SlideShare una empresa de Scribd logo
1 de 70
Descargar para leer sin conexión
Copyright © SEL 2007
Out-Of-Step Protection
Fundamentals
Demetrios Tziouvaras
Schweitzer Engineering Laboratories, Inc.
IEEE PES San Francisco Chapter
December 13, 2007
Introduction
The aim of this presentation is to explain
The fundamentals of out-of-step (OOS)
protection
Discuss which relays and relay systems are
prone to operate during power swings
Share experiences and lessons learnt from the
past to avoid making the same mistakes
Introduction
Interconnected systems experienced an
increased number of large disturbances in
the last 15 years
Protective relay systems are often involved
during major disturbances
In many cases they prevent further propagation
of the disturbance
In some cases undesired relay operations have
contributed to cascading blackouts
Outline
Out of step (OOS) protection fundamentals
Relay performance during OOS conditions
Transmission lines
Generators
System design and protection
improvements
Conclusions
What Is a Power Swing?
Variation of power flow which occurs when
generator rotor angles are advancing or
retarding relative to each other in response to:
System faults
Line switching
Major load switching
Loss of large generation
Major system disturbances
Stable and Unstable Power Swings
Definitions
A power swing is considered stable if the
generators do not slip poles and the system
reaches a new state of equilibrium, i.e. an
acceptable operating condition
An unstable power swing results in a
generator or group of generators
experiencing pole slipping or loss-of-
synchronism for which some corrective
action must be taken.
Out-of-step is the same as an unstable power
swing.
Power Swings can Cause Undesired
Protective Relay Operation
Power swings can cause undesired relay
operation that may lead to:
Undesired tripping of power system elements
at undesired network locations
Weakening of the power system
Possible cascading outages and shutdown of
major portions of the power system
Damage of circuit breakers due to uncontrolled
tripping
Loss of human life
Unstable Power Swings
Damage System Integrity
Pole slipping may damage generators and
turbines
Low voltage conditions experienced during
unstable power swings may cause:
Motor stalling
Generator tripping
Damage to voltage-sensitive loads
Prolonged low voltages could cause instability of
smaller areas within a utility’s system
Need for Out-of-Step Protection
Generators operating asynchronously
with the rest of the power system cannot
regain stability as a result of any
excitation or regulator action
Asynchronous power system areas must
be separated in a controlled fashion to
avoid:
Equipment damage
Widespread outages in the power system
Philosophy of Power-Swing Protection
Detect both stable and unstable power
swings
Block tripping of relay elements prone to
operate during power swings
Differentiate between stable and unstable
power swings
Separate the system into islands during
out-of-step conditions
Philosophy of Power-Swing Protection
Separate the system at locations that
provide good balance of load/generation
in the resulting system islands
Trip only at pre-selected network locations
and block tripping at all other locations
Trip only under controlled transient
recovery voltages or with low current
Power System Stability
Brief Review
Power System Stability
Definition
The ability of the electric power system
to regain a state of operating equilibrium
after being subjected to disturbances
such as faults, line switching, load
rejection, loss-of-excitation, and loss of
generation.
Power Flow
Two-Machine System
1 2
3 4
Line 1
VS VR
Line 2
X
δ
⋅
= sin
X
VV
P
RSVS
VR
δ
Effect of Fault Type on Power Transfer
δ
P
Three-Phase Fault
Phase-Phase-Ground
Fault
Phase-Phase Fault
Single-Line-Ground Fault
Normal System
1 2
3 4
VS VR
Line 1
Line 2
Transient Stability Concepts
1 2
3 4
Prefault state (Both lines in service)
Fault state
Fault state with breaker 3 open
Post-fault state (Line 2 out)
VS VR
Line 1
Line 2
Equal-Area Criterion
δ180°
P0
P
Fault (one
breaker
open)
Fault
Prefault
Post-Fault
1
0
2
3
4
5
6
Area 2Area 1
1 2
3 4
VS VR
Line 1
Line 2
Effect of Fault Clearing Time
Unstable System
Fault
Post-Fault
δ
Prefault
P
Stable and Unstable Power Swings
Rotor Angle
Stable System
Unstable System
t
δ
δ0
δ1
Angular Instability
Distinguishing Features
Large voltage variations
Large power oscillations
Loss of synchronism
Zero voltage at the electrical center
Frequency excursions
Angular Instability
Large Voltage Variations
0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8
-1
0
1
Voltage MagnitudePerunit
Seconds
0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8
0
0.5
1
1.5
PerUnit
Seconds
Angular Instability
Large Power Oscillations
0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8
-1000
-500
0
500
Real and Reactive Power
MW
Seconds
0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8
-400
-200
0
200
400
600
MVar
Seconds
Angular Instability
V1 and Angle of V1 / I1
0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9
0
0.2
0.4
0.6
Positive-Sequence Voltage Magnitude
PerUnit
Seconds
0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9
-200
0
200
400
Angle of (V1 / I1)
Degrees
Seconds
Relay Elements Prone to Operate
During Power Swings
Stable and Unstable Power Swings
Impedance Trajectories
Stable Swing
Unstable Swing
R
X
Relay Elements Prone to Operate
During Power Swings
Instantaneous phase overcurrent
Directional and non-directional
Undervoltage
Short time or instantaneous
Zone 1 distance
Zone 2 distance used in POTT scheme
Line Relays Prone to Operate
During Angular Instability
Zone 1 distance or overreaching distance
elements applied in DCB or POTT schemes
Potential reasons are:
Lack of PSB function or improper settings of
the PSB function
Lack of frequency tracking and long memory
polarizing voltage
Phasor measurement errors due to large
excursions of system frequency during
islanding
Relay Systems Unresponsive
to Power Swings
Phase comparison
Line current differential
Pilot-wire
Impedances Measured
by Distance Relays
21
V I
ZS
ZL ZR
VS VR
( ) SRLS
RS
S
ZZZZ
VV
V
IVZ −++
−
==
Impedance Locus for k = ES / ER = 1.0
δ
ZL
ZR
X
R
δ increases
δ decreases
δ=180°
ZS
0.5ZT
Z
R
S
S
T
Z
2
cotj1
2
Z
Z −⎟
⎠
⎞
⎜
⎝
⎛ δ
−=
R
S
E
E
k =
Two-Machine System Impedance Locii
R
X
S
k > 1
ES > ER
Rk = 1
k < 1
ES < ER
Power-Swing Protection
Relay Functions
Clarify the Terminology
