SlideShare una empresa de Scribd logo
1 de 18
Contents
Definition of Distress
Causes of Distress
Constructional errors
Design Deficiencies
Deterioration of concrete
Need for repairs in structure
Concrete repair system
Durable concrete repair
DISTRESS
• Distress means damage.
• Because of the varying conditions under which it is produced at various
locations, the quality of concrete suffers occasionally either during
production or during service conditions resulting in distress.
2
Causes of distress of concrete
1. Structural causes
- Externally applied loads
- Environmental loads
- Accidents
- Subsidence etc.
2. Errors in design and detailing
3. Poor construction practice
4. Construction overloads
5. Drying shrinkage
6. Thermal stress
7. Weathering
8. Corrosion
3
• In addition to distress in hardened concrete, the plastic concrete may suffer
damage due to,
- Plastic shrinkage
- settlement cracking
- early removal of formwork
- improper design of formwork
4
Construction Errors
1. Use of inferior quality of construction materials.
2. Use of waste water or saline water in construction.
3. Adding of more water to improve workability which increase the w/c
ratio.
4. Poor grading of concrete ingredients.
5. Poor mixing of concrete.
6. Batching of concrete by volume using mortar pans.
7. Insufficient compaction of concrete.
8. Dropping concrete from the height results into segregation.
9. Insufficient reinforcement into slab, beam, column etc.
10. Improper location of reinforcing steel.
5
11. Hooks , bends , overlaps are not properly provided.
12. Formwork props are not resting on a hard surface.
13. Early removal of formwork props.
14. Using props of insufficient strength.
15. Joints are not properly provided.
16. Improper curing of concrete.
17. Segregation of concrete during transportation.
18. Settlement of foundation
6
Design deficiencies
• Inadequate structural design :
1. Error in load calculations.
2. SBC is assumed without carrying out any field test.
3. Design not confirming to IS - 456 : 2000 and IS – 1893 : 1987 guidelines.
4. Design with many cantilevers.
5. Shear wall is not designed in multi storey building.
6. Stiffness in both direction is unequal resulting into torsion.
7. Effect of the short column in single storey.
8. Lack of knowledge of using structural design software like STAAD PRO,
ETABS etc.
7
• Poor design detailing :
1. Abrupt change in section.
2. Insufficient reinforcement at re – entrant corners and openings.
3. Inadequate provision for deflection.
4. Inadequate expansion joints.
5. Inadequate provision of drainage.
6. Material incompatibility.
7. Bent up bars are not properly shown.
8. Spacing of vertical stirrups is wrongly shown.
9. Column spacing of lateral ties is wrongly shown.
10. Ductile detailing is not as per IS – 13920.
8
DETERIORATION in concrete
• Causes of deterioration in concrete :
1. Accidental loading
2. Chemical reactions
- Acid attack
- Alkali carbonate rock reaction
- Alkali silica reaction
- Aggressive water attack
- Sulphate attack
3. Construction errors
4. Corrosion of metals
5. Design errors
- Inadequate structural design
- Poor design details
9
6. Erosion
- Abrasion
- Cavitations
7. Freezing and thawing
8. Settlement and movements
9. Shrinkage
- plastic shrinkage
- Drying shrinkage
10. Temperature changes
- Internally generated
- Externally generated
11. Weathering
10
Need for Repairs of structures
a) Workmanship:
• Repair personnel are responsible for making repairs that are durable and
well bonded to existing structure.
• Workmen should be fully instructed regarding repair procedures and
critical aspects.
• Constant vigilance should be exercised by contractor’s and government
forces to ensure maintenance of necessary standards of workmanship.
11
b) Procedures:
• Use procedures that have been successful or that have a proven high
reliability factor.
• Repairs on new work will develop best bond and likely to be durable and
permanent as original work.
• The method and materials proposed for use should be approved by an
authorized inspector.
12
c) Materials:
• They must be of high quality, relatively fresh and capable of meeting
specifications requirements for particular application or intended use.
• Mill reports or testing laboratory reports is required.
• New, unproven materials should be used only when,
- Standard repair materials are unsuitable
- The owners and parties should be informed about risks associated
with it.
13
Evaluate structures
Project needs
Determine causes of damage & effect
Repair analysis
User needs
Determine repair strategies
Methods and materials
Repair and protect
Urgency Aesthetics Lifespan Environment
Contractibility &
Effectiveness
14
Durable concrete repair
1. Determine the causes of damage
2. Evaluate the extent of damage
3. Evaluate the need of repair
4. Select the repair method
5. Prepare the old concrete for repair
6. Apply the repair method
7. Cure the repair properly
15
1. Determine the causes of damage :
If the cause of the original damage to concrete is not determined and
eliminated , or if an incorrect determination is made, whatever damaged
the original concrete will likely also damage the repaired concrete.
2. Evaluate the extent of damage :
The intent of this step is to determine how much concrete has been
damaged and how this damage will affect serviceability of this structure.
3. Evaluate the need to repair :
With early detection it may be possible to arrest the rate of
deterioration using maintenance procedure . Even if repairs is required,
early detection of damage will allow orderly budgeting of funds to pat the
cost of repair.
16
4. Select the repair methods :
With insufficient information, it is very difficult to make proper ,
economical , and successful selections. This steps define the types of
conditions the repair must resist the available repair construction time
period and when repair must be accomplished.
5. Prepare the old concrete for repair :
Preparation of the old concrete for application of repair material is of
primary importance in the accomplishment of durable repairs.
6. Apply the repair material :
The selected repair material should be applied on the prepared surface
using equipment with proper care.
7. Cure the repair properly :
The repaired concrete should be cured for about 14 days.
17
THANK YOU
18

