SlideShare una empresa de Scribd logo
1 de 1
Descargar para leer sin conexión
PMP® Formula Pocket Guide
Print it - Fold it - Study wherever you go.
Visit www.pmprepcast.com for more PMP resources. Please see disclaimer on the PMP Formula Study Guide.
© 2008 ScopeCreep Project Management Consultants. All rights reserved. Version 1.1
Earned Value
CV = EV - AC
CPI = EV / AC
SV = EV - PV
SPI = EV / PV
EAC ‘no variances’ = BAC / CPI
EAC ‘fundamentally flawed’ = AC + ETC
EAC ‘atypical’ = AC + BAC - EV
EAC ‘typical’ = AC + ((BAC - EV) / CPI)
ETC = EAC - AC
ETC ‘atypical’ = BAC - EV
ETC ‘typical’ = (BAC - EV) / CPI
ETC ‘flawed’ = new estimate
Percent Complete = EV / BAC * 100
VAC = BAC - EAC
EV = % complete * BAC
PERT
PERT 3-point = (Pessimistic+(4*Most Likely)+Optimistic)/6
PERT σ = (Pessimistic - Optimistic) / 6
PERT Activity Variance = ((Pessimistic - Optimistic) / 6)^2
PERT Variance all activities = √sum((Pessimistic - Optimistic) / 6)^2
Network Diagram
Activity Duration = EF - ES + 1 or Activity Duration = LF - LS + 1
Total Float = LS - ES or Total Float = LF – EF
Free Float = ES of Following - ES of Present - DUR of Present
EF = ES + duration - 1
ES = EF of predecessor + 1
LF = LS of successor - 1
LS = LF - duration + 1
Project Selection
PV = FV / (1+r)^n
FV = PV * (1+r)^n
NPV = Formula not required. Select biggest number.
ROI = Formula not required. Select biggest number.
IRR = Formula not required. Select biggest number.
Payback Period = Add up the projected cash inflow minus expenses
until you reach the initial investment.
BCR = Benefit / Cost
CBR = Cost / Benefit
Opportunity Cost = The value of the project not chosen.
Communications
Communication Channels = n * (n-1) / 2
Probability
EMV = Probability * Impact in currency
Procurement
PTA = ((Ceiling Price - Target Price) / Buyer's Share Ratio) + Target
Cost
Depreciation
Straight-line Depreciation:
Depr. Expense = Asset Cost / Useful Life
Depr. Rate = 100% / Useful Life
Double Declining Balance Method:
Depr. Rate = 2 * (100% / Useful Life)
Depr. Expense = Depreciation Rate * Book Value at Beginning of Year
Book Value = Book Value at beginning of year - Depreciation Expense
Sum-of-Years' Digits Method:
Sum of digits = Useful Life + (Useful Life - 1) + (Useful Life - 2) + etc.
Depr. rate = fraction of years left and sum of the digits (i.e. 4/15th)
Mathematical Basics
Average (Mean) = Sum of all members divided by the number of items.
Median = Arrange values from lowest value to highest. Pick the middle
one. If there is an even number of values, calculate the mean of the
two middle values.
Mode = Find the value in a data set that occurs most often.
Values
1 sigma = 68.26%
2 sigma = 95.46%
3 sigma = 99.73%
6 sigma = 99.99%
Control Limits = 3 sigma from mean
Control Specifications = Defined by customer; looser than
the control limits
Order of Magnitude estimate = -25% to +75%
Preliminary estimate = -15% to + 50%
Budget estimate = -10% to +25%
Definitive estimate = -5% to +10%
Final estimate = 0%
Float on the critical path = 0 days
Pareto Diagram = 80/20
Time a PM spends communicating = 90%
Crashing a project = Crash least expensive tasks on critical
path.
JIT inventory = 0% (or very close to 0%.)
Minus 100 = (100) or -100
Acronyms
AC Actual Cost
BAC Budget at Completion
BCR Benefit Cost Ratio
CBR Cost Benefit Ratio
CPI Cost Performance Index
CV Cost Variance
DUR Duration
EAC Estimate at Completion
EF Early Finish
EMV Expected Monetary Value
ES Early Start
ETC Estimate to Complete
EV Earned Value
FV Future Value
IRR Internal Rate of Return
LF Late Finish
LS Late Start
NPV Net Present Value
PERT Program Evaluation and Review Technique
PTA Point of Total Assumption
PV Planned Value
PV Present Value
ROI Return on Investment
SPI Schedule Performance Index
SV Schedule Variance
VAC Variance at Completion
σ Sigma / Standard Deviation
^ “To the power of” (2^3 = 2*2*2 = 8)

