SlideShare una empresa de Scribd logo
1 de 17
S.Balamurugan AP/Mech AAA College of Engg. & Tech.2/22/2018 1
CASH FLOW
CASHFLOW Present Worth Method
Revenue Dominated Cash Flow
Cost – Dominated Cash Flow
Future Worth Method
Revenue Dominated Cash Flow
Cost – Dominated Cash Flow
Annual Equivalent Method
Revenue Dominated Cash Flow
Cost – Dominated Cash Flow
2/22/2018
S.Balamurugan AP/Mech AAA College of
Engg. & Tech.
2
2/22/2018
S.Balamurugan AP/Mech AAA College of
Engg. & Tech.
3
2/22/2018
S.Balamurugan AP/Mech AAA College of
Engg. & Tech.
4
Present Worth Method of Comparison – Revenue Dominated
Positive Sign – Profit, Revenue, Salvage Value (Inflows)
Negative Sign – Costs (Outflows)
• The cash flow of each alternative will reduced to time zero by
assuming interest rate i.(Time zero = Present time)
• Best alternative will be selected by comparing the present
worth amount of alternatives.(Maximum Present Worth)
S
• R1 R2 R3 R4 Rn
i %
0 1 2 3 4 n
P Revenue-Dominated Cash Flow Diagram
PW(i)= - P + R1[1/(1+i)1]+R2[1/(1+i)2]+..+[Rj[1/(1+i)j]+Rn[1/(1+i)n]+S[1/(1+i)n]
S.Balamurugan AP/Mech AAA College of Engg. & Tech.2/22/2018 5
Present Worth Method of Comparison – Cost Dominated
Positive Sign –Costs (Outflows)
Negative Sign – Profit, Revenue, Salvage Value (Inflows)
• The cash flow of each alternative will reduced to time zero by
assuming interest rate i.(Time zero = Present time)
• Best alternative will be selected by comparing the present
worth amount of alternatives. (Minimum Present Worth)
• P C1 C2 C3 C4 Cn
i %
n
0 1 2 3 4
Cost-Dominated Cash Flow Diagram S
PW(i)= P + C1[1/(1+i)1]+C2[1/(1+i)2]+..+[Cj[1/(1+i)j]+Cn[1/(1+i)n] - S[1/(1+i)n]
S.Balamurugan AP/Mech AAA College of Engg. & Tech.2/22/2018 6
• Alpha Industry is planning to expand its production operation. It has identified
three different technologies for meeting the goal. The initial outlay & annual
revenues with respect to each of the technologies are summarized in table.
Suggest the best technology which is to be implemented based on the present
worth method of comparison assuming 20% interest rate, compounded annually.
Present Worth Method of Comparison – Revenue Dominated
Positive Sign – Profit, Revenue, Salvage Value (Inflows)
Negative Sign – Costs (Outflows)
Initial Outlay (Rs.) Annual Revenue (Rs.) Life (years)
Technology 1 12,00,000 4,00,000 10
Technology 2 20,00,000 6,00,000 10
Technology 3 18,00,000 5,00,000 10
Technology 1 PW(20%) = -12,00,000 + 4,00,000 × (P/A, 20%, 10)
PW(20%) = -12,00,000 + 4,00,000 × (4.1925)
PW(20%) = -12,00,000 + 16,77,000 = Rs. 4,77,000
Technology 2 PW(20%) = -20,00,000 + 6,00,000 × (P/A, 20%, 10)
PW(20%) = -20,00,000 + 6,00,000 × (4.1925)
PW(20%) = -20,00,000 + 25,15,500 = Rs. 5,15,500
Technology 3 PW(20%) = -18,00,000 + 5,00,000 × (P/A, 20%, 10)
PW(20%) = -18,00,000 + 5,00,000 × (4.1925)
PW(20%) = -18,00,000 + 20,96,250 = Rs. 2,96,250
2/22/2018
S.Balamurugan AP/Mech AAA College of
Engg. & Tech.
7
Bid Engineer’s Estimates
Initial cost (Rs.) Service life (years) Annual operations &
Maintenance cost (Rs.)
Alpha Elevator Inc. 4,50,000 15 27,000
Beta Elevator Inc. 5,40,000 15 28,500
Present Worth Method of Comparison – Cost Dominated
Positive Sign –Costs (Outflows)
Negative Sign – Profit, Revenue, Salvage Value (Inflows)
An engineer has two bids for an elevator to be installed in a new building. The details of the
bids for the elevators are as follows, Determine which bid should be accepted, based on the
present worth method of comparison assuming 15% interest rate, compounded annually.
Alpha Elevator Inc. PW(15%) = 4,50,000 + 27,000 × (P/A, 15%, 15)
PW(15%) = 4,50,000 + 27,000 × (5.8474)
PW(15%) = 4,50,000 + 1,57,879.80 = Rs. 6,07,879.80
Beta Elevator Inc. PW(15%) = 5,40,000 + 28,500 × (P/A, 15%, 15)
PW(15%) = 5,40,000 + 28,500 × (5.8474)
PW(15%) = 5,40,000 + 1,66,650.90 = Rs. 7,06,650.90
Cost dominated cash flow, the bid 1 is less than that of bid 2. Bid 1 is best
alternative.
2/22/2018
S.Balamurugan AP/Mech AAA College of
Engg. & Tech.
8
• Consider the following two mutually exclusive alternatives: At i = 18%, select the
best alternative based on future worth method of comparison.
Future Worth Method of Comparison – Revenue Dominated
Positive Sign – Profit, Revenue, Salvage Value (Inflows)
Negative Sign – Costs (Outflows)
Alternative A FW(18%) = -50,00,000(F/P, 18%, 4) + 20,00,000 × (F/A, 18%, 4)
FW(18%) = -50,00,000(1.939) + 20,00,000 × (5.215)
FW(18%) = Rs. 7,35,000
Alternative B FW(18%) = -45,00,000(F/P, 18%, 4) + 18,00,000 × (F/A, 18%, 4)
FW(18%) = -45,00,000(1.939) + 18,00,000 × (5.215)
FW(18%) = Rs. 6,61,500
End of Year
Alternative 0 1 2 3 4
A (Rs.) -50,00,000 20,00,000 20,00,000 20,00,000 20,00,000
B (Rs.) -45,00,000 18,00,000 18,00,000 18,00,000 18,00,000
Revenue dominated cash flow, the Alternative A is more than that of Alternative B.
Alternative A is best alternative.
2/22/2018
S.Balamurugan AP/Mech AAA College of
Engg. & Tech.
9
Machine A Machine B
Initial cost (Rs.) Rs. 4,00,000 Rs. 8,00,000
Useful life (years) 4 4
Salvage value at the end of
machine life
Rs. 2,00,000 Rs. 5,50,000
Annual maintenance cost Rs. 40,000 0
Future Worth Method of Comparison – Cost Dominated
Positive Sign –Costs (Outflows)
Negative Sign – Profit, Revenue, Salvage Value (Inflows)
A company must decide whether to buy machine A or machine B: At 12% interest rate,
which machine should be selected? Use future worth method of comparison.
Machine A FW(12%) = 4,00,000 (F/P, 12%, 4) + 40,000 × (F/A, 12%, 4) – 2,00,000
FW(12%) = 4,00,000 (1.574) + 40,000 × (4.779) – 2,00,000
FW(12%) = Rs. 6,20,760
Machine B FW(12%) = 8,00,000 (F/P, 12%, 4) – 5,50,000
FW(12%) = 8,00,000 (1.574) – 5,50,000
FW(12%) = Rs. 7,09,200
Cost dominated cash flow, the machine A is less than that of machine B. machine A
is best alternative.
2/22/2018
S.Balamurugan AP/Mech AAA College of
Engg. & Tech.
10
• A company invests in one of the two mutually exclusive alternatives. The life of
both alternatives is estimated to be 5 years with the following investments, annual
returns and salvage values. Determine the best alternative based on the annual
equivalent method by assuming i = 25%
Annual Equivalent Method of Comparison – Revenue Dominated
Positive Sign – Profit, Revenue, Salvage Value (Inflows)
Negative Sign – Costs (Outflows)
