Project Time Management
                                                    Study Notes




PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the
                                  Project Management Institute, Inc.

                               © 2012 PMstudy.com. All rights reserved
Points to Note

• Please read chapter 6 from Project Management Institute, A Guide to the Project
  Management Body of Knowledge, (PMBOK® Guide) – Fourth Edition, Project Management
  Institute, Inc., 2008 (pages 129-164).


• The study notes explain topics that are important for PMP® exam preparation, and you can
  expect several questions from these topics.

• Pay close attention to all the terms used. It is very important to understand all the concepts
  discussed in this chapter.

• Try to relate the concepts to real life examples.

• After reading the study notes, please answer the chapter test questions in this knowledge
  area. The chapter questions improve your understanding of the concepts discussed in the
  study notes.




                                 © 2012 PMstudy.com. All rights reserved                           2
What is Project Time Management?

• Processes required to manage timely completion of the project.

• Processes involved in the project time management include:

  ◦ Define Activities
  ◦ Sequence Activities
  ◦ Estimate Activity Resources
  ◦ Estimate Activity Durations
  ◦ Develop Schedule
  ◦ Control Schedule


• Each of these processes occur at least once in every project and in one or more project
  phases (if the project is divided into phases).


Please refer to figure 6-1, PMBOK® Guide Fourth Edition, page 131. This provides an
overview of the processes in project time management.




                               © 2012 PMstudy.com. All rights reserved                      3
Define Activities

• Process to identify specific actions that need to be performed to produce project deliverables

• Activities are smaller decomposed components of the project work packages, which represent
  the work necessary to complete the work package.

• Tools and Techniques used in Define Activities process:

  ◦   Decomposition
  ◦   Rolling wave planning
  ◦   Templates
  ◦   Expert judgment

• Outputs of Define Activities process are:

  ◦ Activity list
  ◦ Activity attribute
  ◦ Milestone list




                                © 2012 PMstudy.com. All rights reserved                        4
Decomposition

• Subdivides the project work packages into activities

• Provides better management control

• Leads to activities, the lowest level of the work packages in the Define Activities process

• Leads to the work package, the lowest level in the Work Breakdown Structure (WBS) in the
  Create WBS process, where the deliverables are identified

• Process can involve team members. This can lead to better and more accurate results.




                                 © 2012 PMstudy.com. All rights reserved                        5
Sequence Activities

• Identifies and documents relationships among project activities

• Uses logical relationships

• Can be performed by using manual or automated techniques or project management software

• Tools and Techniques used for the Sequence Activity process are:

  ◦   Precedence diagramming method (PDM)
  ◦   Dependency determination
  ◦   Applying leads and lags
  ◦   Schedule network templates




                               © 2012 PMstudy.com. All rights reserved                6
Types of Dependencies

• Mandatory dependencies:

  ◦ Also referred to as hard logic
  ◦ Required as per contract or inherent in the nature of the work
  ◦ Usually involve physical limitations (e.g., you cannot build the ceiling until walls are
    constructed)
  ◦ Are determined by the project management team during the activity sequencing process

• Discretionary dependencies:

  ◦ Also referred to as preferred logic, preferential logic, or soft logic
  ◦ Are determined by the project management team during the activity sequencing process
  ◦ Should be used with care and well documented, since they may limit later scheduling
    options

• External dependencies:

  ◦ Are determined by the project management team during the activity sequencing process
  ◦ Involve a relationship between project and non-project activities such as activities outside
    the project team’s control (e.g., dependence on external sources for deliveries,
    environmental factors governed by statutes, etc.)


                                © 2012 PMstudy.com. All rights reserved                        7
Precedence Diagramming Method (PDM)

• Used in the Critical Path Methodology (CPM) for constructing the project schedule network
  diagram

• Uses nodes to represent the activities and connects them with arrows that reflect
  dependencies and the logical relationships that exist between the activities

• Includes four types of dependencies or logical relationships:

  ◦   Finish-to-start (FS)
  ◦   Finish-to-finish (FF)
  ◦   Start-to-start (SS)
  ◦   Start-to-finish (SF)

• Uses, most commonly, the finish-to-start (FS) precedence relationship

• Is also called Activity–On-Node (AON) and is used by most project management software
  packages

• Does not use dummy activities

• Does not allow for loops or conditional branches




                                © 2012 PMstudy.com. All rights reserved                       8
Conditional Diagramming Methods

• Allows non-sequential loops or conditional branches

• Example:

  ◦   GERT (graphical evaluation and review techniques)
  ◦   System dynamics




                               © 2012 PMstudy.com. All rights reserved   9
Schedule Network Templates

• Can be used to expedite preparation of networks of project activities

• Includes entire project or only a portion of it

• Portions of a project schedule network diagram are referred to as a subnetwork or a fragment
  network.




                                  © 2012 PMstudy.com. All rights reserved                  10
Project Schedule Network Diagrams

• Is the main output of Sequence activities

• Schematic displays of the project’s schedule activities and the logical relationships among
  them (also referred to as dependencies)

• Can be produced manually or using project management software

• Can have full project details, or have one or more summary activities




                                © 2012 PMstudy.com. All rights reserved                         11
Estimate Activity Resources

• Estimates the type and quantities of material, people, equipment, or supplies required to
  perform each activity.

