EVM Practice
Business Solutions & Lessons Learned

Mohan Kondur
  BE(Honors), PGDIE (Ind Engg), MBA, PMP, PgMP


             EVIAP Project Control & EVM Conference Lisbon, Portugal
               November, 15th & 16th 2011 © 2011 All Rights Reserved
EVM Practice - AGENDA
                        Business Solutions & Lessons Learned
2




                        Introduction
               45 Min
                        Approach
                        Lessons Learned
                        Tool Artifacts



                        Q&A
                15
                Min     Demo



    12/29/20               EVIAP Project Control & EVM Conference Lisbon, Portugal
    11                       November, 15th & 16th 2011 © 2011 All Rights Reserved
Who is Mohan Kondur- BS, MS, MBA, PMP, PgMP
3
               • Program Manager (Delivery , EPMO )
               • EVM Customer &
               • NOT an EVM Insider
     Diverse Industry Sector Engagements
          Health Sector : United Health Group, Detroit Medical Center, BCBSM
          Auto / Manufacturing Sector: GM, Ford, Chrysler ,Delphi, GE, HMT (India)
          Finance / Banking Sector: Ford Credit, Comerica Bank , Allay Bank ( former GMAC)

     35+ years in the field
          Program /Project Management, Business Management & Marketing, Industrial Engineering


     EVM Publication PMI CPM’s Quarterly News Letter “Measurable News” Summer 07
          http://www.pmi-cpm.org/members/library/KondurFINAL.pdf


    12/29/20                   EVIAP Project Control & EVM Conference Lisbon, Portugal
    11                           November, 15th & 16th 2011 © 2011 All Rights Reserved
Presentation Objective ( Share Lessons Learned / Best Practices)


                           Share
                   Lessons Learned
                  EVM Practice Guidelines
                 Model Enhancements (Thought Starters)
                 Earned Schedule (Emerging Practice)
                 DEMO (time permitting)

                  Organizational Transformation
                  Internalize EVM into Project Management


                       EVM Transformation
                                                    Partir   Confiança
Parar !!
                                                                    4
Who is Prj Mgr? Executes EVM           or Executed By EVM?
5




    Executes?



                  Executed?


Key Differentiator.. EV Process Quality & Reliability
    12/29/20    EVIAP Project Control & EVM Conference Lisbon, Portugal
    11            November, 15th & 16th 2011 © 2011 All Rights Reserved
Project Management Process Quality – An Imperative for EVM Practice

6



                     Ensure end-to-end QUALITY
                                                            Closing
     Initiating

                       Initiating Processes
                       Planning Processes
                       Executing Processes
                       Monitoring &
                         Controlling Processes
                       Closing Processes
From                                                        To
Project Cradle                                              Project Grave

    12/29/20             EVIAP Project Control & EVM Conference Lisbon, Portugal
    11                     November, 15th & 16th 2011 © 2011 All Rights Reserved
Hitting EV Bulls Eye
7




               No Pain                                  No Gain

                                                               SPI / CPI &
                                                             Earned Schedule
       TRACKING DUE DILIGENCE




     QUALITY IMPLEMENTATION
       & PROCESS COMPLIANCE
                                     Pain Killers Available
    12/29/20         EVIAP Project Control & EVM Conference Lisbon, Portugal
    11                 November, 15th & 16th 2011 © 2011 All Rights Reserved
SPI & CPI - 101
8

                Status indicators of Schedule & Cost

                Binary by Definition. Either
                      You are On-Track (SPI & CPI = 1.0)
                      Or You are NOT
                Precision Metrics by Nature
            Current         Used to be
     SPI    EV / PV       BCWP / BCWS
    CPI     EV / AC       BCWP / ACWP
Common Thread (or Handicap?) - Cost-Based Model
    12/29/20              EVIAP Project Control & EVM Conference Lisbon, Portugal
    11                      November, 15th & 16th 2011 © 2011 All Rights Reserved
Cost Model SPI/CPI – 3 Showstopper Issues
9
               Issue # 1
                  Financials & WBS are rarely integrated.
                  Budgets are usually managed:
                           At a Contract / Engagement Level
                           Rarely at a WBS Deliverable Level
               Issue # 2
                        Billing Rates: NOT internalized in WBS. Usually
                        managed external to WBS
                         Competition Sensitive Data
                         Artificially Blended Rates
               Issue # 3
                       Typical PM Behavior / Mindset
                         Focus on Schedule, NOT Cost

    12/29/20           EVIAP Project Control & EVM Conference Lisbon, Portugal
    11                   November, 15th & 16th 2011 © 2011 All Rights Reserved
Model Workaround
10




         Cost Model                            Hours Model

     1      BCWS or PV               Baseline Effort Hours




     2      ACWP or AC               Actual Effort Hours

                                                               Determining EV
                                                               Options to
                                                               Calculate
     3      BCWP or EV               Earned Hours




 12/29/20                 EVIAP Project Control & EVM Conference Lisbon, Portugal
 11                         November, 15th & 16th 2011 © 2011 All Rights Reserved
EV – Calculation – PMI Status Quo
11


