26   Chapter 1
exam questions
1. The project manager for a construction project discovers that a new water line is being created in the
neighborhood where he’s managing a project. Company policy requires that a series of forms for city
environmental changes need to be filled out before his team can continue work on the project. This is an
example of:
A portfolioA.	
A programB.	
An enterprise environmental factorC.	
A projectD.	
2. Which of the following is NOT a characteristic of a project?
TemporaryA.	
StrategicB.	
Specific resultC.	
Progressively elaboratedD.	
3. An energy company is investing in a series of initiatives to look for alternative energy sources so that the
company can be competitive in 10 years. The initaitives are tracked and managed together because this goal
is vital to the success of the company. This is an example of...
A portfolioA.	
B.	 A program
A projectC.	
A enterprise environmental factorD.	
4. Which of the following is NOT a responsibility of a project manager?
Managing stakeholder expectationsA.	
Managing project constraintsB.	
Gathering product requirementsC.	
Sponsoring the projectD.	
5. Which of the following is NOT a Process Group?
Monitoring and ControllingA.	
Gathering RequirementsB.	
InitiatingC.	
ClosingD.	
Exam Questions
Download at Boykma.Com
you are here 4   27
introduction to the pmp exam
6. Which of the following is NOT a knowledge area?
ScopeA.	
IntegrationB.	
ProcurementC.	
D.	 Initiating
7. Which of the following is NOT true about portfolio management?
The portfolio manager judges success of the portfolio by combining data from all of its programs andA.	
projects
A portfolio can contain projects and programsB.	
A portfolio is organized around a business goalC.	
A portfolio is always a group of programsD.	
8. You’re managing a project to remodel a kitchen. You use earned value calculations to figure out that
you’re going to run $500 over budget if your project continues at the current rate. Which of the following
core characteristics of a project manager are you using to find the problem?
KnowledgeA.	
PerformanceB.	
PersonalC.	
None of the aboveD.	
9. At the beginning of a project, a software team project manager is given a schedule with everyone’s
vacations on it. She realizes that because the software will be delivered to the QA team exactly when they
have overlapping vacations, there is a serious risk of quality problems because there won’t be anyone to test
the software before it goes into production. What BEST describes the constraint this places on the project?
Quality constraintA.	
Time constraintB.	
Resource constraintC.	
Risk constraintD.	
10. A project manager is having trouble with his project because one of his team members is not performing,
which is causing him to miss an important date he promised to a stakeholder. He discovers that the team
member knew about the project problem, but didn’t tell him because the team members are all afraid of his
bad temper. Which BEST describes how the project manager can avoid this situation in the future?
Increasing his knowledge of the PMBOK® GuideA.	
Measuring personal performanceB.	
Improving his personal skillsC.	
Managing stakeholder expectationsD.	
Exam Questions
Download at Boykma.Com
28   Chapter 1
exam questions answers
1. Answer: C
Since the project manager is filling out forms because of company policy, this is a good example of an
enterprise environmental factor.
2. Answer: B
A project doesn’t have to be strategic or critical. It only needs to be temporary, have a specific result and be
progressively elaborated.
3. Answer: A
Since the initiatives are being managed together because of a strategic business goal, you can tell that this is
a portfolio.
4. Answer: D
The sponsor is the person who pays for the project. The project manager doesn’t usually play that role.
5. Answer: B
The process groups categorize all of the activities that a project goes through in its lifecycle. They are Initiatng,
Planning, Executing, Monitoring and Controlling, and Closing.
6. Answer: D
Initiating is a process group, not a knowledge area. The process groups help you to think about all of the
different stages a project goes through from the time it is first imagined until it is completed. The knowledge
areas are all the things you need to think about as your project goes through those stages.
7. Answer: D
Since a portfolio can be a group of programs and projects, option D is the one that’s not true. It can be a group
of programs, but it doesn’t have to be.
Exam Questions
Answers
Look out for questions like this one on the exam. Common sensemight tell you that a project should be important for a company towant to do it, but that’s not what the question is asking.
Portfolios are organized around business goals and programs areorganized around a shared benefit in managing them together.
Download at Boykma.Com
you are here 4   29
introduction to the pmp exam
Exam Questions
Answers
8. Answer: A
Your knowledge of Earned Value Management techniques is how you can predict that the project will be
over budget. Knowing that could let you plan ahead to avoid further cost overruns. Minimally, it can help
you to reset expectations with your stakeholders so they have a better idea of what’s coming.
9. Answer: C
This is a resource constraint, because the project manager’s resources – in this case, the people who will
be testing the software – are not going to be available to her when she needs them. Yes, this will cause
problems with the quality, introduce risks, and cause schedule problems. But they’re not schedule, time or
risk constraints, because there’s no outside limitation placed on the project quality, schedule or risks. The
only outside limitation is the resource availability. If they were available, there wouldn’t be a problem!
10. Answer: C
The way that the project manager interacts with the people on his team interfered with his work getting
done. This is a good example of how a lack of personal skills can lead directly to major project problems
down the line, and it’s why this particular project manager needs to work on his personal skills.
You made it through
your first chapter and
exam questions! How’d
it go?
The project manager’s temper
led to a disappointed stakeholder,
but that doesn’t mean that the
stakeholder’s expectations were
out of line. This was an avoidable
project problem, and better
personal skills would have fixed it..
Download at Boykma.Com