Alternative A AEA(25%) = - 1,50,000(A/P, 25%, 5) + 60,000 + 15,000 × (A/F, 25%, 5)
AEA(25%) = - 1,50,000(0.3718) + 60,000 + 15,000 × (0.1218)
AEA(25%) = Rs. 6,057
Alternative B AEA(25%) = - 1,75,000(A/P, 25%, 5) + 70,000 + 35,000 × (A/F, 25%, 5)
AEA(25%) = - 1,75,000(0.3718) + 70,000 + 35,000 × (0.1218)
AEA(25%) = Rs. 9,198
Revenue dominated cash flow, the Alternative B is more than that of Alternative A.
Alternative B is best alternative.
Alternative
A B
Investment (Rs.) 1,50,000 1,75,000
Annual equal return (Rs.) 60,000 70,000
Salvage value (Rs.) 15,000 35,000
2/22/2018
S.Balamurugan AP/Mech AAA College of
Engg. & Tech.
11
Around the lake Under the lake
Length 15 km 5 km
First cost (Rs.) 1,50,000 / km 7,50,000 / km
Useful life (years) 15 15
Maintenance cost (Rs.) 6,000 / km / yr 12,000 / km / yr
Salvage value (Rs.) 90,000 / km 1,50,000 / km
Yearly power loss (Rs.) 15,000 / km 15,000 / km
Annual Equivalent Method of Comparison– Cost Dominated
Positive Sign –Costs (Outflows)
Negative Sign – Profit, Revenue, Salvage Value (Inflows)
Two possible routes for laying a power line are under study. Data on the routes are as
follows: If 15% interest is used, should the power line be routed around the lake or
under the lake?
Around the lake –
Alternative 1
First cost = 1,50,000 × 15 = Rs.22,50,000
Maintenance cost / yr = 6,000 × 15 = Rs. 90,000
Power loss/yr = 15,000 × 15 = Rs.2,25,000
Maintenance cost & power loss / yr = Rs.90,000 + Rs.2,25,000 = Rs.3,15,000
Salvage value = 90,000 × 15 = Rs.13,50,000
Under the lake –
Alternative 2
First cost = 7,50,000 × 5 = Rs.37,50,000
Maintenance cost / yr = 12,000 × 5 = Rs. 60,000
Power loss/yr = 15,000 × 5 = Rs.75,000
Maintenance cost & power loss / yr = Rs.60,000 + Rs.75,000 = Rs.1,35,000
Salvage value = 1,50,000 × 5 = Rs.7,50,000
2/22/2018
S.Balamurugan AP/Mech AAA College of
Engg. & Tech.
12
Around the
lake –
Alternative 1
AE(15%) = 22,50,000(A/P, 15%, 15) + 3,15,000 – 13,50,000 × (A/F, 15%, 15)
AE(15%) = 22,50,000(0.1710) + 3,15,000 – 13,50,000 × (0.0210)
AE(15%) = Rs. 6,71,400
Under the
lake –
Alternative 2
AE(15%) = 37,50,000(A/P, 15%, 15) + 1,35,000 – 7,50,000 × (A/F, 15%, 15)
AE(15%) = 37,50,000(0.1710) + 1,35,000 – 7,50,000 × (0.0210)
AE(15%) = Rs. 7,60,500
Around the lake –
Alternative 1
First cost = 1,50,000 × 15 = Rs.22,50,000
Maintenance cost / yr = 6,000 × 15 = Rs. 90,000
Power loss/yr = 15,000 × 15 = Rs.2,25,000
Maintenance cost & power loss / yr = Rs.90,000 + Rs.2,25,000 = Rs.3,15,000
Salvage value = 90,000 × 15 = Rs.13,50,000
Under the lake –
Alternative 2
First cost = 7,50,000 × 5 = Rs.37,50,000
Maintenance cost / yr = 12,000 × 5 = Rs. 60,000
Power loss/yr = 15,000 × 5 = Rs.75,000
Maintenance cost & power loss / yr = Rs.60,000 + Rs.75,000 = Rs.1,35,000
Salvage value = 1,50,000 × 5 = Rs.7,50,000
Annual Equivalent Method of Comparison– Cost Dominated
Cost dominated cash flow, the Alternative 1 is less than that of Alternative 2.
Alternative 1 is best alternative.
2/22/2018
S.Balamurugan AP/Mech AAA College of
Engg. & Tech.
13
Rate of Return Method
The rate of return of a cash flow pattern is
the interest rate at which the present
worth of that cash flow pattern reduces to
zero.
Applications of Rate of Return method
• Useful for making investment decision.
• Ratios typically used by financial analysts to compare a company’s
performance over time or compare performance between companies.
• In capital budgeting process, companies would traditionally compare
the internal rate of return of different projects to decide which projects
to pursue in order to maximize the return.
2/22/2018
S.Balamurugan AP/Mech AAA College of
Engg. & Tech.
14
• A company is planning to expand its present business activity. It has two alternatives
for the expansion programme and the corresponding cash flows are tabulated below.
Each alternative has a life of five years and a negligible salvage value. The minimum
attractive rate of return for the company is 12%. Suggest the best alternative to the
company.
Alternative 1
Net present Worth PW(i) = - 5,00,000 + 1,70,000 (P/A, i, 5)
Rate of Return Method
Initial Investment (Rs.) Yearly revenue (Rs.)
Alternative 1 5,00,000 1,70,000
Alternative 2 8,00,000 2,70,000
i = 15 %,
PW(15%)
= - 5,00,000 + 1,70,000 (P/A, 15%, 5)
= - 5,00,000 + 1,70,000 (3.3522) = Rs. 69,874
i = 17 %,
PW(17%)
= - 5,00,000 + 1,70,000 (P/A, 17%, 5)
= - 5,00,000 + 1,70,000 (3.1993) = Rs. 43,881
i = 20 %,
PW(20%)
= - 5,00,000 + 1,70,000 (P/A, 20%, 5)
= - 5,00,000 + 1,70,000 (2.9906) = Rs. 8,402
i = 22 %,
PW(22%)
= - 5,00,000 + 1,70,000 (P/A, 22%, 5)
= - 5,00,000 + 1,70,000 (2.8636) = Rs. - 13,188
Interpolation
X1 = 20%, X2 = 22%, X =?
Y1 = 8402, Y2 = -13,188,
Y = 0
𝑋 − 𝑋1
𝑋2 − 𝑋1
=
𝑌 − 𝑌1
𝑌2 − 𝑌1
𝑋 − 20
22 − 20
=
0 − 8402
−13188 − 8402
X – 20 = (0.3892) (2)
Rate of Return X = 20.78 %2/22/2018
S.Balamurugan AP/Mech AAA College of
Engg. & Tech.
15
• A company is planning to expand its present business activity. It has two alternatives
for the expansion programme and the corresponding cash flows are tabulated below.
Each alternative has a life of five years and a negligible salvage value. The minimum
attractive rate of return for the company is 12%. Suggest the best alternative to the
company.
Alternative 2
Net present Worth PW(i) = - 8,00,000 + 2,70,000 (P/A, i, 5)
Rate of Return Method
Initial Investment (Rs.) Yearly revenue (Rs.)
Alternative 1 5,00,000 1,70,000
Alternative 2 8,00,000 2,70,000
i = 20 %,
PW(20%)
= - 8,00,000 + 2,70,000 (P/A, 20%, 5)
= - 8,00,000 + 2,70,000 (2.9906) = Rs. 7,462
i = 22 %,
PW(22%)
= - 8,00,000 + 2,70,000 (P/A, 22%, 5)
= - 8,00,000 + 2,70,000 (2.8636) = Rs. - 26,828
Interpolation
X1 = 20%, X2 = 22%, X =?
Y1 = 7462, Y2 = -26,828,
Y = 0
𝑋 − 𝑋1
𝑋2 − 𝑋1
=
𝑌 − 𝑌1
𝑌2 − 𝑌1
𝑋 − 20
22 − 20
=
0 − 7462
−26828 − 7462
X – 20 = (0.2175) (2)
Rate of Return X = 20.435 %
The rate of return of alternative 1 is greater than
that of the alternative 2, So select alternative 1.
2/22/2018
S.Balamurugan AP/Mech AAA College of
Engg. & Tech.
16
Skimming Price Policy
• Price skimming is a pricing strategy in which a marketer sets a
relatively high initial price for a product or service at first, and then
lowers the price over time.
• It allows the firm to recover its sunk costs quickly before competition
steps in and lowers the market price.
2/22/2018
S.Balamurugan AP/Mech AAA College of
Engg. & Tech.
17