                                                                        Remark
     Option     Method                       EV Rule
                                                                          s
                             = 100% of baseline if Task Completed
       1       0 - 100 %                                                Same as
                             = 0% of baseline for any other Status
                                                                          in
                             = 100% of baseline if Task has Completed   PMBOK
              0 – 50 -100%
       2                     = 50% of baseline if Task has Started
               (aka 50-50)
                             = 0% if Task has NOT Started

       3      % Complete     = % Work Complete * Baseline
                                                                        Thought
                                                                        Starters
       4      ETC Forecast   = Baseline – Remaining Work

All Options are Tool Supported;               To Illustrate Option-4

 12/29/20                EVIAP Project Control & EVM Conference Lisbon, Portugal
 11                        November, 15th & 16th 2011 © 2011 All Rights Reserved
Option-4 ETC Forecast Method - Example
12


      Determining Earned Value                              Hours
                    PV - Baseline Work, say
     EV Critical                                              100
                    AC - Actual Work, say
     CPI Critical                                             50
                    ETC - Remaining Work, say
     SPI Critical                                             70
     EVA Critical   EV - Earned Value
                                                               30
                                                      = 100 - 70

      Schedule Driver         “What is Remaining” to Complete

 12/29/20              EVIAP Project Control & EVM Conference Lisbon, Portugal
 11                      November, 15th & 16th 2011 © 2011 All Rights Reserved
EV Risks Corrected Model - Thought Starter
13



       EV Risks
       linked to




                                   EVA Reliability
                                                               WBS

 WBS Quality                                         SPI/CPI



                                                         WBS Quality




 12/29/20          EVIAP Project Control & EVM Conference Lisbon, Portugal
 11                  November, 15th & 16th 2011 © 2011 All Rights Reserved
Risks Corrected EVA = Standard EVA * WBS Quality
14




                                                     Triple
                                                     Constraint
                                                     Risks


1. Scope Risk


        2. Schedule Risk                3. Cost Risk
Overall WBS Risk Quality = Average of Scope, Cost , Schedule
Let us review WBS quality index an example
 12/29/20        EVIAP Project Control & EVM Conference Lisbon, Portugal
 11                November, 15th & 16th 2011 © 2011 All Rights Reserved
WBS Quality Index – EV Risks Measurement Example




                                                             %
               Quality             How Measured            Tasks   Quality
 Risk Source   Weight            (Count # of Tasks)       in WBS   Score

  Scope        1/3          All 10 Tasks Base-Lined       100%     33%
 Schedule      1/3           Only 9 Tasks Estimated       90%      30%
   Cost        1/3       Only 6 Tasks Resource-Assigned   60%      20%

                 Overall WBS % Quality ( = Risk)                   83%15
Interpreting Risk Adjusted EVA
16
                     Standard SPI / CPI
     Green SPI = 1.05 => Ahead of Schedule



                                                        Schedule Quality 90%
            Scope Quality 100%

                                  Cost Quality 60%
                                                                  Risk Adjusted SPI
                                                                  0.87 = 1.05 * 83%
                            Overall WBS Quality = 83%
                                                                  Behind Schedule



 Schedule is Really at Risk or
   87% Confidence about an 1.05 SPI
 12/29/20                  EVIAP Project Control & EVM Conference Lisbon, Portugal
 11                          November, 15th & 16th 2011 © 2011 All Rights Reserved
EVA Custom Tool - MS Project Add-on – Just    a Mouse Click



EVA Knowledge (or Mechanics)- Least Important
PM Delivery Maturity & WBS Quality More Important




   Project
              Generate

                                              SPI / CPI
                         Consolidate          Tool
                       Consolidate & Rollup
             Program
                                                          17
EVA Tool Artifacts Project SPI / CPI - Spreadsheets)
18

              EVA Demo : Earned Value SPI / CPI vs. Baseline
                          (All Tasks ) (Hours Based) - As of 2/9/2007
           Quality :     Overall (83%) Scope (71%), Schedule (100%) Cost(78%)



1.40


1.20

                                                                                 SPI
1.00                                                                            CPI
                                                   CPI
              CPI                                   SPI
                                                                                Risk SPI
0.80                                                Risk CPI                    Risk CPI
              SPI CPI
              Risk                                  Risk SPI

              Risk SPI
0.60


0.40


0.20


0.00
         1/28/2007                            2/4/2007                     2/11/2007
                                       SPI   CPI   Risk SPI    Risk CPI



                         EVIAP Project Control & EVM Conference Lisbon, Portugal
                           November, 15th & 16th 2011 © 2011 All Rights Reserved
Program Roll up - EVMs (SP/CPI)
19
                       Consolidated Demo Project : Schedule Performance Index (SPI)
                                     (Hours Based) - As of 4/29/2005


                  Component Project-3 SPI                                                           Component Project-1 SPI
     1.40


     1.20


     1.00


     0.80


     0.60


     0.40


     0.20


     0.00
            02/05/05   02/12/05   02/19/05   02/26/05   03/05/05   03/12/05   03/19/05   03/26/05   04/02/05   04/09/05   04/16/05   04/23/05   04/30/05

