SlideShare una empresa de Scribd logo
1 de 7
Descargar para leer sin conexión
The electronic version of this document is the latest version.
Page 1 of 7 Rev: 4
Citadel100
Case Study
“KKeeeeppiinngg BBuussiinneessss AAllwwaayyss OOnnlliinnee”
Citadel100 – Simulated Facility Power Outage
The electronic version of this document is the latest version.
Page 2 of 7 Rev: 2
Table of Contents
Facility Power Test.........................................................................................................................3
Timelines............................................................................................................................................4
Graphs..................................................................................................................................................5
Citadel100 – Simulated Facility Power Outage
The electronic version of this document is the latest version.
Page 3 of 7 Rev: 2
FACILITY POWER TEST
Noel,
For your information, we will test the complete power support system for
the facility tomorrow, July 18.
This will entail a simulation of a full utility outage.
We have been planning this operation since last August and have agreed a window for
tomorrow's date with all our customers.
Specialist contractors in attendance will be ESB, Mercury, F G Wilsons, Hitec, Schneider,
Anord and our own team.
The operation starts at 07:00 and power restoration is scheduled for 15:30.
We have full confidence in our resilient design and will notify you when complete.
The above mail was the final notification issued in a process that had been in the planning
stages for almost 12 months.
In any environment testing support equipment is important, in a Data Centre such testing is
critical.
The continual monitoring, measuring, calibration and maintenance of critical power paths in a
Data Centre are a constant, second by second occurrence.
The proving of this support path is only achieved in one way – total removal from the
National Grid.
Citadel100’s world class Data Centre in the National Digital Park, Citywest, Dublin carried
out such a test on July 18th
, 2007.
The actual test was preceded by months of preparation, client engagements and liasing with
all the third party personnel that were required in order to ensure total support for any
eventuality.
The operation itself began with a 07:00 briefing to all persons involved and the assignment of
specific tasks to individuals.
Following this, each person took up his or her post and awaited confirmation that the first
phase had begun.
Phase 1 involved shutting down T7 at 07:31.
T7 is the mechanical transformer feeding chillers, pumps, cooling units and controls.
The power down was effectively recognised by the Energy Management Systems as a power
outage triggering the support systems to take load by energising the Generation sets.
Citadel100 – Simulated Facility Power Outage
The electronic version of this document is the latest version.
Page 4 of 7 Rev: 2
The design of the plant allows cooling to be dropped during a power outage and to restart
when Diesel generation has synchronised and taken up full load.
Cooling was restored at 07:34.
The remainder of the transformers, which feed the critical power to the data suites, were
powered down in numerical sequence.
During this period there was, as designed, zero impact on any of our client’s critical
equipment.
In order to fully test the plant we remained on Generator support until 15:30 at which time
Utility supply was restored.
It was also important to study the impact of power restoration and to note the operation of the
control systems as utility power returned to normal.
The outcome was the complete proving of the entire Facility and confirmation that the design
and implementation was totally resilient.
The result was enhanced client confidence and most importantly keeping our business always
online.
From: Lyons, David
Sent: 18 July 2007 16:40
To: Carroll, Denis; Hennessy, Karl; Mc Donald, George
Cc: McCaul, Sinead; Irwin, Philip; Hurley, Brian; Meaney, Michael
Subject: MV change
Denis, Karl, George,
Just a quick email to thank you for all your efforts in ensuring that there was no impact to HP customers during
the MV settings change today, the transition from ESB to Generator power and back was as seamless as could
be possibly expected.
If you could also pass on our thanks to all facilities staff involved too.
Regards,
David Lyons
Service Business Support Manager
TIMELINES
July 18th
, 2007. 07:00 – Team Briefing.
July 18th
, 2007. 07:31 – T7 shut down.
July 18th
, 2007. 07:32 – Gensets energised.
July 18th
, 2007. 07:34 – Cooling restored.
Citadel100 – Simulated Facility Power Outage
The electronic version of this document is the latest version.
Page 5 of 7 Rev: 2
GRAPHS
The following graphs are snapshots from a single power supply showing
1. Loss of Utility Power.
2. Take – up by Generator supply.
3. Uninterrupted power supply to client equipment.
A) This graph shows the utility power feed from transformer 4A.
Citadel100 – Simulated Facility Power Outage
The electronic version of this document is the latest version.
Page 6 of 7 Rev: 2
B) This graph shows the power feed from the generators to breaker 4A following utility loss.
Citadel100 – Simulated Facility Power Outage
The electronic version of this document is the latest version.
Page 7 of 7 Rev: 2
C) This graph shows the power in the data suite – no break in power during the exercise.

