1
• A definition
• Where did validation come from ?
• Why do it ?
• What are the benefits ?
• How far do we have to go ?
2
“ Establishing the documented evidence which
provides a high degree of assurance that a
specific process will consistently produce a
product of predetermined specifications and
quality attributes.”
(FDA Guidelines 1987)
3
“Process validation is defined as the collection
& evaluation of data, from the process design
stage through commercial production, which
establishes scientific evidence that process is
capable of consistently delivering quality
product.”
(FDA Guidelines, 2011)
4
“Action of proving, in accordance with the
principles of Good Manufacturing Practice
(GMP), that any procedure, process,
equipment, material, activity or system
actually leads to expected results.”
(EU GMP 1997)
5
• Began in 1970’s
• Originally sterilized based.
• Now evolved into all Product, Process and Facility
matters.
6
• Assures Quality
• Regulatory Requirement
• Reduces Cost
• It’s the LAW !
7
Validation can reduce costs by reducing,
•Rejects
•Reworks
•Reliance on In-process controls
•Down time
8
 Reliance on product testing
 Loss of confidence
 Possibility of adulterated products
 Inspection : Observations / 483’s
9
 User Requirement Specification (URS)
 Design Qualification
 Impact Assessment
 Factory Acceptance Testing
 Installation Qualification
10
 Calibration
 Site Acceptance Testing
 Operational Qualification
 Standard Operating Procedures
 Performance Qualification
 Process Validation
 Change Control
11
User Requirement Specification (URS)
 A description of the requirements of the facility
(project) in terms of product to be manufactured,
required throughput and conditions in which the
product should be manufactured.
 Approved statements prepared by the user which
defines what is required by the project.
12
Design Qualification (DQ)
 Documented review of the design, at an
appropriate stage in a project, for conformance
to operational and regulatory expectations.
13
Impact Assessment
 The process of evaluating the impact of the
operating, controlling, alarming and failure
conditions of a system on the quality of a
product
14
Factory Acceptance Testing (FAT)
 Inspection and static and/or dynamic testing of
systems or major system components to
support the qualification of an equipment
system conducted and documented at a
supplier site.
15
 Documented verification that all aspects of a facility,
utility or equipment that can affect the product
quality adhere to approved specifications and are
correctly installed.
 The process of checking/verifying the installation to
ensure that the critical components meet the
approved specifications and that they are installed
correctly in accordance with design documentation.
16
 To establish that the critical components are installed
correctly and in accordance with design
documentation requirements (i.e. PO’s, Contracts
etc.), that supporting documentation is in place and of
suitable quality.
 To record the checks and verifications for critical
components in Direct Impact Systems.
17
 Approval Page
 Objectives
 System Description
 Responsibilities
 Acceptance Criteria
 Engineering Documentation Requirements
 Records of Signatures
 Qualification Test Equipment/Instrument List
 Product Contact Materials Review
 Utilities Verification
 Control System Verification
18
 Instrument/Control Devices Verification
 Equipment Verification
 Piping Installation Verification
 Discrepancy/Justification and corrective Action
 As built P&I Diagrams
 Specifications
 Conclusions
 References
 Modification/ Change Control
 Attachments / Appendices
19
Parameters
 Does the vessel meet the design specification?
 Does the agitator assembly meet the design specification?
 Is the motor housing earthed?
 Is the motor over current device set to correct setting?
 Is all the pipe work connected?
 Are all instruments installed as per P&I diagram?
 Have all the temperature indicators been calibrated?
 Is calibration procedure available?
 Are operation and maintenance manuals available?
 all electrical connections securely and safely fitted?
 Is insulation complete?
 Is vessel clean and free from dirt?
20
 After protocol execution is complete and
deviations evaluated, post execution approval