                                               Demo_Project 1 - ba seline d       Demo_Project 2        Demo_Project 3




                       Program Rollup                                    EV Status Date                               SPI                  CPI
                             Project - 1                                        08/04/06                             0.92                 0.78

                             Project - 3                                        08/04/06                             1.15                 0.99



 12/29/20                                    EVIAP Project Control & EVM Conference Lisbon, Portugal
 11                                            November, 15th & 16th 2011 © 2011 All Rights Reserved
EVM Implementation Lessons Learned
20




             Fortune 100 Implementation
             Not Just Theory
 12/29/20          EVIAP Project Control & EVM Conference Lisbon, Portugal
 11                  November, 15th & 16th 2011 © 2011 All Rights Reserved
EVM Lessons Learned – Environment
21




•    Multi-Year Strategic Program
•    Multi-Supplier Autonomous Projects
•    Program Governance Framework
•    Outsourced Project Management / PMO



 12/29/20    EVIAP Project Control & EVM Conference Lisbon, Portugal
 11            November, 15th & 16th 2011 © 2011 All Rights Reserved
EVM Practice - Lessons Learned
22



     1.     Milestone Mindset - PM & Org Culture Block
     2.     Project Level Ownership Lack of Ownership
     3.     EV Reliability - WBS Quality GIGO
     4.     EVM Initiative Sustenance Keep it simple
     5.     Doctored WBS – Evergreen WYG WYA
     6.     Higher Band Risks Too good to be true
     7.     Program / Portfolio Rollup Not Actionable
     8.     Schedule / Cost Tracking EV Practice Critical

 12/29/20           EVIAP Project Control & EVM Conference Lisbon, Portugal
 11                   November, 15th & 16th 2011 © 2011 All Rights Reserved
Lesson # 1: Milestone / Date Mindset-PM / Organizational Culture Block

23

       SPI / CPI fails whenever Projects communicate only
       through Milestones & Dates
       Resolutions:
               Ensure Deliverables-Oriented WBS
               Track Level of Effort (LoE) Hours
               Train, Educate & Mentor Project Managers




 12/29/20              EVIAP Project Control & EVM Conference Lisbon, Portugal
 11                      November, 15th & 16th 2011 © 2011 All Rights Reserved
Lesson # 2 Project Level PM Ownership & Accountability
24


     PM Ownership is Crucial
     Resolution:
             Project PM generates & owns SPI / CPI
             Resist temptation to generate EV Metrics by
              central PMO or a Project Coordinator




 12/29/20               EVIAP Project Control & EVM Conference Lisbon, Portugal
 11                       November, 15th & 16th 2011 © 2011 All Rights Reserved
Lesson # 3 EV Reliability – WBS Quality
     GIGO ( Garbage in Garbage Out)
25




            Standard SPI / CPI does not
            factor in WBS Quality

            Mitigation Approach:
               Risk-Adjusted SPI/CPI Model


 12/29/20           EVIAP Project Control & EVM Conference Lisbon, Portugal
 11                   November, 15th & 16th 2011 © 2011 All Rights Reserved
Lesson # 4 EVM Sustenance
26


            Sustained EVM initiative requires
            Continuous Accommodation &
            Collaboration, especially in a
            Multi-Supplier Outsourced
            Projects & Stakeholders
            Environment
            Mitigation Approach:
               Keep it Simple & be Flexible
 12/29/20            EVIAP Project Control & EVM Conference Lisbon, Portugal
 11                    November, 15th & 16th 2011 © 2011 All Rights Reserved
Lesson # 5 Doctored WBS - WYGWYA
27

                              3%                               4%       91%                  2%
                        700
                                                                            649

                        600
                                                                              Standard SPI
                        500
                                                                                              Goal 1.0
            Frequency




                        400               Risk-Adjusted
                        300
                                          SPI                                     265

                        200


                        100
                                                                    37 40
                              3   0   1    0   0   3   5   8   14                       13   4    0   3   2   1   2   1   1
                         0
                              0.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0 1.0 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9 2.0

                >1000 Data Points; > 40 Projects                        SPI




     WYGWYA .. What You Get is Whatever You Ask

 12/29/20                                 EVIAP Project Control & EVM Conference Lisbon, Portugal
 11                                         November, 15th & 16th 2011 © 2011 All Rights Reserved
Lesson # 6 Higher Band Lesson
28
     Track being Ahead. But be Suspicious. Too Good to be True !!

