicles-only Bridges
A Study on Development of Live Load Model for Passenger Vehicles-only Bridges A Study on Development of Live Load Model for Passenger Vehicles-only Bridges
A Study on Development of Live Load Model for Passenger Vehicles-only Bridges
 
Designing the highway 2
Designing the highway 2Designing the highway 2
Designing the highway 2
 
summer Internship report L&T_ Bihar museum_Patna
summer Internship report L&T_ Bihar museum_Patnasummer Internship report L&T_ Bihar museum_Patna
summer Internship report L&T_ Bihar museum_Patna
 
Fnl grade separators
Fnl grade separatorsFnl grade separators
Fnl grade separators
 
Concrete Repair: Bridges and Tunnels--Epoxies
Concrete Repair: Bridges and Tunnels--Epoxies Concrete Repair: Bridges and Tunnels--Epoxies
Concrete Repair: Bridges and Tunnels--Epoxies
 
An introduction to civil engineering
An introduction  to civil engineeringAn introduction  to civil engineering
An introduction to civil engineering
 
Designing the highway
Designing the highwayDesigning the highway
Designing the highway
 
Basics of bridge construction
Basics of bridge constructionBasics of bridge construction
Basics of bridge construction
 
Bridge
Bridge Bridge
Bridge
 
Highway Engineering topics
Highway Engineering topicsHighway Engineering topics
Highway Engineering topics
 
Introduction to Civil Engineering
Introduction to Civil Engineering Introduction to Civil Engineering
Introduction to Civil Engineering
 
Bridge engineering
Bridge engineeringBridge engineering
Bridge engineering
 
PPT On Bridge Construction
PPT On Bridge ConstructionPPT On Bridge Construction
PPT On Bridge Construction
 
LinkedIn SlideShare: Knowledge, Well-Presented
LinkedIn SlideShare: Knowledge, Well-PresentedLinkedIn SlideShare: Knowledge, Well-Presented
LinkedIn SlideShare: Knowledge, Well-Presented
 

Similar a Assessment and reinforcement of the 20 existing bridges in the Bozoum-Bossangoa road in Central African Republic. Presentation to the Ministry of Works.

938-Article Text-4728-1-10-20100512.pdf
938-Article Text-4728-1-10-20100512.pdf938-Article Text-4728-1-10-20100512.pdf
938-Article Text-4728-1-10-20100512.pdfIndusConsultants
 
JKrajewski_ODOT214_Bridge of the Gods
JKrajewski_ODOT214_Bridge of the GodsJKrajewski_ODOT214_Bridge of the Gods
JKrajewski_ODOT214_Bridge of the GodsJoe Krajewski
 
CPM UNIT 2 CONSTRUCTION EQUIPMENTS
CPM UNIT 2 CONSTRUCTION EQUIPMENTSCPM UNIT 2 CONSTRUCTION EQUIPMENTS
CPM UNIT 2 CONSTRUCTION EQUIPMENTSSuyash Awasthi
 
Suspension bridges
Suspension bridgesSuspension bridges
Suspension bridgesRana Ibrahim
 
Fiberprofil Americas-Gfrp presentation
Fiberprofil Americas-Gfrp presentationFiberprofil Americas-Gfrp presentation
Fiberprofil Americas-Gfrp presentationralphesteves
 
Maintenance & repair of steel bridges
Maintenance & repair of steel bridgesMaintenance & repair of steel bridges
Maintenance & repair of steel bridgesnaveen kumar
 
Chenab Railway Bridge PPT.pptx
Chenab Railway Bridge PPT.pptxChenab Railway Bridge PPT.pptx
Chenab Railway Bridge PPT.pptxDronaDarkHearted
 
BRIDGE & BEARINGS Awareness.pptx
BRIDGE & BEARINGS Awareness.pptxBRIDGE & BEARINGS Awareness.pptx
BRIDGE & BEARINGS Awareness.pptxSanthosh Kumar S R
 
RUDDER TRUNK MISMATCH
RUDDER TRUNK MISMATCHRUDDER TRUNK MISMATCH
RUDDER TRUNK MISMATCHApoorv Dhawan
 
Alonso & Carus Company Profile
Alonso & Carus Company ProfileAlonso & Carus Company Profile
Alonso & Carus Company Profilejramosjr
 
