SlideShare una empresa de Scribd logo
1 de 48
Estimation
of
Oil & Gas
Reserves
• Reserves are those quantities of petroleum which are
anticipated to be commercially recovered from known
accumulations from a given date forward.
• All reserve estimates involve some degree of uncertainty.
• The uncertainty depends chiefly on the amount of reliable
geologic and engineering data available at the time of the
estimate and the interpretation of these data.
• The relative degree of uncertainty may be conveyed by
placing reserves into one of two principal classifications,
either proved or unproved.
• Unproved reserves are less certain to be recovered than
proved reserves and may be further sub-classified as
probable and possible reserves to denote progressively
increasing uncertainty in their recoverability.
Proven Reserves
• Proven reserves are those reserves claimed to have a
reasonable certainty (normally at least 90% confidence) of
being recoverable under existing economic and political
conditions, with existing technology. Industry specialists
refer to this as P90 i.e., having a 90% certainty of being
produced. Proven reserves are also known in the industry as
1P
• Proven reserves are further subdivided into "proven
developed" (PD) and "proven undeveloped" (PUD).
• PD reserves are reserves that can be produced with existing
wells and perforations, or from additional reservoirs where
minimal additional investment (operating expense) is
required.
• PUD reserves require additional capital investment e.g.,
drilling new wells to bring the oil to the surface.
Proven Reserves
• Proven reserves can further be categorized on the basis of
status of wells and reservoirs as developed and
Undeveloped; producing and nonproducing
Developed:
Developed reserves are expected to be recovered from existing
wells. Improved recovery reserves are considered developed only
after the necessary equipment has been installed, or when the
costs to do so are relatively minor. Developed reserves may be
subcategorized as producing or non-producing.
Producing:
– Reserves subcategorized as producing are expected to be
recovered from completion intervals which are open and
producing at the time of the estimate.
Proven Reserves
Non-producing:
Reserves subcategorized as non-producing include shut-in
and behind-pipe reserves.
Shut-in reserves are expected to be recovered from
(1)completion intervals which are open at the time of the
estimate but which have not started producing,
(2)wells which were shut-in for market conditions or
pipeline connections, or
(3)wells not capable of production for mechanical
reasons. Behind-pipe reserves are expected to be
recovered from zones in existing wells, which will
require additional completion work or future
recompletion prior to the start of production.
Proven Reserves
Undeveloped Reserves:
Undeveloped reserves are expected to be recovered:
(1) from new wells on undrilled acreage,
(2) from deepening existing wells to a different
reservoir, or
(3) where a relatively large expenditure is required to
(a) recomplete an existing well or
(b) install production or transportation facilities for
primary or improved recovery projects.
Unproven Reserves
• Unproven reserves are based on geological and/or engineering
data similar to that used in estimates of proven reserves, but
technical, contractual, or regulatory uncertainties make such
reserves being classified as unproven.
• Unproven reserves may be used internally by oil companies and
government agencies for future planning purposes but are not
routinely compiled. They are sub-classified as probable and
possible
Probable:
Probable reserves are attributed to known accumulations and
claim a 50% confidence level of recovery. Industry specialists refer
to them as P50 i.e., having a 50% certainty of being produced.
These reserves are also referred to in the industry as 2P (proven
plus probable).
Unproven Reserves
Possible:
Possible reserves are attributed to known accumulations
that have a less likely chance of being recovered than
probable reserves. This term is often used for reserves
which are claimed to have at least a 10% certainty of being
produced (P10).
Reasons for classifying reserves as possible include varying
interpretations of geology, reserves not producible at
commercial rates, uncertainty due to reserve infill (seepage
from adjacent areas) and projected reserves based on future
recovery methods. They are referred to in the industry as 3P
(proven plus probable plus possible).
Classification of Reserves
Reserves
Proven Unproven
Probable Possible
Developed Undeveloped
Producing Nonproducing
Cross section View of a Reservoir structure as suggested
from Seismic and Geological data
After Exploration well was drilled
After Delineation
Final Delineation
Estimation of Reserves
• The amount of oil in a subsurface reservoir is called
oil initial in place (OIIP)
• There are a number of different methods of calculating oil
reserves. These methods can be grouped into four general
categories:
A. volumetric,
B. material balance
C. production performance.
D. Comparative methods where comparison is made with
those of offset properties of other fields having same
geologic and other reservoir conditions.
Estimation of Reserves
• The different methods mentioned can be applied in
the following time periods
Time period % of reserves
Produced
Methods of
Estimation
Reasonable
range of error
Prior to Drilling 0 D 10-100 %
After completion 0 A & D 5-50 %
During production 1-10 % A, B & C 5-30 %
During production 10-30 % A, B & C 5-20 %
During production 30-60 % B & C 5-10 %
During production 60 & over C About 5 %
Volumetric Estimation
• Volumetric estimation is the only means available to assess
hydrocarbons in place prior to acquiring sufficient pressure
and production information.
• Volumetric methods are primarily used to evaluate the in-
place hydrocarbons in new, non-producing wells and pools
and new petroleum basins. But even after pressure and
production data exists, volumetric estimates provide a
valuable check on the estimates derived from material
balance and decline analysis methods.
• Volumetric estimation is also known as the “geologist’s
method” as it is based on cores, analysis of wireline logs,
and geological maps.
Volumetric Estimation
Volumetric estimation requires determination of following
reservoir parameters.
a)Estimation of volume of sub surface rock that contains
hydrocarbons. The volume is calculated from the thickness of
the rock containing oil or gas and the areal extent of the
accumulation.
b)Determination of a weighted average effective porosity.
c)Obtaining a reasonable water resistivity value to calculate
water saturation.
With these reservoir rock properties and utilizing the
hydrocarbon fluid properties, original oil-in-place or original
gas-in-place volumes can be calculated.
Volumetric Estimation
For OIL RESERVOIRS the oil initial in-place (OIIP) volumetric
calculation is.
•Metric:
•OIIP (m3
) = Rock Volume * Ø * (1- Sw) * 1/Bo
Where: Rock Volume (m3
) = 104
* A * h
A = Drainage area, hectares (1 ha = 104
m2
)
h = Net pay thickness, meters
Ø= Porosity, fraction of rock volume available to store
fluids
Sw = Volume fraction of porosity filled with interstitial water
Bo = Formation volume factor (m3
/m3
) (dimensionless factor for
the change in oil volume between reservoir conditions and
standard conditions at surface)
Volumetric Estimation
• Imperial:
OIIP (STB) = Rock Volume * 7,758 * Ø * (1- Sw) * 1/Bo
Where: Rock Volume (acre feet) = A * h
A = Drainage area, acres
h = Net pay thickness, feet
7,758 = Bbl per acre-feet (converts acre-feet to stock tank
barrels)
Ø = Porosity, fraction of rock volume available to store fluids
Sw = Volume fraction of porosity filled with interstitial water
Bo = Formation volume factor (Reservoir Bbl/STB)
1/Bo = Shrinkage (STB/reservoir Bbl)
Oil Recovery Factor
• The recovery factor is one of the most important, yet the
most difficult variable to estimate.
• Fluid properties such as formation volume factor, viscosity,
density, and solution gas/oil ratio all influence the recovery
factor.
• In addition, it is also a function of the reservoir drive
mechanism and the interaction between reservoir rock and
the fluids in the reservoir.
Oil Recovery Factor
•The approximate oil recovery range is tabulated
below for various driving mechanisms.
•Note that these calculations are approximate and,
therefore, oil recovery may fall outside these ranges
Estimation of Gas in place
Gas in reservoir occurred as
• Non associated gas
• Associated gas
• Solution gas.
Volumetric Estimation of Non Associated Gas
For GAS RESERVOIRS the gas initial in-place (GIIP) volumetric
calculation is:
•Metric:
GIIP (103
m3
) = Rock Volume * Ø * (1-Sw) * (Ts * Pi) /(Ps * Tf * Zi)
Where: Rock Volume (m3
) = 104
* A * h
A = Drainage area, hectares (1 ha = 104
m2
)
h = Net pay thickness, meters
Ø = Porosity, fraction of rock volume available to store fluids
Sw = Volume fraction of porosity filled with interstitial water
Ts = Base temperature, standard conditions, °Kelvin (273° + 15°C)
Ps = Base pressure, standard conditions, (1.01 kg/cm2
)
Tf = Formation temperature, °Kelvin (273° + °C at formation depth)
Pi = Initial Reservoir pressure, kg/cm2
Zi = Compressibility at Pi and Tf
Volumetric Estimation of Non Associated GAS
• Imperial:
GIIP (MMCF) = Rock Volume * 43,560 * Ø * (1-Sw) * (Ts * Pi)/
(Ps * Tf * Zi)
Where: Rock Volume (acre feet) = A * h
A = Drainage area, acres (1 acre = 43,560 sq. ft)
h = Net pay thickness, feet
Ø = Porosity, fraction of rock volume available to store fluids
Sw = Volume fraction of porosity filled with interstitial water