Más contenido relacionado

La actualidad más candente

10 pmp communication management exam
10 pmp communication  management exam10 pmp communication  management exam
10 pmp communication management exam
Jamil Faraj , PMP
 
PMP Training - 01 introduction to framework
PMP Training - 01 introduction to frameworkPMP Training - 01 introduction to framework
PMP Training - 01 introduction to framework
ejlp12
 

La actualidad más candente (20)

Pmp4
Pmp4Pmp4
Pmp4
 
05 pmp scope management exam
05 pmp scope management exam05 pmp scope management exam
05 pmp scope management exam
 
04 pmp integration management exam
04 pmp integration management exam04 pmp integration management exam
04 pmp integration management exam
 
Exam1
Exam1Exam1
Exam1
 
Introduction to Project Management (workshop) - v.1
Introduction to Project Management (workshop) - v.1Introduction to Project Management (workshop) - v.1
Introduction to Project Management (workshop) - v.1
 
03 pmp project management processes exam
03 pmp project management processes exam03 pmp project management processes exam
03 pmp project management processes exam
 
Project Management Concepts
Project Management ConceptsProject Management Concepts
Project Management Concepts
 
11 pmp risk management exam
11 pmp risk management exam11 pmp risk management exam
11 pmp risk management exam
 
Introduction to Project Management by Javid Hamdard
Introduction to Project Management by Javid HamdardIntroduction to Project Management by Javid Hamdard
Introduction to Project Management by Javid Hamdard
 
Project management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areasProject management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areas
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
 
10 pmp communication management exam
10 pmp communication  management exam10 pmp communication  management exam
10 pmp communication management exam
 
Pmp5
Pmp5Pmp5
Pmp5
 
07 pmp cost management exam
07 pmp cost management exam07 pmp cost management exam
07 pmp cost management exam
 
12 pmp procurement management exam
12 pmp procurement management exam12 pmp procurement management exam
12 pmp procurement management exam
 
Risk 2 simplelearn-exam1-ans
Risk 2 simplelearn-exam1-ansRisk 2 simplelearn-exam1-ans
Risk 2 simplelearn-exam1-ans
 
Pmp6
Pmp6Pmp6
Pmp6
 
Pmp Questions Complete
Pmp Questions CompletePmp Questions Complete
Pmp Questions Complete
 
PMP Training - 01 introduction to framework
PMP Training - 01 introduction to frameworkPMP Training - 01 introduction to framework
PMP Training - 01 introduction to framework
 
Microsoft Projects; a step by-step guide for beginner's
Microsoft Projects; a step by-step guide for beginner'sMicrosoft Projects; a step by-step guide for beginner's
Microsoft Projects; a step by-step guide for beginner's
 

Similar a 01 pmp introduct to project management exam

PMP assessment exam 1.1
PMP assessment exam 1.1PMP assessment exam 1.1
PMP assessment exam 1.1
Daniel Hucks
 
Chapter 2 Questionsand Answers1. There is a difference between t.docx
Chapter 2 Questionsand Answers1. There is a difference between t.docxChapter 2 Questionsand Answers1. There is a difference between t.docx
Chapter 2 Questionsand Answers1. There is a difference between t.docx
walterl4
 
1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docx1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docx
jackiewalcutt
 

Similar a 01 pmp introduct to project management exam (20)

PMP Certificate- introduction
PMP Certificate- introductionPMP Certificate- introduction
PMP Certificate- introduction
 
PMP-Prep-Exam-Test-200_Questions.pdf
PMP-Prep-Exam-Test-200_Questions.pdfPMP-Prep-Exam-Test-200_Questions.pdf
PMP-Prep-Exam-Test-200_Questions.pdf
 
PMP assessment exam 1.1
PMP assessment exam 1.1PMP assessment exam 1.1
PMP assessment exam 1.1
 
Chapter 2 Questionsand Answers1. There is a difference between t.docx
Chapter 2 Questionsand Answers1. There is a difference between t.docxChapter 2 Questionsand Answers1. There is a difference between t.docx
Chapter 2 Questionsand Answers1. There is a difference between t.docx
 
