SlideShare una empresa de Scribd logo
1 de 4
Risks faced by Projects
•   Governance risk: The governance risk arises out of the board and management performance with reference to
    ethics, leadership, reputation of the organization etc.
•   Strategic risk: This risk arises out of an error in strategy adopted by organization. For example, a selection of
    technology that is not suitable to the organization or choosing a strategy that can change the course of business
    drastically.
•   Operational risk: This is a risk of having poor operational systems, poor implementation and process problems
    related to production and distribution.
•   Market risk: The risk arising out of competition, fluctuations in foreign exchange rates, raw material supplies,
    interest rates, credit and liquidity aspects, etc.
•   Legal risk: This risk is a result of legal and regulatory obligations like contract risks and litigation suits filed against
    organization.

Construction phase risks
Completion risk: Completion risk allocation is a vital part of the risk allocation of any project. This phase carries the
greatest risk for the financier. Construction carries the danger that the project will not be completed on time, on budget
or at all because of technical, labor, and other construction difficulties. Such delays or cost increases may delay loan
repayments and cause interest and debt to accumulate. They may also jeopardize contracts for the sale of the project’s
output and supply contacts for raw materials.
Completion risk is managed during the loan period by methods such as making pre-completion phase draw downs of
further funds conditional on certificates being issued by independent experts to confirm that the construction is
progressing as planned.
Operation phase risks
Resource/Reserve risk: This is the risk that for a mining project, rail project, power station or toll road there are
inadequate inputs that can be processed or serviced to produce an adequate return. For example, this is the risk that
there are insufficient reserves for a mine, passengers for a railway, fuel for a power station or vehicles for a toll road.
Operating risk: These are general risks that may affect the cash flow of the project by increasing the operating costs
or affecting the project’s capacity to continue to generate the quantity and quality of the planned output over the life of
the project. Operating risks include, for example, the level of experience and resources of the operator, inefficiencies in
operations or shortages in the supply of skilled labor.

Process of project risk management
Risk Identification: It is definitely a brainstorming process to uncover the risks associated with the project. Several
ideas are taken into account from risk perception of the team members of the project following the documentation
process that are evaluated properly to uncover the risks inherent to the project. The other alternative way is to paint a
picture of the project success. Thereafter, one should move backwards, duly considering the adverse developments that
may affect the path to achieve success. Once the risks are identified, these may be placed as a sticky note on the process
of project schedule, process map, etc.
Risk Analysis: In this step, the overall magnitude of the risk and its expected losses are estimated. In order to achieve
the best outcome, the risk event drivers are determined and the probable worst impact of the same assessed.
Identification of the risk event drivers can be termed as the foundation of the risk management process as it helps us to
mitigate the same.
Risk Prioritization: In this stage, the risks are compared on the basis of their probability of occurrences as well as
the expected amount of losses, if the worst thing is going to occur in future. The risks are listed on the basis of the
resultant product of the above two factors. This steps guides the project manager for the allocation of the resources to
manage the risks actively. Since the resources are limited, the project manager should choose the risks carefully, which
have the higher impact on the organization.
Risk Planning: Once the risks are short listed for their active management, the action plan is also framed
accordingly. The following kinds of actions may be adopted:
• Acceptance: It is adopted when the consequences are negligibly small
• Avoidance: It is the best way of dealing the risk by taking suitable precautionary measures that may rule out the
possibility of the occurrence of the event.
• Transfer: It is another good alternative where the consequences of losses are transferred to a third party like a
contractor or insurer at some nominal expenses.
• Self-financing: Here, on the basis of the past experience of the organization, a separate fund is built up which is
used to meet the consequences for the occurrence of the risk.
The actions described above are broadly categorized as the prevention plans and contingency plans. The first one is the
proactive one while the second one is reactive one and accordingly the resources should be kept ready to meet the risks.
Risk Monitoring: It is the final step of the process of project risk management but it is repeated regularly throughout
the execution of the process of the project. This step consists of the following processes:
• How the actions plans for the actively managed risks are progressing.
• Removal of the risks that have mitigated effectively or cannot be expected to occur.
• Addition to the actively managed risks that has occurred as the execution of the project is underway.
Therefore, monitoring of the risks is the repetition of the other risk management processes as the circumstances are
changing with the passage of time. Incorporating risk management into the projects requires a lot of time and effort,
even if it is scaled down. One should work in advance in order to avoid the occurrence of the consequences of the risks
that will result in predictable outcomes from the project.

