SlideShare una empresa de Scribd logo
1 de 91
Descargar para leer sin conexión
Welcome to El Gallo Complex Mine Tour
                                        1
Ian Ball – Senior Vice President
Introduction                       2
Taking a Phased Approach
       Original Plan

El Gallo + Magistral + Palmarito


       Production 2014
                                   3
Taking a Phased Approach
       A Better Way Forward

   Magistral      El Gallo + Palmarito
   Phase 1              Phase 2



Production 2012    Production 2014

                                         4
Key Benefits
•  Cash flow now
•  Build operational team
•  Test costs assumptions (labour, mining, etc.)
•  Prove success through phased approach


                                                   5
Magistral Mine 2007
                      6
Background
•  Operated 2002-2005

•  Produced 70,000 oz Gold

•  Placed on care maintenance

•  Operating permit remained in place

                                        7
Background
•  2007: McEwen Mining acquired project

•  2009: El Gallo Phase 2 discovered

•  2012: Rebuilt Phase 1

•  2012: Positive Phase 2 feasibility study

                                              8
Past Operational Issues
1.  Poor recoveries: crush size / soluble copper
2.  Long leach times
3.  Low mining rates
4.  Minimal working capital


        Could we fix it? YES!
                                                   9
What Did We Do?
1.  Installed 3 stage crusher: 3/8 inch
2.  Cold strip for soluble copper
3.  Contract mining
4.  Strong balance sheet


                                          10
How Did We Do? Great!
   Budget: $15 Million
 Final cost: $13.5 Million
Completion date: Q3, 2012
Under Budget, On Schedule
                             11
El Gallo Phase 1, 2013
                         12
El Gallo I
EPCM Contractor Overview




    Sonoran Resources
                           13
Sonoran Resources Previous Projects
Cerro Prieto Project                          Santa Elena Mine
Sonora Mexico                                 Sonora Mexico
• EPCM – Gold Silver Mine                     • Procurement and Construction Management
• Oversaw permitting                          • Constructed and commissioned mine
• Negotiations for surface and water rights

Oatman Mine                                   Mesquite Mine
Arizona U.S.A.                                California U.S.A.
• Dewatering underground                      • Construction of ADR Plant
• Upgrades to electrical                      • Recommissioned refinery
• Recommissioning ventilation                 • Development of truck shop
                                              • Electrical upgrades
Golden Summit
Alaska U.S.A.                                 La Bolsa Project
• Fabricated gravity circuit                  Sonora Mexico
• Installed crushing circuit                  • Prefeasibility Study
                                              • Scoping Study
                                                                                          14
Initial Assessment - September 2011
                                      15
Key Areas of Rebuild

  1.  Process Plant

  2.  Crushers

  3.  Heap Leach Expansion

  4.  Process Pond Upgrade

                             16
Process Plant




Before                   After

                                 17
Assay Laboratory




Before                      After

                                    18
Refinery




Before              After

                            19
Vault




Before           After

                         20
Generators




Before                After

                              21
Installed Cold Strip & Acid Wash Circuit
                                           22
Crushers




2 Stage Before              3 Stage After


                                            23
Heap Leach Pad




Before                    After

                                  24
Increased Capacity and Gold Recovery
                                       25
Process Ponds
                26
Increased Capacity and Reliability
                                     27
Gold Pour
            28
El Gallo 1



     A Team That
     Builds Success!


                   29
John Read – Senior Geologist
Exploration                    30
Phase I
Resources                                        M&I	
  Resource	
  
                                                 345,000	
  oz	
  Au	
  
             Samaniego	
  
                Pit	
  

                                                                               M&I	
  Resource	
  
                                 San	
  Rafael	
  Pit	
                        113,350	
  oz	
  Au	
  




                                                                                      Lupita	
  Pit	
  
                             M&I	
  Resource	
  
                             46,600	
  oz	
  Au	
  
0            500
    Meters         N
                                                               Sagrado	
  Corazon	
  Pit	
  
                                                                                                          31
Lupita
Deposit + Pit Design




                       0            200
                           Meters         N



                                              32
NW	
                                                                  SE	
  

 Lupita          46.1m	
  @	
  2.1	
  g /t	
  Au	
  
                 Incl.	
  5m	
  @	
  9.9	
  g /t	
  
  Deposit
                                                           44.4m	
  @	
  1.1	
  g /t	
  Au	
  
SECTION LUP-74                                             Incl.	
  2.5m	
  @	
  9.5	
  g /t	
  