is required.
 Requires sign off by original signatories.
 IQ execution should be complete and approved
prior to the start of OQ.
21
Calibration
 Demonstrating that a measuring device
produces results within the specified limits of
those produced by a reference standard over
an appropriate range of measurements.
 The devices are normally tagged and
supported by a maintenance procedures.
22
Site Acceptance Testing (SAT)
 Inspection and dynamic testing of systems or
major system components to support the
qualification of an equipment system
conducted at a client site.
(Note : Not an obligation)
23
 Documented verification that all aspects of
a facility, utility or equipment that can affect
product quality operate as intended
throughout all anticipated ranges. It is the
process of testing to ensure that individual
components and systems operate as
specified, and how that information is
recorded.
24
 To establish through documented testing, that all
critical components and direct impact systems are
capable of operating within established limits and
tolerances.
 To test parameters that regulate the process or
product quality. To verify the proper operation of
controllers, indicators, recorders, alarms and
interlocks, is performed and documented during the
operational qualification testing.
25
 Approval page
 Pre-requisites
 Objectives
 System Description
 Responsibilities
 Acceptance Criteria
 Records of signatures
 Qualification test Equipment/Instruments list
 Alarm and Interlocks test
 Operation testing
 Capacity testing
 Power failure testing
26
 Sequence testing
 Test data sheets
 SOP’s
 Conclusions
 Modification / change control
 Discrepancy/Justification and corrective action
 Operational Qualification Summary
 References
 Attachments/Appendices
- Verification of test instruments
- Chart recordings
- P&I diagrams
- Printouts
27
Parameters
 Have all Installation Qualification been completed for this system?
 Is the system clean and free from dirt?
 Is the direction of the rotation of agitator correct?
 Check the operation of the agitator emergency stop?
 Check the operation of all agitator controls, both on the main and local
panels?
 Check that the agitator in the vessel free to turn?
 Pressurize the vessel and record the pressure drop for 10 min.
 Perform a vacuum test and record the vacuum drop.
28
 Documented verification that all aspects of
a facility, utility or equipment that can
affect the product quality perform as
intended in meeting the predetermined
acceptance criteria.
29
 To integrate procedures, personnel, systems
and materials to verify that the utility /
environment / equipment / support systems
produces the required output. This output
may be a product contact utility, sterilization
condition or environment.
30
 Approval page
 Pre-requisites
 Objectives
 System Description
 Responsibilities
 Acceptance Criteria
 PQ test plan
 Challenge test plan
 Records of signatures
 Test equipment/Instrument list
 Test data sheets
 SOP’s
 References
 Conclusions
 Attachments
31
Process Validation
 The documented verification providing a high
degree of assurance that a specific process will
consistently produce a product meeting its
predetermined specifications and quality
attributes.
 The new guidelines aligns process validation
activities with a product life cycle concept.
32
 211.42, 211.63, 211.68, 211.84
 211.100(a) , 211.110(a),
211.110(b)
 211.160(b), 211.165(c),
211.165(d), 211.180(e)
33
Life Cycle of the product & the process
 Stage 1 – Process Design
 Stage 2 – Process qualification
 Stage 3 - Continuous process verification
34
 It is the activity of defining the commercial manufacturing
process that will be reflected in planned master production
and control records.
 The goal of this stage is to design a process suitable for
routine commercial manufacturing that can consistently
deliver a product that meets its quality attributes.
 It is based on the knowledge gained through development &
scale-up activities.
35
During this stage, the process design is evaluated to
determine if the process is capable of reproducible
commercial manufacturing. The products
manufactured during this stage, if acceptable , can be
released for distribution.
Two Aspects
 Design of facility and qualification of equipment and