Ts = Base temp., standard conditions, °Rankine (460° + 60°F)
Ps = Base pressure, standard conditions, 14.65 psia
Tf = Formation temp, °Rankine (460° + °F at formation depth)
Pi = Initial Reservoir pressure, psia
Zi = Compressibility at Pi and Tf
Volumetric Estimation of Associated Gas
Associated Gas
• Gas associated with oil as gas cap is known as
associated gas.
• During oil production period this remained shut in.
• Once most of the oil is produced, gas from gas cap
is produced.
• Estimation method is same as described for Non
associated gas.
Volumetric Estimation of Solution Gas
Solution Gas
• Gas liberated from the reservoir during oil
production.
• To estimate the volume of this gas following
formula is applied.
GIIP(soln.) = N(OIIP) x GOR
Gas Recovery Factor
• Volumetric depletion of a gas reservoir with reasonable
permeability at conventional depths in a conventional area
will usually recover 70 to 90% of the gas-in-place.
• However, a reservoir’s recovery factor can be significantly
reduced by factors such as:
low permeability, low production rate, soft sediment
compaction, fines migration, excessive formation depth,
water influx, water coning and/or behind pipe cross flow,
and the position and number of producing wells.
• As an example, a 60% recovery factor might be appropriate
for a gas accumulation overlying a strong aquifer with near
perfect pressure support.
Reservoir Rock
Sand Grain
Cementing material
Interconnected
or effective
porosity
Isolated or non
effective
porosity
Calculations of Rock Volume
• The projected surface area of a hydrocarbon deposit can be
completely defined only by the drill
• Reservoir volumes can be calculated from net pay isopach
maps by planimetering to obtain rock volume (A * h).
• To calculate volumes it is necessary to find the areas between
isopach contours.
• Planimetering can be performed
by hand or computer generated.
• Given the areas between contours,
volumes can be computed using;
Trapezoidal rule, Pyramidal rule,
and/or the Peak rule for calculating
volumes
Calculations of Rock Volume
Following methods can be used to evaluate the rock volume
Trapezoidal Volume
V = h (A1+ A2/2)
Frustum of pyramid
V = h/3 (A1+A2+ A1*A2)
Net Pay
• Net pay is the part of a reservoir from which hydrocarbons
can be produced at economic rates, given a specific
production method.
• The distinction between gross and net pay is made by
applying cut-off values in the petrophysical analysis.
• Net pay cut-offs are used to identify values below which the
reservoir is effectively non-productive.
In general, the cut-off values are determined based on the
relationship between porosity, permeability, and water
saturation from core data and capillary pressure data.
Net Pay
A
B
C
D
E
F
low porosity, low permeability,
very low/ no oil saturation,
Non Pay
high porosity, high permeability,
high oil saturation,
Gross &
net pay
low porosity, low permeability,
very low or no oil saturation
Gross
pay
low porosity, low permeability,
very low or no oil saturation,
Gross
pay
high porosity, high permeability,
high oil saturation,
Gross &
net pay
high porosity, high permeability,
high water saturation,
Non pay
Gross thickness = A+B+C+D+E+F = 6 m, Gross reservoir = B+C+D+E+F = 5 m
Gross pay = B+C+D+E = 4 m , Net thickness = Net reservoir = B+E+F = 3 m
Net pay = B+E = 2 m
Porosity and water saturation
• In evaluation of porosity of individual wells, the weighted
average porosity values are computed.
• Porosity values are assigned as an average over a zone
(single well pool) or as a weighted average value over the
entire pay interval using all wells in a pool.
• If all the intervals sampled from a well are of uniform
thickness, the weighted average and the arithmetic average
are identical.
• If the intervals differ in both thickness and the values then
the two averages will be different.
• Similarly, the average thickness-weighted water saturation
using all wells in the pool is commonly assumed as the pool
average water saturation.
Weighted average Porosity
Depth (Ft) h Ø (%) Øh
3690-3691 1 20 20
3691-3693 2 23 46
3693-3694 1 21 21
3694-3697 3 26 78
Total 7 90 165
Arithmetic average Ø = 90/4 = 22.5%
Weighted average Ø = 165/7= 23.5%
    Inplace Ultimate Cumm Prod Reserve
        Gas     Gas     Gas     Gas
Field Cat Oil  Cond Sol Gas GC F GAS Oil  Cond Sol Gas GC F GAS Oil  Cond Sol Gas GC F GAS Oil  Cond Sol Gas GC F GAS
Bandamurlanka
PD   0.06    157.6  0.03    23.7 0.01      5.2  0.01    18.5
PDPB                   70.9 0.03          0.03    70.9
PB                                        
PS                                        
Bhimanapalli PB         21.8        13.1                  13.1
Endamuru PD   0.06    3214.9  0.05    2175.3 0.02      1484  0.03    691.3
Enugapalli
PD   0.01    378.9        227.3        89.7        137.7
PS         220.6                             
Gedanapalli PD 0.75        0.08                  0.07       
Mandapetta
PD 0.02 1.04    18330  0.73    12820.1  0.05    1842.4  0.68    10977.6
PB   0.3    9060.8  0.21    6394.2            0.21    6394
Mummidivaram
PD         58.7                             
PBPB                   35.2                  35.2
Penugonda PS         2364.6                             
Rangapuram
PD         240.8        144.5        7        137.4
PB         37.9        22.8                  22.8
PS         75.4                             
Table of Reserve
Oil & Gas Reserves
Oil
(MMt)
Cond.
(MMt)
SG+GCG
(MMm3
)
Free Gas
(MMm3
)
Oil +OEG
(MMt)
As on 01.04.2010
Inplace 4793.81 73.94 1277448 994668 7139.87
Ultimate 1323.26 67.22 725965.8 394915.8 25112.36
Reserves 531.55 31.87 301313.7 310181.3 1174.92
As on 01.04.2011
Inplace 4888.1 72.54 1302975.1 113158.5 7376.79
Ultimate 1337.19 66.88 746115.2 445952.9 2596.14
Reserves 523.29 30.15 303661.6 356117.1 1213.22
Material Balance
• When an oil and gas reservoir is put on production it
produces oil, gas and some time water also thereby reducing
the reservoir pressure.
• If the oil and gas bearing strata is hydro dynamically
connected with water strata or aquifer water encroaches in
to the reservoir and accordingly retarding the declining in
pressure.
• The material balance equation is derived as a volume
balance which equates the cumulative observed production,
expressed as an underground withdrawal, to the expansion
of the fluids in the reservoir resulting from finite pressure
drop
Principle of Material Conservation
Amount of fluids
present in the
reservoir initially
(st. vol)
Amount
of fluids
produced
(st. vol)
Amount of fluids
remaining in the
reservoir finally
(st. vol.)
-
The material balance equations are based on simple
mass balance of the fluids in the reservoir, and may be
formulated as
Material Balance Analysis
OIL OIL
Initial stage (1) Final stage (2)
N*Boi (N-Np)*Bo
Material Balance Analysis
Oil present
in the reservoir
initially
(st. vol.)
Oil
produced
(st. vol
Oil remaining
in the reservoir
finally
(st. vol.)
-
Equation 1: Oil material balance
N Boi = (N-Np)Bo
N = Bo*Np/Bo-Boi
Material Balance Analysis
water present
in the reservoir
initially
(st. vol.)
Water
produced
(st. vol)
water remaining
in the reservoir
finally
(st. vol.)
-
Equation 2: Water material balance
Vp1Sw1/Bw1 - Wp + Wi + We= Vp2 Sw2 /Bw2
+
Water
inj.
+
Aquifer
influx
Material Balance Equation for a Closed Gas Reservoir
• The material balance equation for a closed gas reservoir is
very simple. Applying the mass balance principle to a closed
reservoir with 100% gas, we may derive the general
eguation
• GBg1 = (G − Gp )Bg 2
• where
• G is gas initially in place,
• Gp is cumulative gas production, and
• Bg is the formation-volume-factor for gas. Since Bg is given
by the real gas law
• Bg = (constant)Z/P
• (here temperature is assumed to be constant)
Material Balance Equation for a Closed Gas Reservoir
The material balance equation may be rewritten as
G (Z1/P1) =(G-Gp) (Z2/P2)
(P2/Z2)= (1- Gp/G)(P1/Z1)
This equation represents a
straight line relationship on
a P2/Z2 vs. Gp plot.
The straight-line relationship
is very useful in estimating
the initial volume of
gas-in-place (G) from limited
production history
P/Z
Production decline Analysis
• Production decline analysis is a basic tool for forecasting
production from a reservoir once there is sufficient
production to establish a decline trend as a function of time.
• The technique is more accurate than volumetric methods
when sufficient data is available to establish a reliable trend
and is applicable to both oil and gas wells.
• Accordingly, production decline analysis is most applicable
to producing pools with well established trends.
• The rate versus time plot is commonly used to diagnose well
and reservoir performance as shown in the example plot.
• Arps (1945, 1956) developed the initial series of decline
curve equations to model well performance. The equations
were classified as exponential, hyperbolic, or harmonic,
depending on the value of the exponent
Production decline Analysis
Conclusions
•Estimation of reserves is done under conditions of uncertainty
•The principal uncertainties associated with the performance of the
overall reservoir model.
•The type of data which is most important to define the reservoir.
• Reservoir structure
• Reservoir properties
• Reservoir sand connectivity
• Impact of faults
• Relative permeability etc
• Fluid properties
• Aquifer behavior
• Well productivity (fractures, well type, condensate drop out etc.)
•The impact of each of these parameters will vary according to the
particular field.
•It is important that the company is not ignorant of the magnitude of
the contributing uncertainties, so that resources can be directed at cost
effectively reducing specific uncertainties.