Unstable power swing
Out of step (OOS)
Out-of-step blocking (OSB)
Power-swing blocking (PSB)
Out-of-step tripping (OST)
Pole-slip tripping
Power-Swing Protection
Relay Functions
Power-swing blocking (PSB)
Detects both stable and unstable power
swings
Prevents operation of protection elements
Out-of-step tripping (OST)
Detects unstable power swings or OOS
Separates system into islands with good
generation / load balance
Conventional PSB Scheme
Load Region
X
R
A
B
Z1
Inner Z
ElementDistance
Element
Outer Z
Element
Conventional OST Scheme
Load Region
X
R
A
B
Z1
Inner Z
ElementDistance
Element
Outer Z
Element
Disadvantages of
Conventional PSB Scheme
Needs detailed system information
Requires extensive system stability studies
It is difficult to set for long lines with heavy
loads
May fail after severe disturbances on
marginally stable systems
May fail during swings with high slip
frequency
Long Line With Heavy Load
ZL => ZΣ
A R
ZR
ZS
Z2
X
B
Swing Locus
Trajectory ZL
Short Line With Light Load
ZL << ZΣ
A R
ZR
ZS
Z2
X
B
Swing Locus
Trajectory
ZL
Unstable Swing
After Severe Disturbance
A
R
ZR
ZS
Z2
X
Swing Locus
Trajectory
B
ZL
New Zero-Setting PSB Function
Uses swing-center voltage (SCV)
Has no user settings
Does not need system parameters
Does not require system stability studies
Provides PSB during pole open
Detects evolving faults during power swings
Swing-Center Voltage (SCV)
( ) ( ) ( )
⎟
⎠
⎞
⎜
⎝
⎛δ
⋅⎟
⎠
⎞
⎜
⎝
⎛ δ
+ω=
2
t
cos
2
t
tsinE2tSCV
o'
o
o"
Z1S•I Z1L•I
VS
ER
δ
SCV
Z1R•I
ES
VR
SCV During System OOS Condition
Swing-Center Voltage
seconds
voltage(pu) SCV Amplitude
0 0.05 0.1 0.15 0.2
-1
-0.5
0
0.5
1
Local Estimate of SCV: Vcosϕ
ϕ⋅≈ cos|V|SCV S
o'Z1S•I Z1R•Iθ
VS
ES ϕ
SCV
ER
I
Vcosϕ
VR
AnglepedanceImSystem:θ
Local Estimate of SCV: Vcosϕ
⎟
⎠
⎞
⎜
⎝
⎛ δ
⋅=
2
cos1E1SCV
( )
dt
d
2
sin
2
1E
dt
1SCVd δ
⎟
⎠
⎞
⎜
⎝
⎛ δ
−=
Vcosϕ for 1-Rad/Sec OOS Condition
0
0 90 180 270 360
E1
E1/2
d (SCV1) / dt
δ
SCV1
Benefits of SCV for PSB Application
Independent of system source and line
impedance
Bounded:
Lower limit: zero
Upper limit: close to one per unit
Relates directly to angle difference of two
sources, δ
Transmission Line Relay Performance
During Out-of-Step Conditions
500 kV System
Station C
Station D
Station E
Line 1
Line 3
Line 2
Unit 1
Unit 2
Lines 4, 5, and 6
Intertie
System B
System A
Angular Instability
Z1 Trajectory – Line 2 at Station C
-10 -5 0 5 10
-10
-8
-6
-4
-2
0
2
4
6
8
10
23
25
27 29 31 33 35 37 39
41
43
45
Positive-Sequence Impedance (Z1) Locus
Im(Z1)ohm
Re(Z1) ohm
EHV System – Northern California
Station C
Station D
Station E
Line 1
Line 3
Line 2
Unit 1
Unit 2
Lines 4, 5, and 6
Intertie
System B
System A
Zone 1 Operation During OOS
PSB Function not Enabled
Zone 1 Distance Is Blocked
First Slip Cycle
Zone 1 Distance Operates
Second Slip Cycle
Zone 1 Distance Operates
Second Slip Cycle
Fast slip frequency change
Setting fine-tuning could have prevented
operation of Zone 1
Concentric zone settings
Separation between concentric zones
PSB timer
All of these settings are difficult to make
Long heavy loaded lines
Require large number of stability studies
Proper Blocking of Distance Elements
by Zero Setting PSB
0 5 10 15 20
-1
-0.5
0
0.5
1
SCV1 (Solid), dSCV1/dt (Dash)
(pu),(pu/cyc)
0 5 10 15 20
Cycle
S
PSB
DPSB
67QUB
3PF Reset
PSB Reset
SLD Set
Start-Zn
SSD Set
Generator Relay Performance
During Disturbances
Units 1 and 2 Operations
Station C
Station D
Station E
Line 1
Line 3
Line 2
Unit 1
Unit 2
Lines 4, 5, and 6
Intertie
System B
System A
One Unit Trips by Undervoltage
0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9
-1
-0.5
0
0.5
1
Station C Voltage
Perunit
Seconds
Unit 1: Three-Phase P and Q
During OOS
0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8
-2000
0
2000
Real Power
MW
Seconds
0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8
-1000
0
1000
Reactive Power
MVar
Seconds
Units 1 and 2 Trip
Inst. Dir. Phase OC Relay
-20 -10 0 10 20
-40
-30
-20
-10
0
10
1 3 5 7 9
11
13
15
17
19
21
23
25 27 29
Positive-Sequence Impedance (Z1) Locus
Im(Z1)ohm
Re(Z1) ohm
Protection System
and Other System Improvements
to Preserve System Stability
Proper System and Protection Design
Preserve System Stability
Prevent the occurrence of out-of-step
conditions
Install sufficient transmission capacity
Maintain adequate reactive reserves
Apply high-speed relaying systems and
high-speed reclosing
Apply single-phase tripping and reclosing
Apply wide-area stability controls
Wide-Area Stability Controls or SIPS
Preserve System Stability
Wide-area stability controls
Generator dropping
Direct load dropping
Fast valving
Insertion of breaking resistors
Series and shunt capacitor insertion
Use FACTS devices
Protection System
and Other Improvements
Improvements in transient stability
High speed fault clearing
Single phase tripping and reclosing
Apply local breaker failure protection on all
EHV and critical HV substations
Special protection systems
Controlled system separation
UVLS and UFLS
Protection System Improvements
Apply dual pilot protection relay systems on
all EHV and critical HV systems with
PSB capability, or with systems that are
immune to stable or unstable power swings
Replace secondary non-pilot line relay
systems in non-critical HV lines with:
A relay system that has similar functionality
with the main pilot protection system
Consider switching the communications
channel to the secondary relay system when
the Main 1 is out of service
Conclusions
Utilities must take every action economically
justifiable to preserve system stability
Out-of-step tripping should be applied and
operate only as a last resort to preserve
system stability
OST and PSB should be applied based on an
inter-regional controlled system separation
philosophy
Conclusions
OOS tripping must separate the system
at predetermined locations to minimize
the effect of the disturbance
OOS blocking compliments OOS tripping
by blocking relay elements prone to
operate and ensures a controlled system
separation
Controlled separation schemes provide
a safety net to lessen the impacts of
major disturbances
References
Out-Of-Step Protection Fundamentals and Advancements
http://www.selinc.com/techpprs/6163.pdf
Zero-Setting Power-Swing Blocking Protection
http://www.selinc.com/techpprs/6172_ZeroSetting_20050302.pdf
Relay Performance During Major System Disturbances
http://www.selinc.com/techpprs/6244_RelayPerformance_DT_20060914.pdf
Thank You

