SlideShare una empresa de Scribd logo
1 de 22
Determining Estimate At
Completion
4 Scenarios & 5 Formulas
AGENDA
• Definition
• Calculating EAC
• EAC Scenarios & Formulas
Designed and Developed by www.pmbypm.com | Copyright 2018
AGENDA
• Definition
• Calculating EAC
• EAC Scenarios & Formulas
Designed and Developed by www.pmbypm.com | Copyright 2018
ESTIMATE AT COMPLETION
The expected total cost of completing all work expressed as
the sum of the actual cost to date and the estimate to
complete.
How much money is needed to complete the total project
work?
Designed and Developed by www.pmbypm.com | Copyright 2018
Project Status
• On Control Date, some work has been completed while
some is remaining.
Designed and Developed by www.pmbypm.com | Copyright 2018
COMPLETED REMAINING
TOTAL PROJECT SCOPE/WORK
Digramatic Representation of BAC & EAC
• Problem Statement - To calculate the expected cost of Total Project Work (EAC)
Designed and Developed by www.pmbypm.com | Copyright 2018
EARNED VALUE
MONETARY VALUE OF
REMAINING WORK
ORIGINAL PROJECT BUDGET (BAC)
EAC
FORECASTED PROJECT BUDGET
ETCACTUAL COST/EXPENDITURE
AGENDA
• Definition
• Calculating EAC
• EAC Scenarios & Formulas
Designed and Developed by www.pmbypm.com | Copyright 2018
Calculatng EAC
• Actual Expenditure Till Date = AC
• Estimated Future Expenditure = ETC
Designed and Developed by www.pmbypm.com | Copyright 2018
EAC = (Actual Expenditure Till Date) + (Estimated Future Expenditure)
EAC = AC + ETC
PROJECT PLAN
• Reference
– https://www.slideshare.net/pmalik2/101-a-beginners-guide-to-earned-value-management
– https://www.slideshare.net/pmalik2/calculating-etc-in-4-different-scenarios
Designed and Developed by www.pmbypm.com | Copyright 2018
Project Scope Build 80 Tables
Project Time Estimate (Duration) 5 Days
Cost Estimate Per Table $1000
Project Cost (Budget) $1000*80 = $80000
PROJECT STATUS – EXAMPLE PROJECT
Designed and Developed by www.pmbypm.com | Copyright 2018
Work Completed 35 out of 80 tables
Actual Expenditure $36000 for building 35 tables
Remaining Project Work 45 tables
ETC Different in different scenarios
EAC ?
AGENDA
• Definition
• Calculating EAC
• EAC Scenarios & Formulas
– ETC Formulas Referenced from
Designed and Developed by www.pmbypm.com | Copyright 2018
https://www.slideshare.net/pmalik2/calculating-etc-in-4-different-scenarios
SCENARIO I
• The project team believes that the project’s past
performance will continue to effect the future performance.
• The project would continue to expend money at the current
rate.
• The remaining work would be completed at
project’s current cost efficiency.
Designed and Developed by www.pmbypm.com | Copyright 2018
SCENARIO I - FORMULA
• Generic EAC equation: EAC = AC + ETC
Designed and Developed by www.pmbypm.com | Copyright 2018
EAC = AC + (BAC – EV) / CPI
ETC = (BAC – EV) / CPI
ETC Formula 1
EAC Formula 1
SCENARIO I - FORMULA
• Deriving Further from EAC Formula 1
• Replacing CPI with EV/AC
Designed and Developed by www.pmbypm.com | Copyright 2018
EAC = AC + (BAC – EV) / CPI
ETC = (BAC – EV) / CPI
EAC Formula 1
EAC Formula 2
SCENARIO II
• The project team believes that the project’s past
performance will not effect the future performance.
• The irregularities of the past would not be repeated in
future.
• The remaining work would be completed at project’s 100%
cost efficiency (as per the original estimates).
Designed and Developed by www.pmbypm.com | Copyright 2018
SCENARIO II - FORMULA
• Generic EAC equation: EAC = AC + ETC
Designed and Developed by www.pmbypm.com | Copyright 2018
EAC = AC + (BAC – EV)
ETC = (BAC – EV)
ETC Formula 2
EAC Formula 3
SCENARIO III
• The project team believes that the project’s past
performance will not effect the future performance.
• The team also believes that project would expend money
neither at current rate nor at 100%.
• The remaining work would be completed at new cost
efficiency - CPIp.
Designed and Developed by www.pmbypm.com | Copyright 2018
SCENARIO III - FORMULA
• Generic EAC equation: EAC = AC + ETC
Designed and Developed by www.pmbypm.com | Copyright 2018
EAC = AC + (BAC – EV) / CPIp
ETC = (BAC – EV) / CPIp
ETC Formula 3
EAC Formula 4
SCENARIO IV
• After analysing the project’s past performance, The project team
believes that the original estimates were not good.
• The cost of remaining work should be re-estimated i.e. ETC
should be determined afresh.
• A fresh ETC can by found by estimating the cost of remaining
(unfinished) work from the Work Breakdown Structure (WBS).
• The project team can re-estimate the cost of remaining work
components (work packages and activities) and then total then
total them Upwards in the WBS to determine a fresh ETC.
• There is no ETC formula for this scenario.
Designed and Developed by www.pmbypm.com | Copyright 2018
SCENARIO V
• To find revised project budget for completing the project work within
the Original Schedule and at the current CPI.
• Current Project Performance Efficiencies
– Schedule Efficiency - Schedule Performance Index (SPI).
– Cost Efficiency - Cost Performance Index (CPI).
• To determine the budgetary cost to complete the project work within
original schedule, we have to consider both CPI and SPI.
Designed and Developed by www.pmbypm.com | Copyright 2018
EAC = AC + (BAC – EV) / (CPI * SPI)
EAC Formula 5
EAC CALCULATIONS - EXAMPLE PROJECT
Designed and Developed by www.pmbypm.com | Copyright 2018
Scenario EAC Formula ETC Value EAC Value
I 1 & 2 $46286 $82286
II 3 $45000 $81000
III 4 $37500 $73500
V 5 $53019 $89019
YOUR OPINION IS IMPORTANT TO
US
For Any Questions Or Suggestions Contact Us @
https://www.pmbypm.com/contact-praveen-malik/
Designed and Developed by www.pmbypm.com | Copyright 2018

