PROJECT MANAGEMENT
FOR INSTRUCTIONAL
DESIGNERS
Presented by:
Kimberly McKee and Kimberly Klotz
University of Central Arkansas
Instructional Technologies Graduate Program
Kimberly Klotz
(kklotz@uca.edu)
 Bachelor of Arts ‘06 (Art, Journalism)
 Master of Science ‘13 (Instructional
Technology/Distance Education)
 7 years of design/marketing experience in
higher education
 48 hours of Project Management professional
development
 Employed in the Division of Outreach and
Community Engagement, University of Central
Arkansas
Kimberly McKee
(kmckee@uca.edu)
 Bachelor of Arts (English, Writing, Journalism)
 Master of Science ‘13 (Instructional
Technology/Distance Education Emphasis)
 17 years of technical writing experience for a
technology company
 Grant writing contractor
 48 hours of Project Management professional
development
 Employed in the Division of Outreach and
Community Engagement, University of Central
Arkansas
Project Management Institute (PMI)
http://www.pmi.org
PMI is one of the world’s largest not-for-profit
membership associations for the Project Management
profession, with more than 650,000 members and
credential holders in more than 185 countries.
PMI Offers Two Certification Levels:
Project Management Professional (PMP)
Certified Associate in Project
Management (CAPM) – Entry Level
Certification
Project Management
Certification Requirements
1. Bachelor’s degree
2. 3 years of Project Management
experience
3. 4500 hours of leading projects
4. 35 hours of Project Management
education
5. Pass the test
OR
1. High school degree
2. 5 years of Project Management
experience
3. 7500 hours of leading projects
4. 35 hours of Project Management
education
5. Pass the test
1. High school diploma or equivalent
2. 1500 hours of Project Management
experience
3. Pass the test
OR
1. High school diploma or equivalent
2. 23 hours of Project Management
instruction
3. Pass the test
Project Management
Professional (PMP)
Certified Associate
in Project Management (CAPM)
What is Project Management?
 The application of knowledge, skills,
tools and techniques to project
activities to meet the project
requirements. (PMI)
 To determine project success, we
must also include the client. (Meredith & Mantel)
Applying Project Management principles
increases the success of a project.
What is a project?
 Developed to achieve the purposes and goals of an
organization, institution or business
 Purpose and goals are defined by stakeholders
 Initiatives to increase organizational effectiveness or
efficiency (such as incorporating new technologies
and updating/improving processes)
 Major activities outside the normal work of an
organization’s department or functional units or major
activities that cross functional boundaries
Project Characteristics
 Temporary – defined beginning and end
 Create a product, service or result that is
unique
Who can manage a project?
 Outside contractors
 Internal group in a Project Management Office
(PMO)
 Internal team
 Instructional Designer
Core Competencies
of the Project Manager
Key Skills of the Project
Manager
 Develops a plan to meet project goals
 Monitors plan to ensure project stays on track
 Energizes the team around the success of the
project
 Maintains organization
 Establishes priorities
 Communicates clear goals and expectations
A Project Manager is
goal directed and milestone
oriented!
Project Management and ADDIE Instructional Design Model
Project Management:
Initiate
ADDIE: Analyze
 Recognizes a project or the next phase of an
existing project
 Recognizes that resources should be committed
to the project
Activities:
1. Conduct Needs Analysis
2. Develop Project Charter
3. Identify and Document Stakeholders
Step 1: Needs Analysis
 Feasibility study to determine performance
gaps at the individual and business levels
 Presents alternatives and possible solutions
 Prepared by the designer, team, outside
agency
 Approved by leadership
Conducting a Needs
Analysis
 Answers Who, What,
When, Where, Why, How
questions
 Locates the root cause of
the performance gap
 Compares what is
expected to what is
actually achieved
 Understand the
learner (job experiences,
motivation, aptitude,
 Conduct a survey
 Walk thru current processes
 Talk to customers, if possible and
needed
 Review previous training efforts
 Review sales records and
customer feedback forums
 Conduct interviews
 Facilitate focus groups
 Facilitate workshop sessions
 Conduct group brainstorming
 Observations
 Prototype – working model to
obtain feedback before
proceeding with project
WHY? HOW?
Needs Analysis Format
Use this format to develop a Needs Analysis Report.
1. Training requested
2. Job, tasks, duties to be performed
3. Expected performance
4. Data collection method
5. Actual performance
6. Cause of performance gap
7. Cost estimate of training
8. Benefit of training
9. Training proposal
10. Management support recommendations (feedback, measurement)
11. Narrative
Step 2: Project Charter
 Provides structure to the Project Plan
 Justifies the project
 Documents the need being addressed
 Includes a description of the project
 Documents proposed result of the project
 Includes input from stakeholders
 Leadership responsible for obtaining sign-off
by the project sponsor (person financing the
project), senior management, stakeholders
Project Charter Format
Use this format to develop a Project Charter.
1. Purpose
2. Description of Work
3. Objectives
4. In-scope deliverables (what the project includes)
Out-of-scope deliverables (what the project does not include)
5. Roles and responsibilities
6. Milestones
7. Major known risks
8. Assumptions and Constraints
9. Constraints
10. External dependencies
11. Summary of budget
12. Vendors
Stakeholders
 Includes practitioners or groups of people with
specialized knowledge or skills in a particular
area
 Interests should be considered throughout the
project
Stakeholder Log
Format
Use this format to develop a Stakeholder Log.
1. Name
2. Role on Project
3. Department
4. Interest
5. Knowledge level
6. Expectation
7. Level of influence on the project
Project Management: Plan
ADDIE: Design
 40% of time allocated to complete the project
should be spent in planning
 Size and complexity of project determines the
processes to be included
Activities:
1. Instructional Design Document
2. Project Management Plan
3. Components of Project Management Plan
4. Project Scope Statement
5. Work Breakdown Structure (WBS)
Step 3: Instructional Design
Document
 Outlines the framework of the instructional
plan
 Provides high-level overview of the product
content and how it will be treated
 Enables stakeholders to validate the program’s
objectives, architecture, content and concepts
before development
 Identifies learning strategies (learning styles
and adult learning principles)
Instructional Design Document
Format
Use this format to develop an Instructional Design Document.
Learning Objectives
1. Describe what the learner is expected to achieve when performing the
task
2. Task statement
3. Conditions under which the task is performed
Key Points – Content and Concept
