The Gantt Chart
The Theory of Henry
Laurence Gantt
The Purpose of a Gantt Chart:
• To illustrate the relationship between project
activities & time.
• To show the multiple project activities on one chart
• To provide a simple & easy to understand
representation of project scheduling
Example of a simple Gantt Chart
 You will see that a Gantt Chart is basically a Bar Chart.
Representing project activities against time.
Creating a Gantt Chart:
There are two methods to creating a Gantt Chart (Maylor, 2005).
1. Using a Forward Schedule: starting with the list of activities
and a given start date (6th Sept in previous example) follow them
forwards in time until you hit given deadline.
2. Using a Backward Schedule: look at the deadline, from that
date work in the logical list of activities.
Both of these methods allow you to ensure that all necessary
activities can possibly be completed within the given project
time frame.
Steps to Creating a Gantt Chart:
1. Determine Project start date and deadline.
2. Gather all information surrounding the list of activities within
a project – the Work Breakdown Structure may be useful for this.
3. Determine how long each activity will take
4. Evaluate what activities are dependant on others
5. Create Graph shell including the timeline and list of activities.
6. Using either Forward Scheduling or Backward Scheduling,
Begin to add bars ensuring to include dependencies and the full
duration for each activity.
Example:
Consider the following:
Activity Duration Dependant On
1. Read Literature 21 days N/A
2. Conduct Literature Review 14 days 1
3. Arrange Client Visits 7 days N/A
4. Prepare Surveys 5 days 1 and 3
5. Conduct Surveys 14 days 4
6. Analyse Surveys 10 days 5
7. Write Up 30 days 1,2,3,4,5 and 6
Project Start Date = 1st September
Deadline = 20th Decemeber
• Step 5 - From the previous slide, steps 1-4 are
already complete. We now need to create a
‘Graph Shell’.
• Step 6 – have a go at using either Forward
Scheduling or Backward Scheduling to
populate the graph.
The Finished Product:
The Advantages:
• A useful tool for displaying time-based
information within a project.
• Very simple to create
• They provide a useful overview of project
activities, a good starting point for project
planning.
• The charts are widely used and understood.
• There exists several PC software packages that
allow you to build Gantt Charts.
The Limitations:
• The Gantt Chart does not explain the
reasoning behind the chosen duration of each
activity. (Maylor, 2001)
• The Gantt Chart is very difficult to update
when changes to the project plan take place.
This makes it time consuming and results in
long-term planning being very difficult.
(Goldratt, 1997)
• Gantt Charts encourage a one-step approach to
planning – this prevents flexibility in project planning.
• Modern day Gantt Charts, using PC software, can look
very professional without actually having meaning,
preventing project teams from challenging their
content. This can lead to difficulties later in the
project. (Maylor, 2001)
• As Gantt Charts are difficult to update manually, they
can often become obsolete.
• The charts do not consider project costs or resources.
Alternatives
• PERT/GERT
• Work Breakdown Structure
• Critical Path Method
• Resource Levelling
• Many Others!
Program Evaluation and Review
Technique (PERT):
• Also a very traditional project planning
technique
• PERT shows the list of activities within a
project, their duration and the relationship
between them
• PERT is a complex process however it can help
to deliver a well defined project plan.
A Basic PERT Diagram:
Graphical Evaluation and Review
Technique (GERT):
• Similar to PERT, however allows for looping,
branching and the display of multiple project
results.
• GERT can show possibilities if a section of a
project were to fail.
• Further GERT reading = Meredith and Mantel
Further Reading:

Más contenido relacionado

La actualidad más candente

The Gantt Chart
The Gantt ChartThe Gantt Chart
The Gantt Chart
Nicola2903
 

La actualidad más candente (20)

GANTT CHARTS.pptx
GANTT CHARTS.pptxGANTT CHARTS.pptx
GANTT CHARTS.pptx
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project scheduling
 