Más contenido relacionado

La actualidad más candente

Non destructive test on concrete
Non destructive test on concreteNon destructive test on concrete
Non destructive test on concreteAglaia Connect
 
Maintenance and repair strategies
Maintenance and repair strategiesMaintenance and repair strategies
Maintenance and repair strategiesManikandan
 
Causes of deterioration of concrete structures
Causes of deterioration of concrete structuresCauses of deterioration of concrete structures
Causes of deterioration of concrete structuresKarthi Kavya
 
Ultrasonic pulse velocity test for concrete
Ultrasonic pulse velocity test for concreteUltrasonic pulse velocity test for concrete
Ultrasonic pulse velocity test for concreteCivil Engineer
 
Causes and prevention of cracks in buildings
Causes and prevention of cracks in buildingsCauses and prevention of cracks in buildings
Causes and prevention of cracks in buildingsSUPREETH Suppi
 
Repair and strengthening of concrete structures
Repair and strengthening of concrete structuresRepair and strengthening of concrete structures
Repair and strengthening of concrete structuresAbdallah Shaheen
 
Condition Survey, Evaluation & Damage Assessment
Condition Survey, Evaluation & Damage AssessmentCondition Survey, Evaluation & Damage Assessment
Condition Survey, Evaluation & Damage Assessmentwasim shaikh
 
Pull out test for concrete
Pull out test for concretePull out test for concrete
Pull out test for concreteAyaz khan
 
Condition survey and non destructive evalution of concrete
Condition survey and non destructive evalution of concreteCondition survey and non destructive evalution of concrete
Condition survey and non destructive evalution of concreteAvinash Kumar Gupta
 
Repair and rehabilitation of structures
Repair and rehabilitation of structuresRepair and rehabilitation of structures
Repair and rehabilitation of structuresKorrapati Pratyusha
 
Repair & Rehabilitation of Structures
Repair & Rehabilitation of StructuresRepair & Rehabilitation of Structures
Repair & Rehabilitation of StructuresRamanuj Jaldhari
 
Grouting, guniting, jacketing
Grouting, guniting, jacketingGrouting, guniting, jacketing
Grouting, guniting, jacketingAditya Sanyal
 
Cracks in concrete and its remedial measures
Cracks in concrete and its remedial measures Cracks in concrete and its remedial measures
Cracks in concrete and its remedial measures kamariya keyur
 
Deterioration in building
Deterioration in buildingDeterioration in building
Deterioration in buildingRumi Tamakhu
 
Deterioration of concrete
Deterioration of concreteDeterioration of concrete
Deterioration of concreteHarikrishna M.S
 

La actualidad más candente (20)

Non destructive test on concrete
Non destructive test on concreteNon destructive test on concrete
Non destructive test on concrete
 