Más contenido relacionado

La actualidad más candente

PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1Anand Bobade
 
Schedule Review PMI
Schedule Review PMISchedule Review PMI
Schedule Review PMIChris Carson
 
PMP Training - 08 project quality management
PMP Training - 08 project quality managementPMP Training - 08 project quality management
PMP Training - 08 project quality managementejlp12
 
ITFT -Capital Budgeting
ITFT -Capital BudgetingITFT -Capital Budgeting
ITFT -Capital BudgetingAarti Katoch
 
Project Scope Management - PMBOK 5th Edition
Project Scope Management - PMBOK 5th EditionProject Scope Management - PMBOK 5th Edition
Project Scope Management - PMBOK 5th Editionpankajsh10
 
PMP Chap 10 - Project Communication Management Details
PMP  Chap 10 - Project Communication Management DetailsPMP  Chap 10 - Project Communication Management Details
PMP Chap 10 - Project Communication Management DetailsAnand Bobade
 
PgMP Course Training Material Slides PowerPoint Presentation
PgMP Course Training Material Slides PowerPoint PresentationPgMP Course Training Material Slides PowerPoint Presentation
PgMP Course Training Material Slides PowerPoint PresentationOsama Zarzour
 
Project Charter Corrections
Project Charter CorrectionsProject Charter Corrections
Project Charter CorrectionsNicholas Thomson
 