1. Product information, concepts and criteria to be covered in each module
Process and Activity
1. Summary of the types of learning activities that will be completed in the
respective modules
2. Describe how presentation and application methods are distributed
throughout the learning program
Step 4: Project Management
Plan
 Overall approach used to plan and manage a project
 Consists of subsidiary plans that detail how specific areas of the
project will be managed
 Documents cost, time, quality, risk, and resources to complete the
project
Input:
 Project charter
 Instructional design document
 Process outputs that will be used for the project
 Environmental factors outside the organization
 Specific information about what may influence success,
organizational policies, guidelines, procedures, plans, and/or
standards for conducting work
 Stakeholder input, if skills and knowledge warrant
Output:
 Project Management Plan
Project Management Plan
Components
 Project Scope Statement
 Cost and Budget
 Work Breakdown Structure (WBS)
 Schedule Management
 Issues Management
 Change Management
 Quality Management
 Human Resource Management
 Procurement Management
 Risk Management
 Communications Plan
Project Scope Statement
 Documents initial planning efforts for the
project
 Used to reach agreement among managers,
stakeholders and teams before resources are
allocated
Project Scope Statement
Format
Use this format to develop a Project Scope Statement.
1. Purpose and justification
2. Product description
3. Objectives
4. Project description (Includes: deliverables breakdown. Do not
include: completion criteria, external dependencies, assumptions,
constraints.)
5. Milestones and target dates
6. Project approach (describes the plans included, scheduled meetings,
scheduled status reports, issues management, change
management, communications plan, procurement plan, resource
management)
7. Approvals
8. Version history
Work Breakdown Structure
(WBS)
 Comprehensive review of the project scope
 Subdivides major project deliverables and project work into
smaller, more management components called work
packages
 The lowest level tasks should have durations between 2
and 22 days and effort should not take more than one
person more than one week to complete
Work Breakdown Structure
(WBS)
Input:
 Project scope statement
 Organizational policies, guidelines, procedures, plans
and or standards for conducting work
 Activity Lists (outlines all the scheduled activities to be
performed for the project within the scope of work
description of each activity and identification code or
number)
 Activity Attributes (characteristics of the activities)
 Milestone Lists (major accomplishments that signal
completion of a major deliverable)
 Requirements documentation that describe the
connection between individual requirements and the
business need for the project
Work Breakdown Structure
(WBS)
Output:
 WBS in deliverables
 WBS dictionary that includes details for work
attached to each component, milestones,
person responsible, etc.
WBS Steps
Define Project Deliverables
1. Define scheduled activities to complete
project
2. Define tasks for scheduled activities
3. Sequence activities and tasks
4. Identify related dependencies
5. Estimate resources needed/available
6. Estimate duration resources will be required
7. Define milestones and expected target dates
8. Document details for the WBS dictionary
WBS Sequencing Methods
Precedence Diagramming Method
 Finish-to-start (FS): predecessor activity must
finish before successor activity can start
 Start-to-finish (SF): predecessor activity must
start before the successor activity can finish
 Finish-to-finish (FF): predecessor activity must
finish before the successor activity finishes
 Start-to-finish (SS): predecessor activity must
start before the successor activity can start
WBS Sequencing
Methods
Dependency Determination
 Mandatory dependencies: inherent to the nature
of the work being done
 Discretionary dependencies: established based
on best practices within a particular industry or
aspect of the project where an unusual sequence
is desired
Appling Leads and Lags
 Lags delay successor activities and require time
to be added to start or finish date. Leads speed up
successor activity and require time to be taken off
either start or finish date of scheduled activity.
Cost and Budget
Cost of the resources needed to complete project
activities
Input:
 Scope statement
 Work breakdown structure
 Defined activities
 Sequenced activities
 Resource estimates
 Schedule
 Risks
Output:
 Cost baseline
Schedule Management
 Analyzing activity sequences, duration, resource
requirements and schedule constraints to create
the project schedule
 Approved schedule becomes the baseline for
the remainder of the project
 Project progress is monitored and tracked
against the baseline, which determines if the
project is on track
Input:
 Project scope statement
 Activity list
 Activity attributes (characteristics of activity, assumptions,
constraints)
 Diagram of project activities and dependencies
 Activity resource requirements
 Resource calendars
 Activity duration estimates
Output:
 Project schedule
 Schedule data
 Schedule baseline
 Project document updates
Schedule Management
Schedule Management
Scheduling Methods
 Schedule Network Analysis
Calculate early and late start dates, and early and late
finish dates for project activities.
 Critical-Path Method
Identifies tasks that must be completed on time for the
project to be completed by the end date. This data
keeps project on track.
 Schedule Compression
Using mathematical calculations to shorten the
schedule without changing the scope. Allows related
activities to be accomplished sooner than estimated.
 What-if Scenario Analysis
Series of what if questions to present activity
assumptions to determine project duration.
Schedule Management
Scheduling Methods
 Resource Leveling
Under-allocated resources can be assigned to
multiple tasks.
 Critical-Chain Method
Schedule high risk tasks early in project so
problems are identified and addressed as
soon as possible.
 Applying Leads and Lags
Start and finish dates are adjusted.
 Automated Scheduling Tools
Speeds up scheduling process based on data
input.
Schedule Management Plan
Format
Use this format to develop a Schedule Management Plan.
1. Task
2. Responsible
3. Estimated duration to complete
4. Start date
5. Finish date
6. Delays
7. Reason for delay
8. Action steps
Issues Management
 A log to document the issue, the owner,
resolution and status
Use this format to develop an Issues Management Log.
1. How issues are tracked
2. How issues are assigned
3. How issues are prioritized
4. How issues are resolved
5. How issues are communicated
Change Management
Deviations from the project management plan
Use this format to develop a Change Management Process Log.
1. How a change request will be managed
2. How a change request will be reviewed
3. How a change request will be tracked
4. How a change request will be resolved
4. What are possible alternatives and cost
5. Sign off