                                                           12.8m	
  @	
  3.0	
  g /t	
  Au	
  
                                                           Incl.	
  1.1m	
  @	
  23.3	
  g /t	
  




                                                       0                       100
                                                               Meters



                                                                                                    33
NW	
                                          SE	
  

 Lupita
  Deposit
SECTION LUP-58

                                                         11m	
  @	
  0.96	
  g /t	
  Au	
  


            41.2m	
  @	
  1.3	
  g /t	
  Au	
  
                                                           65.2m	
  @	
  0.5	
  g /t	
  Au	
  
            Incl.	
  1.7m	
  @	
  13.4	
  g /t	
  




                                                     0                     100
                                                           Meters
                                                                                                 34
McEwen	
          Sonora      Chihuahua

ExploraGon	
                                         El	
  Gallo	
  
  Project	
                                          Complex	
  

   Baja
 California
                                                     Durango
                                Sinaloa




                                                                       Zacatecas

                                                                            McEwen	
  
                          Pacific Ocean                                    ExploraGon	
  
                                          Guamuchil	
  
                    100
                                                                             Project	
  
      0
                          N                                  Nayarit
              Km



                                                                       Jalisco

                                                                                            35
Mines in
Western Mexico




         N
                 36
El Gallo Complex
Production Areas + New Potential




                                   37
Mina	
  Grande	
  


                               Haciendita	
  



                    	
  




0             500
                           N
    Meters

                                                38
Blast	
  Hole	
  Rig	
     Diamond	
  Drill	
  Rig	
  
                                                         39
40
Haciendita Exploration Project                                       SECTION HC-10

      SW	
                                                                                     NE	
  
           16.4m	
  @	
  2.07	
  g /t	
  Au	
  

                                                                    23.8m	
  @	
  1.3	
  g /t	
  Au	
  

                      5.4m	
  @	
  1.49	
  g /t	
  Au	
              17.8m	
  @	
  1.78	
  g /t	
  Au	
  




                                                            0                100
                                                                Meters

                                                                                                            41
Mina	
  Grande	
  


                                        Haciendita	
  



                          	
  




0            500
                   N
    Meters
                                                         42
43
Mina Grande Exploration Project                             SECTION MG-13
       SW	
                                                                         NE	
  
                4.65m	
  @	
  12.35	
  g /t	
  Au	
  
                 Incl.	
  	
  1m	
  @	
  44.1	
  g /t	
  

                 12.5m	
  @	
  6.43	
  g /t	
  Au	
  
                  Incl.	
  1.2m	
  @	
  49	
  g /t	
         5.1m	
  @	
  5.72	
  g /t	
  Au	
  
                                                             Incl.	
  1.3m	
  @	
  18.6	
  g /t	
  




          0                                  100
                            Meters
                                                                                                      44
Patricia Angulo – Human Resources
Community Relations                 45
Mining brings prosperity to communities where economic
activities are limited.
                                                         46
Compañía Minera Pangea
       in Region since 1995

McEwen Mining Acquired Project 2007




                                      47
Three main municipalities surround the mine:
Mocorito, Salvador Alvarado and Sinaloa.
                                               48
Villages Around
                                                                     the Mine




              Los Becos
                                                                Projects
                           El Tule de Arriba                    Villages
Cerro Agudo               El Tule
                            El Mezquite         San Miguel
         Los Medina


                   Las Milpas de los Gonzalez
                                                                            49
Mission
To develop profitable mineral
  deposits and enhance the
 community where we work.

                                50
Since 2007
McEwen Mining Contributed
      US $3,000,000

                            51
McEwen Mining helps sponsor traditional holidays such as:
Child´s Day, Mother's Day, Teacher’s day, and Christmas.




                                                            52
Providing Water for the
Local Community




                          53
In 2010 US$20,000 donated to 24 schools

Consisting :

Air Conditioners
Water Coolers
Construction Material
Fans
Education Material
Sports Equipment
                                          54
Schools Donation Program
                       Children’s Day




 School Supplies
                                        Christmas




Educational Material




                                                    55
Making Schools Better




Before                       After
                         DESPUES	
     56
El Gallo Multipurpose Court




   In 2011 a multipurpose court was built
        for the El Gallo community.
                                            57
El Valle Road Paving (2 km)
   Investment US$650,000   ANTES	
  