Chap 6.3 Sequence Activity
Chap 6.3 Sequence ActivityChap 6.3 Sequence Activity
Chap 6.3 Sequence Activity
 
PROJECT SCHEDULING
PROJECT SCHEDULINGPROJECT SCHEDULING
PROJECT SCHEDULING
 
Gantt Chart Description
Gantt Chart DescriptionGantt Chart Description
Gantt Chart Description
 
Project Management PERT and CPM
Project Management PERT and CPMProject Management PERT and CPM
Project Management PERT and CPM
 
Gantt chart
Gantt chartGantt chart
Gantt chart
 
Project Management Steps
Project Management StepsProject Management Steps
Project Management Steps
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
Project Implementation.pptx
Project Implementation.pptxProject Implementation.pptx
Project Implementation.pptx
 
Building a-project-schedule
Building a-project-scheduleBuilding a-project-schedule
Building a-project-schedule
 
Waterfall vs Agile : A Beginner's Guide in Project Management
Waterfall vs Agile : A Beginner's Guide in Project ManagementWaterfall vs Agile : A Beginner's Guide in Project Management
Waterfall vs Agile : A Beginner's Guide in Project Management
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
 
Project Duration Estimation
Project Duration EstimationProject Duration Estimation
Project Duration Estimation
 
The Gantt Chart
The Gantt ChartThe Gantt Chart
The Gantt Chart
 
Project Planning Scheduling
Project Planning SchedulingProject Planning Scheduling
Project Planning Scheduling
 
Project Closing
Project ClosingProject Closing
Project Closing
 
Ms Project Workshop
Ms Project WorkshopMs Project Workshop
Ms Project Workshop
 
Gantt Charts.ppt
Gantt Charts.pptGantt Charts.ppt
Gantt Charts.ppt
 
Introduce Project Management
Introduce Project ManagementIntroduce Project Management
Introduce Project Management
 

Similar a Gantt chart discuss 2

Project control tools by Samuel obino mokaya
Project control tools by Samuel obino mokayaProject control tools by Samuel obino mokaya
Project control tools by Samuel obino mokaya
Discover JKUAT
 
Time Management Power Point Presentation
Time Management Power Point PresentationTime Management Power Point Presentation
Time Management Power Point Presentation
klharms
 

Similar a Gantt chart discuss 2 (20)

Unit 3 Project scheduling - gantt chart.pptx
Unit 3 Project scheduling - gantt chart.pptxUnit 3 Project scheduling - gantt chart.pptx
Unit 3 Project scheduling - gantt chart.pptx
 
programmed evaluation and review technique,
programmed evaluation and review technique,programmed evaluation and review technique,
programmed evaluation and review technique,
 
Pert and gantt chart
Pert and gantt chartPert and gantt chart
Pert and gantt chart
 
project management -04.ppt
project management -04.pptproject management -04.ppt
project management -04.ppt
 
Unit II.pptx
Unit II.pptxUnit II.pptx
Unit II.pptx
 
PERT Ghant chart and bench marking with application to nursing
PERT Ghant chart and bench marking with application to nursingPERT Ghant chart and bench marking with application to nursing
PERT Ghant chart and bench marking with application to nursing
 
Project control tools by Samuel obino mokaya
Project control tools by Samuel obino mokayaProject control tools by Samuel obino mokaya
Project control tools by Samuel obino mokaya
 
CTM - 02 - Construction Project Planning - Copy.pptx
CTM - 02 - Construction Project Planning - Copy.pptxCTM - 02 - Construction Project Planning - Copy.pptx
CTM - 02 - Construction Project Planning - Copy.pptx
 
CTM - 02 - Construction Project Planning.pptx
CTM - 02 - Construction Project Planning.pptxCTM - 02 - Construction Project Planning.pptx
CTM - 02 - Construction Project Planning.pptx
 
ctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdf
ctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdfctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdf
ctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdf
 
Chapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapterChapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapter
 
PMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptxPMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptx
 
