I-40/I-77 Work Zone Traffic Control Presentation 3-23-2012
1. Work Zone Traffic Control
I-3819A
I-40 from west of US 21 to east of I-77
Statesville
2. Work Zone Traffic Control
Overview of the Project
General Traffic Patterns During Construction
Road Closures and Detours
Lane Closure Restrictions
Median Crossover Restrictions
Holiday Restrictions
Stopping Traffic
Questions/Discussion
4. General Traffic Patterns During Construction
- Minimum two lanes in each direction on I-40, I-77 & US 21
during time restrictions
- Multiple traffic shifts throughout construction life:
- I-40: throughout the project length
- I-77: just north of existing bridges over I-40
- US 21: Upon completion of US 21 widening, traffic
will be in a one thru lane/one left-turn lane
pattern each way for up to 90 days until final
pattern is open.
19. Off-Site Detour for Ramp C Closure
(I-40E to I-77S) (72 Consecutive Hours)
C
Both ramps closed
simultaneously
20. Lane Closure Restrictions
I-40 & I-77
Monday to Friday: 6 a.m. to 8 p.m.
Saturday & Sunday: 8 a.m. to 9 p.m.
US 21
Monday to Friday: 7 a.m. to 9 p.m.
Saturday & Sunday: 9 a.m. to 8 p.m.
US 64 (Davie Ave.)
Monday to Friday: 7 a.m. to 7 p.m.
Glenway Drive
Monday to Friday: 7 a.m. to 9 p.m.
Saturday & Sunday: 8 a.m. to 9 p.m.
21. Median Crossover Restrictions
I-40 at Radio Road Overpass
Monday to Friday: 6 a.m. to 8 p.m.
Saturday & Sunday: 8 a.m. to 9 p.m.
During crossover operation, traffic will be
reduced to one travel lane in each direction
on one side of I-40 with barrier dividing
traffic directions.
22. Holidays & Events
New Year’s
Easter
Memorial Day
Independence Day
Labor Day
Thanksgiving
Christmas
NASCAR Races in Charlotte
23. Stopping Traffic
Contractor will be allowed to stop traffic for 30
minutes for Traffic Operations (shifts, tie-ins,
etc.) outside the following time restrictions:
I-40: 5 a.m. to 12:00 midnight, Monday to Sunday
I-77: 4 a.m. to 12:00 midnight, Monday to Sunday
US 21: 5 a.m. to 12:00 midnight, Monday to Thursday
5 a.m. Friday to 12:00 midnight Sunday
For overhead structure work, 60 minutes
stoppage time will be allowed on US 21 using
the above restrictions.