INTRODUCTION TO:
PROJECT MANAGEMENT
      PROJECT EXECUTION
     MODULE 2: Day 2 / S2

       by: DREAMSOFT (M)SDN BHD
       http://www.thedreamsoft.com
           admin@thedreamsoft.com
Work Breakdown Structure (WBS)

• A detailed, hierarchical (from
  general to specific) tree structure
  of deliverables and tasks that
  need to be performed to
  complete a project.
purpose or WBS


• to identify actual tasks to be done
  in a project. Serves as basis for
  project planning.

• An extension to PERT.
Standard Work Breakdown Structure
                              Standard Work Breakdown
                                   Structure (WBS)




     1.0           2.0          3.0                 4.0             5.0           6.0
   Mission     Investment     Solution        Implementation    In-Service    Disposition
   Analysis      Analysis   Development                        Management




 Activity A   Activity B    Activity C       Activity D        Activity E    Activity F




  Pre-Project Activities                  Project Specific Activities

                                                                                            LEGEND



                                                     Decomposes to lower level WBS elements
Project Management
          Day 1 / S2
Overview on Planning

             Who Will   By When Must
             Do It?     It Be Done?

                                       How Much Will
How Should                             It Cost?
It Be Done


What Must
Be Done                                 How Good Does
                                        It Has To Be?
Project Planning


Definition
• A Project Plan sets out the phases,
  activities and tasks needed to deliver
  a project.
• The timeframes required to deliver the
  project, along with the resources and
  milestones are also shown in the
  Project Plan.
Main Output From Project Planning



        PROJECT
        PLANNING



        Project       PERT Diagram   Gantt Chart
        Predecessor
        Table
History

• PERT is a network model that allows for
  randomness in activity completion
  times.
• PERT was developed in the late 1950's
  for the U.S. Navy's Polaris project
  having thousands of contractors.
  – It has the potential to reduce both the
    time and cost required to complete a
    project.
Methods

Main methods used in project planning:

3. Project Schedule
4. PERT
5. Gantt Chart
1. Project Schedule

Definition

  • An organized method of presenting in-
    formation on when activities need to be
    started, how long activities are planned
    to take, and when activities are planned
    to be completed.
  • A schedule should also reflect the logical
    relationships between activities.
2. PERT (Project Evaluation Review
Technique)
Definition

• A diagram that shows tasks and their
  relationships. Limited because it shows
  only task relationships. Strength: easy
  to read task relationships.
  – Also known as Network Diagram
Tasks

 Duration of Tasks          Durations
                     PERT   (months)
Precedors of Tasks
3. Gantt Chart

Definition

• A bar chart. While visually appealing
  on a task/duration basis, it is limited
  because it does not show task or
  resource relationships well.
  – Strength: easy to maintain and read.
An Example of a Gantt Chart
Task Name        Predecessor   Task ID Estimated   1 2 3 4 5 6 7 8 9 10
                                          Time


Mark Utilities       B           A         3
Dig Holes            C           B         2
Buy Trees            D           C         1
Buy Flowers           E          D         1
Plant Trees           F          E         2
Plant Flowers       G,H          F         1
Buy Cover             -          G         1
Install Cover         -          H         1

                                          12
Steps in the PERT Planning Process

PERT planning involves the following steps:

• Identify the specific activities and milestones
• Determine the proper sequence of the activities
• Construct a network diagram
• Estimate the time required for each activity
---------------------------
• Determine the Critical Path
• Update the PERT Chart as the project progresses
1. Identify Activities and Milestones


• The activities are the tasks required to
  complete the project.
• The milestones are the events marking
  the beginning and end of one or more
  activities.
  – It is helpful to list the tasks in a table that in
    later steps can be expanded to include
    information on sequence and duration.
2. Determine Activity Sequence

• This step may be combined with the
  activity identification step since the
  activity sequence is evident for some
  tasks.
  – Other tasks may require more analysis to
    determine the exact order in which they
    must be performed.
3. Construct the Network Diagram

• Using the activity sequence
  information, a network diagram can
  be drawn showing the sequence of
  the serial and parallel activities.
  – For the original activity-on-arc model, the
    activities are depicted by arrowed lines
    and milestones are depicted by circles or
    "bubbles".
4. Estimate Activity Times (ET)
For each activity, the model usually includes three
  time estimates:

• Optimistic time - generally the shortest time in which
  the activity can be completed.