Preliminary Scope Statement Template
Preliminary Scope Statement TemplatePreliminary Scope Statement Template
Preliminary Scope Statement TemplateMelanieRos
 
Chap 9.3 Acquire Resources
Chap 9.3   Acquire ResourcesChap 9.3   Acquire Resources
Chap 9.3 Acquire ResourcesAnand Bobade
 
Critical Chain Project Management
Critical Chain Project ManagementCritical Chain Project Management
Critical Chain Project ManagementNarendra Bhandava
 
Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Abhishek Pachisia
 

La actualidad más candente (20)

PMP / Framework 1 2-3
PMP / Framework 1 2-3PMP / Framework 1 2-3
PMP / Framework 1 2-3
 
PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1
 
Project Management
Project ManagementProject Management
Project Management
 
Schedule Review PMI
Schedule Review PMISchedule Review PMI
Schedule Review PMI
 
Chap 4 Defining A Project
Chap 4 Defining A ProjectChap 4 Defining A Project
Chap 4 Defining A Project
 
PMP Training - 08 project quality management
PMP Training - 08 project quality managementPMP Training - 08 project quality management
PMP Training - 08 project quality management
 
ITFT -Capital Budgeting
ITFT -Capital BudgetingITFT -Capital Budgeting
ITFT -Capital Budgeting
 
Project Scope Management - PMBOK 5th Edition
Project Scope Management - PMBOK 5th EditionProject Scope Management - PMBOK 5th Edition
Project Scope Management - PMBOK 5th Edition
 
Pid checklist
Pid checklistPid checklist
Pid checklist
 
Project Planning Scheduling
Project Planning SchedulingProject Planning Scheduling
Project Planning Scheduling
 
PMP Chap 10 - Project Communication Management Details
PMP  Chap 10 - Project Communication Management DetailsPMP  Chap 10 - Project Communication Management Details
PMP Chap 10 - Project Communication Management Details
 
PgMP Course Training Material Slides PowerPoint Presentation
PgMP Course Training Material Slides PowerPoint PresentationPgMP Course Training Material Slides PowerPoint Presentation
PgMP Course Training Material Slides PowerPoint Presentation
 
Project Management PERT and CPM
Project Management PERT and CPMProject Management PERT and CPM
Project Management PERT and CPM
 
Project Charter Corrections
Project Charter CorrectionsProject Charter Corrections
Project Charter Corrections
 
Preliminary Scope Statement Template
Preliminary Scope Statement TemplatePreliminary Scope Statement Template
Preliminary Scope Statement Template
 
Chap 9.3 Acquire Resources
Chap 9.3   Acquire ResourcesChap 9.3   Acquire Resources
Chap 9.3 Acquire Resources
 
Critical Chain Project Management
Critical Chain Project ManagementCritical Chain Project Management
Critical Chain Project Management
 
Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)
 
05 project scope management
05 project scope management05 project scope management
05 project scope management
 
10- PMP Training - Risk Management
10- PMP Training - Risk Management 10- PMP Training - Risk Management
10- PMP Training - Risk Management
 

Similar a Calculating Estimate At Completion (EAC) Using 5 Different Formulas

Calculating ETC In 4 Different Scenarios
Calculating ETC In 4 Different ScenariosCalculating ETC In 4 Different Scenarios
Calculating ETC In 4 Different ScenariosPraveen Malik, PMP
 
101 - A Beginner's Guide To Earned Value Management
101 - A Beginner's Guide To Earned Value Management 101 - A Beginner's Guide To Earned Value Management
101 - A Beginner's Guide To Earned Value Management Praveen Malik, PMP
 
Learn The Right Way To Apply TCPI Formulas In Project Management
Learn The Right Way To Apply TCPI Formulas In Project ManagementLearn The Right Way To Apply TCPI Formulas In Project Management
Learn The Right Way To Apply TCPI Formulas In Project ManagementPraveen Malik, PMP
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagementDhamo daran
 
EVMmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmm.pdf
EVMmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmm.pdfEVMmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmm.pdf
EVMmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmm.pdfRedhaElhuni
 