Más contenido relacionado

La actualidad más candente

Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation training
Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation trainingProject Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation training
Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation trainingJustAcademy
 
Template kick off-meeting
Template kick off-meeting Template kick off-meeting
Template kick off-meeting Hari Krishna
 
The New PMP Exam: Changes and Implications (With Annotation)
The New PMP Exam: Changes and Implications (With Annotation)The New PMP Exam: Changes and Implications (With Annotation)
The New PMP Exam: Changes and Implications (With Annotation)CliffordEgbomeade
 
Agile project management using scrum
Agile project management using scrumAgile project management using scrum
Agile project management using scrumPrudentialSolutions
 
PMP Chapter 2 of 6 Initiating Process Group (2- Processes) (Based on PMBOK 6...
PMP Chapter 2 of 6  Initiating Process Group (2- Processes) (Based on PMBOK 6...PMP Chapter 2 of 6  Initiating Process Group (2- Processes) (Based on PMBOK 6...
PMP Chapter 2 of 6 Initiating Process Group (2- Processes) (Based on PMBOK 6...Shamil Habet
 
PMP-Schedule Management area
PMP-Schedule Management areaPMP-Schedule Management area
PMP-Schedule Management areaZaur Ahmadov, PMP
 
Project Management Tools & Techniques | PMP® Training Videos | Project Manage...
Project Management Tools & Techniques | PMP® Training Videos | Project Manage...Project Management Tools & Techniques | PMP® Training Videos | Project Manage...
Project Management Tools & Techniques | PMP® Training Videos | Project Manage...Edureka!
 
9.0 Project Resource Management Overview
9.0 Project Resource Management Overview9.0 Project Resource Management Overview
9.0 Project Resource Management OverviewDavidMcLachlan1
 
Agile project kick off from the trenches
Agile project kick off from the trenchesAgile project kick off from the trenches
Agile project kick off from the trenchesGeorge Stamos
 
Want to be a (PMP)® with 1250 memorizing notes
Want to be a (PMP)® with 1250 memorizing notesWant to be a (PMP)® with 1250 memorizing notes
Want to be a (PMP)® with 1250 memorizing notesMohammed Shafeea Haddad
 
PMBOK® Guide Processes Flow – 6th Edition (Simplified version)
PMBOK® Guide Processes Flow – 6th Edition (Simplified version)PMBOK® Guide Processes Flow – 6th Edition (Simplified version)
PMBOK® Guide Processes Flow – 6th Edition (Simplified version)Ricardo Viana Vargas
 
PMI-PgMP (Program Management Professional) Approach and plan
PMI-PgMP (Program Management Professional) Approach and planPMI-PgMP (Program Management Professional) Approach and plan
PMI-PgMP (Program Management Professional) Approach and planHarisha Lakkavalli - PgMP, PMP
 

La actualidad más candente (20)

Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation training
Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation trainingProject Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation training
Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation training
 
Template kick off-meeting
Template kick off-meeting Template kick off-meeting
Template kick off-meeting
 
PMP_Project Integration Management
PMP_Project Integration ManagementPMP_Project Integration Management
PMP_Project Integration Management
 
cheat sheet.ppt
cheat sheet.pptcheat sheet.ppt
cheat sheet.ppt
 
The New PMP Exam: Changes and Implications (With Annotation)
The New PMP Exam: Changes and Implications (With Annotation)The New PMP Exam: Changes and Implications (With Annotation)
The New PMP Exam: Changes and Implications (With Annotation)
 
Agile project management using scrum
Agile project management using scrumAgile project management using scrum
Agile project management using scrum
 
PMP Chapter 2 of 6 Initiating Process Group (2- Processes) (Based on PMBOK 6...
PMP Chapter 2 of 6  Initiating Process Group (2- Processes) (Based on PMBOK 6...PMP Chapter 2 of 6  Initiating Process Group (2- Processes) (Based on PMBOK 6...
PMP Chapter 2 of 6 Initiating Process Group (2- Processes) (Based on PMBOK 6...
 