Industrial visit(ved kumar -1216540115)
Industrial visit(ved kumar -1216540115)Industrial visit(ved kumar -1216540115)
Industrial visit(ved kumar -1216540115)VED KUMAR
 
Elevated water tank
Elevated water tankElevated water tank
Elevated water tankAamir Patni
 
Rosemont Project Hydrogeology & Water Supply
Rosemont Project Hydrogeology & Water SupplyRosemont Project Hydrogeology & Water Supply
Rosemont Project Hydrogeology & Water SupplyHudbay Minerals Inc.
 
2014-05-12 255 138th Street NYCTA Structural Drawings
2014-05-12 255 138th Street NYCTA Structural Drawings2014-05-12 255 138th Street NYCTA Structural Drawings
2014-05-12 255 138th Street NYCTA Structural DrawingsTodd Mordoh
 
120CR0393_Subrat Kumar Gaana_Seminar and Technical Writing.pptx
120CR0393_Subrat Kumar Gaana_Seminar and Technical Writing.pptx120CR0393_Subrat Kumar Gaana_Seminar and Technical Writing.pptx
120CR0393_Subrat Kumar Gaana_Seminar and Technical Writing.pptxSubrat Kumar Gaana
 
Water retaining structures quick guide
Water retaining structures quick guideWater retaining structures quick guide
Water retaining structures quick guidejoelorap
 
Bogie and suspension e book
Bogie and suspension e bookBogie and suspension e book
Bogie and suspension e bookDeepak Solanki
 

Similar a Assessment and reinforcement of the 20 existing bridges in the Bozoum-Bossangoa road in Central African Republic. Presentation to the Ministry of Works. (20)

Floating Bridge
Floating BridgeFloating Bridge
Floating Bridge
 
938-Article Text-4728-1-10-20100512.pdf
938-Article Text-4728-1-10-20100512.pdf938-Article Text-4728-1-10-20100512.pdf
938-Article Text-4728-1-10-20100512.pdf
 
JKrajewski_ODOT214_Bridge of the Gods
JKrajewski_ODOT214_Bridge of the GodsJKrajewski_ODOT214_Bridge of the Gods
JKrajewski_ODOT214_Bridge of the Gods
 
CPM UNIT 2 CONSTRUCTION EQUIPMENTS
CPM UNIT 2 CONSTRUCTION EQUIPMENTSCPM UNIT 2 CONSTRUCTION EQUIPMENTS
CPM UNIT 2 CONSTRUCTION EQUIPMENTS
 
Case History Ncdot
Case History NcdotCase History Ncdot
Case History Ncdot
 
Suspension bridges
Suspension bridgesSuspension bridges
Suspension bridges
 
Fiberprofil Americas-Gfrp presentation
Fiberprofil Americas-Gfrp presentationFiberprofil Americas-Gfrp presentation
Fiberprofil Americas-Gfrp presentation
 
Maintenance & repair of steel bridges
Maintenance & repair of steel bridgesMaintenance & repair of steel bridges
Maintenance & repair of steel bridges
 
Paper
PaperPaper
Paper
 
Chenab Railway Bridge PPT.pptx
Chenab Railway Bridge PPT.pptxChenab Railway Bridge PPT.pptx
Chenab Railway Bridge PPT.pptx
 
BRIDGE & BEARINGS Awareness.pptx
BRIDGE & BEARINGS Awareness.pptxBRIDGE & BEARINGS Awareness.pptx
BRIDGE & BEARINGS Awareness.pptx
 
RUDDER TRUNK MISMATCH
RUDDER TRUNK MISMATCHRUDDER TRUNK MISMATCH
RUDDER TRUNK MISMATCH
 
Alonso & Carus Company Profile
Alonso & Carus Company ProfileAlonso & Carus Company Profile
Alonso & Carus Company Profile
 
Industrial visit(ved kumar -1216540115)
Industrial visit(ved kumar -1216540115)Industrial visit(ved kumar -1216540115)
Industrial visit(ved kumar -1216540115)
 
