BAYSIDE ENERGY ADVISORS




Utility Scale Wind Project
Development: 101

prepared by John Chaimanis

April 5, 2012




Bayside Energy Advisors 918 Belmont St Watertown, MA 02472 P: 617.899.7815 E: jchaimanis@twotenthirtythree.com or chaimanis@yahoo.com
Wind Development
                                                                                                                       3

  The Five Elements
                                                                                                                    3

          Land
                                                                                                                         3

          Meteorology
                                                                                                                  3

          Permitting / Environmental Analysis 
                                                                                         4

          Interconnection / Transmission 
                                                                                              4

          Power Sales 
                                                                                                                 4

  Financial Participation in a Wind Project
                                                                                            5

  Fundamental Value Drivers
                                                                                                            6

          Core Components of Value
                                                                                                     6




Bayside Energy Advisors 918 Belmont St Watertown, MA 02472 P: 617.899.7815 E: jchaimanis@twotenthirtythree.com or chaimanis@yahoo.com
BAYSIDE ENERGY ADVISORS




Wind Development

The Five Elements
Utility scale wind projects are good investments for many stakeholders, produce clean renewable electricity, and help the
local economy. Developing a project can be a complex process, although an understanding of the fundamental building
blocks can help interested parties determine the right level of engagement. Every successful utility scale wind project
that has ever been built posses five elements, all of which must satisfactorily be met. The order of attainment can impact
overall cost and speed of development, therefore a strategic approach is necessary in order to reduce risk and exposure
to costly mistakes. The five elements are land, meteorology, permitting / environmental analysis, interconnection /
transmission, and power sales.

The financial, environmental, and generational benefits of wind projects are great. With the right understanding and
guidance it is possible to turn the idea into reality.

Land
Today, it is common for utility scale wind turbine generators to stand 80m tall, and to have a swept rotor diameter of 80m
- 100m, therefore appropriate site control is required for the optimal energy production and safe operation. Commonly,
land is leased (rather than purchased) from one or multiple land owners by a developer in order to form the project area.
Among other things the topography, zoning, chain of title, and proximity to other stakeholders must all be taken into
account. The objective is a contiguous project site which is reasonably build-able and insurable.

Meteorology
The wind is the fuel source, and therefore it is a key input relied upon by investors as a fundamental driver of economics.
While the wind is a free fuel source, its value is directly related to the frequency, distribution, and average speed.
Scientific measurement, correlation to long term reference data, and sophisticated prediction methods are used by



Utility Scale Wind Project Development 
                                                                                    3
BAYSIDE ENERGY ADVISORS



meteorologists to determine the probabilistic future wind performance. Depending on the size of a project, one or
multiple meteorologic towers are erected during the early stages of development to collect on site data which forms the
basis of the future analysis. In some cases technologies like LIDAR an SODAR can be employed during the
meteorological campaign. The objective is to have complete data which shows a regionally competitive wind resource,
that investors are willing to rely upon.

Permitting / Environmental Analysis
Wind energy is very compatible with farming and ranching which makes it an attractive opportunity to many. However
defining the potential impact to existing wildlife and plant life are an important part of responsible development. In
addition to being a good steward to the environment, projects must adhere to federal, state and / or local regulations.

Interconnection / Transmission
Electricity from the wind project must flow over existing or new transmission lines to a point where it can be used by a
load. Utility scale wind projects must apply for the right to interconnect to the power grid. The process is generally well
documented and prescribes a number of steps which could include financial deposits and evidence of development
progress. The ultimate objective is to obtain a Generator Interconnection Agreement.

Power Sales
Generally, developers of wind projects seek a long term power purchase agreement (PPA) with a creditworthy offtaker.
However, in some circumstances, selling power at the spot price into the market or obtaining a structured offtake
agreement (i.e. - hedge / synthetic PPA) is acceptable. Selling power from wind projects can be a competitive activity,
especially if there is small demand for new power, and there are other developers in close proximity. Understanding the
competitive dynamics, and cost of power are essential steps in developing a successful wind project.




Utility Scale Wind Project Development 
                                                                                      4
BAYSIDE ENERGY ADVISORS




Financial Participation in a Wind Project
There are many reasons to participate in a wind project, and this sections focuses on the financial benefits across a
spectrum of involvement. As a basic premise, the earlier an individual or entity becomes involved in the process and the
longer they stay in through operation, the greater the financial benefit. The table below outlines three possible levels of
engagement. There are multiple variations the these themes and additional value streams based on owner preference.