Más contenido relacionado

La actualidad más candente

Directional over current relay
Directional over current relayDirectional over current relay
Directional over current relayCS V
 
Alternator protection
Alternator protectionAlternator protection
Alternator protectionjawaharramaya
 
FUNDAMENTALS OF POWER SYSTEM PROTECTION
FUNDAMENTALS OF POWER SYSTEM PROTECTIONFUNDAMENTALS OF POWER SYSTEM PROTECTION
FUNDAMENTALS OF POWER SYSTEM PROTECTIONPower System Operation
 
Harmonics and mitigation techniques
Harmonics and mitigation techniquesHarmonics and mitigation techniques
Harmonics and mitigation techniquesrifat maryum
 
Protective relay
Protective relay Protective relay
Protective relay Uday Wankar
 
Switchgear and protection 1
Switchgear and protection 1Switchgear and protection 1
Switchgear and protection 1Md Irshad Ahmad
 
Power Transformer Protection
Power Transformer ProtectionPower Transformer Protection
Power Transformer ProtectionAng Sovann
 
Series & shunt compensation and FACTs Devices
Series & shunt compensation and FACTs DevicesSeries & shunt compensation and FACTs Devices
Series & shunt compensation and FACTs Deviceskhemraj298
 
Power system protection
Power system protectionPower system protection
Power system protectionAnu Priya
 
Power System Stabilizer
Power System StabilizerPower System Stabilizer
Power System StabilizerSuman Sourabh
 
Substation protection devices
Substation protection devicesSubstation protection devices
Substation protection devicesRahul Aman
 
Load dispatch center
Load dispatch centerLoad dispatch center
Load dispatch centerddxdharmesh
 
Power system stability
Power system stabilityPower system stability
Power system stabilityBalaram Das
 
DISTANCE PROTECTION RELAY
DISTANCE PROTECTION RELAYDISTANCE PROTECTION RELAY
DISTANCE PROTECTION RELAYRaviraj solanki
 
transformer protection
transformer protection transformer protection
transformer protection jason adidela
 
EXCITATION SYSTEM.ppt
EXCITATION SYSTEM.pptEXCITATION SYSTEM.ppt
EXCITATION SYSTEM.pptvishal laddha
 

La actualidad más candente (20)

Directional over current relay
Directional over current relayDirectional over current relay
Directional over current relay
 
Alternator protection
Alternator protectionAlternator protection
Alternator protection
 
FUNDAMENTALS OF POWER SYSTEM PROTECTION
FUNDAMENTALS OF POWER SYSTEM PROTECTIONFUNDAMENTALS OF POWER SYSTEM PROTECTION
FUNDAMENTALS OF POWER SYSTEM PROTECTION
 
Harmonics and mitigation techniques
Harmonics and mitigation techniquesHarmonics and mitigation techniques
Harmonics and mitigation techniques
 
Protection of alternator
Protection of alternatorProtection of alternator
Protection of alternator
 
Protective relay
Protective relay Protective relay
Protective relay
 
What is Power Swing | Power Swing
What is Power Swing | Power Swing What is Power Swing | Power Swing
What is Power Swing | Power Swing
 
Switchgear and protection 1
Switchgear and protection 1Switchgear and protection 1
Switchgear and protection 1
 
Power Transformer Protection
Power Transformer ProtectionPower Transformer Protection
Power Transformer Protection
 
Series & shunt compensation and FACTs Devices
Series & shunt compensation and FACTs DevicesSeries & shunt compensation and FACTs Devices
Series & shunt compensation and FACTs Devices
 
Power system protection
Power system protectionPower system protection
Power system protection
 
Protection of Transmission lines
Protection of Transmission linesProtection of Transmission lines
Protection of Transmission lines
 
Thyristor switched capacitor
Thyristor switched capacitorThyristor switched capacitor
Thyristor switched capacitor
 
Power System Stabilizer
Power System StabilizerPower System Stabilizer
Power System Stabilizer
 