                                    Higher Band? Ahead ??
                         1.10
        Way Ahead
                         1.00
                                              Goal                  Goal
        On Track
                         0.95
        At Risk          0.90
        Way Behind
                         0.80

                         0.70

                         0.60
                             Wk1         Wk2          Wk3         Wk4
                        EVIAP Project Control & EVM Conference Lisbon, Portugal
                          November, 15th & 16th 2011 © 2011 All Rights Reserved
Lesson # 7 Program Rollup EVM
29

 Program Rollup
 • Practically Useless. NOT ACTIONABLE
 • Usually Great for Boardroom Color Management
Project Level Analysis, Ownership & Accountability is Crucial
               Project       AND / OR    Program / Portfolio
     SPI / CPI
               Structure                 Structure
     Single                                                 SPI-Rollup
      WBS


                                 SPI-1           SPI-2           SPI-3
                   EVIAP Project Control & EVM Conference Lisbon, Portugal
                     November, 15th & 16th 2011 © 2011 All Rights Reserved
Lesson # 8 Schedule / Cost Tracking is EVM Critical
30




           Heavy Cost .. Enterprise Technology
           Low Cost .. Project / Excel Macros
           Choose whatever means ..
             EVMetrics does not Care
             EVM Practice Cares
           Just Ensure Quality Tracking Process

               TRACKING
               FOUNDATIONAL
               PILLAR

 12/29/20             EVIAP Project Control & EVM Conference Lisbon, Portugal
 11                     November, 15th & 16th 2011 © 2011 All Rights Reserved
Tracking Mandatory to Mitigate Project Schedule / Cost Obsolescence Risks



                                               Requires
                                               Tight Rope
                                               Quality Walk




    Any Project Plan becomes obsolete the moment
               finalized Unless Tracked

                                                                      31
Project Schedule / Cost Tracking: Top Challenges
32

      HOW TO:
         Track Without High Costs?
         Maximize Team Collaboration?
         Support Organizational Metrics Initiatives?
         Minimize ADMIN Drudgery?
         Avoid System Choke (Month End, Week End)?
         Simplify Technology and Be User Friendly?

 12/29/20            EVIAP Project Control & EVM Conference Lisbon, Portugal
 11                    November, 15th & 16th 2011 © 2011 All Rights Reserved
Market Scan: Tracking Solutions State
33

    Many Options - Windows, WEB, Others. Typical Outcomes :
         High Cost ($$ /    ) , Hidden / Training Costs, HighTech
         Gold-Plated / Over-Featured
         Unproven. Yet to see evidence of effective implementation

Typical Rollout Experiences ( MS Project Server , Planview)
• Never-ending Mega Projects in themselves
• Hardly Meet Business Expectations
• Significant time wasted on chasing tool issues &
   diverted away from managing / resolving Core Delivery
   & Project Issues

    12/29/20           EVIAP Project Control & EVM Conference Lisbon, Portugal
    11                   November, 15th & 16th 2011 © 2011 All Rights Reserved
LoE Project Tracking – EV Practice Critical
34


            Estimates To Complete (ETC) - Schedule Critical
            Actual Effort - Cost Critical
            Periodic Tracking (ETC & Actual) - EV Practice Critical
                          TOOL SUPPORT (MS Project Platform)

     Electronic LoE Timesheets Tool                   Periodic LoE Tracking Cycle



                                                            Create Validate


                                                                 Apply

 12/29/20                 EVIAP Project Control & EVM Conference Lisbon, Portugal
 11                         November, 15th & 16th 2011 © 2011 All Rights Reserved
Tracking is EV critical
35


    Logistics & How Tracked:
      EVM Does NOT Care about Tracking Logistics

      EVM Does Require Quality Tracking Due diligence



    Tracking Solutions Cost Impact:
      Heavy Cost: Enterprise Technology Solutions

      Low Cost: Project Centric Solutions (MSP / Excel Macros)




 12/29/20           EVIAP Project Control & EVM Conference Lisbon, Portugal
 11                   November, 15th & 16th 2011 © 2011 All Rights Reserved
Conclusion ( Conclusao )
36

     Priorities for Successful EVM Practice
 1. Project Management (PM) Domain
      Ensure      : Quality Planning Process Backbone
      Internalize : EVM into Project Control Practices

2. EVM Domain
EVM Implementation / Adoption / internalized in PM HIGH PRIORITY
EVM ISO Stds  LOW PRIORITY. May follow after PMI releases PM ISO Stds for PM


               •PM  Delivery Maturity & Magic is MORE Crucial
               •Tracking is a MUST


 12/29/20                EVIAP Project Control & EVM Conference Lisbon, Portugal
 11                        November, 15th & 16th 2011 © 2011 All Rights Reserved
Thank You, Obrigados !!
37




                Q&A
                Tool DEMO
                      On-line now, if time permits
                      Off-line later, if required




 12/29/20   EVIAP Project Control & EVM Conference Lisbon, Portugal
 11           November, 15th & 16th 2011 © 2011 All Rights Reserved

Más contenido relacionado

Similar a Eviap Conference Lisbon Portugal 2011

Business Process Modeling Notation Fundamentals
Business Process Modeling Notation FundamentalsBusiness Process Modeling Notation Fundamentals
Business Process Modeling Notation Fundamentals
Mustafa Jarrar
 
Mahmood porter
Mahmood porterMahmood porter
Mahmood porter
NASAPMC
 
Pal gov.tutorial1.session15 16
Pal gov.tutorial1.session15 16Pal gov.tutorial1.session15 16
Pal gov.tutorial1.session15 16
Mustafa Jarrar
 
La visione di Oracle per la Management Excellence e overview di Oracle Hyperi...
La visione di Oracle per la Management Excellence e overview di Oracle Hyperi...La visione di Oracle per la Management Excellence e overview di Oracle Hyperi...
La visione di Oracle per la Management Excellence e overview di Oracle Hyperi...
antonella Buonagurio
 