Más contenido relacionado

La actualidad más candente

PETROLEUM SYSTEM FINAL
PETROLEUM SYSTEM FINALPETROLEUM SYSTEM FINAL
PETROLEUM SYSTEM FINALFarhan Aslam
 
What is the different between the net pay and resrvoir thickness
What is the different between the net pay and resrvoir thicknessWhat is the different between the net pay and resrvoir thickness
What is the different between the net pay and resrvoir thicknessStudent
 
Well Logging: 01 borehole environment
Well Logging: 01 borehole environmentWell Logging: 01 borehole environment
Well Logging: 01 borehole environmentkhaled Zidan
 
Properties of reservoir rocks
Properties of reservoir rocksProperties of reservoir rocks
Properties of reservoir rocksuos
 
Reservoir characterization
Reservoir characterizationReservoir characterization
Reservoir characterizationSirius 100
 
The reservoir (rock porosity and permeability)
The reservoir (rock porosity and permeability)The reservoir (rock porosity and permeability)
The reservoir (rock porosity and permeability)salahudintanoli
 
Introduction to Reservoir Rock & Fluid Properties
Introduction to Reservoir Rock & Fluid PropertiesIntroduction to Reservoir Rock & Fluid Properties
Introduction to Reservoir Rock & Fluid PropertiesM.T.H Group
 
Well Teste Interpretation
Well Teste InterpretationWell Teste Interpretation
Well Teste InterpretationMeg Medeiros
 
Reservoir evaluation method 101
Reservoir evaluation method 101Reservoir evaluation method 101
Reservoir evaluation method 101bachhva
 
4 1 reservoir-drive_mechanisms
4 1 reservoir-drive_mechanisms4 1 reservoir-drive_mechanisms
4 1 reservoir-drive_mechanismsAtils
 
