SlideShare una empresa de Scribd logo
1 de 70
COFFER DAM
S.S.A.S.I.T, SURAT GTU
Definition
Uses
Selection of
Coffer Dams
Types of Coffer
Dams
Design features
of coffer dams
Leakage
Prevention
Economic
Height
2
CONTENTS
DEFINITION OF COFFER
DAM
 Cofferdams are temporary enclosures to keep out water
and soil so as to permit dewatering and construction of the
permanent facility (structure) in the dry.
 A Coffer Dam is a temporary structure which is built
in a river, lake etc. to remove water from an area and
make it possible to carry on the construction work
under reasonably dry conditions.
 Meaning of Coffer Dam : Coffer = Box
 Cofferdams are usually required for projects such as
dams, docks and construction of bridge piers and
abutments.
3
4
REQUIREMENTS OF COFFEDAM
• Cofferdam should be reasonably watertight.
•Ground water or water lying above ground level should be
excluded.
• Materials – earth , timber , steel & concrete.
• Constructed at site of work.
• Depend- depth , soil condition , difference in water level,
availability of materials.
• The design and layout of a cofferdam should be such that
the total cost of construction, maintenance and pumping
is minimum.
• It should be stable against bursting, overturning and
sliding, under the floods and waves.
USES OF COFFERDAMS
• To facilitate pile driving operations.
• To place grillage & raft foundations.
• To construct foundations of piers & abutments of
bridges, dams, docks etc.
• To provide a working platform for the foundations
when water is met with.
5
SELECTION OF TYPE OF COFFERDAMS
1) The area to be protected by a cofferdam (small area or
large area).
2) The depth of water (shallow depth or deep depth).
3) The possibility of overtopping by floods, tides etc.
4) The nature of bed on which the cofferdam is to rest
(pervious or impervious layers).
5) Velocity of flowing water.
6) The possibility of scour due to reduction of waterway
caused by the construction of cofferdam.
7) The availability of construction materials.
8) Transportation facilities available.
6
TYPES OF COFFER DAM
1.Earth fill cofferdams - mainly for low level water
2.Rock fill cofferdams
3.Timber Crib or rock filled crib cofferdams - Construction on
land and than floated into place, which is also known as Gravity Dam
4.Braced / Sheet Pile Coffer Dam- Consisting of Sheet Piles,
mainly used in shallow water depth
(i). Single wall coffer dams
(ii). Double wall coffer dams
(iii). Cellular cofferdams
7
EARTH FILL COFFERDAMS120to150
cm 8
9
It is constructed in places where the depth of water is not much, say
1.3 to 1.8 m.
The earth bank is carried about one meter above the water level.
The top width of the bank should not be less than 1 mtr. and the side
slopes in a vary from 1 : 1 to 1 : 2.
The earth embankment should be built from a mixture of clay and
sand or clay and gravel.
In order to prevent the embankment from scouring due to the action
of water, side slopes of the bank on water side should be pitched with
rubble boulders.
10
ROCK FILL COFFERDAMS 11
 If the depth of water to be retained by the embankment
of cofferdam is of order of 3 m .
 Stone or rubble is used for the embankment.
 This construction is adopted only if the stone is easily
available in the nearby areas.
 The stones are assembled in the required shape of the
embankment and the voids are partially filled with earth
and stone-chips.
 On the waterside, the rock fill is to be provided with an
impervious layer of earth.
12
13
 It consists of timber cribs made from logs of wood
 Constructed on land and floated into place
 It consists of a unit or a cell open at the bottom and
having the framework of horizontal timber members.
 Hollow space formed are then filled with rock or
gravel
 Depth of water – 10 to 20 m
 Used for wide excavation and rocky river bottoms
TIMBER CRIB OR ROCK FILLED CRIB
COFFERDAMS 14
TIMBER CRIB OR ROCK FILLED CRIB COFFERDAMS
15
16
1. SINGLE WALLED COFFER
DAM 17
 Area to be enclosed is small and the depth of water is
more 4.5 to 6 m.
Timber piles known as guide piles are first driven deep
into the firm ground below the river bed.
Depending upon the velocity of the current of the water in
the river, the c/c spacing of the piles may vary between 1.8
to 4.5 m.
Longitudinal runners called Wales are then bolted to the
guide.
18
Steel or wooden sheet piles are then driven into the river
bed along the Wales and are secured to the Wales by bolts.
 The sheets on the two faces are braced by trussed
arrangement of struts. This helps in increasing the stability
of walls against the water pressure.
Half-filled bags of sand stacked on the inside and the
outside faces of the sheets help in increasing the stability of
cofferdam.
After the cofferdam is constructed, the water in the enclosed
area is pumped out and the construction work is taken up.
19
20
21
2. DOUBLE WALLED COFFERDAMS
 Double-walled cofferdam is provided to enclose a larger area.
Its construction is essentially the same as that of a single-walled
cofferdam except that in place of one wall, a pair of walls with a
gap in between is used all along the boundary of the space to be
enclosed.
This type of cofferdam can be used in depth of water up to 12 m.
- The double wall cofferdams are of two types:
(I) Ohio – river type cofferdams
(ii) Timber or steel sheeting cofferdams
22
23
24
OHIO RIVER TYPE COFFERDAM
Ohio river in USA.
Used in hard & soft bed (no erosion).
Unsuitable in deep water & swift flow.
Construction
Wales fixed at 1.50m vertically.
Wale joints, double vertical planks are provided.
Tie rods threaded & cross braces fixed.
Fixes sheet piles.
Beams (inside & outside)
Removing safely.
25
26
27
Timber Sheet Pile
 Timber sheet pile were extensively
used for cofferdam when depth of
water is about 6 to 10 m.
 It can be gradually replaced with
steel pile.
 It can only be used for small
depth since no deep piling in
28
Timber or steel sheeting cofferdams
29
30
3. CELLULAR COFFERDAMS
- The cellular cofferdams are mostly used for dewatering
large areas , where the depth of water may be 19 to 21 m.