Quality Management
 Identifies the quality standards adopted for the
project
 Describes how the quality will be implemented
and managed
Input:
 Customer definition of quality
 Overview of schedule, cost, scope
 Quality assurance activities (testing, audits,
reviews)
 Measurements (within scope, budget, schedule)
Output:
 Quality Management Plan
Quality Management Plan
Format
Use this format to develop a Quality Management Plan.
1. Organization’s quality policy
2. How the customer defines quality
3. Deliverables - acceptable criteria and standards
4. Steps to ensure that quality is part of the product
4. Measurements
5. Scheduled audits
6. Sign off
Human Resource
Management
 Process for organizing and managing the team
 Size of team influenced by duration of the project
Input:
 Factors outside the project that influence project
success
 Organizational policies, guidelines, procedures,
plans and/or standards for conducting work
 Activity resource requirements
Output:
 Human Resource Plan
Human Resource
Management Plan Format
Use this format to develop a Human Resources Management Plan.
1. Roles
2. Responsibilities
3. Reporting relationships
Procurement
Management
 Process of documenting project purchasing decisions, specifying the
approach and identifying potential sellers.
 Identifies project needs that must be met by purchasing products, services
or results outside the organization
Input:
 Factors outside of the project that impact success
 Organizational policies, guidelines, plans and/or standards for conducting
work
 Scope baseline
 Requirements documentation
 Teaming agreements
 Risk information
 Activity-resource requirements
 Project schedule
 Activity cost estimates
 Cost baseline
Output:
 Procurement Management plan
Procurement Management Plan
Format
Use this format to develop a Procurement Management Plan.
1. Procurement statement (products or services being considered)
2. Estimated cost
3. Vendor selection (RFI/RFP/etc.)
4. Procurement definition
(what items will be procured and under what conditions)
5. Selection process criteria
6. Procurement team with contact information and defined roles
7. Contract type and actions required to initiate
8. Standards for each contract
9. Vendor management (steps to ensure everything is received)
9.. Sign off
Risk Management Plan
 Processes necessary to increase the probability and
impact of positive events and decrease probability and
impact of negative events
Input:
 Factors outside of the project that influence success
 Organizational policies, guidelines, procedures, plans
and/or standards for conducting work
 Scope statement
 Cost Management plan
 Schedule Management plan
 Communications Management plan
Output:
 Risk Management plan
Risk Management Plan
Format
Use this format to develop a Risk Management Plan.
1. Risk identification (based on discussions with key stakeholders)
2. Risk categorization
3. Risk probability and impact assessment
4. Risk prioritization
5. Risk response planning
6. Risk management strategy
7. Risk monitoring (build reviews into project schedule)
8. Risk control
9. Assumptions with significant impact on project risk
10. Roles and responsibilities unique to the risk function
Risk Management Plan
Format
Risk Management Plan - Continued
11. Risk management milestones
12. Risk rating score technique
13. Risk thresholds (high, medium, low – based on impact and
probability)
14. Risk communication
15. Risk tracking process
16. Sign off
Communication Plan
 Processes required to ensure timely and appropriate
collection, retrieval and dissemination of project
information
 Ensures that stakeholder needs are met
Input:
 Factors outside the project with significant influence
 Organizational policies, guidelines, procedures, plans
and standards for conducting work
 Project Charter
 Procurement documents
Output:
 Communication Plan
Communication Plan Format
Use this format to develop a Communication Plan.
1. Purpose
2. Need
3. Communication Principles
(ensure consistency and tone in messages and communication
efforts)
4. Communication objectives
5. Target audience
6. Key messages (who, what, when, where, why, how)
7. Change implications
(impact of the organizational changes as a result of the project)
8. Challenges and opportunities
(Factors that help or hinder such as past situations, rumors, trust,
etc.)
9. Sign off
ADDIE: Develop and Implement
Project Management: Execute
 Design document is moved to
development
 Communication is key to the success of
the project
Activities:
1. Preview instructional product
2. Validate instructional product
3. Deliver instructional product
Communication
Barriers
 Perceptions
(How individuals make sense of information)
 Beliefs
(True/false or probable/improbable)
 Attitudes
(Positive/negative responses)
 Values
(Good/bad or preferred/rejected)
 Noise
(Internal/external disruption to the communication
process)
Communication Elements
 Create a positive environment
 Know your audience
 Project credibility
 Listen
 Awareness of verbal and nonverbal
 Response to feedback
Communication Resources
The communication methods chosen should be driven by the needs of
the project.
 Email
 Text Message
 Video conferencing and chat services, like Skype
 Blogs and wikis (WordPress)
 Calendar sharing (Google Docs)
 Postal and shipping services
 Desktop software tools
 Microsoft Office or Open Office Suite
 Visual design and mockup software
 Project management software (Microsoft Project or OpenProject)
 Online project management software (Wrike, TeamBox, ManyMoons)
Validating Product
Content
 Was learning content relevant to the tasks to
be performed?
Process
 Did the presentation method help you learn
the content?
Materials
 Were the manuals, job aids, etc., adequate,
useful and applicable?
ADDIE: Evaluate
Project Management: Close
 Ensure that your customer is content with the
project deliverables
 Obtain sign off by customer that project is
complete
 Hold a “lessons learned” meeting with project
team and appropriate stakeholders
 Celebrate success
Final Project Report Format
Use this format to develop a Final Project Report.
1. Compare project outputs to project objectives
1. Identify what went right or wrong
2. Document weaknesses and strengths
3. Include original project plan
4. Include meeting minutes
5. Include project journals
6. Obtain customer feedback
7. All project documents for archives
8. Accounting documentation
9. Sign off
References
Cox, D. (2009). Project management for instructional. designers: a
practical guide. Bloomington, Indiana: iUniverse
Wiley, D. Project management for instructional designers. Brigham
Young University: Creative Commons license. Retrieved from
http://pm4id.org/(2013).
A guide to the project management body of knowledge. (4th ed.).
project management institute.
Swaim, T. (2013). Project management fundamentals. Ed To Go,
Retrieved from
http://www.ed2go.com/CourseDetails.aspx?tab=detail&course=pmf
Swaim, T. (2013). Pmp certification prep 1. Ed To Go, Retrieved
from
http://www.ed2go.com/CourseDetails.aspx?tab=detail&course=ppf