PMP-Schedule Management area
PMP-Schedule Management areaPMP-Schedule Management area
PMP-Schedule Management area
 
Project Management Tools & Techniques | PMP® Training Videos | Project Manage...
Project Management Tools & Techniques | PMP® Training Videos | Project Manage...Project Management Tools & Techniques | PMP® Training Videos | Project Manage...
Project Management Tools & Techniques | PMP® Training Videos | Project Manage...
 
AXELOS - PRINCE2® Foundation
AXELOS - PRINCE2® FoundationAXELOS - PRINCE2® Foundation
AXELOS - PRINCE2® Foundation
 
9.0 Project Resource Management Overview
9.0 Project Resource Management Overview9.0 Project Resource Management Overview
9.0 Project Resource Management Overview
 
Agile project kick off from the trenches
Agile project kick off from the trenchesAgile project kick off from the trenches
Agile project kick off from the trenches
 
Pmp formula pocket guide
Pmp formula pocket guidePmp formula pocket guide
Pmp formula pocket guide
 
Want to be a (PMP)® with 1250 memorizing notes
Want to be a (PMP)® with 1250 memorizing notesWant to be a (PMP)® with 1250 memorizing notes
Want to be a (PMP)® with 1250 memorizing notes
 
Work Breakdown Structure
Work Breakdown StructureWork Breakdown Structure
Work Breakdown Structure
 
10- PMP Training - Risk Management
10- PMP Training - Risk Management 10- PMP Training - Risk Management
10- PMP Training - Risk Management
 
Advanced Work Packaging: Applying Project Controls
Advanced Work Packaging: Applying Project ControlsAdvanced Work Packaging: Applying Project Controls
Advanced Work Packaging: Applying Project Controls
 
Back to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinarBack to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinar
 
PMBOK® Guide Processes Flow – 6th Edition (Simplified version)
PMBOK® Guide Processes Flow – 6th Edition (Simplified version)PMBOK® Guide Processes Flow – 6th Edition (Simplified version)
PMBOK® Guide Processes Flow – 6th Edition (Simplified version)
 
PMI-PgMP (Program Management Professional) Approach and plan
PMI-PgMP (Program Management Professional) Approach and planPMI-PgMP (Program Management Professional) Approach and plan
PMI-PgMP (Program Management Professional) Approach and plan
 

Similar a Pmp Formula Pocket_Guide

PMP Exam Formulas
PMP Exam FormulasPMP Exam Formulas
PMP Exam FormulasAmr Miqdadi
 
cost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptcost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptRedhaElhuni
 
Important formules for ugc net commerce,management (most important) downl...
Important  formules  for  ugc net commerce,management (most important)  downl...Important  formules  for  ugc net commerce,management (most important)  downl...
Important formules for ugc net commerce,management (most important) downl...DIwakar Rajput
 
fm_formula__ipcc-2.pdf
fm_formula__ipcc-2.pdffm_formula__ipcc-2.pdf
fm_formula__ipcc-2.pdfhitishaagrawal
 
PM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdfPM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdfNajm Naqvi
 
Chapter 7 cost of production
Chapter 7 cost of productionChapter 7 cost of production
Chapter 7 cost of productionYesica Adicondro
 
Risk Concept And Management 5
Risk Concept And Management 5Risk Concept And Management 5
Risk Concept And Management 5rajeevgupta
 
Project : formulation,evaluation and monitoring
Project : formulation,evaluation and monitoringProject : formulation,evaluation and monitoring
Project : formulation,evaluation and monitoringtarzan1990
 
projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)Nita Cristian
 
Project cost & control
Project cost & controlProject cost & control
Project cost & controlAMARAYYA
 

Similar a Pmp Formula Pocket_Guide (20)

