SlideShare una empresa de Scribd logo
1 de 26
Manish Purwar, iZenBridge
   Understanding Earned Value Management
   Calculating To-Complete Performance Index (TCPI)
   Budget forecasting
   Budget variance analysis
   Understanding of Earn Value Management concepts
   Will help in managing projects better in real life
   Will help in solving ~10 questions in PMP exam
   Earned Value Management (EVM) is a project management
    system that combines schedule performance and cost
    performance to answer the question,
        “What did we get for the money we spent?”
   It measures project performance against the project
    baselines. It results from an earned value analysis indicating
    potential deviation of the project from the cost and/or
    schedule baseline.
   It is used to figure out how well project needs
    to perform in the future in order to stay on
    budget.
   Use the information you have about the project right now to
    predict how close it will come to its goals if it keeps going the
    way it has been.
   Throughout your project, you are looking at
    how you are doing as compared to your plan.
    The variance between planned and actual
    performance needs to be carefully analyzed
    to figure out budget or schedule related
    issues.
   Planned Value : The percentage of total
    budget that you are supposed to have earned
    so far.
   BAC (Budget At Completion)
    ◦ It is total budget you have for your project.
   Planned Value
    ◦ Budget you planned on using so far
    ◦ PV = BAC x Planned % Complete
    If BAC is $100,000 and planned % complete is
      30%, then Planned Value is : $100,000 x 30% =
      $30,000
   Earn Value tells you how much your project
    actually earned.
   EV = BAC x Actual % complete
   If BAC is $100,000 and actual % complete is 25%,
    then Earned Value is : $100,000 x 25% = $25,000
   Schedule Performance Index (SPI) = EV / PV
       If SPI > 1 means Earned Value is greater than Planned value so project is
        ahead of schedule
       If SPI < 1 means Earned Value is less than Planned Value so project is
        behind of schedule
   Schedule Variance (SV) = EV – PV
       If SV is positive means EV > PV and it tells you how many dollars you are
        ahead of schedule.
       If SV is negative means EV < PV and it tells you how many dollars you are
        behind schedule.

   Total budget of project is $10,000 and you are halfway through schedule. It
    seems you have only gotten 40% of actual work done.
   What is PV, EV, SPI and SV?
   Is project ahead or behind of schedule?

   Recap : PV = BAC x Planned % Complete, EV = BAC x Actual % complete
   Actual Cost (AC) is the amount of money spent so far on the project.

   Cost Performance Index (CPI) = EV / AC
       If CPI > 1 means Earned Value is greater than Actual Cost so project is under
          budget
       If CPI < 1 means Earned Value is less than Actual Cost so project is over budget
   Cost Variance (CV) = EV – AC
       If CV is positive means EV > AC and it tells you how many dollars you are under
          budget.
       If CV is negative means EV < AC and it tells you how many dollars you are over
          budget.

   Total budget of project is $10,000 and you are halfway through schedule. It seems you
    have only gotten 40% of actual work done. You have spend $6000 so far.
   What is PV, EV, CPI and CV?
   Is project over or under budget?

   Recap : PV = BAC x Planned % Complete, EV = BAC x Actual % complete
   Forecasting is predicting what your project will look like when
    it’s at completion.

   Estimate At Completion (EAC) is Predicting total cost when
    project is complete.
   EAC = BAC / CPI
    ◦ If CPI < 1 mean project is over budget and will give EAC >
      current budget.
    ◦ If CPI > 1 mean project is under budget and will give EAC <
      current budget.

    If CPI is 0.8 and total budget is $10,000, then what will be
    Estimate At Completion (EAC)?
   Estimate To Complete (ETC) is how much more money will be
    spend on project completion.
    ◦ ETC = EAC – AC
   Variance At Completion (VAC) predicts what your budget
    variance will be when the project is complete.
    ◦ VAC = BAC – EAC
    ◦ If you will spend more than your budget, variance will be
      negative.