Pmi rmp
Pmi rmpPmi rmp
Pmi rmp
 
Risk 1 actual test 7 (273 q)
Risk 1 actual test 7 (273 q)Risk 1 actual test 7 (273 q)
Risk 1 actual test 7 (273 q)
 
Mb0049 project management
Mb0049   project management Mb0049   project management
Mb0049 project management
 
Mb0049 project management
Mb0049   project managementMb0049   project management
Mb0049 project management
 
Mb0049 project management
Mb0049   project managementMb0049   project management
Mb0049 project management
 
PMP Exam Sample Questions
PMP Exam Sample QuestionsPMP Exam Sample Questions
PMP Exam Sample Questions
 
Pmp Five Sample Questions
Pmp Five Sample QuestionsPmp Five Sample Questions
Pmp Five Sample Questions
 
PMP Exam Sample Questions
PMP Exam Sample QuestionsPMP Exam Sample Questions
PMP Exam Sample Questions
 
Pmp test 03
Pmp test 03Pmp test 03
Pmp test 03
 
15 Free PMP Exam Questions
15 Free PMP Exam Questions15 Free PMP Exam Questions
15 Free PMP Exam Questions
 
PMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdfPMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdf
 
1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docx1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docx
 
Free PMP Exam Q & A
Free PMP Exam Q & AFree PMP Exam Q & A
Free PMP Exam Q & A
 
PMP® Sample Questions Set #2
PMP® Sample Questions Set #2PMP® Sample Questions Set #2
PMP® Sample Questions Set #2
 
9 Common Challenges in the Software Development Process
9 Common Challenges in the Software Development Process9 Common Challenges in the Software Development Process
9 Common Challenges in the Software Development Process
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 

Más de Jamil Faraj , PMP

Más de Jamil Faraj , PMP (13)

Corona-virus PMP study plan
Corona-virus PMP study planCorona-virus PMP study plan
Corona-virus PMP study plan
 
PMP Study Plan by Jamil Faraj, PMP
PMP Study Plan by Jamil Faraj, PMPPMP Study Plan by Jamil Faraj, PMP
PMP Study Plan by Jamil Faraj, PMP
 
Jamil Faraj CV 2020
Jamil Faraj CV 2020Jamil Faraj CV 2020
Jamil Faraj CV 2020
 
Jamil faraj hassan CV
Jamil faraj hassan CVJamil faraj hassan CV
Jamil faraj hassan CV
 
PMP ITTOs Quick Review
PMP ITTOs Quick Review PMP ITTOs Quick Review
PMP ITTOs Quick Review
 
Jamil pmp Certificate 2020
Jamil pmp Certificate 2020Jamil pmp Certificate 2020
Jamil pmp Certificate 2020
 
2
22
2
 
Pmp3
Pmp3Pmp3
Pmp3
 
Jamil Hassan, PMP lessons learned.
Jamil Hassan, PMP lessons learned.Jamil Hassan, PMP lessons learned.
Jamil Hassan, PMP lessons learned.
 
Jamil Faraj CV- English
Jamil Faraj CV- EnglishJamil Faraj CV- English
Jamil Faraj CV- English
 
Pmp Formula Pocket_Guide
Pmp Formula Pocket_GuidePmp Formula Pocket_Guide
Pmp Formula Pocket_Guide
 
دورة وظيفة العمر
دورة وظيفة العمردورة وظيفة العمر
دورة وظيفة العمر
 
06 pmp time management exam
06 pmp time  management exam06 pmp time  management exam
06 pmp time management exam
 

Último

Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Sheetaleventcompany
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
amitlee9823
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
lizamodels9
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
Matteo Carbone
 
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
amitlee9823
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
dlhescort
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
lizamodels9
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
dollysharma2066
 
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service NoidaCall Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
dlhescort
 
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
amitlee9823
 

Último (20)

Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptx
 
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
 
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
 
Business Model Canvas (BMC)- A new venture concept
Business Model Canvas (BMC)-  A new venture conceptBusiness Model Canvas (BMC)-  A new venture concept
Business Model Canvas (BMC)- A new venture concept
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
 
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort ServiceEluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service NoidaCall Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
 
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service AvailableCall Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
 