Más contenido relacionado

Destacado

SEO do's and don'ts for e-commerce
SEO do's and don'ts for e-commerceSEO do's and don'ts for e-commerce
SEO do's and don'ts for e-commerceBernt Johansson
 
Googles nya spelregler för SEO
Googles nya spelregler för SEOGoogles nya spelregler för SEO
Googles nya spelregler för SEOTommy Skålberg
 
Webbdagarna Stockholm 2014 - Integrering av sök och SEO
Webbdagarna Stockholm 2014 - Integrering av sök och SEOWebbdagarna Stockholm 2014 - Integrering av sök och SEO
Webbdagarna Stockholm 2014 - Integrering av sök och SEOSESNordic AB
 
SEO:d, Analyticsdagarna 141021
SEO:d, Analyticsdagarna 141021SEO:d, Analyticsdagarna 141021
SEO:d, Analyticsdagarna 141021Summit & Friends
 

Destacado (6)

SEO do's and don'ts for e-commerce
SEO do's and don'ts for e-commerceSEO do's and don'ts for e-commerce
SEO do's and don'ts for e-commerce
 
Googles nya spelregler för SEO
Googles nya spelregler för SEOGoogles nya spelregler för SEO
Googles nya spelregler för SEO
 
Webbdagarna Stockholm 2014 - Integrering av sök och SEO
Webbdagarna Stockholm 2014 - Integrering av sök och SEOWebbdagarna Stockholm 2014 - Integrering av sök och SEO
Webbdagarna Stockholm 2014 - Integrering av sök och SEO
 
SEM/SEO
SEM/SEOSEM/SEO
SEM/SEO
 
SEO:d, Analyticsdagarna 141021
SEO:d, Analyticsdagarna 141021SEO:d, Analyticsdagarna 141021
SEO:d, Analyticsdagarna 141021
 
God SEO 2015
God SEO 2015God SEO 2015
God SEO 2015
 

Similar a Case Study

Engineering Practice Report
Engineering Practice ReportEngineering Practice Report
Engineering Practice ReportPaul Soko
 
Net_Alliant_Technologies
Net_Alliant_TechnologiesNet_Alliant_Technologies
Net_Alliant_TechnologiesCris Beagle
 
The role of energy storage with renewable electricity generation
The role of energy storage with renewable electricity generationThe role of energy storage with renewable electricity generation
The role of energy storage with renewable electricity generationGlenn Klith Andersen
 
Gate 2020 Electrical Engineering (29 years solution)
Gate 2020 Electrical Engineering (29 years solution)Gate 2020 Electrical Engineering (29 years solution)
Gate 2020 Electrical Engineering (29 years solution)IES Master
 
AutoGrid DER Webinar Slides
AutoGrid DER Webinar SlidesAutoGrid DER Webinar Slides
AutoGrid DER Webinar SlidesJeffrey Norman
 
Maintaining Reliability in the Modern Power System
Maintaining Reliability in the Modern Power System Maintaining Reliability in the Modern Power System
Maintaining Reliability in the Modern Power System Power System Operation
 