Pmp formulas
Pmp formulasPmp formulas
Pmp formulas
 
Pmp formulas
Pmp  formulasPmp  formulas
Pmp formulas
 
PMP Exam Formulas
PMP Exam FormulasPMP Exam Formulas
PMP Exam Formulas
 
PMBOK 6th ed Formulas.pdf
PMBOK 6th ed Formulas.pdfPMBOK 6th ed Formulas.pdf
PMBOK 6th ed Formulas.pdf
 
PMP Exam Formulas To Know
PMP Exam Formulas To KnowPMP Exam Formulas To Know
PMP Exam Formulas To Know
 
Cost analysis
Cost analysisCost analysis
Cost analysis
 
Learning pmp formulas the easy way
Learning pmp formulas the easy wayLearning pmp formulas the easy way
Learning pmp formulas the easy way
 
Formulas for pmp exam
Formulas for pmp examFormulas for pmp exam
Formulas for pmp exam
 
cost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptcost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.ppt
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
 
Important formules for ugc net commerce,management (most important) downl...
Important  formules  for  ugc net commerce,management (most important)  downl...Important  formules  for  ugc net commerce,management (most important)  downl...
Important formules for ugc net commerce,management (most important) downl...
 
fm_formula__ipcc-2.pdf
fm_formula__ipcc-2.pdffm_formula__ipcc-2.pdf
fm_formula__ipcc-2.pdf
 
PM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdfPM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdf
 
Chapter 7 cost of production
Chapter 7 cost of productionChapter 7 cost of production
Chapter 7 cost of production
 
F0dd9 cost
F0dd9 costF0dd9 cost
F0dd9 cost
 
Risk Concept And Management 5
Risk Concept And Management 5Risk Concept And Management 5
Risk Concept And Management 5
 
Project : formulation,evaluation and monitoring
Project : formulation,evaluation and monitoringProject : formulation,evaluation and monitoring
Project : formulation,evaluation and monitoring
 
projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)
 
Project cost & control
Project cost & controlProject cost & control
Project cost & control
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 

Más de Jamil Faraj , PMP (20)

Corona-virus PMP study plan
Corona-virus PMP study planCorona-virus PMP study plan
Corona-virus PMP study plan
 
PMP Study Plan by Jamil Faraj, PMP
PMP Study Plan by Jamil Faraj, PMPPMP Study Plan by Jamil Faraj, PMP
PMP Study Plan by Jamil Faraj, PMP
 
Jamil Faraj CV 2020
Jamil Faraj CV 2020Jamil Faraj CV 2020
Jamil Faraj CV 2020
 
Jamil faraj hassan CV
Jamil faraj hassan CVJamil faraj hassan CV
Jamil faraj hassan CV
 
PMP ITTOs Quick Review
PMP ITTOs Quick Review PMP ITTOs Quick Review
PMP ITTOs Quick Review
 
Jamil pmp Certificate 2020
Jamil pmp Certificate 2020Jamil pmp Certificate 2020
Jamil pmp Certificate 2020
 
2
22
2
 
1
11
1
 
Pmp exam q&a
Pmp exam q&aPmp exam q&a
Pmp exam q&a
 
Pmp6
Pmp6Pmp6
Pmp6
 
Pmp5
Pmp5Pmp5
Pmp5
 
Pmp4
Pmp4Pmp4
Pmp4
 
Pmp3
Pmp3Pmp3
Pmp3
 
Pmp2
Pmp2Pmp2
Pmp2
 
Pmp1
Pmp1Pmp1
Pmp1
 
Exam1
Exam1Exam1
Exam1
 
Jamil Hassan, PMP lessons learned.
Jamil Hassan, PMP lessons learned.Jamil Hassan, PMP lessons learned.
Jamil Hassan, PMP lessons learned.
 