Más contenido relacionado

La actualidad más candente

Engineering costs and cost estimating
Engineering costs and cost estimatingEngineering costs and cost estimating
Engineering costs and cost estimatinganwar khan
 
MG 6863- ENGG ECONOMICS UNIT II VALUE ENGINEERING
 MG 6863- ENGG ECONOMICS UNIT II  VALUE ENGINEERING MG 6863- ENGG ECONOMICS UNIT II  VALUE ENGINEERING
MG 6863- ENGG ECONOMICS UNIT II VALUE ENGINEERINGAsha A
 
Engineering economics
Engineering economicsEngineering economics
Engineering economicsDeepak Kumar
 
Intro to engineering economy
Intro to engineering economyIntro to engineering economy
Intro to engineering economyKwesi Kissiedu
 
Chapter 5 present worth analysis -with examples
Chapter 5   present worth analysis -with examplesChapter 5   present worth analysis -with examples
Chapter 5 present worth analysis -with examplesAbdulaziz AlSuwaidi
 
Chapter 5 present worth analysis -with examples
Chapter 5   present worth analysis -with examplesChapter 5   present worth analysis -with examples
Chapter 5 present worth analysis -with examplesAbdulaziz AlSuwaidi
 
Introduction to Engineering economics
Introduction to Engineering economicsIntroduction to Engineering economics
Introduction to Engineering economicsDr. C.V. Suresh Babu
 
Replacement analysis importance and application
Replacement analysis importance and applicationReplacement analysis importance and application
Replacement analysis importance and applicationabdus sobhan
 
8. Rate of return analysis
8. Rate of return analysis8. Rate of return analysis
8. Rate of return analysisMohsin Siddique
 
7. annual cash flow analysis
7. annual cash flow analysis7. annual cash flow analysis
7. annual cash flow analysisMohsin Siddique
 
Introduction to Engineering Economics Unit I MG6863
Introduction to Engineering Economics  Unit I MG6863Introduction to Engineering Economics  Unit I MG6863
Introduction to Engineering Economics Unit I MG6863Balamurugan Subburaj
 
Introduction to Engineering Economics
Introduction to Engineering EconomicsIntroduction to Engineering Economics
Introduction to Engineering EconomicsPrabu U
 
Cost and cost concepts (Engineering Economics and Management)
Cost and cost concepts (Engineering Economics and Management)Cost and cost concepts (Engineering Economics and Management)
Cost and cost concepts (Engineering Economics and Management)Shail Nakum
 
Annuities and gradient
Annuities and gradientAnnuities and gradient
Annuities and gradientReyman Solas
 