Topic 10 - Project Performance Management.pdf
Topic 10 - Project Performance Management.pdfTopic 10 - Project Performance Management.pdf
Topic 10 - Project Performance Management.pdfHuyNguyen657394
 
A Comprehensive Beginners Guide To Cost Planning
A Comprehensive Beginners Guide To Cost PlanningA Comprehensive Beginners Guide To Cost Planning
A Comprehensive Beginners Guide To Cost PlanningPraveen Malik, PMP
 
day 3-2 PMP.pptx
day 3-2 PMP.pptxday 3-2 PMP.pptx
day 3-2 PMP.pptxAhmedKayed6
 
Jason douglas earned value 1 0
Jason douglas earned value 1 0Jason douglas earned value 1 0
Jason douglas earned value 1 0Jason Douglas
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost managementImran Jamil
 
L06 cost management
L06 cost managementL06 cost management
L06 cost managementAsa Chan
 
C03.08-09-ExecutionMonitoringControl.key.pdf
C03.08-09-ExecutionMonitoringControl.key.pdfC03.08-09-ExecutionMonitoringControl.key.pdf
C03.08-09-ExecutionMonitoringControl.key.pdfssuser8babb7
 
Construction of 6 CPCL Oil storage tankers - A critical Project Management pe...
Construction of 6 CPCL Oil storage tankers - A critical Project Management pe...Construction of 6 CPCL Oil storage tankers - A critical Project Management pe...
Construction of 6 CPCL Oil storage tankers - A critical Project Management pe...Shanmukha S. Potti
 

Similar a Calculating Estimate At Completion (EAC) Using 5 Different Formulas (20)

Calculating ETC In 4 Different Scenarios
Calculating ETC In 4 Different ScenariosCalculating ETC In 4 Different Scenarios
Calculating ETC In 4 Different Scenarios
 
101 - A Beginner's Guide To Earned Value Management
101 - A Beginner's Guide To Earned Value Management 101 - A Beginner's Guide To Earned Value Management
101 - A Beginner's Guide To Earned Value Management
 
Learn The Right Way To Apply TCPI Formulas In Project Management
Learn The Right Way To Apply TCPI Formulas In Project ManagementLearn The Right Way To Apply TCPI Formulas In Project Management
Learn The Right Way To Apply TCPI Formulas In Project Management
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagement
 
EVMmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmm.pdf
EVMmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmm.pdfEVMmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmm.pdf
EVMmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmm.pdf
 
Earned value 01
Earned value 01Earned value 01
Earned value 01
 
Topic 10 - Project Performance Management.pdf
Topic 10 - Project Performance Management.pdfTopic 10 - Project Performance Management.pdf
Topic 10 - Project Performance Management.pdf
 
An introduction to project accounting
An introduction to project accountingAn introduction to project accounting
An introduction to project accounting
 
A Comprehensive Beginners Guide To Cost Planning
A Comprehensive Beginners Guide To Cost PlanningA Comprehensive Beginners Guide To Cost Planning
A Comprehensive Beginners Guide To Cost Planning
 
PMP Exam Preparation Course: 06 Project Cost Management
PMP Exam Preparation Course: 06 Project Cost ManagementPMP Exam Preparation Course: 06 Project Cost Management
PMP Exam Preparation Course: 06 Project Cost Management
 
Methodologies of Project Progress Measurement
Methodologies of Project Progress MeasurementMethodologies of Project Progress Measurement
Methodologies of Project Progress Measurement
 
day 3-2 PMP.pptx
day 3-2 PMP.pptxday 3-2 PMP.pptx
day 3-2 PMP.pptx
 
Jason douglas earned value 1 0
Jason douglas earned value 1 0Jason douglas earned value 1 0
Jason douglas earned value 1 0
 
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting
 
6- PMP Training - Cost Management
6- PMP Training - Cost Management6- PMP Training - Cost Management
6- PMP Training - Cost Management
 