Substation protection devices
Substation protection devicesSubstation protection devices
Substation protection devices
 
Load dispatch center
Load dispatch centerLoad dispatch center
Load dispatch center
 
Power system stability
Power system stabilityPower system stability
Power system stability
 
DISTANCE PROTECTION RELAY
DISTANCE PROTECTION RELAYDISTANCE PROTECTION RELAY
DISTANCE PROTECTION RELAY
 
transformer protection
transformer protection transformer protection
transformer protection
 
EXCITATION SYSTEM.ppt
EXCITATION SYSTEM.pptEXCITATION SYSTEM.ppt
EXCITATION SYSTEM.ppt
 

Destacado

oshpd emergency power supply systems
oshpd emergency power supply systemsoshpd emergency power supply systems
oshpd emergency power supply systemsmichaeljmack
 
Interconnet protection of
Interconnet protection ofInterconnet protection of
Interconnet protection ofmichaeljmack
 
Transformer differential protection
Transformer differential protection Transformer differential protection
Transformer differential protection michaeljmack
 
Transformer overcurrent
Transformer overcurrentTransformer overcurrent
Transformer overcurrentmichaeljmack
 
Scheme logic implement pwr plant cntrl
Scheme logic implement pwr plant cntrlScheme logic implement pwr plant cntrl
Scheme logic implement pwr plant cntrlmichaeljmack
 
Upgrading gen protect and grounding
Upgrading gen protect and groundingUpgrading gen protect and grounding
Upgrading gen protect and groundingmichaeljmack
 
Digital transformer protection systems
Digital transformer protection systemsDigital transformer protection systems
Digital transformer protection systemsmichaeljmack
 
Auto synch considerations methods
Auto synch considerations methodsAuto synch considerations methods
Auto synch considerations methodsmichaeljmack
 
Generator protection calculations settings
Generator protection calculations settingsGenerator protection calculations settings
Generator protection calculations settingsmichaeljmack
 
Transformer protection commissioning tools
Transformer protection commissioning toolsTransformer protection commissioning tools
Transformer protection commissioning toolsmichaeljmack
 
Automatic synch of gen
Automatic synch of genAutomatic synch of gen
Automatic synch of genmichaeljmack
 
Selective Coodination
Selective CoodinationSelective Coodination
Selective Coodinationmichaeljmack
 
Generator basic concepts
Generator basic conceptsGenerator basic concepts
Generator basic conceptsmichaeljmack
 

Destacado (14)

oshpd emergency power supply systems
oshpd emergency power supply systemsoshpd emergency power supply systems
oshpd emergency power supply systems
 
Interconnet protection of
Interconnet protection ofInterconnet protection of
Interconnet protection of
 
Transformer differential protection
Transformer differential protection Transformer differential protection
Transformer differential protection
 
Ieee pes psrc
Ieee pes psrcIeee pes psrc
Ieee pes psrc
 
Transformer overcurrent
Transformer overcurrentTransformer overcurrent
Transformer overcurrent
 
Scheme logic implement pwr plant cntrl
Scheme logic implement pwr plant cntrlScheme logic implement pwr plant cntrl
Scheme logic implement pwr plant cntrl
 
Upgrading gen protect and grounding
Upgrading gen protect and groundingUpgrading gen protect and grounding
Upgrading gen protect and grounding
 
Digital transformer protection systems
Digital transformer protection systemsDigital transformer protection systems
Digital transformer protection systems
 
Auto synch considerations methods
Auto synch considerations methodsAuto synch considerations methods
Auto synch considerations methods
 
Generator protection calculations settings
Generator protection calculations settingsGenerator protection calculations settings
Generator protection calculations settings
 
Transformer protection commissioning tools
Transformer protection commissioning toolsTransformer protection commissioning tools
Transformer protection commissioning tools
 
Automatic synch of gen
Automatic synch of genAutomatic synch of gen
Automatic synch of gen
 
Selective Coodination
Selective CoodinationSelective Coodination
Selective Coodination
 
Generator basic concepts
Generator basic conceptsGenerator basic concepts
Generator basic concepts
 

Similar a Out of step

Power Swing Phenomena and its Detection and Prevention
Power Swing Phenomena and its Detection and PreventionPower Swing Phenomena and its Detection and Prevention
Power Swing Phenomena and its Detection and PreventionPower System Operation
 
17648889-Introduction-to-Power-System-Protection-Relays.pdf
17648889-Introduction-to-Power-System-Protection-Relays.pdf17648889-Introduction-to-Power-System-Protection-Relays.pdf
17648889-Introduction-to-Power-System-Protection-Relays.pdfThien Phan Bản
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear johny renoald
 
Power Swing Phenomena and Comparative Study of Its Detection on Transmission ...
Power Swing Phenomena and Comparative Study of Its Detection on Transmission ...Power Swing Phenomena and Comparative Study of Its Detection on Transmission ...
Power Swing Phenomena and Comparative Study of Its Detection on Transmission ...ijsrd.com
 
Switch gear and protection
Switch gear and protectionSwitch gear and protection
Switch gear and protectionDinesh Sharma
 
[1339309 x journal of electrical engineering] loss of excitation of synchro...
[1339309 x   journal of electrical engineering] loss of excitation of synchro...[1339309 x   journal of electrical engineering] loss of excitation of synchro...
[1339309 x journal of electrical engineering] loss of excitation of synchro...Abraham Kv
 
New Microsoft Word Document
New Microsoft Word DocumentNew Microsoft Word Document
New Microsoft Word DocumentBarunava Sikdar
 
Generator protection by a. kato
Generator protection by a. katoGenerator protection by a. kato
Generator protection by a. katoAgrey Kato
 
Power System Transient - Introduction.pptx
Power System Transient - Introduction.pptxPower System Transient - Introduction.pptx
Power System Transient - Introduction.pptxssuser6453eb
 
Protection & switchgear
Protection & switchgear  Protection & switchgear
Protection & switchgear johny renoald
 