                                                 BAC
              PV
                                                       EAC
              AC                  ETC
   TCPI represents a target that your CPI would have to hit to meet
    forecasted completion cost.
    ◦ TCPI when you are trying to get your project within your original
      budget,
       TCPI = (BAC – EV) / (BAC – AC) i.e. left Budgeted work / left
        budgeted money
    ◦ TCPI when you are trying to get your project done within Estimate
      At Completion (EAC),
       TCPI = (BAC – EV) / (EAC – AC) i.e. left budgeted work / left
        estimated money

   Higher TCPI means left budgeted work > left budgeted (or
    estimated) money so it’s time to take strict cost management
    approach.
   Lower TCPI means left budgeted work < left budgeted (or estimated)
    money so you are well with in your budget.
   Actual value at any given time of the project
    minus all of the costs associated with it.
   Managers calculate this number to see if it’s
    worth doing a project. Managers select
    project with greatest NPV.

   If Project A will take 3 years to complete and
    has an NPV of $50,000. Project B will take 6
    years to complete and has an NPV of
    $90,000. Which one would you prefer?
   IRR is interest rate at which project inflows
    (revenues) and project outflows (costs) are
    equal.
   If company has more than one project to
    select, project with highest IRR are selected
    for implementation.
   The number of time periods it takes to
    recover your investment in the project before
    you start accumulating profit.

   You have two projects to choose from, Project
    A with a payback period of six months or
    Project B with a payback period of 18 months.
    Which one would you prefer?
   It is ratio of Benefit (i.e. revenue in this case)
    to Cost.
   BCR > 1 means benefits are greater than
    cost.
   Project with highest BCR is selected for
    implementation.
   Opportunity given up by selecting one project
    over another.

   You have two projects to choose from; Project
    A with an NPV of $50,000 or Project B with an
    NPV of $90,000. What is the opportunity cost
    of selecting project B?
   Net Present Value
   Internal Rate of Return
   Payback period
   Benefit Cost Ratio
Drop us a note. Your
feedbacks are valuable
        to us!
   Provide PMP, Agile & Scrum training
   Provide face to face and online training of PMI-ACP (Agile
    Certified Practitioner) certification program
   Help Organizations in adapting agile
   Helps organizations in setting up project governing office.
   Get training calendar at www.iZenBridge.com
Saket Bansal
Saket.Bansal@iZenBridge.com
M: 9910802561
Web: www.iZenBridge.com
LinkedIn: www.linkedin.com/in/saketbansal
Keep in touch for
more interesting
  & interactive
 presentations
Presentation by –
      Manish Purwar
    Contact Manish at
 Mobile : +91 9910500922
purwar_manish@yahoo.com

Más contenido relacionado

La actualidad más candente

Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value ManagementMansoor Shoaib
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)Harshit Mahajan
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 waleed hamdy
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)Glen Alleman
 
Evaluating Earned Value Management
Evaluating Earned Value ManagementEvaluating Earned Value Management
Evaluating Earned Value ManagementKristine Hejna
 
A simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementA simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementProPM Academy
 
EVM of Project Management...
EVM of Project Management...EVM of Project Management...
EVM of Project Management...Fahad Ali
 
Earned value in five easy pieces
Earned value in five easy piecesEarned value in five easy pieces
Earned value in five easy piecesGlen Alleman
 
Earned value management
Earned value managementEarned value management
Earned value managementAshif AR
 
Earned value management (EVM)
Earned value management (EVM)Earned value management (EVM)
Earned value management (EVM)Joshua Render
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)Ejaz Bhatti
 

La actualidad más candente (20)

Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01
 
Learning pmp formulas the easy way
Learning pmp formulas the easy wayLearning pmp formulas the easy way
Learning pmp formulas the easy way
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)
 
Evaluating Earned Value Management
Evaluating Earned Value ManagementEvaluating Earned Value Management
Evaluating Earned Value Management
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Earned value management
Earned value managementEarned value management
Earned value management
 
A simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementA simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value Management
 
EVM of Project Management...
EVM of Project Management...EVM of Project Management...
EVM of Project Management...
 