• Is closely coordinated with the Estimate Costs process

• Tools and Techniques used are:

  ◦   Expert judgment
  ◦   Alternatives analysis
  ◦   Published estimating data
  ◦   Bottom-up estimating
  ◦   Project management software




                                © 2012 PMstudy.com. All rights reserved                       12
Outputs of Estimate Activity Resources

• Activity Resource Requirements

  ◦ Identifies the types and quantities of resources required for each activity in a work package
  ◦ Determines the estimated resources for each work package by aggregating their
    requirements like the types and the quantities
  ◦ Will be documented by including basis of estimates and the assumptions made

• Resource Breakdown Structure

  ◦ Is a hierarchical structure of resources by type and category
  ◦ Organizes and reports project schedule data with resource utilization information

• Project Document Updates

  ◦ The project documents that may be updated include:
    • Activity list
    • Activity attributes
    • Resource calendars




                               © 2012 PMstudy.com. All rights reserved                        13
Estimate Activity Durations

• Process that requires the estimate of the amount of work effort required and the amount of
  resources to be applied for approximating the work periods needed to complete the activity.

• Uses information on the activity scope of work, required resource types, estimated resource
  quantities, and resource calendars, as well as historical information

• Is progressively elaborated with duration estimates becoming progressively more accurate and
  of better quality

• Should take into consideration the input data’s quality and availability

• All assumptions and data used for supporting the duration estimating are documented

• Tools and Techniques used are:

   ◦   Expert judgment
   ◦   Analogous estimating
   ◦   Parametric estimating
   ◦   Three-Points estimating
   ◦   Reserve analysis


                                 © 2012 PMstudy.com. All rights reserved                    14
Historical Information

• Available from:

  ◦ Project files: Records of previous project results that are detailed enough to help in duration
    estimating

  ◦ Commercial duration estimating databases: Available for standard tasks

  ◦ Team members’ past experience: Individual members of the project team, who worked on
    prior similar projects, and who might be able to recollect details of estimates from those
    projects for possible application in the current project




                                © 2012 PMstudy.com. All rights reserved                        15
Analogous Estimating
                        (Top-Down Estimating)
• An estimating technique

• Uses the parameters from a previous, similar project as the basis for estimating the same
  parameter for a future project

• It is a gross value estimating approach

• Uses historical information and expert judgment

• Less costly and time consuming than other techniques

• Generally less accurate

• Most reliable when:

  ◦ Previous activities are similar in fact and not just in appearance.
  ◦ Individuals preparing the estimates have the needed experience.




                               © 2012 PMstudy.com. All rights reserved                        16
Parametric Estimating

• Uses a statistical relationship between historical information and other variables to calculate an
  estimate for activity parameters

• Determines how many times the specific work category is going to be performed in the given
  activity

• Can be applied to a total project or segments of a project

• Activity durations=Quantity of work to be performed x Labor hours per unit of work




                                 © 2012 PMstudy.com. All rights reserved                        17
Develop Schedule

• Analyzes activity sequences, durations, resource requirements, and schedule constraints to
  create the project schedule

• Iterative process

• Determines the project activities’ scheduled start and finish dates

• Determines the milestones’ scheduled start and finish dates

• Tools and Techniques used are:

  ◦   Schedule network analysis
  ◦   Critical path method
  ◦   Critical chain method
  ◦   Resource leveling
  ◦   What-if scenario analysis
  ◦   Applying leads and lags
  ◦   Schedule compression
  ◦   Scheduling tool



                                © 2012 PMstudy.com. All rights reserved                    18
Constraints and Milestones

Constraints:

• Factors that will limit a management team’s options for a defined course of action.
• An internal or external restriction that will affect the project’s performance
• Internal to the project - Dates imposed on any planned activity, used to restrict the start or
  finish dates for the tasks, “start no earlier than” and “finish no later than” types, etc.
• External to the project - Market window on a technology project, weather restrictions on
  outdoor activities, government-mandated compliance requirements, etc.

Key event or major milestone schedule:

• Summarizes schedules that identify significant or major milestones in the project
• Denotes identified deliverables and their specified dates of completion, as requested by project
  sponsor, customer, or other stakeholders
• Once scheduled, the milestones may be difficult to shift




                                  © 2012 PMstudy.com. All rights reserved                          19
Mathematical Analysis

• Involves calculating theoretical early, and late start and finish dates

• Popular techniques:

   ◦ Critical Path Method (CPM):
      • Used to determine the amount of flexibility in scheduling various logical network paths in
        the project schedule network
      • Used to determine the minimum total duration of the project
      • Used to calculate a single deterministic early and late start and finish date for each
        activity based on specified sequential network logic and activity duration estimates

   ◦ Project Evaluation and Review Technique (PERT):
      • A technique that is used to estimate the activity duration by applying a weighted average
        of optimistic (to), pessimistic (tp), and most likely (tm) estimates, when there is
        uncertainty with the individual activity estimates.
      • Analysis calculates the expected activity duration (te) as indicated below:
                                     te = to+ 4tm + tp
                                             6



                                 © 2012 PMstudy.com. All rights reserved                         20
Schedule Compression

• Shortens the project schedule to meet the imposed dates, schedule’s constraints, or other
  objectives without changing the scope of the project

• Techniques used are:

  ◦ Crashing:
    • A technique by which cost and schedule tradeoffs are analyzed to determine how to
      obtain the greatest amount of compression for the least incremental cost
    • Will only work for those activities where additional resources will reduce the duration
    • Does not always produce a viable alternative
    • Could increase either risk or cost, or both risk and cost of the project

  ◦ Fast tracking:
    • A technique of performing activities in parallel that would normally be done in sequence
    • Works only if activities overlap
    • Can result in rework and increased risk




                               © 2012 PMstudy.com. All rights reserved                          21
Simulation, Resource Leveling, and Critical
                Chain Method
Simulation:

• Involves calculating multiple project durations with different sets of activity assumptions to
  assess the feasibility of the project schedule under adverse conditions, such as delay in major
  component delivery, strike, etc.