Elevated water tank
Elevated water tankElevated water tank
Elevated water tank
 
Rosemont Project Hydrogeology & Water Supply
Rosemont Project Hydrogeology & Water SupplyRosemont Project Hydrogeology & Water Supply
Rosemont Project Hydrogeology & Water Supply
 
2014-05-12 255 138th Street NYCTA Structural Drawings
2014-05-12 255 138th Street NYCTA Structural Drawings2014-05-12 255 138th Street NYCTA Structural Drawings
2014-05-12 255 138th Street NYCTA Structural Drawings
 
120CR0393_Subrat Kumar Gaana_Seminar and Technical Writing.pptx
120CR0393_Subrat Kumar Gaana_Seminar and Technical Writing.pptx120CR0393_Subrat Kumar Gaana_Seminar and Technical Writing.pptx
120CR0393_Subrat Kumar Gaana_Seminar and Technical Writing.pptx
 
Water retaining structures quick guide
Water retaining structures quick guideWater retaining structures quick guide
Water retaining structures quick guide
 
Bogie and suspension e book
Bogie and suspension e bookBogie and suspension e book
Bogie and suspension e book
 

Assessment and reinforcement of the 20 existing bridges in the Bozoum-Bossangoa road in Central African Republic. Presentation to the Ministry of Works.

