10 PMP Questions
1. Your company provides specialized IT support services for firmware upgrades. Your
country’s government has passed regulations stating that firmware of all
telecommunication equipment must be upgraded to support IPv6. A government
agency has approached your company to upgrade the firmware of all installed
equipment at the major airports in the country. For your company, this project is a
result of which of the following:
A) Market demand
B) Strategic opportunity
C) Customer request
D) Legal requirement
Anwer: C
Hint: The government agency is asking your company to do a project.
PMBOK Guide 5th Edition, page 69
This is a tricky scenario and the answer is at first a bit surprising. Let’s look at this from the point of
view of both the government and your company:
The government agency approached your company to do this project because they are bound by their
own regulations. So for the government, this project was initiated as a result of their own legal
requirement.For your company, however, the project is initiated by a customer request.
Remember that you don’t own the airports nor the equipment installed there so you don’t have a legal
requirement to update the firmware. The government, on the other hand, owns the airports/equipment
and is therefore asking you to perform this update. In this case, the government is a customer like any
other customer and you are doing this project as result of their request.
2. Nancy is the project manager for a project that will be closing shortly. During a quality
inspection, Nancy detects that the project team has added additional features to one of the
project deliverables that was not authorized. However, Nancy believes that these new
features will add to customer satisfaction. What is Nancy’s best alternative in this situation?
A) Submit a change request to remove these additional features
B) Accept these additional features and proudly present them to the customer
C) Ask the project sponsor for his opinion
D) Ask the customers for their opinion
Answer: A
Hint: Unauthorized feature additions are called gold-plating and this needs to be avoided.
Unauthorized feature additions are called gold-plating and this needs to be avoided. If such features have
been included, they need to be removed using a change request, even if they add to customer satisfaction.
Every project must conform to its approved requirements; nothing more, nothing less.
PMI Code of Ethics and Professional Conduct:
http://en.wikipedia.org/wiki/Gold_plating_(software_engineering)
3. Marilyn’s project is behind schedule. Marilyn opens her scheduling tool and adjusts some
leads and lags in order to fast track the project. As a result, the project is aligned with the
current time constraint. However, when Marilyn uses the “Level Resources” feature, the
project finish date again goes past the time constraint. What is Marilyn’s best option?
A) Marilyn must make sure that she did not make a mistake when using the “Level Resources”
feature
B) Marilyn must not use the “Level Resources” feature after fast tracking the project
C) Marilyn must crash the project after fast tracking it
D) Marilyn must issue a change request
Answer: D
Hint: When the “Resource Leveling” feature delays a project, it means that the resources were over-
allocated.
When the “Resource Leveling” feature delays a project, it means that the resources were over-allocated.
Completing the project on time at the cost of over-utilizing the resources, and especially human resources,
is not ethical. If fast tracking followed by resource leveling does not help in reducing the project time
requirements, Marilyn must consider issuing a change request to obtain additional resources or get the
project deadline extended.
PMI Code of Ethics and Professional Conduct, Honesty
PMBOK Guide 5th Edition, page 179
4. You are managing an automated security system design project. You now want to analyze the
relationship between the consumption of project funds and the physical work being
accomplished for these expenditures. Which of the following should you have completed
before you can perform this activity?
A) Deliverables
B) Reserve Analysis
C) Trend Analysis
D) Project Funding Requirements
Answer:D
Hint: The scenario describes an activity in the Control Costs process.
Did this question confuse you? If yes, then you first need to decipher it. The activity that you want to carry
out is an example of which project management process? The Control Costs process. Once you realize this,
you will see that “Project Management Plan”, “Project Funding Requirements” and “Work Performance
Data” are important inputs to the Control Costs process.
PMBOK Guide 5th Edition, page 215
5. You have just been assigned as the project manager for a process improvement project. You
have broken down your project work into a number of work packages including stakeholder
interviews, surveys, statistical analysis, flow charting of the current processes, analysis of the
processes, cost estimations, and recommendations. You are currently performing the Plan
Quality Management process. Which quality technique should you use during your project
and in your Quality Management Plan if you wish to analyze all the possible process points of
failure and the potential impact they may have?
A) Kaizen approach
B) Total Quality Management (TQM)
C) Failure mode and effects analysis
D) Six Sigma
Answer: C
This technique was formally introduced in the late 1940′s for military use by the U.S. Armed Forces. It was
later used for aerospace/rocket development to avoid errors in small sample sizes of costly rocket
technology. An example of this is the Apollo space program.
Failure modes and effects analysis (FMEA) is a procedure in operations management for analysis of
potential failure modes within a system for classification by severity or determination of the effect of
failures on the system. Failure modes are any errors or defects in a process, design, or item, especially
those that affect the customer, and can be potential or actual. Effects analysis refers to studying the
consequences of those failures.
