Más contenido relacionado Similar a Eviap Conference Lisbon Portugal 2011 (20) Eviap Conference Lisbon Portugal 20111. EVM Practice
Business Solutions & Lessons Learned
Mohan Kondur
BE(Honors), PGDIE (Ind Engg), MBA, PMP, PgMP
EVIAP Project Control & EVM Conference Lisbon, Portugal
November, 15th & 16th 2011 © 2011 All Rights Reserved
2. EVM Practice - AGENDA
Business Solutions & Lessons Learned
2
Introduction
45 Min
Approach
Lessons Learned
Tool Artifacts
Q&A
15
Min Demo
12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal
11 November, 15th & 16th 2011 © 2011 All Rights Reserved
3. Who is Mohan Kondur- BS, MS, MBA, PMP, PgMP
3
• Program Manager (Delivery , EPMO )
• EVM Customer &
• NOT an EVM Insider
Diverse Industry Sector Engagements
Health Sector : United Health Group, Detroit Medical Center, BCBSM
Auto / Manufacturing Sector: GM, Ford, Chrysler ,Delphi, GE, HMT (India)
Finance / Banking Sector: Ford Credit, Comerica Bank , Allay Bank ( former GMAC)
35+ years in the field
Program /Project Management, Business Management & Marketing, Industrial Engineering
EVM Publication PMI CPM’s Quarterly News Letter “Measurable News” Summer 07
http://www.pmi-cpm.org/members/library/KondurFINAL.pdf
12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal
11 November, 15th & 16th 2011 © 2011 All Rights Reserved
4. Presentation Objective ( Share Lessons Learned / Best Practices)
Share
Lessons Learned
EVM Practice Guidelines
Model Enhancements (Thought Starters)
Earned Schedule (Emerging Practice)
DEMO (time permitting)
Organizational Transformation
Internalize EVM into Project Management
EVM Transformation
Partir Confiança
Parar !!
4
5. Who is Prj Mgr? Executes EVM or Executed By EVM?
5
Executes?
Executed?
Key Differentiator.. EV Process Quality & Reliability
12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal
11 November, 15th & 16th 2011 © 2011 All Rights Reserved
6. Project Management Process Quality – An Imperative for EVM Practice
6
Ensure end-to-end QUALITY
Closing
Initiating
Initiating Processes
Planning Processes
Executing Processes
Monitoring &
Controlling Processes
Closing Processes
From To
Project Cradle Project Grave
12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal
11 November, 15th & 16th 2011 © 2011 All Rights Reserved
7. Hitting EV Bulls Eye
7
No Pain No Gain
SPI / CPI &
Earned Schedule
TRACKING DUE DILIGENCE
QUALITY IMPLEMENTATION
& PROCESS COMPLIANCE
Pain Killers Available
12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal
11 November, 15th & 16th 2011 © 2011 All Rights Reserved
8. SPI & CPI - 101
8
Status indicators of Schedule & Cost
Binary by Definition. Either
You are On-Track (SPI & CPI = 1.0)
Or You are NOT
Precision Metrics by Nature
Current Used to be
SPI EV / PV BCWP / BCWS
CPI EV / AC BCWP / ACWP
Common Thread (or Handicap?) - Cost-Based Model
12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal
11 November, 15th & 16th 2011 © 2011 All Rights Reserved
9. Cost Model SPI/CPI – 3 Showstopper Issues
9
Issue # 1
Financials & WBS are rarely integrated.
