1. Meeting Utility Resource Needs
with Solar: The Merits of the Aurora
Solar Project
Nathan Franzen | Geronimo Energy, Director of Solar
Lindsey Hemly | Fredrikson & Byron, Legal Counsel
March 19, 2014
4. Pg. 4
The Impact of Window Energy Efficiency
and How to Make Smart Choices
Thursday, April 10th
11:00 – 12:00 CST
Window retrofit technologies applicable in Minnesota’s two
climate zones as a way for building owners to save money.
Target Audience
•Building managers and facility professionals
•Utility commercial program managers
•Commercial and residential building envelope contractors
•Window and window film manufacturers/installers
•Building scientists and design professionals
Gustav Brandstrom
Project Engineer, CEE
5. Pg. 5
Presenters & Overview
Nathan Franzen
Director of Solar
Lindsey Hemly
Legal counsel
Presentation Outline
•Geronimo background
•Overview of project site, capacity, and innovations
•Benefits of this project over other resource options
•Replicability of project model
6. Geronimo Energy
• 4th
largest wind energy developer in
the U.S.A.
• Headquartered in Minneapolis, MN
• Decades of expertise, on-the-
ground experience
• Over 1,300 MW set for construction
2014-2016
• Ground-mount, rooftop, utility and
commercial scale solar offerings
• Geronimo has a strategic
partnership with Enel Green Power
6March 19, 2014 www.geronimoenergy.com
7. Project Specifications
•Operational Capacity: 100 MW
•Location: 16 Minnesota counties
•Construction Timeline: 2015 - 2016, or 4-9
months for each site
•Number of Sites: ~25 (primary and alternate)
•Project Cost: ~$250 million
•Local Tax Revenue: up to $240,000 annually*
•Expected COD: December 1, 2016
7March 19, 2014 www.geronimoenergy.com
8. Project Details
•100 megawatt (MW) AC distributed solar resource
•Utilizes solar arrays from 2 - 10 MW across Xcel’s
service territory
•Interconnects to multiple Xcel Energy distributed
substations in MN
•Provides energy and MISO accredited capacity to
Xcel and its customers
• The Aurora Solar Project will provide a cost
effective alternative to thermal generation.
8March 19, 2014 www.geronimoenergy.com
9. Unique design delivers many benefits:
•71% MISO accredited capacity
–Helps utilities meet reliability requirements
–100 MW AC = 71 MW of accredited capacity
•Distribution delivery = Reduction in line loss
(4-5%)
•Elimination of transmission costs
–Increases overall grid capacity
9March 19, 2014 www.geronimoenergy.com
10. Unique design delivers many benefits:
•Geographic diversification of generation assets
–No point source failure (think polar vortex)
•Cost
–Fixed price, no fuel cost uncertainty
•Meets solar standards
10March 19, 2014 www.geronimoenergy.com
11. How Did We Get Here?
• PUC found that Xcel had a need
of up to 500 MW by 2019
• Need was defined as “peaking or
intermediate” capacity
• Xcel wanted to propose its own
resources to fill the need
• With Xcel participation, the PUC
evaluates and selects the best
resource(s)
11March 19, 2014 www.geronimoenergy.com
12. What Was Proposed?
Xcel: 3 208 MW
Combustion Turbines
(CTs)
Invenergy: 3 160 MW CTs
Calpine: 345 MW
expansion of Mankato
Combined Cycle (CC)
GRE: 200 MW short term
capacity credits
Geronimo: Aurora SolarMarch 19, 2014 www.geronimoenergy.com 12
13. ALJ Lipman’s Recommendation:
• Xcel’s actual need is uncertain
• Aurora is most economical option
– Least cost option based on Strategist modeling
– Lowest Levelized Cost of Energy (LCOE)
• Scalability
– Solar modular design and short lead time is more suited in a
situation where the need is rapidly changing.
13March 19, 2014 www.geronimoenergy.com
14. ALJ Lipman’s Recommendation:
• Renewable Preference Warranted
• Gas proposals not fully vetted.
– Issues with non-firm gas, unresolved interconnections etc.
– Gas bidders did not offer “fixed price” leaving rate payers exposed.
• Aurora will help meet numerous state policy goals,
including the solar standard
• If the PUC finds additional need, choose GRE
14March 19, 2014 www.geronimoenergy.com
15. ALJ Lipman Determines Aurora
Solar Is Most Economical Option
"Since 1991, Minnesota has had a statutory preference
in favor of renewable energy sources. Yet, that
preference is overridden when the nonrenewable
source has a lower total cost. Notwithstanding the
statutory preference, it seemed that nonrenewable
energy sources always won the head-to-head cost
comparisons. Not anymore." – ALJ Lipman
15March 19, 2014 www.geronimoenergy.com
16. Next Steps
• Xcel and DOC disagree with ALJ report
• Xcel recommends Black Dog + Calpine and
Invenergy
• PUC can accept, reject or modify ALJ
recommendation
• Oral Argument 3/25, Deliberations 3/27
March 19, 2014 www.geronimoenergy.com 16
17. In Summary
Competitive Resource Acquisition
Process
•Pros:
– Transparent process
– Allows side by side comparison of
competing proposals
– Eliminates Utility bias towards rate based
projects
• Con’s
– Expensive, but could be improved upon
•Next Steps
17March 19, 2014 www.geronimoenergy.com
We are the #4 ranked wind project developer in North America, according to Bloomberg New Energy Finance's report, "H2 2013 North America Wind Market Outlook".
For reference:
Geronimo has a strategic partnership with Enel Green Power (EGP):
2nd leading generator of renewable energy in the world
700+ operating plants globally with 7,000+ MW of capacity
2012 revenue = ~$2.7 billion
EBIDTA of ~$2 billion
Market capitalization of ~$8 billion
A majority-owned subsidiary of Enel S.p.A.
Second largest utility in Europe
Investment grade credit rating
A key point of the Competitive Resource Acquisition Process was intended to solicit offers for Capacity – not energy. Specifically, Xcel needed peaking capacity, but not a lot of energy.
Capacity requirements are managed by MISO. Essentially, MISO monitors each utilities peak load, and requires each utility to serve that load + a buffer of approximately 15%. Each generating unit, whether it be coal, gas, solar or wind – has an accredited capacity. That is to say the statistical reliability of a particular unit to be available during peak periods. Wind is accredited for 13% of its nameplate whereas gas peaker is typically over 90%. Solar – falls in between those two categories as it reliable delivers power during the peak periods. For MISO, that is the hours of 1-3pm EST during the months of June, July and August.
We designed Aurora to maximize its accredited capacity by increasing the DC to AC ratio and by utilizing a linear tracker. Whereas, typical solar is in the 50-65% accredited.
Note: reduced needs
Will need to populate slide after ppt is complete and add visuals.