Back to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinarBack to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinar
 
Earned value in five easy pieces
Earned value in five easy piecesEarned value in five easy pieces
Earned value in five easy pieces
 
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting
 
Earned value management
Earned value managementEarned value management
Earned value management
 
Project Control Process
Project Control ProcessProject Control Process
Project Control Process
 
Earned value management (EVM)
Earned value management (EVM)Earned value management (EVM)
Earned value management (EVM)
 
Earned Value
Earned ValueEarned Value
Earned Value
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)
 

Destacado

Can I Take The PMP Exam Even If My Title is not Project Manager
Can I Take The PMP Exam Even If My Title is not Project ManagerCan I Take The PMP Exam Even If My Title is not Project Manager
Can I Take The PMP Exam Even If My Title is not Project ManagerOSP International LLC
 
Integrating Risk With Earned Value
Integrating Risk With Earned ValueIntegrating Risk With Earned Value
Integrating Risk With Earned ValueGlen Alleman
 
The 7 Things You Need to Pass the PMI-ACP® Exam
The 7 Things You Need to Pass the PMI-ACP® ExamThe 7 Things You Need to Pass the PMI-ACP® Exam
The 7 Things You Need to Pass the PMI-ACP® ExamOSP International LLC
 
PMI-ACP Exam Study Flashcards sample
PMI-ACP Exam Study Flashcards samplePMI-ACP Exam Study Flashcards sample
PMI-ACP Exam Study Flashcards sampleJoseph Flahiff
 
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...Project Controls Expo
 
Track Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementBaroness PM
 
Earned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlEarned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlM Maged Hegazy, LLM, MBA, CCP, P3O
 
8.project cost management
8.project cost management8.project cost management
8.project cost managementChanwit Julrod
 
Earned Value Reporting
Earned Value ReportingEarned Value Reporting
Earned Value Reportingcfreema7
 
Successfully Integrating Agile and Earned Value
Successfully Integrating Agile and Earned ValueSuccessfully Integrating Agile and Earned Value
Successfully Integrating Agile and Earned ValueGlen Alleman
 

Destacado (14)

Can I Take The PMP Exam Even If My Title is not Project Manager
Can I Take The PMP Exam Even If My Title is not Project ManagerCan I Take The PMP Exam Even If My Title is not Project Manager
Can I Take The PMP Exam Even If My Title is not Project Manager
 
Integrating Risk With Earned Value
Integrating Risk With Earned ValueIntegrating Risk With Earned Value
Integrating Risk With Earned Value
 
The 7 Things You Need to Pass the PMI-ACP® Exam
The 7 Things You Need to Pass the PMI-ACP® ExamThe 7 Things You Need to Pass the PMI-ACP® Exam
The 7 Things You Need to Pass the PMI-ACP® Exam
 
Earned Value fundamentals
Earned Value fundamentalsEarned Value fundamentals
Earned Value fundamentals
 
PMI-ACP Exam Study Flashcards sample
PMI-ACP Exam Study Flashcards samplePMI-ACP Exam Study Flashcards sample
PMI-ACP Exam Study Flashcards sample
 
07 pmp cost management exam
07 pmp cost management exam07 pmp cost management exam
07 pmp cost management exam
 
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
 
Track Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value Management
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
 
Earned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlEarned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project Control
 
8.project cost management
8.project cost management8.project cost management
8.project cost management
 
Earned Value Reporting
Earned Value ReportingEarned Value Reporting
Earned Value Reporting
 
Successfully Integrating Agile and Earned Value
Successfully Integrating Agile and Earned ValueSuccessfully Integrating Agile and Earned Value
Successfully Integrating Agile and Earned Value
 
PMI-ACP Study Guide
PMI-ACP Study GuidePMI-ACP Study Guide
PMI-ACP Study Guide
 

Similar a Earned value for pmp and pmi acp exam

Earned value management
Earned value managementEarned value management
Earned value managementwhizkris
 
Pm 8 cost_management
Pm 8 cost_managementPm 8 cost_management
Pm 8 cost_managementRadiant Minds
 
Pm 8 cost_management
Pm 8 cost_managementPm 8 cost_management
Pm 8 cost_managementRadiant Minds
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.pptProfDrAnbalaganChinn
 
#Measuring Project Performance - Earned Value Management System# By SN Panigrahi
#Measuring Project Performance - Earned Value Management System# By SN Panigrahi#Measuring Project Performance - Earned Value Management System# By SN Panigrahi
#Measuring Project Performance - Earned Value Management System# By SN PanigrahiSN Panigrahi, PMP
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxsagarlesley
 
Your Projects May Be Robbing You Blind
Your Projects May Be Robbing You BlindYour Projects May Be Robbing You Blind
Your Projects May Be Robbing You BlindEd Kozak
 