MG 6863 Unit III cash flow
MG 6863 Unit III cash flowMG 6863 Unit III cash flow
MG 6863 Unit III cash flowAsha A
 
MG 6863 FORMULA SHEET ENGINEERING ECONOMICS
MG 6863  FORMULA SHEET ENGINEERING ECONOMICSMG 6863  FORMULA SHEET ENGINEERING ECONOMICS
MG 6863 FORMULA SHEET ENGINEERING ECONOMICSAsha A
 
Engineering economics formula sheet
Engineering economics formula sheetEngineering economics formula sheet
Engineering economics formula sheetHaris Hassan
 
introduction to engineering economy
introduction to engineering economy   introduction to engineering economy
introduction to engineering economy Sebghatullah Karimi
 

La actualidad más candente (20)

Engineering costs and cost estimating
Engineering costs and cost estimatingEngineering costs and cost estimating
Engineering costs and cost estimating
 
MG 6863- ENGG ECONOMICS UNIT II VALUE ENGINEERING
 MG 6863- ENGG ECONOMICS UNIT II  VALUE ENGINEERING MG 6863- ENGG ECONOMICS UNIT II  VALUE ENGINEERING
MG 6863- ENGG ECONOMICS UNIT II VALUE ENGINEERING
 
6.2 cash flow - time diagrams
6.2 cash flow - time diagrams6.2 cash flow - time diagrams
6.2 cash flow - time diagrams
 
Engineering economics
Engineering economicsEngineering economics
Engineering economics
 
Intro to engineering economy
Intro to engineering economyIntro to engineering economy
Intro to engineering economy
 
Chapter 5 present worth analysis -with examples
Chapter 5   present worth analysis -with examplesChapter 5   present worth analysis -with examples
Chapter 5 present worth analysis -with examples
 
Chapter 5 present worth analysis -with examples
Chapter 5   present worth analysis -with examplesChapter 5   present worth analysis -with examples
Chapter 5 present worth analysis -with examples
 
Introduction to Engineering economics
Introduction to Engineering economicsIntroduction to Engineering economics
Introduction to Engineering economics
 
Unit 3 ppt
Unit 3 pptUnit 3 ppt
Unit 3 ppt
 
Replacement analysis importance and application
Replacement analysis importance and applicationReplacement analysis importance and application
Replacement analysis importance and application
 
8. Rate of return analysis
8. Rate of return analysis8. Rate of return analysis
8. Rate of return analysis
 
7. annual cash flow analysis
7. annual cash flow analysis7. annual cash flow analysis
7. annual cash flow analysis
 
Introduction to Engineering Economics Unit I MG6863
Introduction to Engineering Economics  Unit I MG6863Introduction to Engineering Economics  Unit I MG6863
Introduction to Engineering Economics Unit I MG6863
 
Introduction to Engineering Economics
Introduction to Engineering EconomicsIntroduction to Engineering Economics
Introduction to Engineering Economics
 
Cost and cost concepts (Engineering Economics and Management)
Cost and cost concepts (Engineering Economics and Management)Cost and cost concepts (Engineering Economics and Management)
Cost and cost concepts (Engineering Economics and Management)
 
Annuities and gradient
Annuities and gradientAnnuities and gradient
Annuities and gradient
 
MG 6863 Unit III cash flow
MG 6863 Unit III cash flowMG 6863 Unit III cash flow
MG 6863 Unit III cash flow
 
MG 6863 FORMULA SHEET ENGINEERING ECONOMICS
MG 6863  FORMULA SHEET ENGINEERING ECONOMICSMG 6863  FORMULA SHEET ENGINEERING ECONOMICS
MG 6863 FORMULA SHEET ENGINEERING ECONOMICS
 
Engineering economics formula sheet
Engineering economics formula sheetEngineering economics formula sheet
Engineering economics formula sheet
 
introduction to engineering economy
introduction to engineering economy   introduction to engineering economy
introduction to engineering economy
 

Similar a Cash Flow - Unit III Engineering Economics - MG6863

Eit orginal
Eit orginalEit orginal
Eit orginalanamsini
 
Eit orginal
Eit orginalEit orginal
Eit orginalanamsini
 
Systematic Economic Analysis Technique for analysis
Systematic Economic Analysis Technique for analysisSystematic Economic Analysis Technique for analysis
Systematic Economic Analysis Technique for analysisNaganna Chetty
 
PPE Depreciation in Financial Accounting
PPE Depreciation in Financial AccountingPPE Depreciation in Financial Accounting
PPE Depreciation in Financial AccountingRiri Ariyanty
 
Acc week 6
Acc week 6Acc week 6
Acc week 6Shu Shin
 
Chapter 13 breakeven analysis
Chapter 13   breakeven analysisChapter 13   breakeven analysis
Chapter 13 breakeven analysisBich Lien Pham
 
Chapter 13 breakeven analysis
Chapter 13   breakeven analysisChapter 13   breakeven analysis
Chapter 13 breakeven analysisBich Lien Pham
 
Chapter 18 - Sensitivity Analysis.pdf
Chapter 18 - Sensitivity Analysis.pdfChapter 18 - Sensitivity Analysis.pdf
Chapter 18 - Sensitivity Analysis.pdf18010YeashRahman
 
9. benefit cost analysis
9. benefit cost analysis9. benefit cost analysis
9. benefit cost analysisMohsin Siddique
 
9 150316005537-conversion-gate01
9 150316005537-conversion-gate019 150316005537-conversion-gate01
9 150316005537-conversion-gate01abidiqbal55
 
Depreciation-3.pptx
Depreciation-3.pptxDepreciation-3.pptx
Depreciation-3.pptxYasirIdrees4
 
Present Worth Method.pdf
Present Worth Method.pdfPresent Worth Method.pdf
Present Worth Method.pdfAsimShehzad28
 
7 150316005526-conversion-gate01
7 150316005526-conversion-gate017 150316005526-conversion-gate01
7 150316005526-conversion-gate01abidiqbal55
 

Similar a Cash Flow - Unit III Engineering Economics - MG6863 (20)

Eit orginal
Eit orginalEit orginal
Eit orginal
 
Eit orginal
Eit orginalEit orginal
Eit orginal
 
7.1 present worth method
7.1 present worth method7.1 present worth method
7.1 present worth method
 