en.wikipedia.org/wiki/Failure_mode_and_effects_analysis PMBOK Guide 5th Edition, page 540
6. You are in the executing phase of your project. You have spent a lot of time negotiating for
the best human resources but the people you have obtained do not have the expertise
necessary to complete the project activities, according to the Project Management Plan.
What is the first thing you should do to try to remedy this situation?
A) Update the Human Resource Management Plan
B) Issue a change request
C) Renegotiate for the required human resources
D) Provide training to the under-skilled human resources
Answer:A
The scenario says that you were unable to acquire a project team according to your plan.
Renegotiating is not a good option as you have already acquired resources. You only issue a change
request when there is a required change in the project baselines. You will also most likely need to provide
training to your under-skilled staff. However, the first thing you need to do is to update the Human
Resource Management Plan to reflect your current staff’s expertise levels and training requirements.
PMBOK Guide 5th Edition, page 272
7. You are managing a telecom project. You have two teams reporting to you. One team is
responsible for equipment installation and the other team is responsible for commissioning
and testing the equipment. Both teams are working in parallel so that as soon as the
installation team finishes equipment installation at one site, they move on to another site for
installation. This allows the commissioning and testing team to start their activities on the
newly installed site. The reporting structure is such that each of the teams has five engineers
and a separate team lead. Each team member interacts with each other but only the team
leads interact with you. Both team leads also interact with each other to synchronize their
operations. How many communication channels do you have on your project?
A) 33
B) 23
C) 42
D) 78
Calculate communication channels for each team and add them together.
This was a difficult question wasn’t it? Let’s analyze the scenario to calculate the answer. We have two
independent teams. Each team has six members (five engineers and one team lead). Each team
member is interacting with each other so communication channels for each team are (6)*(6-1)/2=15.
And because we have two teams like this, the total is 2*15=30. Both team leads are communicating
with you so there are two communication channels for this interaction. In addition, because both team
leads are interacting with each other, there is one additional communication channel. Therefore, the
total communication channels on your project is 30+2+1=33.
PMBOK Guide 5th Edition, page 292
8. Rhonda’s project is half-way complete. None of the project risks have occurred and none of
the contingency reserves have been used. Rhonda finds a few new risks to the project that
were not added to the risk register during the planning phase. Rhonda quickly calculates the
expected values of these risks and requests management to increase the contingency reserve
by the amount required to manage these new risks. What’s wrong with Rhonda’s approach to
dealing with risks?
A) Rhonda should not have requested the increase
B) New risks must be managed with the available management reserves
C) Rhonda should have done a reserve analysis first
D) Rhonda should have first used the contingency amounts for those risks that did not occur
Answer: C
If new and unidentified risks occur, they are managed using management reserves (after management
approval to use the funds). However in this case, the new risks have not occurred, they have only just
been identified.
In this scenario, new risks have been identified. Rhonda can request an increase in the contingency
reserves after she carries out a reserve analysis to determine if the additional funds are indeed
required.
PMI Code of Ethics and Professional Conduct, Responsibility
PMBOK Guide 5th Edition, page 352
9. You are managing a construction project. You have outsourced the labor workforce to a
contractor using a Time and Materials contract. As per the contract, your contractor is
claiming $10 per hour for labor and an average of 10 hours a day per each labor resource
provided. You know that on average only 8 of these 10 hours per day were actually
productive time spent on the project. However, your contract doesn’t state anything
specifically about charging for unproductive time. You now have a hold on all of the
contractor’s invoices until you reach a resolution. Which of the following might be a factor
contributing to this situation?
A) Your contractor is being unreasonable
B) You are being unreasonable towards the contractor
C) You have not drafted the contract properly
D) You have not negotiated the contract properly
Answer: C
Why doesn’t your contract say anything about this?
Don’t get distracted by the scenario. The scenario may put you in the shoes of the project manger, but it
does not mean that you are always right! Assume that you are not the project manager for a moment. In
that case you cannot resolve this dispute in any party’s favor just with the information given. However, you
can easily spot the weakness in the contract since it should have clauses regarding issues such as these.
PMBOK Guide 5th Edition, page 364
10. You are running a public library construction project in which two key stakeholders are in
continuous conflict with each other over location and design of the building. As a project
manager, you have spent many hours resolving their conflicts, but it isn’t getting any better.
What should you do next?
A) Refer to the Project Charter for the escalation process
B) Refer to the Communications Plan for the escalation process
C) Involve the core project team
D) Involve the sponsor
Answer: B
The Communications Plan contains the information about the escalation process.
If a project manager cannot resolve the conflict between stakeholders, he/she should escalate the issue
based on the escalation process listed in the Communications Plan.
PMBOK Guide 5th Edition, page 406