utilities.
 Process Performance Qualification ( PPQ).
36
Def.: “Releasing for distribution a lot of finished
product, manufactured following a qualification
protocol, that meets the standards established in
the protocol, but before the entire study has been
executed”.
 Orphan Drugs
 Specific drug for specific use
 Short Shelf-life radio pharmaceuticals
37
 The goal of this stage is continual assurance that the
process remains in a state of control ( the validated state)
during commercial manufacture.
 The cGMP requirements, specifically the collection &
evaluation of information & data about the performance
of the process will allow detection of undesired process
variability.
 This stage is also applicable for legacy products.
38
Change Control
 Formal evaluation of the potential impact of
planned modifications on the validated status
of a product, process or facility.
39
 Training personnel for IQ/OQ execution.
 The purpose of the equipment/ system.
 Use of test equipment
 Applicable SOP’s
 cGMP documentation of training
 Document all training
 Periodically review training requirements
40
 A document that summarizes and analyses
the test results at the end of PQ.
 Provides a conclusion about the ability of the
system to consistently meet acceptance
criteria.
 May be a stand alone document at each
stage of IQ/OQ and PQ to summarize results.
41
Commissioning and Qualification
Project Phases Validation Phases
Technology Transfer Collecting data
Conceptual Design
Basic Design Preliminary VMP
Detailed Design Detailed VMP
Procurement Detailed planning,DQ
Construction IQ
Pre commissioning
Commissioning OQ
Process operation / Validation
42
43
Introduction Qualification Personnel Schedule
Preventive
Maintenance
Installation
Operation
Process
Responsibilities
Training
Change
Control
Procedures
Documents
Appendices
The company’s overall policy, intentions and
approach to validation, including :
 Validation of production processes
 Cleaning procedures
 Analytical methods
 In-process control test procedures
 Computerized systems
 Persons responsible for design, review, approval
 Documentation of each validation phase
44
 Product validation is NOT ……
- just 3 batches that meet specifications
 Product validation is ……
- an ongoing process to build confidence into
the manufacturing activities
- an ability to demonstrate consistency at any
time.
45
 Cleaning validation is establishing
documented evidence that the equipment
is consistently cleaned from product,
microbial and cleaning agent residues to
predetermined acceptable levels.
46
A written procedure for cleaning validation
which includes :
 Responsibility for development, performance and
approval of the validation study.
 Establishment of SOP’s
 Acceptance criteria
- defined to prevent cross contamination
- definition of residue limits
47
 Cleaning procedure for each piece of equipment
- Flow charts and diagrams
- Cleaning agents, concentration, volume
- Frequency
- time left ‘dirty’
48
 Sampling procedures
- swabs, rinse, location
 Residue limits
 Analytical methods
49
 Validation report
- Results Vs. acceptance criteria
- Deviations and how handled
- Conclusion that cleaning process is
validated
50
 Major change in cleaning procedure
 Change in cleaning agent
 New equipment
51
 Knowledge of the materials
- Potency of the drug
- Pharmacological and toxic properties
- Degradation products
- Cleaning agents
- Micro residues
52
Residual Limits must be………….
 Practical
 Achievable
 Verifiable
 Safe
FDA does not set acceptance specifications
(limits).
53
MAC = TD x BS x SF / LDD
MAC = Maximum Allowable Carryover
TD = Single Therapeutic Dose
BS = Batch size of next product to be
manufactured on the same equipment.
SF = Safety Factor
LDD = Largest Daily Dose of the next product
in the same equipment.
54
Ranitidine Tablets - Ibuprofen Tablets
TD = Single Therapeutic Dose = 150 mg Ranitidine-Tab
BS = Batch Size = 100 kg of Ibuprofen
SF = Safety Factor = 1/1000
LDD = Largest Daily Dose of the next product in the same
equipment = 200 mg X 5 tablets of Ibuprofen
MAC = Max Allowable Carryover = 150 X 100 X 1000 x
1000 X 1/1000 X 1/1000
i.e 15000 mg in 100 kg Batch size
i.e 150 mg in 1 kg = 150 ppm
55
Presented by –
JATIN SINGLA
M.PHARM 1st
year
PH’CEUTICS

