ADB/OECD Anti-Corruption Initiative for Asia and the Pacific
The Secretariat
Jak Jabes, Director, Governance and Regional
Co-operation, ADB
jjabes@adb.org
phone: +63 2 632 5749, fax: +63 2 636 2193
Frédéric Wehrlé, Co-ordinator, Anti-Corruption
Initiatives, Anti-Corruption Division, OECD
frederic.wehrle@oecd.org
phone: +33 1 4524 1855, fax: +33 1 4430 6307
Anti-corruption policies in Asia and the Pacific:
Thematic review on provisions and practices to
curb corruption in public procurement
Self-assessment report Korea
Identifying reform needs, assessing progress and evaluating the effectiveness of anti-corruption
policies and practices are central principles enshrined in the ADB/OECD Initiative and its Action
Plan. In this context, the present self-assessment report from Korea was prepared as background
to the Initiative’s thematic review exercise on measures to curb corruption in public procurement in
the Asia-Pacific region.
This thematic review on public procurement was initiated in reaction to the findings of the
Initiative’s 2003-2004 in-depth analysis of the legal and institutional anti-corruption frameworks of
the Action Plan’s then 21 endorsing countries against the standards of this Plan (“Anti-Corruption
Policies in Asia and the Pacific – the legal and institutional frameworks”, November 2004). In this
study, public procurement was identified as one of the areas requiring particular attention in the
Asia and Pacific region and where consequently the Initiative’s Steering Group had a vital interest
to promote reform.
With this aim, the group agreed to pursue analytical work on corruption in public procurement
through a thorough review of relevant existing policies, practices and rules so as to assist
participating governments in better understanding the corruption risks inherent in their countries’
institutional settings and procurement practices. This thematic review further seeks to assess how
countries translate into practice their commitment made under the Action Plan to curb corruption in
public procurement. Eventually, the review’s findings will provide governments with an analytical
framework to design policies and procedures that ensure greater transparency and integrity in
public procurement and to identify priorities for reform in this respect.
In line with the Action Plan’s principle of self-assessment, the review is conducted on the basis of
information provided by participating countries in reply to a questionnaire specifically prepared for
this purpose by the ADB/OECD Initiative. The present document represents the replies submitted
by Korea in this framework.
Further information on the exercise, on other participating countries and on the analysis’ outcome
is available at the Initiative’s website at http://www1.oecd.org/daf/asiacom/stocktaking.htm#trpp.
ADB/OECD Anti-Corruption Initiative for Asia and the Pacific
Thematic review on public procurement – Country information on the Republic of Korea
– 2 –
A. General framework
Legal and organizational framework:
1. Please list and briefly describe laws and regulations related to government procurement, including
those that give exemption to the standard government procurement rules. Where available, please attach a
copy or indicate an internet-site for download of these regulations, if possible in English language. Ensure to
include secondary legislation, rules and procedures. Also, please indicate relevant international or regional
agreements
1
that your country is committed under, including its level of involvement (e.g. signature,
ratification, implementation).
Law and Regulation Related to Government Procurement
a. The Government Procurement Act determines matters necessary to operate and manage the
procurement business for its efficient performance, which is conducted by the Public Procurement
Service as a central procuring agency. Under the act lie the enforcement decree and the rules
related to the procurement business.
b. The Act on Contracts to which the State is a Party determines basic matters regarding contracts to
which the government is a party. Under the act lies the enforcement decree and rules related to
contracts to which the government is a party.
Special Provisions of the Enforcement Decree of the Act on Contracts to which the State is a Party
for specific procurement determines special provisions regarding the enforcement decree of the act
on contracts to which the state is a party when conducting international bids in accordance with
Article 4 of the Act on Contracts to which the State is a Party in order to implement multilateral or
bilateral government procurement agreements such as the agreement prepared in Marrakech on
April 15, 1994 which the government has established or acceded to. Under these provisions lie the
Special Enforcement Rules of the Act on Contracts to which the State is a Party.
There are also Special Provisions of the Enforcement Decree of the Act on Contracts to which
the State is a Party for the procurement of specific goods, which determines special provisions of
the enforcement decree of the act on contracts to which the state is a party in conducting
procurement of goods by means of the contract through international bidding. Under these
provisions lie Special Rules on Conducting the Contracting Job for the Procurement of Specific
Goods.
c. The Local Finance Act determines basic principles on the finance and accounting for local
autonomies. It stipulates contracts in Article 7, and matters other than the ones determined in this
Act and other regulations that are subject to the Act on Contracts to which the State is a Party.
Under this act lies the Enforcement Decree for the Local Finance Act.
d. The Framework Act on the Management of Government-Invested Institutions determines basic
matters regarding autonomy and accountability in the management of government-invested
institutions. Under this act lie the accounting rules on government-invested institutions, which
regulate accounting, standards of contracts and procedures and the limitation on the participation in
bids for government-invested institutions. Matters that are not regulated in this rule are governed by
the Act on Contracts to which the State is a Party.
1
e.g. APEC Non-Binding Principles on Government Procurement; WTO Agreement on Government Procurement;
etc.
ADB/OECD Anti-Corruption Initiative for Asia and the Pacific
Thematic review on public procurement – Country information on the Republic of Korea
– 3 –
The sites where regulations related to government procurement can be downloaded:
Korean text:
– www.g2b.go.kr (in the section of Regulation Information under Customer Assistance)
– www.moleg.go.kr
English text: www.klri.re.kr/project/emain.nsf
As for the involvement of commitment to international or regional agreements
– The WTO Agreement on Government Procurement
– The OECD Convention on the Bribery of Foreign Public Officials
– The Korea-Chile Free Trade Agreement (FTA) has been implemented.
– The Korea-Singapore FTA has been signed.
2. Please explain the repartition of tasks and responsibilities in the procurement process among
centralized, decentralized and specialized authorities (in particular: design of policies and standards;
capacity building; definition of needs and terms of individual tenders; execution of different procurement
stages from advertising to contract awarding; dispute resolution; control of the fulfillment of the terms and
conditions by the contractor).
– The Public Procurement Service (PPS), the central procuring agency, conducts the procurement
business under Article 3 of the Government Procurement Act.
As for the procedures and scope of procurement of goods, which is regulated in Article 14 of the
Government Procurement Act, the principal of an end-user organization should make a purchase
and supply the request to the PPS Administrator when need arises. It, however, may directly
purchase the goods according to the exception of Article 14.
– The end-user organization can submit its opinions on the specifications and conditions for
participation in bids when making a procurement request, which is finally determined by the PPS
Administrator and then publicized for bid invitation.
– As for the procedures and scope of works, which is regulated in Article 15 of the Enforcement
Decree of the Government Procurement Act, the head of an end-user organization should make a
request for a works contract to the PPS Administrator regarding matters above a certain amount.
They can also make a contract request to the PPS Administrator if necessary, even in cases where it
can directly establish a contract for public works.
Construction designs such as drawings and specifications are prepared by an end-user organization,
and are subject to general contract conditions as determined by the Minister of Finance and
Economy. As for specific conditions, however, the PPS Administrator consults with the end-user
organization and then determines them.
3. Is procurement of goods governed by the same procedures as procurement of services?
There is no difference between goods and services in procurement procedures.
4. Does the procurement law establish a Public Procurement Office (PPO)? Is the PPO appropriately
staffed against its mandate? In this context, please state the total number of staff involved in public
procurement country-wide. Are the procurement entities/PPO provided with adequate financial resources for
the execution of their tasks?
The procurement law establishes the Public Procurement Service as a central procuring agency, which
conducts the procurement business according to the Government Procurement Act. PPS has
approximately 950 employees. PPS receives procurement commissions from its end-users to conduct
procurement business.
ADB/OECD Anti-Corruption Initiative for Asia and the Pacific
Thematic review on public procurement – Country information on the Republic of Korea
– 4 –
5. Please name the sectors, areas or conditions subject to particular procurement rules (if applicable, e.g.
military; local governments; state owned enterprises; urgency).
As for procurement law that is applicable to each organization, be it a national organization, local
autonomy or government-invested institution, see Answer 1. There is a Defense Procurement Agency
as a procuring agency of defense materials, which procures according to the Act on Contracts to which
the State is a Party.
Procurement policies and practices:
6. Do model tender documents exist (e.g. handbooks, model forms, model contracts, etc)? If yes, is their
use mandatory, and do they contain a specific anti-corruption clause?
The law related to government procurement includes standard bid forms, the use of which is
mandatory. A standard bid form includes anti-corruption clauses. The clauses stipulate that bidders
submit their bids in accordance with bid instructions and bid instructions provide for debarred suppliers’
limitation in participating in bids. Aside from the bid instructions, the Special Instruction on Integrity
Bidding and Contract applies to all bids.
7. Please provide the latest available economy-wide annual total numbers and values of purchases, with
breakdown a) by sector and b) by type of procurement. In this context, please describe the procurement
types foreseen by law (e.g. sealed tender, direct purchase; limited tendering) and the policy of your
Government towards these types.
The procurement volume in 2003 reached 74 trillion won: 33.7 trillion won for national organizations;
19.3 trillion won for local autonomies; 12.1 trillion won for government-invested institutions; 8.2 trillion
won for special legal entities such as government-funded organizations; and 9 trillion won for local