• Common techniques:
  ◦ Monte Carlo analysis
  ◦ What-if analysis (using logic network to compute different scenarios)

Resource Leveling Heuristics

• Done because mathematical analysis produces a preliminary early-start schedule that requires
  more than the allocated resources during certain time periods
  e.g., Rule of thumb – “allocate scarce resources to critical path activities first.”

• Often results in a project duration that is longer than the preliminary schedule. (Also called
  “resource based method”).

Critical Chain Method:

• A schedule network analysis technique that modifies the project schedule to account for
  limited resources.



                                 © 2012 PMstudy.com. All rights reserved                           22
Project Schedule

• Should have at least a planned start date and a planned finish date for each activity.

• A targeted schedule can also be made with a defined target start and end date for every
  activity.

• Can be presented in detail or in summary form (referred to as master schedule or milestone
  schedule)

• Often presented graphically or in tabular form

• Graphically presented using:

  ◦ Milestone charts
  ◦ Bar charts
  ◦ Project schedule network diagrams




                                 © 2012 PMstudy.com. All rights reserved                    23
Schedule Updates, Schedule Baseline, Re-
    baselining, and New Target Schedules
• Schedule Updates:
   ◦   Any modifications to the project schedule

• Schedule baseline:
   ◦   Component of the project plan, which is accepted and approved by the project management team
   ◦   Has a baseline start date and baseline finish date. It is an updated version of the project schedule and is
       developed from the schedule network analysis
   ◦   Provides the basis for measuring and reporting schedule performance
   ◦   Can be changed to incorporate the approved change requests related to project scope
       changes/resources/duration estimates

• Re-baselining:
   ◦   Performed if schedule delays are very severe
   ◦   Used to provide realistic data to measure performance (done in only extreme cases, because all historical
       data will be lost).

• New target schedules:
   ◦   If there are small changes to the project schedule, then the schedule baseline is kept constant – but new
       target schedules may be used.
   ◦   If the project schedule gets delayed severely, then a new target schedule has to be developed, which
       forecasts the start and finish dates needed for providing realistic data for directing work, and measuring
       performance and progress.



                                      © 2012 PMstudy.com. All rights reserved                                   24
Three Point Estimate

• With limited information to find out activity durations, the three-point estimation technique is
  used to find a distribution of the durations for different scenarios.
• Three estimates are produced based on prior experience or best-guesses:

  ◦ O = the optimistic estimate
  ◦ M = the most likely estimate
  ◦ L = the least likely estimate.
• These values are used to calculate an E value for the estimate and a standard deviation (SD)
  where:

  ◦ E = (O + 4M + L) / 6
  ◦ SD = (L − O)/6




                                © 2012 PMstudy.com. All rights reserved                         25
Activity on Node

• Activity on Node (AON) or Precedence Diagramming Method (PDM) showcases the inter-
  dependencies among various project activities.
• This technique is used to draw the project schedule network diagrams; e.g. Critical Path
  Network Diagram to identify the Critical path and the float for each activity
• In an AON diagram, each rectangle box represents a node and a project activity. These
  rectangular boxes are connected using arrows to the succeeding activity box thereby
  portraying the project dependencies.
• Activity on Node uses four types of dependencies.

  ◦ Finish to Start (FS): The end of one activity is required for the start of the next one. This is
    the most common dependency
  ◦ Finish to Finish (FF): The end of the first activity is required for the second activity to finish
  ◦ Start To Start (SS): The second activity starts only after the first activity has started
  ◦ Start to Finish (SF): second activity cannot be finished until first activity starts.




                                 © 2012 PMstudy.com. All rights reserved                            26

Más contenido relacionado

La actualidad más candente

Software Project Management lecture 12
Software Project Management lecture 12Software Project Management lecture 12
Software Project Management lecture 12Syed Muhammad Hammad
 
Software Project Management (lecture 2)
Software Project Management (lecture 2)Software Project Management (lecture 2)
Software Project Management (lecture 2)Syed Muhammad Hammad
 
Software Project Management lecture 9
Software Project Management lecture 9Software Project Management lecture 9
Software Project Management lecture 9Syed Muhammad Hammad
 
Project / Program / Portfolio Management and Processes Groups
Project / Program / Portfolio Management and Processes GroupsProject / Program / Portfolio Management and Processes Groups
Project / Program / Portfolio Management and Processes GroupsAhmed Alageed
 
Software Project Management - Introduction and fundamentals
Software Project Management - Introduction and fundamentalsSoftware Project Management - Introduction and fundamentals
Software Project Management - Introduction and fundamentalsEmanuele Della Valle
 
Software Project Management lecture 10
Software Project Management lecture 10Software Project Management lecture 10
Software Project Management lecture 10Syed Muhammad Hammad
 
Software Project Management lecture 7
Software Project Management lecture 7Software Project Management lecture 7
Software Project Management lecture 7Syed Muhammad Hammad
 
Software Project Management lecture 8
Software Project Management lecture 8Software Project Management lecture 8
Software Project Management lecture 8Syed Muhammad Hammad
 