Más contenido relacionado

La actualidad más candente

New approach to Process Validation 4
New approach to Process Validation 4New approach to Process Validation 4
New approach to Process Validation 4
Santosh Singh
 
Process Validation for Beginners - FDA - EMA Approach
Process Validation for Beginners - FDA - EMA ApproachProcess Validation for Beginners - FDA - EMA Approach
Process Validation for Beginners - FDA - EMA Approach
GMP EDUCATION : Not for Profit Organization
 

La actualidad más candente (20)

concept of validation
concept of validationconcept of validation
concept of validation
 
New approach to Process Validation 4
New approach to Process Validation 4New approach to Process Validation 4
New approach to Process Validation 4
 
Urs,dq, iq,oq,pq
Urs,dq, iq,oq,pqUrs,dq, iq,oq,pq
Urs,dq, iq,oq,pq
 
Equipment qualification
Equipment qualificationEquipment qualification
Equipment qualification
 
Vallidation
VallidationVallidation
Vallidation
 
Change control
Change controlChange control
Change control
 
A Lifecycle Approach to Process Validation
A Lifecycle Approach to Process ValidationA Lifecycle Approach to Process Validation
A Lifecycle Approach to Process Validation
 
Validation boot camp 4
Validation boot camp 4Validation boot camp 4
Validation boot camp 4
 
Bioprocess Validation
Bioprocess Validation Bioprocess Validation
Bioprocess Validation
 
Validation Part7
Validation Part7Validation Part7
Validation Part7
 
Water system validation
Water system validationWater system validation
Water system validation
 
Process Validation for Beginners - FDA - EMA Approach
Process Validation for Beginners - FDA - EMA ApproachProcess Validation for Beginners - FDA - EMA Approach
Process Validation for Beginners - FDA - EMA Approach
 
Pharmaceutical validation
Pharmaceutical validationPharmaceutical validation
Pharmaceutical validation
 
Validation Master Plan
Validation Master PlanValidation Master Plan
Validation Master Plan
 
Validation master plan
Validation master planValidation master plan
Validation master plan
 
Validation
ValidationValidation
Validation
 
Validation Program Design
Validation Program DesignValidation Program Design
Validation Program Design
 
Processs validation
Processs validationProcesss validation
Processs validation
 
Design qualification
Design qualificationDesign qualification
Design qualification
 
Process validation
Process validationProcess validation
Process validation
 

Similar a Jatin validation

Similar a Jatin validation (20)

validationksd-140930004558-phpapp01 (1).pdf
validationksd-140930004558-phpapp01 (1).pdfvalidationksd-140930004558-phpapp01 (1).pdf
validationksd-140930004558-phpapp01 (1).pdf
 
Validation
ValidationValidation
Validation
 
Validation ksd
Validation ksdValidation ksd
Validation ksd
 
Validation ksd
Validation ksdValidation ksd
Validation ksd
 
Validation (1).pptx
Validation (1).pptxValidation (1).pptx
Validation (1).pptx
 
4 validation jntu pharmacy
4 validation jntu pharmacy4 validation jntu pharmacy
4 validation jntu pharmacy
 
Validation
ValidationValidation
Validation
 
Process validation ppt.
Process validation ppt.Process validation ppt.
Process validation ppt.
 
validation and verification of medical device.pptx
validation and verification of medical device.pptxvalidation and verification of medical device.pptx
validation and verification of medical device.pptx
 
Basic concept of process validation
Basic concept of process validation Basic concept of process validation
Basic concept of process validation
 
Nguyên tắc Thẩm định theo Bộ tiêu chuẩn GMP Nhật Bản
Nguyên tắc Thẩm định theo Bộ tiêu chuẩn GMP Nhật BảnNguyên tắc Thẩm định theo Bộ tiêu chuẩn GMP Nhật Bản
Nguyên tắc Thẩm định theo Bộ tiêu chuẩn GMP Nhật Bản
 
Pharmaceutical Qualification & Validation
Pharmaceutical Qualification & ValidationPharmaceutical Qualification & Validation
Pharmaceutical Qualification & Validation
 