public corporations.
It is difficult to confirm the procurement volume by type of procurement, though the principle of the
procurement type is for open competition in the Act on Contracts to which the State is a Party.
However, procurement can be made through the use of limited competition, nomination, and private
contract according to the Presidential Decree when such method is necessary, considering the
objective, nature and size of the contract, as is suggested in Article 7 of the Act on Contracts to which
the State is a Party.
8. Please explain under which conditions pre-selection procedures are conducted.
According to Article 13 of the Enforcement Decree of the Act on Contracts to which the State is a Party,
as for works determined by the Ministry of Finance and Economy’s order, applicants are examined for
the review of qualifications prior to the bid, and then eligible ones can participate in a competitive bid
once selected and are notified of their results.
When it is necessary to examine bidder’s qualifications in order to participate in bids, PPS requires
detailed examination criteria in accordance with the examination criteria determined by the Minister of
Finance and Economy which should then be accessible by hopeful bidders before they participate in the
bid.
9. If your country is currently engaged in or planning a major reform of its procurement system, please
briefly state the scope and objectives of this reform.
Korea acceded to the WTO Agreement on Government Procurement in 1994 and revised the entire
government contract law in 1995.
ADB/OECD Anti-Corruption Initiative for Asia and the Pacific
Thematic review on public procurement – Country information on the Republic of Korea
– 5 –
On Sept. 30, 2002, PPS adopted the Government e-Procurement System (GEPS), and made it
mandatory to publicize bid invitations by all public institutions in GEPS. The entire procurement process
is processed electronically in terms of bid execution, awardee selection, contract establishment through
to payment.
Starting from 2005, PPS introduced multiple award methods similar to the Framework Agreement of
Britain, and the Multiple Award Schedule of the USA in order to provide a greater range of choices to
end-user organizations.
B. Transparency and Fairness
Transparency of general procurement policies and regulations:
10. Are the existing laws, regulations and policy guidelines on public procurement publicly available and, if
yes, where/how?
The laws, regulations and guidelines on public procurement are available in the Government e-
Procurement System and are accessible via the Internet, www.g2b.go.kr.
The Republic of Korea’s laws, including ones on government procurement, are available in the Ministry
of Legislation’s homepage, www.moleg.go.kr
11. In your country, do certain territorial entities or institutions establish lists of eligible contractors
(sometimes called “white-lists”)? If yes, please explain the criteria for a company to be included in or
excluded from this list, and what use is made of such lists.
Korea has operated a competitive system by means of an eligible bidder list for public works since
1975. The purpose of the system is to equally divide construction projects between big, medium-sized
and small enterprises according to their capability.
Construction companies are categorized into seven levels based on their performance capability
amount, which is announced by the Korean Construction Association every year. Each construction
company is entitled to participate in bids for projects that are allocated according to their level.
12. Is a bid security and/or a performance guarantee required from the bidder? What are the procedures for
advertisement of procurement opportunities?
The laws on procurement require a payment of 5% of the contract amount for bid security and 10% for
performance bond in principle. However, the bid security payment is exempted before the bidding takes
place, except for special circumstances. Contents on whether and how to pay a bid security are
contained in the bid invitation.
Transparency of procurement opportunities:
13. Describe where and how tender opportunities are published, including if their publication is mandatory
or depends on certain criteria (if so, please list)? Please state if a fee has to be paid to receive tendering
documents and – if yes – how this fee is fixed and whether other processing fees apply. Please briefly
explain whether your country allows adequate and reasonable time for interested suppliers to prepare and
submit responsive bids.
All bid invitations by public institutions must be made in the Government e-Procurement System.
ADB/OECD Anti-Corruption Initiative for Asia and the Pacific
Thematic review on public procurement – Country information on the Republic of Korea
– 6 –
There are no fees to participate in a bid in most cases, but some local autonomies collect them.
The laws on procurement stipulate the bid invitation period, considering the time needed for preparing a
bid. This must be honored by public institutions.
14. Are selection and award criteria prescribed by law? If yes, are they prescribed in an exclusive manner?
Please name these criteria a) for procurement of goods, and b) for procurement of services (e.g. technical
requirements, qualification of the bidder, evaluated price, expertise/experience, etc.) and those that are
explicitly excluded (e.g. nationality of the bidder or other affinity, etc.). Is the description of these criteria in
the tender documentation mandatory?
The award criteria are stipulated in Paragraph 2 of Article 10 of the Enforcement Decree of the Act on
Contracts to which the State is a Party, including;
– those who are capable of fulfilling a contract and have submitted the lowest price;
– those who have submitted the most advantageous bid to the government according to evaluation
criteria mentioned in bid documents such as bid invitations; and
– those who have submitted the most appropriate bid, compared to the special standards mentioned in
the Presidential Decree, taking into consideration the nature and scope of the contract.
Contract methods, qualifications to participate in a bid, contents to be included in a bid, bid evaluation
and award criteria are subject to laws related to procurement, and should be included in bid documents
such as the bid invitation concerned.
Bidding methods and bid nullification are regulated in Article 42 or 44 of the Enforcement Rules, the Act
on Contracts to which the State is a Party. When nullifying the bid, a contracting official must notify the
bidder of the reason.
Transparency of contract evaluation and award procedures:
15. What is the procedure if none of the bids or too few – relative to a prescribed limit – fulfill the technical
requirements as defined in the call for tender (e.g. reopening of the bid, negotiations, etc.)? Do you keep a
register of all bids received?
Two or more valid bids comprise a competitive bidding according to Article 11 of the Enforcement
Decree of the Act on Contracts to which the State is a Party.
– When there are not two or more valid bidders or awardees, re-bidding can be made again at the
same place according to Paragraph 1, Article 20, the Enforcement Decree of the Act on Contracts to
which the State is a Party.
– When there are no bidders or awardees or the awardee did not establish a contract, the bid can be
invited again according to Paragraph 2, Article 20, the Enforcement Decree of the Act on Contracts
to which the State is a Party.
When the bid results show that there was only one bidder and it is apparent in the case of bids to be
invited again that there will be only one qualified bidder, and when the re-invited bidding showed that
there were no bidders or awardee, the procurement can be made by a private contract according to
Article 27 of the Enforcement Decree of the Act on Contracts to which the State is a Party.
Bidding and contracting documents are maintained by the owner institution for five years according to
the law concerning the management of records for public institutions.
ADB/OECD Anti-Corruption Initiative for Asia and the Pacific
Thematic review on public procurement – Country information on the Republic of Korea
– 7 –
16. Where and how are actions and decisions in the procurement process recorded? How long and where
are these records preserved, and who can access this information?
Actions and decisions in the procurement process are recorded and managed in written form by the
owner institution. With the introduction of the Government e-Procurement System made on Sept. 30,
2002 and its growing use, there are a growing number of e-documents managed in this system.
Documents related to bidding and contracts are preserved by the owner institution for five years
according to the law on the management of records by public institutions.
They are also accessible to the public according to the law on publicizing the information on public
institutions. All contents on bid invitations, e-bid results and award results using the Government e-
Procurement System are accessible in real time through the Internet.
17. How and to whom is the final decision on awarding the tender disclosed? Do reasons for the selection
of the winning bidder have to be stated? Are post-awarding negotiations allowed and, if yes, under what
conditions?
All contents on bid invitations, e-bid results and award results using the Government e-Procurement
System are accessible in real time through the Internet.
Since awarding is subject to criteria determined in the bid invitation, the reason for the selection of the
awardee is not separately stated.
In the case of negotiated contracts in accordance with Article 43 of the Enforcement Decree of the Act
on Contracts to which the State is a Party, negotiations are conducted before selecting an awardee. In
this case, the criteria and procedures required for establishing a contract must be determined previously
and must be accessible to negotiating bidders.
18. Are framework contracts allowed? If yes, what measures are taken to control against corrupt or
unnecessary demands?
In order to offer a wider choice for end-user organizations, Korea has adopted a multiple award method
similar to a framework contract, starting from 2005.
In the case of the Multiple Award Schedule, PPS has operated the price review council with the
involvement of external members to enhance transparency and fairness since Jan. 19, 2005. The
council reviews major agendas related to determining price.
C. Integrity
Integrity of procurement personnel:
19. Do codes of ethics or similar instruments exist that explicitly apply to procurement personnel and
entities? If yes, do they specifically address corruption risks, and do they contain conflict of interest
provisions (e.g. provisions making mandatory the declaration of personal interests by agents and buyers)?
To establish a law-abiding mindset for public officials and discipline in the public service, PPS has
enacted and implemented the Procurement Service Charter, the Code of Conduct for Safeguarding
Integrity for PPS officials, criteria for determining the level of sanctions on PPS officials, and Integrity
Contract, as government guidelines.
PPS is focusing on creating a working environment to eradicate and prevent corruption through the
detection and elimination of the causes of corruption by exploring ways to attain anti-corruption
measures.
ADB/OECD Anti-Corruption Initiative for Asia and the Pacific
Thematic review on public procurement – Country information on the Republic of Korea
– 8 –
By operating the Procurement Complaint Center on the PPS homepage to impose controls by citizens
