LiDAR – BIM
Exceeding our Clients Needs


Tina Murphy, P.E.
February 9, 2010
Agenda

•   Motivation
•   Adopting BIM
•   Pilot Project
•   Future Value of BIM
Motivation

              Municipal Client’s Problem
                                                        Demand on
     Regulatory time line in which to comply            Capacity




   Time Required to complete traditional Design Bid Build process




 Permitting       Engineering         Bid      Construction and
                                                re-engineering
Motivation

              Municipal Client’s Solution
                                                     Demand on
     Regulatory time line in which to comply         Capacity


  Time Required to complete Design
             Build process


                                  60% Plans break ground

Permitting             Engineering

                 Construction and re-engineering
Motivation

                Municipal Client’s Solution
Municipalities are looking to Design Build relationships to meet their
Regulatory requirements
What does Design Build give our client?
   • Single point accountability
   • Time Savings                             Scope
   • Costs Savings

Design Build costs our client in the
form of trade-off among scope,
schedule, and quality.               Schedule        Costs
Adopting BIM

                       Our Solution
BIM is our foundation for Virtual
    Design and Construction (VDC)          Scope
What does VDC give our client?
It gives….
     • Single point accountability
     • Increased time Savings
     • Increased cost Savings      Schedule      Costs
     • Minimized the trade-off
        among scope, schedule, and
        quality (change orders)
     • Useable final product
Pilot Project

• Pilot project was the rehabilitation of a
  32 MGD Water Treatment Plant
  constructed in 1940s
  – Most of the structures and equipment are still original
  – Approximately 80 projects totaling a construction
    estimate of $70 million

• Pilot completed in summer 2009
• Full company roll out end of 2010
Pilot Project - Expectations

•   Revit MEP = BIM = More Software
        ©


•   Insert LiDAR into Revit
                        ©


•   Complete virtual model
•   Easily document the process
•   Be able to calculate Return on
    Investment (ROI)
Pilot Project - The Starting Point


• The initial design effort began with as-built
  plans and site investigations

  – Construction
    plans from the
    1940s
  – Site photos
Pilot Project - Data Acquisition
 using LiDAR
• LiDAR was employed to capture the
  intricate network of pipes and mechanical
  equipment
Pilot Project - 3D Modeling with
Revit ©



• The building structure was modeled in Revit
  MEP from 1940s construction plans
      ©


• The Revit model was used as a base for
           ©


  the mechanical model being developed from
  3D laser scanning effort
Pilot Project - Data Acquisition
 using LiDAR
• The scan data was delivered as TruView   ©


  and 3D AutoCAD files
                  ©
Pilot Project -TruView

• TruView was used to validate data in CAD
  Model
• Dimension miscellaneous data
• Replaced the printed plans
• Discovery tool
  – Modifications occurring during scan
  – Some of the columns interfered with the proposed
    construction
  – Located an access hatch to be used during construction
  – Penetrations through ceiling for conduit
Pilot Project - TruView

  Modifications occurring during scan
Pilot Project -TruView

  Located access hatch
Pilot Project - TruView

  Penetrations through ceiling for conduit
Pilot Project - The Complete As-
Built
• The 3D CAD model was then referenced
  into the Revit model
             ©
Pilot Project - deliverable

• Tying into existing equipment was done
  with greater confidence
• Traditional design deliverables were easily
  created
Pilot Project - Deliverable

• The completed Revit model was used to
                    ©


  print the 3D model
Pilot Project - Challenges

• Communication barriers
  –   Engineer misunderstanding
  –   Unrealistic client expectations
  –   Revit expert had no experience with piping
  –   Vendors are confused / not willing to give up information

• Revit MEP does not equal BIM
                  ©
Pilot Project - Challenges

• LiDAR data does not directly insert into
  Revit ©

  – Pipe runs had to be re-digitized in Revit
  – Revit MEP© would kick back error messages when we
    tried to duplicate existing conditions

• There was no easy or obvious way to
  measure ROI or soft cost savings
Pilot Project - Discoveries

• The whole process was more
  complicated than originally assumed
• Support from sub-consultant exceeded
  expectations
• Greater flexibility to work on the
  project – access to all data in and out
  of the office.
• We are confident in the measurements
  and not hoping they are right
Pilot Project - Lessons Learned

• True and accurate as-builts are not
  entirely desirable
• When communicating to new clients
  we need to show them not tell them
• Standards, details, and project work
  flow need to be recreated
• BIM adoption needs to be done slowly
  and carefully
Future value of BIM