Jamil Faraj CV- English
Jamil Faraj CV- EnglishJamil Faraj CV- English
Jamil Faraj CV- English
 
دورة وظيفة العمر
دورة وظيفة العمردورة وظيفة العمر
دورة وظيفة العمر
 
01 pmp introduct to project management exam
01 pmp introduct to project management exam01 pmp introduct to project management exam
01 pmp introduct to project management exam
 

Pmp Formula Pocket_Guide

  • 1. PMP® Formula Pocket Guide Print it - Fold it - Study wherever you go. Visit www.pmprepcast.com for more PMP resources. Please see disclaimer on the PMP Formula Study Guide. © 2008 ScopeCreep Project Management Consultants. All rights reserved. Version 1.1 Earned Value CV = EV - AC CPI = EV / AC SV = EV - PV SPI = EV / PV EAC ‘no variances’ = BAC / CPI EAC ‘fundamentally flawed’ = AC + ETC EAC ‘atypical’ = AC + BAC - EV EAC ‘typical’ = AC + ((BAC - EV) / CPI) ETC = EAC - AC ETC ‘atypical’ = BAC - EV ETC ‘typical’ = (BAC - EV) / CPI ETC ‘flawed’ = new estimate Percent Complete = EV / BAC * 100 VAC = BAC - EAC EV = % complete * BAC PERT PERT 3-point = (Pessimistic+(4*Most Likely)+Optimistic)/6 PERT σ = (Pessimistic - Optimistic) / 6 PERT Activity Variance = ((Pessimistic - Optimistic) / 6)^2 PERT Variance all activities = √sum((Pessimistic - Optimistic) / 6)^2 Network Diagram Activity Duration = EF - ES + 1 or Activity Duration = LF - LS + 1 Total Float = LS - ES or Total Float = LF – EF Free Float = ES of Following - ES of Present - DUR of Present EF = ES + duration - 1 ES = EF of predecessor + 1 LF = LS of successor - 1 LS = LF - duration + 1 Project Selection PV = FV / (1+r)^n FV = PV * (1+r)^n NPV = Formula not required. Select biggest number. ROI = Formula not required. Select biggest number. IRR = Formula not required. Select biggest number. Payback Period = Add up the projected cash inflow minus expenses until you reach the initial investment. BCR = Benefit / Cost CBR = Cost / Benefit Opportunity Cost = The value of the project not chosen. Communications Communication Channels = n * (n-1) / 2 Probability EMV = Probability * Impact in currency Procurement PTA = ((Ceiling Price - Target Price) / Buyer's Share Ratio) + Target Cost Depreciation Straight-line Depreciation: Depr. Expense = Asset Cost / Useful Life Depr. Rate = 100% / Useful Life Double Declining Balance Method: Depr. Rate = 2 * (100% / Useful Life) Depr. Expense = Depreciation Rate * Book Value at Beginning of Year Book Value = Book Value at beginning of year - Depreciation Expense Sum-of-Years' Digits Method: Sum of digits = Useful Life + (Useful Life - 1) + (Useful Life - 2) + etc. Depr. rate = fraction of years left and sum of the digits (i.e. 4/15th) Mathematical Basics Average (Mean) = Sum of all members divided by the number of items. Median = Arrange values from lowest value to highest. Pick the middle one. If there is an even number of values, calculate the mean of the two middle values. Mode = Find the value in a data set that occurs most often. Values 1 sigma = 68.26% 2 sigma = 95.46% 3 sigma = 99.73% 6 sigma = 99.99% Control Limits = 3 sigma from mean Control Specifications = Defined by customer; looser than the control limits Order of Magnitude estimate = -25% to +75% Preliminary estimate = -15% to + 50% Budget estimate = -10% to +25% Definitive estimate = -5% to +10% Final estimate = 0% Float on the critical path = 0 days Pareto Diagram = 80/20 Time a PM spends communicating = 90% Crashing a project = Crash least expensive tasks on critical path. JIT inventory = 0% (or very close to 0%.) Minus 100 = (100) or -100 Acronyms AC Actual Cost BAC Budget at Completion BCR Benefit Cost Ratio CBR Cost Benefit Ratio CPI Cost Performance Index CV Cost Variance DUR Duration EAC Estimate at Completion EF Early Finish EMV Expected Monetary Value ES Early Start ETC Estimate to Complete EV Earned Value FV Future Value IRR Internal Rate of Return LF Late Finish LS Late Start NPV Net Present Value PERT Program Evaluation and Review Technique PTA Point of Total Assumption PV Planned Value PV Present Value ROI Return on Investment SPI Schedule Performance Index SV Schedule Variance VAC Variance at Completion σ Sigma / Standard Deviation ^ “To the power of” (2^3 = 2*2*2 = 8)