Reservoir Modeling with Petrel
Reservoir Modeling with PetrelReservoir Modeling with Petrel
Reservoir Modeling with Petreladeeba setu
 

La actualidad más candente (20)

PETROLEUM SYSTEM FINAL
PETROLEUM SYSTEM FINALPETROLEUM SYSTEM FINAL
PETROLEUM SYSTEM FINAL
 
Basics of petroleum geology
Basics of petroleum geologyBasics of petroleum geology
Basics of petroleum geology
 
Well Log Interpretation
Well Log InterpretationWell Log Interpretation
Well Log Interpretation
 
What is the different between the net pay and resrvoir thickness
What is the different between the net pay and resrvoir thicknessWhat is the different between the net pay and resrvoir thickness
What is the different between the net pay and resrvoir thickness
 
Well Logging: 01 borehole environment
Well Logging: 01 borehole environmentWell Logging: 01 borehole environment
Well Logging: 01 borehole environment
 
Properties of reservoir rocks
Properties of reservoir rocksProperties of reservoir rocks
Properties of reservoir rocks
 
Reservoir
ReservoirReservoir
Reservoir
 
Reservoir characterization
Reservoir characterizationReservoir characterization
Reservoir characterization
 
The reservoir (rock porosity and permeability)
The reservoir (rock porosity and permeability)The reservoir (rock porosity and permeability)
The reservoir (rock porosity and permeability)
 
Reservoir rock & fluid
Reservoir rock & fluidReservoir rock & fluid
Reservoir rock & fluid
 
Reservoir Rock Properties
Reservoir Rock Properties Reservoir Rock Properties
Reservoir Rock Properties
 
Introduction to Reservoir Rock & Fluid Properties
Introduction to Reservoir Rock & Fluid PropertiesIntroduction to Reservoir Rock & Fluid Properties
Introduction to Reservoir Rock & Fluid Properties
 
Volume calculation
Volume calculationVolume calculation
Volume calculation
 
Well Teste Interpretation
Well Teste InterpretationWell Teste Interpretation
Well Teste Interpretation
 
Reservoir evaluation method 101
Reservoir evaluation method 101Reservoir evaluation method 101
Reservoir evaluation method 101
 
Well test analysis
Well test analysisWell test analysis
Well test analysis
 
4 1 reservoir-drive_mechanisms
4 1 reservoir-drive_mechanisms4 1 reservoir-drive_mechanisms
4 1 reservoir-drive_mechanisms
 
Reservoir Modeling with Petrel
Reservoir Modeling with PetrelReservoir Modeling with Petrel
Reservoir Modeling with Petrel
 
Basic Petrophysics
Basic PetrophysicsBasic Petrophysics
Basic Petrophysics
 
Drilling fluids
Drilling fluidsDrilling fluids
Drilling fluids
 

Destacado

Cairn case study
Cairn case studyCairn case study
Cairn case studySwapnil Pal
 
Basic well log interpretation
Basic well log interpretationBasic well log interpretation
Basic well log interpretationShahnawaz Mustafa
 
Formation evaluation and well log correlation
Formation evaluation and well log correlationFormation evaluation and well log correlation
Formation evaluation and well log correlationSwapnil Pal
 
Petroleum resources reserves
Petroleum resources reservesPetroleum resources reserves
Petroleum resources reservesSrikanth G
 
Reservoir Characterization 062816
Reservoir Characterization 062816Reservoir Characterization 062816
Reservoir Characterization 062816Calvin Reppe
 
Well logging and interpretation techniques asin b000bhl7ou
Well logging and interpretation techniques asin  b000bhl7ouWell logging and interpretation techniques asin  b000bhl7ou
Well logging and interpretation techniques asin b000bhl7ouAhmed Raafat
 
Well logging analysis: methods and interpretation
Well logging analysis: methods and interpretationWell logging analysis: methods and interpretation
Well logging analysis: methods and interpretationCristiano Ascolani
 
NTG-Oil-Gas-Analysis-FINAL
NTG-Oil-Gas-Analysis-FINALNTG-Oil-Gas-Analysis-FINAL
NTG-Oil-Gas-Analysis-FINALRichard Exley
 
petroleum-development-geology
 petroleum-development-geology petroleum-development-geology
petroleum-development-geologyShahnawaz Mustafa
 
Classification of reservoirs
Classification of reservoirsClassification of reservoirs
Classification of reservoirsFertiglobe
 
Reservoir capacity
Reservoir capacityReservoir capacity
Reservoir capacityonyx3
 
well logging tools and exercise_dileep p allavarapu
well logging tools and exercise_dileep p allavarapuwell logging tools and exercise_dileep p allavarapu
well logging tools and exercise_dileep p allavarapuknigh7
 
formation evaluation chapter 1
formation evaluation chapter 1formation evaluation chapter 1
formation evaluation chapter 1mohamadfadhli
 

Destacado (20)

Reservoir mapping
Reservoir mappingReservoir mapping
Reservoir mapping
 
Cairn case study
Cairn case studyCairn case study
Cairn case study
 
Basic well log interpretation
Basic well log interpretationBasic well log interpretation
Basic well log interpretation
 
TYPES OF RESERVOIR
TYPES OF RESERVOIRTYPES OF RESERVOIR
TYPES OF RESERVOIR
 
Formation evaluation and well log correlation
Formation evaluation and well log correlationFormation evaluation and well log correlation
Formation evaluation and well log correlation
 
Petroleum resources reserves
Petroleum resources reservesPetroleum resources reserves
Petroleum resources reserves
 
Unitization
UnitizationUnitization
Unitization
 
Reservoir Characterization 062816
Reservoir Characterization 062816Reservoir Characterization 062816
Reservoir Characterization 062816
 
Reservoir Rock Properties
Reservoir Rock PropertiesReservoir Rock Properties
Reservoir Rock Properties
 
Well logging
Well loggingWell logging
Well logging
 
Well logging and interpretation techniques asin b000bhl7ou
Well logging and interpretation techniques asin  b000bhl7ouWell logging and interpretation techniques asin  b000bhl7ou
Well logging and interpretation techniques asin b000bhl7ou
 
Well logging analysis: methods and interpretation
Well logging analysis: methods and interpretationWell logging analysis: methods and interpretation
Well logging analysis: methods and interpretation
 
NTG-Oil-Gas-Analysis-FINAL
NTG-Oil-Gas-Analysis-FINALNTG-Oil-Gas-Analysis-FINAL
NTG-Oil-Gas-Analysis-FINAL
 
petroleum-development-geology
 petroleum-development-geology petroleum-development-geology
petroleum-development-geology
 
Petrel course
Petrel coursePetrel course
Petrel course
 
Classification of reservoirs
Classification of reservoirsClassification of reservoirs
Classification of reservoirs
 