IRJET- Hybrid Renewable Energy Based Micro Grid
IRJET- Hybrid Renewable Energy Based Micro GridIRJET- Hybrid Renewable Energy Based Micro Grid
IRJET- Hybrid Renewable Energy Based Micro GridIRJET Journal
 
Ebook - Future Power Systems
Ebook - Future Power SystemsEbook - Future Power Systems
Ebook - Future Power SystemsLeonardo ENERGY
 
Report angel fern_ndez_sarabia
Report angel fern_ndez_sarabiaReport angel fern_ndez_sarabia
Report angel fern_ndez_sarabiaSalwaElSamannoudy
 
Report angel fern_ndez_sarabia
Report angel fern_ndez_sarabiaReport angel fern_ndez_sarabia
Report angel fern_ndez_sarabia.AHMED AMER
 
Impact_of_distributed_generation_on_dist (1).pdf
Impact_of_distributed_generation_on_dist (1).pdfImpact_of_distributed_generation_on_dist (1).pdf
Impact_of_distributed_generation_on_dist (1).pdfAashishChoudhary23
 
Power management for a changing world
Power management for a changing worldPower management for a changing world
Power management for a changing worldBassam Gomaa
 
Increasing Data Center Energy Efficiency By Monitoring And Targeting To Heati...
Increasing Data Center Energy Efficiency By Monitoring And Targeting To Heati...Increasing Data Center Energy Efficiency By Monitoring And Targeting To Heati...
Increasing Data Center Energy Efficiency By Monitoring And Targeting To Heati...TrendPoint Systems, LLC
 
Estimating Reliability of Power Factor Correction Circuits: A Comparative Study
Estimating Reliability of Power Factor Correction Circuits: A Comparative StudyEstimating Reliability of Power Factor Correction Circuits: A Comparative Study
Estimating Reliability of Power Factor Correction Circuits: A Comparative StudyIJERA Editor
 
Implementation of a Microcontroller Base Single Phase Automatic Changeover
Implementation of a Microcontroller Base Single Phase Automatic Changeover Implementation of a Microcontroller Base Single Phase Automatic Changeover
Implementation of a Microcontroller Base Single Phase Automatic Changeover IJSRED
 
The Value of Concentrating Solar Power and Thermal Energy Storage NREL
The Value of Concentrating Solar Power and Thermal Energy Storage NRELThe Value of Concentrating Solar Power and Thermal Energy Storage NREL
The Value of Concentrating Solar Power and Thermal Energy Storage NRELJustin Bean
 
IT and the smart grid, Peter Will,Information Sciences Institute, USC'
IT and the smart grid, Peter Will,Information Sciences Institute, USC'IT and the smart grid, Peter Will,Information Sciences Institute, USC'
IT and the smart grid, Peter Will,Information Sciences Institute, USC'University of Southern California
 
High level explanation of smart grids and battery energy storage systems
High level explanation of smart grids and battery energy storage systemsHigh level explanation of smart grids and battery energy storage systems
High level explanation of smart grids and battery energy storage systemsMircea Gingu
 
How we saved a Process Plant from break-down
How we saved a Process Plant from break-downHow we saved a Process Plant from break-down
How we saved a Process Plant from break-downSystem Protection
 

Similar a Case Study (20)

Engineering Practice Report
Engineering Practice ReportEngineering Practice Report
Engineering Practice Report
 
Net_Alliant_Technologies
Net_Alliant_TechnologiesNet_Alliant_Technologies
Net_Alliant_Technologies
 
The role of energy storage with renewable electricity generation
The role of energy storage with renewable electricity generationThe role of energy storage with renewable electricity generation
The role of energy storage with renewable electricity generation
 
Gate 2020 Electrical Engineering (29 years solution)
Gate 2020 Electrical Engineering (29 years solution)Gate 2020 Electrical Engineering (29 years solution)
Gate 2020 Electrical Engineering (29 years solution)
 