WBS Gantt chart and project management for Jira users
WBS Gantt chart and project management for Jira usersWBS Gantt chart and project management for Jira users
WBS Gantt chart and project management for Jira users
 
-Project-Management.ppt
-Project-Management.ppt-Project-Management.ppt
-Project-Management.ppt
 
PM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptxPM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptx
 
PM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptxPM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptx
 
Time Management Power Point Presentation
Time Management Power Point PresentationTime Management Power Point Presentation
Time Management Power Point Presentation
 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Management
 
Critical Path Analysis
Critical Path AnalysisCritical Path Analysis
Critical Path Analysis
 
GANTT CHART nursing Management for Msc nursing
GANTT CHART nursing Management for Msc nursingGANTT CHART nursing Management for Msc nursing
GANTT CHART nursing Management for Msc nursing
 

Más de Makati Science High School

Más de Makati Science High School (20)

Writing a Scientific Paper
Writing a Scientific PaperWriting a Scientific Paper
Writing a Scientific Paper
 
Research Paper Rubrics 2020
Research Paper Rubrics 2020Research Paper Rubrics 2020
Research Paper Rubrics 2020
 
Statistical test discuss 5
Statistical test discuss 5Statistical test discuss 5
Statistical test discuss 5
 
Measures of variation discuss 2.1
Measures of variation discuss  2.1Measures of variation discuss  2.1
Measures of variation discuss 2.1
 
Measures of dispersion discuss 2.2
Measures of dispersion discuss 2.2Measures of dispersion discuss 2.2
Measures of dispersion discuss 2.2
 
Materials and methods discuss
Materials and methods  discussMaterials and methods  discuss
Materials and methods discuss
 
Inferential stat tests samples discuss 4
Inferential stat tests samples discuss 4Inferential stat tests samples discuss 4
Inferential stat tests samples discuss 4
 
Ds vs Is discuss 3.1
Ds vs Is discuss 3.1Ds vs Is discuss 3.1
Ds vs Is discuss 3.1
 
Descriptive inferential-discuss 1
Descriptive  inferential-discuss 1Descriptive  inferential-discuss 1
Descriptive inferential-discuss 1
 
Central tendency m,m,m 1.2
Central tendency m,m,m 1.2Central tendency m,m,m 1.2
Central tendency m,m,m 1.2
 
Central tendency discuss 2
Central tendency  discuss 2Central tendency  discuss 2
Central tendency discuss 2
 
Types of graphs and charts and their uses with examples and pics
Types of graphs and charts and their uses  with examples and picsTypes of graphs and charts and their uses  with examples and pics
Types of graphs and charts and their uses with examples and pics
 
Levels of measurement discuss
Levels of measurement   discussLevels of measurement   discuss
Levels of measurement discuss
 
Gantt chart discuss 3
Gantt chart discuss 3Gantt chart discuss 3
Gantt chart discuss 3
 
Gantt chart discuss 1
Gantt chart discuss 1Gantt chart discuss 1
Gantt chart discuss 1
 
Research Designs -9 experimental Designs
Research Designs -9 experimental DesignsResearch Designs -9 experimental Designs
Research Designs -9 experimental Designs
 
Research designs Pt 1
Research designs Pt 1Research designs Pt 1
Research designs Pt 1
 
Identifying variables
Identifying variablesIdentifying variables
Identifying variables
 
Kinds and classifications of research
Kinds and classifications of researchKinds and classifications of research
Kinds and classifications of research
 
Research Ethical Issues
Research Ethical IssuesResearch Ethical Issues
Research Ethical Issues
 

Último

Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
kauryashika82
 
Making and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfMaking and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdf
Chris Hunter
 
An Overview of Mutual Funds Bcom Project.pdf
An Overview of Mutual Funds Bcom Project.pdfAn Overview of Mutual Funds Bcom Project.pdf
An Overview of Mutual Funds Bcom Project.pdf
SanaAli374401
 
Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.
MateoGardella
 

Último (20)

Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Making and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfMaking and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdf
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..
 