PMI - ACP: Domain 6 - Problem Detection and resolution-v2.2_lite_4_60_pages
PMI - ACP: Domain 6 - Problem Detection and resolution-v2.2_lite_4_60_pagesPMI - ACP: Domain 6 - Problem Detection and resolution-v2.2_lite_4_60_pages
PMI - ACP: Domain 6 - Problem Detection and resolution-v2.2_lite_4_60_pagesPhuocNT (Fresher.VN)
 
Introduction to Software Project Management
Introduction to Software Project ManagementIntroduction to Software Project Management
Introduction to Software Project ManagementSaadi Jadoon
 
Richard.laws
Richard.lawsRichard.laws
Richard.lawsNASAPMC
 
SOFTWARE ENGINEERING
SOFTWARE ENGINEERING  SOFTWARE ENGINEERING
SOFTWARE ENGINEERING Gaditek
 
Law.richard
Law.richardLaw.richard
Law.richardNASAPMC
 
Software engineering by Dr. vishnu sharma
Software engineering by Dr. vishnu sharmaSoftware engineering by Dr. vishnu sharma
Software engineering by Dr. vishnu sharmaVishnu Sharma
 
Software Project Management
Software Project ManagementSoftware Project Management
Software Project ManagementShauryaGupta38
 
Backup jim cassidy
Backup jim cassidyBackup jim cassidy
Backup jim cassidyNASAPMC
 

La actualidad más candente (20)

Chapter 03
Chapter 03Chapter 03
Chapter 03
 
Software Project Management lecture 12
Software Project Management lecture 12Software Project Management lecture 12
Software Project Management lecture 12
 
Software Project Management (lecture 2)
Software Project Management (lecture 2)Software Project Management (lecture 2)
Software Project Management (lecture 2)
 
Software Project Management lecture 9
Software Project Management lecture 9Software Project Management lecture 9
Software Project Management lecture 9
 
Project / Program / Portfolio Management and Processes Groups
Project / Program / Portfolio Management and Processes GroupsProject / Program / Portfolio Management and Processes Groups
Project / Program / Portfolio Management and Processes Groups
 
Software Project Management - Introduction and fundamentals
Software Project Management - Introduction and fundamentalsSoftware Project Management - Introduction and fundamentals
Software Project Management - Introduction and fundamentals
 
Software Project Management lecture 10
Software Project Management lecture 10Software Project Management lecture 10
Software Project Management lecture 10
 
PM Symposium RUP UC Realization
PM Symposium RUP UC RealizationPM Symposium RUP UC Realization
PM Symposium RUP UC Realization
 
Unit 1 spm
Unit 1  spmUnit 1  spm
Unit 1 spm
 
Software Project Management lecture 7
Software Project Management lecture 7Software Project Management lecture 7
Software Project Management lecture 7
 
Software Project Management lecture 8
Software Project Management lecture 8Software Project Management lecture 8
Software Project Management lecture 8
 
PMI - ACP: Domain 6 - Problem Detection and resolution-v2.2_lite_4_60_pages
PMI - ACP: Domain 6 - Problem Detection and resolution-v2.2_lite_4_60_pagesPMI - ACP: Domain 6 - Problem Detection and resolution-v2.2_lite_4_60_pages
PMI - ACP: Domain 6 - Problem Detection and resolution-v2.2_lite_4_60_pages
 
Introduction to Software Project Management
Introduction to Software Project ManagementIntroduction to Software Project Management
Introduction to Software Project Management
 
Richard.laws
Richard.lawsRichard.laws
Richard.laws
 
SOFTWARE ENGINEERING
SOFTWARE ENGINEERING  SOFTWARE ENGINEERING
SOFTWARE ENGINEERING
 
Q7503 4post
Q7503 4postQ7503 4post
Q7503 4post
 
Law.richard
Law.richardLaw.richard
Law.richard
 
Software engineering by Dr. vishnu sharma
Software engineering by Dr. vishnu sharmaSoftware engineering by Dr. vishnu sharma
Software engineering by Dr. vishnu sharma
 
Software Project Management
Software Project ManagementSoftware Project Management
Software Project Management
 
Backup jim cassidy
Backup jim cassidyBackup jim cassidy
Backup jim cassidy
 

Destacado

Create your first_website_now
Create your first_website_nowCreate your first_website_now
Create your first_website_nowAmr Miqdadi
 
Code of Ethics and Professional Conduct
Code of Ethics and Professional Conduct Code of Ethics and Professional Conduct
Code of Ethics and Professional Conduct Amr Miqdadi
 
Understand PMBoK 4th
Understand PMBoK 4thUnderstand PMBoK 4th
Understand PMBoK 4thAmr Miqdadi
 
PMP Exam Prep-ITTOs and KP
PMP Exam Prep-ITTOs and KPPMP Exam Prep-ITTOs and KP
PMP Exam Prep-ITTOs and KPAmr Miqdadi
 
PMP Knowledge Areas Summary
PMP Knowledge Areas SummaryPMP Knowledge Areas Summary
PMP Knowledge Areas SummaryAmr Miqdadi
 
Undestand PMBok 5th, Section 1&2
Undestand PMBok 5th, Section 1&2Undestand PMBok 5th, Section 1&2
Undestand PMBok 5th, Section 1&2Amr Miqdadi
 
Undestand PMBok 5th, Section 4
Undestand PMBok 5th, Section 4Undestand PMBok 5th, Section 4
Undestand PMBok 5th, Section 4Amr Miqdadi
 
Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3Amr Miqdadi
 
Pmp exam prep Pdf- 2
Pmp exam prep Pdf- 2Pmp exam prep Pdf- 2
Pmp exam prep Pdf- 2Amr Miqdadi
 
PMP Exam Formulas
PMP Exam FormulasPMP Exam Formulas
PMP Exam FormulasAmr Miqdadi
 
Pmp Exam Prep PDF-1
Pmp Exam Prep PDF-1Pmp Exam Prep PDF-1
Pmp Exam Prep PDF-1Amr Miqdadi
 
Understand PMBoK 5th edition
Understand PMBoK 5th editionUnderstand PMBoK 5th edition
Understand PMBoK 5th editionAmr Miqdadi
 
Pert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gertPert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gertRaj J Das
 
PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...
PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...
PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...JustAcademy
 

Destacado (14)

Create your first_website_now
Create your first_website_nowCreate your first_website_now
Create your first_website_now
 
Code of Ethics and Professional Conduct
Code of Ethics and Professional Conduct Code of Ethics and Professional Conduct
Code of Ethics and Professional Conduct
 
Understand PMBoK 4th
Understand PMBoK 4thUnderstand PMBoK 4th
Understand PMBoK 4th
 
PMP Exam Prep-ITTOs and KP
PMP Exam Prep-ITTOs and KPPMP Exam Prep-ITTOs and KP
PMP Exam Prep-ITTOs and KP
 
PMP Knowledge Areas Summary
PMP Knowledge Areas SummaryPMP Knowledge Areas Summary
PMP Knowledge Areas Summary
 
Undestand PMBok 5th, Section 1&2
Undestand PMBok 5th, Section 1&2Undestand PMBok 5th, Section 1&2
Undestand PMBok 5th, Section 1&2
 
Undestand PMBok 5th, Section 4
Undestand PMBok 5th, Section 4Undestand PMBok 5th, Section 4
Undestand PMBok 5th, Section 4
 
Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3
 
Pmp exam prep Pdf- 2
Pmp exam prep Pdf- 2Pmp exam prep Pdf- 2
Pmp exam prep Pdf- 2
 
PMP Exam Formulas
PMP Exam FormulasPMP Exam Formulas
PMP Exam Formulas
 
Pmp Exam Prep PDF-1
Pmp Exam Prep PDF-1Pmp Exam Prep PDF-1
Pmp Exam Prep PDF-1
 
Understand PMBoK 5th edition
Understand PMBoK 5th editionUnderstand PMBoK 5th edition
Understand PMBoK 5th edition
 
Pert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gertPert,cpm, resource allocation and gert
Pert,cpm, resource allocation and gert
 
PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...
PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...
PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...
 

Similar a Time management

DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project ManagementRasan Samarasinghe
 
Software development planning and essentials
Software development planning and essentialsSoftware development planning and essentials
Software development planning and essentialsRajesh P
 
Software development planning and essentials
Software development planning and essentialsSoftware development planning and essentials
Software development planning and essentialsRajesh P
 
Episode 23 : PROJECT TIME MANAGEMENT
Episode 23 : PROJECT TIME MANAGEMENTEpisode 23 : PROJECT TIME MANAGEMENT
Episode 23 : PROJECT TIME MANAGEMENTSAJJAD KHUDHUR ABBAS
 
0121_RESOURCE_SoftwareDevelopmentLifecycles.pdf
0121_RESOURCE_SoftwareDevelopmentLifecycles.pdf0121_RESOURCE_SoftwareDevelopmentLifecycles.pdf
0121_RESOURCE_SoftwareDevelopmentLifecycles.pdfBinNguynVn3
 
PMP Training - Project Time Management Part 2
PMP Training - Project Time Management Part 2PMP Training - Project Time Management Part 2
PMP Training - Project Time Management Part 2Skillogic Solutions
 
Day 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptxDay 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptxMohanadRabea1
 
Chapter 4 Software Project Planning.pptx
Chapter 4 Software Project Planning.pptxChapter 4 Software Project Planning.pptx
Chapter 4 Software Project Planning.pptxgadisaAdamu
 
System and Infrastructure Lifecycle Management.pptx
System and Infrastructure Lifecycle Management.pptxSystem and Infrastructure Lifecycle Management.pptx
System and Infrastructure Lifecycle Management.pptxPangeranSilalahi
 
UNIT V - 1 SPM.pptx
UNIT V - 1 SPM.pptxUNIT V - 1 SPM.pptx
UNIT V - 1 SPM.pptxDevnath13
 
Managing the information system project
Managing the information system projectManaging the information system project
Managing the information system projecta23ccb
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..pptPedadaSaikumar
 
Time management pressent
Time management pressentTime management pressent
Time management pressentiklil fairuz
 
Chapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapterChapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapterpreetidamakale
 

Similar a Time management (20)

SPM_UNIT-1(1).pptx
SPM_UNIT-1(1).pptxSPM_UNIT-1(1).pptx
SPM_UNIT-1(1).pptx
 
Proj Mgmt.ppt
Proj Mgmt.pptProj Mgmt.ppt
Proj Mgmt.ppt
 
DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project Management
 
Software development planning and essentials
Software development planning and essentialsSoftware development planning and essentials
Software development planning and essentials
 
Software development planning and essentials
Software development planning and essentialsSoftware development planning and essentials
Software development planning and essentials
 