- Mostly used the construction of marine structures like
Dams, Locks etc.
- The two common shapes of the cellular cofferdam are:
(i) Circular type
(ii) Diaphragm type
31
Circular type cellular cofferdam:
 The circular type of cellular cofferdam has the advantage that
each cell may be filled completely to the top before starting
the construction of the next cell without causing any
distortion to the shell of the cofferdam.
 Thus, when one cell is completely filled up with crushed
stone, broken bricks, gravel and sand. It can be used for
placing crane or other equipment required for the construction of
other cells.
32
33
 In addition, each cell acts as a self-supporting independent unit
and in case one of the cells collapses due to scour or interlock
damage or some other reason, it does not produce any adverse
effect on the neighboring cells. It is found that the interlock
stresses reach their maximum permissible value when the
diameter of cell is about 21 meter.
 Hence in case, from design consideration it is necessary to have
effective width of the cofferdam more than 21 meter,
diaphragm type of cofferdam must be used.
34
35
36
37
38
Diaphragm type cellular cofferdam:
• This Consists of a series of arcs of steel sheet piles connected as
shown in the image.
• The straight diaphragm wails are connected to each other by steel
piles arranged in the form of arches on either sides.
• The radius of the connecting arcs is generally made equal to
the distance between the straight diaphragm walls.
39
40
• After the cells are driven to the required depth, they are filled with earth,
sand, gravel or other filling material. In this type of cofferdam, as the
diaphragm which separates the two cells is a straight wall, it is
necessary to fill adjacent cells at approximately the same rate.
• If this is not done, the unbalanced pressure from the fill will distort the
diaphragm (cross-walls) which may result in the failure of the
interlocks.
• In this respect, the circular type cofferdam has the advantage over the
diaphragm type cofferdam because in the former, it is not necessary to fill
the adjacent cells at the same time.
41
42
43
 These are actually small concrete dams and they have been used
economically on many jobs.
The framework usually consist of pre cast R.C.C piles and sheets.
 The pre cast R.C.C sheet piles are provided with suitable edges
and they are driven in a similar manner to steel sheet piles.
 The main disadvantage of this cofferdam is that it is costly. But
when it is to be incorporated as a part of permanent structure it
proves to be economical.
CONCRETE COFFERDAM
44
MOVABLE OR SUSPENDED
COFFERDAMS
 Where there are numbers of repetition work in
under water foundations ,such as in the piers
of multi span river bridges , it is economical to
design the cofferdams to be moved as a single
unit from one foundation to another.
45
46
47
Water may leak through the underground flow of water or through the
piling sheet of the cofferdam. The following measures can be adopted
to prevent leakages in cofferdam.
1.Water entering the dewatered area through fissures or cracks in the
rocks can be stopped by grouting the fissures by cement grout.
2. Clay or mixture of clay and sand can be dumped in form of beams
both on inside and outside faces of the cofferdam.
3. In case of single-walled cofferdams, sheeting should be connected
through V-shaped notches and filled with clay puddle.
4. Cracks or fine joints or nail holes in the sheet piles should be
closed using bitumen or cement mortar.
LEAKAGE PREVENTION IN COFFERDAMS
48
5. If a lot of leakages is taking place and no measures stated above
have been to control it, the water face of the cofferdam may be
completely covered with canvass coated with tar or tarpaulin.
6. In case of double-walled cofferdams leakage is generally because of
insufficient compaction of the filling material. In this case, measures to
control seepage through filling material should be adopted.
7. Another method may be a box filled with the mixture of ashes and
sawdust held near the leaking joints. Leaking water carries these
contents into the joints and thus helps check the leakage to some
extent.
8. Sufficient grease applied at interlocks of sheet piles also helps check
leakage of water.
DESIGN FEATURES OF COFFERDAMS
 The design of a cofferdam depends on various factors such as.
(i) Hydrostatic head of Water
(ii) Dimensions of the area to be covered by the cofferdams
(iii) Subsoil conditions
(iv) Fluctuations or of outside water level
(v) Possibility of erosion
(vi) Presence of ice
(vii) Floating logs(the stem of a cut-down tree, etc.
49
 A purely theoretically designed cofferdam may fail for
factors unaccounted in its design.
 Therefore ,become necessary to combine practical
knowledge or experience with the theoretical aspects in the
design of a cofferdam.
 For width and Depth of cofferdam :
for H < 3 m, W = H
H > 3, W = 3 + 1/3*(H - 3)
Where, W = Width of cofferdam in metres
H = Height of water above river bed in metres
50
• 1.Depth of Water
- Low depth => Earthen Dam
- High Depth => Sheet Pile Coffer Dam
• 2.Current and nature of flowering of Sheet Pile
- High Current => Sheet Pile Coffer Dam (Higher Seepage
Control Capacity)
- Low Current => Earthen or any other Dam (Less Seepage
Control Capacity)
Factors governing the Economic
Height of Coffer Dam 51
The maximum height of cofferdam for which its total cost is
minimums known as the most economic height of cofferdam.
• 3.Type and Period of Work
- Short Duration Work => Timber Dam
- Long Duration work => Sheet Pile Coffer Dam
• 4.High and Low Tide Level of Reservoir
- Sheet Pile must have top level slightly higher than that
of the HTL. So that even in extreme case water can not
over top the coffer dam, to achieve the dry working
through out the season.
52
PHOTO GALLERY OF COFFER DAM
53
54
55
56
57
58
59
60
GAMMON INDIA LIMITED
CABLE -STAY BRIDGE SURAT
AP-02 (EXCAVATION WORK)
61
Bracing welding work in progress
62
63
64
65
SHEET PILE COFFER DAM
66
67
68
69
70

