SlideShare una empresa de Scribd logo
1 de 58
T.Y. Planning ( SEM-VI )
College of Engineering, Pune
Project Formulation and
Management
Project Scope Management
Guided by:
Mahindra Bawaria
Presentation by:
Hrishikesh Satpute (111514040)
Project Scope Management
• Ensure that the project includes all the work required to complete
the project successfully.
• Defining and controlling what is and is not included in the project.
Define
Scope
Verify
Scope
Control
Scope
Create
WBS
Defining and
Documenting
stakeholders
need
Developing a
detailed
description of
project &
product
Monitoring
the status
& managing
changes to the
scope
baseline
Collect
Requirement
Formalizing
acceptance of
the completed
project
deliverables
Project
deliverables &
project works
into more
manageable
component
Figure No. 1.1 Processes in Project Scope Management.
1.1.
Collect Requirements
Inputs
1. Project charter
2. Stakeholder Register
Tools & Techniques
1. Interviews
2. Focus Groups
3. Facilitated Workshops
4. Group Creativity Techniques
5. Group Decision Making
Techniques
6. Questionnaires And Surveys
7. Observation
8. Prototypes.
Outputs
1. Requirements
Documentation
2. Requirements
Management Plan
3. Requirements Traceability
Matrix
• The process of determining, documenting and managing
stakeholders’ needs to meet the project objectives.
• The project’s success is directly influenced by the care taken in
capturing and managing project and product requirements.
• Collecting requirements is defining and managing customer
expectations.
Figure No. 1.2. Collect Requirements : Inputs, Tools & Techniques and Outputs.
Collect Requirement
Requirements
Product
Requirements
Project
Requirements
“Many organizations categorize requirements into project
requirements and product requirements.”
 Business
Requirements
 Project
Management
Requirements
 Delivery
Requirements
 Technical
Requirements
 Security
Requirements
 Performance
Requirements
Figure No. 1.3. Project Requirements and Product Requirements.
1.2.
Collect Requirements:
Inputs
Project Charter
Provide the project requirements and detail product
description of the project.
Outlines the project objective.
Stakeholder Register
The stakeholder register is used to identify stakeholders that
can provide information on detailed project and product
requirements.
1.3
Collect Requirements:
Tools and Techniques
Interviews
• An interview is a formal or informal approach performed by asking
prepared and spontaneous questions and recording the responses
to discover information.
Focus groups
• Focus groups bring together prequalified stakeholders and subject
matter experts to learn about their expectations and attitudes about
a proposed product, service, or result.
Facilitated Workshops
• Primary technique for quickly defining requirements and reconciling
stakeholder differences. Because of their interactive group nature,
well-facilitated sessions can build trust, foster relationships, and
improve communication among the participants which can lead to
increased stakeholder consensus.
• Issues can be discovered and resolved more quickly than in
individual sessions.
Group Creativity Techniques
 Brainstorming:
Generate and collect multiple ideas related to project and
product requirements.
 Nominal Group Technique:
Enhances brainstorming with a voting process used to rank
the most useful ideas for further brainstorming or for prioritization.
 The Delphi Technique:
A selected group of experts answers questionnaires and
provides feedback regarding the responses from each round of
requirements gathering.
 Idea/mind mapping:
Ideas created through individual brainstorming are
consolidated into a single map to reflect commonality and differences
in understanding, and generate new ideas.
 Affinity diagram:
Allows large numbers of ideas to be sorted into groups for
review and analysis.
Group Decision Making
Techniques
• Assessment process of multiple alternatives with an expected
outcome in the form of future actions resolution.
• These techniques can be used to generate, classify, and prioritize
product requirements.
• There are multiple methods of reaching a group decision, for
example:
 Unanimity: Everyone agrees on a single course of action.
 Majority: Support from more than 50% of the members of the
group.
 Plurality: The largest block in a group decides even if a majority is
not achieved.
 Dictatorship: One individual makes the decision for the group.
• Almost any of the decision methods described previously can be
applied to the group techniques used in the requirements gathering
process.
Questionnaires and Surveys
• Written sets of questions designed to quickly accumulate
information from a wide number of respondents.
Observations
• Direct way of viewing individuals in their environment and how they
perform
• Helpful for detailed processes when the people that use the product
have difficulty or are reluctant to articulate their requirements.
Prototypes
• Obtaining early feedback on requirements by providing a working
model of the expected product before actually building it.
• It allows stakeholders to experiment with a model of their final
product rather than only discussing abstract representations of their
requirements.
1.4
Collect Requirements:
Outputs
Requirements Documentation
• Describes how individual requirements meet the business need for
the project. Before being baselined, requirements must be
unambiguous (measurable and testable), traceable, complete,
consistent, and acceptable to key stakeholders.