• Most likely time - the completion time having the
  highest probability. Note that this time is different
  from the expected time.

• Pessimistic time - the longest time that an activity
  might require. Three standard deviations from the
  mean is commonly used for the pessimistic time.
Expected Time



               Expected time =
  ( Optimistic + 4 x Most likely + Pessimistic ) / 6
Standard Work Breakdown Structure
                                             Standard Work Breakdown
                                                  Structure (WBS)




     1.0            2.0            3.0           4.0             5.0            6.0            7.0            8.0
  ET:3 days      ET:2 days     ET: 1 day     ET: 1 day        ET2 days       ET:1 day       ET:1 day       ET:1 day




    A                B           C              D                 E              F             G               H
Mark Utilities   Dig Holes    Buy Trees    Buy Flowers       Plant Trees   Plant Flowers   Buy Edging   Install Edging




Project Specific Activities

                                                                                             LEGEND



                                                         Decomposes to lower level WBS elements
An Example of a Logical Sequence
Predecessor Table

Task Name /               Estimated Time   Activity   Predecessor
Description

Mark Utilities                                           B,C,D
Dig Holes                                                  E
Buy Trees                                                G,E
Buy Flowers                                                F
Plant Trees                                                F
Plant Flowers                                             E,D
Buy Edging                                                C
Install Edging                                            F,G
                 TOTALS

      Card Activities****
From PERT to GANTT Chart
An Example of a Gantt Chart
Task Name /      Predecessor Activity   Estimated    1 2 3 4 5 6 7 8 9 10
Description                              Time (ET)


Mark Utilities        B         A           3
Dig Holes            C           B          2
Buy Trees             D         C           1
Buy Flowers           E         D           1
Plant Trees           F          E          2
Plant Flowers       G,H          F          1
Buy Cover             -         G           1
Install Cover         -         H           1

                                           12
Exercise:
‘PROJECT LANDSCAPE DARUL AMAN’
Refer to Template:

• Predecessor Table
• PERT
• GANTT Chart
lesson learned

•   __________________________________   •   __________________________________
•   __________________________________   •   __________________________________
•   __________________________________   •   __________________________________
•   __________________________________   •   __________________________________
•   __________________________________   •   __________________________________
•   __________________________________   •   __________________________________
•   __________________________________   •   __________________________________
•   __________________________________   •   __________________________________
•   __________________________________   •   __________________________________
•   __________________________________   •   __________________________________
•   __________________________________   •   __________________________________
•   __________________________________   •   __________________________________
•   __________________________________   •   __________________________________
•   __________________________________   •   __________________________________
•   __________________________________   •   __________________________________

Más contenido relacionado

La actualidad más candente

Project Management Life Cycle
Project Management Life CycleProject Management Life Cycle
Project Management Life CycleReema
 
Lec 03 project life cycle
Lec 03 project life cycleLec 03 project life cycle
Lec 03 project life cycleSAJID ALI RUK
 
Project management
Project managementProject management
Project managementArsh Koul
 
Project planning
Project planning Project planning
Project planning Dereje Jima
 
Project planning and planning process
Project planning and planning processProject planning and planning process
Project planning and planning processShamim Hossain
 
Project monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoringProject monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoringSandeep Kumar
 
Project planning and Scheduling
Project planning and SchedulingProject planning and Scheduling
Project planning and Schedulingsaurabmi2
 
Project Monitoring And Controlling
Project Monitoring And ControllingProject Monitoring And Controlling
Project Monitoring And ControllingTom Milner
 
Elements of Project Management
Elements of Project ManagementElements of Project Management
Elements of Project ManagementKevin Thomas
 
PROJECT CONTROL PROCESS
PROJECT CONTROL PROCESS PROJECT CONTROL PROCESS
PROJECT CONTROL PROCESS Akash Prasanna
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Managementmovinghats
 