Más contenido relacionado

La actualidad más candente

Chapter 4 seepage theories
Chapter 4 seepage theoriesChapter 4 seepage theories
Chapter 4 seepage theoriesMohsin Siddique
 
Concrete dam lecture 1
Concrete dam lecture 1Concrete dam lecture 1
Concrete dam lecture 1Vidhi Khokhani
 
Chapter 3 shallow foundations
Chapter 3 shallow foundationsChapter 3 shallow foundations
Chapter 3 shallow foundationsKHUSHBU SHAH
 
Design of Hydraulic Structures
Design of Hydraulic StructuresDesign of Hydraulic Structures
Design of Hydraulic StructuresDamalla Rams
 
Canal alignment
Canal alignmentCanal alignment
Canal alignmentNaveenaa
 
TERZAGHI’S BEARING CAPACITY THEORY
TERZAGHI’S BEARING CAPACITY THEORYTERZAGHI’S BEARING CAPACITY THEORY
TERZAGHI’S BEARING CAPACITY THEORYSANJEEV Wazir
 
Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)Ankit Singh
 
Design and construction of well foundations
Design and construction of well foundationsDesign and construction of well foundations
Design and construction of well foundationsDar Hilal
 
energy dissipator in hydraulic structure
energy dissipator  in  hydraulic structure energy dissipator  in  hydraulic structure
energy dissipator in hydraulic structure Kiran Jadhav
 
7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERING7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERINGVATSAL PATEL
 
Gravity dam stability analysis
Gravity dam stability analysisGravity dam stability analysis
Gravity dam stability analysisDivya Vishnoi
 
Canal Regulation & Cross Drainage Works
Canal Regulation & Cross Drainage WorksCanal Regulation & Cross Drainage Works
Canal Regulation & Cross Drainage WorksGAURAV. H .TANDON
 

La actualidad más candente (20)

Chapter 4 seepage theories
Chapter 4 seepage theoriesChapter 4 seepage theories
Chapter 4 seepage theories
 
Concrete dam lecture 1
Concrete dam lecture 1Concrete dam lecture 1
Concrete dam lecture 1
 
Chapter 3 shallow foundations
Chapter 3 shallow foundationsChapter 3 shallow foundations
Chapter 3 shallow foundations
 