Requirements Management Plan
• Documents how requirements will be analyzed and managed
throughout the project.
Requirements Traceability Matrix
• Table that links requirements to their origin and traces them
throughout the project life cycle.
• Helps ensure that each requirement adds business value by
linking it to the business and project objectives.
2.1.
Define Scope
Scope
• A process of developing a detailed description of the project and
product.
• The preparation of a detailed project scope statement is critical to
project success and builds upon the major deliverables, assumptions,
and constraints that are documented during Project Initiation.
• During planning, the project scope is defined and described with
greater specificity as more information about the project is known.
• Existing risks, assumptions, and constraints are analyzed for
completeness; additional risks, assumptions, and constraints are
added as necessary.
Inputs
1. Project charter
2. Requirements
documentation
3. Organizational
process assets
Tools & Techniques
1. Expert judgment
2. Product analysis
3. Alternatives
identification
4. Facilitated
workshops
Outputs
1. Project scope
statement
2. Project document
updates
Figure No. 2.1. Define Scope: Inputs, Tools & Techniques, and Outputs
Figure No. 2.2. Define Scope Data Flow Diagram
Collect
Requirement
Project Scope Management
Define Scope
Create WBS
Develop project
Charter
Enterprise /
Organization
Sequence Activities
Estimate Activity
Durations
Develop Schedule
Project Documents
Develop Project
Management Plan
Plan Risk
ManagementPerform Qualitative
Risk Analysis
• Organizational process assets
• Project Charter
• Requirement
Documentation • Project
document
updates
• Project
scope
statement
2.2.
Define Scope: Inputs
Project Charter
• The project charter provides the high-level project description and
product characteristics and contains project approval
requirements.
• If a project charter is not used in the performing organization,
then comparable information needs to be acquired or developed,
and used as a basis for the detailed Project Scope Statement.
Organizational Process Assets
Examples of organizational process assets that can influence the
Define Scope process includes :
• Policies, procedures, and templates for a project scope statement,
• Project files from previous projects, and
• Lessons learned from previous phases or projects.
2.3.
Scope: Tools and
Techniques
Expert Judgment
Expert judgment is often used to analyze the information
needed to develop the project scope statement. Such expertise is
provided by any group or individual with specialized knowledge or
training, and is available from many sources, including:
• Other units within the organization,
• Consultants,
• Stakeholders, including customers or sponsors,
• Professional and technical associations,
• Industry groups
Product Analysis
• For projects that have a product as a deliverable, as opposed to a
service or result, product analysis can be an effective tool.
• Product analysis includes techniques such as product breakdown,
systems analysis, requirements analysis, systems engineering, value
engineering, and value analysis.
Alternatives Identification
• Identifying alternatives is a technique used to generate different
approaches to execute and perform the work of the project.
• A variety of general management techniques can be used such as
brainstorming, lateral thinking, pair wise comparisons, etc.
2.4.
Scope: Outputs
Project Scope Statement
• The project scope statement describes, in detail, the project’s
deliverables and the work required to create those deliverables.
• It also provides a common understanding of the project scope
among project stakeholders.
• The degree and level of detail to which the project scope
statement defines the work that will be performed and the work
that is excluded can determine how well the project
management team can control the overall project scope.
• The detailed project scope statement includes, either directly, or
by reference to other documents.
Product Scope Description
• Elaborates the characteristics of the product, service and result
Product Acceptance Criteria
• Defines the process and criteria for accepting completed
product, service and result
Project Document Updates
Project documents that may be updated include, but are not
limited to:
• Stakeholder register,
• Requirements documentation, and
• Requirements traceability matrix.
Project Deliverables
• It include both the output and ancillary results such as Project
Management Report.
Project Exclusions
• Identifies what is excluded in the Project
Project Constrains
• List and describe the specific project constrains associated with
the project scope that limits the teams options.
3.1
Create Work Breakdown
Structure (WBS)
• The process of dividing project deliverables and project work into
smaller, more management component.
• It is hierarchical decomposition of work that to be executed.
Inputs
1. Project scope
statement
2. Requirements
documentation
3. Organizational
process assets
Tools & Techniques
1. Decomposition
Outputs
1. WBS
2.WBS dictionary
3.Scope baseline
4.Project document
updates.
Work Breakdown Structure
(WBS)
Figure No. 3.1..
Figure No. 3.2..
3.2.
Create WBS Inputs
Examples of organizational process assets that can influence the
Define Scope process include, but are not limited to:
• Policies, procedures, and templates for a project scope
statement,