What Is Earned Value Analysis
What Is Earned Value AnalysisWhat Is Earned Value Analysis
What Is Earned Value AnalysisSimonRobertson
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisBECM, RUET, Bangladesh
 
PMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - FormulasPMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - FormulasAnand Bobade
 
Projects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneProjects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneWaleed Hamdy Albana
 

Similar a Earned value for pmp and pmi acp exam (20)

Project Management EVM & SCBA
Project Management EVM & SCBAProject Management EVM & SCBA
Project Management EVM & SCBA
 
Earned value management
Earned value managementEarned value management
Earned value management
 
Pm 8 cost_management
Pm 8 cost_managementPm 8 cost_management
Pm 8 cost_management
 
Pm 8 cost_management
Pm 8 cost_managementPm 8 cost_management
Pm 8 cost_management
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
 
#Measuring Project Performance - Earned Value Management System# By SN Panigrahi
#Measuring Project Performance - Earned Value Management System# By SN Panigrahi#Measuring Project Performance - Earned Value Management System# By SN Panigrahi
#Measuring Project Performance - Earned Value Management System# By SN Panigrahi
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysis
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
 
Your Projects May Be Robbing You Blind
Your Projects May Be Robbing You BlindYour Projects May Be Robbing You Blind
Your Projects May Be Robbing You Blind
 
What Is Earned Value Analysis
What Is Earned Value AnalysisWhat Is Earned Value Analysis
What Is Earned Value Analysis
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
EVA - Metrics.ppt
EVA - Metrics.pptEVA - Metrics.ppt
EVA - Metrics.ppt
 
Project Health.doc
Project Health.docProject Health.doc
Project Health.doc
 
PMP COST FORMULAE
PMP COST FORMULAEPMP COST FORMULAE
PMP COST FORMULAE
 
PMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - FormulasPMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - Formulas
 
Project managment 6 (a)
Project managment 6 (a)Project managment 6 (a)
Project managment 6 (a)
 
Projects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneProjects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part One
 
An introduction to project accounting
An introduction to project accountingAn introduction to project accounting
An introduction to project accounting
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgeting
 