in order to prevent corruption, PPS receives and processes reports of irregularities and the cases of
acts of overt kindness or unfriendliness. The Kickbacks Reporting Center in the PPS’ EDMS bulletin
board serves as a reporting center for the informant as well as others.
20. Does your country provide for specific training for procurement personnel that include integrity issues?
Please list manuals or policy guidelines that might exist to clarify procurement procedures and principles to
procurement personnel (if existing please attach a copy or internet-address for download).
In order to establish an image of integrity for procurement officials, PPS conducts one or more special
training sessions to implement a code of conduct for PPS officials every year and checks whether or not
it is being honored every month.
To strengthen anti-corruption education and promotion, PPS has allocated anti-corruption training within
the professional procurement education course in which procurement officials in all levels of
government participate and utilize professional instructors from the Korean Independent Commission
against Corruption when conducting education on a regular basis.
All data related to procurement such as bidding and contract data, product information, and relevant
laws are registered on the PPS homepage, www.pps.go.kr in detail, which are used by procurement
personnel at home and abroad.
21. Is procurement personnel required – and if yes by what regulation and to what institution – to report
attempts by suppliers to undermine the impartiality and independence of action by offering bribes, benefits or
other forms of inducement?
As for illegal activities such as the offering of bribes by the supplier, Article 18 of the Code of Conduct
for Safeguarding the Integrity for PPS Officials requires such acts to be reported to the Code of Conduct
Officer or Audit Officer. Cases involving the PPS administrator, however, should be directly reported to
the Korean Independent Commission against Corruption.
22. Which penal and/or administrative sanctions are applicable to procurement personnel for accepting or
soliciting bribes? Are public officials liable for the economic damage that the procuring entity suffers? What is
the policy that applies to procurement personnel for accepting or soliciting small facilitation payments such
as gifts, benefits, hospitality (e.g. outright forbidden, accepted under certain circumstances, etc.; please
explain).
Public officials who are found to be involved in the acceptance or solicitation of bribes are punished in
accordance with the Penal Code (Article 129~132 and 134~135) or according to Paragraph 1 or 2 of
Article 2 of the Act on Increased Penalty for Specific Crimes in the case of bribes exceeding 50 million
won. They will receive disciplines according to the criteria for determining the level of discipline on
corrupt PPS officials.
When someone has incurred economic damages on the government, he or she shall offer
compensatory responsibility to the government, and procedures for this case are regulated in the Act on
Responsibility of Accounting Employees.
The Code of Conduct for Safeguarding Integrity for PPS Officials prevents work-related people,
businesses, and work-related public officials from receiving money, property, gifts or entertainment in
principle. However, Article 14 of the code stipulates a range of kickbacks that are exceptions to this
Article.
ADB/OECD Anti-Corruption Initiative for Asia and the Pacific
Thematic review on public procurement – Country information on the Republic of Korea
– 9 –
Integrity of bidders and suppliers:
23. Which penal sanctions are applied to a bidding company as a legal person and to its employees if it is
found guilty of corruption related to the bidding procedure? Is the company liable for the economic damage
that the procuring entity suffers?
If a bidding business or its employees are found guilty of corruption related to the bidding procedure,
they are subject to imprisonment of five years or less or fines of 20 million won or less according to
Article 133 of the Penal Code.
As for economic damage on the government incurred by a business because of its illegal activities, the
government can cancel the contract with the business according to Article 75 of the Enforcement
Decree of the Act on Contracts to which the State is a Party, and the business shall offer compensatory
damage according to Article 750 of the Civil Law.
24. Do your country’s laws and regulations permit authorities to suspend, temporarily or permanently, from
competition for public contracts and/or from other commercial activities an enterprise determined to have
bribed a public official? If yes, is such disqualification mandatory or optional and which body decides on the
disqualification and its exact terms? Which means are employed to implement the disqualification (e.g.
publicly available list, declaration in the bidding process…)?
Authorities can impose disqualification on those who have committed irregularities such as the offering
of bribes to public officials or such businesses for a certain period of time so that they are prevented
from participating in all biddings by public institutions according to Paragraph 1, Article 76, the
Enforcement Decree of the Act on Contracts to which the State is a Party. And the authorities cannot
establish a private contract with them without exceptional reasons to do so.
As for penal procedures, a hearing is conducted in accordance with Article 21 of the Administrative
Procedures Act and then agendas are discussed by the contract review committee and the
disqualification can last from one month to two years.
The contents of disqualification are registered in the Government e-Procurement System in order to
prevent the participation in biddings in the first place.
25. Do bidders have to explicitly declare their abstention from any means that could improperly influence
the procurement process or decision and, if yes, do such declarations also cover such unlawful practices by
subcontractors or other third parties?
A bid invitation contains the Special Instruction of Integrity Contract for all biddings. Bidders are
regarded as having submitted the Pledge to implement the integrity contract and the awardee has to
sign and submit the pledge before establishing a contract. The pledge states that the bidders will not
commit any unfair acts related to bidding and contract.
26. Do bidders have to disclose commissions, gratuities, or fees that have been or have to be legally paid
to individuals or sub-contractors for their services provided for instance in the preparation of a bid or the
execution of the contract?
It is not mandatory to disclose commissions, gratuities or fees that have been paid by bidders in the
preparation of a bid or the execution of the contract.
ADB/OECD Anti-Corruption Initiative for Asia and the Pacific
Thematic review on public procurement – Country information on the Republic of Korea
– 10 –
D. Accountability
Separation of responsibilities and independent scrutiny:
27. Which means are employed to avoid insulation of procurement staff and to ensure mutual control? (e.g.
rotation of officers, decisions taken/validated by more than one actor, etc.)?
The criteria for managing the positions assigned to PPS officials require the work of two years at the
same place in principle and then rotate the position.
Objectivity and fairness are ensured by;
– mutual controls by business division such as the separation of a contract division from a payment
division;
– the separation of drafting from signing;
– the determination, publication and processing of standard operating procedures and criteria; and
– the determination of important decisions by the review council, consultation body or committees that
involve NGOs.
28. Are there regular and systematic internal and external audits of procuring entities/PPOs? If yes, are
they mandatory; which bodies are in charge of this audit; are the audit reports publicly available? Are
independent actors/NGOs invited to monitor the procurement procedures and what is the setting prescribed
by law?
There are internal audits, and external ones conducted by the Audit and Inspection Board, the Office of
Government Policy Coordination, and the National Assembly.
There are also regular audits that are conducted with the interval of one or three years or irregular
audits.
External audits are mandatory.
Audit results are accessible through the Internet or to the public in written form.
The Ombudsman system or committees that involve NGOs are put in place to monitor the procurement
procedures, which is conducted by the Korean Independent Commission against Corruption, the
Ombudsman Committee, and the Audit and Inspection Board.
Review and complaint mechanisms:
29. Do your laws and regulations provide for review and complaints procedures? If yes, are they at
administrative and/or judicial levels; what is the time limit for complaint/appeal, if any? How many complaint
cases related to procurement are handled per year?
Review and complaint procedures are provided for by the Petition Act, the law on processing civil
affairs, the Arbitration Act and the Civil Litigation Act.
Complaints about international bidding can be filed in accordance with Article 28 of the Act on Contracts
to which the State is a Party. If there is complaint against the review results, it can be filed with the
International Contract Dispute Mediation Committee according to Article 29.
The complaint for the breach of the act as proscribed by Article 28 of the Act on Contracts to which the
State is a Party should be made to the principal of a central executive agency within 15 days after the
breach has occurred or within 10 days after knowing that such breach occurred.
ADB/OECD Anti-Corruption Initiative for Asia and the Pacific
Thematic review on public procurement – Country information on the Republic of Korea
– 11 –
After the International Contract Dispute Mediation Committee’s mediation is completed, it has the same
effect as reconciliation at a court, if not challenged within 15 days.
In 2004, PPS received 574 written questions, 8,921 questions over the Internet, and 52 litigations.
30. Who is entitled to initiate a complaint procedure (e.g. competing bidders, any citizen, etc.) and how are
potential informants protected against retaliation (e.g. confidentiality, anonymity)? Are the decisions of the
body handling complaints binding? What are the consequences if a complaint is proven valid (e.g. reopening
of the bidding, liquidation of damages, etc.)?
Petitions as prescribed by the Petition Act or civil complaints as prescribed by the law on processing
civil affairs can be filed by interested parties as well as the general public. In the case of international
bidding as prescribed by the Act on Contracts to which the State is a Party, complaints or petitions for
review can be filed by affected parties.
The principal of a central executive agency should review the complaint within 10 days after it was
received and take necessary measures such as correction and notify the results of the applicant. There
is no retaliation or disadvantages against the applicant. Informants are protected by maintaining their
confidentiality and anonymity, and rewards are provided to them.
When one is not satisfied with the decision for the complaint, he or she can file the petition for review. If
he or she is not satisfied with the examination of or mediation for the review, he or she can file a lawsuit
according to the Civil Litigation Act.
If the complaint is found to be legitimate, then adequate corrective measures such as re-bidding or
compensation for the damage must be provided.