 BIM is the foundation of Virtual Design
   and Construction
BIM is our foundation for Virtual Design and Construction (VDC)
What does VDC give our client?
   • Single point accountability
   • Increased time savings
   • Increased cost savings
   • Minimizes the trade-off among scope, schedule, and
       quality
   • Useable final product
Future value of BIM


                          3D model




          Facilities                       Cost
         Management                     Estimating


                         Virtual
                       Design and
                       Construction
           Virtual                       Schedule
          Mockups                       Integration



                           Facilities
                           Analysis

Más contenido relacionado

La actualidad más candente

BIM SHOW LIVE 14 - Story of BIM from design to use
BIM SHOW LIVE 14 - Story of BIM from design to useBIM SHOW LIVE 14 - Story of BIM from design to use
BIM SHOW LIVE 14 - Story of BIM from design to useBuiltEnvironmentUBM
 
Building information modeling BIM
Building information modeling BIMBuilding information modeling BIM
Building information modeling BIMfitsum yonas
 
BASIC TERMS IN BIM-REVIT
BASIC TERMS IN BIM-REVITBASIC TERMS IN BIM-REVIT
BASIC TERMS IN BIM-REVITnilesh masne
 
Bim level-2 information-management
Bim level-2 information-managementBim level-2 information-management
Bim level-2 information-managementIbrahem Naeem
 
5th Qatar BIM User Day, Expanding BIM into Augmented and Virtual Reality
5th Qatar BIM User Day, Expanding BIM into Augmented and Virtual Reality5th Qatar BIM User Day, Expanding BIM into Augmented and Virtual Reality
5th Qatar BIM User Day, Expanding BIM into Augmented and Virtual RealityBIM User Day
 
BIM for Interior Design
BIM for Interior DesignBIM for Interior Design
BIM for Interior DesignJeff Hong
 
Build Source-Company_Profile
Build Source-Company_ProfileBuild Source-Company_Profile
Build Source-Company_Profilebuildsource
 
VideoSurveyor (Georgia Tech)
VideoSurveyor (Georgia Tech)VideoSurveyor (Georgia Tech)
VideoSurveyor (Georgia Tech)habibfathi
 
Introduction to BIM and business case of BIM
Introduction to BIM and business case of BIMIntroduction to BIM and business case of BIM
Introduction to BIM and business case of BIMreem-yousef
 
How to Create a Rock Star BIM Execution Plan (BEP) and MPDT* (Responsibility ...
How to Create a Rock Star BIM Execution Plan (BEP) and MPDT* (Responsibility ...How to Create a Rock Star BIM Execution Plan (BEP) and MPDT* (Responsibility ...
How to Create a Rock Star BIM Execution Plan (BEP) and MPDT* (Responsibility ...Fabio Roberti
 
MOSAIC BIM- Innovative Design & Construction Solutions
MOSAIC BIM- Innovative Design & Construction SolutionsMOSAIC BIM- Innovative Design & Construction Solutions
MOSAIC BIM- Innovative Design & Construction Solutionscloudfusion
 
4th Qatar BIM User Day, Pragmatic Use of COBie As-Built BIM for FM
4th Qatar BIM User Day, Pragmatic Use of COBie As-Built BIM for FM4th Qatar BIM User Day, Pragmatic Use of COBie As-Built BIM for FM
4th Qatar BIM User Day, Pragmatic Use of COBie As-Built BIM for FMBIM User Day
 
Potted History of BIM from an MEP Perspective
Potted History of BIM from an MEP PerspectivePotted History of BIM from an MEP Perspective
Potted History of BIM from an MEP PerspectiveBe2camp Admin
 
BIM process adoption for integrated design and constuction
BIM process adoption for integrated design and constuctionBIM process adoption for integrated design and constuction
BIM process adoption for integrated design and constuctionReshma Philip
 

La actualidad más candente (20)

BIM SHOW LIVE 14 - Story of BIM from design to use
BIM SHOW LIVE 14 - Story of BIM from design to useBIM SHOW LIVE 14 - Story of BIM from design to use
BIM SHOW LIVE 14 - Story of BIM from design to use
 
Building information modeling BIM
Building information modeling BIMBuilding information modeling BIM
Building information modeling BIM
 
BASIC TERMS IN BIM-REVIT
BASIC TERMS IN BIM-REVITBASIC TERMS IN BIM-REVIT
BASIC TERMS IN BIM-REVIT
 
Bim level-2 information-management
Bim level-2 information-managementBim level-2 information-management
Bim level-2 information-management
 