Project planning and scheduling
Project planning and schedulingProject planning and scheduling
Project planning and schedulingadeel hamid
 
An Introduction to Project Management
An Introduction to Project Management An Introduction to Project Management
An Introduction to Project Management Krishna Kant
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project schedulingSoe Naing Win
 
Introduction to Project Management (workshop) - v.1
Introduction to Project Management (workshop) - v.1Introduction to Project Management (workshop) - v.1
Introduction to Project Management (workshop) - v.1Mena M. Eissa
 
Project management (1)
Project management (1)Project management (1)
Project management (1)Hetal Visaria
 

La actualidad más candente (20)

Project Management Life Cycle
Project Management Life CycleProject Management Life Cycle
Project Management Life Cycle
 
Lec 03 project life cycle
Lec 03 project life cycleLec 03 project life cycle
Lec 03 project life cycle
 
Project Implementation
Project ImplementationProject Implementation
Project Implementation
 
Project management
Project managementProject management
Project management
 
Project planning
Project planning Project planning
Project planning
 
Project planning and planning process
Project planning and planning processProject planning and planning process
Project planning and planning process
 
project monitoring and control
project monitoring and controlproject monitoring and control
project monitoring and control
 
Project monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoringProject monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoring
 
Project planning and Scheduling
Project planning and SchedulingProject planning and Scheduling
Project planning and Scheduling
 
Project Monitoring And Controlling
Project Monitoring And ControllingProject Monitoring And Controlling
Project Monitoring And Controlling
 
Elements of Project Management
Elements of Project ManagementElements of Project Management
Elements of Project Management
 
PROJECT CONTROL PROCESS
PROJECT CONTROL PROCESS PROJECT CONTROL PROCESS
PROJECT CONTROL PROCESS
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
 
Project planning and scheduling
Project planning and schedulingProject planning and scheduling
Project planning and scheduling
 
An Introduction to Project Management
An Introduction to Project Management An Introduction to Project Management
An Introduction to Project Management
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
 
Project Development
Project Development Project Development
Project Development
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project scheduling
 
Introduction to Project Management (workshop) - v.1
Introduction to Project Management (workshop) - v.1Introduction to Project Management (workshop) - v.1
Introduction to Project Management (workshop) - v.1
 
Project management (1)
Project management (1)Project management (1)
Project management (1)
 

Destacado

Planning and Resourcing a Project
Planning and Resourcing a ProjectPlanning and Resourcing a Project
Planning and Resourcing a ProjectNishant Munjal
 
Project Planning Basics - Everything you need to start managing a project
Project Planning Basics - Everything you need to start managing a projectProject Planning Basics - Everything you need to start managing a project
Project Planning Basics - Everything you need to start managing a projectKeely Killpack, PhD
 
4 Project Pre-Planning & Stakeholder Analysis
4 Project Pre-Planning & Stakeholder Analysis4 Project Pre-Planning & Stakeholder Analysis
4 Project Pre-Planning & Stakeholder AnalysisTony
 
3 Project Cycle and Planning (4-6 hours)
3 Project Cycle and Planning (4-6 hours)3 Project Cycle and Planning (4-6 hours)
3 Project Cycle and Planning (4-6 hours)Tony
 
Managing Project Resources
Managing Project ResourcesManaging Project Resources
Managing Project ResourcesToyin Osunlaja
 
Planning And Controlling
Planning And ControllingPlanning And Controlling
Planning And ControllingManuel Ardales
 
5 The Logical Framework - a short course for NGOs
5 The Logical Framework - a short course for NGOs5 The Logical Framework - a short course for NGOs
5 The Logical Framework - a short course for NGOsTony
 
Importance of Ethics
Importance of EthicsImportance of Ethics
Importance of EthicsSayak Sarkar
 
Introduction to Agile Project Planning and Project Management
Introduction to Agile Project Planning and Project ManagementIntroduction to Agile Project Planning and Project Management
Introduction to Agile Project Planning and Project ManagementMike Cottmeyer
 
Fundamentals of Project Management
Fundamentals of Project ManagementFundamentals of Project Management
Fundamentals of Project ManagementRodolfo Siles
 