Chap. 6.pptx
Chap. 6.pptxChap. 6.pptx
Chap. 6.pptx
 
Systematic Economic Analysis Technique for analysis
Systematic Economic Analysis Technique for analysisSystematic Economic Analysis Technique for analysis
Systematic Economic Analysis Technique for analysis
 
chap8.pdf
chap8.pdfchap8.pdf
chap8.pdf
 
unit 4.pdf
unit 4.pdfunit 4.pdf
unit 4.pdf
 
theoty x and y
theoty x and ytheoty x and y
theoty x and y
 
Chap6
Chap6Chap6
Chap6
 
PPE Depreciation in Financial Accounting
PPE Depreciation in Financial AccountingPPE Depreciation in Financial Accounting
PPE Depreciation in Financial Accounting
 
Acc week 6
Acc week 6Acc week 6
Acc week 6
 
Chapter 13 breakeven analysis
Chapter 13   breakeven analysisChapter 13   breakeven analysis
Chapter 13 breakeven analysis
 
Chapter 13 breakeven analysis
Chapter 13   breakeven analysisChapter 13   breakeven analysis
Chapter 13 breakeven analysis
 
Chapter 18 - Sensitivity Analysis.pdf
Chapter 18 - Sensitivity Analysis.pdfChapter 18 - Sensitivity Analysis.pdf
Chapter 18 - Sensitivity Analysis.pdf
 
Nce603 mod unit3
Nce603 mod unit3Nce603 mod unit3
Nce603 mod unit3
 
9. benefit cost analysis
9. benefit cost analysis9. benefit cost analysis
9. benefit cost analysis
 
9 150316005537-conversion-gate01
9 150316005537-conversion-gate019 150316005537-conversion-gate01
9 150316005537-conversion-gate01
 
Depreciation-3.pptx
Depreciation-3.pptxDepreciation-3.pptx
Depreciation-3.pptx
 
Present Worth Method.pdf
Present Worth Method.pdfPresent Worth Method.pdf
Present Worth Method.pdf
 
7 150316005526-conversion-gate01
7 150316005526-conversion-gate017 150316005526-conversion-gate01
7 150316005526-conversion-gate01
 

Más de Balamurugan Subburaj

CELLULAR MANUFACTURING & FLEXIBLE MANUFACTURING SYSTEM - UNIT 5 - CAD & M
CELLULAR MANUFACTURING & FLEXIBLE MANUFACTURING SYSTEM - UNIT 5 - CAD & MCELLULAR MANUFACTURING & FLEXIBLE MANUFACTURING SYSTEM - UNIT 5 - CAD & M
CELLULAR MANUFACTURING & FLEXIBLE MANUFACTURING SYSTEM - UNIT 5 - CAD & MBalamurugan Subburaj
 
FUNDAMENTALS OF CNC & PART PROGRAMMING - UNIT - 4 CAD&M
FUNDAMENTALS OF CNC & PART PROGRAMMING - UNIT - 4 CAD&MFUNDAMENTALS OF CNC & PART PROGRAMMING - UNIT - 4 CAD&M
FUNDAMENTALS OF CNC & PART PROGRAMMING - UNIT - 4 CAD&MBalamurugan Subburaj
 
INTRODUCTION TO COMPUTER AIDED DESIGN & MANUFACTURING
INTRODUCTION TO COMPUTER AIDED DESIGN & MANUFACTURINGINTRODUCTION TO COMPUTER AIDED DESIGN & MANUFACTURING
INTRODUCTION TO COMPUTER AIDED DESIGN & MANUFACTURINGBalamurugan Subburaj
 
Energy, economic and environmental issues of power plants
Energy, economic and environmental issues of power plantsEnergy, economic and environmental issues of power plants
Energy, economic and environmental issues of power plantsBalamurugan Subburaj
 
DIESEL, GAS TURBINE & COMBINED CYCLE POWER PLANTS UNIT III
DIESEL, GAS TURBINE & COMBINED CYCLE POWER PLANTS UNIT IIIDIESEL, GAS TURBINE & COMBINED CYCLE POWER PLANTS UNIT III
DIESEL, GAS TURBINE & COMBINED CYCLE POWER PLANTS UNIT IIIBalamurugan Subburaj
 
COAL BASED POWER PLANT UNIT 1 - POWER PLANT ENGINEERING
COAL BASED POWER PLANT UNIT 1 - POWER PLANT ENGINEERINGCOAL BASED POWER PLANT UNIT 1 - POWER PLANT ENGINEERING
COAL BASED POWER PLANT UNIT 1 - POWER PLANT ENGINEERINGBalamurugan Subburaj
 
Replacement & Maintenance Analysis Unit IV MG 6863
Replacement & Maintenance Analysis Unit IV MG 6863Replacement & Maintenance Analysis Unit IV MG 6863
Replacement & Maintenance Analysis Unit IV MG 6863Balamurugan Subburaj
 

Más de Balamurugan Subburaj (18)

CAD STANDARDS
CAD STANDARDSCAD STANDARDS
CAD STANDARDS
 
CELLULAR MANUFACTURING & FLEXIBLE MANUFACTURING SYSTEM - UNIT 5 - CAD & M
CELLULAR MANUFACTURING & FLEXIBLE MANUFACTURING SYSTEM - UNIT 5 - CAD & MCELLULAR MANUFACTURING & FLEXIBLE MANUFACTURING SYSTEM - UNIT 5 - CAD & M
CELLULAR MANUFACTURING & FLEXIBLE MANUFACTURING SYSTEM - UNIT 5 - CAD & M
 
FUNDAMENTALS OF CNC & PART PROGRAMMING - UNIT - 4 CAD&M
FUNDAMENTALS OF CNC & PART PROGRAMMING - UNIT - 4 CAD&MFUNDAMENTALS OF CNC & PART PROGRAMMING - UNIT - 4 CAD&M
FUNDAMENTALS OF CNC & PART PROGRAMMING - UNIT - 4 CAD&M
 
GEOMETRIC MODELING
GEOMETRIC MODELINGGEOMETRIC MODELING
GEOMETRIC MODELING
 
INTRODUCTION TO COMPUTER AIDED DESIGN & MANUFACTURING
INTRODUCTION TO COMPUTER AIDED DESIGN & MANUFACTURINGINTRODUCTION TO COMPUTER AIDED DESIGN & MANUFACTURING
INTRODUCTION TO COMPUTER AIDED DESIGN & MANUFACTURING
 
Manufacture of plastic components
Manufacture of plastic componentsManufacture of plastic components
Manufacture of plastic components
 
Sheet metal processes
Sheet metal processesSheet metal processes
Sheet metal processes
 