           2012




                                       58
El Valle Paving Road Inauguration
April 2012                          59
El Magistral, Mocorito, Sinaloa
In 2012, 4 houses built to relocate residents
                                                60
61
Bill Faust – COO / Fernando Aguilar – Operations Manager
El Gallo Phase 2
                                                           62
El Gallo Complex




                   63
El Gallo Phase 2
•  Conventional Open Pit, Mill, Agitated Leach
•  Est. Capex $180 Million
•  Est. production 5 Million silver oz / year
•  Est. cash cost $10 / oz
•  Mine life est. 6.5 years
                                                 64
Looking North Towards Process Plant
                                      65
Looking South Towards Open Pit
                                 66
Stoc
                                    Leach Ore




                 kpile
                         Open Pit


                                                Waste Dump




El Gallo Open Pit Design
                                                             67
View of Historic Palmarito Pit
 68                              68
Open Pit




                                  Waste Dump
                 N




Palmarito Open Pit Design
                                               69
El Gallo Phase 2 Reserve

                              Tonnes    Silver   Gold     Silver     Gold
Classification
                               (000’)    (g/t)   (g/t)   (000’oz)    (oz)
Proven Mineral Reserve         11,185   101.0    0.125     36,336    44,816
Probable Mineral Reserve          534   107.2    0.075       1,840    1,286
Proven and Probable Reserve    11,719   101.3    0.123     38,176    46,102




                                                                              70
El Gallo - Construction
•  Pits mined using contractor
•  Permitting underway submittal Q1 2013
•  EPCM Contractor – M3 Engineering
•  Construction start expected Q3 2013


                                           71
CYCLONE
                 CLUSTERS                 Process Flowsheet
              3-STAGE
 STOCKPILE
             CRUSHING


                                           LEACH TANKS
                             BALL
                             MILL




                            CCD CIRCUIT

                              DORE


                                      REFINERY   MERRILL CROWE
DRY STACK
 TAILINGS                                                        72
Tailings Storage
Mill




  Open Pit                     N




                                    Surface Rights




El Gallo Phase 2 Site Layout
                                                 73
Surface Rights
                                                 Boundary

                                  Substation



         Water Storage                                      CCD Tanks




       Crushers
                         Ball
                         Mill
                                Leach                           Merrill
                                Tanks                           Crowe
 N




El Gallo Phase 2 Process Plant Layout
                                                                          74
Planned Site for Process Plant
                                 75
Dry Stacked Tailings
                       76
Future Substation Site – Project Power
                                         77
Ian Ball – Senior Vice President
El Gallo Phase 2 Economics         78
El Gallo Phase 2 Initial Capital - $180 M
           Process                  US Dollars (x000)
           Site Prep.                            $3,867
           Crushing                             $15,686
           Ore Storage                           $3,435
           Mill                                 $12,836
           Leaching                             $28,552
           Merrill-Crowe                         $9,688
           Refinery                              $4,168
           Tailings                             $20,195
           Water                                 $4,765
           Power                                 $8,382
           Reagents Tanks                        $3,570
           Buildings                             $2,632
           Freight                               $8,590
           Subtotal                            $126,365
           Indirect Costs
           Mobilization                          $1,856
           EPCM                                 $19,903
           Commissioning / Spares                $2,345
           Owner’s Cost                          $8,766
           Contingency (14.4%)                  $18,813
           Subtotal                             $51,683
           Total                               $178,048
                                                          79
El Gallo Phase 2 Operating Costs
     Production Cost $10 / oz Silver
                                              Cost Per Ore
                                                 Tonne
                                               Processed
  Mining                                              $7.40
  Processing                                         $21.37
  Refining                                            $1.43
  Royalty                                             $1.01
  G&A                                                 $2.16
  Gold By-Product Credit ($1,415 per ounce)         ($4.63)
  Total Operating Costs                              $28.74


                                                              80
El Gallo Phase 2 Mine Plan
               Avg 5.2 Million oz Silver / yr
          Silver     Silver      Gold      Gold                     Ore
        Production   Grade    Production   Grade    Strip Ratio   Tonnes
Year      (000’)     (gpt)        (oz)     (gpt)   (Waste:Ore)     (000’)
  1        6,113     135.1       4,030     0.095        1.99       1,669
  2        5,540     113.4      11,754     0.248        2.65       1,825
  3        5,562     113.6       6,189     0.123        2.89       1,825
  4        4,241      86.0       5,271     0.106        3.22       1,825
  5        4,632      94.4       4,949     0.099        2.53       1,825
  6        4,749      95.5       4,152     0.088        1.84       1,825
  7        1,182      47.8       1,964     0.078        2.22        925
Total     32,019     101.3      38,309     0.123        2.61       11,719