                                       Lease Holder               Project Originator /           Developer & Investor
                                                                         Developer
Activities                     Generally passive host for     Coordinates all activities up   All activities noted for
                               the project turbines. Some     through commencement of         Originator plus coordination
                               additional activities could    construction. Requires at       of project construction,
                               include supplying gravel /     least one expert who can        procurement, and financing
                               water during construction.     manage partners and             (including equity, tax equity,
                                                              consultants through the         and debt). Operation could
                                                              process.                        be in house or outsourced.
Control                        Minimal                        High until sale                 Total
Costs                          Essentially none. Attorney     Depending on the project        Development expenses
                               fees.                          maturity at the time of sale    $1.5M - $3M
                                                              between $100K - $3M.
                                                                                              Capital Investment $150 -
                                                                                              $190M
Profit Streams                  2% - 6% of revenues once       Purchase price payment and All income and tax benefits.
                               the project is operational. In recovery of expenses at sale Could structure royalty to
                               some cases an annual fee       of project.                     land as well.
                               per acre during
                                                              Ongoing royalty stream in
                               development.
                                                              some cases.
Value for a 100MW wind         $400,000 - $800,000 / year; 1) Recover all expenses            Leveraged 20 year equity
project with a $40/MWh         $8M - $14M over 20 years       2) $4M - $10M at project        IRR of 12% - 17%. Total
PPA and 40% NCF                                               sale (could be less if sold     value of tax benefits and
                                                              very early)                     income streams up to
                                                              3) $8M - $14M in lease          $400M.
                                                              royalties - if also the
                                                              landowner.




Utility Scale Wind Project Development 
                                                                                       5
BAYSIDE ENERGY ADVISORS




Fundamental Value Drivers

Core Components of Value
Although a wind project is effected by hundred’s of variables and many of those have implications on overall economics,
there are three core drivers of economic value inherent in a wind project.

A) Wind

B) Power Prices

C) Capital Costs



                                                       Wind


                                                                   Power
                                                                   Prices
                                                 Capital
                                                 Costs




                                      Core components of a successful wind project




Utility Scale Wind Project Development 
                                                                                  6

Más contenido relacionado

Último

Último (20)

Top 10 Most Downloaded Games on Play Store in 2024
Top 10 Most Downloaded Games on Play Store in 2024Top 10 Most Downloaded Games on Play Store in 2024
Top 10 Most Downloaded Games on Play Store in 2024
 
Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
 
AWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of Terraform
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
 
Manulife - Insurer Innovation Award 2024
Manulife - Insurer Innovation Award 2024Manulife - Insurer Innovation Award 2024
Manulife - Insurer Innovation Award 2024
 
MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
 
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
 
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
 
Artificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : UncertaintyArtificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : Uncertainty
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivity
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 

Destacado

Social Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie InsightsSocial Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie Insights
Kurio // The Social Media Age(ncy)
 

Destacado (20)

Skeleton Culture Code
Skeleton Culture CodeSkeleton Culture Code
Skeleton Culture Code
 
PEPSICO Presentation to CAGNY Conference Feb 2024
PEPSICO Presentation to CAGNY Conference Feb 2024PEPSICO Presentation to CAGNY Conference Feb 2024
PEPSICO Presentation to CAGNY Conference Feb 2024
 
Content Methodology: A Best Practices Report (Webinar)
Content Methodology: A Best Practices Report (Webinar)Content Methodology: A Best Practices Report (Webinar)
Content Methodology: A Best Practices Report (Webinar)
 
How to Prepare For a Successful Job Search for 2024
How to Prepare For a Successful Job Search for 2024How to Prepare For a Successful Job Search for 2024
How to Prepare For a Successful Job Search for 2024
 
Social Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie InsightsSocial Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie Insights
 
Trends In Paid Search: Navigating The Digital Landscape In 2024
Trends In Paid Search: Navigating The Digital Landscape In 2024Trends In Paid Search: Navigating The Digital Landscape In 2024
Trends In Paid Search: Navigating The Digital Landscape In 2024
 