PHARMACEUTICAL VALIADATION
PHARMACEUTICAL VALIADATIONPHARMACEUTICAL VALIADATION
PHARMACEUTICAL VALIADATION
 
Pharmaceutical validation.pptx
Pharmaceutical validation.pptxPharmaceutical validation.pptx
Pharmaceutical validation.pptx
 
Process validation and its types
Process validation and its typesProcess validation and its types
Process validation and its types
 
Pharmaceuticalvalidation maharaja mla
Pharmaceuticalvalidation maharaja mlaPharmaceuticalvalidation maharaja mla
Pharmaceuticalvalidation maharaja mla
 
calibration-and-validation
calibration-and-validationcalibration-and-validation
calibration-and-validation
 
Validation and calibration master plan
Validation and calibration master planValidation and calibration master plan
Validation and calibration master plan
 
Notes for the subject 'Pharmaceutical Validation'
Notes for the subject 'Pharmaceutical Validation' Notes for the subject 'Pharmaceutical Validation'
Notes for the subject 'Pharmaceutical Validation'
 
Equipment qualification
Equipment qualificationEquipment qualification
Equipment qualification
 

Más de jatin singla

regulation of herbal products
regulation of herbal productsregulation of herbal products
regulation of herbal products
jatin singla
 
Jatin an overview of sunscreen regulations in the world
Jatin  an overview of sunscreen regulations in the worldJatin  an overview of sunscreen regulations in the world
Jatin an overview of sunscreen regulations in the world
jatin singla
 

Más de jatin singla (20)

Non linear pharmacokinetics.
Non linear pharmacokinetics.Non linear pharmacokinetics.
Non linear pharmacokinetics.
 
Jatin singla
Jatin singlaJatin singla
Jatin singla
 
Jatin singla
Jatin singlaJatin singla
Jatin singla
 
Jatin singla
Jatin singlaJatin singla
Jatin singla
 
Jatin singla
Jatin singlaJatin singla
Jatin singla
 
Jatin singla
Jatin singlaJatin singla
Jatin singla
 
Jatin
JatinJatin
Jatin
 
Jatin singla
Jatin singlaJatin singla
Jatin singla
 
Jatin
JatinJatin
Jatin
 
Singla
SinglaSingla
Singla
 
Jatin singla
Jatin singlaJatin singla
Jatin singla
 
Jatin singla (2)
Jatin singla (2)Jatin singla (2)
Jatin singla (2)
 
Jatin singla project ppt
Jatin singla project pptJatin singla project ppt
Jatin singla project ppt
 
Jatin industrial ppt
Jatin industrial  pptJatin industrial  ppt
Jatin industrial ppt
 
regulation of herbal products
regulation of herbal productsregulation of herbal products
regulation of herbal products
 
Jatin an overview of sunscreen regulations in the world
Jatin  an overview of sunscreen regulations in the worldJatin  an overview of sunscreen regulations in the world
Jatin an overview of sunscreen regulations in the world
 
Jatin article qbd
Jatin article qbdJatin article qbd
Jatin article qbd
 
Multiple emulsion
Multiple emulsionMultiple emulsion
Multiple emulsion
 
Jatin. biovailability
Jatin. biovailabilityJatin. biovailability
Jatin. biovailability
 
Jatin ivivc
Jatin ivivcJatin ivivc
Jatin ivivc
 

Último

The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
heathfieldcps1
 
Spellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please PractiseSpellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please Practise
AnaAcapella
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
ZurliaSoop
 

Último (20)

Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
 
REMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptxREMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptx
 
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
 
Spellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please PractiseSpellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please Practise
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
 
Graduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - EnglishGraduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - English
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
Interdisciplinary_Insights_Data_Collection_Methods.pptx
Interdisciplinary_Insights_Data_Collection_Methods.pptxInterdisciplinary_Insights_Data_Collection_Methods.pptx
Interdisciplinary_Insights_Data_Collection_Methods.pptx
 