  • 1. THE ROAD (137 km) AND THE BRIDGES REHABILITATION DE LA R.R. N°8 BOSSANGOA – BOZOUM BOSSANGOA BOZOUM OUHAM BAC
  • 2. EXISTING BRIDGES - DESCRIPTION REHABILITATION DE LA R.R. N°8 BOSSANGOA – BOZOUM STEEL GIRDERS TIMBER DECKING STONE MASONRY ABUTMENTS • THERE ARE 20 BRIDGES ON THE BOSSANGOA-BOZOUM ROAD • THE CONSTRUCTION METHOD IS THE SAME FOR ALL THE BRIDGES: TIMBER DECKING ON 4 STEEL GIRDERS WITH STONE MASONRY ABUTMENTS
  • 3. EXISTING BRIDGES - CONSERVATION STATE • TIMBER DECKING – ON THE BOSSANGOA SIDE, THE TIMBER DECKING IS STILL IN POSITION, BUT GENERALLY IN POOR CONDITION. – ON THE BOZOUM SIDE THE ORIGINAL DECKING HAS COLLAPSED AND HAS BEEN REPLACED BY WOODEN BRANCHES. • STEEL GIRDERS – THE CONDITION IS GOOD. • MASONRY ABUTMENTS – THE CONSERVATION IS GENERALLY GOOD, EXCEPT FOR 7 BRIDGES WITH CRACKS THAT REQUIRE REINFORCING. REHABILITATION DE LA R.R. N°8 BOSSANGOA – BOZOUM
  • 4. EXISTING BRIDGES - CONSERVATION STATE PONT N° 16 (BOSSANGOA SIDE) – THE TIMBER DECKING REHABILITATION DE LA R.R. N°8 BOSSANGOA – BOZOUM
  • 5. EXISTING BRIDGES - CONSERVATION STATE PONT N° 17 (BOSSANGOA SIDE) – THE TIMBER DECKING REHABILITATION DE LA R.R. N°8 BOSSANGOA – BOZOUM
  • 6. EXISTING BRIDGES - CONSERVATION STATE PONT N° 19 (BOSSANGOA SIDE) – THE TIMBER DECKING REHABILITATION DE LA R.R. N°8 BOSSANGOA – BOZOUM
  • 7. EXISTING BRIDGES - CONSERVATION STATE PONT N° 8 (BOZOUM SIDE) – THE TIMBER DECKING REHABILITATION DE LA R.R. N°8 BOSSANGOA – BOZOUM
  • 8. EXISTING BRIDGES - CONSERVATION STATE PONT N° 10 (BOZOUM SIDE) – THE TIMBER DECKING REHABILITATION DE LA R.R. N°8 BOSSANGOA – BOZOUM
  • 9. EXISTING BRIDGES - CONSERVATION STATE PONT N° 12 (BOZOUM SIDE) – THE TIMBER DECKING REHABILITATION DE LA R.R. N°8 BOSSANGOA – BOZOUM
  • 10. EXISTING BRIDGES - CONSERVATION STATE PONT N° 20 (BOZOUM SIDE) – THE STEEL GIRDERS REHABILITATION DE LA R.R. N°8 BOSSANGOA – BOZOUM
  • 11. EXISTING BRIDGES - CONSERVATION STATE PONT N° 4 (BOZOUM SIDE) – THE STEEL GIRDERS REHABILITATION DE LA R.R. N°8 BOSSANGOA – BOZOUM
  • 12. EXISTING BRIDGES - CONSERVATION STATE PONT N° 7 (BOZOUM SIDE) – THE STEEL GIRDERS REHABILITATION DE LA R.R. N°8 BOSSANGOA – BOZOUM
  • 13. EXISTING BRIDGES - CONSERVATION STATE PONT N° 4 (BOZOUM SIDE) – THE ABUTMENTS REHABILITATION DE LA R.R. N°8 BOSSANGOA – BOZOUM
  • 14. EXISTING BRIDGES - CONSERVATION STATE PONT N° 16 (BOSSANGOA SIDE) – THE ABUTMENTS REHABILITATION DE LA R.R. N°8 BOSSANGOA – BOZOUM
  • 15. EXISTING BRIDGES - CONSERVATION STATE PONT N° 20 (BOZOUM SIDE) – THE ABUTMENTS REHABILITATION DE LA R.R. N°8 BOSSANGOA – BOZOUM
  • 16. EXISTING BRIDGES - CONSERVATION STATE PONT N° 3 (BOZOUM SIDE) – THE ABUTMENTS REHABILITATION DE LA R.R. N°8 BOSSANGOA – BOZOUM
  • 17. EXISTING BRIDGES - CONSERVATION STATE PONT N° 18 (BOSSANGOA SIDE) – THE ABUTMENTS REHABILITATION DE LA R.R. N°8 BOSSANGOA – BOZOUM