5 Public speaking tips from TED - Visualized summary
5 Public speaking tips from TED - Visualized summary5 Public speaking tips from TED - Visualized summary
5 Public speaking tips from TED - Visualized summary
 
ChatGPT and the Future of Work - Clark Boyd
ChatGPT and the Future of Work - Clark Boyd ChatGPT and the Future of Work - Clark Boyd
ChatGPT and the Future of Work - Clark Boyd
 
Getting into the tech field. what next
Getting into the tech field. what next Getting into the tech field. what next
Getting into the tech field. what next
 
Google's Just Not That Into You: Understanding Core Updates & Search Intent
Google's Just Not That Into You: Understanding Core Updates & Search IntentGoogle's Just Not That Into You: Understanding Core Updates & Search Intent
Google's Just Not That Into You: Understanding Core Updates & Search Intent
 
How to have difficult conversations
How to have difficult conversations How to have difficult conversations
How to have difficult conversations
 
Introduction to Data Science
Introduction to Data ScienceIntroduction to Data Science
Introduction to Data Science
 
Time Management & Productivity - Best Practices
Time Management & Productivity -  Best PracticesTime Management & Productivity -  Best Practices
Time Management & Productivity - Best Practices
 
The six step guide to practical project management
The six step guide to practical project managementThe six step guide to practical project management
The six step guide to practical project management
 
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
 
Unlocking the Power of ChatGPT and AI in Testing - A Real-World Look, present...
Unlocking the Power of ChatGPT and AI in Testing - A Real-World Look, present...Unlocking the Power of ChatGPT and AI in Testing - A Real-World Look, present...
Unlocking the Power of ChatGPT and AI in Testing - A Real-World Look, present...
 
12 Ways to Increase Your Influence at Work
12 Ways to Increase Your Influence at Work12 Ways to Increase Your Influence at Work
12 Ways to Increase Your Influence at Work
 
ChatGPT webinar slides
ChatGPT webinar slidesChatGPT webinar slides
ChatGPT webinar slides
 
More than Just Lines on a Map: Best Practices for U.S Bike Routes
More than Just Lines on a Map: Best Practices for U.S Bike RoutesMore than Just Lines on a Map: Best Practices for U.S Bike Routes
More than Just Lines on a Map: Best Practices for U.S Bike Routes
 
Ride the Storm: Navigating Through Unstable Periods / Katerina Rudko (Belka G...
Ride the Storm: Navigating Through Unstable Periods / Katerina Rudko (Belka G...Ride the Storm: Navigating Through Unstable Periods / Katerina Rudko (Belka G...
Ride the Storm: Navigating Through Unstable Periods / Katerina Rudko (Belka G...
 