Más contenido relacionado

La actualidad más candente

La actualidad más candente (20)

07 pmp cost management exam
07 pmp cost management exam07 pmp cost management exam
07 pmp cost management exam
 
Pmp4
Pmp4Pmp4
Pmp4
 
Pmp5
Pmp5Pmp5
Pmp5
 
04 pmp integration management exam
04 pmp integration management exam04 pmp integration management exam
04 pmp integration management exam
 
04 pmp integration management exam
04 pmp integration management exam04 pmp integration management exam
04 pmp integration management exam
 
05 pmp scope management exam
05 pmp scope management exam05 pmp scope management exam
05 pmp scope management exam
 
06 pmp time management exam
06 pmp time  management exam06 pmp time  management exam
06 pmp time management exam
 
Pmp3
Pmp3Pmp3
Pmp3
 
02 pmp project life cycle exam
02 pmp project life cycle exam02 pmp project life cycle exam
02 pmp project life cycle exam
 
Pmp1
Pmp1Pmp1
Pmp1
 
PMP 1600 Questions by TechFAQ360
PMP 1600 Questions by TechFAQ360PMP 1600 Questions by TechFAQ360
PMP 1600 Questions by TechFAQ360
 
11 pmp risk management exam
11 pmp risk management exam11 pmp risk management exam
11 pmp risk management exam
 
12 pmp procurement management exam
12 pmp procurement management exam12 pmp procurement management exam
12 pmp procurement management exam
 
Pmp6
Pmp6Pmp6
Pmp6
 
Pmstudy exam 4
Pmstudy exam 4Pmstudy exam 4
Pmstudy exam 4
 
Project Management Professional (PMP) | Lesson 02 | Project Management Framework
Project Management Professional (PMP) | Lesson 02 | Project Management FrameworkProject Management Professional (PMP) | Lesson 02 | Project Management Framework
Project Management Professional (PMP) | Lesson 02 | Project Management Framework
 
Pmi sp questions with answers
Pmi sp questions with answersPmi sp questions with answers
Pmi sp questions with answers
 
Pmp test 02
Pmp test 02Pmp test 02
Pmp test 02
 
13 pmp professional responsibility exam
13 pmp professional responsibility exam13 pmp professional responsibility exam
13 pmp professional responsibility exam
 
Pmp stakeholder chapter 13
Pmp stakeholder chapter 13Pmp stakeholder chapter 13
Pmp stakeholder chapter 13
 

Destacado (7)

2
22
2
 
Jamil faraj hassan CV
Jamil faraj hassan CVJamil faraj hassan CV
Jamil faraj hassan CV
 
Jamil Hassan, PMP lessons learned.
Jamil Hassan, PMP lessons learned.Jamil Hassan, PMP lessons learned.
Jamil Hassan, PMP lessons learned.
 