Budgets are usually managed:
At a Contract / Engagement Level
Rarely at a WBS Deliverable Level
Issue # 2
Billing Rates: NOT internalized in WBS. Usually
managed external to WBS
Competition Sensitive Data
Artificially Blended Rates
Issue # 3
Typical PM Behavior / Mindset
Focus on Schedule, NOT Cost
12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal
11 November, 15th & 16th 2011 © 2011 All Rights Reserved
10. Model Workaround
10
Cost Model Hours Model
1 BCWS or PV Baseline Effort Hours
2 ACWP or AC Actual Effort Hours
Determining EV
Options to
Calculate
3 BCWP or EV Earned Hours
12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal
11 November, 15th & 16th 2011 © 2011 All Rights Reserved
11. EV – Calculation – PMI Status Quo
11
Remark
Option Method EV Rule
s
= 100% of baseline if Task Completed
1 0 - 100 % Same as
= 0% of baseline for any other Status
in
= 100% of baseline if Task has Completed PMBOK
0 – 50 -100%
2 = 50% of baseline if Task has Started
(aka 50-50)
= 0% if Task has NOT Started
3 % Complete = % Work Complete * Baseline
Thought
Starters
4 ETC Forecast = Baseline – Remaining Work
All Options are Tool Supported; To Illustrate Option-4
12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal
11 November, 15th & 16th 2011 © 2011 All Rights Reserved
12. Option-4 ETC Forecast Method - Example
12
Determining Earned Value Hours
PV - Baseline Work, say
EV Critical 100
AC - Actual Work, say
CPI Critical 50
ETC - Remaining Work, say
SPI Critical 70
EVA Critical EV - Earned Value
30
= 100 - 70
Schedule Driver “What is Remaining” to Complete
12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal
11 November, 15th & 16th 2011 © 2011 All Rights Reserved
13. EV Risks Corrected Model - Thought Starter
13
EV Risks
linked to
EVA Reliability
WBS
WBS Quality SPI/CPI
WBS Quality
12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal
11 November, 15th & 16th 2011 © 2011 All Rights Reserved
14. Risks Corrected EVA = Standard EVA * WBS Quality
14
Triple
Constraint
Risks
1. Scope Risk
2. Schedule Risk 3. Cost Risk
Overall WBS Risk Quality = Average of Scope, Cost , Schedule
Let us review WBS quality index an example
12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal
11 November, 15th & 16th 2011 © 2011 All Rights Reserved
15. WBS Quality Index – EV Risks Measurement Example
%
Quality How Measured Tasks Quality
Risk Source Weight (Count # of Tasks) in WBS Score
Scope 1/3 All 10 Tasks Base-Lined 100% 33%
Schedule 1/3 Only 9 Tasks Estimated 90% 30%
Cost 1/3 Only 6 Tasks Resource-Assigned 60% 20%
Overall WBS % Quality ( = Risk) 83%15
16. Interpreting Risk Adjusted EVA
16
Standard SPI / CPI
Green SPI = 1.05 => Ahead of Schedule
Schedule Quality 90%
Scope Quality 100%
Cost Quality 60%
Risk Adjusted SPI
0.87 = 1.05 * 83%
Overall WBS Quality = 83%
Behind Schedule
Schedule is Really at Risk or
87% Confidence about an 1.05 SPI
12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal
11 November, 15th & 16th 2011 © 2011 All Rights Reserved
17. EVA Custom Tool - MS Project Add-on – Just a Mouse Click
EVA Knowledge (or Mechanics)- Least Important
PM Delivery Maturity & WBS Quality More Important
Project
Generate
SPI / CPI
Consolidate Tool
Consolidate & Rollup
Program
17
18. EVA Tool Artifacts Project SPI / CPI - Spreadsheets)
18
EVA Demo : Earned Value SPI / CPI vs. Baseline
(All Tasks ) (Hours Based) - As of 2/9/2007
Quality : Overall (83%) Scope (71%), Schedule (100%) Cost(78%)
1.40
1.20
SPI
1.00 CPI
CPI
CPI SPI
Risk SPI
0.80 Risk CPI Risk CPI
SPI CPI
Risk Risk SPI
Risk SPI
0.60
0.40
0.20
0.00
1/28/2007 2/4/2007 2/11/2007
SPI CPI Risk SPI Risk CPI
EVIAP Project Control & EVM Conference Lisbon, Portugal