Earthen Dams
Earthen DamsEarthen Dams
Earthen Dams
 
Chapter 3 caisson
Chapter 3 caissonChapter 3 caisson
Chapter 3 caisson
 
Design of Hydraulic Structures
Design of Hydraulic StructuresDesign of Hydraulic Structures
Design of Hydraulic Structures
 
Well foundation
Well foundationWell foundation
Well foundation
 
Reservoir Planning
Reservoir PlanningReservoir Planning
Reservoir Planning
 
Diversion Headworks
Diversion HeadworksDiversion Headworks
Diversion Headworks
 
Canal alignment
Canal alignmentCanal alignment
Canal alignment
 
Gravity Dam
Gravity DamGravity Dam
Gravity Dam
 
Canal Fall
Canal FallCanal Fall
Canal Fall
 
TERZAGHI’S BEARING CAPACITY THEORY
TERZAGHI’S BEARING CAPACITY THEORYTERZAGHI’S BEARING CAPACITY THEORY
TERZAGHI’S BEARING CAPACITY THEORY
 
Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)
 
Design and construction of well foundations
Design and construction of well foundationsDesign and construction of well foundations
Design and construction of well foundations
 
energy dissipator in hydraulic structure
energy dissipator  in  hydraulic structure energy dissipator  in  hydraulic structure
energy dissipator in hydraulic structure
 
7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERING7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERING
 
Gravity dam stability analysis
Gravity dam stability analysisGravity dam stability analysis
Gravity dam stability analysis
 
Canal Regulation & Cross Drainage Works
Canal Regulation & Cross Drainage WorksCanal Regulation & Cross Drainage Works
Canal Regulation & Cross Drainage Works
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 

Similar a Chapter 2 coffer-dam

Similar a Chapter 2 coffer-dam (20)

BCT- Module 5 a coffer-dam (Part_2)
BCT- Module 5 a coffer-dam (Part_2)BCT- Module 5 a coffer-dam (Part_2)
BCT- Module 5 a coffer-dam (Part_2)
 
types of coffer dam
types of coffer dam types of coffer dam
types of coffer dam
 
Types of-cofferdams
Types of-cofferdamsTypes of-cofferdams
Types of-cofferdams
 
Coffer dams types
Coffer dams  typesCoffer dams  types
Coffer dams types
 
caissons and cofferdam in substructure construction
caissons and cofferdam in substructure constructioncaissons and cofferdam in substructure construction
caissons and cofferdam in substructure construction
 
Earthwork & track formation Railway Engineering
Earthwork & track formation Railway EngineeringEarthwork & track formation Railway Engineering
Earthwork & track formation Railway Engineering
 
Dams
DamsDams
Dams
 
Dams
DamsDams
Dams
 
cofferdam-150424121052-conversion-gate01.pptx
cofferdam-150424121052-conversion-gate01.pptxcofferdam-150424121052-conversion-gate01.pptx
cofferdam-150424121052-conversion-gate01.pptx
 
Earthen dam
Earthen damEarthen dam
Earthen dam
 
4. COFFERDAM (ACE) 2160601 GTU
4. COFFERDAM (ACE) 2160601 GTU4. COFFERDAM (ACE) 2160601 GTU
4. COFFERDAM (ACE) 2160601 GTU
 
Cofferdam_ppt.pptx
Cofferdam_ppt.pptxCofferdam_ppt.pptx
Cofferdam_ppt.pptx
 
First assignment group (2) presentation.pdf
First assignment group (2) presentation.pdfFirst assignment group (2) presentation.pdf
First assignment group (2) presentation.pdf
 
Coffer dams
Coffer damsCoffer dams
Coffer dams
 
Pile Foundation by Pratik Solanki (tes.google.com/site/infodiplomacivil/)
Pile Foundation by Pratik Solanki (tes.google.com/site/infodiplomacivil/)Pile Foundation by Pratik Solanki (tes.google.com/site/infodiplomacivil/)
Pile Foundation by Pratik Solanki (tes.google.com/site/infodiplomacivil/)
 
Well Foundation
Well FoundationWell Foundation
Well Foundation
 
Aravind B RGUKT Basar
Aravind B RGUKT BasarAravind B RGUKT Basar
Aravind B RGUKT Basar
 
ALL ABOUT DEEP FOUNDATIONS
ALL ABOUT DEEP FOUNDATIONSALL ABOUT DEEP FOUNDATIONS
ALL ABOUT DEEP FOUNDATIONS
 
Deep foundation
Deep foundationDeep foundation
Deep foundation
 
06. Diversion Headworks-2.pdf
06. Diversion Headworks-2.pdf06. Diversion Headworks-2.pdf
06. Diversion Headworks-2.pdf
 

Más de KHUSHBU SHAH

PLANE TABLE SURVEY
PLANE TABLE SURVEYPLANE TABLE SURVEY
PLANE TABLE SURVEYKHUSHBU SHAH
 
DEMOLITION & DISMANTLING OF WORK
DEMOLITION & DISMANTLING OF WORKDEMOLITION & DISMANTLING OF WORK
DEMOLITION & DISMANTLING OF WORKKHUSHBU SHAH
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWAREKHUSHBU SHAH
 