Destacado (15)

Project planning
Project planning Project planning
Project planning
 
Planning and Resourcing a Project
Planning and Resourcing a ProjectPlanning and Resourcing a Project
Planning and Resourcing a Project
 
Project Planning Basics - Everything you need to start managing a project
Project Planning Basics - Everything you need to start managing a projectProject Planning Basics - Everything you need to start managing a project
Project Planning Basics - Everything you need to start managing a project
 
4 Project Pre-Planning & Stakeholder Analysis
4 Project Pre-Planning & Stakeholder Analysis4 Project Pre-Planning & Stakeholder Analysis
4 Project Pre-Planning & Stakeholder Analysis
 
3 Project Cycle and Planning (4-6 hours)
3 Project Cycle and Planning (4-6 hours)3 Project Cycle and Planning (4-6 hours)
3 Project Cycle and Planning (4-6 hours)
 
Managing Project Resources
Managing Project ResourcesManaging Project Resources
Managing Project Resources
 
Project planning and project work plan
Project planning and project work planProject planning and project work plan
Project planning and project work plan
 
Project organization
Project organizationProject organization
Project organization
 
Planning And Controlling
Planning And ControllingPlanning And Controlling
Planning And Controlling
 
Project planning and control
Project planning and controlProject planning and control
Project planning and control
 
5 The Logical Framework - a short course for NGOs
5 The Logical Framework - a short course for NGOs5 The Logical Framework - a short course for NGOs
5 The Logical Framework - a short course for NGOs
 
Importance of Ethics
Importance of EthicsImportance of Ethics
Importance of Ethics
 
Introduction to Agile Project Planning and Project Management
Introduction to Agile Project Planning and Project ManagementIntroduction to Agile Project Planning and Project Management
Introduction to Agile Project Planning and Project Management
 
Ethics
EthicsEthics
Ethics
 
Fundamentals of Project Management
Fundamentals of Project ManagementFundamentals of Project Management
Fundamentals of Project Management
 

Similar a Project Planning

Chapter 2
Chapter 2Chapter 2
Chapter 2Mr SMAK
 
Chapter 2 ASE
Chapter 2 ASEChapter 2 ASE
Chapter 2 ASEMr SMAK
 
Software project-scheduling
Software project-schedulingSoftware project-scheduling
Software project-schedulingsaurabhshertukde
 
WBS And Scheduling for eLearning Project Managament
WBS And Scheduling for eLearning Project ManagamentWBS And Scheduling for eLearning Project Managament
WBS And Scheduling for eLearning Project ManagamentMichael M Grant
 
Ms Project Workshop
Ms Project WorkshopMs Project Workshop
Ms Project WorkshopEder Alves
 
Project Management Through Gantt & Pert Chart
Project Management Through Gantt & Pert ChartProject Management Through Gantt & Pert Chart
Project Management Through Gantt & Pert ChartVinay Prajapati
 
Project mgt
Project mgtProject mgt
Project mgtNgoc Dep
 
Barbayanni results and approach 2013
Barbayanni results and approach 2013Barbayanni results and approach 2013
Barbayanni results and approach 2013Matilda Barbayanni
 
Barbayanni -results and approach
Barbayanni -results and approach Barbayanni -results and approach
Barbayanni -results and approach Matilda Barbayanni
 
Barbayanni -Results and Approach
Barbayanni -Results and Approach Barbayanni -Results and Approach
Barbayanni -Results and Approach Matilda Barbayanni
 
Barbayanni results and approach 2013
Barbayanni results and approach 2013Barbayanni results and approach 2013
Barbayanni results and approach 2013Matilda Barbayanni
 
Eggert.joe
Eggert.joeEggert.joe
Eggert.joeNASAPMC
 
Software engineering ppt on pert and gantt charts
Software engineering ppt on pert and gantt chartsSoftware engineering ppt on pert and gantt charts
Software engineering ppt on pert and gantt chartsGovadaDhana
 

Similar a Project Planning (20)