Pmp Formula Pocket_Guide
Pmp Formula Pocket_GuidePmp Formula Pocket_Guide
Pmp Formula Pocket_Guide
 
Jamil Faraj CV- English
Jamil Faraj CV- EnglishJamil Faraj CV- English
Jamil Faraj CV- English
 
Jamil pmp Certificate 2020
Jamil pmp Certificate 2020Jamil pmp Certificate 2020
Jamil pmp Certificate 2020
 
175 pmp sample_questions
175 pmp sample_questions175 pmp sample_questions
175 pmp sample_questions
 

Similar a Pmp exam q&a

Pm0011 project planning and scheduling
Pm0011   project planning and schedulingPm0011   project planning and scheduling
Pm0011 project planning and scheduling
smumbahelp
 
aw_survivalguide_r2opt
aw_survivalguide_r2optaw_survivalguide_r2opt
aw_survivalguide_r2opt
Reza Abed
 
Running Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT .docx
Running Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT      .docxRunning Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT      .docx
Running Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT .docx
jeanettehully
 
Running head PROJECT CHARTER ABOUT CREATING A WEBSITE FOR HR .docx
Running head PROJECT CHARTER ABOUT CREATING A WEBSITE FOR HR   .docxRunning head PROJECT CHARTER ABOUT CREATING A WEBSITE FOR HR   .docx
Running head PROJECT CHARTER ABOUT CREATING A WEBSITE FOR HR .docx
toltonkendal
 
FIN320 – Gallaher – Prep for Exam 3 – Computational Questions1.docx
FIN320 – Gallaher – Prep for Exam 3 – Computational Questions1.docxFIN320 – Gallaher – Prep for Exam 3 – Computational Questions1.docx
FIN320 – Gallaher – Prep for Exam 3 – Computational Questions1.docx
mydrynan
 
Sheet2ScoresMaxActualComments1. Effort Estimate. Estimate the e.docx
Sheet2ScoresMaxActualComments1.  Effort Estimate.   Estimate the e.docxSheet2ScoresMaxActualComments1.  Effort Estimate.   Estimate the e.docx
Sheet2ScoresMaxActualComments1. Effort Estimate. Estimate the e.docx
bjohn46
 
Scope Statement1Scope Statement10Scope StatementCP.docx
Scope Statement1Scope Statement10Scope StatementCP.docxScope Statement1Scope Statement10Scope StatementCP.docx
Scope Statement1Scope Statement10Scope StatementCP.docx
bagotjesusa
 
VoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docx
VoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docxVoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docx
VoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docx
jessiehampson
 

Similar a Pmp exam q&a (20)

about start up for you 12
about start up for you 12about start up for you 12
about start up for you 12
 
Pmp test 03
Pmp test 03Pmp test 03
Pmp test 03
 
PMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdfPMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdf
 
Interview questions-answers-for-planning-engineers-r.00
Interview questions-answers-for-planning-engineers-r.00Interview questions-answers-for-planning-engineers-r.00
Interview questions-answers-for-planning-engineers-r.00
 
Risk 3 simplelearn-exam2-ans
Risk 3 simplelearn-exam2-ansRisk 3 simplelearn-exam2-ans
Risk 3 simplelearn-exam2-ans
 
Project Planning in Software Engineering
Project Planning in Software EngineeringProject Planning in Software Engineering
Project Planning in Software Engineering
 
Pm0011 project planning and scheduling
Pm0011   project planning and schedulingPm0011   project planning and scheduling
Pm0011 project planning and scheduling
 
aw_survivalguide_r2opt
aw_survivalguide_r2optaw_survivalguide_r2opt
aw_survivalguide_r2opt
 
SE18_Lec 13_ Project Planning
SE18_Lec 13_ Project PlanningSE18_Lec 13_ Project Planning
SE18_Lec 13_ Project Planning
 