METAL FORMING PROCESS
METAL FORMING PROCESSMETAL FORMING PROCESS
METAL FORMING PROCESS
 
Welding - Joining Processes
Welding - Joining ProcessesWelding - Joining Processes
Welding - Joining Processes
 
METAL CASTING PROCESSES
METAL CASTING PROCESSESMETAL CASTING PROCESSES
METAL CASTING PROCESSES
 
Energy, economic and environmental issues of power plants
Energy, economic and environmental issues of power plantsEnergy, economic and environmental issues of power plants
Energy, economic and environmental issues of power plants
 
Power from renewable energy
Power from renewable energyPower from renewable energy
Power from renewable energy
 
NUCLEAR POWER PLANT
NUCLEAR POWER PLANTNUCLEAR POWER PLANT
NUCLEAR POWER PLANT
 
DIESEL, GAS TURBINE & COMBINED CYCLE POWER PLANTS UNIT III
DIESEL, GAS TURBINE & COMBINED CYCLE POWER PLANTS UNIT IIIDIESEL, GAS TURBINE & COMBINED CYCLE POWER PLANTS UNIT III
DIESEL, GAS TURBINE & COMBINED CYCLE POWER PLANTS UNIT III
 
COAL BASED POWER PLANT UNIT 1 - POWER PLANT ENGINEERING
COAL BASED POWER PLANT UNIT 1 - POWER PLANT ENGINEERINGCOAL BASED POWER PLANT UNIT 1 - POWER PLANT ENGINEERING
COAL BASED POWER PLANT UNIT 1 - POWER PLANT ENGINEERING
 
DEPRECIATION - UNIT V- MG6863
DEPRECIATION - UNIT V- MG6863DEPRECIATION - UNIT V- MG6863
DEPRECIATION - UNIT V- MG6863
 
Replacement & Maintenance Analysis Unit IV MG 6863
Replacement & Maintenance Analysis Unit IV MG 6863Replacement & Maintenance Analysis Unit IV MG 6863
Replacement & Maintenance Analysis Unit IV MG 6863
 
Value Engineering Unit 2 MG6863
Value Engineering Unit 2 MG6863Value Engineering Unit 2 MG6863
Value Engineering Unit 2 MG6863
 

Último

Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsKarinaGenton
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfUmakantAnnand
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991RKavithamani
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxRoyAbrique
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppCeline George
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
Micromeritics - Fundamental and Derived Properties of Powders
Micromeritics - Fundamental and Derived Properties of PowdersMicromeritics - Fundamental and Derived Properties of Powders
Micromeritics - Fundamental and Derived Properties of PowdersChitralekhaTherkar
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingTechSoup
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 

Último (20)

Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its Characteristics
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.Compdf
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website App
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Micromeritics - Fundamental and Derived Properties of Powders
Micromeritics - Fundamental and Derived Properties of PowdersMicromeritics - Fundamental and Derived Properties of Powders
Micromeritics - Fundamental and Derived Properties of Powders
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 