Maintenance and repair strategies
Maintenance and repair strategiesMaintenance and repair strategies
Maintenance and repair strategies
 
Types of cracks in concrete
Types of cracks in concreteTypes of cracks in concrete
Types of cracks in concrete
 
Causes of deterioration of concrete structures
Causes of deterioration of concrete structuresCauses of deterioration of concrete structures
Causes of deterioration of concrete structures
 
Ultrasonic pulse velocity test for concrete
Ultrasonic pulse velocity test for concreteUltrasonic pulse velocity test for concrete
Ultrasonic pulse velocity test for concrete
 
Causes and prevention of cracks in buildings
Causes and prevention of cracks in buildingsCauses and prevention of cracks in buildings
Causes and prevention of cracks in buildings
 
Repair and strengthening of concrete structures
Repair and strengthening of concrete structuresRepair and strengthening of concrete structures
Repair and strengthening of concrete structures
 
Condition Survey, Evaluation & Damage Assessment
Condition Survey, Evaluation & Damage AssessmentCondition Survey, Evaluation & Damage Assessment
Condition Survey, Evaluation & Damage Assessment
 
Prestressed composite beams
Prestressed composite beamsPrestressed composite beams
Prestressed composite beams
 
Cracks in Buildings
Cracks in BuildingsCracks in Buildings
Cracks in Buildings
 
Pull out test for concrete
Pull out test for concretePull out test for concrete
Pull out test for concrete
 
Condition survey and non destructive evalution of concrete
Condition survey and non destructive evalution of concreteCondition survey and non destructive evalution of concrete
Condition survey and non destructive evalution of concrete
 
Repair and rehabilitation of structures
Repair and rehabilitation of structuresRepair and rehabilitation of structures
Repair and rehabilitation of structures
 
Concrete repair
Concrete repairConcrete repair
Concrete repair
 
Repair & Rehabilitation of Structures
Repair & Rehabilitation of StructuresRepair & Rehabilitation of Structures
Repair & Rehabilitation of Structures
 
Grouting, guniting, jacketing
Grouting, guniting, jacketingGrouting, guniting, jacketing
Grouting, guniting, jacketing
 
Rebound hammer test
Rebound hammer testRebound hammer test
Rebound hammer test
 
Cracks in concrete and its remedial measures
Cracks in concrete and its remedial measures Cracks in concrete and its remedial measures
Cracks in concrete and its remedial measures
 
Deterioration in building
Deterioration in buildingDeterioration in building
Deterioration in building
 
Deterioration of concrete
Deterioration of concreteDeterioration of concrete
Deterioration of concrete
 

Similar a Concrete Distress Causes and Repair Methods

Construction practices aphb
Construction practices aphbConstruction practices aphb
Construction practices aphbhlksd
 
Maintenance and repair strategies Question answers
Maintenance and repair strategies Question answersMaintenance and repair strategies Question answers
Maintenance and repair strategies Question answersRAMPRASAD KUMAWAT
 
Concreting of super structure
Concreting of super structureConcreting of super structure
Concreting of super structureMinh Bui Si
 
Building defect, Structure 1, ARC3400, FRSB, Universiti Putra Malaysia
Building defect, Structure 1, ARC3400, FRSB, Universiti Putra MalaysiaBuilding defect, Structure 1, ARC3400, FRSB, Universiti Putra Malaysia
Building defect, Structure 1, ARC3400, FRSB, Universiti Putra MalaysiaNangkula utaberta
 
Bps 5205 sustainability construction and maintainability velpandi & maria
Bps 5205  sustainability construction and maintainability  velpandi & mariaBps 5205  sustainability construction and maintainability  velpandi & maria
Bps 5205 sustainability construction and maintainability velpandi & mariaMaria Archana
 
Prefabricated Column
Prefabricated ColumnPrefabricated Column
Prefabricated ColumnAnees Khan
 
Chapter 1 repair stratergies
Chapter 1 repair stratergiesChapter 1 repair stratergies
Chapter 1 repair stratergiesAnkit Patel
 
Innovation in construction industry
Innovation in construction industryInnovation in construction industry
Innovation in construction industryYamini K
 
