Drilling the Tune field with potassium formate brine
1. Tune Case (NH)
Experience from Drilling and
Completion using formate based fluids
Drilling & Completion Fluid Seminar, Aberdeen 03.06.24
By Atle Nottveit, Manager Well Completion
2. Agenda – 03.06.24
Tune Field Information
Mud and completion fluids criteria
Fluids alternative
Drilling and completion experience
3. %[
%[
&
%[
%[
$Z $Z$Z
$Z
$Z
$Z
$T
$T
$T
Tune Field data
Location
Block 30/8
ca. 130 km northwest of Bergen
10km west of Oseberg Field Centre
Fluids
Gas/ condensate @ 525 bar, 131 o
C
Production strategy
Pure gas depletion
Reserves
Gas
– 22.9 GSm3 Phase1
– (27.1 GSm3 incl. Phase 2 &3)
Condensate:
– 5.8 MSm3 Phase 1
– (7.0 MSm3 incl. Phase 2&3)
Producers: 4 ( +1+1 Phase 2&3)
Sub sea template, tie-in Oseberg Field
Centre
2 x 11 km 11.5” Carbon pipelines
Oseberg
Tune
Oseberg Sør
Brage
Field Centre/
OSA/OSB/OSD
OSC
Oseberg Øst
5. Fluids criteria
Drillability
MW = 1.65sg
Open hole completion
Minimum formation damage
Avoid plugging of sand screens
Fluid loss control, while running sand screen
Same type of fluid both for drilling and
completion
Limitation of pit capacity at rigsite
(Deep Sea Delta)
6. Fluid alternatives
Alternative #1
OBM as drilling fluid and run sand screen in same.
Alternative #2
OBM as drilling fluid. Run screen through OBM with
LSOBM (Low solids oil based mud) in open hole.
Alternative #3
Formpro (Potassium formate) RDIF as drilling fluid and
run screen in same.
Alternative #4
Formpro (Potassium/Cesium formate) RDIF as drilling
fluid and run screen in same.
7. Fluid alternatives
Alternative #3 chosen, but during drilling,
well clean up was delayed from 2-3 weeks
until 1 year.
Well A 14 an A 11 was therefore completed in
Potassium/Cesium Formate based Formpro.
Well A 12 AH displaced to Potassium/Cesium
formate based Formpro in reservoir section after 7
months.
A 13 only well left with Potassium Formate based
Formpro.