• Project files from previous projects, and
• Lessons learned from previous phases or projects.
Project Scope Statement.
Requirements Documentation.
Organizational Process Assets.
3.3.
Create WBS :
Tools & Techniques.
Decomposition
• Subdivision of project deliverables into smaller, more manageable
component until the work is done.
• Deliverables are defined to the work package level.
• Work Package level is the lowest level in the WBS and is the point
at which the cost and activity duration for the work can be reliably
estimated and managed.
Simple Work Breakdown
Structure
Figure No. 3.1.
Figure No. 3.2.
3.4.
Create WBS Output
WBS
• WBS is finalized by establishing control account. These control
account provide hierarchical cost, schedule and resource
information.
• A control account is a management control point where scope,
cost, schedule are integrated and compared.
• A control account may contain one or more work package but each
work package must be associated with only one control account.
WBS Dictionary
• The WBS dictionary is document generated from WBS process.
• Which give detailed description of WBS, Work package and control
account.
• Scope baseline is component of Project management plan.
• Component of scope baseline includes:
1. Project scope statement.
2. WBS
3. WBS dictionary.
Scope Baseline
Project Document Updates
Project document gate updated due to creation of
WBS process.
4.1
Verify Scope
What does it mean?
What does it not mean?
• Reviewing deliverables with the customers to ensure that they
are completed satisfactorily and obtaining formal acceptance
from them.
• It does not mean to ensure the correctness of deliverables and meeting the
quality requirements. It is quality control. It is done before verifying scope or
sometimes also parallel
• Verifying scope is concerned with the acceptance only.
Collect
RequirementsDevelop Project
Management
Plan
Perform Quality
Control
Perform
Integrated
Change Control
Close Project or
Phase
Project
Documents
Verify Scope
Scope Baseline
Validate
Deliverables
Requirements
Documents
Change
Requests
Accepted
Deliverables
Project Documents
Updates
Project Scope Management
Requirements
Traceability Matrix
4.2
Verify Scope : Input
Requirements Documentation
Project Management Plan
Components of scope baseline includes,
• Project Scope Statement. Includes project scope description,
project deliverables and defines product user acceptance
criteria.
• WBS. Defines the deliverables and its decomposition in to work
packages.
• Lists all the project, product, technical and other types of
requirements.
• Also the acceptance criteria.
Requirements Traceability
Matrix
Links requirements to their origin and tracks them till
the project is completed.
These are completed and checked products for
correctness in terms of quality.
Validated Deliverables
4.3
Verify Scope : Techniques
Inspection
• Includes measuring, examining, and verifying whether the
work and deliverables meet the acceptance criteria.
• Also called as reviews, audits, walkthroughs.
4.4
Verify Scope : Outputs
Accepted Deliverables
The deliverables which meet acceptance criteria are
formally signed off and approved by customer or sponsor which
then leads to Close Project.
Change Request
• The deliverables which are not accepted are documented
along with the reasons for non-acceptance.
• These require change request for defect repair.
Project documents that may be updated as a result of
the verify scope process include any documents that define the
product or report status on product completion.
Project Document Updates
5.1
Control Scope
• Control Scope is the process of monitoring the status of the project
and product scope and managing the changes to the scope
baseline.
• Controlling the project scope ensures all requested changes and
recommendation and preventive action.
Inputs
1. Project management plan.
2.Work performance
information.
3.Requirements
documentation
4.Requirement traceability
matrix.
5.Organizational process
assets.
Tools & Techniques
1. Variance Analysis
Outputs
1. Work performance
measurement.
2.Organizational process
asset updates.
3.Change request.
4.Project management plan
update.
5.Project document update.
Figure No. 5.1.
5.2.
Control Scope : Input
Project Management Plan
Project management plan includes following information that is
used to control scope.
• Scope baseline
• Scope management plan
• Change management plan.
• Configuration management plan.
• Requirement management plan.
Work performance
information
Information about project progress, such as which
deliverables have started, their progress and which deliverables
have finished.
5.3.
Control Scope : Tools &
Technique
Variance Analysis
• It assess the magnitude of variation from original scope baseline.
• Important aspect of project control include determining the cause,
the degree of variance relative to the scope baseline and deciding
preventive or corrective action is required.
5.4.
Control Scope :Output
1. Work Performance
Measurement
Measurements include planned vs actual performance
or other scope performance measurements.
2. Organizational Process
Asset Updates
Updates includes causes of variance, corrective action
chosen and reason.
5. Project Document Update
3. Change Request
4. Project Management Plan
Update
• Scope baseline update
• Other baseline update
Analysis of scope performance can result in change
request to the scope baseline or other components of projects of the
project management plan..
Thanks!