Más contenido relacionado

La actualidad más candente

Project management fundamentals
Project management fundamentalsProject management fundamentals
Project management fundamentalsshantdey
 
Program Vs Project Clp 2011 10
Program Vs Project Clp 2011 10Program Vs Project Clp 2011 10
Program Vs Project Clp 2011 10gculpan
 
Instructor Slides - PMP/CAPM PMBOK 6th Edition
Instructor Slides - PMP/CAPM PMBOK 6th EditionInstructor Slides - PMP/CAPM PMBOK 6th Edition
Instructor Slides - PMP/CAPM PMBOK 6th EditionMnbianchi
 
PMP Exam Prep_sample slides
PMP Exam Prep_sample slidesPMP Exam Prep_sample slides
PMP Exam Prep_sample slidesWilber Tuttleman
 
Project Management Chap. 1 Introduction
Project Management   Chap. 1 IntroductionProject Management   Chap. 1 Introduction
Project Management Chap. 1 IntroductionAperto Libro Academy
 
Program management - Fundamentals
Program management   - FundamentalsProgram management   - Fundamentals
Program management - FundamentalsJulen Mohanty
 
Project management pmi_approach_pmp
Project management pmi_approach_pmpProject management pmi_approach_pmp
Project management pmi_approach_pmpSayed Ahmed
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management FundamentalsOxfordCambridge
 
Portfolio, Project and Programme Management
Portfolio, Project and Programme ManagementPortfolio, Project and Programme Management
Portfolio, Project and Programme ManagementBruce Levitan
 
Project management fundamentals
Project management fundamentals Project management fundamentals
Project management fundamentals Rajasekar M
 

La actualidad más candente (20)

Program Management
Program ManagementProgram Management
Program Management
 
Program Management
Program ManagementProgram Management
Program Management
 
Pmi rmp-2020 - v6
Pmi rmp-2020 - v6Pmi rmp-2020 - v6
Pmi rmp-2020 - v6
 
Project management fundamentals
Project management fundamentalsProject management fundamentals
Project management fundamentals
 
Project Relationship Management (PRM)
Project Relationship Management (PRM)Project Relationship Management (PRM)
Project Relationship Management (PRM)
 
Overview of Program Management
Overview of Program ManagementOverview of Program Management
Overview of Program Management
 
Program Management Deployment Concept Consulting
Program Management Deployment Concept ConsultingProgram Management Deployment Concept Consulting
Program Management Deployment Concept Consulting
 
Program Vs Project Clp 2011 10
Program Vs Project Clp 2011 10Program Vs Project Clp 2011 10
Program Vs Project Clp 2011 10
 
Instructor Slides - PMP/CAPM PMBOK 6th Edition
Instructor Slides - PMP/CAPM PMBOK 6th EditionInstructor Slides - PMP/CAPM PMBOK 6th Edition
Instructor Slides - PMP/CAPM PMBOK 6th Edition
 
PMP Exam Prep_sample slides
PMP Exam Prep_sample slidesPMP Exam Prep_sample slides
PMP Exam Prep_sample slides
 
Project Management Chap. 1 Introduction
Project Management   Chap. 1 IntroductionProject Management   Chap. 1 Introduction
Project Management Chap. 1 Introduction
 
Program management - Fundamentals
Program management   - FundamentalsProgram management   - Fundamentals
Program management - Fundamentals
 
041006-Program Management PMI NB - PMI Logo
041006-Program Management PMI NB - PMI Logo041006-Program Management PMI NB - PMI Logo
041006-Program Management PMI NB - PMI Logo
 
Project management fundamentals
Project management fundamentalsProject management fundamentals
Project management fundamentals
 
Project management pmi_approach_pmp
Project management pmi_approach_pmpProject management pmi_approach_pmp
Project management pmi_approach_pmp
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management Fundamentals
 
Portfolio, Project and Programme Management
Portfolio, Project and Programme ManagementPortfolio, Project and Programme Management
Portfolio, Project and Programme Management
 
PMP_Project Human Resources Management
PMP_Project Human Resources ManagementPMP_Project Human Resources Management
PMP_Project Human Resources Management
 
Atppmp1ov1
Atppmp1ov1Atppmp1ov1
Atppmp1ov1
 
Project management fundamentals
Project management fundamentals Project management fundamentals
Project management fundamentals
 

Destacado

Project management for instructional designers
Project management for instructional designersProject management for instructional designers
Project management for instructional designersKimberly Kaye
 
PMP Training - Project Time Management Part 2
PMP Training - Project Time Management Part 2PMP Training - Project Time Management Part 2
PMP Training - Project Time Management Part 2Skillogic Solutions
 
PMP Training - 08 project quality management
PMP Training - 08 project quality managementPMP Training - 08 project quality management
PMP Training - 08 project quality managementejlp12
 
PMP Training - 06 project time management2
PMP Training - 06 project time management2PMP Training - 06 project time management2
PMP Training - 06 project time management2ejlp12
 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Managementrielaantonio
 

Destacado (6)

Project management for instructional designers
Project management for instructional designersProject management for instructional designers
Project management for instructional designers
 
PMP Training - Project Time Management Part 2
PMP Training - Project Time Management Part 2PMP Training - Project Time Management Part 2
PMP Training - Project Time Management Part 2
 
PMP PMBOK 5TH Ch 6 time management
PMP PMBOK 5TH Ch 6 time managementPMP PMBOK 5TH Ch 6 time management
PMP PMBOK 5TH Ch 6 time management
 
PMP Training - 08 project quality management
PMP Training - 08 project quality managementPMP Training - 08 project quality management
PMP Training - 08 project quality management
 
PMP Training - 06 project time management2
PMP Training - 06 project time management2PMP Training - 06 project time management2
PMP Training - 06 project time management2
 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Management
 