Measuring Effectiveness of Risk management Measures
An action initiated for managing risks does not mean that the desired results will be achieved. In order to know
whether the risk management tools and techniques implemented to mitigate the risks have succeeded in achieving the
desired results, organizations need to measure the effectiveness of the risk management measures on a regular basis.
One method of measuring the effectiveness is, by comparing the monetary exposure of the project before and after risk
mitigation actions. Pre-mitigation exposure can be calculated by multiplying the monetary impact of the risk with the
probability of risk. The amount arrived at can be compared after risk mitigation process. The difference can be seen
clearly between the amounts, as the risk mitigation actions will reduce either the probability of risk or the monetary
exposure. This method can be utilized, only if the financial loss or exposure is quantified during initial risk analysis.
Another way to measure for all the risks and the cost of mitigation action. After calculating the values, a ratio of the
two parameters can be calculated to determine the cost effectiveness of the actions taken.
While the above two methods measure the risk mitigation pre and post-actions, another way to measure the
effectiveness of the actions is, by reviewing the actions along the progress of the project. While reviewing the project
activities, organizations need to include the review of project risk mitigation actions invariably. By doing so,
organizations can review along with the progress of the project, whether project manager and project teams are
performing their schedule risk management activities as planned. This also enables the management to decide whether
specific additional assistance needs to be provided to the teams to accomplish the objectives of risk management apart
from the scope to modify the actions in the light of new developments. With growing complexities in business
environment and emergence of new forms of risks, project risk management should be treated as a separate activity and
reviewed along the length of the project.

Risk Response planning
Risk response planning determines the action for enhancing the opportunities and reducing the threats in a project. The
common strategies to deal with threats are avoidance, transfer, mitigation and acceptance.(as said before)
•    Risk avoidance refers to those actions that can nullify the impact of risk events on a project. Project managers can
     achieve it either by changing the way of carrying activities or by changing the project objectives.
•    Risk transfer implies that the third party will shield the project from the impact of all or few risk events. The risk
     transfer approach is a middle path approach, which makes the best alternative less good and the worst alternative
     less bad.
•    Risk mitigation approach is possible when the potential impact of the risk is above a certain threshold.
•    Risk acceptance is about planning for the options that can be considered when the risk arises. Options may be in
     active or passive forms according to the severity of an event. For active acceptance, contingency plans are
     developed so that the impact of the risk can be reduced to an acceptable level.
Benefits of using risk response planning chart:
•    Decision can be taken proactively to counter a risk by assuming that it will happen in the future.
•    Events or risks with high threshold can be minimized.
•    Events with passive impact can be found out and ignored.
•    Few risks lie between the passive acceptance and avoidance situations. It is not worth for the company to go for a
     contingency plan. The identification of those risks to transfer is possible by using this chart.
•    The risks that are likely to occur many times can be accepted actively and their impact can be reduced.
•    Risk mitigation can be implemented wherever it is required

Risk management measures in practice
Conservative Estimates of Profitability
Preparation of projected profitability estimates, balance sheets and cash flow statements is done with reference to the
cost of the project, means of finance, underlying assumptions relating to capacity utilization, schedule of
implementation, selling price realization, raw material costs, other production costs, administrative and selling
overheads, depreciation rates, tax rates and tax benefits, etc. These assumptions need to be realistic. This provides a
cushion against the unforeseen events that could influence the projected profitability, negatively. Key assumptions,
where the principle of conservatism is applied, are as under:
(i) Capacity Utilization: Though a project, if successful, will run at its optimum capacity in the very first/second
year of its commissioning, as a shield against uncertain future, the following safeguards are taken in the projections a. In
the case of a new venture, capacity utilization is gradually increased over 3-4 years to reach and then stabilize at an
optimum level based on the actual capacity utilization being achieved in the related industry.
b. In the case of expansion by an existing unit, past levels achieved in capacity utilization provide the benchmark for
assuming the gradual capacity utilization increase in the new project.
(ii) Selling Prices: To begin with, the unit-selling price is taken based on the generally prevailing market price in the
case of a new venture and already realized price by an existing unit in the case of an expansion project. This price is
then discounted for factors, such as, variations in the prices in the past, the need to sell at a lower price due to likely
competition or to establish the product in the case of a new entrant, fluctuations in prices in case of products whose
prices fluctuate at short intervals, etc.
(iii) Raw Material Prices: Here again the beginning price is taken based on the generally prevailing market price in
the case of a new venture and the price at which the material is already being purchased by an existing unit in the case
of an expansion project. This price is then revised in the light of considerations, such as likely demand-supply scenario,
short interval fluctuations, past trend in the prices and cyclicality of the supplier industry.
The above risk management measures in respect of profitability projections result in lower projections. The project
should withstand, and justify its financing based on these lower projections.
Conservative Assumptions in Financial Evaluation Criteria
These are the assumptions for computing the IRR for evaluating the financial viability of the project and assessing the
associated risk:
(i) Project Life: The life of the project is generally taken to be 12 years or even less, depending upon the nature of the
industry, say, where the technical obsolescence is high, except of course for infrastructure ones. The life as estimated as
per the technical appraisal is disregarded unless, of course, it is shorter than the assumed norm.
(ii) Salvage Value: In the terminal year, that is, at the end of the assumed project life cash inflows are computed
assuming the following salvage values
a. In the case of fixed assets other than land ó5% of the original cost, despite the fact that 95% of the cost might not
have been depreciated over the assumed life and that, generally, due to considerations of inflation and hassles associated
with the establishment of a new plant, etc. The actual realizable price could be much higher.
b. In the case of land, 100% of original cost, though in most cases it will fetch a very high premium after the lapse of 12
years or so of assumed project life.
The result is that the IRR so arrived at provides a lower value than it could be achieved in real life. The project should
withstand, and justify its financing based on, this lower conservatively arrived IRR.
Sensitivity Analysis
Sensitivity analysis is a further exercise, and at that a very popular one, in risk management. Sensitivity analysis
involves identifying most critical factors that could lead to risk, quantifying likely variations therein and subjecting the
entire financial evaluation criterion, as mentioned earlier, to them. The objective is to see the response of the projected
profitability to each of these factors and to identify the areas most vulnerable to a project so that the management could
adequately address them while running the operations. There can be no fixed norms for the extent to which the
variation in the critical factors could be quantified. Normally, financial projections are subjected to 5% variation in
projected capacity utilization, that is, quantum of sales, selling prices of finished products and raw material prices.
Analysis could also be carried out by combining the effect of two factors depending upon the risk perception of the
project. In case of import- intensive and export-oriented projects, they are subjected to likely foreign exchange
fluctuations.
INFRASTRUCTURE PROJECTS