Más contenido relacionado

La actualidad más candente

Presintation on Project constraint
Presintation on Project constraint Presintation on Project constraint
Presintation on Project constraint
university(kust)
 
Production operation management-scheduling PPT
Production operation management-scheduling PPTProduction operation management-scheduling PPT
Production operation management-scheduling PPT
NewGate India
 

La actualidad más candente (20)

Tender Evaluation.pptx
Tender Evaluation.pptxTender Evaluation.pptx
Tender Evaluation.pptx
 
Модуль 13. Лекция 53-54. Управление закупками проекта
Модуль 13. Лекция 53-54. Управление закупками проектаМодуль 13. Лекция 53-54. Управление закупками проекта
Модуль 13. Лекция 53-54. Управление закупками проекта
 
Project organization
Project organizationProject organization
Project organization
 
Presintation on Project constraint
Presintation on Project constraint Presintation on Project constraint
Presintation on Project constraint
 
Guideline for the Preparation of a Concept Note
Guideline for the Preparation of a Concept NoteGuideline for the Preparation of a Concept Note
Guideline for the Preparation of a Concept Note
 
Project Team Building
Project Team BuildingProject Team Building
Project Team Building
 
An Introduction to Project Management
An Introduction to Project Management An Introduction to Project Management
An Introduction to Project Management
 
Estimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkEstimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction Work
 
Production operation management-scheduling PPT
Production operation management-scheduling PPTProduction operation management-scheduling PPT
Production operation management-scheduling PPT
 
Project Estimating
Project EstimatingProject Estimating
Project Estimating
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
06. Project Management Process Groups
06. Project Management Process Groups06. Project Management Process Groups
06. Project Management Process Groups
 
Final Project Closing
Final Project ClosingFinal Project Closing
Final Project Closing
 
Project Scope Management - PMBOK6
Project Scope Management - PMBOK6Project Scope Management - PMBOK6
Project Scope Management - PMBOK6
 
Chap03 the project management process groups
Chap03 the project management process groupsChap03 the project management process groups
Chap03 the project management process groups
 
SCSI / RICS Presentation on Construction Quantum - Part 1
SCSI / RICS Presentation on Construction Quantum - Part 1SCSI / RICS Presentation on Construction Quantum - Part 1
SCSI / RICS Presentation on Construction Quantum - Part 1
 
Introduction to construction project management
Introduction to construction project managementIntroduction to construction project management
Introduction to construction project management
 
Project management
Project managementProject management
Project management
 
Swot analysis in project management
Swot analysis in project managementSwot analysis in project management
Swot analysis in project management
 
Project Closing
Project ClosingProject Closing
Project Closing
 

Similar a Project Formulation and Management - Project Scope Management

projectscopemanagement1-140220062122-phpapp01 (1).pdf
projectscopemanagement1-140220062122-phpapp01 (1).pdfprojectscopemanagement1-140220062122-phpapp01 (1).pdf
projectscopemanagement1-140220062122-phpapp01 (1).pdf
AbdiqadirOsman
 
Requirementsdevelopment 120207165817-phpapp02
Requirementsdevelopment 120207165817-phpapp02Requirementsdevelopment 120207165817-phpapp02
Requirementsdevelopment 120207165817-phpapp02
Oginni Olumide
 
Projects2016_Franks_Top10ReasonsProjectsFail
Projects2016_Franks_Top10ReasonsProjectsFailProjects2016_Franks_Top10ReasonsProjectsFail
Projects2016_Franks_Top10ReasonsProjectsFail
Barbara Franks
 

Similar a Project Formulation and Management - Project Scope Management (20)

projectscopemanagement1-140220062122-phpapp01 (1).pdf
projectscopemanagement1-140220062122-phpapp01 (1).pdfprojectscopemanagement1-140220062122-phpapp01 (1).pdf
projectscopemanagement1-140220062122-phpapp01 (1).pdf
 
PMP PMBok 5th ch 5 scope management
PMP PMBok 5th ch 5 scope managementPMP PMBok 5th ch 5 scope management
PMP PMBok 5th ch 5 scope management
 
Requirementsdevelopment 120207165817-phpapp02
Requirementsdevelopment 120207165817-phpapp02Requirementsdevelopment 120207165817-phpapp02
Requirementsdevelopment 120207165817-phpapp02
 
Pmp scope chapter 5
Pmp scope chapter 5Pmp scope chapter 5
Pmp scope chapter 5
 
Topic 7 - Project Scope Management.pdf
Topic 7 - Project Scope Management.pdfTopic 7 - Project Scope Management.pdf
Topic 7 - Project Scope Management.pdf
 
04 projectintegrationmanagement
04 projectintegrationmanagement04 projectintegrationmanagement
04 projectintegrationmanagement
 
Pmp chapter(5) Scope Management
Pmp chapter(5) Scope ManagementPmp chapter(5) Scope Management
Pmp chapter(5) Scope Management
 
PMBOK 5th Planning Process Group Part One
PMBOK 5th Planning Process Group Part OnePMBOK 5th Planning Process Group Part One
PMBOK 5th Planning Process Group Part One
 
Project scope management 1
Project scope management 1Project scope management 1
Project scope management 1
 
PMP-Scope Management area
PMP-Scope Management areaPMP-Scope Management area
PMP-Scope Management area
 