Bridge Engineering
Bridge EngineeringBridge Engineering
Bridge EngineeringKHUSHBU SHAH
 
Chapter 7 Maintenance of railway track
Chapter 7 Maintenance of railway trackChapter 7 Maintenance of railway track
Chapter 7 Maintenance of railway trackKHUSHBU SHAH
 
Chapter 6 Points,crossings and yards
Chapter 6 Points,crossings and yardsChapter 6 Points,crossings and yards
Chapter 6 Points,crossings and yardsKHUSHBU SHAH
 
Chapter 5 Introduction to railway
Chapter 5 Introduction to railwayChapter 5 Introduction to railway
Chapter 5 Introduction to railwayKHUSHBU SHAH
 
Chapter 4 Drainge and maintenance of road
Chapter 4 Drainge and maintenance of roadChapter 4 Drainge and maintenance of road
Chapter 4 Drainge and maintenance of roadKHUSHBU SHAH
 
Chapter 2 Road geometrics
Chapter 2 Road geometricsChapter 2 Road geometrics
Chapter 2 Road geometricsKHUSHBU SHAH
 
Chapter 1 Introduction to road
Chapter 1 Introduction to roadChapter 1 Introduction to road
Chapter 1 Introduction to roadKHUSHBU SHAH
 
Equipment management
Equipment managementEquipment management
Equipment managementKHUSHBU SHAH
 
Material management
Material managementMaterial management
Material managementKHUSHBU SHAH
 
Chapter 8 introduction to construction equipments
Chapter 8 introduction to construction equipmentsChapter 8 introduction to construction equipments
Chapter 8 introduction to construction equipmentsKHUSHBU SHAH
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formworkKHUSHBU SHAH
 
Chapter 4 control of ground water in excavations
Chapter 4 control of ground water in excavationsChapter 4 control of ground water in excavations
Chapter 4 control of ground water in excavationsKHUSHBU SHAH
 
Chapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONSChapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONSKHUSHBU SHAH
 
Chapter 13 green building
Chapter 13 green buildingChapter 13 green building
Chapter 13 green buildingKHUSHBU SHAH
 
Chapter 12 special treatments
Chapter 12 special treatmentsChapter 12 special treatments
Chapter 12 special treatmentsKHUSHBU SHAH
 
Chapter 11 temporary works
Chapter 11 temporary worksChapter 11 temporary works
Chapter 11 temporary worksKHUSHBU SHAH
 

Más de KHUSHBU SHAH (20)

PLANE TABLE SURVEY
PLANE TABLE SURVEYPLANE TABLE SURVEY
PLANE TABLE SURVEY
 
DEMOLITION & DISMANTLING OF WORK
DEMOLITION & DISMANTLING OF WORKDEMOLITION & DISMANTLING OF WORK
DEMOLITION & DISMANTLING OF WORK
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
 
Bridge Engineering
Bridge EngineeringBridge Engineering
Bridge Engineering
 
Chapter 7 Maintenance of railway track
Chapter 7 Maintenance of railway trackChapter 7 Maintenance of railway track
Chapter 7 Maintenance of railway track
 
Chapter 6 Points,crossings and yards
Chapter 6 Points,crossings and yardsChapter 6 Points,crossings and yards
Chapter 6 Points,crossings and yards
 
Chapter 5 Introduction to railway
Chapter 5 Introduction to railwayChapter 5 Introduction to railway
Chapter 5 Introduction to railway
 
Chapter 4 Drainge and maintenance of road
Chapter 4 Drainge and maintenance of roadChapter 4 Drainge and maintenance of road
Chapter 4 Drainge and maintenance of road
 
Chapter 2 Road geometrics
Chapter 2 Road geometricsChapter 2 Road geometrics
Chapter 2 Road geometrics
 
Chapter 1 Introduction to road
Chapter 1 Introduction to roadChapter 1 Introduction to road
Chapter 1 Introduction to road
 
Equipment management
Equipment managementEquipment management
Equipment management
 
Labour management
Labour managementLabour management
Labour management
 
Material management
Material managementMaterial management
Material management
 
Chapter 8 introduction to construction equipments
Chapter 8 introduction to construction equipmentsChapter 8 introduction to construction equipments
Chapter 8 introduction to construction equipments
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
 