Más contenido relacionado

La actualidad más candente

Draft Criminal Code and Commentary - as published Sept 2013
Draft Criminal Code and Commentary - as published Sept 2013Draft Criminal Code and Commentary - as published Sept 2013
Draft Criminal Code and Commentary - as published Sept 2013
Jane Mulcahy
 
Revised version2-Bid Rigging in Pakistan [Manila April 2015]
Revised version2-Bid Rigging in Pakistan [Manila April 2015]Revised version2-Bid Rigging in Pakistan [Manila April 2015]
Revised version2-Bid Rigging in Pakistan [Manila April 2015]
Ahmed Qadir
 
GSA Regulatory Reform Plan August 2011
GSA Regulatory Reform Plan August 2011GSA Regulatory Reform Plan August 2011
GSA Regulatory Reform Plan August 2011
Obama White House
 
Igor Munteanu, Executive Director, IDIS "Viitorul": Regulation of political p...
Igor Munteanu, Executive Director, IDIS "Viitorul": Regulation of political p...Igor Munteanu, Executive Director, IDIS "Viitorul": Regulation of political p...
Igor Munteanu, Executive Director, IDIS "Viitorul": Regulation of political p...
IDIS Viitorul
 

La actualidad más candente (20)

Untangling bureaucratic procurement processes
Untangling bureaucratic procurement processesUntangling bureaucratic procurement processes
Untangling bureaucratic procurement processes
 
Comar 101, Far 101 And Board Policy
Comar 101, Far 101 And Board PolicyComar 101, Far 101 And Board Policy
Comar 101, Far 101 And Board Policy
 
Labor regime
Labor regimeLabor regime
Labor regime
 
Hong kong Six Monthly Report Jul-Dec 2014 (UK Government)
Hong kong Six Monthly Report Jul-Dec 2014 (UK Government)Hong kong Six Monthly Report Jul-Dec 2014 (UK Government)
Hong kong Six Monthly Report Jul-Dec 2014 (UK Government)
 
Draft Criminal Code and Commentary - as published Sept 2013
Draft Criminal Code and Commentary - as published Sept 2013Draft Criminal Code and Commentary - as published Sept 2013
Draft Criminal Code and Commentary - as published Sept 2013
 
Revised version2-Bid Rigging in Pakistan [Manila April 2015]
Revised version2-Bid Rigging in Pakistan [Manila April 2015]Revised version2-Bid Rigging in Pakistan [Manila April 2015]
Revised version2-Bid Rigging in Pakistan [Manila April 2015]
 
GSA Regulatory Reform Plan August 2011
GSA Regulatory Reform Plan August 2011GSA Regulatory Reform Plan August 2011
GSA Regulatory Reform Plan August 2011
 
A newsletter of the CPLR No6 (March 2018)
A newsletter of the CPLR No6 (March 2018)A newsletter of the CPLR No6 (March 2018)
A newsletter of the CPLR No6 (March 2018)
 
Public procurement act_2063
Public procurement act_2063Public procurement act_2063
Public procurement act_2063
 
1 1 - 1-4 introduction of foreign investment law system in china
1 1 - 1-4 introduction of foreign investment law system in china1 1 - 1-4 introduction of foreign investment law system in china
1 1 - 1-4 introduction of foreign investment law system in china
 
HRB 68448 G20 anti corruption working group germany
HRB 68448 G20 anti corruption working group germanyHRB 68448 G20 anti corruption working group germany
HRB 68448 G20 anti corruption working group germany
 
MONEY FOR POLITICAL PARTIES
MONEY FOR POLITICAL PARTIESMONEY FOR POLITICAL PARTIES
MONEY FOR POLITICAL PARTIES
 
Article on Pricing in International Transaction
Article on Pricing in International TransactionArticle on Pricing in International Transaction
Article on Pricing in International Transaction
 
Le tran vietnam labor law review (aug - sep 2018).final.en
Le tran vietnam labor law review (aug - sep 2018).final.enLe tran vietnam labor law review (aug - sep 2018).final.en
Le tran vietnam labor law review (aug - sep 2018).final.en
 
Department of Justice Preliminary Regulatory Reform Plan
Department of Justice Preliminary Regulatory Reform PlanDepartment of Justice Preliminary Regulatory Reform Plan
Department of Justice Preliminary Regulatory Reform Plan
 
Investment declaration eng
Investment declaration engInvestment declaration eng
Investment declaration eng
 
China's Two Sessions 2018
China's Two Sessions 2018China's Two Sessions 2018
China's Two Sessions 2018
 
Planning for the Regional Public Procurement Market: The Legal Perspective - ...
Planning for the Regional Public Procurement Market: The Legal Perspective - ...Planning for the Regional Public Procurement Market: The Legal Perspective - ...
Planning for the Regional Public Procurement Market: The Legal Perspective - ...
 
Dipp Consolidated Circular Issues
Dipp Consolidated Circular IssuesDipp Consolidated Circular Issues
Dipp Consolidated Circular Issues
 
Igor Munteanu, Executive Director, IDIS "Viitorul": Regulation of political p...
Igor Munteanu, Executive Director, IDIS "Viitorul": Regulation of political p...Igor Munteanu, Executive Director, IDIS "Viitorul": Regulation of political p...
Igor Munteanu, Executive Director, IDIS "Viitorul": Regulation of political p...
 

Destacado

Chalengous pic
Chalengous picChalengous pic
Chalengous pic
harshita84
 
Defcon 16-pilosov-kapela
Defcon 16-pilosov-kapelaDefcon 16-pilosov-kapela
Defcon 16-pilosov-kapela
Hai Nguyen
 
Ijcsi 9-4-2-457-462
Ijcsi 9-4-2-457-462Ijcsi 9-4-2-457-462
Ijcsi 9-4-2-457-462
Hai Nguyen
 

Destacado (20)

Csd6059
Csd6059Csd6059
Csd6059
 
Spoliation Sanctions by Circuit Courts (printable chart)
Spoliation Sanctions by Circuit Courts (printable chart)Spoliation Sanctions by Circuit Courts (printable chart)
Spoliation Sanctions by Circuit Courts (printable chart)
 
B com 2014 | Performance Marketing: saper sfruttare la Long Tail. Il caso di ...
B com 2014 | Performance Marketing: saper sfruttare la Long Tail. Il caso di ...B com 2014 | Performance Marketing: saper sfruttare la Long Tail. Il caso di ...
B com 2014 | Performance Marketing: saper sfruttare la Long Tail. Il caso di ...
 
E-learning eenrichtingsverkeer?
E-learning eenrichtingsverkeer? E-learning eenrichtingsverkeer?
E-learning eenrichtingsverkeer?
 
Disable your internet access
Disable your internet accessDisable your internet access
Disable your internet access
 
Droom of nachtmerrie
Droom of nachtmerrieDroom of nachtmerrie
Droom of nachtmerrie
 
A powerpoint about alan cumming
A powerpoint about alan cummingA powerpoint about alan cumming
A powerpoint about alan cumming
 
Chalengous pic
Chalengous picChalengous pic
Chalengous pic
 
B com 2014 | Il mobile marketing come fenomeno abilitante per comprendere il ...
B com 2014 | Il mobile marketing come fenomeno abilitante per comprendere il ...B com 2014 | Il mobile marketing come fenomeno abilitante per comprendere il ...
B com 2014 | Il mobile marketing come fenomeno abilitante per comprendere il ...
 
B com 2014 | Strategie di content marketing per un engagement multicanale_Pao...
B com 2014 | Strategie di content marketing per un engagement multicanale_Pao...B com 2014 | Strategie di content marketing per un engagement multicanale_Pao...
B com 2014 | Strategie di content marketing per un engagement multicanale_Pao...
 
MoneyTrac CPG: Adding a new debit credit card
MoneyTrac CPG: Adding a new debit credit cardMoneyTrac CPG: Adding a new debit credit card
MoneyTrac CPG: Adding a new debit credit card
 
Defcon 16-pilosov-kapela
Defcon 16-pilosov-kapelaDefcon 16-pilosov-kapela
Defcon 16-pilosov-kapela
 
Kahn Help for ACT Math II
Kahn Help for ACT Math IIKahn Help for ACT Math II
Kahn Help for ACT Math II
 
Enmat v2.1 presentation Envantage ltd Jan 2014
Enmat v2.1 presentation Envantage ltd Jan 2014Enmat v2.1 presentation Envantage ltd Jan 2014
Enmat v2.1 presentation Envantage ltd Jan 2014
 
B com 2013 | Intershop 7, flessibilità tecnologica per un mercato in divenire...
B com 2013 | Intershop 7, flessibilità tecnologica per un mercato in divenire...B com 2013 | Intershop 7, flessibilità tecnologica per un mercato in divenire...
B com 2013 | Intershop 7, flessibilità tecnologica per un mercato in divenire...
 
Whitepaper: Legal Holds & Data Preservation 2014
Whitepaper: Legal Holds & Data Preservation 2014Whitepaper: Legal Holds & Data Preservation 2014
Whitepaper: Legal Holds & Data Preservation 2014
 
B com 2013 | Il digitale a servizio dell'internazionalizzazione del Made in I...
B com 2013 | Il digitale a servizio dell'internazionalizzazione del Made in I...B com 2013 | Il digitale a servizio dell'internazionalizzazione del Made in I...
B com 2013 | Il digitale a servizio dell'internazionalizzazione del Made in I...
 