Power sector
Power sectorPower sector
Power sector
 
AutoGrid DER Webinar Slides
AutoGrid DER Webinar SlidesAutoGrid DER Webinar Slides
AutoGrid DER Webinar Slides
 
Maintaining Reliability in the Modern Power System
Maintaining Reliability in the Modern Power System Maintaining Reliability in the Modern Power System
Maintaining Reliability in the Modern Power System
 
IRJET- Hybrid Renewable Energy Based Micro Grid
IRJET- Hybrid Renewable Energy Based Micro GridIRJET- Hybrid Renewable Energy Based Micro Grid
IRJET- Hybrid Renewable Energy Based Micro Grid
 
Ebook - Future Power Systems
Ebook - Future Power SystemsEbook - Future Power Systems
Ebook - Future Power Systems
 
Report angel fern_ndez_sarabia
Report angel fern_ndez_sarabiaReport angel fern_ndez_sarabia
Report angel fern_ndez_sarabia
 
Report angel fern_ndez_sarabia
Report angel fern_ndez_sarabiaReport angel fern_ndez_sarabia
Report angel fern_ndez_sarabia
 
Impact_of_distributed_generation_on_dist (1).pdf
Impact_of_distributed_generation_on_dist (1).pdfImpact_of_distributed_generation_on_dist (1).pdf
Impact_of_distributed_generation_on_dist (1).pdf
 
Power management for a changing world
Power management for a changing worldPower management for a changing world
Power management for a changing world
 
Increasing Data Center Energy Efficiency By Monitoring And Targeting To Heati...
Increasing Data Center Energy Efficiency By Monitoring And Targeting To Heati...Increasing Data Center Energy Efficiency By Monitoring And Targeting To Heati...
Increasing Data Center Energy Efficiency By Monitoring And Targeting To Heati...
 
Estimating Reliability of Power Factor Correction Circuits: A Comparative Study
Estimating Reliability of Power Factor Correction Circuits: A Comparative StudyEstimating Reliability of Power Factor Correction Circuits: A Comparative Study
Estimating Reliability of Power Factor Correction Circuits: A Comparative Study
 
Implementation of a Microcontroller Base Single Phase Automatic Changeover
Implementation of a Microcontroller Base Single Phase Automatic Changeover Implementation of a Microcontroller Base Single Phase Automatic Changeover
Implementation of a Microcontroller Base Single Phase Automatic Changeover
 
The Value of Concentrating Solar Power and Thermal Energy Storage NREL
The Value of Concentrating Solar Power and Thermal Energy Storage NRELThe Value of Concentrating Solar Power and Thermal Energy Storage NREL
The Value of Concentrating Solar Power and Thermal Energy Storage NREL
 
IT and the smart grid, Peter Will,Information Sciences Institute, USC'
IT and the smart grid, Peter Will,Information Sciences Institute, USC'IT and the smart grid, Peter Will,Information Sciences Institute, USC'
IT and the smart grid, Peter Will,Information Sciences Institute, USC'
 
High level explanation of smart grids and battery energy storage systems
High level explanation of smart grids and battery energy storage systemsHigh level explanation of smart grids and battery energy storage systems
High level explanation of smart grids and battery energy storage systems
 
How we saved a Process Plant from break-down
How we saved a Process Plant from break-downHow we saved a Process Plant from break-down
How we saved a Process Plant from break-down
 