                                                                            81
El Gallo Phase 2 Metallurgical Testing
        Area          Silver Recovery   Gold Recovery
                             (%)             (%)

Silver and Gold            84.3             83.2
Recovery

Cyanide (kg/tonnes)        1.52

Lime (kg/tonne)            6.77

                                                        82
El Gallo Phase 2 Financial Returns
      After Income Tax         Base Case       Spot Case
                              ($25 Silver /   ($32 Silver /
                              $1,415 Gold)    $1,700 Gold)
     IRR                          26%             44%
     NPV 0%                       $184            $354
     NPV 5%                       $118            $248
     NPV 10%                      $73             $174
     Annual Cash Flow             $56             $82
     Payback (yrs)                 2.6             1.8

*Dollar figures in millions
                                                              83
Simon Quick – VP Projects
Permitting, Water Rights and Supply   84
Experienced Team
Permit Specialist:            Water Rights + Supply:
 Patricia Aguayo                Dr. Miguel Rangal
•  MS Chemical Engineering      •  Ph.D. in hydrology
•  Permitted: Alamo Dorado,     •  Current projects:
   La Bolsa Mine                   Torex, Timmins Gold,
•  Good relationship with          Goldcorp.
   SERMANAT                     •  Specializes in Water
                                   Rights Registration

                                                          85
Sinaloa Permitting Favourable
Marlin Gold permit submitted:
                                El Gallo Complex
(May   1st,   2012)
•  Located in Sinaloa
•  Granted 140 days
•  Positive sign…!
                                                   86
3 Required Permits:
(MIA) Manifestacion de Impacto Ambiental
   •  EIS equivalent USA

(ETJ) Estudio Justificativo Para Cambio Uso Suelo
   •  Change of Land Use

(ER) Analisis de Riesgo
   •  Risk Analysis

                                                    87
Permitting Schedule
MIA                                                          (60 – 120 Days)



ETJ                                                          (60 – 120 Days)



ER                                                           (60 – 120 Days)

                  Permit Submission               Expected Approval

      Q1	
  2013	
         Q2	
  2013	
     Q3	
  2013	
       Q4	
  2013	
  
                                                                                88
Regulators Like Safe & Simple
        Dry Tailings
   Eliminates dam failure
Reduces environmental impact
  Lowers reclamation costs

                                89
  Water rights secured: 1 Million M3 / Year x 2
  Water requirements satisfied: 17 l/s
                                                     Well 5
               Well 1                                6.3 l/s
               2.2 l/s



                                                         Well 3
                                                         3.3 l/s


                                                     Well 4
                                                     40.4 l/s

                                                        - Production well
                                                   l/s 	
   Litre per second
                                                       -                   90
Filter Press – Dry Stack Tailings
                                    91

Más contenido relacionado

Similar a Explore New Potential at El Gallo Complex Mine

Cortona Resources- Resources & Energy Symposium 2012
Cortona Resources- Resources & Energy Symposium 2012Cortona Resources- Resources & Energy Symposium 2012
Cortona Resources- Resources & Energy Symposium 2012Symposium
 
Jon dugdale Red Mountain Mining
Jon dugdale  Red Mountain MiningJon dugdale  Red Mountain Mining
Jon dugdale Red Mountain MiningSymposium
 
Investor Presentation | Impact Minerals (ASX:IPT) | Gold Investment Symposium...
Investor Presentation | Impact Minerals (ASX:IPT) | Gold Investment Symposium...Investor Presentation | Impact Minerals (ASX:IPT) | Gold Investment Symposium...
Investor Presentation | Impact Minerals (ASX:IPT) | Gold Investment Symposium...Symposium
 
The discovery and evaluation of AK6
The discovery and evaluation of AK6The discovery and evaluation of AK6
The discovery and evaluation of AK6James AH Campbell
 
CPV - Copper Creek Gold Updated Overview
CPV - Copper  Creek  Gold Updated OverviewCPV - Copper  Creek  Gold Updated Overview
CPV - Copper Creek Gold Updated OverviewViral Network Inc
 
Objective Capital Global Mining Investment Conference - North America: Stephe...
Objective Capital Global Mining Investment Conference - North America: Stephe...Objective Capital Global Mining Investment Conference - North America: Stephe...
Objective Capital Global Mining Investment Conference - North America: Stephe...Objective Capital Conferences
 