2. Project Scope Management.ppt
2. Project Scope Management.ppt2. Project Scope Management.ppt
2. Project Scope Management.ppt
 
Project Management Framework.pptx
Project Management Framework.pptxProject Management Framework.pptx
Project Management Framework.pptx
 
Project Scope Management
Project Scope ManagementProject Scope Management
Project Scope Management
 
Projects2016_Franks_Top10ReasonsProjectsFail
Projects2016_Franks_Top10ReasonsProjectsFailProjects2016_Franks_Top10ReasonsProjectsFail
Projects2016_Franks_Top10ReasonsProjectsFail
 
Is your project not going well this will help you get it back on track
Is your project not going well this will help you get it back on trackIs your project not going well this will help you get it back on track
Is your project not going well this will help you get it back on track
 
Session 04 - Project Planning
Session 04 - Project PlanningSession 04 - Project Planning
Session 04 - Project Planning
 
04 projectintegrationmanagement
04 projectintegrationmanagement04 projectintegrationmanagement
04 projectintegrationmanagement
 
Session 3 4th edition
Session   3 4th editionSession   3 4th edition
Session 3 4th edition
 
05 project scope management
05 project scope management05 project scope management
05 project scope management
 
CISA Training - Chapter 3 - 2016
CISA Training - Chapter 3 - 2016CISA Training - Chapter 3 - 2016
CISA Training - Chapter 3 - 2016
 

Más de Hrishikesh Satpute

Más de Hrishikesh Satpute (15)

Cyclone Phailin in Odisha, 2013
Cyclone Phailin in Odisha, 2013Cyclone Phailin in Odisha, 2013
Cyclone Phailin in Odisha, 2013
 
Energy Efficient Planning for a Local Area: A Case Study of Aurangabad City (...
Energy Efficient Planning for a Local Area: A Case Study of Aurangabad City (...Energy Efficient Planning for a Local Area: A Case Study of Aurangabad City (...
Energy Efficient Planning for a Local Area: A Case Study of Aurangabad City (...
 
Indian Green Building Council (IGBC) Green New Buildings – 2014
Indian Green Building Council (IGBC) Green New Buildings – 2014Indian Green Building Council (IGBC) Green New Buildings – 2014
Indian Green Building Council (IGBC) Green New Buildings – 2014
 
The Kaldor Hicks Compensation Principle
The Kaldor Hicks Compensation PrincipleThe Kaldor Hicks Compensation Principle
The Kaldor Hicks Compensation Principle
 
Cost Benefit Analysis
Cost Benefit AnalysisCost Benefit Analysis
Cost Benefit Analysis
 
Ion Chromatography
Ion ChromatographyIon Chromatography
Ion Chromatography
 
Multiple Nuclei Model by Harris and Ullman (1945)
Multiple Nuclei Model by Harris and Ullman (1945)Multiple Nuclei Model by Harris and Ullman (1945)
Multiple Nuclei Model by Harris and Ullman (1945)
 
Physical Infrastructure Assessment Report: A case study of Gaya, Bihar
Physical Infrastructure Assessment Report: A case study of Gaya, BiharPhysical Infrastructure Assessment Report: A case study of Gaya, Bihar
Physical Infrastructure Assessment Report: A case study of Gaya, Bihar
 
Paper Review of Local building materials: affordable strategy for housing the...
Paper Review of Local building materials: affordable strategy for housing the...Paper Review of Local building materials: affordable strategy for housing the...
Paper Review of Local building materials: affordable strategy for housing the...
 
Jalna Municipal Council Budget Analysis
Jalna Municipal Council Budget AnalysisJalna Municipal Council Budget Analysis
Jalna Municipal Council Budget Analysis
 
PLANNING AND MANAGEMENT OF INFORMAL SECTOR REPORT - PUNE SLUM
 PLANNING AND MANAGEMENT OF INFORMAL SECTOR REPORT - PUNE SLUM PLANNING AND MANAGEMENT OF INFORMAL SECTOR REPORT - PUNE SLUM
PLANNING AND MANAGEMENT OF INFORMAL SECTOR REPORT - PUNE SLUM
 
Minning Application and Remote Sensing Using Aster Imagery
Minning Application and Remote Sensing Using Aster ImageryMinning Application and Remote Sensing Using Aster Imagery
Minning Application and Remote Sensing Using Aster Imagery
 
Local Area Plan : Vancouver
Local Area Plan : VancouverLocal Area Plan : Vancouver
Local Area Plan : Vancouver
 
Housing and Community Planning - Chennai
Housing and Community Planning - ChennaiHousing and Community Planning - Chennai
Housing and Community Planning - Chennai
 
Latur, Patna RP & PMAY, Rurban Scheme
Latur, Patna RP & PMAY, Rurban SchemeLatur, Patna RP & PMAY, Rurban Scheme
Latur, Patna RP & PMAY, Rurban Scheme
 