Understanding Accommodations and Modifications
Understanding  Accommodations and ModificationsUnderstanding  Accommodations and Modifications
Understanding Accommodations and Modifications
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 
Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)
 
How to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxHow to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptx
 
SOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning PresentationSOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning Presentation
 

Jatin validation

  • 2. • A definition • Where did validation come from ? • Why do it ? • What are the benefits ? • How far do we have to go ? 2
  • 3. “ Establishing the documented evidence which provides a high degree of assurance that a specific process will consistently produce a product of predetermined specifications and quality attributes.” (FDA Guidelines 1987) 3
  • 4. “Process validation is defined as the collection & evaluation of data, from the process design stage through commercial production, which establishes scientific evidence that process is capable of consistently delivering quality product.” (FDA Guidelines, 2011) 4
  • 5. “Action of proving, in accordance with the principles of Good Manufacturing Practice (GMP), that any procedure, process, equipment, material, activity or system actually leads to expected results.” (EU GMP 1997) 5
  • 6. • Began in 1970’s • Originally sterilized based. • Now evolved into all Product, Process and Facility matters. 6
  • 7. • Assures Quality • Regulatory Requirement • Reduces Cost • It’s the LAW ! 7
  • 8. Validation can reduce costs by reducing, •Rejects •Reworks •Reliance on In-process controls •Down time 8
  • 9.  Reliance on product testing  Loss of confidence  Possibility of adulterated products  Inspection : Observations / 483’s 9
  • 10.  User Requirement Specification (URS)  Design Qualification  Impact Assessment  Factory Acceptance Testing  Installation Qualification 10
  • 11.  Calibration  Site Acceptance Testing  Operational Qualification  Standard Operating Procedures  Performance Qualification  Process Validation  Change Control 11
  • 12. User Requirement Specification (URS)  A description of the requirements of the facility (project) in terms of product to be manufactured, required throughput and conditions in which the product should be manufactured.  Approved statements prepared by the user which defines what is required by the project. 12
  • 13. Design Qualification (DQ)  Documented review of the design, at an appropriate stage in a project, for conformance to operational and regulatory expectations. 13
  • 14. Impact Assessment  The process of evaluating the impact of the operating, controlling, alarming and failure conditions of a system on the quality of a product 14
  • 15. Factory Acceptance Testing (FAT)  Inspection and static and/or dynamic testing of systems or major system components to support the qualification of an equipment system conducted and documented at a supplier site. 15
  • 16.  Documented verification that all aspects of a facility, utility or equipment that can affect the product quality adhere to approved specifications and are correctly installed.  The process of checking/verifying the installation to ensure that the critical components meet the approved specifications and that they are installed correctly in accordance with design documentation. 16
  • 17.  To establish that the critical components are installed correctly and in accordance with design documentation requirements (i.e. PO’s, Contracts etc.), that supporting documentation is in place and of suitable quality.  To record the checks and verifications for critical components in Direct Impact Systems. 17
  • 18.  Approval Page  Objectives  System Description  Responsibilities  Acceptance Criteria  Engineering Documentation Requirements  Records of Signatures  Qualification Test Equipment/Instrument List  Product Contact Materials Review  Utilities Verification  Control System Verification 18
  • 19.  Instrument/Control Devices Verification  Equipment Verification  Piping Installation Verification  Discrepancy/Justification and corrective Action  As built P&I Diagrams  Specifications  Conclusions  References  Modification/ Change Control  Attachments / Appendices 19