1. introduction
1. introduction1. introduction
1. introduction
 
Episode 23 : PROJECT TIME MANAGEMENT
Episode 23 : PROJECT TIME MANAGEMENTEpisode 23 : PROJECT TIME MANAGEMENT
Episode 23 : PROJECT TIME MANAGEMENT
 
SPM_UNIT-2.pptx
SPM_UNIT-2.pptxSPM_UNIT-2.pptx
SPM_UNIT-2.pptx
 
0121_RESOURCE_SoftwareDevelopmentLifecycles.pdf
0121_RESOURCE_SoftwareDevelopmentLifecycles.pdf0121_RESOURCE_SoftwareDevelopmentLifecycles.pdf
0121_RESOURCE_SoftwareDevelopmentLifecycles.pdf
 
PMP Training - Project Time Management Part 2
PMP Training - Project Time Management Part 2PMP Training - Project Time Management Part 2
PMP Training - Project Time Management Part 2
 
Day 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptxDay 3 Schedule -walaa (3).pptx
Day 3 Schedule -walaa (3).pptx
 
Chapter 4 Software Project Planning.pptx
Chapter 4 Software Project Planning.pptxChapter 4 Software Project Planning.pptx
Chapter 4 Software Project Planning.pptx
 
Proposal DMS
Proposal   DMS Proposal   DMS
Proposal DMS
 
System and Infrastructure Lifecycle Management.pptx
System and Infrastructure Lifecycle Management.pptxSystem and Infrastructure Lifecycle Management.pptx
System and Infrastructure Lifecycle Management.pptx
 
UNIT V - 1 SPM.pptx
UNIT V - 1 SPM.pptxUNIT V - 1 SPM.pptx
UNIT V - 1 SPM.pptx
 
Managing the information system project
Managing the information system projectManaging the information system project
Managing the information system project
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt
 
Time management pressent
Time management pressentTime management pressent
Time management pressent
 
Chapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapterChapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapter
 
Project management
Project managementProject management
Project management
 

Último

Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...allensay1
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsP&CO
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...amitlee9823
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756dollysharma2066
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMANIlamathiKannappan
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataExhibitors Data
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service AvailableCall Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service AvailableSeo
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876dlhescort
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...amitlee9823
 
Falcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to ProsperityFalcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to Prosperityhemanthkumar470700
 
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...lizamodels9
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with CultureSeta Wicaksana
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...daisycvs
 
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...Sheetaleventcompany
 

Último (20)

(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7
(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7
(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7
 
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors Data
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
Falcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in indiaFalcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in india
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service AvailableCall Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
 
Falcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to ProsperityFalcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to Prosperity
 