Pal gov.tutorial1.session13 14
Pal gov.tutorial1.session13 14Pal gov.tutorial1.session13 14
Pal gov.tutorial1.session13 14
Mustafa Jarrar
 
NG BB 55 CONTROL Tollgate
NG BB 55 CONTROL TollgateNG BB 55 CONTROL Tollgate
NG BB 55 CONTROL Tollgate
Leanleaders.org
 

Similar a Eviap Conference Lisbon Portugal 2011 (20)

Project Controls Expo – 13th Nov 2013- "The Key Role of the Cost Engineer Ach...
Project Controls Expo – 13th Nov 2013- "The Key Role of the Cost Engineer Ach...Project Controls Expo – 13th Nov 2013- "The Key Role of the Cost Engineer Ach...
Project Controls Expo – 13th Nov 2013- "The Key Role of the Cost Engineer Ach...
 
Project Controls Expo, 13th Nov 2013 - "EVM for the Rest of Us" By Javier Slo...
Project Controls Expo, 13th Nov 2013 - "EVM for the Rest of Us" By Javier Slo...Project Controls Expo, 13th Nov 2013 - "EVM for the Rest of Us" By Javier Slo...
Project Controls Expo, 13th Nov 2013 - "EVM for the Rest of Us" By Javier Slo...
 
Sourcing
SourcingSourcing
Sourcing
 
Business Process Modeling Notation Fundamentals
Business Process Modeling Notation FundamentalsBusiness Process Modeling Notation Fundamentals
Business Process Modeling Notation Fundamentals
 
How to setup EVM within a PMO
How to setup EVM within a PMOHow to setup EVM within a PMO
How to setup EVM within a PMO
 
Strome | Innovation in expense management
Strome | Innovation in expense managementStrome | Innovation in expense management
Strome | Innovation in expense management
 
Improving Quality and Cost-effectiveness in Enterprise Software Application ...
Improving Quality and Cost-effectiveness in  Enterprise Software Application ...Improving Quality and Cost-effectiveness in  Enterprise Software Application ...
Improving Quality and Cost-effectiveness in Enterprise Software Application ...
 
Rfid roi-sme pilots presentation and results ueapme august 2012
Rfid roi-sme pilots presentation and results ueapme august 2012Rfid roi-sme pilots presentation and results ueapme august 2012
Rfid roi-sme pilots presentation and results ueapme august 2012
 
ESE 2010 - eBPM - Business Process Management for OSGi
ESE 2010 - eBPM - Business Process Management for OSGiESE 2010 - eBPM - Business Process Management for OSGi
ESE 2010 - eBPM - Business Process Management for OSGi
 
Mahmood porter
Mahmood porterMahmood porter
Mahmood porter
 
Pal gov.tutorial1.session15 16
Pal gov.tutorial1.session15 16Pal gov.tutorial1.session15 16
Pal gov.tutorial1.session15 16
 
La visione di Oracle per la Management Excellence e overview di Oracle Hyperi...
La visione di Oracle per la Management Excellence e overview di Oracle Hyperi...La visione di Oracle per la Management Excellence e overview di Oracle Hyperi...
La visione di Oracle per la Management Excellence e overview di Oracle Hyperi...
 
European projects at ISPIM conference
European projects at ISPIM conferenceEuropean projects at ISPIM conference
European projects at ISPIM conference
 
Pal gov.tutorial1.session13 14
Pal gov.tutorial1.session13 14Pal gov.tutorial1.session13 14
Pal gov.tutorial1.session13 14
 
Practical M&E
Practical M&EPractical M&E
Practical M&E
 
A Model-Driven Approach to Implementing Coordination Protocols in BPEL
A Model-Driven Approach to Implementing Coordination Protocols in BPELA Model-Driven Approach to Implementing Coordination Protocols in BPEL
A Model-Driven Approach to Implementing Coordination Protocols in BPEL
 
PEPPOL Pilot Execution Guidelines
PEPPOL Pilot Execution GuidelinesPEPPOL Pilot Execution Guidelines
PEPPOL Pilot Execution Guidelines
 
NG BB 55 CONTROL Tollgate
NG BB 55 CONTROL TollgateNG BB 55 CONTROL Tollgate
NG BB 55 CONTROL Tollgate
 
How Do Our Clients Use CONOPS?
How Do Our Clients Use CONOPS?How Do Our Clients Use CONOPS?
How Do Our Clients Use CONOPS?
 