Generator protection by bhushan kumbhalkar
Generator protection by bhushan kumbhalkarGenerator protection by bhushan kumbhalkar
Generator protection by bhushan kumbhalkarBhushan Kumbhalkar
 
Power system stability
Power  system  stabilityPower  system  stability
Power system stabilityrohit kumar
 
Transient Stability Analysis with SSSC and UPFC in Multi-Machine Power System...
Transient Stability Analysis with SSSC and UPFC in Multi-Machine Power System...Transient Stability Analysis with SSSC and UPFC in Multi-Machine Power System...
Transient Stability Analysis with SSSC and UPFC in Multi-Machine Power System...IRJET Journal
 
Introduction to Small Signal Stability and Low Frequency Oscillation
Introduction to Small Signal Stability and Low Frequency OscillationIntroduction to Small Signal Stability and Low Frequency Oscillation
Introduction to Small Signal Stability and Low Frequency OscillationPower System Operation
 
Introduction to small signal stability and low frequency oscillation
Introduction to small signal stability and low frequency oscillationIntroduction to small signal stability and low frequency oscillation
Introduction to small signal stability and low frequency oscillationPower System Operation
 

Similar a Out of step (20)

Power Swing Phenomena and its Detection and Prevention
Power Swing Phenomena and its Detection and PreventionPower Swing Phenomena and its Detection and Prevention
Power Swing Phenomena and its Detection and Prevention
 
17648889-Introduction-to-Power-System-Protection-Relays.pdf
17648889-Introduction-to-Power-System-Protection-Relays.pdf17648889-Introduction-to-Power-System-Protection-Relays.pdf
17648889-Introduction-to-Power-System-Protection-Relays.pdf
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear
 
Power Swing Phenomena and Comparative Study of Its Detection on Transmission ...
Power Swing Phenomena and Comparative Study of Its Detection on Transmission ...Power Swing Phenomena and Comparative Study of Its Detection on Transmission ...
Power Swing Phenomena and Comparative Study of Its Detection on Transmission ...
 
Generator protection
Generator protectionGenerator protection
Generator protection
 
Switch gear and protection
Switch gear and protectionSwitch gear and protection
Switch gear and protection
 
[1339309 x journal of electrical engineering] loss of excitation of synchro...
[1339309 x   journal of electrical engineering] loss of excitation of synchro...[1339309 x   journal of electrical engineering] loss of excitation of synchro...
[1339309 x journal of electrical engineering] loss of excitation of synchro...
 
New Microsoft Word Document
New Microsoft Word DocumentNew Microsoft Word Document
New Microsoft Word Document
 
L58037783
L58037783L58037783
L58037783
 
Generator protection by a. kato
Generator protection by a. katoGenerator protection by a. kato
Generator protection by a. kato
 
Et601 chapter1 ayu
Et601  chapter1 ayuEt601  chapter1 ayu
Et601 chapter1 ayu
 
Power System Transient - Introduction.pptx
Power System Transient - Introduction.pptxPower System Transient - Introduction.pptx
Power System Transient - Introduction.pptx
 
Protection & switchgear
Protection & switchgear  Protection & switchgear
Protection & switchgear
 
Balanced faults
Balanced faultsBalanced faults
Balanced faults
 
Generator protection by bhushan kumbhalkar
Generator protection by bhushan kumbhalkarGenerator protection by bhushan kumbhalkar
Generator protection by bhushan kumbhalkar
 
5010566.ppt
5010566.ppt5010566.ppt
5010566.ppt
 
Power system stability
Power  system  stabilityPower  system  stability
Power system stability
 
Transient Stability Analysis with SSSC and UPFC in Multi-Machine Power System...
Transient Stability Analysis with SSSC and UPFC in Multi-Machine Power System...Transient Stability Analysis with SSSC and UPFC in Multi-Machine Power System...
Transient Stability Analysis with SSSC and UPFC in Multi-Machine Power System...
 
Introduction to Small Signal Stability and Low Frequency Oscillation
Introduction to Small Signal Stability and Low Frequency OscillationIntroduction to Small Signal Stability and Low Frequency Oscillation
Introduction to Small Signal Stability and Low Frequency Oscillation
 
Introduction to small signal stability and low frequency oscillation
Introduction to small signal stability and low frequency oscillationIntroduction to small signal stability and low frequency oscillation
Introduction to small signal stability and low frequency oscillation
 

Más de michaeljmack

Auburn, NY - 200 Years of History 1793-1993
Auburn, NY - 200 Years of History  1793-1993Auburn, NY - 200 Years of History  1793-1993
Auburn, NY - 200 Years of History 1793-1993michaeljmack
 
Auburn High School, Auburn, NY, 1982 Yearbook
Auburn High School, Auburn, NY, 1982 YearbookAuburn High School, Auburn, NY, 1982 Yearbook
Auburn High School, Auburn, NY, 1982 Yearbookmichaeljmack
 
Auburn High School, Auburn, NY, 1980 Yearbook
Auburn High School, Auburn, NY, 1980 YearbookAuburn High School, Auburn, NY, 1980 Yearbook
Auburn High School, Auburn, NY, 1980 Yearbookmichaeljmack
 
Diesel Particulate Filters Control Systems
Diesel Particulate Filters Control SystemsDiesel Particulate Filters Control Systems
Diesel Particulate Filters Control Systemsmichaeljmack
 
Understanding Arc Flash
Understanding Arc FlashUnderstanding Arc Flash
Understanding Arc Flashmichaeljmack
 
Siemens MV GIS Switchgear
Siemens MV GIS SwitchgearSiemens MV GIS Switchgear
Siemens MV GIS Switchgearmichaeljmack
 
Fundamentals of transformer inrush
Fundamentals of transformer inrushFundamentals of transformer inrush
Fundamentals of transformer inrushmichaeljmack
 
Building information modeling
Building information modelingBuilding information modeling
Building information modelingmichaeljmack
 
15 years of experience stator ground fault protection
15 years of experience stator ground fault protection15 years of experience stator ground fault protection
15 years of experience stator ground fault protectionmichaeljmack
 