Chapter 2
Chapter 2Chapter 2
Chapter 2
 
Chapter 2 ASE
Chapter 2 ASEChapter 2 ASE
Chapter 2 ASE
 
Software project-scheduling
Software project-schedulingSoftware project-scheduling
Software project-scheduling
 
WBS And Scheduling for eLearning Project Managament
WBS And Scheduling for eLearning Project ManagamentWBS And Scheduling for eLearning Project Managament
WBS And Scheduling for eLearning Project Managament
 
Ms Project Workshop
Ms Project WorkshopMs Project Workshop
Ms Project Workshop
 
Chap003
Chap003Chap003
Chap003
 
Ch3 proj.mgt
Ch3 proj.mgtCh3 proj.mgt
Ch3 proj.mgt
 
Project admin lu3
Project admin   lu3Project admin   lu3
Project admin lu3
 
Ch3 proj.mgt
Ch3 proj.mgtCh3 proj.mgt
Ch3 proj.mgt
 
Slides 2015 for contact 1
Slides 2015 for contact 1Slides 2015 for contact 1
Slides 2015 for contact 1
 
Project Management Through Gantt & Pert Chart
Project Management Through Gantt & Pert ChartProject Management Through Gantt & Pert Chart
Project Management Through Gantt & Pert Chart
 
Project mgt
Project mgtProject mgt
Project mgt
 
Barbayanni results and approach 2013
Barbayanni results and approach 2013Barbayanni results and approach 2013
Barbayanni results and approach 2013
 
Barbayanni -results and approach
Barbayanni -results and approach Barbayanni -results and approach
Barbayanni -results and approach
 
Barbayanni -Results and Approach
Barbayanni -Results and Approach Barbayanni -Results and Approach
Barbayanni -Results and Approach
 
Barbayanni results and approach 2013
Barbayanni results and approach 2013Barbayanni results and approach 2013
Barbayanni results and approach 2013
 
CPM-PERT.ppt
CPM-PERT.pptCPM-PERT.ppt
CPM-PERT.ppt
 
Eggert.joe
Eggert.joeEggert.joe
Eggert.joe
 
D07 Project Charter
D07 Project CharterD07 Project Charter
D07 Project Charter
 
Software engineering ppt on pert and gantt charts
Software engineering ppt on pert and gantt chartsSoftware engineering ppt on pert and gantt charts
Software engineering ppt on pert and gantt charts
 

Más de megat zainurul anuar

Más de megat zainurul anuar (7)

Final Project Closing
Final Project ClosingFinal Project Closing
Final Project Closing
 
Project Execution
Project ExecutionProject Execution
Project Execution
 
Project Scope Managemen Final Megat
Project Scope Managemen Final MegatProject Scope Managemen Final Megat
Project Scope Managemen Final Megat
 
Introduction To Project Management Megat
Introduction To Project Management MegatIntroduction To Project Management Megat
Introduction To Project Management Megat
 
Information And Decision Support System
Information And Decision Support SystemInformation And Decision Support System
Information And Decision Support System
 
Information System and Information Technology
Information System and Information TechnologyInformation System and Information Technology
Information System and Information Technology
 
Knowledge Management Megat
Knowledge Management MegatKnowledge Management Megat
Knowledge Management Megat
 

Último

Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherRemote DBA Services
 
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWEREMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWERMadyBayot
 
"I see eyes in my soup": How Delivery Hero implemented the safety system for ...
"I see eyes in my soup": How Delivery Hero implemented the safety system for ..."I see eyes in my soup": How Delivery Hero implemented the safety system for ...
"I see eyes in my soup": How Delivery Hero implemented the safety system for ...Zilliz
 
Corporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptxCorporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptxRustici Software
 
GenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdfGenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdflior mazor
 
Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...apidays
 
Navi Mumbai Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Navi Mumbai Call Girls 🥰 8617370543 Service Offer VIP Hot ModelNavi Mumbai Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Navi Mumbai Call Girls 🥰 8617370543 Service Offer VIP Hot ModelDeepika Singh
 
DBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDropbox
 
Manulife - Insurer Transformation Award 2024
Manulife - Insurer Transformation Award 2024Manulife - Insurer Transformation Award 2024
Manulife - Insurer Transformation Award 2024The Digital Insurer
 