    Features of the infrastructure projects
•      These projects need a very high amount of initial outlay e.g. the cost of setting the metro railways in Kolkata or
       Delhi was/is in the range of thousand crores of rupees.
•      The gestation period of these projects is relatively longer e.g. for an infrastructure project, the average time required
       to get a satisfactory return on investment is about 15 years.
•      The economic life of the infrastructure thus built is also longer e.g. the working life of a river bridge is more than a
       century.
•      These projects generally break geographical barrier e.g. road or railways or telephonic connectivity generally brings
       people nearer irrespective of the geographical distance among them.
•      In many cases, these projects are undertaken for greater interest of the society e.g. the jobs like, road or railways or
       telephonic connectivity are generally undertaken for the convenience of the masses.
•      The risk of technological obsolescence is less. The construction of the infrastructure projects is a matter of great
       challenge. Thereafter, as long as the facilities are required, it will be useful to the people.
•      Execution of the project is generally a very complex task. As the projects needs a very high volume of work, for
       example setting the east-west corridor for a length of more than 2000 kilometers, the erection and execution of the
       project is complex in nature.

    A note on infrastructure project financing practice in India
    Infrastructure projects are mostly being financed by the planned allocation of the Planning Commission of India and
    partially by the banks. The choice of the project, amount of allocation and time of disbursement are seriously
    influenced by actions of the political leaders. Therefore, economically unviable projects are also getting financed as
    these are considered to be socially desirable by the politicians in order to protect their vote bank. Therefore, a large
    amount of government money will be wasted, causing severe hardship to the taxpayers. It is correct that the
    government should also have some social goals. But the social commitment should outweigh the business requirements
    in a country like, India where the industry is sharpen their competitive edge with the support of a better infrastructure.
    Such growth will lead to higher employment and better standard of living and thereby overall development of the
    economy. While for the bank financing, the project finance is available for a very short term, while the gestation period
    for any project is long term to very long term. Therefore, one cannot rule out the possibility of the asset-liability
    mismatching that may be inconvenient to the lenders as well as the borrower.
    Infrastructure projects generally need a significant amount of capital investment where the gestation period varies from
    long term to very long term. Therefore, we are required to find out such a type of liability where the cash flows match
    the liabilities, ruling out the possibility of asset-liability mismatches. Bank finance or the other debt instruments as
    presently available in the markets cannot fulfill such requirements. The sponsor should consider equity investment in
    this context for the development of any infrastructure facilities in any part of the country. Apart from it, the recently
    formed private insurers as well as the upcoming pension fund providers can be offered some incentives for making
    investments in this sector – either in the form of equity or debt. Since their liabilities are long term in nature, there will
    not be any asset-liability mismatch. These investments will help to achieve the growth of the infrastructure facilities in
    the country while the private players will get a lucrative opportunity to invest in the fund starved sector.
    The government has to play a key role for the success of the financing requirements by the Indian infrastructure
    sectors. It is required to formulate clear and consistent policy in this regard. The investors should be properly
    compensated for the risk assumed by them by making an investment. Wherever possible, the government should also
    assure the means of getting adequate returns from such investment. Simultaneously, the uniformity of these policies
    must have to be maintained, irrespective of the ideology of party ruling the country. In this context, the Enron episode,
    related to the Dabhol Power Company cannot be forgettable as one government run by one party signed the agreement
    while the successive government run by the another party scrapped the same, causing widespread frustration among
    the investors.