Chapter 4 control of ground water in excavations
Chapter 4 control of ground water in excavationsChapter 4 control of ground water in excavations
Chapter 4 control of ground water in excavations
 
Chapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONSChapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONS
 
Chapter 13 green building
Chapter 13 green buildingChapter 13 green building
Chapter 13 green building
 
Chapter 12 special treatments
Chapter 12 special treatmentsChapter 12 special treatments
Chapter 12 special treatments
 
Chapter 11 temporary works
Chapter 11 temporary worksChapter 11 temporary works
Chapter 11 temporary works
 

Último

Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...ZurliaSoop
 
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxHMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxmarlenawright1
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptxMaritesTamaniVerdade
 
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...Nguyen Thanh Tu Collection
 
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...Pooja Bhuva
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.christianmathematics
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxAreebaZafar22
 
SOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning PresentationSOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning Presentationcamerronhm
 
How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17Celine George
 
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptxCOMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptxannathomasp01
 
Plant propagation: Sexual and Asexual propapagation.pptx
Plant propagation: Sexual and Asexual propapagation.pptxPlant propagation: Sexual and Asexual propapagation.pptx
Plant propagation: Sexual and Asexual propapagation.pptxUmeshTimilsina1
 
REMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptxREMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptxDr. Ravikiran H M Gowda
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxheathfieldcps1
 
Google Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptxGoogle Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptxDr. Sarita Anand
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibitjbellavia9
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17Celine George
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSCeline George
 
How to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxHow to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxCeline George
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxDenish Jangid
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfAdmir Softic
 

Último (20)

Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
 
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxHMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
 
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
 
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 
SOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning PresentationSOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning Presentation
 
How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17
 
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptxCOMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
 
Plant propagation: Sexual and Asexual propapagation.pptx
Plant propagation: Sexual and Asexual propapagation.pptxPlant propagation: Sexual and Asexual propapagation.pptx
Plant propagation: Sexual and Asexual propapagation.pptx
 
REMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptxREMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptx
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
 
Google Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptxGoogle Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptx
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibit
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POS
 
How to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxHow to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptx
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 