  • 20. Parameters  Does the vessel meet the design specification?  Does the agitator assembly meet the design specification?  Is the motor housing earthed?  Is the motor over current device set to correct setting?  Is all the pipe work connected?  Are all instruments installed as per P&I diagram?  Have all the temperature indicators been calibrated?  Is calibration procedure available?  Are operation and maintenance manuals available?  all electrical connections securely and safely fitted?  Is insulation complete?  Is vessel clean and free from dirt? 20
  • 21.  After protocol execution is complete and deviations evaluated, post execution approval is required.  Requires sign off by original signatories.  IQ execution should be complete and approved prior to the start of OQ. 21
  • 22. Calibration  Demonstrating that a measuring device produces results within the specified limits of those produced by a reference standard over an appropriate range of measurements.  The devices are normally tagged and supported by a maintenance procedures. 22
  • 23. Site Acceptance Testing (SAT)  Inspection and dynamic testing of systems or major system components to support the qualification of an equipment system conducted at a client site. (Note : Not an obligation) 23
  • 24.  Documented verification that all aspects of a facility, utility or equipment that can affect product quality operate as intended throughout all anticipated ranges. It is the process of testing to ensure that individual components and systems operate as specified, and how that information is recorded. 24
  • 25.  To establish through documented testing, that all critical components and direct impact systems are capable of operating within established limits and tolerances.  To test parameters that regulate the process or product quality. To verify the proper operation of controllers, indicators, recorders, alarms and interlocks, is performed and documented during the operational qualification testing. 25
  • 26.  Approval page  Pre-requisites  Objectives  System Description  Responsibilities  Acceptance Criteria  Records of signatures  Qualification test Equipment/Instruments list  Alarm and Interlocks test  Operation testing  Capacity testing  Power failure testing 26
  • 27.  Sequence testing  Test data sheets  SOP’s  Conclusions  Modification / change control  Discrepancy/Justification and corrective action  Operational Qualification Summary  References  Attachments/Appendices - Verification of test instruments - Chart recordings - P&I diagrams - Printouts 27
  • 28. Parameters  Have all Installation Qualification been completed for this system?  Is the system clean and free from dirt?  Is the direction of the rotation of agitator correct?  Check the operation of the agitator emergency stop?  Check the operation of all agitator controls, both on the main and local panels?  Check that the agitator in the vessel free to turn?  Pressurize the vessel and record the pressure drop for 10 min.  Perform a vacuum test and record the vacuum drop. 28
  • 29.  Documented verification that all aspects of a facility, utility or equipment that can affect the product quality perform as intended in meeting the predetermined acceptance criteria. 29
  • 30.  To integrate procedures, personnel, systems and materials to verify that the utility / environment / equipment / support systems produces the required output. This output may be a product contact utility, sterilization condition or environment. 30
  • 31.  Approval page  Pre-requisites  Objectives  System Description  Responsibilities  Acceptance Criteria  PQ test plan  Challenge test plan  Records of signatures  Test equipment/Instrument list  Test data sheets  SOP’s  References  Conclusions  Attachments 31
  • 32. Process Validation  The documented verification providing a high degree of assurance that a specific process will consistently produce a product meeting its predetermined specifications and quality attributes.  The new guidelines aligns process validation activities with a product life cycle concept. 32
  • 33.  211.42, 211.63, 211.68, 211.84  211.100(a) , 211.110(a), 211.110(b)  211.160(b), 211.165(c), 211.165(d), 211.180(e) 33
  • 34. Life Cycle of the product & the process  Stage 1 – Process Design  Stage 2 – Process qualification  Stage 3 - Continuous process verification 34
  • 35.  It is the activity of defining the commercial manufacturing process that will be reflected in planned master production and control records.  The goal of this stage is to design a process suitable for routine commercial manufacturing that can consistently deliver a product that meets its quality attributes.  It is based on the knowledge gained through development & scale-up activities. 35