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
 

01 pmp introduct to project management exam

  • 1. 26   Chapter 1 exam questions 1. The project manager for a construction project discovers that a new water line is being created in the neighborhood where he’s managing a project. Company policy requires that a series of forms for city environmental changes need to be filled out before his team can continue work on the project. This is an example of: A portfolioA. A programB. An enterprise environmental factorC. A projectD. 2. Which of the following is NOT a characteristic of a project? TemporaryA. StrategicB. Specific resultC. Progressively elaboratedD. 3. An energy company is investing in a series of initiatives to look for alternative energy sources so that the company can be competitive in 10 years. The initaitives are tracked and managed together because this goal is vital to the success of the company. This is an example of... A portfolioA. B. A program A projectC. A enterprise environmental factorD. 4. Which of the following is NOT a responsibility of a project manager? Managing stakeholder expectationsA. Managing project constraintsB. Gathering product requirementsC. Sponsoring the projectD. 5. Which of the following is NOT a Process Group? Monitoring and ControllingA. Gathering RequirementsB. InitiatingC. ClosingD. Exam Questions Download at Boykma.Com
  • 2. you are here 4   27 introduction to the pmp exam 6. Which of the following is NOT a knowledge area? ScopeA. IntegrationB. ProcurementC. D. Initiating 7. Which of the following is NOT true about portfolio management? The portfolio manager judges success of the portfolio by combining data from all of its programs andA. projects A portfolio can contain projects and programsB. A portfolio is organized around a business goalC. A portfolio is always a group of programsD. 8. You’re managing a project to remodel a kitchen. You use earned value calculations to figure out that you’re going to run $500 over budget if your project continues at the current rate. Which of the following core characteristics of a project manager are you using to find the problem? KnowledgeA. PerformanceB. PersonalC. None of the aboveD. 9. At the beginning of a project, a software team project manager is given a schedule with everyone’s vacations on it. She realizes that because the software will be delivered to the QA team exactly when they have overlapping vacations, there is a serious risk of quality problems because there won’t be anyone to test the software before it goes into production. What BEST describes the constraint this places on the project? Quality constraintA. Time constraintB. Resource constraintC. Risk constraintD. 10. A project manager is having trouble with his project because one of his team members is not performing, which is causing him to miss an important date he promised to a stakeholder. He discovers that the team member knew about the project problem, but didn’t tell him because the team members are all afraid of his bad temper. Which BEST describes how the project manager can avoid this situation in the future? Increasing his knowledge of the PMBOK® GuideA. Measuring personal performanceB. Improving his personal skillsC. Managing stakeholder expectationsD. Exam Questions Download at Boykma.Com
  • 3. 28   Chapter 1 exam questions answers 1. Answer: C Since the project manager is filling out forms because of company policy, this is a good example of an enterprise environmental factor. 2. Answer: B A project doesn’t have to be strategic or critical. It only needs to be temporary, have a specific result and be progressively elaborated. 3. Answer: A Since the initiatives are being managed together because of a strategic business goal, you can tell that this is a portfolio. 4. Answer: D The sponsor is the person who pays for the project. The project manager doesn’t usually play that role. 5. Answer: B The process groups categorize all of the activities that a project goes through in its lifecycle. They are Initiatng, Planning, Executing, Monitoring and Controlling, and Closing. 6. Answer: D Initiating is a process group, not a knowledge area. The process groups help you to think about all of the different stages a project goes through from the time it is first imagined until it is completed. The knowledge areas are all the things you need to think about as your project goes through those stages. 7. Answer: D Since a portfolio can be a group of programs and projects, option D is the one that’s not true. It can be a group of programs, but it doesn’t have to be. Exam Questions Answers Look out for questions like this one on the exam. Common sensemight tell you that a project should be important for a company towant to do it, but that’s not what the question is asking. Portfolios are organized around business goals and programs areorganized around a shared benefit in managing them together. Download at Boykma.Com
  • 4. you are here 4   29 introduction to the pmp exam Exam Questions Answers 8. Answer: A Your knowledge of Earned Value Management techniques is how you can predict that the project will be over budget. Knowing that could let you plan ahead to avoid further cost overruns. Minimally, it can help you to reset expectations with your stakeholders so they have a better idea of what’s coming. 9. Answer: C This is a resource constraint, because the project manager’s resources – in this case, the people who will be testing the software – are not going to be available to her when she needs them. Yes, this will cause problems with the quality, introduce risks, and cause schedule problems. But they’re not schedule, time or risk constraints, because there’s no outside limitation placed on the project quality, schedule or risks. The only outside limitation is the resource availability. If they were available, there wouldn’t be a problem! 10. Answer: C The way that the project manager interacts with the people on his team interfered with his work getting done. This is a good example of how a lack of personal skills can lead directly to major project problems down the line, and it’s why this particular project manager needs to work on his personal skills. You made it through your first chapter and exam questions! How’d it go? The project manager’s temper led to a disappointed stakeholder, but that doesn’t mean that the stakeholder’s expectations were out of line. This was an avoidable project problem, and better personal skills would have fixed it.. Download at Boykma.Com