  • 18. THE DESIGN • GOAL OF THE DESIGN: – REOPEN THE ROAD AND THE BRIDGES TO TRAFFIC IN A SAFE, FAST AND COST-EFFECTIVE WAY. WE HAVE TRIED TO CONSERVATE AND REUSE TO THE MAXIMUM THE EXISTING BRIDGES, IDENTIFYING THE ALLOWABLE LOAD OF THE STRUCTURES AND REINFORCEING THEM WHERE NEEDED. • METHOD OF WORK: – FOR ALL THE BRIDGES WE HAVE CONDUCTED A STRUCTURAL ANALYSIS WITH COMPUTER FINITE ELEMENT MODELS TO DEFINE THE MAXIMUM LOAD THAT THE BRIDGES CAN SUPPORT AND THEREFORE THE ALLOWABLE LOAD OF THE ROAD. THE CALCULATIONS HAVE BEEN DONE ACCORDING TO EUROCODES AND AASHTO “STANDARD SPECIFICATIONS FOR HIGHWAY BRIDGES”. REHABILITATION DE LA R.R. N°8 BOSSANGOA – BOZOUM
  • 19. THE DESIGN – THE STRUCTURAL ANALYSIS • DESIGN LOAD: (FROM AMERICAN AASHTO CODES) • THE MATERIALS: – TIMBER: MUKULUNGU – STEEL: ? FOR THE EXISTING GIRDERS WE HAVE NO INFORMATION ON THE GRADE OF THE STEEL AND ITS RESISTANCE. WE HAVE CONSERVATIVELY ASSUMED THAT THE GIRDERS ARE MADE OF S235 STEEL (yielding strength = 235 MPa) WHICH IS THE LOWEST OF THE 3 COMMERCIAL STEEL GRADES (235, 275 O 355 MPa) REHABILITATION DE LA R.R. N°8 BOSSANGOA – BOZOUM
  • 20. THE DESIGN – THE STRUCTURAL ANALYSIS REHABILITATION DE LA R.R. N°8 BOSSANGOA – BOZOUM FINITE ELEMENT MODEL (2D) FINITE ELEMENT MODEL (3D) BENDING MOMENT CALCULATED DEFLECTION MAXIMUM CALCULATED DEFLECTION
  • 21. THE DESIGN – CONCLUSIONS • REPLACE THE TIMBER DECKING FOR ALL BRIDGES • REINFORCE THE ABUTMENTS OF 7 BRIDGES • MAINTAIN THE STEEL GIRDERS FOR ALL BRIDGES EXCEPT BRIDGE N° 18 WHICH HAS A LOWER LOAD CAPACITY: 2 NEW GIRDERS WILL BE ADDED FOR THIS BRIDGE. REHABILITATION DE LA R.R. N°8 BOSSANGOA – BOZOUM
  • 22. THE DESIGN – REPLACEMENT OF THE DECKING REHABILITATION DE LA R.R. N°8 BOSSANGOA – BOZOUM MUKULUNGU TIMBER FOR TRANSVERSE MADRIERS AND LONGITUDINAL ELEMENTS: RESISTANT AND DURABLE
  • 23. THE DESIGN – REPLACEMENT OF THE DECKING REHABILITATION DE LA R.R. N°8 BOSSANGOA – BOZOUM CLOSER MADRIERS (25 cm INSTEAD OF 30 cm) TO INCREASE RESISTANCE AND SAFETY OF PEDESTRIANS RECONSTRUCTION OF THE SAFETY POSTS ON EACH SIDE OF THE ABUTMENTS TO ENSURE THAT VEHICLES TRAVEL ON THE CENTER OF THE BRIDGE
  • 24. THE DESIGN – REPLACEMENT OF THE DECKING REHABILITATION DE LA R.R. N°8 BOSSANGOA – BOZOUM RUNNING SURFACE MADE WITH 8 cm MADRIERS INSTEAD OF 3 cm PLANKS TO INCREASE DURABILITY
  • 25. THE DESIGN – REPLACEMENT OF THE DECKING REHABILITATION DE LA R.R. N°8 BOSSANGOA – BOZOUM LAG SCREWS INSTEAD OF NAILS TO INCREASE DURABILITY RUNNING SURFACE MADE WITH 8 cm MADRIERS INSTEAD OF 3 cm PLANKS TO INCREASE DURABILITY
  • 26. REHABILITATION DE LA R.R. N°8 BOSSANGOA – BOZOUM THE DESIGN – REINFORCEMENT OF THE ABUTMENTS • SIMPLE AND EFFECTIVE REINFORCEMENT TECHNIQUES (FOR EXAMPLE CONCRETE COATING) HAVE BEEN CHOSEN FOR THE ABUTMENTS EXAMPLE OF THE REINFORCEMENT FOR BRIDGES 1, 2, 14 AND 20:
  • 27. REHABILITATION DE LA R.R. N°8 BOSSANGOA – BOZOUM THE DESIGN – ALLOWABLE LOAD • THE CALCULATIONS HAVE SHOWN THAT, ASSUMING A STEEL RESISTANCE OF 235 MPa, ALL OF THE BRIDGES (EXCEPT ONE) CAN SUPPORT AN AXLE LOAD OF AT LEAST 100 kN (10 tons) • THE EXCEPTION IS BRIDGE n° 18 (pk 32.5) WHICH CAN SUPPORT AN AXLE LOAD OF JUST 70 kN (7 tons) • THEREFORE, BRIDGE N° 18 WILL BE REINFORCED BY ADDING 2 NEW GIRDERS BESIDES THE EXISTING ONES, INCREASING ITS LOAD CAPACITY TO 100 kN (10 tons). • TO ACCOUNT FOR POSSIBLE OVERLOADED TRUCKS, WE WILL CONSIDER AN ADDITIONAL 15% SAFETY FACTOR, THEREFORE THE ALLOWABLE AXLE LOAD ON THE ROAD WILL BE: 85 kN (8.5 tons)