Delivering nothing efficiently
Delivering nothing efficientlyDelivering nothing efficiently
Delivering nothing efficiently
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
 
L06 cost management
L06 cost managementL06 cost management
L06 cost management
 
C03.08-09-ExecutionMonitoringControl.key.pdf
C03.08-09-ExecutionMonitoringControl.key.pdfC03.08-09-ExecutionMonitoringControl.key.pdf
C03.08-09-ExecutionMonitoringControl.key.pdf
 
Construction of 6 CPCL Oil storage tankers - A critical Project Management pe...
Construction of 6 CPCL Oil storage tankers - A critical Project Management pe...Construction of 6 CPCL Oil storage tankers - A critical Project Management pe...
Construction of 6 CPCL Oil storage tankers - A critical Project Management pe...
 

Más de Praveen Malik, PMP

How To Use Scheduling Lead And Lag With 4 Types Of Relationships
How To Use Scheduling Lead And Lag With 4 Types Of RelationshipsHow To Use Scheduling Lead And Lag With 4 Types Of Relationships
How To Use Scheduling Lead And Lag With 4 Types Of RelationshipsPraveen Malik, PMP
 
How To Do Planning Using 4 Types of Project Dependencies?
How To Do Planning Using 4 Types of Project Dependencies?How To Do Planning Using 4 Types of Project Dependencies?
How To Do Planning Using 4 Types of Project Dependencies?Praveen Malik, PMP
 
5 Steps Of Project Scheduling Process For Absolute Beginners
5 Steps Of Project Scheduling Process For Absolute Beginners5 Steps Of Project Scheduling Process For Absolute Beginners
5 Steps Of Project Scheduling Process For Absolute BeginnersPraveen Malik, PMP
 
Successful Project Managers Use These 5 Ways to Represent Project Schedule
Successful Project Managers Use These 5 Ways to Represent Project ScheduleSuccessful Project Managers Use These 5 Ways to Represent Project Schedule
Successful Project Managers Use These 5 Ways to Represent Project SchedulePraveen Malik, PMP
 
4 Project Estimation Techniques That Can Make You Super Successful
4 Project Estimation Techniques That Can Make You Super Successful4 Project Estimation Techniques That Can Make You Super Successful
4 Project Estimation Techniques That Can Make You Super SuccessfulPraveen Malik, PMP
 
Ignore Project Scope & WBS At Your Own Peril
Ignore Project Scope & WBS At Your Own PerilIgnore Project Scope & WBS At Your Own Peril
Ignore Project Scope & WBS At Your Own PerilPraveen Malik, PMP
 
How Project Network Diagram's Can Help You Become A Better Project Manager
How Project Network Diagram's Can Help You Become A Better Project ManagerHow Project Network Diagram's Can Help You Become A Better Project Manager
How Project Network Diagram's Can Help You Become A Better Project ManagerPraveen Malik, PMP
 

Más de Praveen Malik, PMP (7)

How To Use Scheduling Lead And Lag With 4 Types Of Relationships
How To Use Scheduling Lead And Lag With 4 Types Of RelationshipsHow To Use Scheduling Lead And Lag With 4 Types Of Relationships
How To Use Scheduling Lead And Lag With 4 Types Of Relationships
 
How To Do Planning Using 4 Types of Project Dependencies?
How To Do Planning Using 4 Types of Project Dependencies?How To Do Planning Using 4 Types of Project Dependencies?
How To Do Planning Using 4 Types of Project Dependencies?
 