Reservoir capacity
Reservoir capacityReservoir capacity
Reservoir capacity
 
well logging tools and exercise_dileep p allavarapu
well logging tools and exercise_dileep p allavarapuwell logging tools and exercise_dileep p allavarapu
well logging tools and exercise_dileep p allavarapu
 
formation evaluation chapter 1
formation evaluation chapter 1formation evaluation chapter 1
formation evaluation chapter 1
 
Reservoir simulation study
Reservoir simulation study Reservoir simulation study
Reservoir simulation study
 

Similar a Estmation of oil & gas proven probable posiible

Reservoir engineering.ppt
Reservoir engineering.pptReservoir engineering.ppt
Reservoir engineering.pptYusufAdamu10
 
lec 1.pdf PETROLEUM PROPERTIES RESERVIOUR
lec 1.pdf  PETROLEUM PROPERTIES RESERVIOURlec 1.pdf  PETROLEUM PROPERTIES RESERVIOUR
lec 1.pdf PETROLEUM PROPERTIES RESERVIOURsarahrashid24
 
Gas storage industry primer-Niska
Gas storage industry primer-NiskaGas storage industry primer-Niska
Gas storage industry primer-NiskaGE 94
 
Fundamentals Of Reservoir.pdf
Fundamentals Of Reservoir.pdfFundamentals Of Reservoir.pdf
Fundamentals Of Reservoir.pdfYashGyanchandani5
 
Life Cycle of Oil & Gas Wells
Life Cycle of Oil & Gas WellsLife Cycle of Oil & Gas Wells
Life Cycle of Oil & Gas WellsMohamed Elnagar
 
Conference dschand school_of_sci_&_tech_15-01-18
Conference dschand school_of_sci_&_tech_15-01-18Conference dschand school_of_sci_&_tech_15-01-18
Conference dschand school_of_sci_&_tech_15-01-18Université de Dschang
 
Conference dschang school_of_sci_&_tech_15-01-18
Conference dschang school_of_sci_&_tech_15-01-18Conference dschang school_of_sci_&_tech_15-01-18
Conference dschang school_of_sci_&_tech_15-01-18Université de Dschang
 
Semester Assignment Drilling, Reservoir & Well Engineering Study
Semester Assignment Drilling, Reservoir & Well Engineering StudySemester Assignment Drilling, Reservoir & Well Engineering Study
Semester Assignment Drilling, Reservoir & Well Engineering StudyNikolaos Felessakis
 
Graduation Project Book 2020
Graduation Project Book 2020Graduation Project Book 2020
Graduation Project Book 2020Mahmoud Morsy
 
Key aspects of reservoir evaluation for deep water reservoirs
Key aspects of reservoir evaluation for deep water reservoirsKey aspects of reservoir evaluation for deep water reservoirs
Key aspects of reservoir evaluation for deep water reservoirsM.T.H Group
 
CO2 Storage capacity assessment, Ed Steadman, EERC
CO2 Storage capacity assessment, Ed Steadman, EERCCO2 Storage capacity assessment, Ed Steadman, EERC
CO2 Storage capacity assessment, Ed Steadman, EERCGlobal CCS Institute
 
IRJET- Analysis of Reserve Estimation using Volumetric Method on Taq Taq Oil ...
IRJET- Analysis of Reserve Estimation using Volumetric Method on Taq Taq Oil ...IRJET- Analysis of Reserve Estimation using Volumetric Method on Taq Taq Oil ...
IRJET- Analysis of Reserve Estimation using Volumetric Method on Taq Taq Oil ...IRJET Journal
 

Similar a Estmation of oil & gas proven probable posiible (20)

Reservoir engineering.ppt
Reservoir engineering.pptReservoir engineering.ppt
Reservoir engineering.ppt
 
lec 1.pdf PETROLEUM PROPERTIES RESERVIOUR
lec 1.pdf  PETROLEUM PROPERTIES RESERVIOURlec 1.pdf  PETROLEUM PROPERTIES RESERVIOUR
lec 1.pdf PETROLEUM PROPERTIES RESERVIOUR
 
Oil and Gas Industry.pdf
Oil and Gas Industry.pdfOil and Gas Industry.pdf
Oil and Gas Industry.pdf
 
part 1 .pdf.pdf
part 1 .pdf.pdfpart 1 .pdf.pdf
part 1 .pdf.pdf
 
Gas storage industry primer-Niska
Gas storage industry primer-NiskaGas storage industry primer-Niska
Gas storage industry primer-Niska
 
FIELD DEVELOPMENT PLANNING.pptx
FIELD DEVELOPMENT PLANNING.pptxFIELD DEVELOPMENT PLANNING.pptx
FIELD DEVELOPMENT PLANNING.pptx
 
Fundamentals Of Reservoir.pdf
Fundamentals Of Reservoir.pdfFundamentals Of Reservoir.pdf
Fundamentals Of Reservoir.pdf
 
Life Cycle of Oil & Gas Wells
Life Cycle of Oil & Gas WellsLife Cycle of Oil & Gas Wells
Life Cycle of Oil & Gas Wells
 
Conference dschand school_of_sci_&_tech_15-01-18
Conference dschand school_of_sci_&_tech_15-01-18Conference dschand school_of_sci_&_tech_15-01-18
Conference dschand school_of_sci_&_tech_15-01-18
 
Conference dschang school_of_sci_&_tech_15-01-18
Conference dschang school_of_sci_&_tech_15-01-18Conference dschang school_of_sci_&_tech_15-01-18
Conference dschang school_of_sci_&_tech_15-01-18
 
Introduction to Oil and Gas Industry - Upstream Midstream Downstream
Introduction to Oil and Gas Industry - Upstream Midstream DownstreamIntroduction to Oil and Gas Industry - Upstream Midstream Downstream
Introduction to Oil and Gas Industry - Upstream Midstream Downstream
 
Semester Assignment Drilling, Reservoir & Well Engineering Study
Semester Assignment Drilling, Reservoir & Well Engineering StudySemester Assignment Drilling, Reservoir & Well Engineering Study
Semester Assignment Drilling, Reservoir & Well Engineering Study
 
1 ior-eor rd-plans
1 ior-eor  rd-plans1 ior-eor  rd-plans
1 ior-eor rd-plans
 
Graduation Project Book 2020
Graduation Project Book 2020Graduation Project Book 2020
Graduation Project Book 2020
 
Key aspects of reservoir evaluation for deep water reservoirs
Key aspects of reservoir evaluation for deep water reservoirsKey aspects of reservoir evaluation for deep water reservoirs
Key aspects of reservoir evaluation for deep water reservoirs
 
CO2 Storage capacity assessment, Ed Steadman, EERC
CO2 Storage capacity assessment, Ed Steadman, EERCCO2 Storage capacity assessment, Ed Steadman, EERC
CO2 Storage capacity assessment, Ed Steadman, EERC
 
8 lecture.pptx
8 lecture.pptx8 lecture.pptx
8 lecture.pptx
 
Rig inspection, Sigve Hamilton Aspelund
Rig inspection, Sigve Hamilton AspelundRig inspection, Sigve Hamilton Aspelund
Rig inspection, Sigve Hamilton Aspelund
 
Oil & gas
Oil & gasOil & gas
Oil & gas
 
IRJET- Analysis of Reserve Estimation using Volumetric Method on Taq Taq Oil ...
IRJET- Analysis of Reserve Estimation using Volumetric Method on Taq Taq Oil ...IRJET- Analysis of Reserve Estimation using Volumetric Method on Taq Taq Oil ...
IRJET- Analysis of Reserve Estimation using Volumetric Method on Taq Taq Oil ...
 