Más contenido relacionado

La actualidad más candente

Project identification (report)
Project identification (report)Project identification (report)
Project identification (report)christopher abne
 
Factors to be considered for project selection
Factors to be considered for project selectionFactors to be considered for project selection
Factors to be considered for project selectionYuvaraj neelakandan
 
Development project appraisal and sd(L6)1
Development project appraisal and sd(L6)1Development project appraisal and sd(L6)1
Development project appraisal and sd(L6)1Farha Sharmin
 
Preparation of project ppt
Preparation of project pptPreparation of project ppt
Preparation of project pptMit mysore
 
Bank project appraisal,
Bank  project appraisal, Bank  project appraisal,
Bank project appraisal, sksbatish
 
Project formulation and appraisal
Project formulation and appraisalProject formulation and appraisal
Project formulation and appraisalSurya C D
 
Project feasibility study report
Project feasibility study report Project feasibility study report
Project feasibility study report Harish Satya
 
Project appraisal and its techniques
Project appraisal and its techniquesProject appraisal and its techniques
Project appraisal and its techniquesAksharaMahesh
 
Techno Economic Feasibility Report I Gaurav Singh Rajput
Techno Economic Feasibility Report I Gaurav Singh RajputTechno Economic Feasibility Report I Gaurav Singh Rajput
Techno Economic Feasibility Report I Gaurav Singh RajputGaurav Singh Rajput
 
18611 project identification
18611 project identification18611 project identification
18611 project identificationSingh Deep
 
Project Identification Technique
Project Identification TechniqueProject Identification Technique
Project Identification TechniqueSamreenAkhtar8
 
project appraisal
project appraisal project appraisal
project appraisal Dronak Sahu
 
Preparation of Project Report
Preparation of Project ReportPreparation of Project Report
Preparation of Project Reportguest821cf8f
 
Project management
Project management Project management
Project management Azam FA
 
ITFT - Business Opportunity
ITFT - Business OpportunityITFT - Business Opportunity
ITFT - Business OpportunityAarti Katoch
 
Business Planning for Regeneration Fund Applications
Business Planning for Regeneration Fund Applications Business Planning for Regeneration Fund Applications
Business Planning for Regeneration Fund Applications kateiom
 
Feasibility study ppt
Feasibility study pptFeasibility study ppt
Feasibility study pptkunal kishore
 

La actualidad más candente (20)

Project identification (report)
Project identification (report)Project identification (report)
Project identification (report)
 
Factors to be considered for project selection
Factors to be considered for project selectionFactors to be considered for project selection
Factors to be considered for project selection
 
Project appraisal
Project appraisalProject appraisal
Project appraisal
 
Development project appraisal and sd(L6)1
Development project appraisal and sd(L6)1Development project appraisal and sd(L6)1
Development project appraisal and sd(L6)1
 
Preparation of project ppt
Preparation of project pptPreparation of project ppt
Preparation of project ppt
 
Bank project appraisal,
Bank  project appraisal, Bank  project appraisal,
Bank project appraisal,
 
Project formulation and appraisal
Project formulation and appraisalProject formulation and appraisal
Project formulation and appraisal
 
feasibility study
 feasibility study feasibility study
feasibility study
 
Project Planning & Feasibility Study
Project Planning & Feasibility StudyProject Planning & Feasibility Study
Project Planning & Feasibility Study
 
Project feasibility study report
Project feasibility study report Project feasibility study report
Project feasibility study report
 
Project appraisal and its techniques
Project appraisal and its techniquesProject appraisal and its techniques
Project appraisal and its techniques
 
Techno Economic Feasibility Report I Gaurav Singh Rajput
Techno Economic Feasibility Report I Gaurav Singh RajputTechno Economic Feasibility Report I Gaurav Singh Rajput
Techno Economic Feasibility Report I Gaurav Singh Rajput
 
18611 project identification
18611 project identification18611 project identification
18611 project identification
 
Project Identification Technique
Project Identification TechniqueProject Identification Technique
Project Identification Technique
 
project appraisal
project appraisal project appraisal
project appraisal
 
Preparation of Project Report
Preparation of Project ReportPreparation of Project Report
Preparation of Project Report
 
Project management
Project management Project management
Project management
 
ITFT - Business Opportunity
ITFT - Business OpportunityITFT - Business Opportunity
ITFT - Business Opportunity
 
Business Planning for Regeneration Fund Applications
Business Planning for Regeneration Fund Applications Business Planning for Regeneration Fund Applications
Business Planning for Regeneration Fund Applications
 
Feasibility study ppt
Feasibility study pptFeasibility study ppt
Feasibility study ppt
 

Similar a Risk project mgt, infra

Risk response planning.pptx
Risk response planning.pptxRisk response planning.pptx
Risk response planning.pptxSaranSaravanan22
 
Risk strategies presentation
Risk strategies presentationRisk strategies presentation
Risk strategies presentationRaven Morgan
 
Lecture 6 Managing risk.pptx
Lecture 6 Managing risk.pptxLecture 6 Managing risk.pptx
Lecture 6 Managing risk.pptxMehediHasan636262
 
· How should the risks be prioritized· Who should do the priori.docx
· How should the risks be prioritized· Who should do the priori.docx· How should the risks be prioritized· Who should do the priori.docx
· How should the risks be prioritized· Who should do the priori.docxalinainglis
 
Risk 0-risk-guide book for pmi-rmp by amer elbaz
Risk 0-risk-guide book for pmi-rmp by amer elbazRisk 0-risk-guide book for pmi-rmp by amer elbaz
Risk 0-risk-guide book for pmi-rmp by amer elbazMohamed Saeed
 