5 Steps Of Project Scheduling Process For Absolute Beginners
5 Steps Of Project Scheduling Process For Absolute Beginners5 Steps Of Project Scheduling Process For Absolute Beginners
5 Steps Of Project Scheduling Process For Absolute Beginners
 
Successful Project Managers Use These 5 Ways to Represent Project Schedule
Successful Project Managers Use These 5 Ways to Represent Project ScheduleSuccessful Project Managers Use These 5 Ways to Represent Project Schedule
Successful Project Managers Use These 5 Ways to Represent Project Schedule
 
4 Project Estimation Techniques That Can Make You Super Successful
4 Project Estimation Techniques That Can Make You Super Successful4 Project Estimation Techniques That Can Make You Super Successful
4 Project Estimation Techniques That Can Make You Super Successful
 
Ignore Project Scope & WBS At Your Own Peril
Ignore Project Scope & WBS At Your Own PerilIgnore Project Scope & WBS At Your Own Peril
Ignore Project Scope & WBS At Your Own Peril
 
How Project Network Diagram's Can Help You Become A Better Project Manager
How Project Network Diagram's Can Help You Become A Better Project ManagerHow Project Network Diagram's Can Help You Become A Better Project Manager
How Project Network Diagram's Can Help You Become A Better Project Manager
 

Último

This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.christianmathematics
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfAdmir Softic
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhikauryashika82
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfPoh-Sun Goh
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphThiyagu K
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptxMaritesTamaniVerdade
 
Making and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfMaking and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfChris Hunter
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxVishalSingh1417
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...Nguyen Thanh Tu Collection
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfAyushMahapatra5
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxnegromaestrong
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin ClassesCeline George
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104misteraugie
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeThiyagu K
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxRamakrishna Reddy Bijjam
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsMebane Rash
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...Poonam Aher Patil
 

Último (20)

This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdf
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
 
Making and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfMaking and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdf
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdf
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptx
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...
 