Retrofitting sequences by mostafa sameer
Retrofitting sequences by mostafa sameerRetrofitting sequences by mostafa sameer
Retrofitting sequences by mostafa sameerMostafa Sameer
 
Retrofitting Sequences of Existing Factory Buildings In Chittagong, Banglades...
Retrofitting Sequences of Existing Factory Buildings In Chittagong, Banglades...Retrofitting Sequences of Existing Factory Buildings In Chittagong, Banglades...
Retrofitting Sequences of Existing Factory Buildings In Chittagong, Banglades...Mostafa Sameer
 
Structural Analysis for Rehabilitation of Reinforced Concrete Structure
Structural Analysis for Rehabilitation of Reinforced Concrete StructureStructural Analysis for Rehabilitation of Reinforced Concrete Structure
Structural Analysis for Rehabilitation of Reinforced Concrete StructureIJERA Editor
 
Cost effectiveness in qulaity construction
Cost effectiveness in qulaity constructionCost effectiveness in qulaity construction
Cost effectiveness in qulaity constructionSeetha Ram P G
 
REPAIR AND REHABILITATION OF STRUCTURES.pptx
REPAIR AND REHABILITATION OF STRUCTURES.pptxREPAIR AND REHABILITATION OF STRUCTURES.pptx
REPAIR AND REHABILITATION OF STRUCTURES.pptxKavinKumars19
 
3rd Day - Mahmoud Abufouda
3rd Day - Mahmoud Abufouda3rd Day - Mahmoud Abufouda
3rd Day - Mahmoud AbufoudaMAHMOUD ABUFOUDA
 
capstoe PPT FINAL GLAX G.S.pptx
capstoe PPT FINAL GLAX G.S.pptxcapstoe PPT FINAL GLAX G.S.pptx
capstoe PPT FINAL GLAX G.S.pptxYogitaSalunke1
 

Similar a Concrete Distress Causes and Repair Methods (20)

Construction practices aphb
Construction practices aphbConstruction practices aphb
Construction practices aphb
 
Maintenance and repair strategies Question answers
Maintenance and repair strategies Question answersMaintenance and repair strategies Question answers
Maintenance and repair strategies Question answers
 
13324396.pptx
13324396.pptx13324396.pptx
13324396.pptx
 
Column & beam
Column & beamColumn & beam
Column & beam
 
Question & Answers RR&S
Question & Answers RR&SQuestion & Answers RR&S
Question & Answers RR&S
 
Concreting of super structure
Concreting of super structureConcreting of super structure
Concreting of super structure
 
Building defect, Structure 1, ARC3400, FRSB, Universiti Putra Malaysia
Building defect, Structure 1, ARC3400, FRSB, Universiti Putra MalaysiaBuilding defect, Structure 1, ARC3400, FRSB, Universiti Putra Malaysia
Building defect, Structure 1, ARC3400, FRSB, Universiti Putra Malaysia
 
Deterioration of Concrete
Deterioration of ConcreteDeterioration of Concrete
Deterioration of Concrete
 
Bps 5205 sustainability construction and maintainability velpandi & maria
Bps 5205  sustainability construction and maintainability  velpandi & mariaBps 5205  sustainability construction and maintainability  velpandi & maria
Bps 5205 sustainability construction and maintainability velpandi & maria
 
Prefabricated Column
Prefabricated ColumnPrefabricated Column
Prefabricated Column
 
Chapter 1 repair stratergies
Chapter 1 repair stratergiesChapter 1 repair stratergies
Chapter 1 repair stratergies
 
Innovation in construction industry
Innovation in construction industryInnovation in construction industry
Innovation in construction industry
 
Retrofitting sequences by mostafa sameer
Retrofitting sequences by mostafa sameerRetrofitting sequences by mostafa sameer
Retrofitting sequences by mostafa sameer
 
Retrofitting Sequences of Existing Factory Buildings In Chittagong, Banglades...
Retrofitting Sequences of Existing Factory Buildings In Chittagong, Banglades...Retrofitting Sequences of Existing Factory Buildings In Chittagong, Banglades...
Retrofitting Sequences of Existing Factory Buildings In Chittagong, Banglades...
 