November, 15th & 16th 2011 © 2011 All Rights Reserved
19. Program Roll up - EVMs (SP/CPI)
19
Consolidated Demo Project : Schedule Performance Index (SPI)
(Hours Based) - As of 4/29/2005
Component Project-3 SPI Component Project-1 SPI
1.40
1.20
1.00
0.80
0.60
0.40
0.20
0.00
02/05/05 02/12/05 02/19/05 02/26/05 03/05/05 03/12/05 03/19/05 03/26/05 04/02/05 04/09/05 04/16/05 04/23/05 04/30/05
Demo_Project 1 - ba seline d Demo_Project 2 Demo_Project 3
Program Rollup EV Status Date SPI CPI
Project - 1 08/04/06 0.92 0.78
Project - 3 08/04/06 1.15 0.99
12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal
11 November, 15th & 16th 2011 © 2011 All Rights Reserved
20. EVM Implementation Lessons Learned
20
Fortune 100 Implementation
Not Just Theory
12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal
11 November, 15th & 16th 2011 © 2011 All Rights Reserved
21. EVM Lessons Learned – Environment
21
• Multi-Year Strategic Program
• Multi-Supplier Autonomous Projects
• Program Governance Framework
• Outsourced Project Management / PMO
12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal
11 November, 15th & 16th 2011 © 2011 All Rights Reserved
22. EVM Practice - Lessons Learned
22
1. Milestone Mindset - PM & Org Culture Block
2. Project Level Ownership Lack of Ownership
3. EV Reliability - WBS Quality GIGO
4. EVM Initiative Sustenance Keep it simple
5. Doctored WBS – Evergreen WYG WYA
6. Higher Band Risks Too good to be true
7. Program / Portfolio Rollup Not Actionable
8. Schedule / Cost Tracking EV Practice Critical
12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal
11 November, 15th & 16th 2011 © 2011 All Rights Reserved
23. Lesson # 1: Milestone / Date Mindset-PM / Organizational Culture Block
23
SPI / CPI fails whenever Projects communicate only
through Milestones & Dates
Resolutions:
Ensure Deliverables-Oriented WBS
Track Level of Effort (LoE) Hours
Train, Educate & Mentor Project Managers
12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal
11 November, 15th & 16th 2011 © 2011 All Rights Reserved
24. Lesson # 2 Project Level PM Ownership & Accountability
24
PM Ownership is Crucial
Resolution:
Project PM generates & owns SPI / CPI
Resist temptation to generate EV Metrics by
central PMO or a Project Coordinator
12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal
11 November, 15th & 16th 2011 © 2011 All Rights Reserved
25. Lesson # 3 EV Reliability – WBS Quality
GIGO ( Garbage in Garbage Out)
25
Standard SPI / CPI does not
factor in WBS Quality
Mitigation Approach:
Risk-Adjusted SPI/CPI Model
12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal
11 November, 15th & 16th 2011 © 2011 All Rights Reserved
26. Lesson # 4 EVM Sustenance
26
Sustained EVM initiative requires
Continuous Accommodation &
Collaboration, especially in a
Multi-Supplier Outsourced
Projects & Stakeholders
Environment
Mitigation Approach:
Keep it Simple & be Flexible
12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal
11 November, 15th & 16th 2011 © 2011 All Rights Reserved
27. Lesson # 5 Doctored WBS - WYGWYA
27
3% 4% 91% 2%
700
649
600
Standard SPI
500
Goal 1.0
Frequency
400 Risk-Adjusted
300
SPI 265
200
100
37 40
3 0 1 0 0 3 5 8 14 13 4 0 3 2 1 2 1 1
0
0.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0 1.0 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9 2.0
>1000 Data Points; > 40 Projects SPI
WYGWYA .. What You Get is Whatever You Ask
12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal
11 November, 15th & 16th 2011 © 2011 All Rights Reserved
28. Lesson # 6 Higher Band Lesson
28
Track being Ahead. But be Suspicious. Too Good to be True !!
Higher Band? Ahead ??