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingEdi Saputra
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...apidays
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Scriptwesley chun
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...Martijn de Jong
 
Apidays Singapore 2024 - Modernizing Securities Finance by Madhu Subbu
Apidays Singapore 2024 - Modernizing Securities Finance by Madhu SubbuApidays Singapore 2024 - Modernizing Securities Finance by Madhu Subbu
Apidays Singapore 2024 - Modernizing Securities Finance by Madhu Subbuapidays
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoffsammart93
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century educationjfdjdjcjdnsjd
 
A Beginners Guide to Building a RAG App Using Open Source Milvus
A Beginners Guide to Building a RAG App Using Open Source MilvusA Beginners Guide to Building a RAG App Using Open Source Milvus
A Beginners Guide to Building a RAG App Using Open Source MilvusZilliz
 
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...apidays
 
MS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectorsMS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectorsNanddeep Nachan
 

Último (20)

Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a Fresher
 
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWEREMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
 
"I see eyes in my soup": How Delivery Hero implemented the safety system for ...
"I see eyes in my soup": How Delivery Hero implemented the safety system for ..."I see eyes in my soup": How Delivery Hero implemented the safety system for ...
"I see eyes in my soup": How Delivery Hero implemented the safety system for ...
 
Corporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptxCorporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptx
 
GenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdfGenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdf
 
Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...
 
Navi Mumbai Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Navi Mumbai Call Girls 🥰 8617370543 Service Offer VIP Hot ModelNavi Mumbai Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Navi Mumbai Call Girls 🥰 8617370543 Service Offer VIP Hot Model
 
DBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor Presentation
 
Manulife - Insurer Transformation Award 2024
Manulife - Insurer Transformation Award 2024Manulife - Insurer Transformation Award 2024
Manulife - Insurer Transformation Award 2024
 
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Script
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...
 
Apidays Singapore 2024 - Modernizing Securities Finance by Madhu Subbu
Apidays Singapore 2024 - Modernizing Securities Finance by Madhu SubbuApidays Singapore 2024 - Modernizing Securities Finance by Madhu Subbu
Apidays Singapore 2024 - Modernizing Securities Finance by Madhu Subbu
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century education
 
A Beginners Guide to Building a RAG App Using Open Source Milvus
A Beginners Guide to Building a RAG App Using Open Source MilvusA Beginners Guide to Building a RAG App Using Open Source Milvus
A Beginners Guide to Building a RAG App Using Open Source Milvus
 
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
 
MS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectorsMS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectors
 