Precast
PrecastPrecast
Precast
 
Structural Analysis for Rehabilitation of Reinforced Concrete Structure
Structural Analysis for Rehabilitation of Reinforced Concrete StructureStructural Analysis for Rehabilitation of Reinforced Concrete Structure
Structural Analysis for Rehabilitation of Reinforced Concrete Structure
 
Cost effectiveness in qulaity construction
Cost effectiveness in qulaity constructionCost effectiveness in qulaity construction
Cost effectiveness in qulaity construction
 
REPAIR AND REHABILITATION OF STRUCTURES.pptx
REPAIR AND REHABILITATION OF STRUCTURES.pptxREPAIR AND REHABILITATION OF STRUCTURES.pptx
REPAIR AND REHABILITATION OF STRUCTURES.pptx
 
3rd Day - Mahmoud Abufouda
3rd Day - Mahmoud Abufouda3rd Day - Mahmoud Abufouda
3rd Day - Mahmoud Abufouda
 
capstoe PPT FINAL GLAX G.S.pptx
capstoe PPT FINAL GLAX G.S.pptxcapstoe PPT FINAL GLAX G.S.pptx
capstoe PPT FINAL GLAX G.S.pptx
 

Más de kamariya keyur

Más de kamariya keyur (16)

estimation of structure
estimation of structureestimation of structure
estimation of structure
 
Pavement
PavementPavement
Pavement
 
Curing
CuringCuring
Curing
 
Connections
Connections Connections
Connections
 
Tunneling in soft ground and hard rock
Tunneling in soft ground and hard rockTunneling in soft ground and hard rock
Tunneling in soft ground and hard rock
 
Theory of errors
Theory of errors Theory of errors
Theory of errors
 
traffic characteristics
traffic characteristicstraffic characteristics
traffic characteristics
 
column and strut
column and strutcolumn and strut
column and strut
 
Plain sedimentation
Plain sedimentationPlain sedimentation
Plain sedimentation
 
Open channel flow
Open channel flowOpen channel flow
Open channel flow
 
Isolated column footing
Isolated column footingIsolated column footing
Isolated column footing
 
Flat slab
Flat slab Flat slab
Flat slab
 
durability and permeability of concrete
durability and permeability of concretedurability and permeability of concrete
durability and permeability of concrete
 
Cost & value management
Cost & value management Cost & value management
Cost & value management
 
Retaining wall
 Retaining wall  Retaining wall
Retaining wall
 
Compression member
Compression memberCompression member
Compression member
 

Último

Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Vishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsVishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsSachinPawar510423
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substationstephanwindworld
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitterShivangiSharma879191
 
lifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptxlifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptxsomshekarkn64
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Solving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptSolving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptJasonTagapanGulla
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 

Último (20)

9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Vishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsVishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documents
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substation
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter
 
lifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptxlifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptx
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Solving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptSolving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.ppt
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 