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
 
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
 

Time management

  • 1. Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. © 2012 PMstudy.com. All rights reserved
  • 2. Points to Note • Please read chapter 6 from Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fourth Edition, Project Management Institute, Inc., 2008 (pages 129-164). • The study notes explain topics that are important for PMP® exam preparation, and you can expect several questions from these topics. • Pay close attention to all the terms used. It is very important to understand all the concepts discussed in this chapter. • Try to relate the concepts to real life examples. • After reading the study notes, please answer the chapter test questions in this knowledge area. The chapter questions improve your understanding of the concepts discussed in the study notes. © 2012 PMstudy.com. All rights reserved 2
  • 3. What is Project Time Management? • Processes required to manage timely completion of the project. • Processes involved in the project time management include: ◦ Define Activities ◦ Sequence Activities ◦ Estimate Activity Resources ◦ Estimate Activity Durations ◦ Develop Schedule ◦ Control Schedule • Each of these processes occur at least once in every project and in one or more project phases (if the project is divided into phases). Please refer to figure 6-1, PMBOK® Guide Fourth Edition, page 131. This provides an overview of the processes in project time management. © 2012 PMstudy.com. All rights reserved 3
  • 4. Define Activities • Process to identify specific actions that need to be performed to produce project deliverables • Activities are smaller decomposed components of the project work packages, which represent the work necessary to complete the work package. • Tools and Techniques used in Define Activities process: ◦ Decomposition ◦ Rolling wave planning ◦ Templates ◦ Expert judgment • Outputs of Define Activities process are: ◦ Activity list ◦ Activity attribute ◦ Milestone list © 2012 PMstudy.com. All rights reserved 4
  • 5. Decomposition • Subdivides the project work packages into activities • Provides better management control • Leads to activities, the lowest level of the work packages in the Define Activities process • Leads to the work package, the lowest level in the Work Breakdown Structure (WBS) in the Create WBS process, where the deliverables are identified • Process can involve team members. This can lead to better and more accurate results. © 2012 PMstudy.com. All rights reserved 5
  • 6. Sequence Activities • Identifies and documents relationships among project activities • Uses logical relationships • Can be performed by using manual or automated techniques or project management software • Tools and Techniques used for the Sequence Activity process are: ◦ Precedence diagramming method (PDM) ◦ Dependency determination ◦ Applying leads and lags ◦ Schedule network templates © 2012 PMstudy.com. All rights reserved 6
  • 7. Types of Dependencies • Mandatory dependencies: ◦ Also referred to as hard logic ◦ Required as per contract or inherent in the nature of the work ◦ Usually involve physical limitations (e.g., you cannot build the ceiling until walls are constructed) ◦ Are determined by the project management team during the activity sequencing process • Discretionary dependencies: ◦ Also referred to as preferred logic, preferential logic, or soft logic ◦ Are determined by the project management team during the activity sequencing process ◦ Should be used with care and well documented, since they may limit later scheduling options • External dependencies: ◦ Are determined by the project management team during the activity sequencing process ◦ Involve a relationship between project and non-project activities such as activities outside the project team’s control (e.g., dependence on external sources for deliveries, environmental factors governed by statutes, etc.) © 2012 PMstudy.com. All rights reserved 7
  • 8. Precedence Diagramming Method (PDM) • Used in the Critical Path Methodology (CPM) for constructing the project schedule network diagram • Uses nodes to represent the activities and connects them with arrows that reflect dependencies and the logical relationships that exist between the activities • Includes four types of dependencies or logical relationships: ◦ Finish-to-start (FS) ◦ Finish-to-finish (FF) ◦ Start-to-start (SS) ◦ Start-to-finish (SF) • Uses, most commonly, the finish-to-start (FS) precedence relationship • Is also called Activity–On-Node (AON) and is used by most project management software packages • Does not use dummy activities • Does not allow for loops or conditional branches © 2012 PMstudy.com. All rights reserved 8
  • 9. Conditional Diagramming Methods • Allows non-sequential loops or conditional branches • Example: ◦ GERT (graphical evaluation and review techniques) ◦ System dynamics © 2012 PMstudy.com. All rights reserved 9
  • 10. Schedule Network Templates • Can be used to expedite preparation of networks of project activities • Includes entire project or only a portion of it • Portions of a project schedule network diagram are referred to as a subnetwork or a fragment network. © 2012 PMstudy.com. All rights reserved 10
  • 11. Project Schedule Network Diagrams • Is the main output of Sequence activities • Schematic displays of the project’s schedule activities and the logical relationships among them (also referred to as dependencies) • Can be produced manually or using project management software • Can have full project details, or have one or more summary activities © 2012 PMstudy.com. All rights reserved 11
  • 12. Estimate Activity Resources • Estimates the type and quantities of material, people, equipment, or supplies required to perform each activity. • Is closely coordinated with the Estimate Costs process • Tools and Techniques used are: ◦ Expert judgment ◦ Alternatives analysis ◦ Published estimating data ◦ Bottom-up estimating ◦ Project management software © 2012 PMstudy.com. All rights reserved 12
  • 13. Outputs of Estimate Activity Resources • Activity Resource Requirements ◦ Identifies the types and quantities of resources required for each activity in a work package ◦ Determines the estimated resources for each work package by aggregating their requirements like the types and the quantities ◦ Will be documented by including basis of estimates and the assumptions made • Resource Breakdown Structure ◦ Is a hierarchical structure of resources by type and category ◦ Organizes and reports project schedule data with resource utilization information • Project Document Updates ◦ The project documents that may be updated include: • Activity list • Activity attributes • Resource calendars © 2012 PMstudy.com. All rights reserved 13
  • 14. Estimate Activity Durations • Process that requires the estimate of the amount of work effort required and the amount of resources to be applied for approximating the work periods needed to complete the activity. • Uses information on the activity scope of work, required resource types, estimated resource quantities, and resource calendars, as well as historical information • Is progressively elaborated with duration estimates becoming progressively more accurate and of better quality • Should take into consideration the input data’s quality and availability • All assumptions and data used for supporting the duration estimating are documented • Tools and Techniques used are: ◦ Expert judgment ◦ Analogous estimating ◦ Parametric estimating ◦ Three-Points estimating ◦ Reserve analysis © 2012 PMstudy.com. All rights reserved 14
  • 15. Historical Information • Available from: ◦ Project files: Records of previous project results that are detailed enough to help in duration estimating ◦ Commercial duration estimating databases: Available for standard tasks ◦ Team members’ past experience: Individual members of the project team, who worked on prior similar projects, and who might be able to recollect details of estimates from those projects for possible application in the current project © 2012 PMstudy.com. All rights reserved 15