Wind Development 101 J Chaimanis

  • 1. BAYSIDE ENERGY ADVISORS Utility Scale Wind Project Development: 101 prepared by John Chaimanis April 5, 2012 Bayside Energy Advisors 918 Belmont St Watertown, MA 02472 P: 617.899.7815 E: jchaimanis@twotenthirtythree.com or chaimanis@yahoo.com
  • 2. Wind Development 3 The Five Elements 3 Land 3 Meteorology 3 Permitting / Environmental Analysis 4 Interconnection / Transmission 4 Power Sales 4 Financial Participation in a Wind Project 5 Fundamental Value Drivers 6 Core Components of Value 6 Bayside Energy Advisors 918 Belmont St Watertown, MA 02472 P: 617.899.7815 E: jchaimanis@twotenthirtythree.com or chaimanis@yahoo.com
  • 3. BAYSIDE ENERGY ADVISORS Wind Development The Five Elements Utility scale wind projects are good investments for many stakeholders, produce clean renewable electricity, and help the local economy. Developing a project can be a complex process, although an understanding of the fundamental building blocks can help interested parties determine the right level of engagement. Every successful utility scale wind project that has ever been built posses five elements, all of which must satisfactorily be met. The order of attainment can impact overall cost and speed of development, therefore a strategic approach is necessary in order to reduce risk and exposure to costly mistakes. The five elements are land, meteorology, permitting / environmental analysis, interconnection / transmission, and power sales. The financial, environmental, and generational benefits of wind projects are great. With the right understanding and guidance it is possible to turn the idea into reality. Land Today, it is common for utility scale wind turbine generators to stand 80m tall, and to have a swept rotor diameter of 80m - 100m, therefore appropriate site control is required for the optimal energy production and safe operation. Commonly, land is leased (rather than purchased) from one or multiple land owners by a developer in order to form the project area. Among other things the topography, zoning, chain of title, and proximity to other stakeholders must all be taken into account. The objective is a contiguous project site which is reasonably build-able and insurable. Meteorology The wind is the fuel source, and therefore it is a key input relied upon by investors as a fundamental driver of economics. While the wind is a free fuel source, its value is directly related to the frequency, distribution, and average speed. Scientific measurement, correlation to long term reference data, and sophisticated prediction methods are used by Utility Scale Wind Project Development 3
  • 4. BAYSIDE ENERGY ADVISORS meteorologists to determine the probabilistic future wind performance. Depending on the size of a project, one or multiple meteorologic towers are erected during the early stages of development to collect on site data which forms the basis of the future analysis. In some cases technologies like LIDAR an SODAR can be employed during the meteorological campaign. The objective is to have complete data which shows a regionally competitive wind resource, that investors are willing to rely upon. Permitting / Environmental Analysis Wind energy is very compatible with farming and ranching which makes it an attractive opportunity to many. However defining the potential impact to existing wildlife and plant life are an important part of responsible development. In addition to being a good steward to the environment, projects must adhere to federal, state and / or local regulations. Interconnection / Transmission Electricity from the wind project must flow over existing or new transmission lines to a point where it can be used by a load. Utility scale wind projects must apply for the right to interconnect to the power grid. The process is generally well documented and prescribes a number of steps which could include financial deposits and evidence of development progress. The ultimate objective is to obtain a Generator Interconnection Agreement. Power Sales Generally, developers of wind projects seek a long term power purchase agreement (PPA) with a creditworthy offtaker. However, in some circumstances, selling power at the spot price into the market or obtaining a structured offtake agreement (i.e. - hedge / synthetic PPA) is acceptable. Selling power from wind projects can be a competitive activity, especially if there is small demand for new power, and there are other developers in close proximity. Understanding the competitive dynamics, and cost of power are essential steps in developing a successful wind project. Utility Scale Wind Project Development 4
  • 5. BAYSIDE ENERGY ADVISORS Financial Participation in a Wind Project There are many reasons to participate in a wind project, and this sections focuses on the financial benefits across a spectrum of involvement. As a basic premise, the earlier an individual or entity becomes involved in the process and the longer they stay in through operation, the greater the financial benefit. The table below outlines three possible levels of engagement. There are multiple variations the these themes and additional value streams based on owner preference. Lease Holder Project Originator / Developer & Investor Developer Activities Generally passive host for Coordinates all activities up All activities noted for the project turbines. Some through commencement of Originator plus coordination additional activities could construction. Requires at of project construction, include supplying gravel / least one expert who can procurement, and financing water during construction. manage partners and (including equity, tax equity, consultants through the and debt). Operation could process. be in house or outsourced. Control Minimal High until sale Total Costs Essentially none. Attorney Depending on the project Development expenses fees. maturity at the time of sale $1.5M - $3M between $100K - $3M. Capital Investment $150 - $190M Profit Streams 2% - 6% of revenues once Purchase price payment and All income and tax benefits. the project is operational. In recovery of expenses at sale Could structure royalty to some cases an annual fee of project. land as well. per acre during Ongoing royalty stream in development. some cases. Value for a 100MW wind $400,000 - $800,000 / year; 1) Recover all expenses Leveraged 20 year equity project with a $40/MWh $8M - $14M over 20 years 2) $4M - $10M at project IRR of 12% - 17%. Total PPA and 40% NCF sale (could be less if sold value of tax benefits and very early) income streams up to 3) $8M - $14M in lease $400M. royalties - if also the landowner. Utility Scale Wind Project Development 5
  • 6. BAYSIDE ENERGY ADVISORS Fundamental Value Drivers Core Components of Value Although a wind project is effected by hundred’s of variables and many of those have implications on overall economics, there are three core drivers of economic value inherent in a wind project. A) Wind B) Power Prices C) Capital Costs Wind Power Prices Capital Costs Core components of a successful wind project Utility Scale Wind Project Development 6