Introduction to OSLC and Linked Data
Introduction to OSLC and Linked DataIntroduction to OSLC and Linked Data
Introduction to OSLC and Linked Data
 

Eviap Conference Lisbon Portugal 2011

  • 1. EVM Practice Business Solutions & Lessons Learned Mohan Kondur BE(Honors), PGDIE (Ind Engg), MBA, PMP, PgMP EVIAP Project Control & EVM Conference Lisbon, Portugal November, 15th & 16th 2011 © 2011 All Rights Reserved
  • 2. EVM Practice - AGENDA Business Solutions & Lessons Learned 2 Introduction 45 Min Approach Lessons Learned Tool Artifacts Q&A 15 Min Demo 12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal 11 November, 15th & 16th 2011 © 2011 All Rights Reserved
  • 3. Who is Mohan Kondur- BS, MS, MBA, PMP, PgMP 3 • Program Manager (Delivery , EPMO ) • EVM Customer & • NOT an EVM Insider  Diverse Industry Sector Engagements  Health Sector : United Health Group, Detroit Medical Center, BCBSM  Auto / Manufacturing Sector: GM, Ford, Chrysler ,Delphi, GE, HMT (India)  Finance / Banking Sector: Ford Credit, Comerica Bank , Allay Bank ( former GMAC)  35+ years in the field  Program /Project Management, Business Management & Marketing, Industrial Engineering  EVM Publication PMI CPM’s Quarterly News Letter “Measurable News” Summer 07  http://www.pmi-cpm.org/members/library/KondurFINAL.pdf 12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal 11 November, 15th & 16th 2011 © 2011 All Rights Reserved
  • 4. Presentation Objective ( Share Lessons Learned / Best Practices) Share  Lessons Learned  EVM Practice Guidelines Model Enhancements (Thought Starters) Earned Schedule (Emerging Practice) DEMO (time permitting) Organizational Transformation Internalize EVM into Project Management EVM Transformation Partir Confiança Parar !! 4
  • 5. Who is Prj Mgr? Executes EVM or Executed By EVM? 5 Executes? Executed? Key Differentiator.. EV Process Quality & Reliability 12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal 11 November, 15th & 16th 2011 © 2011 All Rights Reserved
  • 6. Project Management Process Quality – An Imperative for EVM Practice 6 Ensure end-to-end QUALITY Closing Initiating Initiating Processes Planning Processes Executing Processes Monitoring & Controlling Processes Closing Processes From To Project Cradle Project Grave 12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal 11 November, 15th & 16th 2011 © 2011 All Rights Reserved
  • 7. Hitting EV Bulls Eye 7 No Pain No Gain SPI / CPI & Earned Schedule TRACKING DUE DILIGENCE QUALITY IMPLEMENTATION & PROCESS COMPLIANCE Pain Killers Available 12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal 11 November, 15th & 16th 2011 © 2011 All Rights Reserved
  • 8. SPI & CPI - 101 8  Status indicators of Schedule & Cost  Binary by Definition. Either  You are On-Track (SPI & CPI = 1.0)  Or You are NOT  Precision Metrics by Nature Current Used to be SPI EV / PV BCWP / BCWS CPI EV / AC BCWP / ACWP Common Thread (or Handicap?) - Cost-Based Model 12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal 11 November, 15th & 16th 2011 © 2011 All Rights Reserved
  • 9. Cost Model SPI/CPI – 3 Showstopper Issues 9 Issue # 1 Financials & WBS are rarely integrated. Budgets are usually managed:  At a Contract / Engagement Level  Rarely at a WBS Deliverable Level Issue # 2 Billing Rates: NOT internalized in WBS. Usually managed external to WBS Competition Sensitive Data Artificially Blended Rates Issue # 3 Typical PM Behavior / Mindset Focus on Schedule, NOT Cost 12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal 11 November, 15th & 16th 2011 © 2011 All Rights Reserved
  • 10. Model Workaround 10 Cost Model Hours Model 1 BCWS or PV Baseline Effort Hours 2 ACWP or AC Actual Effort Hours Determining EV Options to Calculate 3 BCWP or EV Earned Hours 12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal 11 November, 15th & 16th 2011 © 2011 All Rights Reserved
  • 11. EV – Calculation – PMI Status Quo 11 Remark Option Method EV Rule s = 100% of baseline if Task Completed 1 0 - 100 % Same as = 0% of baseline for any other Status in = 100% of baseline if Task has Completed PMBOK 0 – 50 -100% 2 = 50% of baseline if Task has Started (aka 50-50) = 0% if Task has NOT Started 3 % Complete = % Work Complete * Baseline Thought Starters 4 ETC Forecast = Baseline – Remaining Work All Options are Tool Supported; To Illustrate Option-4 12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal 11 November, 15th & 16th 2011 © 2011 All Rights Reserved
  • 12. Option-4 ETC Forecast Method - Example 12 Determining Earned Value Hours PV - Baseline Work, say EV Critical 100 AC - Actual Work, say CPI Critical 50 ETC - Remaining Work, say SPI Critical 70 EVA Critical EV - Earned Value 30 = 100 - 70 Schedule Driver “What is Remaining” to Complete 12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal 11 November, 15th & 16th 2011 © 2011 All Rights Reserved