Running Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT .docx
Running Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT      .docxRunning Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT      .docx
Running Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT .docx
 
Running head PROJECT CHARTER ABOUT CREATING A WEBSITE FOR HR .docx
Running head PROJECT CHARTER ABOUT CREATING A WEBSITE FOR HR   .docxRunning head PROJECT CHARTER ABOUT CREATING A WEBSITE FOR HR   .docx
Running head PROJECT CHARTER ABOUT CREATING A WEBSITE FOR HR .docx
 
FIN320 – Gallaher – Prep for Exam 3 – Computational Questions1.docx
FIN320 – Gallaher – Prep for Exam 3 – Computational Questions1.docxFIN320 – Gallaher – Prep for Exam 3 – Computational Questions1.docx
FIN320 – Gallaher – Prep for Exam 3 – Computational Questions1.docx
 
Sheet2ScoresMaxActualComments1. Effort Estimate. Estimate the e.docx
Sheet2ScoresMaxActualComments1.  Effort Estimate.   Estimate the e.docxSheet2ScoresMaxActualComments1.  Effort Estimate.   Estimate the e.docx
Sheet2ScoresMaxActualComments1. Effort Estimate. Estimate the e.docx
 
COMP6214 Project 2.docx
COMP6214 Project 2.docxCOMP6214 Project 2.docx
COMP6214 Project 2.docx
 
Scope Statement1Scope Statement10Scope StatementCP.docx
Scope Statement1Scope Statement10Scope StatementCP.docxScope Statement1Scope Statement10Scope StatementCP.docx
Scope Statement1Scope Statement10Scope StatementCP.docx
 
VoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docx
VoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docxVoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docx
VoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docx
 
Pm0011 project planning and scheduling
Pm0011  project planning and schedulingPm0011  project planning and scheduling
Pm0011 project planning and scheduling
 
Why do the Projects fail
Why do the Projects failWhy do the Projects fail
Why do the Projects fail
 
Sad considerations for-candidate_system
Sad considerations for-candidate_systemSad considerations for-candidate_system
Sad considerations for-candidate_system
 
CAPM Study Session 3
CAPM Study Session 3CAPM Study Session 3
CAPM Study Session 3
 

Último

Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Sheetaleventcompany
 
Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...
Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...
Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...
lizamodels9
 
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
lizamodels9
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
amitlee9823
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
dollysharma2066
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
Abortion pills in Kuwait Cytotec pills in Kuwait
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
amitlee9823
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
daisycvs
 

Último (20)

Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876
Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876
Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
 
Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptx
 
Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...
Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...
Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...
 
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
 
Falcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investors
 
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort ServiceEluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
 
Falcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business GrowthFalcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business Growth
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
 
Falcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in indiaFalcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in india
 
Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
PHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation FinalPHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation Final
 