  • 36. During this stage, the process design is evaluated to determine if the process is capable of reproducible commercial manufacturing. The products manufactured during this stage, if acceptable , can be released for distribution. Two Aspects  Design of facility and qualification of equipment and utilities.  Process Performance Qualification ( PPQ). 36
  • 37. Def.: “Releasing for distribution a lot of finished product, manufactured following a qualification protocol, that meets the standards established in the protocol, but before the entire study has been executed”.  Orphan Drugs  Specific drug for specific use  Short Shelf-life radio pharmaceuticals 37
  • 38.  The goal of this stage is continual assurance that the process remains in a state of control ( the validated state) during commercial manufacture.  The cGMP requirements, specifically the collection & evaluation of information & data about the performance of the process will allow detection of undesired process variability.  This stage is also applicable for legacy products. 38
  • 39. Change Control  Formal evaluation of the potential impact of planned modifications on the validated status of a product, process or facility. 39
  • 40.  Training personnel for IQ/OQ execution.  The purpose of the equipment/ system.  Use of test equipment  Applicable SOP’s  cGMP documentation of training  Document all training  Periodically review training requirements 40
  • 41.  A document that summarizes and analyses the test results at the end of PQ.  Provides a conclusion about the ability of the system to consistently meet acceptance criteria.  May be a stand alone document at each stage of IQ/OQ and PQ to summarize results. 41
  • 42. Commissioning and Qualification Project Phases Validation Phases Technology Transfer Collecting data Conceptual Design Basic Design Preliminary VMP Detailed Design Detailed VMP Procurement Detailed planning,DQ Construction IQ Pre commissioning Commissioning OQ Process operation / Validation 42
  • 43. 43 Introduction Qualification Personnel Schedule Preventive Maintenance Installation Operation Process Responsibilities Training Change Control Procedures Documents Appendices
  • 44. The company’s overall policy, intentions and approach to validation, including :  Validation of production processes  Cleaning procedures  Analytical methods  In-process control test procedures  Computerized systems  Persons responsible for design, review, approval  Documentation of each validation phase 44
  • 45.  Product validation is NOT …… - just 3 batches that meet specifications  Product validation is …… - an ongoing process to build confidence into the manufacturing activities - an ability to demonstrate consistency at any time. 45
  • 46.  Cleaning validation is establishing documented evidence that the equipment is consistently cleaned from product, microbial and cleaning agent residues to predetermined acceptable levels. 46
  • 47. A written procedure for cleaning validation which includes :  Responsibility for development, performance and approval of the validation study.  Establishment of SOP’s  Acceptance criteria - defined to prevent cross contamination - definition of residue limits 47
  • 48.  Cleaning procedure for each piece of equipment - Flow charts and diagrams - Cleaning agents, concentration, volume - Frequency - time left ‘dirty’ 48
  • 49.  Sampling procedures - swabs, rinse, location  Residue limits  Analytical methods 49
  • 50.  Validation report - Results Vs. acceptance criteria - Deviations and how handled - Conclusion that cleaning process is validated 50
  • 51.  Major change in cleaning procedure  Change in cleaning agent  New equipment 51
  • 52.  Knowledge of the materials - Potency of the drug - Pharmacological and toxic properties - Degradation products - Cleaning agents - Micro residues 52
  • 53. Residual Limits must be………….  Practical  Achievable  Verifiable  Safe FDA does not set acceptance specifications (limits). 53
  • 54. MAC = TD x BS x SF / LDD MAC = Maximum Allowable Carryover TD = Single Therapeutic Dose BS = Batch size of next product to be manufactured on the same equipment. SF = Safety Factor LDD = Largest Daily Dose of the next product in the same equipment. 54
  • 55. Ranitidine Tablets - Ibuprofen Tablets TD = Single Therapeutic Dose = 150 mg Ranitidine-Tab BS = Batch Size = 100 kg of Ibuprofen SF = Safety Factor = 1/1000 LDD = Largest Daily Dose of the next product in the same equipment = 200 mg X 5 tablets of Ibuprofen MAC = Max Allowable Carryover = 150 X 100 X 1000 x 1000 X 1/1000 X 1/1000 i.e 15000 mg in 100 kg Batch size i.e 150 mg in 1 kg = 150 ppm 55
  • 56. Presented by – JATIN SINGLA M.PHARM 1st year PH’CEUTICS