Advance Mobile Application Development class 07
Advance Mobile Application Development class 07Advance Mobile Application Development class 07
Advance Mobile Application Development class 07
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
An Overview of Mutual Funds Bcom Project.pdf
An Overview of Mutual Funds Bcom Project.pdfAn Overview of Mutual Funds Bcom Project.pdf
An Overview of Mutual Funds Bcom Project.pdf
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdf
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.
 

Gantt chart discuss 2

  • 1. The Gantt Chart The Theory of Henry Laurence Gantt
  • 2. The Purpose of a Gantt Chart: • To illustrate the relationship between project activities & time. • To show the multiple project activities on one chart • To provide a simple & easy to understand representation of project scheduling
  • 3. Example of a simple Gantt Chart  You will see that a Gantt Chart is basically a Bar Chart. Representing project activities against time.
  • 4. Creating a Gantt Chart: There are two methods to creating a Gantt Chart (Maylor, 2005). 1. Using a Forward Schedule: starting with the list of activities and a given start date (6th Sept in previous example) follow them forwards in time until you hit given deadline. 2. Using a Backward Schedule: look at the deadline, from that date work in the logical list of activities. Both of these methods allow you to ensure that all necessary activities can possibly be completed within the given project time frame.
  • 5. Steps to Creating a Gantt Chart: 1. Determine Project start date and deadline. 2. Gather all information surrounding the list of activities within a project – the Work Breakdown Structure may be useful for this. 3. Determine how long each activity will take 4. Evaluate what activities are dependant on others 5. Create Graph shell including the timeline and list of activities. 6. Using either Forward Scheduling or Backward Scheduling, Begin to add bars ensuring to include dependencies and the full duration for each activity.
  • 6. Example: Consider the following: Activity Duration Dependant On 1. Read Literature 21 days N/A 2. Conduct Literature Review 14 days 1 3. Arrange Client Visits 7 days N/A 4. Prepare Surveys 5 days 1 and 3 5. Conduct Surveys 14 days 4 6. Analyse Surveys 10 days 5 7. Write Up 30 days 1,2,3,4,5 and 6 Project Start Date = 1st September Deadline = 20th Decemeber
  • 7. • Step 5 - From the previous slide, steps 1-4 are already complete. We now need to create a ‘Graph Shell’.
  • 8. • Step 6 – have a go at using either Forward Scheduling or Backward Scheduling to populate the graph. The Finished Product:
  • 9. The Advantages: • A useful tool for displaying time-based information within a project. • Very simple to create • They provide a useful overview of project activities, a good starting point for project planning. • The charts are widely used and understood. • There exists several PC software packages that allow you to build Gantt Charts.
  • 10. The Limitations: • The Gantt Chart does not explain the reasoning behind the chosen duration of each activity. (Maylor, 2001) • The Gantt Chart is very difficult to update when changes to the project plan take place. This makes it time consuming and results in long-term planning being very difficult. (Goldratt, 1997)
  • 11. • Gantt Charts encourage a one-step approach to planning – this prevents flexibility in project planning. • Modern day Gantt Charts, using PC software, can look very professional without actually having meaning, preventing project teams from challenging their content. This can lead to difficulties later in the project. (Maylor, 2001) • As Gantt Charts are difficult to update manually, they can often become obsolete. • The charts do not consider project costs or resources.
  • 12. Alternatives • PERT/GERT • Work Breakdown Structure • Critical Path Method • Resource Levelling • Many Others!
  • 13. Program Evaluation and Review Technique (PERT): • Also a very traditional project planning technique • PERT shows the list of activities within a project, their duration and the relationship between them • PERT is a complex process however it can help to deliver a well defined project plan.
  • 14. A Basic PERT Diagram:
  • 15. Graphical Evaluation and Review Technique (GERT): • Similar to PERT, however allows for looping, branching and the display of multiple project results. • GERT can show possibilities if a section of a project were to fail. • Further GERT reading = Meredith and Mantel