Case Study

  • 1. The electronic version of this document is the latest version. Page 1 of 7 Rev: 4 Citadel100 Case Study “KKeeeeppiinngg BBuussiinneessss AAllwwaayyss OOnnlliinnee”
  • 2. Citadel100 – Simulated Facility Power Outage The electronic version of this document is the latest version. Page 2 of 7 Rev: 2 Table of Contents Facility Power Test.........................................................................................................................3 Timelines............................................................................................................................................4 Graphs..................................................................................................................................................5
  • 3. Citadel100 – Simulated Facility Power Outage The electronic version of this document is the latest version. Page 3 of 7 Rev: 2 FACILITY POWER TEST Noel, For your information, we will test the complete power support system for the facility tomorrow, July 18. This will entail a simulation of a full utility outage. We have been planning this operation since last August and have agreed a window for tomorrow's date with all our customers. Specialist contractors in attendance will be ESB, Mercury, F G Wilsons, Hitec, Schneider, Anord and our own team. The operation starts at 07:00 and power restoration is scheduled for 15:30. We have full confidence in our resilient design and will notify you when complete. The above mail was the final notification issued in a process that had been in the planning stages for almost 12 months. In any environment testing support equipment is important, in a Data Centre such testing is critical. The continual monitoring, measuring, calibration and maintenance of critical power paths in a Data Centre are a constant, second by second occurrence. The proving of this support path is only achieved in one way – total removal from the National Grid. Citadel100’s world class Data Centre in the National Digital Park, Citywest, Dublin carried out such a test on July 18th , 2007. The actual test was preceded by months of preparation, client engagements and liasing with all the third party personnel that were required in order to ensure total support for any eventuality. The operation itself began with a 07:00 briefing to all persons involved and the assignment of specific tasks to individuals. Following this, each person took up his or her post and awaited confirmation that the first phase had begun. Phase 1 involved shutting down T7 at 07:31. T7 is the mechanical transformer feeding chillers, pumps, cooling units and controls. The power down was effectively recognised by the Energy Management Systems as a power outage triggering the support systems to take load by energising the Generation sets.
  • 4. Citadel100 – Simulated Facility Power Outage The electronic version of this document is the latest version. Page 4 of 7 Rev: 2 The design of the plant allows cooling to be dropped during a power outage and to restart when Diesel generation has synchronised and taken up full load. Cooling was restored at 07:34. The remainder of the transformers, which feed the critical power to the data suites, were powered down in numerical sequence. During this period there was, as designed, zero impact on any of our client’s critical equipment. In order to fully test the plant we remained on Generator support until 15:30 at which time Utility supply was restored. It was also important to study the impact of power restoration and to note the operation of the control systems as utility power returned to normal. The outcome was the complete proving of the entire Facility and confirmation that the design and implementation was totally resilient. The result was enhanced client confidence and most importantly keeping our business always online. From: Lyons, David Sent: 18 July 2007 16:40 To: Carroll, Denis; Hennessy, Karl; Mc Donald, George Cc: McCaul, Sinead; Irwin, Philip; Hurley, Brian; Meaney, Michael Subject: MV change Denis, Karl, George, Just a quick email to thank you for all your efforts in ensuring that there was no impact to HP customers during the MV settings change today, the transition from ESB to Generator power and back was as seamless as could be possibly expected. If you could also pass on our thanks to all facilities staff involved too. Regards, David Lyons Service Business Support Manager TIMELINES July 18th , 2007. 07:00 – Team Briefing. July 18th , 2007. 07:31 – T7 shut down. July 18th , 2007. 07:32 – Gensets energised. July 18th , 2007. 07:34 – Cooling restored.
  • 5. Citadel100 – Simulated Facility Power Outage The electronic version of this document is the latest version. Page 5 of 7 Rev: 2 GRAPHS The following graphs are snapshots from a single power supply showing 1. Loss of Utility Power. 2. Take – up by Generator supply. 3. Uninterrupted power supply to client equipment. A) This graph shows the utility power feed from transformer 4A.
  • 6. Citadel100 – Simulated Facility Power Outage The electronic version of this document is the latest version. Page 6 of 7 Rev: 2 B) This graph shows the power feed from the generators to breaker 4A following utility loss.
  • 7. Citadel100 – Simulated Facility Power Outage The electronic version of this document is the latest version. Page 7 of 7 Rev: 2 C) This graph shows the power in the data suite – no break in power during the exercise.