Kick-off meeting Insulated Cable Power
1. KICK OF MEETING
NCDT PROJECT
Presentation title | Prysmian Group | Date 1
2. KOM FOR SUPPLY ELECTRICAL
CABLES
Project Name : EPCC New Condensate & Diesel Tanks
Organization Structure Indonesia | Prysmian Group | March 2014 2
Project
Project Location : Tangguh LNG – Papua Barat
Project Owner : BP Berau
EPC Contractor : PT Wijaya Karya (Persero) Tbk
Sub-Contractor : PT Prysmian Cables indonesia
Scope of Works : Supply Electrical Cables
LOI from WIKA : TP.01.01/U.DEP.IP.NCDT-TGH.
2239/III/2014
DATE: 05 MAY 2014
MENARA BANK DANAMON 21ST FLOOR
4. Organization Structure Indonesia | Prysmian Group | March 2014 4
No
General Requirement
Desc.
Requirements
1 Item Power Cable Control Cable Earthing Cable
2 Description Copper Conductor, PVC
Insulated, Armour Steel
Tape, Jacekting PVC Flame
Retardant Cat.C, Rated
voltage 0.6/ 1 kV
Copper Conductor, PVC Insulated,
Armour Steel Tape, Jacekting PVC
Flame Retardant Cat.C, Rated voltage
0.6/ 1 kV
Copper Conductor, PVC Insulated,
0.6/ 1 kV
3 Quantity 11 items 1 items 3 items
4 Operating
Conditions
Underground cable.
Conductor operating
temperature, max. 70 deg
C
Underground cable. Conductor
operating temperature, max. 70 deg
C
Indoor. Conductor operating
temperature, max. 70 deg C
5 Electrical
Characteristics
See Technical Data See Technical Data See Technical Data
6 Deliver to DDP WIKA Warehouse
Jakarta
DDP WIKA Warehouse Jakarta DDP WIKA Warehouse Jakarta
7 COO Prysmian Cables Indonesia Prysmian Cables Indonesia Prysmian Cables Indonesia
5. Project Schedules : Electrical Cable
No Description Dates of Works Remarks
1 LOI/PO 15 April 2014
2 Contract Release TBA by WIKA
3 Submission of
Organization Structure Indonesia | Prysmian Group | March 2014 5
Key documents
Pre KOM (05 May 2014) Drawing, Datasheet,
ITP
4 Engineering
Approval
Pre KOM (05 May 2014) If the approval is late,
the completion
delivery will delayed
5 Fabrication Start 07 May 2014 (After Approval TD
and Drum Schedule)
6 Fabrication Finish 08 Aug 2014
7 Inspection / FAT 11 Aug 2014
8 Packing 12 Aug 2014
9 Ex Work Factory 12 Aug 2014 Prysmian, Cikampek
10 DDP 13 Aug 2014
6. Organization Structure Indonesia | Prysmian Group | March 2014 6
Supporting Document
1. Drawing and Technical Data
2. ITP
3. Local Content
4. Calibration Measurement