Rio Silver Presentation - RYO.V - September 2019
Rio Silver Presentation - RYO.V - September 2019Rio Silver Presentation - RYO.V - September 2019
Rio Silver Presentation - RYO.V - September 2019MomentumPR
 
F R X Presentation May 19 2010
F R X  Presentation  May 19 2010F R X  Presentation  May 19 2010
F R X Presentation May 19 2010ManexGroup
 
Magellan Minerals Corporate Presentation
Magellan Minerals Corporate PresentationMagellan Minerals Corporate Presentation
Magellan Minerals Corporate PresentationMagellan Minerals Ltd.
 
Sage february 2012.v5_ppt
Sage february 2012.v5_pptSage february 2012.v5_ppt
Sage february 2012.v5_pptSagegold
 
Corporate Presentation December 2012
Corporate Presentation December 2012Corporate Presentation December 2012
Corporate Presentation December 2012FirstQuantum
 
TNR Gold Investor Presentation
TNR Gold Investor PresentationTNR Gold Investor Presentation
TNR Gold Investor PresentationViral Network Inc
 

Similar a Explore New Potential at El Gallo Complex Mine (20)

Minaurum Presentation
Minaurum PresentationMinaurum Presentation
Minaurum Presentation
 
Cortona Resources- Resources & Energy Symposium 2012
Cortona Resources- Resources & Energy Symposium 2012Cortona Resources- Resources & Energy Symposium 2012
Cortona Resources- Resources & Energy Symposium 2012
 
Corporate Presentation
Corporate PresentationCorporate Presentation
Corporate Presentation
 
Corporate Presentation
Corporate PresentationCorporate Presentation
Corporate Presentation
 
Corporate Presentation
Corporate PresentationCorporate Presentation
Corporate Presentation
 
Aa ggold 10 20-10
Aa ggold 10 20-10Aa ggold 10 20-10
Aa ggold 10 20-10
 
Jon dugdale Red Mountain Mining
Jon dugdale  Red Mountain MiningJon dugdale  Red Mountain Mining
Jon dugdale Red Mountain Mining
 
Impact Silver
Impact SilverImpact Silver
Impact Silver
 
Investor Presentation | Impact Minerals (ASX:IPT) | Gold Investment Symposium...
Investor Presentation | Impact Minerals (ASX:IPT) | Gold Investment Symposium...Investor Presentation | Impact Minerals (ASX:IPT) | Gold Investment Symposium...
Investor Presentation | Impact Minerals (ASX:IPT) | Gold Investment Symposium...
 
The discovery and evaluation of AK6
The discovery and evaluation of AK6The discovery and evaluation of AK6
The discovery and evaluation of AK6
 
CPV - Copper Creek Gold Updated Overview
CPV - Copper  Creek  Gold Updated OverviewCPV - Copper  Creek  Gold Updated Overview
CPV - Copper Creek Gold Updated Overview
 
Objective Capital Global Mining Investment Conference - North America: Stephe...
Objective Capital Global Mining Investment Conference - North America: Stephe...Objective Capital Global Mining Investment Conference - North America: Stephe...
Objective Capital Global Mining Investment Conference - North America: Stephe...
 
Rio Silver Presentation - RYO.V - September 2019
Rio Silver Presentation - RYO.V - September 2019Rio Silver Presentation - RYO.V - September 2019
Rio Silver Presentation - RYO.V - September 2019
 
November 2011
November 2011November 2011
November 2011
 
F R X Presentation May 19 2010
F R X  Presentation  May 19 2010F R X  Presentation  May 19 2010
F R X Presentation May 19 2010
 
Magellan Minerals Corporate Presentation
Magellan Minerals Corporate PresentationMagellan Minerals Corporate Presentation
Magellan Minerals Corporate Presentation
 
Sage february 2012.v5_ppt
Sage february 2012.v5_pptSage february 2012.v5_ppt
Sage february 2012.v5_ppt
 
Corporate Presentation December 2012
Corporate Presentation December 2012Corporate Presentation December 2012
Corporate Presentation December 2012
 
TNR Gold Investor Presentation
TNR Gold Investor PresentationTNR Gold Investor Presentation
TNR Gold Investor Presentation
 
Brixton presentation 2015 June
Brixton presentation 2015 JuneBrixton presentation 2015 June
Brixton presentation 2015 June
 