1.10
Way Ahead
1.00
Goal Goal
On Track
0.95
At Risk 0.90
Way Behind
0.80
0.70
0.60
Wk1 Wk2 Wk3 Wk4
EVIAP Project Control & EVM Conference Lisbon, Portugal
November, 15th & 16th 2011 © 2011 All Rights Reserved
29. Lesson # 7 Program Rollup EVM
29
Program Rollup
• Practically Useless. NOT ACTIONABLE
• Usually Great for Boardroom Color Management
Project Level Analysis, Ownership & Accountability is Crucial
Project AND / OR Program / Portfolio
SPI / CPI
Structure Structure
Single SPI-Rollup
WBS
SPI-1 SPI-2 SPI-3
EVIAP Project Control & EVM Conference Lisbon, Portugal
November, 15th & 16th 2011 © 2011 All Rights Reserved
30. Lesson # 8 Schedule / Cost Tracking is EVM Critical
30
Heavy Cost .. Enterprise Technology
Low Cost .. Project / Excel Macros
Choose whatever means ..
EVMetrics does not Care
EVM Practice Cares
Just Ensure Quality Tracking Process
TRACKING
FOUNDATIONAL
PILLAR
12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal
11 November, 15th & 16th 2011 © 2011 All Rights Reserved
31. Tracking Mandatory to Mitigate Project Schedule / Cost Obsolescence Risks
Requires
Tight Rope
Quality Walk
Any Project Plan becomes obsolete the moment
finalized Unless Tracked
31
32. Project Schedule / Cost Tracking: Top Challenges
32
HOW TO:
Track Without High Costs?
Maximize Team Collaboration?
Support Organizational Metrics Initiatives?
Minimize ADMIN Drudgery?
Avoid System Choke (Month End, Week End)?
Simplify Technology and Be User Friendly?
12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal
11 November, 15th & 16th 2011 © 2011 All Rights Reserved
33. Market Scan: Tracking Solutions State
33
Many Options - Windows, WEB, Others. Typical Outcomes :
High Cost ($$ / ) , Hidden / Training Costs, HighTech
Gold-Plated / Over-Featured
Unproven. Yet to see evidence of effective implementation
Typical Rollout Experiences ( MS Project Server , Planview)
• Never-ending Mega Projects in themselves
• Hardly Meet Business Expectations
• Significant time wasted on chasing tool issues &
diverted away from managing / resolving Core Delivery
& Project Issues
12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal
11 November, 15th & 16th 2011 © 2011 All Rights Reserved
34. LoE Project Tracking – EV Practice Critical
34
Estimates To Complete (ETC) - Schedule Critical
Actual Effort - Cost Critical
Periodic Tracking (ETC & Actual) - EV Practice Critical
TOOL SUPPORT (MS Project Platform)
Electronic LoE Timesheets Tool Periodic LoE Tracking Cycle
Create Validate
Apply
12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal
11 November, 15th & 16th 2011 © 2011 All Rights Reserved
35. Tracking is EV critical
35
Logistics & How Tracked:
EVM Does NOT Care about Tracking Logistics
EVM Does Require Quality Tracking Due diligence
Tracking Solutions Cost Impact:
Heavy Cost: Enterprise Technology Solutions
Low Cost: Project Centric Solutions (MSP / Excel Macros)
12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal
11 November, 15th & 16th 2011 © 2011 All Rights Reserved
36. Conclusion ( Conclusao )
36
Priorities for Successful EVM Practice
1. Project Management (PM) Domain
Ensure : Quality Planning Process Backbone
Internalize : EVM into Project Control Practices
2. EVM Domain
EVM Implementation / Adoption / internalized in PM HIGH PRIORITY
EVM ISO Stds LOW PRIORITY. May follow after PMI releases PM ISO Stds for PM
•PM Delivery Maturity & Magic is MORE Crucial
•Tracking is a MUST
12/29/20 EVIAP Project Control & EVM Conference Lisbon, Portugal
11 November, 15th & 16th 2011 © 2011 All Rights Reserved
37. Thank You, Obrigados !!
37
Q&A