Project Planning

  • 1. INTRODUCTION TO: PROJECT MANAGEMENT PROJECT EXECUTION MODULE 2: Day 2 / S2 by: DREAMSOFT (M)SDN BHD http://www.thedreamsoft.com admin@thedreamsoft.com
  • 2. Work Breakdown Structure (WBS) • A detailed, hierarchical (from general to specific) tree structure of deliverables and tasks that need to be performed to complete a project.
  • 3. purpose or WBS • to identify actual tasks to be done in a project. Serves as basis for project planning. • An extension to PERT.
  • 4. Standard Work Breakdown Structure Standard Work Breakdown Structure (WBS) 1.0 2.0 3.0 4.0 5.0 6.0 Mission Investment Solution Implementation In-Service Disposition Analysis Analysis Development Management Activity A Activity B Activity C Activity D Activity E Activity F Pre-Project Activities Project Specific Activities LEGEND Decomposes to lower level WBS elements
  • 5. Project Management Day 1 / S2
  • 6. Overview on Planning Who Will By When Must Do It? It Be Done? How Much Will How Should It Cost? It Be Done What Must Be Done How Good Does It Has To Be?
  • 7. Project Planning Definition • A Project Plan sets out the phases, activities and tasks needed to deliver a project. • The timeframes required to deliver the project, along with the resources and milestones are also shown in the Project Plan.
  • 8. Main Output From Project Planning PROJECT PLANNING Project PERT Diagram Gantt Chart Predecessor Table
  • 9. History • PERT is a network model that allows for randomness in activity completion times. • PERT was developed in the late 1950's for the U.S. Navy's Polaris project having thousands of contractors. – It has the potential to reduce both the time and cost required to complete a project.
  • 10. Methods Main methods used in project planning: 3. Project Schedule 4. PERT 5. Gantt Chart
  • 11. 1. Project Schedule Definition • An organized method of presenting in- formation on when activities need to be started, how long activities are planned to take, and when activities are planned to be completed. • A schedule should also reflect the logical relationships between activities.
  • 12. 2. PERT (Project Evaluation Review Technique) Definition • A diagram that shows tasks and their relationships. Limited because it shows only task relationships. Strength: easy to read task relationships. – Also known as Network Diagram
  • 13. Tasks Duration of Tasks Durations PERT (months) Precedors of Tasks
  • 14. 3. Gantt Chart Definition • A bar chart. While visually appealing on a task/duration basis, it is limited because it does not show task or resource relationships well. – Strength: easy to maintain and read.
  • 15. An Example of a Gantt Chart Task Name Predecessor Task ID Estimated 1 2 3 4 5 6 7 8 9 10 Time Mark Utilities B A 3 Dig Holes C B 2 Buy Trees D C 1 Buy Flowers E D 1 Plant Trees F E 2 Plant Flowers G,H F 1 Buy Cover - G 1 Install Cover - H 1 12
  • 16. Steps in the PERT Planning Process PERT planning involves the following steps: • Identify the specific activities and milestones • Determine the proper sequence of the activities • Construct a network diagram • Estimate the time required for each activity --------------------------- • Determine the Critical Path • Update the PERT Chart as the project progresses
  • 17. 1. Identify Activities and Milestones • The activities are the tasks required to complete the project. • The milestones are the events marking the beginning and end of one or more activities. – It is helpful to list the tasks in a table that in later steps can be expanded to include information on sequence and duration.
  • 18. 2. Determine Activity Sequence • This step may be combined with the activity identification step since the activity sequence is evident for some tasks. – Other tasks may require more analysis to determine the exact order in which they must be performed.
  • 19. 3. Construct the Network Diagram • Using the activity sequence information, a network diagram can be drawn showing the sequence of the serial and parallel activities. – For the original activity-on-arc model, the activities are depicted by arrowed lines and milestones are depicted by circles or "bubbles".
  • 20. 4. Estimate Activity Times (ET) For each activity, the model usually includes three time estimates: • Optimistic time - generally the shortest time in which the activity can be completed. • Most likely time - the completion time having the highest probability. Note that this time is different from the expected time. • Pessimistic time - the longest time that an activity might require. Three standard deviations from the mean is commonly used for the pessimistic time.
  • 21. Expected Time Expected time = ( Optimistic + 4 x Most likely + Pessimistic ) / 6
  • 22. Standard Work Breakdown Structure Standard Work Breakdown Structure (WBS) 1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 ET:3 days ET:2 days ET: 1 day ET: 1 day ET2 days ET:1 day ET:1 day ET:1 day A B C D E F G H Mark Utilities Dig Holes Buy Trees Buy Flowers Plant Trees Plant Flowers Buy Edging Install Edging Project Specific Activities LEGEND Decomposes to lower level WBS elements
  • 23. An Example of a Logical Sequence Predecessor Table Task Name / Estimated Time Activity Predecessor Description Mark Utilities B,C,D Dig Holes E Buy Trees G,E Buy Flowers F Plant Trees F Plant Flowers E,D Buy Edging C Install Edging F,G TOTALS Card Activities****
  • 24. From PERT to GANTT Chart
  • 25. An Example of a Gantt Chart Task Name / Predecessor Activity Estimated 1 2 3 4 5 6 7 8 9 10 Description Time (ET) Mark Utilities B A 3 Dig Holes C B 2 Buy Trees D C 1 Buy Flowers E D 1 Plant Trees F E 2 Plant Flowers G,H F 1 Buy Cover - G 1 Install Cover - H 1 12
  • 26. Exercise: ‘PROJECT LANDSCAPE DARUL AMAN’ Refer to Template: • Predecessor Table • PERT • GANTT Chart
  • 27. lesson learned • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________