Cash Flow - Unit III Engineering Economics - MG6863

  • 1. S.Balamurugan AP/Mech AAA College of Engg. & Tech.2/22/2018 1
  • 2. CASH FLOW CASHFLOW Present Worth Method Revenue Dominated Cash Flow Cost – Dominated Cash Flow Future Worth Method Revenue Dominated Cash Flow Cost – Dominated Cash Flow Annual Equivalent Method Revenue Dominated Cash Flow Cost – Dominated Cash Flow 2/22/2018 S.Balamurugan AP/Mech AAA College of Engg. & Tech. 2
  • 3. 2/22/2018 S.Balamurugan AP/Mech AAA College of Engg. & Tech. 3
  • 4. 2/22/2018 S.Balamurugan AP/Mech AAA College of Engg. & Tech. 4
  • 5. Present Worth Method of Comparison – Revenue Dominated Positive Sign – Profit, Revenue, Salvage Value (Inflows) Negative Sign – Costs (Outflows) • The cash flow of each alternative will reduced to time zero by assuming interest rate i.(Time zero = Present time) • Best alternative will be selected by comparing the present worth amount of alternatives.(Maximum Present Worth) S • R1 R2 R3 R4 Rn i % 0 1 2 3 4 n P Revenue-Dominated Cash Flow Diagram PW(i)= - P + R1[1/(1+i)1]+R2[1/(1+i)2]+..+[Rj[1/(1+i)j]+Rn[1/(1+i)n]+S[1/(1+i)n] S.Balamurugan AP/Mech AAA College of Engg. & Tech.2/22/2018 5
  • 6. Present Worth Method of Comparison – Cost Dominated Positive Sign –Costs (Outflows) Negative Sign – Profit, Revenue, Salvage Value (Inflows) • The cash flow of each alternative will reduced to time zero by assuming interest rate i.(Time zero = Present time) • Best alternative will be selected by comparing the present worth amount of alternatives. (Minimum Present Worth) • P C1 C2 C3 C4 Cn i % n 0 1 2 3 4 Cost-Dominated Cash Flow Diagram S PW(i)= P + C1[1/(1+i)1]+C2[1/(1+i)2]+..+[Cj[1/(1+i)j]+Cn[1/(1+i)n] - S[1/(1+i)n] S.Balamurugan AP/Mech AAA College of Engg. & Tech.2/22/2018 6
  • 7. • Alpha Industry is planning to expand its production operation. It has identified three different technologies for meeting the goal. The initial outlay & annual revenues with respect to each of the technologies are summarized in table. Suggest the best technology which is to be implemented based on the present worth method of comparison assuming 20% interest rate, compounded annually. Present Worth Method of Comparison – Revenue Dominated Positive Sign – Profit, Revenue, Salvage Value (Inflows) Negative Sign – Costs (Outflows) Initial Outlay (Rs.) Annual Revenue (Rs.) Life (years) Technology 1 12,00,000 4,00,000 10 Technology 2 20,00,000 6,00,000 10 Technology 3 18,00,000 5,00,000 10 Technology 1 PW(20%) = -12,00,000 + 4,00,000 × (P/A, 20%, 10) PW(20%) = -12,00,000 + 4,00,000 × (4.1925) PW(20%) = -12,00,000 + 16,77,000 = Rs. 4,77,000 Technology 2 PW(20%) = -20,00,000 + 6,00,000 × (P/A, 20%, 10) PW(20%) = -20,00,000 + 6,00,000 × (4.1925) PW(20%) = -20,00,000 + 25,15,500 = Rs. 5,15,500 Technology 3 PW(20%) = -18,00,000 + 5,00,000 × (P/A, 20%, 10) PW(20%) = -18,00,000 + 5,00,000 × (4.1925) PW(20%) = -18,00,000 + 20,96,250 = Rs. 2,96,250 2/22/2018 S.Balamurugan AP/Mech AAA College of Engg. & Tech. 7
  • 8. Bid Engineer’s Estimates Initial cost (Rs.) Service life (years) Annual operations & Maintenance cost (Rs.) Alpha Elevator Inc. 4,50,000 15 27,000 Beta Elevator Inc. 5,40,000 15 28,500 Present Worth Method of Comparison – Cost Dominated Positive Sign –Costs (Outflows) Negative Sign – Profit, Revenue, Salvage Value (Inflows) An engineer has two bids for an elevator to be installed in a new building. The details of the bids for the elevators are as follows, Determine which bid should be accepted, based on the present worth method of comparison assuming 15% interest rate, compounded annually. Alpha Elevator Inc. PW(15%) = 4,50,000 + 27,000 × (P/A, 15%, 15) PW(15%) = 4,50,000 + 27,000 × (5.8474) PW(15%) = 4,50,000 + 1,57,879.80 = Rs. 6,07,879.80 Beta Elevator Inc. PW(15%) = 5,40,000 + 28,500 × (P/A, 15%, 15) PW(15%) = 5,40,000 + 28,500 × (5.8474) PW(15%) = 5,40,000 + 1,66,650.90 = Rs. 7,06,650.90 Cost dominated cash flow, the bid 1 is less than that of bid 2. Bid 1 is best alternative. 2/22/2018 S.Balamurugan AP/Mech AAA College of Engg. & Tech. 8
  • 9. • Consider the following two mutually exclusive alternatives: At i = 18%, select the best alternative based on future worth method of comparison. Future Worth Method of Comparison – Revenue Dominated Positive Sign – Profit, Revenue, Salvage Value (Inflows) Negative Sign – Costs (Outflows) Alternative A FW(18%) = -50,00,000(F/P, 18%, 4) + 20,00,000 × (F/A, 18%, 4) FW(18%) = -50,00,000(1.939) + 20,00,000 × (5.215) FW(18%) = Rs. 7,35,000 Alternative B FW(18%) = -45,00,000(F/P, 18%, 4) + 18,00,000 × (F/A, 18%, 4) FW(18%) = -45,00,000(1.939) + 18,00,000 × (5.215) FW(18%) = Rs. 6,61,500 End of Year Alternative 0 1 2 3 4 A (Rs.) -50,00,000 20,00,000 20,00,000 20,00,000 20,00,000 B (Rs.) -45,00,000 18,00,000 18,00,000 18,00,000 18,00,000 Revenue dominated cash flow, the Alternative A is more than that of Alternative B. Alternative A is best alternative. 2/22/2018 S.Balamurugan AP/Mech AAA College of Engg. & Tech. 9
  • 10. Machine A Machine B Initial cost (Rs.) Rs. 4,00,000 Rs. 8,00,000 Useful life (years) 4 4 Salvage value at the end of machine life Rs. 2,00,000 Rs. 5,50,000 Annual maintenance cost Rs. 40,000 0 Future Worth Method of Comparison – Cost Dominated Positive Sign –Costs (Outflows) Negative Sign – Profit, Revenue, Salvage Value (Inflows) A company must decide whether to buy machine A or machine B: At 12% interest rate, which machine should be selected? Use future worth method of comparison. Machine A FW(12%) = 4,00,000 (F/P, 12%, 4) + 40,000 × (F/A, 12%, 4) – 2,00,000 FW(12%) = 4,00,000 (1.574) + 40,000 × (4.779) – 2,00,000 FW(12%) = Rs. 6,20,760 Machine B FW(12%) = 8,00,000 (F/P, 12%, 4) – 5,50,000 FW(12%) = 8,00,000 (1.574) – 5,50,000 FW(12%) = Rs. 7,09,200 Cost dominated cash flow, the machine A is less than that of machine B. machine A is best alternative. 2/22/2018 S.Balamurugan AP/Mech AAA College of Engg. & Tech. 10