5th Qatar BIM User Day, Expanding BIM into Augmented and Virtual Reality
5th Qatar BIM User Day, Expanding BIM into Augmented and Virtual Reality5th Qatar BIM User Day, Expanding BIM into Augmented and Virtual Reality
5th Qatar BIM User Day, Expanding BIM into Augmented and Virtual Reality
 
The Bim Process Explained
The Bim Process ExplainedThe Bim Process Explained
The Bim Process Explained
 
BIM for Interior Design
BIM for Interior DesignBIM for Interior Design
BIM for Interior Design
 
Build Source-Company_Profile
Build Source-Company_ProfileBuild Source-Company_Profile
Build Source-Company_Profile
 
VideoSurveyor (Georgia Tech)
VideoSurveyor (Georgia Tech)VideoSurveyor (Georgia Tech)
VideoSurveyor (Georgia Tech)
 
BIM_ME_EBrochure
BIM_ME_EBrochureBIM_ME_EBrochure
BIM_ME_EBrochure
 
Bim Facades.Final
Bim Facades.FinalBim Facades.Final
Bim Facades.Final
 
Introduction to BIM and business case of BIM
Introduction to BIM and business case of BIMIntroduction to BIM and business case of BIM
Introduction to BIM and business case of BIM
 
How to Create a Rock Star BIM Execution Plan (BEP) and MPDT* (Responsibility ...
How to Create a Rock Star BIM Execution Plan (BEP) and MPDT* (Responsibility ...How to Create a Rock Star BIM Execution Plan (BEP) and MPDT* (Responsibility ...
How to Create a Rock Star BIM Execution Plan (BEP) and MPDT* (Responsibility ...
 
MOSAIC BIM- Innovative Design & Construction Solutions
MOSAIC BIM- Innovative Design & Construction SolutionsMOSAIC BIM- Innovative Design & Construction Solutions
MOSAIC BIM- Innovative Design & Construction Solutions
 
BIM
BIMBIM
BIM
 
MelBIM 190619
MelBIM 190619MelBIM 190619
MelBIM 190619
 
4th Qatar BIM User Day, Pragmatic Use of COBie As-Built BIM for FM
4th Qatar BIM User Day, Pragmatic Use of COBie As-Built BIM for FM4th Qatar BIM User Day, Pragmatic Use of COBie As-Built BIM for FM
4th Qatar BIM User Day, Pragmatic Use of COBie As-Built BIM for FM
 
Potted History of BIM from an MEP Perspective
Potted History of BIM from an MEP PerspectivePotted History of BIM from an MEP Perspective
Potted History of BIM from an MEP Perspective
 
BIM process adoption for integrated design and constuction
BIM process adoption for integrated design and constuctionBIM process adoption for integrated design and constuction
BIM process adoption for integrated design and constuction
 
Virtual Design and Construction
Virtual Design and ConstructionVirtual Design and Construction
Virtual Design and Construction
 

Similar a Spar2010murphy

Use of BIM in planning and construction and implementation in real project
Use of BIM in planning and construction and implementation in real projectUse of BIM in planning and construction and implementation in real project
Use of BIM in planning and construction and implementation in real projectMANNU KUMAR
 
NW BIM 2018 3 Mabey
NW BIM 2018 3 MabeyNW BIM 2018 3 Mabey
NW BIM 2018 3 MabeyDavid Owens
 
BIM Bringing A Real Change in Construction
BIM Bringing A Real Change in ConstructionBIM Bringing A Real Change in Construction
BIM Bringing A Real Change in ConstructionSukh Singh, MBA
 
COMIT Community Day Winter 2018 - Mabey Hire's Presentation
COMIT Community Day Winter 2018 - Mabey Hire's Presentation COMIT Community Day Winter 2018 - Mabey Hire's Presentation
COMIT Community Day Winter 2018 - Mabey Hire's Presentation Comit Projects Ltd
 
BIM- Park in California
BIM- Park in CaliforniaBIM- Park in California
BIM- Park in CaliforniaGaurav Kumar
 
BIM Engineering US., L.L.C. - VDC/BIM Services in US
BIM Engineering US., L.L.C. - VDC/BIM Services in USBIM Engineering US., L.L.C. - VDC/BIM Services in US
BIM Engineering US., L.L.C. - VDC/BIM Services in USBIM Engineering LLC U.S.
 