Emergency, Legally Required and Optional Standby Systems
Emergency, Legally Required and Optional Standby SystemsEmergency, Legally Required and Optional Standby Systems
Emergency, Legally Required and Optional Standby Systemsmichaeljmack
 
Lighting Control Solutions for Daylit Spaces
Lighting Control Solutions for Daylit SpacesLighting Control Solutions for Daylit Spaces
Lighting Control Solutions for Daylit Spacesmichaeljmack
 
COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708michaeljmack
 
Seismic Compliance of Electrical Distribution
Seismic Compliance of Electrical DistributionSeismic Compliance of Electrical Distribution
Seismic Compliance of Electrical Distributionmichaeljmack
 
Generator Set Transient Performance
Generator Set Transient PerformanceGenerator Set Transient Performance
Generator Set Transient Performancemichaeljmack
 
Modeling of a digital protective relay in a RT Digital Simulator
Modeling of a digital protective relay in a RT Digital SimulatorModeling of a digital protective relay in a RT Digital Simulator
Modeling of a digital protective relay in a RT Digital Simulatormichaeljmack
 
Facts on Grid Friendly Wind Plants
Facts on Grid Friendly Wind PlantsFacts on Grid Friendly Wind Plants
Facts on Grid Friendly Wind Plantsmichaeljmack
 
Power Plant Horror Stories
Power Plant Horror StoriesPower Plant Horror Stories
Power Plant Horror Storiesmichaeljmack
 
Blackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load SheddingBlackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load Sheddingmichaeljmack
 
Transformer Fundamentals
Transformer FundamentalsTransformer Fundamentals
Transformer Fundamentalsmichaeljmack
 

Más de michaeljmack (20)

Auburn, NY - 200 Years of History 1793-1993
Auburn, NY - 200 Years of History  1793-1993Auburn, NY - 200 Years of History  1793-1993
Auburn, NY - 200 Years of History 1793-1993
 
Auburn High School, Auburn, NY, 1982 Yearbook
Auburn High School, Auburn, NY, 1982 YearbookAuburn High School, Auburn, NY, 1982 Yearbook
Auburn High School, Auburn, NY, 1982 Yearbook
 
Auburn High School, Auburn, NY, 1980 Yearbook
Auburn High School, Auburn, NY, 1980 YearbookAuburn High School, Auburn, NY, 1980 Yearbook
Auburn High School, Auburn, NY, 1980 Yearbook
 
Surge Protection
Surge ProtectionSurge Protection
Surge Protection
 
Diesel Particulate Filters Control Systems
Diesel Particulate Filters Control SystemsDiesel Particulate Filters Control Systems
Diesel Particulate Filters Control Systems
 
Understanding Arc Flash
Understanding Arc FlashUnderstanding Arc Flash
Understanding Arc Flash
 
Siemens MV GIS Switchgear
Siemens MV GIS SwitchgearSiemens MV GIS Switchgear
Siemens MV GIS Switchgear
 
Fundamentals of transformer inrush
Fundamentals of transformer inrushFundamentals of transformer inrush
Fundamentals of transformer inrush
 
Building information modeling
Building information modelingBuilding information modeling
Building information modeling
 
15 years of experience stator ground fault protection
15 years of experience stator ground fault protection15 years of experience stator ground fault protection
15 years of experience stator ground fault protection
 
Emergency, Legally Required and Optional Standby Systems
Emergency, Legally Required and Optional Standby SystemsEmergency, Legally Required and Optional Standby Systems
Emergency, Legally Required and Optional Standby Systems
 
Lighting Control Solutions for Daylit Spaces
Lighting Control Solutions for Daylit SpacesLighting Control Solutions for Daylit Spaces
Lighting Control Solutions for Daylit Spaces
 
COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708
 
Seismic Compliance of Electrical Distribution
Seismic Compliance of Electrical DistributionSeismic Compliance of Electrical Distribution
Seismic Compliance of Electrical Distribution
 
Generator Set Transient Performance
Generator Set Transient PerformanceGenerator Set Transient Performance
Generator Set Transient Performance
 
Modeling of a digital protective relay in a RT Digital Simulator
Modeling of a digital protective relay in a RT Digital SimulatorModeling of a digital protective relay in a RT Digital Simulator
Modeling of a digital protective relay in a RT Digital Simulator
 
Facts on Grid Friendly Wind Plants
Facts on Grid Friendly Wind PlantsFacts on Grid Friendly Wind Plants
Facts on Grid Friendly Wind Plants
 
Power Plant Horror Stories
Power Plant Horror StoriesPower Plant Horror Stories
Power Plant Horror Stories
 
Blackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load SheddingBlackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load Shedding
 
Transformer Fundamentals
Transformer FundamentalsTransformer Fundamentals
Transformer Fundamentals
 

Último

Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 

Último (20)

Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 

Out of step

  • 1. Copyright © SEL 2007 Out-Of-Step Protection Fundamentals Demetrios Tziouvaras Schweitzer Engineering Laboratories, Inc. IEEE PES San Francisco Chapter December 13, 2007
  • 2. Introduction The aim of this presentation is to explain The fundamentals of out-of-step (OOS) protection Discuss which relays and relay systems are prone to operate during power swings Share experiences and lessons learnt from the past to avoid making the same mistakes
  • 3. Introduction Interconnected systems experienced an increased number of large disturbances in the last 15 years Protective relay systems are often involved during major disturbances In many cases they prevent further propagation of the disturbance In some cases undesired relay operations have contributed to cascading blackouts
  • 4. Outline Out of step (OOS) protection fundamentals Relay performance during OOS conditions Transmission lines Generators System design and protection improvements Conclusions
  • 5. What Is a Power Swing? Variation of power flow which occurs when generator rotor angles are advancing or retarding relative to each other in response to: System faults Line switching Major load switching Loss of large generation Major system disturbances
  • 6. Stable and Unstable Power Swings Definitions A power swing is considered stable if the generators do not slip poles and the system reaches a new state of equilibrium, i.e. an acceptable operating condition An unstable power swing results in a generator or group of generators experiencing pole slipping or loss-of- synchronism for which some corrective action must be taken. Out-of-step is the same as an unstable power swing.
  • 7. Power Swings can Cause Undesired Protective Relay Operation Power swings can cause undesired relay operation that may lead to: Undesired tripping of power system elements at undesired network locations Weakening of the power system Possible cascading outages and shutdown of major portions of the power system Damage of circuit breakers due to uncontrolled tripping Loss of human life
  • 8. Unstable Power Swings Damage System Integrity Pole slipping may damage generators and turbines Low voltage conditions experienced during unstable power swings may cause: Motor stalling Generator tripping Damage to voltage-sensitive loads Prolonged low voltages could cause instability of smaller areas within a utility’s system
  • 9. Need for Out-of-Step Protection Generators operating asynchronously with the rest of the power system cannot regain stability as a result of any excitation or regulator action Asynchronous power system areas must be separated in a controlled fashion to avoid: Equipment damage Widespread outages in the power system
  • 10. Philosophy of Power-Swing Protection Detect both stable and unstable power swings Block tripping of relay elements prone to operate during power swings Differentiate between stable and unstable power swings Separate the system into islands during out-of-step conditions
  • 11. Philosophy of Power-Swing Protection Separate the system at locations that provide good balance of load/generation in the resulting system islands Trip only at pre-selected network locations and block tripping at all other locations Trip only under controlled transient recovery voltages or with low current
  • 13. Power System Stability Definition The ability of the electric power system to regain a state of operating equilibrium after being subjected to disturbances such as faults, line switching, load rejection, loss-of-excitation, and loss of generation.
  • 14. Power Flow Two-Machine System 1 2 3 4 Line 1 VS VR Line 2 X δ ⋅ = sin X VV P RSVS VR δ
  • 15. Effect of Fault Type on Power Transfer δ P Three-Phase Fault Phase-Phase-Ground Fault Phase-Phase Fault Single-Line-Ground Fault Normal System 1 2 3 4 VS VR Line 1 Line 2
  • 16. Transient Stability Concepts 1 2 3 4 Prefault state (Both lines in service) Fault state Fault state with breaker 3 open Post-fault state (Line 2 out) VS VR Line 1 Line 2
  • 18. Effect of Fault Clearing Time Unstable System Fault Post-Fault δ Prefault P
  • 19. Stable and Unstable Power Swings Rotor Angle Stable System Unstable System t δ δ0 δ1
  • 20. Angular Instability Distinguishing Features Large voltage variations Large power oscillations Loss of synchronism Zero voltage at the electrical center Frequency excursions
  • 21. Angular Instability Large Voltage Variations 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 -1 0 1 Voltage MagnitudePerunit Seconds 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0 0.5 1 1.5 PerUnit Seconds
  • 22. Angular Instability Large Power Oscillations 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 -1000 -500 0 500 Real and Reactive Power MW Seconds 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 -400 -200 0 200 400 600 MVar Seconds
  • 23. Angular Instability V1 and Angle of V1 / I1 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 0 0.2 0.4 0.6 Positive-Sequence Voltage Magnitude PerUnit Seconds 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 -200 0 200 400 Angle of (V1 / I1) Degrees Seconds
  • 24. Relay Elements Prone to Operate During Power Swings
  • 25. Stable and Unstable Power Swings Impedance Trajectories Stable Swing Unstable Swing R X
  • 26. Relay Elements Prone to Operate During Power Swings Instantaneous phase overcurrent Directional and non-directional Undervoltage Short time or instantaneous Zone 1 distance Zone 2 distance used in POTT scheme
  • 27. Line Relays Prone to Operate During Angular Instability Zone 1 distance or overreaching distance elements applied in DCB or POTT schemes Potential reasons are: Lack of PSB function or improper settings of the PSB function Lack of frequency tracking and long memory polarizing voltage Phasor measurement errors due to large excursions of system frequency during islanding
  • 28. Relay Systems Unresponsive to Power Swings Phase comparison Line current differential Pilot-wire
  • 29. Impedances Measured by Distance Relays 21 V I ZS ZL ZR VS VR ( ) SRLS RS S ZZZZ VV V IVZ −++ − ==
  • 30. Impedance Locus for k = ES / ER = 1.0 δ ZL ZR X R δ increases δ decreases δ=180° ZS 0.5ZT Z R S S T Z 2 cotj1 2 Z Z −⎟ ⎠ ⎞ ⎜ ⎝ ⎛ δ −= R S E E k =
  • 31. Two-Machine System Impedance Locii R X S k > 1 ES > ER Rk = 1 k < 1 ES < ER
  • 33. Clarify the Terminology Unstable power swing Out of step (OOS) Out-of-step blocking (OSB) Power-swing blocking (PSB) Out-of-step tripping (OST) Pole-slip tripping