  • 11. • A company invests in one of the two mutually exclusive alternatives. The life of both alternatives is estimated to be 5 years with the following investments, annual returns and salvage values. Determine the best alternative based on the annual equivalent method by assuming i = 25% Annual Equivalent Method of Comparison – Revenue Dominated Positive Sign – Profit, Revenue, Salvage Value (Inflows) Negative Sign – Costs (Outflows) Alternative A AEA(25%) = - 1,50,000(A/P, 25%, 5) + 60,000 + 15,000 × (A/F, 25%, 5) AEA(25%) = - 1,50,000(0.3718) + 60,000 + 15,000 × (0.1218) AEA(25%) = Rs. 6,057 Alternative B AEA(25%) = - 1,75,000(A/P, 25%, 5) + 70,000 + 35,000 × (A/F, 25%, 5) AEA(25%) = - 1,75,000(0.3718) + 70,000 + 35,000 × (0.1218) AEA(25%) = Rs. 9,198 Revenue dominated cash flow, the Alternative B is more than that of Alternative A. Alternative B is best alternative. Alternative A B Investment (Rs.) 1,50,000 1,75,000 Annual equal return (Rs.) 60,000 70,000 Salvage value (Rs.) 15,000 35,000 2/22/2018 S.Balamurugan AP/Mech AAA College of Engg. & Tech. 11
  • 12. Around the lake Under the lake Length 15 km 5 km First cost (Rs.) 1,50,000 / km 7,50,000 / km Useful life (years) 15 15 Maintenance cost (Rs.) 6,000 / km / yr 12,000 / km / yr Salvage value (Rs.) 90,000 / km 1,50,000 / km Yearly power loss (Rs.) 15,000 / km 15,000 / km Annual Equivalent Method of Comparison– Cost Dominated Positive Sign –Costs (Outflows) Negative Sign – Profit, Revenue, Salvage Value (Inflows) Two possible routes for laying a power line are under study. Data on the routes are as follows: If 15% interest is used, should the power line be routed around the lake or under the lake? Around the lake – Alternative 1 First cost = 1,50,000 × 15 = Rs.22,50,000 Maintenance cost / yr = 6,000 × 15 = Rs. 90,000 Power loss/yr = 15,000 × 15 = Rs.2,25,000 Maintenance cost & power loss / yr = Rs.90,000 + Rs.2,25,000 = Rs.3,15,000 Salvage value = 90,000 × 15 = Rs.13,50,000 Under the lake – Alternative 2 First cost = 7,50,000 × 5 = Rs.37,50,000 Maintenance cost / yr = 12,000 × 5 = Rs. 60,000 Power loss/yr = 15,000 × 5 = Rs.75,000 Maintenance cost & power loss / yr = Rs.60,000 + Rs.75,000 = Rs.1,35,000 Salvage value = 1,50,000 × 5 = Rs.7,50,000 2/22/2018 S.Balamurugan AP/Mech AAA College of Engg. & Tech. 12
  • 13. Around the lake – Alternative 1 AE(15%) = 22,50,000(A/P, 15%, 15) + 3,15,000 – 13,50,000 × (A/F, 15%, 15) AE(15%) = 22,50,000(0.1710) + 3,15,000 – 13,50,000 × (0.0210) AE(15%) = Rs. 6,71,400 Under the lake – Alternative 2 AE(15%) = 37,50,000(A/P, 15%, 15) + 1,35,000 – 7,50,000 × (A/F, 15%, 15) AE(15%) = 37,50,000(0.1710) + 1,35,000 – 7,50,000 × (0.0210) AE(15%) = Rs. 7,60,500 Around the lake – Alternative 1 First cost = 1,50,000 × 15 = Rs.22,50,000 Maintenance cost / yr = 6,000 × 15 = Rs. 90,000 Power loss/yr = 15,000 × 15 = Rs.2,25,000 Maintenance cost & power loss / yr = Rs.90,000 + Rs.2,25,000 = Rs.3,15,000 Salvage value = 90,000 × 15 = Rs.13,50,000 Under the lake – Alternative 2 First cost = 7,50,000 × 5 = Rs.37,50,000 Maintenance cost / yr = 12,000 × 5 = Rs. 60,000 Power loss/yr = 15,000 × 5 = Rs.75,000 Maintenance cost & power loss / yr = Rs.60,000 + Rs.75,000 = Rs.1,35,000 Salvage value = 1,50,000 × 5 = Rs.7,50,000 Annual Equivalent Method of Comparison– Cost Dominated Cost dominated cash flow, the Alternative 1 is less than that of Alternative 2. Alternative 1 is best alternative. 2/22/2018 S.Balamurugan AP/Mech AAA College of Engg. & Tech. 13
  • 14. Rate of Return Method The rate of return of a cash flow pattern is the interest rate at which the present worth of that cash flow pattern reduces to zero. Applications of Rate of Return method • Useful for making investment decision. • Ratios typically used by financial analysts to compare a company’s performance over time or compare performance between companies. • In capital budgeting process, companies would traditionally compare the internal rate of return of different projects to decide which projects to pursue in order to maximize the return. 2/22/2018 S.Balamurugan AP/Mech AAA College of Engg. & Tech. 14
  • 15. • A company is planning to expand its present business activity. It has two alternatives for the expansion programme and the corresponding cash flows are tabulated below. Each alternative has a life of five years and a negligible salvage value. The minimum attractive rate of return for the company is 12%. Suggest the best alternative to the company. Alternative 1 Net present Worth PW(i) = - 5,00,000 + 1,70,000 (P/A, i, 5) Rate of Return Method Initial Investment (Rs.) Yearly revenue (Rs.) Alternative 1 5,00,000 1,70,000 Alternative 2 8,00,000 2,70,000 i = 15 %, PW(15%) = - 5,00,000 + 1,70,000 (P/A, 15%, 5) = - 5,00,000 + 1,70,000 (3.3522) = Rs. 69,874 i = 17 %, PW(17%) = - 5,00,000 + 1,70,000 (P/A, 17%, 5) = - 5,00,000 + 1,70,000 (3.1993) = Rs. 43,881 i = 20 %, PW(20%) = - 5,00,000 + 1,70,000 (P/A, 20%, 5) = - 5,00,000 + 1,70,000 (2.9906) = Rs. 8,402 i = 22 %, PW(22%) = - 5,00,000 + 1,70,000 (P/A, 22%, 5) = - 5,00,000 + 1,70,000 (2.8636) = Rs. - 13,188 Interpolation X1 = 20%, X2 = 22%, X =? Y1 = 8402, Y2 = -13,188, Y = 0 𝑋 − 𝑋1 𝑋2 − 𝑋1 = 𝑌 − 𝑌1 𝑌2 − 𝑌1 𝑋 − 20 22 − 20 = 0 − 8402 −13188 − 8402 X – 20 = (0.3892) (2) Rate of Return X = 20.78 %2/22/2018 S.Balamurugan AP/Mech AAA College of Engg. & Tech. 15
  • 16. • A company is planning to expand its present business activity. It has two alternatives for the expansion programme and the corresponding cash flows are tabulated below. Each alternative has a life of five years and a negligible salvage value. The minimum attractive rate of return for the company is 12%. Suggest the best alternative to the company. Alternative 2 Net present Worth PW(i) = - 8,00,000 + 2,70,000 (P/A, i, 5) Rate of Return Method Initial Investment (Rs.) Yearly revenue (Rs.) Alternative 1 5,00,000 1,70,000 Alternative 2 8,00,000 2,70,000 i = 20 %, PW(20%) = - 8,00,000 + 2,70,000 (P/A, 20%, 5) = - 8,00,000 + 2,70,000 (2.9906) = Rs. 7,462 i = 22 %, PW(22%) = - 8,00,000 + 2,70,000 (P/A, 22%, 5) = - 8,00,000 + 2,70,000 (2.8636) = Rs. - 26,828 Interpolation X1 = 20%, X2 = 22%, X =? Y1 = 7462, Y2 = -26,828, Y = 0 𝑋 − 𝑋1 𝑋2 − 𝑋1 = 𝑌 − 𝑌1 𝑌2 − 𝑌1 𝑋 − 20 22 − 20 = 0 − 7462 −26828 − 7462 X – 20 = (0.2175) (2) Rate of Return X = 20.435 % The rate of return of alternative 1 is greater than that of the alternative 2, So select alternative 1. 2/22/2018 S.Balamurugan AP/Mech AAA College of Engg. & Tech. 16
  • 17. Skimming Price Policy • Price skimming is a pricing strategy in which a marketer sets a relatively high initial price for a product or service at first, and then lowers the price over time. • It allows the firm to recover its sunk costs quickly before competition steps in and lowers the market price. 2/22/2018 S.Balamurugan AP/Mech AAA College of Engg. & Tech. 17