  • 28. REHABILITATION DE LA R.R. N°8 BOSSANGOA – BOZOUM BRIDGE n° 18 – REINFORCEMENT • TWO NEW GIRDERS WILL BE ADDED BESIDES THE EXISTING ONES, INCREASING THE LOAD CAPACITY
  • 29. REHABILITATION DE LA R.R. N°8 BOSSANGOA – BOZOUM TEST LOADS – DURING CONSTRUCTION • DURING CONSTRUCTION IT WILL BE IMPORTANT TO CHECK THAT THE BENDING RESISTANCE OF THE MUKULUNGU TIMBER ISN’T LOWER THAN THE VALUE CONSIDERED IN THE DESIGN (30 MPa) • SIMPLE RESISTANCE TESTS WILL HAVE TO BE MADE ON THE TIMBER MADRIERS
  • 30. REHABILITATION DE LA R.R. N°8 BOSSANGOA – BOZOUM TEST LOADS – DURING CONSTRUCTION • TEST LOADS ON THE TIMBER MADRIERS
  • 31. REHABILITATION DE LA R.R. N°8 BOSSANGOA – BOZOUM TEST LOADS – AFTER CONSTRUCTION • AFTER CONSTRUCTION IT WILL BE IMPORTANT TO CHECK THAT THE RESPONSE OF THE BRIDGE CORRESPONDS TO THE EXPECTED PERFORMANCE. • LOAD TESTS WILL BE MADE ON THE BRIDGES TO CHECK THAT THE REAL DEFLECTION CORRESPONDS TO THE CALCULATED DEFLECTION. A TRUCK WITH THE SAME WEIGHT AS THE DESIGN LOAD WILL STAY ON THE BRIDGE WITH THE AXLE PLACED IN MIDSPAN, AND THE MAXIMUM DEFLECTION WILL BE MEASURED WITH A DIAL GAUGE.
  • 32. REHABILITATION DE LA R.R. N°8 BOSSANGOA – BOZOUM MAINTENANCE AND MONITORING IN ORDER TO ENSURE THE DURABILITY OF THE BRIDGES IT IS NECESSARY TO REGULARLY MAINTAIN AND MONITOR THEM. • TIMBER RUNNING SURFACE: IT IS ONE OF THE MOST EXPOSED PARTS TO WEAR AND DEGRADATION, AND SHOULD BE CHECKED EVERY 4 MONTHS TO IDENTIFY DAMAGED PARTS THAT SHOULD BE REPLACED. • TRANSVERSE MADRIERS: THE TRANSVERSE MADRIERS SHOULD BE INSPECTED EVERY 4 MONTHS TO FIND DAMAGED OR BROKEN ELEMENTS THAT SHOULD BE IMMEDIATELY REPLACED. • TIMBER CONNECTIONS: THE CONNECTIONS BETWEEN THE TIMBER ELEMENTS ARE PARTICULARLY SENSITIVE TO VIBRATIONS AND TRAFFIC. THEY SHOULD BE CHECKED EVERY 4 MONTHS; THEY SHOULD BE TIGHTENED WHEN NECESSARY, AND REPLACED IMMEDIATELY IF FOUND TO BE MISSING. • SAFETY POSTS: THE SAFETY POSTS ON THE ABUTMENTS ARE ESSENTIAL FOR THE SAFETY OF THE BRIDGES: THEY SHOULD BE CHECKED EVERY 2 MONTHS AND IMMEDIATELY REPLACED IF BROKEN. • ABUTMENTS: ABUTMENTS SHOULD BE CHECKED REGULARLY FOR CRACKS, DISPLACED STONES, SCOUR ON FOUNDATIONS, ETC. AND APPROPRIATE RECONSTRUCTION/REINFORCEMENT SHOULD BE DONE. A COMPLETE INSPECTION SHOULD BE DONE EVERY SIX MONTHS. • VEGETATION: VEGETATION SHOULD BE CLEARED FROM THE BRIDGE ANNUALLY. VEGETATION SHOULD ALSO CAREFULLY BE REMOVED FROM THE ABUTMENTS WITHOUT DAMAGING THE MASONRY.
  • 33. REHABILITATION DE LA R.R. N°8 BOSSANGOA – BOZOUM THANKYOU FOR YOUR ATTENTION

Notas del editor

  1. 1.5 Safety factor for yielding (according to Eurocodes) + approx. 30% for dynamic impact factor + aprox. 25% for eccentric loading