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
 

Pmp exam q&a

  • 1. 10 PMP Questions 1. Your company provides specialized IT support services for firmware upgrades. Your country’s government has passed regulations stating that firmware of all telecommunication equipment must be upgraded to support IPv6. A government agency has approached your company to upgrade the firmware of all installed equipment at the major airports in the country. For your company, this project is a result of which of the following: A) Market demand B) Strategic opportunity C) Customer request D) Legal requirement Anwer: C Hint: The government agency is asking your company to do a project. PMBOK Guide 5th Edition, page 69 This is a tricky scenario and the answer is at first a bit surprising. Let’s look at this from the point of view of both the government and your company: The government agency approached your company to do this project because they are bound by their own regulations. So for the government, this project was initiated as a result of their own legal requirement.For your company, however, the project is initiated by a customer request. Remember that you don’t own the airports nor the equipment installed there so you don’t have a legal requirement to update the firmware. The government, on the other hand, owns the airports/equipment and is therefore asking you to perform this update. In this case, the government is a customer like any other customer and you are doing this project as result of their request. 2. Nancy is the project manager for a project that will be closing shortly. During a quality inspection, Nancy detects that the project team has added additional features to one of the project deliverables that was not authorized. However, Nancy believes that these new features will add to customer satisfaction. What is Nancy’s best alternative in this situation? A) Submit a change request to remove these additional features B) Accept these additional features and proudly present them to the customer C) Ask the project sponsor for his opinion D) Ask the customers for their opinion
  • 2. Answer: A Hint: Unauthorized feature additions are called gold-plating and this needs to be avoided. Unauthorized feature additions are called gold-plating and this needs to be avoided. If such features have been included, they need to be removed using a change request, even if they add to customer satisfaction. Every project must conform to its approved requirements; nothing more, nothing less. PMI Code of Ethics and Professional Conduct: http://en.wikipedia.org/wiki/Gold_plating_(software_engineering) 3. Marilyn’s project is behind schedule. Marilyn opens her scheduling tool and adjusts some leads and lags in order to fast track the project. As a result, the project is aligned with the current time constraint. However, when Marilyn uses the “Level Resources” feature, the project finish date again goes past the time constraint. What is Marilyn’s best option? A) Marilyn must make sure that she did not make a mistake when using the “Level Resources” feature B) Marilyn must not use the “Level Resources” feature after fast tracking the project C) Marilyn must crash the project after fast tracking it D) Marilyn must issue a change request Answer: D Hint: When the “Resource Leveling” feature delays a project, it means that the resources were over- allocated. When the “Resource Leveling” feature delays a project, it means that the resources were over-allocated. Completing the project on time at the cost of over-utilizing the resources, and especially human resources, is not ethical. If fast tracking followed by resource leveling does not help in reducing the project time requirements, Marilyn must consider issuing a change request to obtain additional resources or get the project deadline extended. PMI Code of Ethics and Professional Conduct, Honesty PMBOK Guide 5th Edition, page 179 4. You are managing an automated security system design project. You now want to analyze the relationship between the consumption of project funds and the physical work being accomplished for these expenditures. Which of the following should you have completed before you can perform this activity? A) Deliverables B) Reserve Analysis
  • 3. C) Trend Analysis D) Project Funding Requirements Answer:D Hint: The scenario describes an activity in the Control Costs process. Did this question confuse you? If yes, then you first need to decipher it. The activity that you want to carry out is an example of which project management process? The Control Costs process. Once you realize this, you will see that “Project Management Plan”, “Project Funding Requirements” and “Work Performance Data” are important inputs to the Control Costs process. PMBOK Guide 5th Edition, page 215 5. You have just been assigned as the project manager for a process improvement project. You have broken down your project work into a number of work packages including stakeholder interviews, surveys, statistical analysis, flow charting of the current processes, analysis of the processes, cost estimations, and recommendations. You are currently performing the Plan Quality Management process. Which quality technique should you use during your project and in your Quality Management Plan if you wish to analyze all the possible process points of failure and the potential impact they may have? A) Kaizen approach B) Total Quality Management (TQM) C) Failure mode and effects analysis D) Six Sigma Answer: C This technique was formally introduced in the late 1940′s for military use by the U.S. Armed Forces. It was later used for aerospace/rocket development to avoid errors in small sample sizes of costly rocket technology. An example of this is the Apollo space program. Failure modes and effects analysis (FMEA) is a procedure in operations management for analysis of potential failure modes within a system for classification by severity or determination of the effect of failures on the system. Failure modes are any errors or defects in a process, design, or item, especially those that affect the customer, and can be potential or actual. Effects analysis refers to studying the consequences of those failures. en.wikipedia.org/wiki/Failure_mode_and_effects_analysis PMBOK Guide 5th Edition, page 540 6. You are in the executing phase of your project. You have spent a lot of time negotiating for the best human resources but the people you have obtained do not have the expertise