Más de Narendra Kumar Dewangan (12)

Directional Drilling
Directional DrillingDirectional Drilling
Directional Drilling
 
Reservoir engineering aspect of fractured formations
Reservoir engineering aspect of fractured formationsReservoir engineering aspect of fractured formations
Reservoir engineering aspect of fractured formations
 
Cementation
CementationCementation
Cementation
 
Reservoir rock & fluid
Reservoir rock & fluidReservoir rock & fluid
Reservoir rock & fluid
 
Well test-procedures-manual
Well test-procedures-manualWell test-procedures-manual
Well test-procedures-manual
 
Introduction to drilling
Introduction to drillingIntroduction to drilling
Introduction to drilling
 
Casing design
Casing designCasing design
Casing design
 
Well test procedures manual
Well test procedures manualWell test procedures manual
Well test procedures manual
 
Oil gas seabed logging
Oil gas seabed loggingOil gas seabed logging
Oil gas seabed logging
 
cement plug job
cement plug jobcement plug job
cement plug job
 
Drilling fluids
Drilling fluidsDrilling fluids
Drilling fluids
 
Rtd
RtdRtd
Rtd
 

Último

Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdfKamal Acharya
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptMsecMca
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesRAJNEESHKUMAR341697
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Arindam Chakraborty, Ph.D., P.E. (CA, TX)
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Servicemeghakumariji156
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdfKamal Acharya
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptNANDHAKUMARA10
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesMayuraD1
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayEpec Engineered Technologies
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptxJIT KUMAR GUPTA
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaOmar Fathy
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 
kiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadkiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadhamedmustafa094
 
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...Health
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...HenryBriggs2
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxSCMS School of Architecture
 

Último (20)

Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planes
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
kiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadkiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal load
 