Similar a Project management for Instructional Designers

Project management for instructional designers
Project management for instructional designersProject management for instructional designers
Project management for instructional designersKimberly Klotz
 
Pmi presentation structuring project v2
Pmi presentation   structuring project v2Pmi presentation   structuring project v2
Pmi presentation structuring project v2Deepak Mehtani
 
Projects Management
Projects ManagementProjects Management
Projects ManagementNirmal Shah
 
Project Management for Technical Communication Professionals
Project Management for Technical Communication ProfessionalsProject Management for Technical Communication Professionals
Project Management for Technical Communication Professionalsstcindiana
 
ICT4GOV PROJECT MANAGEMENT
ICT4GOV PROJECT MANAGEMENTICT4GOV PROJECT MANAGEMENT
ICT4GOV PROJECT MANAGEMENTJohn Macasio
 
Intro to PM.pdf
Intro to PM.pdfIntro to PM.pdf
Intro to PM.pdfDaveNjoga1
 
Introduction To Project Management
Introduction To Project ManagementIntroduction To Project Management
Introduction To Project ManagementUW Madison
 
Is5540 course review
Is5540 course reviewIs5540 course review
Is5540 course reviewAsa Chan
 
Chap 1 Modern Project Management
Chap 1 Modern Project ManagementChap 1 Modern Project Management
Chap 1 Modern Project Managementproject management
 
Chapter 3 Lecture Slides
Chapter 3 Lecture SlidesChapter 3 Lecture Slides
Chapter 3 Lecture Slidesdotesch
 
2 project management-level 1
2 project management-level 12 project management-level 1
2 project management-level 1Juwad AlOmari
 
The Art Of Project Management
The Art Of Project ManagementThe Art Of Project Management
The Art Of Project Managementhatemk
 
PMBOK 5th Planning Process Group Part One
PMBOK 5th Planning Process Group Part OnePMBOK 5th Planning Process Group Part One
PMBOK 5th Planning Process Group Part OneHossam Maghrabi
 
PMO 3.0 - Next Gen Lean Model - Doug Floyd
PMO 3.0 - Next Gen Lean Model - Doug FloydPMO 3.0 - Next Gen Lean Model - Doug Floyd
PMO 3.0 - Next Gen Lean Model - Doug Floyddvfloyd
 

Similar a Project management for Instructional Designers (20)

Project management for instructional designers
Project management for instructional designersProject management for instructional designers
Project management for instructional designers
 
Pmi presentation structuring project v2
Pmi presentation   structuring project v2Pmi presentation   structuring project v2
Pmi presentation structuring project v2
 
project and risk management level 1 2 3 and ms project
project and risk management level 1 2 3 and ms projectproject and risk management level 1 2 3 and ms project
project and risk management level 1 2 3 and ms project
 
Projects Management
Projects ManagementProjects Management
Projects Management
 
Project Management for Technical Communication Professionals
Project Management for Technical Communication ProfessionalsProject Management for Technical Communication Professionals
Project Management for Technical Communication Professionals
 
pmppgoav14.ppt
pmppgoav14.pptpmppgoav14.ppt
pmppgoav14.ppt
 
Project management
Project managementProject management
Project management
 
ICT4GOV PROJECT MANAGEMENT
ICT4GOV PROJECT MANAGEMENTICT4GOV PROJECT MANAGEMENT
ICT4GOV PROJECT MANAGEMENT
 
Project Management U 1.pptx
Project Management U 1.pptxProject Management U 1.pptx
Project Management U 1.pptx
 
Intro to PM.pdf
Intro to PM.pdfIntro to PM.pdf
Intro to PM.pdf
 
Introduction To Project Management
Introduction To Project ManagementIntroduction To Project Management
Introduction To Project Management
 
Is5540 course review
Is5540 course reviewIs5540 course review
Is5540 course review
 
Chap 1 Modern Project Management
Chap 1 Modern Project ManagementChap 1 Modern Project Management
Chap 1 Modern Project Management
 
6396901
63969016396901
6396901
 
project management concepts
project management conceptsproject management concepts
project management concepts
 
Chapter 3 Lecture Slides
Chapter 3 Lecture SlidesChapter 3 Lecture Slides
Chapter 3 Lecture Slides
 
2 project management-level 1
2 project management-level 12 project management-level 1
2 project management-level 1
 
The Art Of Project Management
The Art Of Project ManagementThe Art Of Project Management
The Art Of Project Management
 
PMBOK 5th Planning Process Group Part One
PMBOK 5th Planning Process Group Part OnePMBOK 5th Planning Process Group Part One
PMBOK 5th Planning Process Group Part One
 
PMO 3.0 - Next Gen Lean Model - Doug Floyd
PMO 3.0 - Next Gen Lean Model - Doug FloydPMO 3.0 - Next Gen Lean Model - Doug Floyd
PMO 3.0 - Next Gen Lean Model - Doug Floyd
 

Último

ACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfSpandanaRallapalli
 
Gas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxGas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxDr.Ibrahim Hassaan
 
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSJoshuaGantuangco2
 
Science 7 Quarter 4 Module 2: Natural Resources.pptx
Science 7 Quarter 4 Module 2: Natural Resources.pptxScience 7 Quarter 4 Module 2: Natural Resources.pptx
Science 7 Quarter 4 Module 2: Natural Resources.pptxMaryGraceBautista27
 
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxBarangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxCarlos105
 
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)lakshayb543
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...Nguyen Thanh Tu Collection
 
ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4MiaBumagat1
 
How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17Celine George
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfMr Bounab Samir
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designMIPLM
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for BeginnersSabitha Banu
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfAMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfphamnguyenenglishnb
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPCeline George
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 

Último (20)

ACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdf
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
Gas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxGas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptx
 
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
 
Science 7 Quarter 4 Module 2: Natural Resources.pptx
Science 7 Quarter 4 Module 2: Natural Resources.pptxScience 7 Quarter 4 Module 2: Natural Resources.pptx
Science 7 Quarter 4 Module 2: Natural Resources.pptx
 
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxBarangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
 
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
 
ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4
 
How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-design
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for Beginners
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfAMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
 