Trishul Presentation 2012
Trishul Presentation 2012Trishul Presentation 2012
Trishul Presentation 2012yogeshtrishul
 
Aec bim presentation
Aec bim presentationAec bim presentation
Aec bim presentationAnkur Sardana
 
CAD and BIM Outsourcing Services
CAD and BIM Outsourcing ServicesCAD and BIM Outsourcing Services
CAD and BIM Outsourcing Servicestheaecassociates1
 
Revit and Building Information Modeling (BIM) Presentation
Revit and Building Information Modeling (BIM) PresentationRevit and Building Information Modeling (BIM) Presentation
Revit and Building Information Modeling (BIM) Presentationryanabarton
 
BIM Process & BIM Pilot Project
BIM Process & BIM Pilot ProjectBIM Process & BIM Pilot Project
BIM Process & BIM Pilot ProjectNguyen Manh Tuan
 
PMIGLC CQM Discussion Panel on BIM4CQM-Haitham Sarsam
PMIGLC CQM Discussion Panel on BIM4CQM-Haitham SarsamPMIGLC CQM Discussion Panel on BIM4CQM-Haitham Sarsam
PMIGLC CQM Discussion Panel on BIM4CQM-Haitham SarsamHani
 
Barriers to bim implementation in gcc
Barriers to bim implementation in gccBarriers to bim implementation in gcc
Barriers to bim implementation in gccHamzeh Nawar, MCIOB
 

Similar a Spar2010murphy (20)

Use of BIM in planning and construction and implementation in real project
Use of BIM in planning and construction and implementation in real projectUse of BIM in planning and construction and implementation in real project
Use of BIM in planning and construction and implementation in real project
 
NW BIM 2018 3 Mabey
NW BIM 2018 3 MabeyNW BIM 2018 3 Mabey
NW BIM 2018 3 Mabey
 
atb-brochure.pdf
atb-brochure.pdfatb-brochure.pdf
atb-brochure.pdf
 
GTB-brochure.pdf
GTB-brochure.pdfGTB-brochure.pdf
GTB-brochure.pdf
 
BIM Bringing A Real Change in Construction
BIM Bringing A Real Change in ConstructionBIM Bringing A Real Change in Construction
BIM Bringing A Real Change in Construction
 
Innovation in practice presentation 10 06-15
Innovation in practice presentation 10 06-15Innovation in practice presentation 10 06-15
Innovation in practice presentation 10 06-15
 
COMIT Community Day Winter 2018 - Mabey Hire's Presentation
COMIT Community Day Winter 2018 - Mabey Hire's Presentation COMIT Community Day Winter 2018 - Mabey Hire's Presentation
COMIT Community Day Winter 2018 - Mabey Hire's Presentation
 
Nathan Hildebrandt
Nathan HildebrandtNathan Hildebrandt
Nathan Hildebrandt
 
BIM- Park in California
BIM- Park in CaliforniaBIM- Park in California
BIM- Park in California
 
Make BIM work for you
Make BIM work for youMake BIM work for you
Make BIM work for you
 
BIM Engineering US., L.L.C. - VDC/BIM Services in US
BIM Engineering US., L.L.C. - VDC/BIM Services in USBIM Engineering US., L.L.C. - VDC/BIM Services in US
BIM Engineering US., L.L.C. - VDC/BIM Services in US
 
Alastair Gardner: BIM Overview
Alastair Gardner: BIM OverviewAlastair Gardner: BIM Overview
Alastair Gardner: BIM Overview
 
Trishul Presentation 2012
Trishul Presentation 2012Trishul Presentation 2012
Trishul Presentation 2012
 
Aec bim presentation
Aec bim presentationAec bim presentation
Aec bim presentation
 
CAD and BIM Outsourcing Services
CAD and BIM Outsourcing ServicesCAD and BIM Outsourcing Services
CAD and BIM Outsourcing Services
 
Building Information Modeling
Building Information ModelingBuilding Information Modeling
Building Information Modeling
 
Revit and Building Information Modeling (BIM) Presentation
Revit and Building Information Modeling (BIM) PresentationRevit and Building Information Modeling (BIM) Presentation
Revit and Building Information Modeling (BIM) Presentation
 
BIM Process & BIM Pilot Project
BIM Process & BIM Pilot ProjectBIM Process & BIM Pilot Project
BIM Process & BIM Pilot Project
 
PMIGLC CQM Discussion Panel on BIM4CQM-Haitham Sarsam
PMIGLC CQM Discussion Panel on BIM4CQM-Haitham SarsamPMIGLC CQM Discussion Panel on BIM4CQM-Haitham Sarsam
PMIGLC CQM Discussion Panel on BIM4CQM-Haitham Sarsam
 
Barriers to bim implementation in gcc
Barriers to bim implementation in gccBarriers to bim implementation in gcc
Barriers to bim implementation in gcc
 