Critical role of_risk_assessment_in_international_projects_en
Critical role of_risk_assessment_in_international_projects_enCritical role of_risk_assessment_in_international_projects_en
Critical role of_risk_assessment_in_international_projects_enVyacheslav Guzovsky
 
Implementing Ways to Limit Risk (Risk Mitigation)
Implementing Ways to Limit Risk (Risk Mitigation)Implementing Ways to Limit Risk (Risk Mitigation)
Implementing Ways to Limit Risk (Risk Mitigation)JOSEPH Maas
 
Risk management overview
Risk management overviewRisk management overview
Risk management overviewHossam Maghrabi
 
Control only.pdf
Control only.pdfControl only.pdf
Control only.pdfNmnKmr2
 
2.11 risk management 1
2.11 risk management 12.11 risk management 1
2.11 risk management 1reddvise
 
Risk Management Best Practices
Risk Management Best PracticesRisk Management Best Practices
Risk Management Best PracticesPMILebanonChapter
 
Planning risk responses and Risk Controlling
Planning risk responses and Risk ControllingPlanning risk responses and Risk Controlling
Planning risk responses and Risk ControllingUsama Fayyaz
 
Construction project management & risk mitigation
Construction project management & risk mitigationConstruction project management & risk mitigation
Construction project management & risk mitigationrajlaxmipardeshi
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk ManagementKaustubh Gupta
 
Managing Risk as Opportunity
Managing Risk as OpportunityManaging Risk as Opportunity
Managing Risk as OpportunityGlen Alleman
 

Similar a Risk project mgt, infra (20)

Risk response planning.pptx
Risk response planning.pptxRisk response planning.pptx
Risk response planning.pptx
 
Risk management
Risk management Risk management
Risk management
 
Risk strategies presentation
Risk strategies presentationRisk strategies presentation
Risk strategies presentation
 
Lecture 6 Managing risk.pptx
Lecture 6 Managing risk.pptxLecture 6 Managing risk.pptx
Lecture 6 Managing risk.pptx
 
Risk based thinking
Risk based thinkingRisk based thinking
Risk based thinking
 
· How should the risks be prioritized· Who should do the priori.docx
· How should the risks be prioritized· Who should do the priori.docx· How should the risks be prioritized· Who should do the priori.docx
· How should the risks be prioritized· Who should do the priori.docx
 
Risk 0-risk-guide book for pmi-rmp by amer elbaz
Risk 0-risk-guide book for pmi-rmp by amer elbazRisk 0-risk-guide book for pmi-rmp by amer elbaz
Risk 0-risk-guide book for pmi-rmp by amer elbaz
 
Critical role of_risk_assessment_in_international_projects_en
Critical role of_risk_assessment_in_international_projects_enCritical role of_risk_assessment_in_international_projects_en
Critical role of_risk_assessment_in_international_projects_en
 
Implementing Ways to Limit Risk (Risk Mitigation)
Implementing Ways to Limit Risk (Risk Mitigation)Implementing Ways to Limit Risk (Risk Mitigation)
Implementing Ways to Limit Risk (Risk Mitigation)
 
Risk management overview
Risk management overviewRisk management overview
Risk management overview
 
Control only.pdf
Control only.pdfControl only.pdf
Control only.pdf
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
Project risk management
Project risk managementProject risk management
Project risk management
 
2.11 risk management 1
2.11 risk management 12.11 risk management 1
2.11 risk management 1
 
Risk Management Best Practices
Risk Management Best PracticesRisk Management Best Practices
Risk Management Best Practices
 
Planning risk responses and Risk Controlling
Planning risk responses and Risk ControllingPlanning risk responses and Risk Controlling
Planning risk responses and Risk Controlling
 
Construction project management & risk mitigation
Construction project management & risk mitigationConstruction project management & risk mitigation
Construction project management & risk mitigation
 
Chap007
Chap007Chap007
Chap007
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Managing Risk as Opportunity
Managing Risk as OpportunityManaging Risk as Opportunity
Managing Risk as Opportunity
 

Más de Kinshook Chaturvedi (20)

Working and functions_of_rbi[1]
Working and functions_of_rbi[1]Working and functions_of_rbi[1]
Working and functions_of_rbi[1]
 
Role of idfc_in_infrastucture_finance
Role of idfc_in_infrastucture_financeRole of idfc_in_infrastucture_finance
Role of idfc_in_infrastucture_finance
 
Mutual funds
Mutual fundsMutual funds
Mutual funds
 
Iifcl ppt
Iifcl pptIifcl ppt
Iifcl ppt
 
Basel ii norms.ppt
Basel ii norms.pptBasel ii norms.ppt
Basel ii norms.ppt
 
Retail banking pres
Retail banking presRetail banking pres
Retail banking pres
 
Presentation on lic of india
Presentation on lic of indiaPresentation on lic of india
Presentation on lic of india
 
Mfi dfi
Mfi dfiMfi dfi
Mfi dfi
 
Management of np as imt
Management of np as imtManagement of np as imt
Management of np as imt
 