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptxFINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
 
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptxYOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERP
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 

Project management for Instructional Designers

  • 1. PROJECT MANAGEMENT FOR INSTRUCTIONAL DESIGNERS Presented by: Kimberly McKee and Kimberly Klotz University of Central Arkansas Instructional Technologies Graduate Program
  • 2. Kimberly Klotz (kklotz@uca.edu)  Bachelor of Arts ‘06 (Art, Journalism)  Master of Science ‘13 (Instructional Technology/Distance Education)  7 years of design/marketing experience in higher education  48 hours of Project Management professional development  Employed in the Division of Outreach and Community Engagement, University of Central Arkansas
  • 3. Kimberly McKee (kmckee@uca.edu)  Bachelor of Arts (English, Writing, Journalism)  Master of Science ‘13 (Instructional Technology/Distance Education Emphasis)  17 years of technical writing experience for a technology company  Grant writing contractor  48 hours of Project Management professional development  Employed in the Division of Outreach and Community Engagement, University of Central Arkansas
  • 4. Project Management Institute (PMI) http://www.pmi.org PMI is one of the world’s largest not-for-profit membership associations for the Project Management profession, with more than 650,000 members and credential holders in more than 185 countries. PMI Offers Two Certification Levels: Project Management Professional (PMP) Certified Associate in Project Management (CAPM) – Entry Level Certification
  • 5. Project Management Certification Requirements 1. Bachelor’s degree 2. 3 years of Project Management experience 3. 4500 hours of leading projects 4. 35 hours of Project Management education 5. Pass the test OR 1. High school degree 2. 5 years of Project Management experience 3. 7500 hours of leading projects 4. 35 hours of Project Management education 5. Pass the test 1. High school diploma or equivalent 2. 1500 hours of Project Management experience 3. Pass the test OR 1. High school diploma or equivalent 2. 23 hours of Project Management instruction 3. Pass the test Project Management Professional (PMP) Certified Associate in Project Management (CAPM)
  • 6. What is Project Management?  The application of knowledge, skills, tools and techniques to project activities to meet the project requirements. (PMI)  To determine project success, we must also include the client. (Meredith & Mantel) Applying Project Management principles increases the success of a project.
  • 7.
  • 8. What is a project?  Developed to achieve the purposes and goals of an organization, institution or business  Purpose and goals are defined by stakeholders  Initiatives to increase organizational effectiveness or efficiency (such as incorporating new technologies and updating/improving processes)  Major activities outside the normal work of an organization’s department or functional units or major activities that cross functional boundaries
  • 9. Project Characteristics  Temporary – defined beginning and end  Create a product, service or result that is unique
  • 10. Who can manage a project?  Outside contractors  Internal group in a Project Management Office (PMO)  Internal team  Instructional Designer
  • 11. Core Competencies of the Project Manager
  • 12. Key Skills of the Project Manager  Develops a plan to meet project goals  Monitors plan to ensure project stays on track  Energizes the team around the success of the project  Maintains organization  Establishes priorities  Communicates clear goals and expectations A Project Manager is goal directed and milestone oriented!
  • 13. Project Management and ADDIE Instructional Design Model
  • 14.
  • 15. Project Management: Initiate ADDIE: Analyze  Recognizes a project or the next phase of an existing project  Recognizes that resources should be committed to the project Activities: 1. Conduct Needs Analysis 2. Develop Project Charter 3. Identify and Document Stakeholders
  • 16. Step 1: Needs Analysis  Feasibility study to determine performance gaps at the individual and business levels  Presents alternatives and possible solutions  Prepared by the designer, team, outside agency  Approved by leadership
  • 17. Conducting a Needs Analysis  Answers Who, What, When, Where, Why, How questions  Locates the root cause of the performance gap  Compares what is expected to what is actually achieved  Understand the learner (job experiences, motivation, aptitude,  Conduct a survey  Walk thru current processes  Talk to customers, if possible and needed  Review previous training efforts  Review sales records and customer feedback forums  Conduct interviews  Facilitate focus groups  Facilitate workshop sessions  Conduct group brainstorming  Observations  Prototype – working model to obtain feedback before proceeding with project WHY? HOW?
  • 18. Needs Analysis Format Use this format to develop a Needs Analysis Report. 1. Training requested 2. Job, tasks, duties to be performed 3. Expected performance 4. Data collection method 5. Actual performance 6. Cause of performance gap 7. Cost estimate of training 8. Benefit of training 9. Training proposal 10. Management support recommendations (feedback, measurement) 11. Narrative
  • 19. Step 2: Project Charter  Provides structure to the Project Plan  Justifies the project  Documents the need being addressed  Includes a description of the project  Documents proposed result of the project  Includes input from stakeholders  Leadership responsible for obtaining sign-off by the project sponsor (person financing the project), senior management, stakeholders
  • 20. Project Charter Format Use this format to develop a Project Charter. 1. Purpose 2. Description of Work 3. Objectives 4. In-scope deliverables (what the project includes) Out-of-scope deliverables (what the project does not include) 5. Roles and responsibilities 6. Milestones 7. Major known risks 8. Assumptions and Constraints 9. Constraints 10. External dependencies 11. Summary of budget 12. Vendors
  • 21. Stakeholders  Includes practitioners or groups of people with specialized knowledge or skills in a particular area  Interests should be considered throughout the project
  • 22. Stakeholder Log Format Use this format to develop a Stakeholder Log. 1. Name 2. Role on Project 3. Department 4. Interest 5. Knowledge level 6. Expectation 7. Level of influence on the project
  • 23.
  • 24. Project Management: Plan ADDIE: Design  40% of time allocated to complete the project should be spent in planning  Size and complexity of project determines the processes to be included Activities: 1. Instructional Design Document 2. Project Management Plan 3. Components of Project Management Plan 4. Project Scope Statement 5. Work Breakdown Structure (WBS)
  • 25. Step 3: Instructional Design Document  Outlines the framework of the instructional plan  Provides high-level overview of the product content and how it will be treated  Enables stakeholders to validate the program’s objectives, architecture, content and concepts before development  Identifies learning strategies (learning styles and adult learning principles)