  • 16. Analogous Estimating (Top-Down Estimating) • An estimating technique • Uses the parameters from a previous, similar project as the basis for estimating the same parameter for a future project • It is a gross value estimating approach • Uses historical information and expert judgment • Less costly and time consuming than other techniques • Generally less accurate • Most reliable when: ◦ Previous activities are similar in fact and not just in appearance. ◦ Individuals preparing the estimates have the needed experience. © 2012 PMstudy.com. All rights reserved 16
  • 17. Parametric Estimating • Uses a statistical relationship between historical information and other variables to calculate an estimate for activity parameters • Determines how many times the specific work category is going to be performed in the given activity • Can be applied to a total project or segments of a project • Activity durations=Quantity of work to be performed x Labor hours per unit of work © 2012 PMstudy.com. All rights reserved 17
  • 18. Develop Schedule • Analyzes activity sequences, durations, resource requirements, and schedule constraints to create the project schedule • Iterative process • Determines the project activities’ scheduled start and finish dates • Determines the milestones’ scheduled start and finish dates • Tools and Techniques used are: ◦ Schedule network analysis ◦ Critical path method ◦ Critical chain method ◦ Resource leveling ◦ What-if scenario analysis ◦ Applying leads and lags ◦ Schedule compression ◦ Scheduling tool © 2012 PMstudy.com. All rights reserved 18
  • 19. Constraints and Milestones Constraints: • Factors that will limit a management team’s options for a defined course of action. • An internal or external restriction that will affect the project’s performance • Internal to the project - Dates imposed on any planned activity, used to restrict the start or finish dates for the tasks, “start no earlier than” and “finish no later than” types, etc. • External to the project - Market window on a technology project, weather restrictions on outdoor activities, government-mandated compliance requirements, etc. Key event or major milestone schedule: • Summarizes schedules that identify significant or major milestones in the project • Denotes identified deliverables and their specified dates of completion, as requested by project sponsor, customer, or other stakeholders • Once scheduled, the milestones may be difficult to shift © 2012 PMstudy.com. All rights reserved 19
  • 20. Mathematical Analysis • Involves calculating theoretical early, and late start and finish dates • Popular techniques: ◦ Critical Path Method (CPM): • Used to determine the amount of flexibility in scheduling various logical network paths in the project schedule network • Used to determine the minimum total duration of the project • Used to calculate a single deterministic early and late start and finish date for each activity based on specified sequential network logic and activity duration estimates ◦ Project Evaluation and Review Technique (PERT): • A technique that is used to estimate the activity duration by applying a weighted average of optimistic (to), pessimistic (tp), and most likely (tm) estimates, when there is uncertainty with the individual activity estimates. • Analysis calculates the expected activity duration (te) as indicated below: te = to+ 4tm + tp 6 © 2012 PMstudy.com. All rights reserved 20
  • 21. Schedule Compression • Shortens the project schedule to meet the imposed dates, schedule’s constraints, or other objectives without changing the scope of the project • Techniques used are: ◦ Crashing: • A technique by which cost and schedule tradeoffs are analyzed to determine how to obtain the greatest amount of compression for the least incremental cost • Will only work for those activities where additional resources will reduce the duration • Does not always produce a viable alternative • Could increase either risk or cost, or both risk and cost of the project ◦ Fast tracking: • A technique of performing activities in parallel that would normally be done in sequence • Works only if activities overlap • Can result in rework and increased risk © 2012 PMstudy.com. All rights reserved 21
  • 22. Simulation, Resource Leveling, and Critical Chain Method Simulation: • Involves calculating multiple project durations with different sets of activity assumptions to assess the feasibility of the project schedule under adverse conditions, such as delay in major component delivery, strike, etc. • Common techniques: ◦ Monte Carlo analysis ◦ What-if analysis (using logic network to compute different scenarios) Resource Leveling Heuristics • Done because mathematical analysis produces a preliminary early-start schedule that requires more than the allocated resources during certain time periods e.g., Rule of thumb – “allocate scarce resources to critical path activities first.” • Often results in a project duration that is longer than the preliminary schedule. (Also called “resource based method”). Critical Chain Method: • A schedule network analysis technique that modifies the project schedule to account for limited resources. © 2012 PMstudy.com. All rights reserved 22
  • 23. Project Schedule • Should have at least a planned start date and a planned finish date for each activity. • A targeted schedule can also be made with a defined target start and end date for every activity. • Can be presented in detail or in summary form (referred to as master schedule or milestone schedule) • Often presented graphically or in tabular form • Graphically presented using: ◦ Milestone charts ◦ Bar charts ◦ Project schedule network diagrams © 2012 PMstudy.com. All rights reserved 23
  • 24. Schedule Updates, Schedule Baseline, Re- baselining, and New Target Schedules • Schedule Updates: ◦ Any modifications to the project schedule • Schedule baseline: ◦ Component of the project plan, which is accepted and approved by the project management team ◦ Has a baseline start date and baseline finish date. It is an updated version of the project schedule and is developed from the schedule network analysis ◦ Provides the basis for measuring and reporting schedule performance ◦ Can be changed to incorporate the approved change requests related to project scope changes/resources/duration estimates • Re-baselining: ◦ Performed if schedule delays are very severe ◦ Used to provide realistic data to measure performance (done in only extreme cases, because all historical data will be lost). • New target schedules: ◦ If there are small changes to the project schedule, then the schedule baseline is kept constant – but new target schedules may be used. ◦ If the project schedule gets delayed severely, then a new target schedule has to be developed, which forecasts the start and finish dates needed for providing realistic data for directing work, and measuring performance and progress. © 2012 PMstudy.com. All rights reserved 24
  • 25. Three Point Estimate • With limited information to find out activity durations, the three-point estimation technique is used to find a distribution of the durations for different scenarios. • Three estimates are produced based on prior experience or best-guesses: ◦ O = the optimistic estimate ◦ M = the most likely estimate ◦ L = the least likely estimate. • These values are used to calculate an E value for the estimate and a standard deviation (SD) where: ◦ E = (O + 4M + L) / 6 ◦ SD = (L − O)/6 © 2012 PMstudy.com. All rights reserved 25
  • 26. Activity on Node • Activity on Node (AON) or Precedence Diagramming Method (PDM) showcases the inter- dependencies among various project activities. • This technique is used to draw the project schedule network diagrams; e.g. Critical Path Network Diagram to identify the Critical path and the float for each activity • In an AON diagram, each rectangle box represents a node and a project activity. These rectangular boxes are connected using arrows to the succeeding activity box thereby portraying the project dependencies. • Activity on Node uses four types of dependencies. ◦ Finish to Start (FS): The end of one activity is required for the start of the next one. This is the most common dependency ◦ Finish to Finish (FF): The end of the first activity is required for the second activity to finish ◦ Start To Start (SS): The second activity starts only after the first activity has started ◦ Start to Finish (SF): second activity cannot be finished until first activity starts. © 2012 PMstudy.com. All rights reserved 26