Chapter 2 coffer-dam

  • 2. Definition Uses Selection of Coffer Dams Types of Coffer Dams Design features of coffer dams Leakage Prevention Economic Height 2 CONTENTS
  • 3. DEFINITION OF COFFER DAM  Cofferdams are temporary enclosures to keep out water and soil so as to permit dewatering and construction of the permanent facility (structure) in the dry.  A Coffer Dam is a temporary structure which is built in a river, lake etc. to remove water from an area and make it possible to carry on the construction work under reasonably dry conditions.  Meaning of Coffer Dam : Coffer = Box  Cofferdams are usually required for projects such as dams, docks and construction of bridge piers and abutments. 3
  • 4. 4 REQUIREMENTS OF COFFEDAM • Cofferdam should be reasonably watertight. •Ground water or water lying above ground level should be excluded. • Materials – earth , timber , steel & concrete. • Constructed at site of work. • Depend- depth , soil condition , difference in water level, availability of materials. • The design and layout of a cofferdam should be such that the total cost of construction, maintenance and pumping is minimum. • It should be stable against bursting, overturning and sliding, under the floods and waves.
  • 5. USES OF COFFERDAMS • To facilitate pile driving operations. • To place grillage & raft foundations. • To construct foundations of piers & abutments of bridges, dams, docks etc. • To provide a working platform for the foundations when water is met with. 5
  • 6. SELECTION OF TYPE OF COFFERDAMS 1) The area to be protected by a cofferdam (small area or large area). 2) The depth of water (shallow depth or deep depth). 3) The possibility of overtopping by floods, tides etc. 4) The nature of bed on which the cofferdam is to rest (pervious or impervious layers). 5) Velocity of flowing water. 6) The possibility of scour due to reduction of waterway caused by the construction of cofferdam. 7) The availability of construction materials. 8) Transportation facilities available. 6
  • 7. TYPES OF COFFER DAM 1.Earth fill cofferdams - mainly for low level water 2.Rock fill cofferdams 3.Timber Crib or rock filled crib cofferdams - Construction on land and than floated into place, which is also known as Gravity Dam 4.Braced / Sheet Pile Coffer Dam- Consisting of Sheet Piles, mainly used in shallow water depth (i). Single wall coffer dams (ii). Double wall coffer dams (iii). Cellular cofferdams 7
  • 9. 9 It is constructed in places where the depth of water is not much, say 1.3 to 1.8 m. The earth bank is carried about one meter above the water level. The top width of the bank should not be less than 1 mtr. and the side slopes in a vary from 1 : 1 to 1 : 2. The earth embankment should be built from a mixture of clay and sand or clay and gravel. In order to prevent the embankment from scouring due to the action of water, side slopes of the bank on water side should be pitched with rubble boulders.
  • 10. 10
  • 12.  If the depth of water to be retained by the embankment of cofferdam is of order of 3 m .  Stone or rubble is used for the embankment.  This construction is adopted only if the stone is easily available in the nearby areas.  The stones are assembled in the required shape of the embankment and the voids are partially filled with earth and stone-chips.  On the waterside, the rock fill is to be provided with an impervious layer of earth. 12
  • 13. 13
  • 14.  It consists of timber cribs made from logs of wood  Constructed on land and floated into place  It consists of a unit or a cell open at the bottom and having the framework of horizontal timber members.  Hollow space formed are then filled with rock or gravel  Depth of water – 10 to 20 m  Used for wide excavation and rocky river bottoms TIMBER CRIB OR ROCK FILLED CRIB COFFERDAMS 14
  • 15. TIMBER CRIB OR ROCK FILLED CRIB COFFERDAMS 15
  • 16. 16
  • 17. 1. SINGLE WALLED COFFER DAM 17  Area to be enclosed is small and the depth of water is more 4.5 to 6 m. Timber piles known as guide piles are first driven deep into the firm ground below the river bed. Depending upon the velocity of the current of the water in the river, the c/c spacing of the piles may vary between 1.8 to 4.5 m. Longitudinal runners called Wales are then bolted to the guide.
  • 18. 18 Steel or wooden sheet piles are then driven into the river bed along the Wales and are secured to the Wales by bolts.  The sheets on the two faces are braced by trussed arrangement of struts. This helps in increasing the stability of walls against the water pressure. Half-filled bags of sand stacked on the inside and the outside faces of the sheets help in increasing the stability of cofferdam. After the cofferdam is constructed, the water in the enclosed area is pumped out and the construction work is taken up.
  • 19. 19
  • 20. 20
  • 21. 21
  • 22. 2. DOUBLE WALLED COFFERDAMS  Double-walled cofferdam is provided to enclose a larger area. Its construction is essentially the same as that of a single-walled cofferdam except that in place of one wall, a pair of walls with a gap in between is used all along the boundary of the space to be enclosed. This type of cofferdam can be used in depth of water up to 12 m. - The double wall cofferdams are of two types: (I) Ohio – river type cofferdams (ii) Timber or steel sheeting cofferdams 22
  • 23. 23
  • 24. 24
  • 25. OHIO RIVER TYPE COFFERDAM Ohio river in USA. Used in hard & soft bed (no erosion). Unsuitable in deep water & swift flow. Construction Wales fixed at 1.50m vertically. Wale joints, double vertical planks are provided. Tie rods threaded & cross braces fixed. Fixes sheet piles. Beams (inside & outside) Removing safely. 25
  • 26. 26
  • 27. 27
  • 28. Timber Sheet Pile  Timber sheet pile were extensively used for cofferdam when depth of water is about 6 to 10 m.  It can be gradually replaced with steel pile.  It can only be used for small depth since no deep piling in 28
  • 29. Timber or steel sheeting cofferdams 29
  • 30. 30
  • 31. 3. CELLULAR COFFERDAMS - The cellular cofferdams are mostly used for dewatering large areas , where the depth of water may be 19 to 21 m. - Mostly used the construction of marine structures like Dams, Locks etc. - The two common shapes of the cellular cofferdam are: (i) Circular type (ii) Diaphragm type 31