  • 26. Instructional Design Document Format Use this format to develop an Instructional Design Document. Learning Objectives 1. Describe what the learner is expected to achieve when performing the task 2. Task statement 3. Conditions under which the task is performed Key Points – Content and Concept 1. Product information, concepts and criteria to be covered in each module Process and Activity 1. Summary of the types of learning activities that will be completed in the respective modules 2. Describe how presentation and application methods are distributed throughout the learning program
  • 27. Step 4: Project Management Plan  Overall approach used to plan and manage a project  Consists of subsidiary plans that detail how specific areas of the project will be managed  Documents cost, time, quality, risk, and resources to complete the project Input:  Project charter  Instructional design document  Process outputs that will be used for the project  Environmental factors outside the organization  Specific information about what may influence success, organizational policies, guidelines, procedures, plans, and/or standards for conducting work  Stakeholder input, if skills and knowledge warrant Output:  Project Management Plan
  • 28. Project Management Plan Components  Project Scope Statement  Cost and Budget  Work Breakdown Structure (WBS)  Schedule Management  Issues Management  Change Management  Quality Management  Human Resource Management  Procurement Management  Risk Management  Communications Plan
  • 29. Project Scope Statement  Documents initial planning efforts for the project  Used to reach agreement among managers, stakeholders and teams before resources are allocated
  • 30. Project Scope Statement Format Use this format to develop a Project Scope Statement. 1. Purpose and justification 2. Product description 3. Objectives 4. Project description (Includes: deliverables breakdown. Do not include: completion criteria, external dependencies, assumptions, constraints.) 5. Milestones and target dates 6. Project approach (describes the plans included, scheduled meetings, scheduled status reports, issues management, change management, communications plan, procurement plan, resource management) 7. Approvals 8. Version history
  • 31. Work Breakdown Structure (WBS)  Comprehensive review of the project scope  Subdivides major project deliverables and project work into smaller, more management components called work packages  The lowest level tasks should have durations between 2 and 22 days and effort should not take more than one person more than one week to complete
  • 32. Work Breakdown Structure (WBS) Input:  Project scope statement  Organizational policies, guidelines, procedures, plans and or standards for conducting work  Activity Lists (outlines all the scheduled activities to be performed for the project within the scope of work description of each activity and identification code or number)  Activity Attributes (characteristics of the activities)  Milestone Lists (major accomplishments that signal completion of a major deliverable)  Requirements documentation that describe the connection between individual requirements and the business need for the project
  • 33. Work Breakdown Structure (WBS) Output:  WBS in deliverables  WBS dictionary that includes details for work attached to each component, milestones, person responsible, etc.
  • 34. WBS Steps Define Project Deliverables 1. Define scheduled activities to complete project 2. Define tasks for scheduled activities 3. Sequence activities and tasks 4. Identify related dependencies 5. Estimate resources needed/available 6. Estimate duration resources will be required 7. Define milestones and expected target dates 8. Document details for the WBS dictionary
  • 35. WBS Sequencing Methods Precedence Diagramming Method  Finish-to-start (FS): predecessor activity must finish before successor activity can start  Start-to-finish (SF): predecessor activity must start before the successor activity can finish  Finish-to-finish (FF): predecessor activity must finish before the successor activity finishes  Start-to-finish (SS): predecessor activity must start before the successor activity can start
  • 36. WBS Sequencing Methods Dependency Determination  Mandatory dependencies: inherent to the nature of the work being done  Discretionary dependencies: established based on best practices within a particular industry or aspect of the project where an unusual sequence is desired Appling Leads and Lags  Lags delay successor activities and require time to be added to start or finish date. Leads speed up successor activity and require time to be taken off either start or finish date of scheduled activity.
  • 37. Cost and Budget Cost of the resources needed to complete project activities Input:  Scope statement  Work breakdown structure  Defined activities  Sequenced activities  Resource estimates  Schedule  Risks Output:  Cost baseline
  • 38. Schedule Management  Analyzing activity sequences, duration, resource requirements and schedule constraints to create the project schedule  Approved schedule becomes the baseline for the remainder of the project  Project progress is monitored and tracked against the baseline, which determines if the project is on track
  • 39. Input:  Project scope statement  Activity list  Activity attributes (characteristics of activity, assumptions, constraints)  Diagram of project activities and dependencies  Activity resource requirements  Resource calendars  Activity duration estimates Output:  Project schedule  Schedule data  Schedule baseline  Project document updates Schedule Management
  • 40. Schedule Management Scheduling Methods  Schedule Network Analysis Calculate early and late start dates, and early and late finish dates for project activities.  Critical-Path Method Identifies tasks that must be completed on time for the project to be completed by the end date. This data keeps project on track.  Schedule Compression Using mathematical calculations to shorten the schedule without changing the scope. Allows related activities to be accomplished sooner than estimated.  What-if Scenario Analysis Series of what if questions to present activity assumptions to determine project duration.
  • 41. Schedule Management Scheduling Methods  Resource Leveling Under-allocated resources can be assigned to multiple tasks.  Critical-Chain Method Schedule high risk tasks early in project so problems are identified and addressed as soon as possible.  Applying Leads and Lags Start and finish dates are adjusted.  Automated Scheduling Tools Speeds up scheduling process based on data input.
  • 42. Schedule Management Plan Format Use this format to develop a Schedule Management Plan. 1. Task 2. Responsible 3. Estimated duration to complete 4. Start date 5. Finish date 6. Delays 7. Reason for delay 8. Action steps
  • 43. Issues Management  A log to document the issue, the owner, resolution and status Use this format to develop an Issues Management Log. 1. How issues are tracked 2. How issues are assigned 3. How issues are prioritized 4. How issues are resolved 5. How issues are communicated
  • 44. Change Management Deviations from the project management plan Use this format to develop a Change Management Process Log. 1. How a change request will be managed 2. How a change request will be reviewed 3. How a change request will be tracked 4. How a change request will be resolved 4. What are possible alternatives and cost 5. Sign off