Life insurance in india final raja
Life insurance in india final rajaLife insurance in india final raja
Life insurance in india final raja
 
Financial inclusion
Financial inclusionFinancial inclusion
Financial inclusion
 
Corporate banking v2
Corporate banking v2Corporate banking v2
Corporate banking v2
 
Corporate banking latest
Corporate banking latestCorporate banking latest
Corporate banking latest
 
Financial mgt exercises
Financial mgt exercisesFinancial mgt exercises
Financial mgt exercises
 
Csac10[1].p
Csac10[1].pCsac10[1].p
Csac10[1].p
 
Csac08[1].p
Csac08[1].pCsac08[1].p
Csac08[1].p
 
Csac05[1].p
Csac05[1].pCsac05[1].p
Csac05[1].p
 
Csac14[1].p
Csac14[1].pCsac14[1].p
Csac14[1].p
 
Csac06[1].p
Csac06[1].pCsac06[1].p
Csac06[1].p
 
Xyber001 16 12_09 (2)
Xyber001 16 12_09 (2)Xyber001 16 12_09 (2)
Xyber001 16 12_09 (2)
 

Risk project mgt, infra

  • 1. Risks faced by Projects • Governance risk: The governance risk arises out of the board and management performance with reference to ethics, leadership, reputation of the organization etc. • Strategic risk: This risk arises out of an error in strategy adopted by organization. For example, a selection of technology that is not suitable to the organization or choosing a strategy that can change the course of business drastically. • Operational risk: This is a risk of having poor operational systems, poor implementation and process problems related to production and distribution. • Market risk: The risk arising out of competition, fluctuations in foreign exchange rates, raw material supplies, interest rates, credit and liquidity aspects, etc. • Legal risk: This risk is a result of legal and regulatory obligations like contract risks and litigation suits filed against organization. Construction phase risks Completion risk: Completion risk allocation is a vital part of the risk allocation of any project. This phase carries the greatest risk for the financier. Construction carries the danger that the project will not be completed on time, on budget or at all because of technical, labor, and other construction difficulties. Such delays or cost increases may delay loan repayments and cause interest and debt to accumulate. They may also jeopardize contracts for the sale of the project’s output and supply contacts for raw materials. Completion risk is managed during the loan period by methods such as making pre-completion phase draw downs of further funds conditional on certificates being issued by independent experts to confirm that the construction is progressing as planned. Operation phase risks Resource/Reserve risk: This is the risk that for a mining project, rail project, power station or toll road there are inadequate inputs that can be processed or serviced to produce an adequate return. For example, this is the risk that there are insufficient reserves for a mine, passengers for a railway, fuel for a power station or vehicles for a toll road. Operating risk: These are general risks that may affect the cash flow of the project by increasing the operating costs or affecting the project’s capacity to continue to generate the quantity and quality of the planned output over the life of the project. Operating risks include, for example, the level of experience and resources of the operator, inefficiencies in operations or shortages in the supply of skilled labor. Process of project risk management Risk Identification: It is definitely a brainstorming process to uncover the risks associated with the project. Several ideas are taken into account from risk perception of the team members of the project following the documentation process that are evaluated properly to uncover the risks inherent to the project. The other alternative way is to paint a picture of the project success. Thereafter, one should move backwards, duly considering the adverse developments that may affect the path to achieve success. Once the risks are identified, these may be placed as a sticky note on the process of project schedule, process map, etc. Risk Analysis: In this step, the overall magnitude of the risk and its expected losses are estimated. In order to achieve the best outcome, the risk event drivers are determined and the probable worst impact of the same assessed. Identification of the risk event drivers can be termed as the foundation of the risk management process as it helps us to mitigate the same. Risk Prioritization: In this stage, the risks are compared on the basis of their probability of occurrences as well as the expected amount of losses, if the worst thing is going to occur in future. The risks are listed on the basis of the resultant product of the above two factors. This steps guides the project manager for the allocation of the resources to manage the risks actively. Since the resources are limited, the project manager should choose the risks carefully, which have the higher impact on the organization. Risk Planning: Once the risks are short listed for their active management, the action plan is also framed accordingly. The following kinds of actions may be adopted: • Acceptance: It is adopted when the consequences are negligibly small • Avoidance: It is the best way of dealing the risk by taking suitable precautionary measures that may rule out the possibility of the occurrence of the event. • Transfer: It is another good alternative where the consequences of losses are transferred to a third party like a contractor or insurer at some nominal expenses. • Self-financing: Here, on the basis of the past experience of the organization, a separate fund is built up which is used to meet the consequences for the occurrence of the risk. The actions described above are broadly categorized as the prevention plans and contingency plans. The first one is the proactive one while the second one is reactive one and accordingly the resources should be kept ready to meet the risks.