Ijcsi 9-4-2-457-462
Ijcsi 9-4-2-457-462Ijcsi 9-4-2-457-462
Ijcsi 9-4-2-457-462
 
120 i143
120 i143120 i143
120 i143
 
5 goede redenen om verplichte bijscholing online te doen
5 goede redenen om verplichte bijscholing online te doen5 goede redenen om verplichte bijscholing online te doen
5 goede redenen om verplichte bijscholing online te doen
 

Similar a 35054148

OVERVIEW OF PUBLIC PROCUREMENT UNDER THE PUBLIC PROCUREMENT[23058430092159162...
OVERVIEW OF PUBLIC PROCUREMENT UNDER THE PUBLIC PROCUREMENT[23058430092159162...OVERVIEW OF PUBLIC PROCUREMENT UNDER THE PUBLIC PROCUREMENT[23058430092159162...
OVERVIEW OF PUBLIC PROCUREMENT UNDER THE PUBLIC PROCUREMENT[23058430092159162...
UbongAkpekong1
 
Federal Acquisitionr Regulatory Reform Plan August 2011
Federal Acquisitionr Regulatory Reform Plan August 2011Federal Acquisitionr Regulatory Reform Plan August 2011
Federal Acquisitionr Regulatory Reform Plan August 2011
Obama White House
 
Public procurement regularity authority (ppra)
Public procurement regularity authority (ppra)Public procurement regularity authority (ppra)
Public procurement regularity authority (ppra)
TaseerBaloch1
 
Public procurement regularity authority (ppra)
Public procurement regularity authority (ppra)Public procurement regularity authority (ppra)
Public procurement regularity authority (ppra)
TaseerBaloch1
 

Similar a 35054148 (20)

Frequently-asked-questions-about-ra-9184
Frequently-asked-questions-about-ra-9184Frequently-asked-questions-about-ra-9184
Frequently-asked-questions-about-ra-9184
 
OVERVIEW OF PUBLIC PROCUREMENT UNDER THE PUBLIC PROCUREMENT[23058430092159162...
OVERVIEW OF PUBLIC PROCUREMENT UNDER THE PUBLIC PROCUREMENT[23058430092159162...OVERVIEW OF PUBLIC PROCUREMENT UNDER THE PUBLIC PROCUREMENT[23058430092159162...
OVERVIEW OF PUBLIC PROCUREMENT UNDER THE PUBLIC PROCUREMENT[23058430092159162...
 
Federal Acquisitionr Regulatory Reform Plan August 2011
Federal Acquisitionr Regulatory Reform Plan August 2011Federal Acquisitionr Regulatory Reform Plan August 2011
Federal Acquisitionr Regulatory Reform Plan August 2011
 
11 Public procurement policy in Republic of Moldova_English
11 Public procurement policy in Republic of Moldova_English11 Public procurement policy in Republic of Moldova_English
11 Public procurement policy in Republic of Moldova_English
 
Public procurement regularity authority (ppra)
Public procurement regularity authority (ppra)Public procurement regularity authority (ppra)
Public procurement regularity authority (ppra)
 
Public procurement regularity authority (ppra)
Public procurement regularity authority (ppra)Public procurement regularity authority (ppra)
Public procurement regularity authority (ppra)
 
20160826-IRR-RA-9184-procurement-reform (1).pdf
20160826-IRR-RA-9184-procurement-reform (1).pdf20160826-IRR-RA-9184-procurement-reform (1).pdf
20160826-IRR-RA-9184-procurement-reform (1).pdf
 
Presentation on theme.docx
Presentation on theme.docxPresentation on theme.docx
Presentation on theme.docx
 
Salient Features_RA 9184.pptx
Salient Features_RA 9184.pptxSalient Features_RA 9184.pptx
Salient Features_RA 9184.pptx
 
Ra9184 rules
Ra9184 rulesRa9184 rules
Ra9184 rules
 
THE 2016 REVISED IMPLEMENTING RULES AND REGULATIONS OF.pptx
THE 2016 REVISED IMPLEMENTING RULES   AND REGULATIONS OF.pptxTHE 2016 REVISED IMPLEMENTING RULES   AND REGULATIONS OF.pptx
THE 2016 REVISED IMPLEMENTING RULES AND REGULATIONS OF.pptx
 
2016 RA 9184 REVISED
2016 RA 9184 REVISED2016 RA 9184 REVISED
2016 RA 9184 REVISED
 
Revised irr.ra9184 2009
Revised irr.ra9184 2009Revised irr.ra9184 2009
Revised irr.ra9184 2009
 
Volume 1. intro
Volume 1. introVolume 1. intro
Volume 1. intro
 
Vietnam - The World Bank is asking Duane Morris about Doing Business and Gove...
Vietnam - The World Bank is asking Duane Morris about Doing Business and Gove...Vietnam - The World Bank is asking Duane Morris about Doing Business and Gove...
Vietnam - The World Bank is asking Duane Morris about Doing Business and Gove...
 
Mrtp cci
Mrtp cciMrtp cci
Mrtp cci
 
Constitutional aspect of comp. law
Constitutional aspect of comp. lawConstitutional aspect of comp. law
Constitutional aspect of comp. law
 
governmentprocurementactww-180625195256.pptx
governmentprocurementactww-180625195256.pptxgovernmentprocurementactww-180625195256.pptx
governmentprocurementactww-180625195256.pptx
 
Session 3_Luca Fontana.pdf
Session 3_Luca Fontana.pdfSession 3_Luca Fontana.pdf
Session 3_Luca Fontana.pdf
 
Government procurement Act RA 9184
Government procurement Act  RA 9184Government procurement Act  RA 9184
Government procurement Act RA 9184
 

Más de Hai Nguyen

Sp 29 two_factor_auth_guide
Sp 29 two_factor_auth_guideSp 29 two_factor_auth_guide
Sp 29 two_factor_auth_guide
Hai Nguyen
 
Session 7 e_raja_kailar
Session 7 e_raja_kailarSession 7 e_raja_kailar
Session 7 e_raja_kailar
Hai Nguyen
 
Securing corporate assets_with_2_fa
Securing corporate assets_with_2_faSecuring corporate assets_with_2_fa
Securing corporate assets_with_2_fa
Hai Nguyen
 
Scc soft token datasheet
Scc soft token datasheetScc soft token datasheet
Scc soft token datasheet
Hai Nguyen
 
Rsa two factorauthentication
Rsa two factorauthenticationRsa two factorauthentication
Rsa two factorauthentication
Hai Nguyen
 
Quest defender provides_secure__affordable_two-factor_authentication_for_okla...
Quest defender provides_secure__affordable_two-factor_authentication_for_okla...Quest defender provides_secure__affordable_two-factor_authentication_for_okla...
Quest defender provides_secure__affordable_two-factor_authentication_for_okla...
Hai Nguyen
 
Pg 2 fa_tech_brief
Pg 2 fa_tech_briefPg 2 fa_tech_brief
Pg 2 fa_tech_brief
Hai Nguyen
 
Ouch 201211 en
Ouch 201211 enOuch 201211 en
Ouch 201211 en
Hai Nguyen
 
N ye c-rfp-two-factor-authentication
N ye c-rfp-two-factor-authenticationN ye c-rfp-two-factor-authentication
N ye c-rfp-two-factor-authentication
Hai Nguyen
 
Multiple credentials-in-the-enterprise
Multiple credentials-in-the-enterpriseMultiple credentials-in-the-enterprise
Multiple credentials-in-the-enterprise
Hai Nguyen
 
Mobile authentication
Mobile authenticationMobile authentication
Mobile authentication
Hai Nguyen
 
Identity cues two factor data sheet
Identity cues two factor data sheetIdentity cues two factor data sheet
Identity cues two factor data sheet
Hai Nguyen
 
Hotpin datasheet
Hotpin datasheetHotpin datasheet
Hotpin datasheet
Hai Nguyen
 
Ds netsuite-two-factor-authentication
Ds netsuite-two-factor-authenticationDs netsuite-two-factor-authentication
Ds netsuite-two-factor-authentication
Hai Nguyen
 
Datasheet two factor-authenticationx
Datasheet two factor-authenticationxDatasheet two factor-authenticationx
Datasheet two factor-authenticationx
Hai Nguyen
 
Cryptomathic white paper 2fa for banking
Cryptomathic white paper 2fa for bankingCryptomathic white paper 2fa for banking
Cryptomathic white paper 2fa for banking
Hai Nguyen
 
Citrix sb 0707-lowres
Citrix sb 0707-lowresCitrix sb 0707-lowres
Citrix sb 0707-lowres
Hai Nguyen
 

Más de Hai Nguyen (20)

Sp 29 two_factor_auth_guide
Sp 29 two_factor_auth_guideSp 29 two_factor_auth_guide
Sp 29 two_factor_auth_guide
 
Sms based otp
Sms based otpSms based otp
Sms based otp
 
Session 7 e_raja_kailar
Session 7 e_raja_kailarSession 7 e_raja_kailar
Session 7 e_raja_kailar
 
Securing corporate assets_with_2_fa
Securing corporate assets_with_2_faSecuring corporate assets_with_2_fa
Securing corporate assets_with_2_fa
 
Scc soft token datasheet
Scc soft token datasheetScc soft token datasheet
Scc soft token datasheet
 
Rsa two factorauthentication
Rsa two factorauthenticationRsa two factorauthentication
Rsa two factorauthentication
 
Quest defender provides_secure__affordable_two-factor_authentication_for_okla...
Quest defender provides_secure__affordable_two-factor_authentication_for_okla...Quest defender provides_secure__affordable_two-factor_authentication_for_okla...
Quest defender provides_secure__affordable_two-factor_authentication_for_okla...
 