  • 13. EV Risks Corrected Model - Thought Starter 13 EV Risks linked to EVA Reliability WBS WBS Quality SPI/CPI WBS Quality 12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal 11 November, 15th & 16th 2011 © 2011 All Rights Reserved
  • 14. Risks Corrected EVA = Standard EVA * WBS Quality 14 Triple Constraint Risks 1. Scope Risk 2. Schedule Risk 3. Cost Risk Overall WBS Risk Quality = Average of Scope, Cost , Schedule Let us review WBS quality index an example 12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal 11 November, 15th & 16th 2011 © 2011 All Rights Reserved
  • 15. WBS Quality Index – EV Risks Measurement Example % Quality How Measured Tasks Quality Risk Source Weight (Count # of Tasks) in WBS Score Scope 1/3 All 10 Tasks Base-Lined 100% 33% Schedule 1/3 Only 9 Tasks Estimated 90% 30% Cost 1/3 Only 6 Tasks Resource-Assigned 60% 20% Overall WBS % Quality ( = Risk) 83%15
  • 16. Interpreting Risk Adjusted EVA 16 Standard SPI / CPI Green SPI = 1.05 => Ahead of Schedule Schedule Quality 90% Scope Quality 100% Cost Quality 60% Risk Adjusted SPI 0.87 = 1.05 * 83% Overall WBS Quality = 83% Behind Schedule  Schedule is Really at Risk or  87% Confidence about an 1.05 SPI 12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal 11 November, 15th & 16th 2011 © 2011 All Rights Reserved
  • 17. EVA Custom Tool - MS Project Add-on – Just a Mouse Click EVA Knowledge (or Mechanics)- Least Important PM Delivery Maturity & WBS Quality More Important Project Generate SPI / CPI Consolidate Tool Consolidate & Rollup Program 17
  • 18. EVA Tool Artifacts Project SPI / CPI - Spreadsheets) 18 EVA Demo : Earned Value SPI / CPI vs. Baseline (All Tasks ) (Hours Based) - As of 2/9/2007 Quality : Overall (83%) Scope (71%), Schedule (100%) Cost(78%) 1.40 1.20 SPI 1.00 CPI CPI CPI SPI Risk SPI 0.80 Risk CPI Risk CPI SPI CPI Risk Risk SPI Risk SPI 0.60 0.40 0.20 0.00 1/28/2007 2/4/2007 2/11/2007 SPI CPI Risk SPI Risk CPI EVIAP Project Control & EVM Conference Lisbon, Portugal November, 15th & 16th 2011 © 2011 All Rights Reserved
  • 19. Program Roll up - EVMs (SP/CPI) 19 Consolidated Demo Project : Schedule Performance Index (SPI) (Hours Based) - As of 4/29/2005 Component Project-3 SPI Component Project-1 SPI 1.40 1.20 1.00 0.80 0.60 0.40 0.20 0.00 02/05/05 02/12/05 02/19/05 02/26/05 03/05/05 03/12/05 03/19/05 03/26/05 04/02/05 04/09/05 04/16/05 04/23/05 04/30/05 Demo_Project 1 - ba seline d Demo_Project 2 Demo_Project 3 Program Rollup EV Status Date SPI CPI Project - 1 08/04/06 0.92 0.78 Project - 3 08/04/06 1.15 0.99 12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal 11 November, 15th & 16th 2011 © 2011 All Rights Reserved
  • 20. EVM Implementation Lessons Learned 20  Fortune 100 Implementation  Not Just Theory 12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal 11 November, 15th & 16th 2011 © 2011 All Rights Reserved
  • 21. EVM Lessons Learned – Environment 21 • Multi-Year Strategic Program • Multi-Supplier Autonomous Projects • Program Governance Framework • Outsourced Project Management / PMO 12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal 11 November, 15th & 16th 2011 © 2011 All Rights Reserved
  • 22. EVM Practice - Lessons Learned 22 1. Milestone Mindset - PM & Org Culture Block 2. Project Level Ownership Lack of Ownership 3. EV Reliability - WBS Quality GIGO 4. EVM Initiative Sustenance Keep it simple 5. Doctored WBS – Evergreen WYG WYA 6. Higher Band Risks Too good to be true 7. Program / Portfolio Rollup Not Actionable 8. Schedule / Cost Tracking EV Practice Critical 12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal 11 November, 15th & 16th 2011 © 2011 All Rights Reserved
  • 23. Lesson # 1: Milestone / Date Mindset-PM / Organizational Culture Block 23 SPI / CPI fails whenever Projects communicate only through Milestones & Dates Resolutions:  Ensure Deliverables-Oriented WBS  Track Level of Effort (LoE) Hours  Train, Educate & Mentor Project Managers 12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal 11 November, 15th & 16th 2011 © 2011 All Rights Reserved
  • 24. Lesson # 2 Project Level PM Ownership & Accountability 24 PM Ownership is Crucial Resolution:  Project PM generates & owns SPI / CPI  Resist temptation to generate EV Metrics by central PMO or a Project Coordinator 12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal 11 November, 15th & 16th 2011 © 2011 All Rights Reserved
  • 25. Lesson # 3 EV Reliability – WBS Quality GIGO ( Garbage in Garbage Out) 25 Standard SPI / CPI does not factor in WBS Quality Mitigation Approach:  Risk-Adjusted SPI/CPI Model 12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal 11 November, 15th & 16th 2011 © 2011 All Rights Reserved