  • 45. Quality Management  Identifies the quality standards adopted for the project  Describes how the quality will be implemented and managed Input:  Customer definition of quality  Overview of schedule, cost, scope  Quality assurance activities (testing, audits, reviews)  Measurements (within scope, budget, schedule) Output:  Quality Management Plan
  • 46. Quality Management Plan Format Use this format to develop a Quality Management Plan. 1. Organization’s quality policy 2. How the customer defines quality 3. Deliverables - acceptable criteria and standards 4. Steps to ensure that quality is part of the product 4. Measurements 5. Scheduled audits 6. Sign off
  • 47. Human Resource Management  Process for organizing and managing the team  Size of team influenced by duration of the project Input:  Factors outside the project that influence project success  Organizational policies, guidelines, procedures, plans and/or standards for conducting work  Activity resource requirements Output:  Human Resource Plan
  • 48. Human Resource Management Plan Format Use this format to develop a Human Resources Management Plan. 1. Roles 2. Responsibilities 3. Reporting relationships
  • 49. Procurement Management  Process of documenting project purchasing decisions, specifying the approach and identifying potential sellers.  Identifies project needs that must be met by purchasing products, services or results outside the organization Input:  Factors outside of the project that impact success  Organizational policies, guidelines, plans and/or standards for conducting work  Scope baseline  Requirements documentation  Teaming agreements  Risk information  Activity-resource requirements  Project schedule  Activity cost estimates  Cost baseline Output:  Procurement Management plan
  • 50. Procurement Management Plan Format Use this format to develop a Procurement Management Plan. 1. Procurement statement (products or services being considered) 2. Estimated cost 3. Vendor selection (RFI/RFP/etc.) 4. Procurement definition (what items will be procured and under what conditions) 5. Selection process criteria 6. Procurement team with contact information and defined roles 7. Contract type and actions required to initiate 8. Standards for each contract 9. Vendor management (steps to ensure everything is received) 9.. Sign off
  • 51. Risk Management Plan  Processes necessary to increase the probability and impact of positive events and decrease probability and impact of negative events Input:  Factors outside of the project that influence success  Organizational policies, guidelines, procedures, plans and/or standards for conducting work  Scope statement  Cost Management plan  Schedule Management plan  Communications Management plan Output:  Risk Management plan
  • 52. Risk Management Plan Format Use this format to develop a Risk Management Plan. 1. Risk identification (based on discussions with key stakeholders) 2. Risk categorization 3. Risk probability and impact assessment 4. Risk prioritization 5. Risk response planning 6. Risk management strategy 7. Risk monitoring (build reviews into project schedule) 8. Risk control 9. Assumptions with significant impact on project risk 10. Roles and responsibilities unique to the risk function
  • 53. Risk Management Plan Format Risk Management Plan - Continued 11. Risk management milestones 12. Risk rating score technique 13. Risk thresholds (high, medium, low – based on impact and probability) 14. Risk communication 15. Risk tracking process 16. Sign off
  • 54. Communication Plan  Processes required to ensure timely and appropriate collection, retrieval and dissemination of project information  Ensures that stakeholder needs are met Input:  Factors outside the project with significant influence  Organizational policies, guidelines, procedures, plans and standards for conducting work  Project Charter  Procurement documents Output:  Communication Plan
  • 55. Communication Plan Format Use this format to develop a Communication Plan. 1. Purpose 2. Need 3. Communication Principles (ensure consistency and tone in messages and communication efforts) 4. Communication objectives 5. Target audience 6. Key messages (who, what, when, where, why, how) 7. Change implications (impact of the organizational changes as a result of the project) 8. Challenges and opportunities (Factors that help or hinder such as past situations, rumors, trust, etc.) 9. Sign off
  • 56.
  • 57. ADDIE: Develop and Implement Project Management: Execute  Design document is moved to development  Communication is key to the success of the project Activities: 1. Preview instructional product 2. Validate instructional product 3. Deliver instructional product
  • 58. Communication Barriers  Perceptions (How individuals make sense of information)  Beliefs (True/false or probable/improbable)  Attitudes (Positive/negative responses)  Values (Good/bad or preferred/rejected)  Noise (Internal/external disruption to the communication process)
  • 59. Communication Elements  Create a positive environment  Know your audience  Project credibility  Listen  Awareness of verbal and nonverbal  Response to feedback
  • 60. Communication Resources The communication methods chosen should be driven by the needs of the project.  Email  Text Message  Video conferencing and chat services, like Skype  Blogs and wikis (WordPress)  Calendar sharing (Google Docs)  Postal and shipping services  Desktop software tools  Microsoft Office or Open Office Suite  Visual design and mockup software  Project management software (Microsoft Project or OpenProject)  Online project management software (Wrike, TeamBox, ManyMoons)
  • 61. Validating Product Content  Was learning content relevant to the tasks to be performed? Process  Did the presentation method help you learn the content? Materials  Were the manuals, job aids, etc., adequate, useful and applicable?
  • 62.
  • 63. ADDIE: Evaluate Project Management: Close  Ensure that your customer is content with the project deliverables  Obtain sign off by customer that project is complete  Hold a “lessons learned” meeting with project team and appropriate stakeholders  Celebrate success
  • 64. Final Project Report Format Use this format to develop a Final Project Report. 1. Compare project outputs to project objectives 1. Identify what went right or wrong 2. Document weaknesses and strengths 3. Include original project plan 4. Include meeting minutes 5. Include project journals 6. Obtain customer feedback 7. All project documents for archives 8. Accounting documentation 9. Sign off
  • 65. References Cox, D. (2009). Project management for instructional. designers: a practical guide. Bloomington, Indiana: iUniverse Wiley, D. Project management for instructional designers. Brigham Young University: Creative Commons license. Retrieved from http://pm4id.org/(2013). A guide to the project management body of knowledge. (4th ed.). project management institute. Swaim, T. (2013). Project management fundamentals. Ed To Go, Retrieved from http://www.ed2go.com/CourseDetails.aspx?tab=detail&course=pmf Swaim, T. (2013). Pmp certification prep 1. Ed To Go, Retrieved from http://www.ed2go.com/CourseDetails.aspx?tab=detail&course=ppf