Pg 2 fa_tech_brief
Pg 2 fa_tech_briefPg 2 fa_tech_brief
Pg 2 fa_tech_brief
 
Ouch 201211 en
Ouch 201211 enOuch 201211 en
Ouch 201211 en
 
N ye c-rfp-two-factor-authentication
N ye c-rfp-two-factor-authenticationN ye c-rfp-two-factor-authentication
N ye c-rfp-two-factor-authentication
 
Multiple credentials-in-the-enterprise
Multiple credentials-in-the-enterpriseMultiple credentials-in-the-enterprise
Multiple credentials-in-the-enterprise
 
Mobile authentication
Mobile authenticationMobile authentication
Mobile authentication
 
Identity cues two factor data sheet
Identity cues two factor data sheetIdentity cues two factor data sheet
Identity cues two factor data sheet
 
Hotpin datasheet
Hotpin datasheetHotpin datasheet
Hotpin datasheet
 
Gambling
GamblingGambling
Gambling
 
Ds netsuite-two-factor-authentication
Ds netsuite-two-factor-authenticationDs netsuite-two-factor-authentication
Ds netsuite-two-factor-authentication
 
Datasheet two factor-authenticationx
Datasheet two factor-authenticationxDatasheet two factor-authenticationx
Datasheet two factor-authenticationx
 
Cryptomathic white paper 2fa for banking
Cryptomathic white paper 2fa for bankingCryptomathic white paper 2fa for banking
Cryptomathic white paper 2fa for banking
 
Citrix sb 0707-lowres
Citrix sb 0707-lowresCitrix sb 0707-lowres
Citrix sb 0707-lowres
 
