Más contenido relacionado La actualidad más candente (20) Similar a Agile project tracking - burn up charts (20) Agile project tracking - burn up charts14. scope = story points* time = iterations *story point = estimation unit 40. Track when a story is added Story: Add a big red button to the homepage Estimate: 2 points Iteration added: 1 41. Track when a story is done Story: Add a big red button to the homepage Estimate: 2 points Iteration added: 1 Iteration signed off: 3 42. Plot them on a chart Story: Add a big red button to the homepage Estimate: 2 points Iteration added: 1 Iteration signed off: 3 46. Scope Time Expect scope to grow … So factor in a schedule buffer in your release plans 47. Agile teams test as they go … If you’re not continuously testing in a production-like environment, expect to spend time testing and stabilizing at the end of the project 49. Development complete ≠ complete A story doesn’t count as finished until it’s verified to be working in a production-like environment 50. There are still risks Continue to track risks, issues and external dependencies(they’re not going away)