  • 32. Circular type cellular cofferdam:  The circular type of cellular cofferdam has the advantage that each cell may be filled completely to the top before starting the construction of the next cell without causing any distortion to the shell of the cofferdam.  Thus, when one cell is completely filled up with crushed stone, broken bricks, gravel and sand. It can be used for placing crane or other equipment required for the construction of other cells. 32
  • 33. 33  In addition, each cell acts as a self-supporting independent unit and in case one of the cells collapses due to scour or interlock damage or some other reason, it does not produce any adverse effect on the neighboring cells. It is found that the interlock stresses reach their maximum permissible value when the diameter of cell is about 21 meter.  Hence in case, from design consideration it is necessary to have effective width of the cofferdam more than 21 meter, diaphragm type of cofferdam must be used.
  • 34. 34
  • 35. 35
  • 36. 36
  • 37. 37
  • 38. 38
  • 39. Diaphragm type cellular cofferdam: • This Consists of a series of arcs of steel sheet piles connected as shown in the image. • The straight diaphragm wails are connected to each other by steel piles arranged in the form of arches on either sides. • The radius of the connecting arcs is generally made equal to the distance between the straight diaphragm walls. 39
  • 40. 40 • After the cells are driven to the required depth, they are filled with earth, sand, gravel or other filling material. In this type of cofferdam, as the diaphragm which separates the two cells is a straight wall, it is necessary to fill adjacent cells at approximately the same rate. • If this is not done, the unbalanced pressure from the fill will distort the diaphragm (cross-walls) which may result in the failure of the interlocks. • In this respect, the circular type cofferdam has the advantage over the diaphragm type cofferdam because in the former, it is not necessary to fill the adjacent cells at the same time.
  • 41. 41
  • 42. 42
  • 43. 43  These are actually small concrete dams and they have been used economically on many jobs. The framework usually consist of pre cast R.C.C piles and sheets.  The pre cast R.C.C sheet piles are provided with suitable edges and they are driven in a similar manner to steel sheet piles.  The main disadvantage of this cofferdam is that it is costly. But when it is to be incorporated as a part of permanent structure it proves to be economical. CONCRETE COFFERDAM
  • 44. 44
  • 45. MOVABLE OR SUSPENDED COFFERDAMS  Where there are numbers of repetition work in under water foundations ,such as in the piers of multi span river bridges , it is economical to design the cofferdams to be moved as a single unit from one foundation to another. 45
  • 46. 46
  • 47. 47 Water may leak through the underground flow of water or through the piling sheet of the cofferdam. The following measures can be adopted to prevent leakages in cofferdam. 1.Water entering the dewatered area through fissures or cracks in the rocks can be stopped by grouting the fissures by cement grout. 2. Clay or mixture of clay and sand can be dumped in form of beams both on inside and outside faces of the cofferdam. 3. In case of single-walled cofferdams, sheeting should be connected through V-shaped notches and filled with clay puddle. 4. Cracks or fine joints or nail holes in the sheet piles should be closed using bitumen or cement mortar. LEAKAGE PREVENTION IN COFFERDAMS
  • 48. 48 5. If a lot of leakages is taking place and no measures stated above have been to control it, the water face of the cofferdam may be completely covered with canvass coated with tar or tarpaulin. 6. In case of double-walled cofferdams leakage is generally because of insufficient compaction of the filling material. In this case, measures to control seepage through filling material should be adopted. 7. Another method may be a box filled with the mixture of ashes and sawdust held near the leaking joints. Leaking water carries these contents into the joints and thus helps check the leakage to some extent. 8. Sufficient grease applied at interlocks of sheet piles also helps check leakage of water.
  • 49. DESIGN FEATURES OF COFFERDAMS  The design of a cofferdam depends on various factors such as. (i) Hydrostatic head of Water (ii) Dimensions of the area to be covered by the cofferdams (iii) Subsoil conditions (iv) Fluctuations or of outside water level (v) Possibility of erosion (vi) Presence of ice (vii) Floating logs(the stem of a cut-down tree, etc. 49
  • 50.  A purely theoretically designed cofferdam may fail for factors unaccounted in its design.  Therefore ,become necessary to combine practical knowledge or experience with the theoretical aspects in the design of a cofferdam.  For width and Depth of cofferdam : for H < 3 m, W = H H > 3, W = 3 + 1/3*(H - 3) Where, W = Width of cofferdam in metres H = Height of water above river bed in metres 50
  • 51. • 1.Depth of Water - Low depth => Earthen Dam - High Depth => Sheet Pile Coffer Dam • 2.Current and nature of flowering of Sheet Pile - High Current => Sheet Pile Coffer Dam (Higher Seepage Control Capacity) - Low Current => Earthen or any other Dam (Less Seepage Control Capacity) Factors governing the Economic Height of Coffer Dam 51 The maximum height of cofferdam for which its total cost is minimums known as the most economic height of cofferdam.
  • 52. • 3.Type and Period of Work - Short Duration Work => Timber Dam - Long Duration work => Sheet Pile Coffer Dam • 4.High and Low Tide Level of Reservoir - Sheet Pile must have top level slightly higher than that of the HTL. So that even in extreme case water can not over top the coffer dam, to achieve the dry working through out the season. 52
  • 53. PHOTO GALLERY OF COFFER DAM 53
  • 54. 54
  • 55. 55
  • 56. 56
  • 57. 57
  • 58. 58
  • 59. 59
  • 60. 60
  • 61. GAMMON INDIA LIMITED CABLE -STAY BRIDGE SURAT AP-02 (EXCAVATION WORK) 61
  • 62. Bracing welding work in progress 62
  • 63. 63
  • 64. 64
  • 65. 65
  • 67. 67
  • 68. 68
  • 69. 69
  • 70. 70