Bi guardotp
Bi guardotpBi guardotp
Bi guardotp
 

35054148

  • 1. ADB/OECD Anti-Corruption Initiative for Asia and the Pacific The Secretariat Jak Jabes, Director, Governance and Regional Co-operation, ADB jjabes@adb.org phone: +63 2 632 5749, fax: +63 2 636 2193 Frédéric Wehrlé, Co-ordinator, Anti-Corruption Initiatives, Anti-Corruption Division, OECD frederic.wehrle@oecd.org phone: +33 1 4524 1855, fax: +33 1 4430 6307 Anti-corruption policies in Asia and the Pacific: Thematic review on provisions and practices to curb corruption in public procurement Self-assessment report Korea Identifying reform needs, assessing progress and evaluating the effectiveness of anti-corruption policies and practices are central principles enshrined in the ADB/OECD Initiative and its Action Plan. In this context, the present self-assessment report from Korea was prepared as background to the Initiative’s thematic review exercise on measures to curb corruption in public procurement in the Asia-Pacific region. This thematic review on public procurement was initiated in reaction to the findings of the Initiative’s 2003-2004 in-depth analysis of the legal and institutional anti-corruption frameworks of the Action Plan’s then 21 endorsing countries against the standards of this Plan (“Anti-Corruption Policies in Asia and the Pacific – the legal and institutional frameworks”, November 2004). In this study, public procurement was identified as one of the areas requiring particular attention in the Asia and Pacific region and where consequently the Initiative’s Steering Group had a vital interest to promote reform. With this aim, the group agreed to pursue analytical work on corruption in public procurement through a thorough review of relevant existing policies, practices and rules so as to assist participating governments in better understanding the corruption risks inherent in their countries’ institutional settings and procurement practices. This thematic review further seeks to assess how countries translate into practice their commitment made under the Action Plan to curb corruption in public procurement. Eventually, the review’s findings will provide governments with an analytical framework to design policies and procedures that ensure greater transparency and integrity in public procurement and to identify priorities for reform in this respect. In line with the Action Plan’s principle of self-assessment, the review is conducted on the basis of information provided by participating countries in reply to a questionnaire specifically prepared for this purpose by the ADB/OECD Initiative. The present document represents the replies submitted by Korea in this framework. Further information on the exercise, on other participating countries and on the analysis’ outcome is available at the Initiative’s website at http://www1.oecd.org/daf/asiacom/stocktaking.htm#trpp.
  • 2. ADB/OECD Anti-Corruption Initiative for Asia and the Pacific Thematic review on public procurement – Country information on the Republic of Korea – 2 – A. General framework Legal and organizational framework: 1. Please list and briefly describe laws and regulations related to government procurement, including those that give exemption to the standard government procurement rules. Where available, please attach a copy or indicate an internet-site for download of these regulations, if possible in English language. Ensure to include secondary legislation, rules and procedures. Also, please indicate relevant international or regional agreements 1 that your country is committed under, including its level of involvement (e.g. signature, ratification, implementation). Law and Regulation Related to Government Procurement a. The Government Procurement Act determines matters necessary to operate and manage the procurement business for its efficient performance, which is conducted by the Public Procurement Service as a central procuring agency. Under the act lie the enforcement decree and the rules related to the procurement business. b. The Act on Contracts to which the State is a Party determines basic matters regarding contracts to which the government is a party. Under the act lies the enforcement decree and rules related to contracts to which the government is a party. Special Provisions of the Enforcement Decree of the Act on Contracts to which the State is a Party for specific procurement determines special provisions regarding the enforcement decree of the act on contracts to which the state is a party when conducting international bids in accordance with Article 4 of the Act on Contracts to which the State is a Party in order to implement multilateral or bilateral government procurement agreements such as the agreement prepared in Marrakech on April 15, 1994 which the government has established or acceded to. Under these provisions lie the Special Enforcement Rules of the Act on Contracts to which the State is a Party. There are also Special Provisions of the Enforcement Decree of the Act on Contracts to which the State is a Party for the procurement of specific goods, which determines special provisions of the enforcement decree of the act on contracts to which the state is a party in conducting procurement of goods by means of the contract through international bidding. Under these provisions lie Special Rules on Conducting the Contracting Job for the Procurement of Specific Goods. c. The Local Finance Act determines basic principles on the finance and accounting for local autonomies. It stipulates contracts in Article 7, and matters other than the ones determined in this Act and other regulations that are subject to the Act on Contracts to which the State is a Party. Under this act lies the Enforcement Decree for the Local Finance Act. d. The Framework Act on the Management of Government-Invested Institutions determines basic matters regarding autonomy and accountability in the management of government-invested institutions. Under this act lie the accounting rules on government-invested institutions, which regulate accounting, standards of contracts and procedures and the limitation on the participation in bids for government-invested institutions. Matters that are not regulated in this rule are governed by the Act on Contracts to which the State is a Party. 1 e.g. APEC Non-Binding Principles on Government Procurement; WTO Agreement on Government Procurement; etc.
  • 3. ADB/OECD Anti-Corruption Initiative for Asia and the Pacific Thematic review on public procurement – Country information on the Republic of Korea – 3 – The sites where regulations related to government procurement can be downloaded: Korean text: – www.g2b.go.kr (in the section of Regulation Information under Customer Assistance) – www.moleg.go.kr English text: www.klri.re.kr/project/emain.nsf As for the involvement of commitment to international or regional agreements – The WTO Agreement on Government Procurement – The OECD Convention on the Bribery of Foreign Public Officials – The Korea-Chile Free Trade Agreement (FTA) has been implemented. – The Korea-Singapore FTA has been signed. 2. Please explain the repartition of tasks and responsibilities in the procurement process among centralized, decentralized and specialized authorities (in particular: design of policies and standards; capacity building; definition of needs and terms of individual tenders; execution of different procurement stages from advertising to contract awarding; dispute resolution; control of the fulfillment of the terms and conditions by the contractor). – The Public Procurement Service (PPS), the central procuring agency, conducts the procurement business under Article 3 of the Government Procurement Act. As for the procedures and scope of procurement of goods, which is regulated in Article 14 of the Government Procurement Act, the principal of an end-user organization should make a purchase and supply the request to the PPS Administrator when need arises. It, however, may directly purchase the goods according to the exception of Article 14. – The end-user organization can submit its opinions on the specifications and conditions for participation in bids when making a procurement request, which is finally determined by the PPS Administrator and then publicized for bid invitation. – As for the procedures and scope of works, which is regulated in Article 15 of the Enforcement Decree of the Government Procurement Act, the head of an end-user organization should make a request for a works contract to the PPS Administrator regarding matters above a certain amount. They can also make a contract request to the PPS Administrator if necessary, even in cases where it can directly establish a contract for public works. Construction designs such as drawings and specifications are prepared by an end-user organization, and are subject to general contract conditions as determined by the Minister of Finance and Economy. As for specific conditions, however, the PPS Administrator consults with the end-user organization and then determines them. 3. Is procurement of goods governed by the same procedures as procurement of services? There is no difference between goods and services in procurement procedures. 4. Does the procurement law establish a Public Procurement Office (PPO)? Is the PPO appropriately staffed against its mandate? In this context, please state the total number of staff involved in public procurement country-wide. Are the procurement entities/PPO provided with adequate financial resources for the execution of their tasks? The procurement law establishes the Public Procurement Service as a central procuring agency, which conducts the procurement business according to the Government Procurement Act. PPS has approximately 950 employees. PPS receives procurement commissions from its end-users to conduct procurement business.
  • 4. ADB/OECD Anti-Corruption Initiative for Asia and the Pacific Thematic review on public procurement – Country information on the Republic of Korea – 4 – 5. Please name the sectors, areas or conditions subject to particular procurement rules (if applicable, e.g. military; local governments; state owned enterprises; urgency). As for procurement law that is applicable to each organization, be it a national organization, local autonomy or government-invested institution, see Answer 1. There is a Defense Procurement Agency as a procuring agency of defense materials, which procures according to the Act on Contracts to which the State is a Party. Procurement policies and practices: 6. Do model tender documents exist (e.g. handbooks, model forms, model contracts, etc)? If yes, is their use mandatory, and do they contain a specific anti-corruption clause? The law related to government procurement includes standard bid forms, the use of which is mandatory. A standard bid form includes anti-corruption clauses. The clauses stipulate that bidders submit their bids in accordance with bid instructions and bid instructions provide for debarred suppliers’ limitation in participating in bids. Aside from the bid instructions, the Special Instruction on Integrity Bidding and Contract applies to all bids. 7. Please provide the latest available economy-wide annual total numbers and values of purchases, with breakdown a) by sector and b) by type of procurement. In this context, please describe the procurement types foreseen by law (e.g. sealed tender, direct purchase; limited tendering) and the policy of your Government towards these types. The procurement volume in 2003 reached 74 trillion won: 33.7 trillion won for national organizations; 19.3 trillion won for local autonomies; 12.1 trillion won for government-invested institutions; 8.2 trillion won for special legal entities such as government-funded organizations; and 9 trillion won for local public corporations. It is difficult to confirm the procurement volume by type of procurement, though the principle of the procurement type is for open competition in the Act on Contracts to which the State is a Party. However, procurement can be made through the use of limited competition, nomination, and private contract according to the Presidential Decree when such method is necessary, considering the objective, nature and size of the contract, as is suggested in Article 7 of the Act on Contracts to which the State is a Party. 8. Please explain under which conditions pre-selection procedures are conducted. According to Article 13 of the Enforcement Decree of the Act on Contracts to which the State is a Party, as for works determined by the Ministry of Finance and Economy’s order, applicants are examined for the review of qualifications prior to the bid, and then eligible ones can participate in a competitive bid once selected and are notified of their results. When it is necessary to examine bidder’s qualifications in order to participate in bids, PPS requires detailed examination criteria in accordance with the examination criteria determined by the Minister of Finance and Economy which should then be accessible by hopeful bidders before they participate in the bid. 9. If your country is currently engaged in or planning a major reform of its procurement system, please briefly state the scope and objectives of this reform. Korea acceded to the WTO Agreement on Government Procurement in 1994 and revised the entire government contract law in 1995.
  • 5. ADB/OECD Anti-Corruption Initiative for Asia and the Pacific Thematic review on public procurement – Country information on the Republic of Korea – 5 – On Sept. 30, 2002, PPS adopted the Government e-Procurement System (GEPS), and made it mandatory to publicize bid invitations by all public institutions in GEPS. The entire procurement process is processed electronically in terms of bid execution, awardee selection, contract establishment through to payment. Starting from 2005, PPS introduced multiple award methods similar to the Framework Agreement of Britain, and the Multiple Award Schedule of the USA in order to provide a greater range of choices to end-user organizations. B. Transparency and Fairness Transparency of general procurement policies and regulations: 10. Are the existing laws, regulations and policy guidelines on public procurement publicly available and, if yes, where/how? The laws, regulations and guidelines on public procurement are available in the Government e- Procurement System and are accessible via the Internet, www.g2b.go.kr. The Republic of Korea’s laws, including ones on government procurement, are available in the Ministry of Legislation’s homepage, www.moleg.go.kr 11. In your country, do certain territorial entities or institutions establish lists of eligible contractors (sometimes called “white-lists”)? If yes, please explain the criteria for a company to be included in or excluded from this list, and what use is made of such lists. Korea has operated a competitive system by means of an eligible bidder list for public works since 1975. The purpose of the system is to equally divide construction projects between big, medium-sized and small enterprises according to their capability. Construction companies are categorized into seven levels based on their performance capability amount, which is announced by the Korean Construction Association every year. Each construction company is entitled to participate in bids for projects that are allocated according to their level. 12. Is a bid security and/or a performance guarantee required from the bidder? What are the procedures for advertisement of procurement opportunities? The laws on procurement require a payment of 5% of the contract amount for bid security and 10% for performance bond in principle. However, the bid security payment is exempted before the bidding takes place, except for special circumstances. Contents on whether and how to pay a bid security are contained in the bid invitation. Transparency of procurement opportunities: 13. Describe where and how tender opportunities are published, including if their publication is mandatory or depends on certain criteria (if so, please list)? Please state if a fee has to be paid to receive tendering documents and – if yes – how this fee is fixed and whether other processing fees apply. Please briefly explain whether your country allows adequate and reasonable time for interested suppliers to prepare and submit responsive bids. All bid invitations by public institutions must be made in the Government e-Procurement System.