  • 4. necessary to complete the project activities, according to the Project Management Plan. What is the first thing you should do to try to remedy this situation? A) Update the Human Resource Management Plan B) Issue a change request C) Renegotiate for the required human resources D) Provide training to the under-skilled human resources Answer:A The scenario says that you were unable to acquire a project team according to your plan. Renegotiating is not a good option as you have already acquired resources. You only issue a change request when there is a required change in the project baselines. You will also most likely need to provide training to your under-skilled staff. However, the first thing you need to do is to update the Human Resource Management Plan to reflect your current staff’s expertise levels and training requirements. PMBOK Guide 5th Edition, page 272 7. You are managing a telecom project. You have two teams reporting to you. One team is responsible for equipment installation and the other team is responsible for commissioning and testing the equipment. Both teams are working in parallel so that as soon as the installation team finishes equipment installation at one site, they move on to another site for installation. This allows the commissioning and testing team to start their activities on the newly installed site. The reporting structure is such that each of the teams has five engineers and a separate team lead. Each team member interacts with each other but only the team leads interact with you. Both team leads also interact with each other to synchronize their operations. How many communication channels do you have on your project? A) 33 B) 23 C) 42 D) 78 Calculate communication channels for each team and add them together. This was a difficult question wasn’t it? Let’s analyze the scenario to calculate the answer. We have two independent teams. Each team has six members (five engineers and one team lead). Each team member is interacting with each other so communication channels for each team are (6)*(6-1)/2=15. And because we have two teams like this, the total is 2*15=30. Both team leads are communicating with you so there are two communication channels for this interaction. In addition, because both team leads are interacting with each other, there is one additional communication channel. Therefore, the total communication channels on your project is 30+2+1=33. PMBOK Guide 5th Edition, page 292
  • 5. 8. Rhonda’s project is half-way complete. None of the project risks have occurred and none of the contingency reserves have been used. Rhonda finds a few new risks to the project that were not added to the risk register during the planning phase. Rhonda quickly calculates the expected values of these risks and requests management to increase the contingency reserve by the amount required to manage these new risks. What’s wrong with Rhonda’s approach to dealing with risks? A) Rhonda should not have requested the increase B) New risks must be managed with the available management reserves C) Rhonda should have done a reserve analysis first D) Rhonda should have first used the contingency amounts for those risks that did not occur Answer: C If new and unidentified risks occur, they are managed using management reserves (after management approval to use the funds). However in this case, the new risks have not occurred, they have only just been identified. In this scenario, new risks have been identified. Rhonda can request an increase in the contingency reserves after she carries out a reserve analysis to determine if the additional funds are indeed required. PMI Code of Ethics and Professional Conduct, Responsibility PMBOK Guide 5th Edition, page 352 9. You are managing a construction project. You have outsourced the labor workforce to a contractor using a Time and Materials contract. As per the contract, your contractor is claiming $10 per hour for labor and an average of 10 hours a day per each labor resource provided. You know that on average only 8 of these 10 hours per day were actually productive time spent on the project. However, your contract doesn’t state anything specifically about charging for unproductive time. You now have a hold on all of the contractor’s invoices until you reach a resolution. Which of the following might be a factor contributing to this situation? A) Your contractor is being unreasonable B) You are being unreasonable towards the contractor C) You have not drafted the contract properly D) You have not negotiated the contract properly Answer: C Why doesn’t your contract say anything about this? Don’t get distracted by the scenario. The scenario may put you in the shoes of the project manger, but it does not mean that you are always right! Assume that you are not the project manager for a moment. In that case you cannot resolve this dispute in any party’s favor just with the information given. However, you
  • 6. can easily spot the weakness in the contract since it should have clauses regarding issues such as these. PMBOK Guide 5th Edition, page 364 10. You are running a public library construction project in which two key stakeholders are in continuous conflict with each other over location and design of the building. As a project manager, you have spent many hours resolving their conflicts, but it isn’t getting any better. What should you do next? A) Refer to the Project Charter for the escalation process B) Refer to the Communications Plan for the escalation process C) Involve the core project team D) Involve the sponsor Answer: B The Communications Plan contains the information about the escalation process. If a project manager cannot resolve the conflict between stakeholders, he/she should escalate the issue based on the escalation process listed in the Communications Plan. PMBOK Guide 5th Edition, page 406