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 

Estmation of oil & gas proven probable posiible

  • 2. Reserves • Reserves are those quantities of petroleum which are anticipated to be commercially recovered from known accumulations from a given date forward. • All reserve estimates involve some degree of uncertainty. • The uncertainty depends chiefly on the amount of reliable geologic and engineering data available at the time of the estimate and the interpretation of these data. • The relative degree of uncertainty may be conveyed by placing reserves into one of two principal classifications, either proved or unproved. • Unproved reserves are less certain to be recovered than proved reserves and may be further sub-classified as probable and possible reserves to denote progressively increasing uncertainty in their recoverability.
  • 3. Proven Reserves • Proven reserves are those reserves claimed to have a reasonable certainty (normally at least 90% confidence) of being recoverable under existing economic and political conditions, with existing technology. Industry specialists refer to this as P90 i.e., having a 90% certainty of being produced. Proven reserves are also known in the industry as 1P • Proven reserves are further subdivided into "proven developed" (PD) and "proven undeveloped" (PUD). • PD reserves are reserves that can be produced with existing wells and perforations, or from additional reservoirs where minimal additional investment (operating expense) is required. • PUD reserves require additional capital investment e.g., drilling new wells to bring the oil to the surface.
  • 4. Proven Reserves • Proven reserves can further be categorized on the basis of status of wells and reservoirs as developed and Undeveloped; producing and nonproducing Developed: Developed reserves are expected to be recovered from existing wells. Improved recovery reserves are considered developed only after the necessary equipment has been installed, or when the costs to do so are relatively minor. Developed reserves may be subcategorized as producing or non-producing. Producing: – Reserves subcategorized as producing are expected to be recovered from completion intervals which are open and producing at the time of the estimate.
  • 5. Proven Reserves Non-producing: Reserves subcategorized as non-producing include shut-in and behind-pipe reserves. Shut-in reserves are expected to be recovered from (1)completion intervals which are open at the time of the estimate but which have not started producing, (2)wells which were shut-in for market conditions or pipeline connections, or (3)wells not capable of production for mechanical reasons. Behind-pipe reserves are expected to be recovered from zones in existing wells, which will require additional completion work or future recompletion prior to the start of production.
  • 6. Proven Reserves Undeveloped Reserves: Undeveloped reserves are expected to be recovered: (1) from new wells on undrilled acreage, (2) from deepening existing wells to a different reservoir, or (3) where a relatively large expenditure is required to (a) recomplete an existing well or (b) install production or transportation facilities for primary or improved recovery projects.
  • 7. Unproven Reserves • Unproven reserves are based on geological and/or engineering data similar to that used in estimates of proven reserves, but technical, contractual, or regulatory uncertainties make such reserves being classified as unproven. • Unproven reserves may be used internally by oil companies and government agencies for future planning purposes but are not routinely compiled. They are sub-classified as probable and possible Probable: Probable reserves are attributed to known accumulations and claim a 50% confidence level of recovery. Industry specialists refer to them as P50 i.e., having a 50% certainty of being produced. These reserves are also referred to in the industry as 2P (proven plus probable).
  • 8. Unproven Reserves Possible: Possible reserves are attributed to known accumulations that have a less likely chance of being recovered than probable reserves. This term is often used for reserves which are claimed to have at least a 10% certainty of being produced (P10). Reasons for classifying reserves as possible include varying interpretations of geology, reserves not producible at commercial rates, uncertainty due to reserve infill (seepage from adjacent areas) and projected reserves based on future recovery methods. They are referred to in the industry as 3P (proven plus probable plus possible).
  • 9. Classification of Reserves Reserves Proven Unproven Probable Possible Developed Undeveloped Producing Nonproducing
  • 10. Cross section View of a Reservoir structure as suggested from Seismic and Geological data
  • 11.
  • 12. After Exploration well was drilled
  • 13.
  • 16. Estimation of Reserves • The amount of oil in a subsurface reservoir is called oil initial in place (OIIP) • There are a number of different methods of calculating oil reserves. These methods can be grouped into four general categories: A. volumetric, B. material balance C. production performance. D. Comparative methods where comparison is made with those of offset properties of other fields having same geologic and other reservoir conditions.
  • 17. Estimation of Reserves • The different methods mentioned can be applied in the following time periods Time period % of reserves Produced Methods of Estimation Reasonable range of error Prior to Drilling 0 D 10-100 % After completion 0 A & D 5-50 % During production 1-10 % A, B & C 5-30 % During production 10-30 % A, B & C 5-20 % During production 30-60 % B & C 5-10 % During production 60 & over C About 5 %
  • 18. Volumetric Estimation • Volumetric estimation is the only means available to assess hydrocarbons in place prior to acquiring sufficient pressure and production information. • Volumetric methods are primarily used to evaluate the in- place hydrocarbons in new, non-producing wells and pools and new petroleum basins. But even after pressure and production data exists, volumetric estimates provide a valuable check on the estimates derived from material balance and decline analysis methods. • Volumetric estimation is also known as the “geologist’s method” as it is based on cores, analysis of wireline logs, and geological maps.
  • 19. Volumetric Estimation Volumetric estimation requires determination of following reservoir parameters. a)Estimation of volume of sub surface rock that contains hydrocarbons. The volume is calculated from the thickness of the rock containing oil or gas and the areal extent of the accumulation. b)Determination of a weighted average effective porosity. c)Obtaining a reasonable water resistivity value to calculate water saturation. With these reservoir rock properties and utilizing the hydrocarbon fluid properties, original oil-in-place or original gas-in-place volumes can be calculated.
  • 20. Volumetric Estimation For OIL RESERVOIRS the oil initial in-place (OIIP) volumetric calculation is. •Metric: •OIIP (m3 ) = Rock Volume * Ø * (1- Sw) * 1/Bo Where: Rock Volume (m3 ) = 104 * A * h A = Drainage area, hectares (1 ha = 104 m2 ) h = Net pay thickness, meters Ø= Porosity, fraction of rock volume available to store fluids Sw = Volume fraction of porosity filled with interstitial water Bo = Formation volume factor (m3 /m3 ) (dimensionless factor for the change in oil volume between reservoir conditions and standard conditions at surface)
  • 21. Volumetric Estimation • Imperial: OIIP (STB) = Rock Volume * 7,758 * Ø * (1- Sw) * 1/Bo Where: Rock Volume (acre feet) = A * h A = Drainage area, acres h = Net pay thickness, feet 7,758 = Bbl per acre-feet (converts acre-feet to stock tank barrels) Ø = Porosity, fraction of rock volume available to store fluids Sw = Volume fraction of porosity filled with interstitial water Bo = Formation volume factor (Reservoir Bbl/STB) 1/Bo = Shrinkage (STB/reservoir Bbl)
  • 22. Oil Recovery Factor • The recovery factor is one of the most important, yet the most difficult variable to estimate. • Fluid properties such as formation volume factor, viscosity, density, and solution gas/oil ratio all influence the recovery factor. • In addition, it is also a function of the reservoir drive mechanism and the interaction between reservoir rock and the fluids in the reservoir.
  • 23. Oil Recovery Factor •The approximate oil recovery range is tabulated below for various driving mechanisms. •Note that these calculations are approximate and, therefore, oil recovery may fall outside these ranges
  • 24. Estimation of Gas in place Gas in reservoir occurred as • Non associated gas • Associated gas • Solution gas.
  • 25. Volumetric Estimation of Non Associated Gas For GAS RESERVOIRS the gas initial in-place (GIIP) volumetric calculation is: •Metric: GIIP (103 m3 ) = Rock Volume * Ø * (1-Sw) * (Ts * Pi) /(Ps * Tf * Zi) Where: Rock Volume (m3 ) = 104 * A * h A = Drainage area, hectares (1 ha = 104 m2 ) h = Net pay thickness, meters Ø = Porosity, fraction of rock volume available to store fluids Sw = Volume fraction of porosity filled with interstitial water Ts = Base temperature, standard conditions, °Kelvin (273° + 15°C) Ps = Base pressure, standard conditions, (1.01 kg/cm2 ) Tf = Formation temperature, °Kelvin (273° + °C at formation depth) Pi = Initial Reservoir pressure, kg/cm2 Zi = Compressibility at Pi and Tf
  • 26. Volumetric Estimation of Non Associated GAS • Imperial: GIIP (MMCF) = Rock Volume * 43,560 * Ø * (1-Sw) * (Ts * Pi)/ (Ps * Tf * Zi) Where: Rock Volume (acre feet) = A * h A = Drainage area, acres (1 acre = 43,560 sq. ft) h = Net pay thickness, feet Ø = Porosity, fraction of rock volume available to store fluids Sw = Volume fraction of porosity filled with interstitial water Ts = Base temp., standard conditions, °Rankine (460° + 60°F) Ps = Base pressure, standard conditions, 14.65 psia Tf = Formation temp, °Rankine (460° + °F at formation depth) Pi = Initial Reservoir pressure, psia Zi = Compressibility at Pi and Tf