Spar2010murphy

  • 1. LiDAR – BIM Exceeding our Clients Needs Tina Murphy, P.E. February 9, 2010
  • 2. Agenda • Motivation • Adopting BIM • Pilot Project • Future Value of BIM
  • 3. Motivation Municipal Client’s Problem Demand on Regulatory time line in which to comply Capacity Time Required to complete traditional Design Bid Build process Permitting Engineering Bid Construction and re-engineering
  • 4. Motivation Municipal Client’s Solution Demand on Regulatory time line in which to comply Capacity Time Required to complete Design Build process 60% Plans break ground Permitting Engineering Construction and re-engineering
  • 5. Motivation Municipal Client’s Solution Municipalities are looking to Design Build relationships to meet their Regulatory requirements What does Design Build give our client? • Single point accountability • Time Savings Scope • Costs Savings Design Build costs our client in the form of trade-off among scope, schedule, and quality. Schedule Costs
  • 6. Adopting BIM Our Solution BIM is our foundation for Virtual Design and Construction (VDC) Scope What does VDC give our client? It gives…. • Single point accountability • Increased time Savings • Increased cost Savings Schedule Costs • Minimized the trade-off among scope, schedule, and quality (change orders) • Useable final product
  • 7. Pilot Project • Pilot project was the rehabilitation of a 32 MGD Water Treatment Plant constructed in 1940s – Most of the structures and equipment are still original – Approximately 80 projects totaling a construction estimate of $70 million • Pilot completed in summer 2009 • Full company roll out end of 2010
  • 8. Pilot Project - Expectations • Revit MEP = BIM = More Software © • Insert LiDAR into Revit © • Complete virtual model • Easily document the process • Be able to calculate Return on Investment (ROI)
  • 9. Pilot Project - The Starting Point • The initial design effort began with as-built plans and site investigations – Construction plans from the 1940s – Site photos
  • 10. Pilot Project - Data Acquisition using LiDAR • LiDAR was employed to capture the intricate network of pipes and mechanical equipment
  • 11. Pilot Project - 3D Modeling with Revit © • The building structure was modeled in Revit MEP from 1940s construction plans © • The Revit model was used as a base for © the mechanical model being developed from 3D laser scanning effort
  • 12. Pilot Project - Data Acquisition using LiDAR • The scan data was delivered as TruView © and 3D AutoCAD files ©
  • 13. Pilot Project -TruView • TruView was used to validate data in CAD Model • Dimension miscellaneous data • Replaced the printed plans • Discovery tool – Modifications occurring during scan – Some of the columns interfered with the proposed construction – Located an access hatch to be used during construction – Penetrations through ceiling for conduit
  • 14. Pilot Project - TruView Modifications occurring during scan
  • 15. Pilot Project -TruView Located access hatch
  • 16. Pilot Project - TruView Penetrations through ceiling for conduit
  • 17. Pilot Project - The Complete As- Built • The 3D CAD model was then referenced into the Revit model ©
  • 18. Pilot Project - deliverable • Tying into existing equipment was done with greater confidence • Traditional design deliverables were easily created
  • 19. Pilot Project - Deliverable • The completed Revit model was used to © print the 3D model
  • 20. Pilot Project - Challenges • Communication barriers – Engineer misunderstanding – Unrealistic client expectations – Revit expert had no experience with piping – Vendors are confused / not willing to give up information • Revit MEP does not equal BIM ©
  • 21. Pilot Project - Challenges • LiDAR data does not directly insert into Revit © – Pipe runs had to be re-digitized in Revit – Revit MEP© would kick back error messages when we tried to duplicate existing conditions • There was no easy or obvious way to measure ROI or soft cost savings
  • 22. Pilot Project - Discoveries • The whole process was more complicated than originally assumed • Support from sub-consultant exceeded expectations • Greater flexibility to work on the project – access to all data in and out of the office. • We are confident in the measurements and not hoping they are right
  • 23. Pilot Project - Lessons Learned • True and accurate as-builts are not entirely desirable • When communicating to new clients we need to show them not tell them • Standards, details, and project work flow need to be recreated • BIM adoption needs to be done slowly and carefully
  • 24. Future value of BIM BIM is the foundation of Virtual Design and Construction BIM is our foundation for Virtual Design and Construction (VDC) What does VDC give our client? • Single point accountability • Increased time savings • Increased cost savings • Minimizes the trade-off among scope, schedule, and quality • Useable final product
  • 25. Future value of BIM 3D model Facilities Cost Management Estimating Virtual Design and Construction Virtual Schedule Mockups Integration Facilities Analysis