  • 34. Power-Swing Protection Relay Functions Power-swing blocking (PSB) Detects both stable and unstable power swings Prevents operation of protection elements Out-of-step tripping (OST) Detects unstable power swings or OOS Separates system into islands with good generation / load balance
  • 35. Conventional PSB Scheme Load Region X R A B Z1 Inner Z ElementDistance Element Outer Z Element
  • 36. Conventional OST Scheme Load Region X R A B Z1 Inner Z ElementDistance Element Outer Z Element
  • 37. Disadvantages of Conventional PSB Scheme Needs detailed system information Requires extensive system stability studies It is difficult to set for long lines with heavy loads May fail after severe disturbances on marginally stable systems May fail during swings with high slip frequency
  • 38. Long Line With Heavy Load ZL => ZΣ A R ZR ZS Z2 X B Swing Locus Trajectory ZL
  • 39. Short Line With Light Load ZL << ZΣ A R ZR ZS Z2 X B Swing Locus Trajectory ZL
  • 40. Unstable Swing After Severe Disturbance A R ZR ZS Z2 X Swing Locus Trajectory B ZL
  • 41. New Zero-Setting PSB Function Uses swing-center voltage (SCV) Has no user settings Does not need system parameters Does not require system stability studies Provides PSB during pole open Detects evolving faults during power swings
  • 42. Swing-Center Voltage (SCV) ( ) ( ) ( ) ⎟ ⎠ ⎞ ⎜ ⎝ ⎛δ ⋅⎟ ⎠ ⎞ ⎜ ⎝ ⎛ δ +ω= 2 t cos 2 t tsinE2tSCV o' o o" Z1S•I Z1L•I VS ER δ SCV Z1R•I ES VR
  • 43. SCV During System OOS Condition Swing-Center Voltage seconds voltage(pu) SCV Amplitude 0 0.05 0.1 0.15 0.2 -1 -0.5 0 0.5 1
  • 44. Local Estimate of SCV: Vcosϕ ϕ⋅≈ cos|V|SCV S o'Z1S•I Z1R•Iθ VS ES ϕ SCV ER I Vcosϕ VR AnglepedanceImSystem:θ
  • 45. Local Estimate of SCV: Vcosϕ ⎟ ⎠ ⎞ ⎜ ⎝ ⎛ δ ⋅= 2 cos1E1SCV ( ) dt d 2 sin 2 1E dt 1SCVd δ ⎟ ⎠ ⎞ ⎜ ⎝ ⎛ δ −=
  • 46. Vcosϕ for 1-Rad/Sec OOS Condition 0 0 90 180 270 360 E1 E1/2 d (SCV1) / dt δ SCV1
  • 47. Benefits of SCV for PSB Application Independent of system source and line impedance Bounded: Lower limit: zero Upper limit: close to one per unit Relates directly to angle difference of two sources, δ
  • 48. Transmission Line Relay Performance During Out-of-Step Conditions
  • 49. 500 kV System Station C Station D Station E Line 1 Line 3 Line 2 Unit 1 Unit 2 Lines 4, 5, and 6 Intertie System B System A
  • 50. Angular Instability Z1 Trajectory – Line 2 at Station C -10 -5 0 5 10 -10 -8 -6 -4 -2 0 2 4 6 8 10 23 25 27 29 31 33 35 37 39 41 43 45 Positive-Sequence Impedance (Z1) Locus Im(Z1)ohm Re(Z1) ohm
  • 51. EHV System – Northern California Station C Station D Station E Line 1 Line 3 Line 2 Unit 1 Unit 2 Lines 4, 5, and 6 Intertie System B System A
  • 52. Zone 1 Operation During OOS PSB Function not Enabled
  • 53. Zone 1 Distance Is Blocked First Slip Cycle
  • 54. Zone 1 Distance Operates Second Slip Cycle
  • 55. Zone 1 Distance Operates Second Slip Cycle Fast slip frequency change Setting fine-tuning could have prevented operation of Zone 1 Concentric zone settings Separation between concentric zones PSB timer All of these settings are difficult to make Long heavy loaded lines Require large number of stability studies
  • 56. Proper Blocking of Distance Elements by Zero Setting PSB 0 5 10 15 20 -1 -0.5 0 0.5 1 SCV1 (Solid), dSCV1/dt (Dash) (pu),(pu/cyc) 0 5 10 15 20 Cycle S PSB DPSB 67QUB 3PF Reset PSB Reset SLD Set Start-Zn SSD Set
  • 58. Units 1 and 2 Operations Station C Station D Station E Line 1 Line 3 Line 2 Unit 1 Unit 2 Lines 4, 5, and 6 Intertie System B System A
  • 59. One Unit Trips by Undervoltage 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 -1 -0.5 0 0.5 1 Station C Voltage Perunit Seconds
  • 60. Unit 1: Three-Phase P and Q During OOS 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 -2000 0 2000 Real Power MW Seconds 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 -1000 0 1000 Reactive Power MVar Seconds
  • 61. Units 1 and 2 Trip Inst. Dir. Phase OC Relay -20 -10 0 10 20 -40 -30 -20 -10 0 10 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 Positive-Sequence Impedance (Z1) Locus Im(Z1)ohm Re(Z1) ohm
  • 62. Protection System and Other System Improvements to Preserve System Stability
  • 63. Proper System and Protection Design Preserve System Stability Prevent the occurrence of out-of-step conditions Install sufficient transmission capacity Maintain adequate reactive reserves Apply high-speed relaying systems and high-speed reclosing Apply single-phase tripping and reclosing Apply wide-area stability controls
  • 64. Wide-Area Stability Controls or SIPS Preserve System Stability Wide-area stability controls Generator dropping Direct load dropping Fast valving Insertion of breaking resistors Series and shunt capacitor insertion Use FACTS devices
  • 65. Protection System and Other Improvements Improvements in transient stability High speed fault clearing Single phase tripping and reclosing Apply local breaker failure protection on all EHV and critical HV substations Special protection systems Controlled system separation UVLS and UFLS
  • 66. Protection System Improvements Apply dual pilot protection relay systems on all EHV and critical HV systems with PSB capability, or with systems that are immune to stable or unstable power swings Replace secondary non-pilot line relay systems in non-critical HV lines with: A relay system that has similar functionality with the main pilot protection system Consider switching the communications channel to the secondary relay system when the Main 1 is out of service
  • 67. Conclusions Utilities must take every action economically justifiable to preserve system stability Out-of-step tripping should be applied and operate only as a last resort to preserve system stability OST and PSB should be applied based on an inter-regional controlled system separation philosophy
  • 68. Conclusions OOS tripping must separate the system at predetermined locations to minimize the effect of the disturbance OOS blocking compliments OOS tripping by blocking relay elements prone to operate and ensures a controlled system separation Controlled separation schemes provide a safety net to lessen the impacts of major disturbances
  • 69. References Out-Of-Step Protection Fundamentals and Advancements http://www.selinc.com/techpprs/6163.pdf Zero-Setting Power-Swing Blocking Protection http://www.selinc.com/techpprs/6172_ZeroSetting_20050302.pdf Relay Performance During Major System Disturbances http://www.selinc.com/techpprs/6244_RelayPerformance_DT_20060914.pdf