Concrete Distress Causes and Repair Methods

  • 1. Contents Definition of Distress Causes of Distress Constructional errors Design Deficiencies Deterioration of concrete Need for repairs in structure Concrete repair system Durable concrete repair
  • 2. DISTRESS • Distress means damage. • Because of the varying conditions under which it is produced at various locations, the quality of concrete suffers occasionally either during production or during service conditions resulting in distress. 2
  • 3. Causes of distress of concrete 1. Structural causes - Externally applied loads - Environmental loads - Accidents - Subsidence etc. 2. Errors in design and detailing 3. Poor construction practice 4. Construction overloads 5. Drying shrinkage 6. Thermal stress 7. Weathering 8. Corrosion 3
  • 4. • In addition to distress in hardened concrete, the plastic concrete may suffer damage due to, - Plastic shrinkage - settlement cracking - early removal of formwork - improper design of formwork 4
  • 5. Construction Errors 1. Use of inferior quality of construction materials. 2. Use of waste water or saline water in construction. 3. Adding of more water to improve workability which increase the w/c ratio. 4. Poor grading of concrete ingredients. 5. Poor mixing of concrete. 6. Batching of concrete by volume using mortar pans. 7. Insufficient compaction of concrete. 8. Dropping concrete from the height results into segregation. 9. Insufficient reinforcement into slab, beam, column etc. 10. Improper location of reinforcing steel. 5
  • 6. 11. Hooks , bends , overlaps are not properly provided. 12. Formwork props are not resting on a hard surface. 13. Early removal of formwork props. 14. Using props of insufficient strength. 15. Joints are not properly provided. 16. Improper curing of concrete. 17. Segregation of concrete during transportation. 18. Settlement of foundation 6
  • 7. Design deficiencies • Inadequate structural design : 1. Error in load calculations. 2. SBC is assumed without carrying out any field test. 3. Design not confirming to IS - 456 : 2000 and IS – 1893 : 1987 guidelines. 4. Design with many cantilevers. 5. Shear wall is not designed in multi storey building. 6. Stiffness in both direction is unequal resulting into torsion. 7. Effect of the short column in single storey. 8. Lack of knowledge of using structural design software like STAAD PRO, ETABS etc. 7
  • 8. • Poor design detailing : 1. Abrupt change in section. 2. Insufficient reinforcement at re – entrant corners and openings. 3. Inadequate provision for deflection. 4. Inadequate expansion joints. 5. Inadequate provision of drainage. 6. Material incompatibility. 7. Bent up bars are not properly shown. 8. Spacing of vertical stirrups is wrongly shown. 9. Column spacing of lateral ties is wrongly shown. 10. Ductile detailing is not as per IS – 13920. 8
  • 9. DETERIORATION in concrete • Causes of deterioration in concrete : 1. Accidental loading 2. Chemical reactions - Acid attack - Alkali carbonate rock reaction - Alkali silica reaction - Aggressive water attack - Sulphate attack 3. Construction errors 4. Corrosion of metals 5. Design errors - Inadequate structural design - Poor design details 9
  • 10. 6. Erosion - Abrasion - Cavitations 7. Freezing and thawing 8. Settlement and movements 9. Shrinkage - plastic shrinkage - Drying shrinkage 10. Temperature changes - Internally generated - Externally generated 11. Weathering 10
  • 11. Need for Repairs of structures a) Workmanship: • Repair personnel are responsible for making repairs that are durable and well bonded to existing structure. • Workmen should be fully instructed regarding repair procedures and critical aspects. • Constant vigilance should be exercised by contractor’s and government forces to ensure maintenance of necessary standards of workmanship. 11
  • 12. b) Procedures: • Use procedures that have been successful or that have a proven high reliability factor. • Repairs on new work will develop best bond and likely to be durable and permanent as original work. • The method and materials proposed for use should be approved by an authorized inspector. 12
  • 13. c) Materials: • They must be of high quality, relatively fresh and capable of meeting specifications requirements for particular application or intended use. • Mill reports or testing laboratory reports is required. • New, unproven materials should be used only when, - Standard repair materials are unsuitable - The owners and parties should be informed about risks associated with it. 13
  • 14. Evaluate structures Project needs Determine causes of damage & effect Repair analysis User needs Determine repair strategies Methods and materials Repair and protect Urgency Aesthetics Lifespan Environment Contractibility & Effectiveness 14
  • 15. Durable concrete repair 1. Determine the causes of damage 2. Evaluate the extent of damage 3. Evaluate the need of repair 4. Select the repair method 5. Prepare the old concrete for repair 6. Apply the repair method 7. Cure the repair properly 15
  • 16. 1. Determine the causes of damage : If the cause of the original damage to concrete is not determined and eliminated , or if an incorrect determination is made, whatever damaged the original concrete will likely also damage the repaired concrete. 2. Evaluate the extent of damage : The intent of this step is to determine how much concrete has been damaged and how this damage will affect serviceability of this structure. 3. Evaluate the need to repair : With early detection it may be possible to arrest the rate of deterioration using maintenance procedure . Even if repairs is required, early detection of damage will allow orderly budgeting of funds to pat the cost of repair. 16
  • 17. 4. Select the repair methods : With insufficient information, it is very difficult to make proper , economical , and successful selections. This steps define the types of conditions the repair must resist the available repair construction time period and when repair must be accomplished. 5. Prepare the old concrete for repair : Preparation of the old concrete for application of repair material is of primary importance in the accomplishment of durable repairs. 6. Apply the repair material : The selected repair material should be applied on the prepared surface using equipment with proper care. 7. Cure the repair properly : The repaired concrete should be cured for about 14 days. 17