Basics of EVM.pdf
Basics of  EVM.pdfBasics of  EVM.pdf
Basics of EVM.pdf
 

Earned value for pmp and pmi acp exam

  • 2. Understanding Earned Value Management  Calculating To-Complete Performance Index (TCPI)  Budget forecasting  Budget variance analysis
  • 3. Understanding of Earn Value Management concepts  Will help in managing projects better in real life  Will help in solving ~10 questions in PMP exam
  • 4. Earned Value Management (EVM) is a project management system that combines schedule performance and cost performance to answer the question,  “What did we get for the money we spent?”  It measures project performance against the project baselines. It results from an earned value analysis indicating potential deviation of the project from the cost and/or schedule baseline.
  • 5. It is used to figure out how well project needs to perform in the future in order to stay on budget.
  • 6. Use the information you have about the project right now to predict how close it will come to its goals if it keeps going the way it has been.
  • 7. Throughout your project, you are looking at how you are doing as compared to your plan. The variance between planned and actual performance needs to be carefully analyzed to figure out budget or schedule related issues.
  • 8. Planned Value : The percentage of total budget that you are supposed to have earned so far.  BAC (Budget At Completion) ◦ It is total budget you have for your project.  Planned Value ◦ Budget you planned on using so far ◦ PV = BAC x Planned % Complete If BAC is $100,000 and planned % complete is 30%, then Planned Value is : $100,000 x 30% = $30,000
  • 9. Earn Value tells you how much your project actually earned.  EV = BAC x Actual % complete  If BAC is $100,000 and actual % complete is 25%, then Earned Value is : $100,000 x 25% = $25,000
  • 10. Schedule Performance Index (SPI) = EV / PV  If SPI > 1 means Earned Value is greater than Planned value so project is ahead of schedule  If SPI < 1 means Earned Value is less than Planned Value so project is behind of schedule  Schedule Variance (SV) = EV – PV  If SV is positive means EV > PV and it tells you how many dollars you are ahead of schedule.  If SV is negative means EV < PV and it tells you how many dollars you are behind schedule.  Total budget of project is $10,000 and you are halfway through schedule. It seems you have only gotten 40% of actual work done.  What is PV, EV, SPI and SV?  Is project ahead or behind of schedule?  Recap : PV = BAC x Planned % Complete, EV = BAC x Actual % complete
  • 11. Actual Cost (AC) is the amount of money spent so far on the project.  Cost Performance Index (CPI) = EV / AC  If CPI > 1 means Earned Value is greater than Actual Cost so project is under budget  If CPI < 1 means Earned Value is less than Actual Cost so project is over budget  Cost Variance (CV) = EV – AC  If CV is positive means EV > AC and it tells you how many dollars you are under budget.  If CV is negative means EV < AC and it tells you how many dollars you are over budget.  Total budget of project is $10,000 and you are halfway through schedule. It seems you have only gotten 40% of actual work done. You have spend $6000 so far.  What is PV, EV, CPI and CV?  Is project over or under budget?  Recap : PV = BAC x Planned % Complete, EV = BAC x Actual % complete
  • 12.
  • 13. Forecasting is predicting what your project will look like when it’s at completion.  Estimate At Completion (EAC) is Predicting total cost when project is complete.  EAC = BAC / CPI ◦ If CPI < 1 mean project is over budget and will give EAC > current budget. ◦ If CPI > 1 mean project is under budget and will give EAC < current budget.  If CPI is 0.8 and total budget is $10,000, then what will be Estimate At Completion (EAC)?
  • 14. Estimate To Complete (ETC) is how much more money will be spend on project completion. ◦ ETC = EAC – AC  Variance At Completion (VAC) predicts what your budget variance will be when the project is complete. ◦ VAC = BAC – EAC ◦ If you will spend more than your budget, variance will be negative. BAC PV EAC AC ETC
  • 15. TCPI represents a target that your CPI would have to hit to meet forecasted completion cost. ◦ TCPI when you are trying to get your project within your original budget,  TCPI = (BAC – EV) / (BAC – AC) i.e. left Budgeted work / left budgeted money ◦ TCPI when you are trying to get your project done within Estimate At Completion (EAC),  TCPI = (BAC – EV) / (EAC – AC) i.e. left budgeted work / left estimated money  Higher TCPI means left budgeted work > left budgeted (or estimated) money so it’s time to take strict cost management approach.  Lower TCPI means left budgeted work < left budgeted (or estimated) money so you are well with in your budget.
  • 16. Actual value at any given time of the project minus all of the costs associated with it.  Managers calculate this number to see if it’s worth doing a project. Managers select project with greatest NPV.  If Project A will take 3 years to complete and has an NPV of $50,000. Project B will take 6 years to complete and has an NPV of $90,000. Which one would you prefer?
  • 17. IRR is interest rate at which project inflows (revenues) and project outflows (costs) are equal.  If company has more than one project to select, project with highest IRR are selected for implementation.
  • 18. The number of time periods it takes to recover your investment in the project before you start accumulating profit.  You have two projects to choose from, Project A with a payback period of six months or Project B with a payback period of 18 months. Which one would you prefer?
  • 19. It is ratio of Benefit (i.e. revenue in this case) to Cost.  BCR > 1 means benefits are greater than cost.  Project with highest BCR is selected for implementation.
  • 20. Opportunity given up by selecting one project over another.  You have two projects to choose from; Project A with an NPV of $50,000 or Project B with an NPV of $90,000. What is the opportunity cost of selecting project B?
  • 21. Net Present Value  Internal Rate of Return  Payback period  Benefit Cost Ratio
  • 22. Drop us a note. Your feedbacks are valuable to us!
  • 23. Provide PMP, Agile & Scrum training  Provide face to face and online training of PMI-ACP (Agile Certified Practitioner) certification program  Help Organizations in adapting agile  Helps organizations in setting up project governing office.  Get training calendar at www.iZenBridge.com
  • 24. Saket Bansal Saket.Bansal@iZenBridge.com M: 9910802561 Web: www.iZenBridge.com LinkedIn: www.linkedin.com/in/saketbansal
  • 25. Keep in touch for more interesting & interactive presentations
  • 26. Presentation by – Manish Purwar Contact Manish at Mobile : +91 9910500922 purwar_manish@yahoo.com