Explore New Potential at El Gallo Complex Mine

  • 1. Welcome to El Gallo Complex Mine Tour 1
  • 2. Ian Ball – Senior Vice President Introduction 2
  • 3. Taking a Phased Approach Original Plan El Gallo + Magistral + Palmarito Production 2014 3
  • 4. Taking a Phased Approach A Better Way Forward Magistral El Gallo + Palmarito Phase 1 Phase 2 Production 2012 Production 2014 4
  • 5. Key Benefits •  Cash flow now •  Build operational team •  Test costs assumptions (labour, mining, etc.) •  Prove success through phased approach 5
  • 7. Background •  Operated 2002-2005 •  Produced 70,000 oz Gold •  Placed on care maintenance •  Operating permit remained in place 7
  • 8. Background •  2007: McEwen Mining acquired project •  2009: El Gallo Phase 2 discovered •  2012: Rebuilt Phase 1 •  2012: Positive Phase 2 feasibility study 8
  • 9. Past Operational Issues 1.  Poor recoveries: crush size / soluble copper 2.  Long leach times 3.  Low mining rates 4.  Minimal working capital Could we fix it? YES! 9
  • 10. What Did We Do? 1.  Installed 3 stage crusher: 3/8 inch 2.  Cold strip for soluble copper 3.  Contract mining 4.  Strong balance sheet 10
  • 11. How Did We Do? Great! Budget: $15 Million Final cost: $13.5 Million Completion date: Q3, 2012 Under Budget, On Schedule 11
  • 12. El Gallo Phase 1, 2013 12
  • 13. El Gallo I EPCM Contractor Overview Sonoran Resources 13
  • 14. Sonoran Resources Previous Projects Cerro Prieto Project Santa Elena Mine Sonora Mexico Sonora Mexico • EPCM – Gold Silver Mine • Procurement and Construction Management • Oversaw permitting • Constructed and commissioned mine • Negotiations for surface and water rights Oatman Mine Mesquite Mine Arizona U.S.A. California U.S.A. • Dewatering underground • Construction of ADR Plant • Upgrades to electrical • Recommissioned refinery • Recommissioning ventilation • Development of truck shop • Electrical upgrades Golden Summit Alaska U.S.A. La Bolsa Project • Fabricated gravity circuit Sonora Mexico • Installed crushing circuit • Prefeasibility Study • Scoping Study 14
  • 15. Initial Assessment - September 2011 15
  • 16. Key Areas of Rebuild 1.  Process Plant 2.  Crushers 3.  Heap Leach Expansion 4.  Process Pond Upgrade 16
  • 19. Refinery Before After 19
  • 20. Vault Before After 20
  • 21. Generators Before After 21
  • 22. Installed Cold Strip & Acid Wash Circuit 22
  • 23. Crushers 2 Stage Before 3 Stage After 23
  • 25. Increased Capacity and Gold Recovery 25
  • 27. Increased Capacity and Reliability 27
  • 28. Gold Pour 28
  • 29. El Gallo 1 A Team That Builds Success! 29
  • 30. John Read – Senior Geologist Exploration 30
  • 31. Phase I Resources M&I  Resource   345,000  oz  Au   Samaniego   Pit   M&I  Resource   San  Rafael  Pit   113,350  oz  Au   Lupita  Pit   M&I  Resource   46,600  oz  Au   0 500 Meters N Sagrado  Corazon  Pit   31
  • 32. Lupita Deposit + Pit Design 0 200 Meters N 32
  • 33. NW   SE   Lupita 46.1m  @  2.1  g /t  Au   Incl.  5m  @  9.9  g /t   Deposit 44.4m  @  1.1  g /t  Au   SECTION LUP-74 Incl.  2.5m  @  9.5  g /t   12.8m  @  3.0  g /t  Au   Incl.  1.1m  @  23.3  g /t   0 100 Meters 33
  • 34. NW   SE   Lupita Deposit SECTION LUP-58 11m  @  0.96  g /t  Au   41.2m  @  1.3  g /t  Au   65.2m  @  0.5  g /t  Au   Incl.  1.7m  @  13.4  g /t   0 100 Meters 34
  • 35. McEwen   Sonora Chihuahua ExploraGon   El  Gallo   Project   Complex   Baja California Durango Sinaloa Zacatecas McEwen   Pacific Ocean ExploraGon   Guamuchil   100 Project   0 N Nayarit Km Jalisco 35