Último

Salient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsSalient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functions
KarakKing
 
Vishram Singh - Textbook of Anatomy Upper Limb and Thorax.. Volume 1 (1).pdf
Vishram Singh - Textbook of Anatomy  Upper Limb and Thorax.. Volume 1 (1).pdfVishram Singh - Textbook of Anatomy  Upper Limb and Thorax.. Volume 1 (1).pdf
Vishram Singh - Textbook of Anatomy Upper Limb and Thorax.. Volume 1 (1).pdf
ssuserdda66b
 

Último (20)

Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
Graduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - EnglishGraduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - English
 
Spatium Project Simulation student brief
Spatium Project Simulation student briefSpatium Project Simulation student brief
Spatium Project Simulation student brief
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)
 
ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
 
SOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning PresentationSOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning Presentation
 
Salient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsSalient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functions
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
Fostering Friendships - Enhancing Social Bonds in the Classroom
Fostering Friendships - Enhancing Social Bonds  in the ClassroomFostering Friendships - Enhancing Social Bonds  in the Classroom
Fostering Friendships - Enhancing Social Bonds in the Classroom
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
Vishram Singh - Textbook of Anatomy Upper Limb and Thorax.. Volume 1 (1).pdf
Vishram Singh - Textbook of Anatomy  Upper Limb and Thorax.. Volume 1 (1).pdfVishram Singh - Textbook of Anatomy  Upper Limb and Thorax.. Volume 1 (1).pdf
Vishram Singh - Textbook of Anatomy Upper Limb and Thorax.. Volume 1 (1).pdf
 
Understanding Accommodations and Modifications
Understanding  Accommodations and ModificationsUnderstanding  Accommodations and Modifications
Understanding Accommodations and Modifications
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdf
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 