  • 6. ADB/OECD Anti-Corruption Initiative for Asia and the Pacific Thematic review on public procurement – Country information on the Republic of Korea – 6 – There are no fees to participate in a bid in most cases, but some local autonomies collect them. The laws on procurement stipulate the bid invitation period, considering the time needed for preparing a bid. This must be honored by public institutions. 14. Are selection and award criteria prescribed by law? If yes, are they prescribed in an exclusive manner? Please name these criteria a) for procurement of goods, and b) for procurement of services (e.g. technical requirements, qualification of the bidder, evaluated price, expertise/experience, etc.) and those that are explicitly excluded (e.g. nationality of the bidder or other affinity, etc.). Is the description of these criteria in the tender documentation mandatory? The award criteria are stipulated in Paragraph 2 of Article 10 of the Enforcement Decree of the Act on Contracts to which the State is a Party, including; – those who are capable of fulfilling a contract and have submitted the lowest price; – those who have submitted the most advantageous bid to the government according to evaluation criteria mentioned in bid documents such as bid invitations; and – those who have submitted the most appropriate bid, compared to the special standards mentioned in the Presidential Decree, taking into consideration the nature and scope of the contract. Contract methods, qualifications to participate in a bid, contents to be included in a bid, bid evaluation and award criteria are subject to laws related to procurement, and should be included in bid documents such as the bid invitation concerned. Bidding methods and bid nullification are regulated in Article 42 or 44 of the Enforcement Rules, the Act on Contracts to which the State is a Party. When nullifying the bid, a contracting official must notify the bidder of the reason. Transparency of contract evaluation and award procedures: 15. What is the procedure if none of the bids or too few – relative to a prescribed limit – fulfill the technical requirements as defined in the call for tender (e.g. reopening of the bid, negotiations, etc.)? Do you keep a register of all bids received? Two or more valid bids comprise a competitive bidding according to Article 11 of the Enforcement Decree of the Act on Contracts to which the State is a Party. – When there are not two or more valid bidders or awardees, re-bidding can be made again at the same place according to Paragraph 1, Article 20, the Enforcement Decree of the Act on Contracts to which the State is a Party. – When there are no bidders or awardees or the awardee did not establish a contract, the bid can be invited again according to Paragraph 2, Article 20, the Enforcement Decree of the Act on Contracts to which the State is a Party. When the bid results show that there was only one bidder and it is apparent in the case of bids to be invited again that there will be only one qualified bidder, and when the re-invited bidding showed that there were no bidders or awardee, the procurement can be made by a private contract according to Article 27 of the Enforcement Decree of the Act on Contracts to which the State is a Party. Bidding and contracting documents are maintained by the owner institution for five years according to the law concerning the management of records for public institutions.
  • 7. ADB/OECD Anti-Corruption Initiative for Asia and the Pacific Thematic review on public procurement – Country information on the Republic of Korea – 7 – 16. Where and how are actions and decisions in the procurement process recorded? How long and where are these records preserved, and who can access this information? Actions and decisions in the procurement process are recorded and managed in written form by the owner institution. With the introduction of the Government e-Procurement System made on Sept. 30, 2002 and its growing use, there are a growing number of e-documents managed in this system. Documents related to bidding and contracts are preserved by the owner institution for five years according to the law on the management of records by public institutions. They are also accessible to the public according to the law on publicizing the information on public institutions. All contents on bid invitations, e-bid results and award results using the Government e- Procurement System are accessible in real time through the Internet. 17. How and to whom is the final decision on awarding the tender disclosed? Do reasons for the selection of the winning bidder have to be stated? Are post-awarding negotiations allowed and, if yes, under what conditions? All contents on bid invitations, e-bid results and award results using the Government e-Procurement System are accessible in real time through the Internet. Since awarding is subject to criteria determined in the bid invitation, the reason for the selection of the awardee is not separately stated. In the case of negotiated contracts in accordance with Article 43 of the Enforcement Decree of the Act on Contracts to which the State is a Party, negotiations are conducted before selecting an awardee. In this case, the criteria and procedures required for establishing a contract must be determined previously and must be accessible to negotiating bidders. 18. Are framework contracts allowed? If yes, what measures are taken to control against corrupt or unnecessary demands? In order to offer a wider choice for end-user organizations, Korea has adopted a multiple award method similar to a framework contract, starting from 2005. In the case of the Multiple Award Schedule, PPS has operated the price review council with the involvement of external members to enhance transparency and fairness since Jan. 19, 2005. The council reviews major agendas related to determining price. C. Integrity Integrity of procurement personnel: 19. Do codes of ethics or similar instruments exist that explicitly apply to procurement personnel and entities? If yes, do they specifically address corruption risks, and do they contain conflict of interest provisions (e.g. provisions making mandatory the declaration of personal interests by agents and buyers)? To establish a law-abiding mindset for public officials and discipline in the public service, PPS has enacted and implemented the Procurement Service Charter, the Code of Conduct for Safeguarding Integrity for PPS officials, criteria for determining the level of sanctions on PPS officials, and Integrity Contract, as government guidelines. PPS is focusing on creating a working environment to eradicate and prevent corruption through the detection and elimination of the causes of corruption by exploring ways to attain anti-corruption measures.
  • 8. ADB/OECD Anti-Corruption Initiative for Asia and the Pacific Thematic review on public procurement – Country information on the Republic of Korea – 8 – By operating the Procurement Complaint Center on the PPS homepage to impose controls by citizens in order to prevent corruption, PPS receives and processes reports of irregularities and the cases of acts of overt kindness or unfriendliness. The Kickbacks Reporting Center in the PPS’ EDMS bulletin board serves as a reporting center for the informant as well as others. 20. Does your country provide for specific training for procurement personnel that include integrity issues? Please list manuals or policy guidelines that might exist to clarify procurement procedures and principles to procurement personnel (if existing please attach a copy or internet-address for download). In order to establish an image of integrity for procurement officials, PPS conducts one or more special training sessions to implement a code of conduct for PPS officials every year and checks whether or not it is being honored every month. To strengthen anti-corruption education and promotion, PPS has allocated anti-corruption training within the professional procurement education course in which procurement officials in all levels of government participate and utilize professional instructors from the Korean Independent Commission against Corruption when conducting education on a regular basis. All data related to procurement such as bidding and contract data, product information, and relevant laws are registered on the PPS homepage, www.pps.go.kr in detail, which are used by procurement personnel at home and abroad. 21. Is procurement personnel required – and if yes by what regulation and to what institution – to report attempts by suppliers to undermine the impartiality and independence of action by offering bribes, benefits or other forms of inducement? As for illegal activities such as the offering of bribes by the supplier, Article 18 of the Code of Conduct for Safeguarding the Integrity for PPS Officials requires such acts to be reported to the Code of Conduct Officer or Audit Officer. Cases involving the PPS administrator, however, should be directly reported to the Korean Independent Commission against Corruption. 22. Which penal and/or administrative sanctions are applicable to procurement personnel for accepting or soliciting bribes? Are public officials liable for the economic damage that the procuring entity suffers? What is the policy that applies to procurement personnel for accepting or soliciting small facilitation payments such as gifts, benefits, hospitality (e.g. outright forbidden, accepted under certain circumstances, etc.; please explain). Public officials who are found to be involved in the acceptance or solicitation of bribes are punished in accordance with the Penal Code (Article 129~132 and 134~135) or according to Paragraph 1 or 2 of Article 2 of the Act on Increased Penalty for Specific Crimes in the case of bribes exceeding 50 million won. They will receive disciplines according to the criteria for determining the level of discipline on corrupt PPS officials. When someone has incurred economic damages on the government, he or she shall offer compensatory responsibility to the government, and procedures for this case are regulated in the Act on Responsibility of Accounting Employees. The Code of Conduct for Safeguarding Integrity for PPS Officials prevents work-related people, businesses, and work-related public officials from receiving money, property, gifts or entertainment in principle. However, Article 14 of the code stipulates a range of kickbacks that are exceptions to this Article.
  • 9. ADB/OECD Anti-Corruption Initiative for Asia and the Pacific Thematic review on public procurement – Country information on the Republic of Korea – 9 – Integrity of bidders and suppliers: 23. Which penal sanctions are applied to a bidding company as a legal person and to its employees if it is found guilty of corruption related to the bidding procedure? Is the company liable for the economic damage that the procuring entity suffers? If a bidding business or its employees are found guilty of corruption related to the bidding procedure, they are subject to imprisonment of five years or less or fines of 20 million won or less according to Article 133 of the Penal Code. As for economic damage on the government incurred by a business because of its illegal activities, the government can cancel the contract with the business according to Article 75 of the Enforcement Decree of the Act on Contracts to which the State is a Party, and the business shall offer compensatory damage according to Article 750 of the Civil Law. 24. Do your country’s laws and regulations permit authorities to suspend, temporarily or permanently, from competition for public contracts and/or from other commercial activities an enterprise determined to have bribed a public official? If yes, is such disqualification mandatory or optional and which body decides on the disqualification and its exact terms? Which means are employed to implement the disqualification (e.g. publicly available list, declaration in the bidding process…)? Authorities can impose disqualification on those who have committed irregularities such as the offering of bribes to public officials or such businesses for a certain period of time so that they are prevented from participating in all biddings by public institutions according to Paragraph 1, Article 76, the Enforcement Decree of the Act on Contracts to which the State is a Party. And the authorities cannot establish a private contract with them without exceptional reasons to do so. As for penal procedures, a hearing is conducted in accordance with Article 21 of the Administrative Procedures Act and then agendas are discussed by the contract review committee and the disqualification can last from one month to two years. The contents of disqualification are registered in the Government e-Procurement System in order to prevent the participation in biddings in the first place. 25. Do bidders have to explicitly declare their abstention from any means that could improperly influence the procurement process or decision and, if yes, do such declarations also cover such unlawful practices by subcontractors or other third parties? A bid invitation contains the Special Instruction of Integrity Contract for all biddings. Bidders are regarded as having submitted the Pledge to implement the integrity contract and the awardee has to sign and submit the pledge before establishing a contract. The pledge states that the bidders will not commit any unfair acts related to bidding and contract. 26. Do bidders have to disclose commissions, gratuities, or fees that have been or have to be legally paid to individuals or sub-contractors for their services provided for instance in the preparation of a bid or the execution of the contract? It is not mandatory to disclose commissions, gratuities or fees that have been paid by bidders in the preparation of a bid or the execution of the contract.
  • 10. ADB/OECD Anti-Corruption Initiative for Asia and the Pacific Thematic review on public procurement – Country information on the Republic of Korea – 10 – D. Accountability Separation of responsibilities and independent scrutiny: 27. Which means are employed to avoid insulation of procurement staff and to ensure mutual control? (e.g. rotation of officers, decisions taken/validated by more than one actor, etc.)? The criteria for managing the positions assigned to PPS officials require the work of two years at the same place in principle and then rotate the position. Objectivity and fairness are ensured by; – mutual controls by business division such as the separation of a contract division from a payment division; – the separation of drafting from signing; – the determination, publication and processing of standard operating procedures and criteria; and – the determination of important decisions by the review council, consultation body or committees that involve NGOs. 28. Are there regular and systematic internal and external audits of procuring entities/PPOs? If yes, are they mandatory; which bodies are in charge of this audit; are the audit reports publicly available? Are independent actors/NGOs invited to monitor the procurement procedures and what is the setting prescribed by law? There are internal audits, and external ones conducted by the Audit and Inspection Board, the Office of Government Policy Coordination, and the National Assembly. There are also regular audits that are conducted with the interval of one or three years or irregular audits. External audits are mandatory. Audit results are accessible through the Internet or to the public in written form. The Ombudsman system or committees that involve NGOs are put in place to monitor the procurement procedures, which is conducted by the Korean Independent Commission against Corruption, the Ombudsman Committee, and the Audit and Inspection Board. Review and complaint mechanisms: 29. Do your laws and regulations provide for review and complaints procedures? If yes, are they at administrative and/or judicial levels; what is the time limit for complaint/appeal, if any? How many complaint cases related to procurement are handled per year? Review and complaint procedures are provided for by the Petition Act, the law on processing civil affairs, the Arbitration Act and the Civil Litigation Act. Complaints about international bidding can be filed in accordance with Article 28 of the Act on Contracts to which the State is a Party. If there is complaint against the review results, it can be filed with the International Contract Dispute Mediation Committee according to Article 29. The complaint for the breach of the act as proscribed by Article 28 of the Act on Contracts to which the State is a Party should be made to the principal of a central executive agency within 15 days after the breach has occurred or within 10 days after knowing that such breach occurred.
  • 11. ADB/OECD Anti-Corruption Initiative for Asia and the Pacific Thematic review on public procurement – Country information on the Republic of Korea – 11 – After the International Contract Dispute Mediation Committee’s mediation is completed, it has the same effect as reconciliation at a court, if not challenged within 15 days. In 2004, PPS received 574 written questions, 8,921 questions over the Internet, and 52 litigations. 30. Who is entitled to initiate a complaint procedure (e.g. competing bidders, any citizen, etc.) and how are potential informants protected against retaliation (e.g. confidentiality, anonymity)? Are the decisions of the body handling complaints binding? What are the consequences if a complaint is proven valid (e.g. reopening of the bidding, liquidation of damages, etc.)? Petitions as prescribed by the Petition Act or civil complaints as prescribed by the law on processing civil affairs can be filed by interested parties as well as the general public. In the case of international bidding as prescribed by the Act on Contracts to which the State is a Party, complaints or petitions for review can be filed by affected parties. The principal of a central executive agency should review the complaint within 10 days after it was received and take necessary measures such as correction and notify the results of the applicant. There is no retaliation or disadvantages against the applicant. Informants are protected by maintaining their confidentiality and anonymity, and rewards are provided to them. When one is not satisfied with the decision for the complaint, he or she can file the petition for review. If he or she is not satisfied with the examination of or mediation for the review, he or she can file a lawsuit according to the Civil Litigation Act. If the complaint is found to be legitimate, then adequate corrective measures such as re-bidding or compensation for the damage must be provided.