  • 37. El Gallo Complex Production Areas + New Potential 37
  • 38. Mina  Grande   Haciendita     0 500 N Meters 38
  • 39. Blast  Hole  Rig   Diamond  Drill  Rig   39
  • 40. 40
  • 41. Haciendita Exploration Project SECTION HC-10 SW   NE   16.4m  @  2.07  g /t  Au   23.8m  @  1.3  g /t  Au   5.4m  @  1.49  g /t  Au   17.8m  @  1.78  g /t  Au   0 100 Meters 41
  • 42. Mina  Grande   Haciendita     0 500 N Meters 42
  • 43. 43
  • 44. Mina Grande Exploration Project SECTION MG-13 SW   NE   4.65m  @  12.35  g /t  Au   Incl.    1m  @  44.1  g /t   12.5m  @  6.43  g /t  Au   Incl.  1.2m  @  49  g /t   5.1m  @  5.72  g /t  Au   Incl.  1.3m  @  18.6  g /t   0 100 Meters 44
  • 45. Patricia Angulo – Human Resources Community Relations 45
  • 46. Mining brings prosperity to communities where economic activities are limited. 46
  • 47. Compañía Minera Pangea in Region since 1995 McEwen Mining Acquired Project 2007 47
  • 48. Three main municipalities surround the mine: Mocorito, Salvador Alvarado and Sinaloa. 48
  • 49. Villages Around the Mine Los Becos Projects El Tule de Arriba Villages Cerro Agudo El Tule El Mezquite San Miguel Los Medina Las Milpas de los Gonzalez 49
  • 50. Mission To develop profitable mineral deposits and enhance the community where we work. 50
  • 51. Since 2007 McEwen Mining Contributed US $3,000,000 51
  • 52. McEwen Mining helps sponsor traditional holidays such as: Child´s Day, Mother's Day, Teacher’s day, and Christmas. 52
  • 53. Providing Water for the Local Community 53
  • 54. In 2010 US$20,000 donated to 24 schools Consisting : Air Conditioners Water Coolers Construction Material Fans Education Material Sports Equipment 54
  • 55. Schools Donation Program Children’s Day School Supplies Christmas Educational Material 55
  • 56. Making Schools Better Before After DESPUES   56
  • 57. El Gallo Multipurpose Court In 2011 a multipurpose court was built for the El Gallo community. 57
  • 58. El Valle Road Paving (2 km) Investment US$650,000 ANTES   2012 58
  • 59. El Valle Paving Road Inauguration April 2012 59
  • 60. El Magistral, Mocorito, Sinaloa In 2012, 4 houses built to relocate residents 60
  • 61. 61
  • 62. Bill Faust – COO / Fernando Aguilar – Operations Manager El Gallo Phase 2 62
  • 64. El Gallo Phase 2 •  Conventional Open Pit, Mill, Agitated Leach •  Est. Capex $180 Million •  Est. production 5 Million silver oz / year •  Est. cash cost $10 / oz •  Mine life est. 6.5 years 64
  • 65. Looking North Towards Process Plant 65
  • 66. Looking South Towards Open Pit 66
  • 67. Stoc Leach Ore kpile Open Pit Waste Dump El Gallo Open Pit Design 67
  • 68. View of Historic Palmarito Pit 68 68
  • 69. Open Pit Waste Dump N Palmarito Open Pit Design 69
  • 70. El Gallo Phase 2 Reserve Tonnes Silver Gold Silver Gold Classification (000’) (g/t) (g/t) (000’oz) (oz) Proven Mineral Reserve 11,185 101.0 0.125 36,336 44,816 Probable Mineral Reserve 534 107.2 0.075 1,840 1,286 Proven and Probable Reserve 11,719 101.3 0.123 38,176 46,102 70
  • 71. El Gallo - Construction •  Pits mined using contractor •  Permitting underway submittal Q1 2013 •  EPCM Contractor – M3 Engineering •  Construction start expected Q3 2013 71
  • 72. CYCLONE CLUSTERS Process Flowsheet 3-STAGE STOCKPILE CRUSHING LEACH TANKS BALL MILL CCD CIRCUIT DORE REFINERY MERRILL CROWE DRY STACK TAILINGS 72