Project Formulation and Management - Project Scope Management

  • 1. T.Y. Planning ( SEM-VI ) College of Engineering, Pune Project Formulation and Management Project Scope Management Guided by: Mahindra Bawaria Presentation by: Hrishikesh Satpute (111514040)
  • 2. Project Scope Management • Ensure that the project includes all the work required to complete the project successfully. • Defining and controlling what is and is not included in the project. Define Scope Verify Scope Control Scope Create WBS Defining and Documenting stakeholders need Developing a detailed description of project & product Monitoring the status & managing changes to the scope baseline Collect Requirement Formalizing acceptance of the completed project deliverables Project deliverables & project works into more manageable component Figure No. 1.1 Processes in Project Scope Management.
  • 4. Inputs 1. Project charter 2. Stakeholder Register Tools & Techniques 1. Interviews 2. Focus Groups 3. Facilitated Workshops 4. Group Creativity Techniques 5. Group Decision Making Techniques 6. Questionnaires And Surveys 7. Observation 8. Prototypes. Outputs 1. Requirements Documentation 2. Requirements Management Plan 3. Requirements Traceability Matrix • The process of determining, documenting and managing stakeholders’ needs to meet the project objectives. • The project’s success is directly influenced by the care taken in capturing and managing project and product requirements. • Collecting requirements is defining and managing customer expectations. Figure No. 1.2. Collect Requirements : Inputs, Tools & Techniques and Outputs. Collect Requirement
  • 5. Requirements Product Requirements Project Requirements “Many organizations categorize requirements into project requirements and product requirements.”  Business Requirements  Project Management Requirements  Delivery Requirements  Technical Requirements  Security Requirements  Performance Requirements Figure No. 1.3. Project Requirements and Product Requirements.
  • 7. Project Charter Provide the project requirements and detail product description of the project. Outlines the project objective. Stakeholder Register The stakeholder register is used to identify stakeholders that can provide information on detailed project and product requirements.
  • 9. Interviews • An interview is a formal or informal approach performed by asking prepared and spontaneous questions and recording the responses to discover information. Focus groups • Focus groups bring together prequalified stakeholders and subject matter experts to learn about their expectations and attitudes about a proposed product, service, or result. Facilitated Workshops • Primary technique for quickly defining requirements and reconciling stakeholder differences. Because of their interactive group nature, well-facilitated sessions can build trust, foster relationships, and improve communication among the participants which can lead to increased stakeholder consensus. • Issues can be discovered and resolved more quickly than in individual sessions.
  • 10. Group Creativity Techniques  Brainstorming: Generate and collect multiple ideas related to project and product requirements.  Nominal Group Technique: Enhances brainstorming with a voting process used to rank the most useful ideas for further brainstorming or for prioritization.  The Delphi Technique: A selected group of experts answers questionnaires and provides feedback regarding the responses from each round of requirements gathering.  Idea/mind mapping: Ideas created through individual brainstorming are consolidated into a single map to reflect commonality and differences in understanding, and generate new ideas.  Affinity diagram: Allows large numbers of ideas to be sorted into groups for review and analysis.
  • 11. Group Decision Making Techniques • Assessment process of multiple alternatives with an expected outcome in the form of future actions resolution. • These techniques can be used to generate, classify, and prioritize product requirements. • There are multiple methods of reaching a group decision, for example:  Unanimity: Everyone agrees on a single course of action.  Majority: Support from more than 50% of the members of the group.  Plurality: The largest block in a group decides even if a majority is not achieved.  Dictatorship: One individual makes the decision for the group. • Almost any of the decision methods described previously can be applied to the group techniques used in the requirements gathering process.
  • 12. Questionnaires and Surveys • Written sets of questions designed to quickly accumulate information from a wide number of respondents. Observations • Direct way of viewing individuals in their environment and how they perform • Helpful for detailed processes when the people that use the product have difficulty or are reluctant to articulate their requirements. Prototypes • Obtaining early feedback on requirements by providing a working model of the expected product before actually building it. • It allows stakeholders to experiment with a model of their final product rather than only discussing abstract representations of their requirements.
  • 14. Requirements Documentation • Describes how individual requirements meet the business need for the project. Before being baselined, requirements must be unambiguous (measurable and testable), traceable, complete, consistent, and acceptable to key stakeholders. Requirements Management Plan • Documents how requirements will be analyzed and managed throughout the project. Requirements Traceability Matrix • Table that links requirements to their origin and traces them throughout the project life cycle. • Helps ensure that each requirement adds business value by linking it to the business and project objectives.
  • 16. Scope • A process of developing a detailed description of the project and product. • The preparation of a detailed project scope statement is critical to project success and builds upon the major deliverables, assumptions, and constraints that are documented during Project Initiation. • During planning, the project scope is defined and described with greater specificity as more information about the project is known. • Existing risks, assumptions, and constraints are analyzed for completeness; additional risks, assumptions, and constraints are added as necessary. Inputs 1. Project charter 2. Requirements documentation 3. Organizational process assets Tools & Techniques 1. Expert judgment 2. Product analysis 3. Alternatives identification 4. Facilitated workshops Outputs 1. Project scope statement 2. Project document updates Figure No. 2.1. Define Scope: Inputs, Tools & Techniques, and Outputs
  • 17. Figure No. 2.2. Define Scope Data Flow Diagram Collect Requirement Project Scope Management Define Scope Create WBS Develop project Charter Enterprise / Organization Sequence Activities Estimate Activity Durations Develop Schedule Project Documents Develop Project Management Plan Plan Risk ManagementPerform Qualitative Risk Analysis • Organizational process assets • Project Charter • Requirement Documentation • Project document updates • Project scope statement
  • 19. Project Charter • The project charter provides the high-level project description and product characteristics and contains project approval requirements. • If a project charter is not used in the performing organization, then comparable information needs to be acquired or developed, and used as a basis for the detailed Project Scope Statement. Organizational Process Assets Examples of organizational process assets that can influence the Define Scope process includes : • Policies, procedures, and templates for a project scope statement, • Project files from previous projects, and • Lessons learned from previous phases or projects.