  • 27. Volumetric Estimation of Associated Gas Associated Gas • Gas associated with oil as gas cap is known as associated gas. • During oil production period this remained shut in. • Once most of the oil is produced, gas from gas cap is produced. • Estimation method is same as described for Non associated gas.
  • 28. Volumetric Estimation of Solution Gas Solution Gas • Gas liberated from the reservoir during oil production. • To estimate the volume of this gas following formula is applied. GIIP(soln.) = N(OIIP) x GOR
  • 29. Gas Recovery Factor • Volumetric depletion of a gas reservoir with reasonable permeability at conventional depths in a conventional area will usually recover 70 to 90% of the gas-in-place. • However, a reservoir’s recovery factor can be significantly reduced by factors such as: low permeability, low production rate, soft sediment compaction, fines migration, excessive formation depth, water influx, water coning and/or behind pipe cross flow, and the position and number of producing wells. • As an example, a 60% recovery factor might be appropriate for a gas accumulation overlying a strong aquifer with near perfect pressure support.
  • 30. Reservoir Rock Sand Grain Cementing material Interconnected or effective porosity Isolated or non effective porosity
  • 31. Calculations of Rock Volume • The projected surface area of a hydrocarbon deposit can be completely defined only by the drill • Reservoir volumes can be calculated from net pay isopach maps by planimetering to obtain rock volume (A * h). • To calculate volumes it is necessary to find the areas between isopach contours. • Planimetering can be performed by hand or computer generated. • Given the areas between contours, volumes can be computed using; Trapezoidal rule, Pyramidal rule, and/or the Peak rule for calculating volumes
  • 32. Calculations of Rock Volume Following methods can be used to evaluate the rock volume Trapezoidal Volume V = h (A1+ A2/2) Frustum of pyramid V = h/3 (A1+A2+ A1*A2)
  • 33. Net Pay • Net pay is the part of a reservoir from which hydrocarbons can be produced at economic rates, given a specific production method. • The distinction between gross and net pay is made by applying cut-off values in the petrophysical analysis. • Net pay cut-offs are used to identify values below which the reservoir is effectively non-productive. In general, the cut-off values are determined based on the relationship between porosity, permeability, and water saturation from core data and capillary pressure data.
  • 34. Net Pay A B C D E F low porosity, low permeability, very low/ no oil saturation, Non Pay high porosity, high permeability, high oil saturation, Gross & net pay low porosity, low permeability, very low or no oil saturation Gross pay low porosity, low permeability, very low or no oil saturation, Gross pay high porosity, high permeability, high oil saturation, Gross & net pay high porosity, high permeability, high water saturation, Non pay Gross thickness = A+B+C+D+E+F = 6 m, Gross reservoir = B+C+D+E+F = 5 m Gross pay = B+C+D+E = 4 m , Net thickness = Net reservoir = B+E+F = 3 m Net pay = B+E = 2 m
  • 35. Porosity and water saturation • In evaluation of porosity of individual wells, the weighted average porosity values are computed. • Porosity values are assigned as an average over a zone (single well pool) or as a weighted average value over the entire pay interval using all wells in a pool. • If all the intervals sampled from a well are of uniform thickness, the weighted average and the arithmetic average are identical. • If the intervals differ in both thickness and the values then the two averages will be different. • Similarly, the average thickness-weighted water saturation using all wells in the pool is commonly assumed as the pool average water saturation.
  • 36. Weighted average Porosity Depth (Ft) h Ø (%) Øh 3690-3691 1 20 20 3691-3693 2 23 46 3693-3694 1 21 21 3694-3697 3 26 78 Total 7 90 165 Arithmetic average Ø = 90/4 = 22.5% Weighted average Ø = 165/7= 23.5%
  • 37.     Inplace Ultimate Cumm Prod Reserve         Gas     Gas     Gas     Gas Field Cat Oil  Cond Sol Gas GC F GAS Oil  Cond Sol Gas GC F GAS Oil  Cond Sol Gas GC F GAS Oil  Cond Sol Gas GC F GAS Bandamurlanka PD   0.06    157.6  0.03    23.7 0.01      5.2  0.01    18.5 PDPB                   70.9 0.03          0.03    70.9 PB                                         PS                                         Bhimanapalli PB         21.8        13.1                  13.1 Endamuru PD   0.06    3214.9  0.05    2175.3 0.02      1484  0.03    691.3 Enugapalli PD   0.01    378.9        227.3        89.7        137.7 PS         220.6                              Gedanapalli PD 0.75        0.08                  0.07        Mandapetta PD 0.02 1.04    18330  0.73    12820.1  0.05    1842.4  0.68    10977.6 PB   0.3    9060.8  0.21    6394.2            0.21    6394 Mummidivaram PD         58.7                              PBPB                   35.2                  35.2 Penugonda PS         2364.6                              Rangapuram PD         240.8        144.5        7        137.4 PB         37.9        22.8                  22.8 PS         75.4                              Table of Reserve
  • 38. Oil & Gas Reserves Oil (MMt) Cond. (MMt) SG+GCG (MMm3 ) Free Gas (MMm3 ) Oil +OEG (MMt) As on 01.04.2010 Inplace 4793.81 73.94 1277448 994668 7139.87 Ultimate 1323.26 67.22 725965.8 394915.8 25112.36 Reserves 531.55 31.87 301313.7 310181.3 1174.92 As on 01.04.2011 Inplace 4888.1 72.54 1302975.1 113158.5 7376.79 Ultimate 1337.19 66.88 746115.2 445952.9 2596.14 Reserves 523.29 30.15 303661.6 356117.1 1213.22
  • 39. Material Balance • When an oil and gas reservoir is put on production it produces oil, gas and some time water also thereby reducing the reservoir pressure. • If the oil and gas bearing strata is hydro dynamically connected with water strata or aquifer water encroaches in to the reservoir and accordingly retarding the declining in pressure. • The material balance equation is derived as a volume balance which equates the cumulative observed production, expressed as an underground withdrawal, to the expansion of the fluids in the reservoir resulting from finite pressure drop
  • 40. Principle of Material Conservation Amount of fluids present in the reservoir initially (st. vol) Amount of fluids produced (st. vol) Amount of fluids remaining in the reservoir finally (st. vol.) - The material balance equations are based on simple mass balance of the fluids in the reservoir, and may be formulated as
  • 41. Material Balance Analysis OIL OIL Initial stage (1) Final stage (2) N*Boi (N-Np)*Bo
  • 42. Material Balance Analysis Oil present in the reservoir initially (st. vol.) Oil produced (st. vol Oil remaining in the reservoir finally (st. vol.) - Equation 1: Oil material balance N Boi = (N-Np)Bo N = Bo*Np/Bo-Boi
  • 43. Material Balance Analysis water present in the reservoir initially (st. vol.) Water produced (st. vol) water remaining in the reservoir finally (st. vol.) - Equation 2: Water material balance Vp1Sw1/Bw1 - Wp + Wi + We= Vp2 Sw2 /Bw2 + Water inj. + Aquifer influx
  • 44. Material Balance Equation for a Closed Gas Reservoir • The material balance equation for a closed gas reservoir is very simple. Applying the mass balance principle to a closed reservoir with 100% gas, we may derive the general eguation • GBg1 = (G − Gp )Bg 2 • where • G is gas initially in place, • Gp is cumulative gas production, and • Bg is the formation-volume-factor for gas. Since Bg is given by the real gas law • Bg = (constant)Z/P • (here temperature is assumed to be constant)
  • 45. Material Balance Equation for a Closed Gas Reservoir The material balance equation may be rewritten as G (Z1/P1) =(G-Gp) (Z2/P2) (P2/Z2)= (1- Gp/G)(P1/Z1) This equation represents a straight line relationship on a P2/Z2 vs. Gp plot. The straight-line relationship is very useful in estimating the initial volume of gas-in-place (G) from limited production history P/Z
  • 46. Production decline Analysis • Production decline analysis is a basic tool for forecasting production from a reservoir once there is sufficient production to establish a decline trend as a function of time. • The technique is more accurate than volumetric methods when sufficient data is available to establish a reliable trend and is applicable to both oil and gas wells. • Accordingly, production decline analysis is most applicable to producing pools with well established trends. • The rate versus time plot is commonly used to diagnose well and reservoir performance as shown in the example plot. • Arps (1945, 1956) developed the initial series of decline curve equations to model well performance. The equations were classified as exponential, hyperbolic, or harmonic, depending on the value of the exponent
  • 48. Conclusions •Estimation of reserves is done under conditions of uncertainty •The principal uncertainties associated with the performance of the overall reservoir model. •The type of data which is most important to define the reservoir. • Reservoir structure • Reservoir properties • Reservoir sand connectivity • Impact of faults • Relative permeability etc • Fluid properties • Aquifer behavior • Well productivity (fractures, well type, condensate drop out etc.) •The impact of each of these parameters will vary according to the particular field. •It is important that the company is not ignorant of the magnitude of the contributing uncertainties, so that resources can be directed at cost effectively reducing specific uncertainties.