  • 73. Tailings Storage Mill Open Pit N Surface Rights El Gallo Phase 2 Site Layout 73
  • 74. Surface Rights Boundary Substation Water Storage CCD Tanks Crushers Ball Mill Leach Merrill Tanks Crowe N El Gallo Phase 2 Process Plant Layout 74
  • 75. Planned Site for Process Plant 75
  • 77. Future Substation Site – Project Power 77
  • 78. Ian Ball – Senior Vice President El Gallo Phase 2 Economics 78
  • 79. El Gallo Phase 2 Initial Capital - $180 M Process US Dollars (x000) Site Prep. $3,867 Crushing $15,686 Ore Storage $3,435 Mill $12,836 Leaching $28,552 Merrill-Crowe $9,688 Refinery $4,168 Tailings $20,195 Water $4,765 Power $8,382 Reagents Tanks $3,570 Buildings $2,632 Freight $8,590 Subtotal $126,365 Indirect Costs Mobilization $1,856 EPCM $19,903 Commissioning / Spares $2,345 Owner’s Cost $8,766 Contingency (14.4%) $18,813 Subtotal $51,683 Total $178,048 79
  • 80. El Gallo Phase 2 Operating Costs Production Cost $10 / oz Silver Cost Per Ore Tonne Processed Mining $7.40 Processing $21.37 Refining $1.43 Royalty $1.01 G&A $2.16 Gold By-Product Credit ($1,415 per ounce) ($4.63) Total Operating Costs $28.74 80
  • 81. El Gallo Phase 2 Mine Plan Avg 5.2 Million oz Silver / yr Silver Silver Gold Gold Ore Production Grade Production Grade Strip Ratio Tonnes Year (000’) (gpt) (oz) (gpt) (Waste:Ore) (000’) 1 6,113 135.1 4,030 0.095 1.99 1,669 2 5,540 113.4 11,754 0.248 2.65 1,825 3 5,562 113.6 6,189 0.123 2.89 1,825 4 4,241 86.0 5,271 0.106 3.22 1,825 5 4,632 94.4 4,949 0.099 2.53 1,825 6 4,749 95.5 4,152 0.088 1.84 1,825 7 1,182 47.8 1,964 0.078 2.22 925 Total 32,019 101.3 38,309 0.123 2.61 11,719 81
  • 82. El Gallo Phase 2 Metallurgical Testing Area Silver Recovery Gold Recovery (%) (%) Silver and Gold 84.3 83.2 Recovery Cyanide (kg/tonnes) 1.52 Lime (kg/tonne) 6.77 82
  • 83. El Gallo Phase 2 Financial Returns After Income Tax Base Case Spot Case ($25 Silver / ($32 Silver / $1,415 Gold) $1,700 Gold) IRR 26% 44% NPV 0% $184 $354 NPV 5% $118 $248 NPV 10% $73 $174 Annual Cash Flow $56 $82 Payback (yrs) 2.6 1.8 *Dollar figures in millions 83
  • 84. Simon Quick – VP Projects Permitting, Water Rights and Supply 84
  • 85. Experienced Team Permit Specialist: Water Rights + Supply: Patricia Aguayo Dr. Miguel Rangal •  MS Chemical Engineering •  Ph.D. in hydrology •  Permitted: Alamo Dorado, •  Current projects: La Bolsa Mine Torex, Timmins Gold, •  Good relationship with Goldcorp. SERMANAT •  Specializes in Water Rights Registration 85
  • 86. Sinaloa Permitting Favourable Marlin Gold permit submitted: El Gallo Complex (May 1st, 2012) •  Located in Sinaloa •  Granted 140 days •  Positive sign…! 86
  • 87. 3 Required Permits: (MIA) Manifestacion de Impacto Ambiental •  EIS equivalent USA (ETJ) Estudio Justificativo Para Cambio Uso Suelo •  Change of Land Use (ER) Analisis de Riesgo •  Risk Analysis 87
  • 88. Permitting Schedule MIA (60 – 120 Days) ETJ (60 – 120 Days) ER (60 – 120 Days) Permit Submission Expected Approval Q1  2013   Q2  2013   Q3  2013   Q4  2013   88
  • 89. Regulators Like Safe & Simple Dry Tailings Eliminates dam failure Reduces environmental impact Lowers reclamation costs 89
  • 90.   Water rights secured: 1 Million M3 / Year x 2   Water requirements satisfied: 17 l/s Well 5 Well 1 6.3 l/s 2.2 l/s Well 3 3.3 l/s Well 4 40.4 l/s - Production well l/s   Litre per second - 90
  • 91. Filter Press – Dry Stack Tailings 91