  • 2. Risk Monitoring: It is the final step of the process of project risk management but it is repeated regularly throughout the execution of the process of the project. This step consists of the following processes: • How the actions plans for the actively managed risks are progressing. • Removal of the risks that have mitigated effectively or cannot be expected to occur. • Addition to the actively managed risks that has occurred as the execution of the project is underway. Therefore, monitoring of the risks is the repetition of the other risk management processes as the circumstances are changing with the passage of time. Incorporating risk management into the projects requires a lot of time and effort, even if it is scaled down. One should work in advance in order to avoid the occurrence of the consequences of the risks that will result in predictable outcomes from the project. Measuring Effectiveness of Risk management Measures An action initiated for managing risks does not mean that the desired results will be achieved. In order to know whether the risk management tools and techniques implemented to mitigate the risks have succeeded in achieving the desired results, organizations need to measure the effectiveness of the risk management measures on a regular basis. One method of measuring the effectiveness is, by comparing the monetary exposure of the project before and after risk mitigation actions. Pre-mitigation exposure can be calculated by multiplying the monetary impact of the risk with the probability of risk. The amount arrived at can be compared after risk mitigation process. The difference can be seen clearly between the amounts, as the risk mitigation actions will reduce either the probability of risk or the monetary exposure. This method can be utilized, only if the financial loss or exposure is quantified during initial risk analysis. Another way to measure for all the risks and the cost of mitigation action. After calculating the values, a ratio of the two parameters can be calculated to determine the cost effectiveness of the actions taken. While the above two methods measure the risk mitigation pre and post-actions, another way to measure the effectiveness of the actions is, by reviewing the actions along the progress of the project. While reviewing the project activities, organizations need to include the review of project risk mitigation actions invariably. By doing so, organizations can review along with the progress of the project, whether project manager and project teams are performing their schedule risk management activities as planned. This also enables the management to decide whether specific additional assistance needs to be provided to the teams to accomplish the objectives of risk management apart from the scope to modify the actions in the light of new developments. With growing complexities in business environment and emergence of new forms of risks, project risk management should be treated as a separate activity and reviewed along the length of the project. Risk Response planning Risk response planning determines the action for enhancing the opportunities and reducing the threats in a project. The common strategies to deal with threats are avoidance, transfer, mitigation and acceptance.(as said before) • Risk avoidance refers to those actions that can nullify the impact of risk events on a project. Project managers can achieve it either by changing the way of carrying activities or by changing the project objectives. • Risk transfer implies that the third party will shield the project from the impact of all or few risk events. The risk transfer approach is a middle path approach, which makes the best alternative less good and the worst alternative less bad. • Risk mitigation approach is possible when the potential impact of the risk is above a certain threshold. • Risk acceptance is about planning for the options that can be considered when the risk arises. Options may be in active or passive forms according to the severity of an event. For active acceptance, contingency plans are developed so that the impact of the risk can be reduced to an acceptable level. Benefits of using risk response planning chart: • Decision can be taken proactively to counter a risk by assuming that it will happen in the future. • Events or risks with high threshold can be minimized. • Events with passive impact can be found out and ignored. • Few risks lie between the passive acceptance and avoidance situations. It is not worth for the company to go for a contingency plan. The identification of those risks to transfer is possible by using this chart. • The risks that are likely to occur many times can be accepted actively and their impact can be reduced. • Risk mitigation can be implemented wherever it is required Risk management measures in practice Conservative Estimates of Profitability Preparation of projected profitability estimates, balance sheets and cash flow statements is done with reference to the cost of the project, means of finance, underlying assumptions relating to capacity utilization, schedule of implementation, selling price realization, raw material costs, other production costs, administrative and selling overheads, depreciation rates, tax rates and tax benefits, etc. These assumptions need to be realistic. This provides a
  • 3. cushion against the unforeseen events that could influence the projected profitability, negatively. Key assumptions, where the principle of conservatism is applied, are as under: (i) Capacity Utilization: Though a project, if successful, will run at its optimum capacity in the very first/second year of its commissioning, as a shield against uncertain future, the following safeguards are taken in the projections a. In the case of a new venture, capacity utilization is gradually increased over 3-4 years to reach and then stabilize at an optimum level based on the actual capacity utilization being achieved in the related industry. b. In the case of expansion by an existing unit, past levels achieved in capacity utilization provide the benchmark for assuming the gradual capacity utilization increase in the new project. (ii) Selling Prices: To begin with, the unit-selling price is taken based on the generally prevailing market price in the case of a new venture and already realized price by an existing unit in the case of an expansion project. This price is then discounted for factors, such as, variations in the prices in the past, the need to sell at a lower price due to likely competition or to establish the product in the case of a new entrant, fluctuations in prices in case of products whose prices fluctuate at short intervals, etc. (iii) Raw Material Prices: Here again the beginning price is taken based on the generally prevailing market price in the case of a new venture and the price at which the material is already being purchased by an existing unit in the case of an expansion project. This price is then revised in the light of considerations, such as likely demand-supply scenario, short interval fluctuations, past trend in the prices and cyclicality of the supplier industry. The above risk management measures in respect of profitability projections result in lower projections. The project should withstand, and justify its financing based on these lower projections. Conservative Assumptions in Financial Evaluation Criteria These are the assumptions for computing the IRR for evaluating the financial viability of the project and assessing the associated risk: (i) Project Life: The life of the project is generally taken to be 12 years or even less, depending upon the nature of the