  • 21. Expert Judgment Expert judgment is often used to analyze the information needed to develop the project scope statement. Such expertise is provided by any group or individual with specialized knowledge or training, and is available from many sources, including: • Other units within the organization, • Consultants, • Stakeholders, including customers or sponsors, • Professional and technical associations, • Industry groups Product Analysis • For projects that have a product as a deliverable, as opposed to a service or result, product analysis can be an effective tool. • Product analysis includes techniques such as product breakdown, systems analysis, requirements analysis, systems engineering, value engineering, and value analysis.
  • 22. Alternatives Identification • Identifying alternatives is a technique used to generate different approaches to execute and perform the work of the project. • A variety of general management techniques can be used such as brainstorming, lateral thinking, pair wise comparisons, etc.
  • 24. Project Scope Statement • The project scope statement describes, in detail, the project’s deliverables and the work required to create those deliverables. • It also provides a common understanding of the project scope among project stakeholders. • The degree and level of detail to which the project scope statement defines the work that will be performed and the work that is excluded can determine how well the project management team can control the overall project scope. • The detailed project scope statement includes, either directly, or by reference to other documents. Product Scope Description • Elaborates the characteristics of the product, service and result Product Acceptance Criteria • Defines the process and criteria for accepting completed product, service and result
  • 25. Project Document Updates Project documents that may be updated include, but are not limited to: • Stakeholder register, • Requirements documentation, and • Requirements traceability matrix. Project Deliverables • It include both the output and ancillary results such as Project Management Report. Project Exclusions • Identifies what is excluded in the Project Project Constrains • List and describe the specific project constrains associated with the project scope that limits the teams options.
  • 27. • The process of dividing project deliverables and project work into smaller, more management component. • It is hierarchical decomposition of work that to be executed. Inputs 1. Project scope statement 2. Requirements documentation 3. Organizational process assets Tools & Techniques 1. Decomposition Outputs 1. WBS 2.WBS dictionary 3.Scope baseline 4.Project document updates. Work Breakdown Structure (WBS) Figure No. 3.1..
  • 30. Examples of organizational process assets that can influence the Define Scope process include, but are not limited to: • Policies, procedures, and templates for a project scope statement, • Project files from previous projects, and • Lessons learned from previous phases or projects. Project Scope Statement. Requirements Documentation. Organizational Process Assets.
  • 31. 3.3. Create WBS : Tools & Techniques.
  • 32. Decomposition • Subdivision of project deliverables into smaller, more manageable component until the work is done. • Deliverables are defined to the work package level. • Work Package level is the lowest level in the WBS and is the point at which the cost and activity duration for the work can be reliably estimated and managed.
  • 36. WBS • WBS is finalized by establishing control account. These control account provide hierarchical cost, schedule and resource information. • A control account is a management control point where scope, cost, schedule are integrated and compared. • A control account may contain one or more work package but each work package must be associated with only one control account. WBS Dictionary • The WBS dictionary is document generated from WBS process. • Which give detailed description of WBS, Work package and control account.
  • 37. • Scope baseline is component of Project management plan. • Component of scope baseline includes: 1. Project scope statement. 2. WBS 3. WBS dictionary. Scope Baseline Project Document Updates Project document gate updated due to creation of WBS process.
  • 39. What does it mean? What does it not mean? • Reviewing deliverables with the customers to ensure that they are completed satisfactorily and obtaining formal acceptance from them. • It does not mean to ensure the correctness of deliverables and meeting the quality requirements. It is quality control. It is done before verifying scope or sometimes also parallel • Verifying scope is concerned with the acceptance only.
  • 40. Collect RequirementsDevelop Project Management Plan Perform Quality Control Perform Integrated Change Control Close Project or Phase Project Documents Verify Scope Scope Baseline Validate Deliverables Requirements Documents Change Requests Accepted Deliverables Project Documents Updates Project Scope Management Requirements Traceability Matrix
  • 42. Requirements Documentation Project Management Plan Components of scope baseline includes, • Project Scope Statement. Includes project scope description, project deliverables and defines product user acceptance criteria. • WBS. Defines the deliverables and its decomposition in to work packages. • Lists all the project, product, technical and other types of requirements. • Also the acceptance criteria.
  • 43. Requirements Traceability Matrix Links requirements to their origin and tracks them till the project is completed. These are completed and checked products for correctness in terms of quality. Validated Deliverables
  • 44. 4.3 Verify Scope : Techniques
  • 45. Inspection • Includes measuring, examining, and verifying whether the work and deliverables meet the acceptance criteria. • Also called as reviews, audits, walkthroughs.
  • 47. Accepted Deliverables The deliverables which meet acceptance criteria are formally signed off and approved by customer or sponsor which then leads to Close Project.
  • 48. Change Request • The deliverables which are not accepted are documented along with the reasons for non-acceptance. • These require change request for defect repair. Project documents that may be updated as a result of the verify scope process include any documents that define the product or report status on product completion. Project Document Updates
  • 50. • Control Scope is the process of monitoring the status of the project and product scope and managing the changes to the scope baseline. • Controlling the project scope ensures all requested changes and recommendation and preventive action. Inputs 1. Project management plan. 2.Work performance information. 3.Requirements documentation 4.Requirement traceability matrix. 5.Organizational process assets. Tools & Techniques 1. Variance Analysis Outputs 1. Work performance measurement. 2.Organizational process asset updates. 3.Change request. 4.Project management plan update. 5.Project document update. Figure No. 5.1.
  • 52. Project Management Plan Project management plan includes following information that is used to control scope. • Scope baseline • Scope management plan • Change management plan. • Configuration management plan. • Requirement management plan. Work performance information Information about project progress, such as which deliverables have started, their progress and which deliverables have finished.
  • 53. 5.3. Control Scope : Tools & Technique
  • 54. Variance Analysis • It assess the magnitude of variation from original scope baseline. • Important aspect of project control include determining the cause, the degree of variance relative to the scope baseline and deciding preventive or corrective action is required.
  • 56. 1. Work Performance Measurement Measurements include planned vs actual performance or other scope performance measurements. 2. Organizational Process Asset Updates Updates includes causes of variance, corrective action chosen and reason.
  • 57. 5. Project Document Update 3. Change Request 4. Project Management Plan Update • Scope baseline update • Other baseline update Analysis of scope performance can result in change request to the scope baseline or other components of projects of the project management plan..