  • 26. Lesson # 4 EVM Sustenance 26 Sustained EVM initiative requires Continuous Accommodation & Collaboration, especially in a Multi-Supplier Outsourced Projects & Stakeholders Environment Mitigation Approach:  Keep it Simple & be Flexible 12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal 11 November, 15th & 16th 2011 © 2011 All Rights Reserved
  • 27. Lesson # 5 Doctored WBS - WYGWYA 27 3% 4% 91% 2% 700 649 600 Standard SPI 500 Goal 1.0 Frequency 400 Risk-Adjusted 300 SPI 265 200 100 37 40 3 0 1 0 0 3 5 8 14 13 4 0 3 2 1 2 1 1 0 0.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0 1.0 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9 2.0 >1000 Data Points; > 40 Projects SPI WYGWYA .. What You Get is Whatever You Ask 12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal 11 November, 15th & 16th 2011 © 2011 All Rights Reserved
  • 28. Lesson # 6 Higher Band Lesson 28 Track being Ahead. But be Suspicious. Too Good to be True !! Higher Band? Ahead ?? 1.10 Way Ahead 1.00 Goal Goal On Track 0.95 At Risk 0.90 Way Behind 0.80 0.70 0.60 Wk1 Wk2 Wk3 Wk4 EVIAP Project Control & EVM Conference Lisbon, Portugal November, 15th & 16th 2011 © 2011 All Rights Reserved
  • 29. Lesson # 7 Program Rollup EVM 29 Program Rollup • Practically Useless. NOT ACTIONABLE • Usually Great for Boardroom Color Management Project Level Analysis, Ownership & Accountability is Crucial Project AND / OR Program / Portfolio SPI / CPI Structure Structure Single SPI-Rollup WBS SPI-1 SPI-2 SPI-3 EVIAP Project Control & EVM Conference Lisbon, Portugal November, 15th & 16th 2011 © 2011 All Rights Reserved
  • 30. Lesson # 8 Schedule / Cost Tracking is EVM Critical 30  Heavy Cost .. Enterprise Technology  Low Cost .. Project / Excel Macros  Choose whatever means ..  EVMetrics does not Care  EVM Practice Cares  Just Ensure Quality Tracking Process TRACKING FOUNDATIONAL PILLAR 12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal 11 November, 15th & 16th 2011 © 2011 All Rights Reserved
  • 31. Tracking Mandatory to Mitigate Project Schedule / Cost Obsolescence Risks Requires Tight Rope Quality Walk Any Project Plan becomes obsolete the moment finalized Unless Tracked 31
  • 32. Project Schedule / Cost Tracking: Top Challenges 32 HOW TO:  Track Without High Costs?  Maximize Team Collaboration?  Support Organizational Metrics Initiatives?  Minimize ADMIN Drudgery?  Avoid System Choke (Month End, Week End)?  Simplify Technology and Be User Friendly? 12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal 11 November, 15th & 16th 2011 © 2011 All Rights Reserved
  • 33. Market Scan: Tracking Solutions State 33  Many Options - Windows, WEB, Others. Typical Outcomes :  High Cost ($$ / ) , Hidden / Training Costs, HighTech  Gold-Plated / Over-Featured  Unproven. Yet to see evidence of effective implementation Typical Rollout Experiences ( MS Project Server , Planview) • Never-ending Mega Projects in themselves • Hardly Meet Business Expectations • Significant time wasted on chasing tool issues & diverted away from managing / resolving Core Delivery & Project Issues 12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal 11 November, 15th & 16th 2011 © 2011 All Rights Reserved
  • 34. LoE Project Tracking – EV Practice Critical 34 Estimates To Complete (ETC) - Schedule Critical Actual Effort - Cost Critical Periodic Tracking (ETC & Actual) - EV Practice Critical TOOL SUPPORT (MS Project Platform) Electronic LoE Timesheets Tool Periodic LoE Tracking Cycle Create Validate Apply 12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal 11 November, 15th & 16th 2011 © 2011 All Rights Reserved
  • 35. Tracking is EV critical 35  Logistics & How Tracked:  EVM Does NOT Care about Tracking Logistics  EVM Does Require Quality Tracking Due diligence  Tracking Solutions Cost Impact:  Heavy Cost: Enterprise Technology Solutions  Low Cost: Project Centric Solutions (MSP / Excel Macros) 12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal 11 November, 15th & 16th 2011 © 2011 All Rights Reserved
  • 36. Conclusion ( Conclusao ) 36 Priorities for Successful EVM Practice 1. Project Management (PM) Domain Ensure : Quality Planning Process Backbone Internalize : EVM into Project Control Practices 2. EVM Domain EVM Implementation / Adoption / internalized in PM HIGH PRIORITY EVM ISO Stds LOW PRIORITY. May follow after PMI releases PM ISO Stds for PM •PM Delivery Maturity & Magic is MORE Crucial •Tracking is a MUST 12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal 11 November, 15th & 16th 2011 © 2011 All Rights Reserved
  • 37. Thank You, Obrigados !! 37  Q&A  Tool DEMO  On-line now, if time permits  Off-line later, if required 12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal 11 November, 15th & 16th 2011 © 2011 All Rights Reserved