industry, say, where the technical obsolescence is high, except of course for infrastructure ones. The life as estimated as per the technical appraisal is disregarded unless, of course, it is shorter than the assumed norm. (ii) Salvage Value: In the terminal year, that is, at the end of the assumed project life cash inflows are computed assuming the following salvage values a. In the case of fixed assets other than land ó5% of the original cost, despite the fact that 95% of the cost might not have been depreciated over the assumed life and that, generally, due to considerations of inflation and hassles associated with the establishment of a new plant, etc. The actual realizable price could be much higher. b. In the case of land, 100% of original cost, though in most cases it will fetch a very high premium after the lapse of 12 years or so of assumed project life. The result is that the IRR so arrived at provides a lower value than it could be achieved in real life. The project should withstand, and justify its financing based on, this lower conservatively arrived IRR. Sensitivity Analysis Sensitivity analysis is a further exercise, and at that a very popular one, in risk management. Sensitivity analysis involves identifying most critical factors that could lead to risk, quantifying likely variations therein and subjecting the entire financial evaluation criterion, as mentioned earlier, to them. The objective is to see the response of the projected profitability to each of these factors and to identify the areas most vulnerable to a project so that the management could adequately address them while running the operations. There can be no fixed norms for the extent to which the variation in the critical factors could be quantified. Normally, financial projections are subjected to 5% variation in projected capacity utilization, that is, quantum of sales, selling prices of finished products and raw material prices. Analysis could also be carried out by combining the effect of two factors depending upon the risk perception of the project. In case of import- intensive and export-oriented projects, they are subjected to likely foreign exchange fluctuations.
  • 4. INFRASTRUCTURE PROJECTS Features of the infrastructure projects • These projects need a very high amount of initial outlay e.g. the cost of setting the metro railways in Kolkata or Delhi was/is in the range of thousand crores of rupees. • The gestation period of these projects is relatively longer e.g. for an infrastructure project, the average time required to get a satisfactory return on investment is about 15 years. • The economic life of the infrastructure thus built is also longer e.g. the working life of a river bridge is more than a century. • These projects generally break geographical barrier e.g. road or railways or telephonic connectivity generally brings people nearer irrespective of the geographical distance among them. • In many cases, these projects are undertaken for greater interest of the society e.g. the jobs like, road or railways or telephonic connectivity are generally undertaken for the convenience of the masses. • The risk of technological obsolescence is less. The construction of the infrastructure projects is a matter of great challenge. Thereafter, as long as the facilities are required, it will be useful to the people. • Execution of the project is generally a very complex task. As the projects needs a very high volume of work, for example setting the east-west corridor for a length of more than 2000 kilometers, the erection and execution of the project is complex in nature. A note on infrastructure project financing practice in India Infrastructure projects are mostly being financed by the planned allocation of the Planning Commission of India and partially by the banks. The choice of the project, amount of allocation and time of disbursement are seriously influenced by actions of the political leaders. Therefore, economically unviable projects are also getting financed as these are considered to be socially desirable by the politicians in order to protect their vote bank. Therefore, a large amount of government money will be wasted, causing severe hardship to the taxpayers. It is correct that the government should also have some social goals. But the social commitment should outweigh the business requirements in a country like, India where the industry is sharpen their competitive edge with the support of a better infrastructure. Such growth will lead to higher employment and better standard of living and thereby overall development of the economy. While for the bank financing, the project finance is available for a very short term, while the gestation period for any project is long term to very long term. Therefore, one cannot rule out the possibility of the asset-liability mismatching that may be inconvenient to the lenders as well as the borrower. Infrastructure projects generally need a significant amount of capital investment where the gestation period varies from long term to very long term. Therefore, we are required to find out such a type of liability where the cash flows match the liabilities, ruling out the possibility of asset-liability mismatches. Bank finance or the other debt instruments as presently available in the markets cannot fulfill such requirements. The sponsor should consider equity investment in this context for the development of any infrastructure facilities in any part of the country. Apart from it, the recently formed private insurers as well as the upcoming pension fund providers can be offered some incentives for making investments in this sector – either in the form of equity or debt. Since their liabilities are long term in nature, there will not be any asset-liability mismatch. These investments will help to achieve the growth of the infrastructure facilities in the country while the private players will get a lucrative opportunity to invest in the fund starved sector. The government has to play a key role for the success of the financing requirements by the Indian infrastructure sectors. It is required to formulate clear and consistent policy in this regard. The investors should be properly compensated for the risk assumed by them by making an investment. Wherever possible, the government should also assure the means of getting adequate returns from such investment. Simultaneously, the uniformity of these policies must have to be maintained, irrespective of the ideology of party ruling the country. In this context, the Enron episode, related to the Dabhol Power Company cannot be forgettable as one government run by one party signed the agreement while the successive government run by the another party scrapped the same, causing widespread frustration among the investors.