Calculating Estimate At Completion (EAC) Using 5 Different Formulas

  • 1. Determining Estimate At Completion 4 Scenarios & 5 Formulas
  • 2. AGENDA • Definition • Calculating EAC • EAC Scenarios & Formulas Designed and Developed by www.pmbypm.com | Copyright 2018
  • 3. AGENDA • Definition • Calculating EAC • EAC Scenarios & Formulas Designed and Developed by www.pmbypm.com | Copyright 2018
  • 4. ESTIMATE AT COMPLETION The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete. How much money is needed to complete the total project work? Designed and Developed by www.pmbypm.com | Copyright 2018
  • 5. Project Status • On Control Date, some work has been completed while some is remaining. Designed and Developed by www.pmbypm.com | Copyright 2018 COMPLETED REMAINING TOTAL PROJECT SCOPE/WORK
  • 6. Digramatic Representation of BAC & EAC • Problem Statement - To calculate the expected cost of Total Project Work (EAC) Designed and Developed by www.pmbypm.com | Copyright 2018 EARNED VALUE MONETARY VALUE OF REMAINING WORK ORIGINAL PROJECT BUDGET (BAC) EAC FORECASTED PROJECT BUDGET ETCACTUAL COST/EXPENDITURE
  • 7. AGENDA • Definition • Calculating EAC • EAC Scenarios & Formulas Designed and Developed by www.pmbypm.com | Copyright 2018
  • 8. Calculatng EAC • Actual Expenditure Till Date = AC • Estimated Future Expenditure = ETC Designed and Developed by www.pmbypm.com | Copyright 2018 EAC = (Actual Expenditure Till Date) + (Estimated Future Expenditure) EAC = AC + ETC
  • 9. PROJECT PLAN • Reference – https://www.slideshare.net/pmalik2/101-a-beginners-guide-to-earned-value-management – https://www.slideshare.net/pmalik2/calculating-etc-in-4-different-scenarios Designed and Developed by www.pmbypm.com | Copyright 2018 Project Scope Build 80 Tables Project Time Estimate (Duration) 5 Days Cost Estimate Per Table $1000 Project Cost (Budget) $1000*80 = $80000
  • 10. PROJECT STATUS – EXAMPLE PROJECT Designed and Developed by www.pmbypm.com | Copyright 2018 Work Completed 35 out of 80 tables Actual Expenditure $36000 for building 35 tables Remaining Project Work 45 tables ETC Different in different scenarios EAC ?
  • 11. AGENDA • Definition • Calculating EAC • EAC Scenarios & Formulas – ETC Formulas Referenced from Designed and Developed by www.pmbypm.com | Copyright 2018 https://www.slideshare.net/pmalik2/calculating-etc-in-4-different-scenarios
  • 12. SCENARIO I • The project team believes that the project’s past performance will continue to effect the future performance. • The project would continue to expend money at the current rate. • The remaining work would be completed at project’s current cost efficiency. Designed and Developed by www.pmbypm.com | Copyright 2018
  • 13. SCENARIO I - FORMULA • Generic EAC equation: EAC = AC + ETC Designed and Developed by www.pmbypm.com | Copyright 2018 EAC = AC + (BAC – EV) / CPI ETC = (BAC – EV) / CPI ETC Formula 1 EAC Formula 1
  • 14. SCENARIO I - FORMULA • Deriving Further from EAC Formula 1 • Replacing CPI with EV/AC Designed and Developed by www.pmbypm.com | Copyright 2018 EAC = AC + (BAC – EV) / CPI ETC = (BAC – EV) / CPI EAC Formula 1 EAC Formula 2
  • 15. SCENARIO II • The project team believes that the project’s past performance will not effect the future performance. • The irregularities of the past would not be repeated in future. • The remaining work would be completed at project’s 100% cost efficiency (as per the original estimates). Designed and Developed by www.pmbypm.com | Copyright 2018
  • 16. SCENARIO II - FORMULA • Generic EAC equation: EAC = AC + ETC Designed and Developed by www.pmbypm.com | Copyright 2018 EAC = AC + (BAC – EV) ETC = (BAC – EV) ETC Formula 2 EAC Formula 3
  • 17. SCENARIO III • The project team believes that the project’s past performance will not effect the future performance. • The team also believes that project would expend money neither at current rate nor at 100%. • The remaining work would be completed at new cost efficiency - CPIp. Designed and Developed by www.pmbypm.com | Copyright 2018
  • 18. SCENARIO III - FORMULA • Generic EAC equation: EAC = AC + ETC Designed and Developed by www.pmbypm.com | Copyright 2018 EAC = AC + (BAC – EV) / CPIp ETC = (BAC – EV) / CPIp ETC Formula 3 EAC Formula 4
  • 19. SCENARIO IV • After analysing the project’s past performance, The project team believes that the original estimates were not good. • The cost of remaining work should be re-estimated i.e. ETC should be determined afresh. • A fresh ETC can by found by estimating the cost of remaining (unfinished) work from the Work Breakdown Structure (WBS). • The project team can re-estimate the cost of remaining work components (work packages and activities) and then total then total them Upwards in the WBS to determine a fresh ETC. • There is no ETC formula for this scenario. Designed and Developed by www.pmbypm.com | Copyright 2018
  • 20. SCENARIO V • To find revised project budget for completing the project work within the Original Schedule and at the current CPI. • Current Project Performance Efficiencies – Schedule Efficiency - Schedule Performance Index (SPI). – Cost Efficiency - Cost Performance Index (CPI). • To determine the budgetary cost to complete the project work within original schedule, we have to consider both CPI and SPI. Designed and Developed by www.pmbypm.com | Copyright 2018 EAC = AC + (BAC – EV) / (CPI * SPI) EAC Formula 5
  • 21. EAC CALCULATIONS - EXAMPLE PROJECT Designed and Developed by www.pmbypm.com | Copyright 2018 Scenario EAC Formula ETC Value EAC Value I 1 & 2 $46286 $82286 II 3 $45000 $81000 III 4 $37500 $73500 V 5 $53019 $89019
  • 22. YOUR OPINION IS IMPORTANT TO US For Any Questions Or Suggestions Contact Us @ https://www.pmbypm.com/contact-praveen-malik/ Designed and Developed by www.pmbypm.com | Copyright 2018