1. Role of Project Engineering in
Project Management
Dr. P. M. Deshpande
Ph.D.(Chem), M. Tech. Energy System (IIT),
Chartered Engineer ,Fellow of IE India
2. Engineering and Infrastructure Project
• To develop the facility for product
– Generation of Electricity
– Transmission of Electricity
– Water treatment plant
– Waste water treatment plant
– Automobile factory
• To develop the facility for service
– Air port
– High ways
– Ports
6/13/2019 2Project Managers Cliub of PUNE
3. Definition
• The word project comes from
the Latin word projectum from the Latin
verb proicere, "before an action"
• In turn comes from pro-, which denotes
precedence, something that comes before
something else in time
• paralleling the Greek πρό and iacere, "to do".
The word "project" thus originally meant
"before an action".
6/13/2019 3Project Managers Cliub of PUNE
4. Principle of Project
The principle is Concept To Completion
1st step DEFINE THE GOLE
2nd step DEVELP CONCEPT
3rd step DEVELP PRELIMINARY DESIGN
4TH step STUDY THE FESIBLITY –Techno -
Economics
5TH step DETAIED OUT ENGGINEERING DESIGH
PPF-PF-PD-PE-PH-PO
6/13/2019 4Project Managers Cliub of PUNE
7. Deign Engineering Process
• Develop the preliminary design (Basic Engineering)
– for engineering feasibility
– Based on standard engineering practice
• System engineering ( Process Design- PFD/ SFD)
– Defining System
– Defining size
Process Design Drawing
• Detail Engineering
– System engineering
– Product, Process Equipment Detailing
– Plant layout
• Different engineering drawings
– Bill of Material
– Specifications
6/13/2019 7Project Managers Cliub of PUNE
8. Project Engineering
• Study of engineering specification
• Bill of material BOM
• Convert to BOQ based on wastage, process,
– Example is bar bending
• Study the plant layout
• Define the erection/ contraction /method
• Identify and define
civil/mechanical/electrical/instrumentation scope
• Define/redefine WBS for constructability
• Identify the resources
- unskilled/ skilled/semi-skilled/technical
List out the requirements to convert design in to work for
the development of facility
6/13/2019 8Project Managers Cliub of PUNE
9. Scope of Project
The project goal is achieved if the scope of project is
detailed out in different phases of project
• Project Feasibility
• Project Development
• Project Execution
• Project Handing over
• Project Operation
Project scope is defined by project engineering in
terms of engineering details , specification , resources
The successes of project in terms of cost, time, and
different factors depends on implementation of
project management principles
6/13/2019 9Project Managers Cliub of PUNE
10. Project Development
Project development is based of Project Feasibility DPR
– To develop project for capacity as per project goal
– Detailed out design to achieve project goal
– To define the scope and its specification
– Define the required resources for project
– Define the knowledge, technology, engineering, construction
needs
– Define WBS
– Define mechanical, electrical, civil , instrumentation and allied
work based on project
– Develop Construction plan
– All these activates are based on Project Engineering Inputs
• ALL OUTPUTS OF THESE ACTIVITEIES LEADS TO
SPECIFICATIO, QUANTITY, ACTIVITY FOR
CONSTUCTION AS INPUT FOR PROJECT
PLANNING AND SUBSEQUET REVISIONS
6/13/2019 10Project Managers Cliub of PUNE
11. Stack holders Aspects Of
project
Phase of Project Project
operation
Finance Scope of project Project
Feasibility
Tender
Bidding
Client legal Project
Development
Planning/sch
eduling
PMC /EPC Commercial Project
Execution
Contracting
Technology
Provider
Finanancial
Social
Project
Handover
Execution
Contractor Planning Project
Operation
Cost
estimation
Engineering
Contractor
Safety, Risk Project Handover Funding
Overview of Project Management Environment
6/13/2019 11Project Managers Cliub of PUNE
12. Corporate Project Stage Different contributes
Client Preliminary stage Design
Consultant Project Feasibility Scope
Technology Provider Project Development Tender, Contract
EPC/PMC Project Execution Cost estimation
Contractor Project Handover Planning Scheduling
Project OPERATI On Finance, Execution
Responsibilities of stack holder
6/13/2019 12Project Managers Cliub of PUNE
13. Project Management –PMBOK approach
• Project Stack holder
• Project Organization
• Project management process
• Project integration
• Project scope management
• Project time management
• Project cost management
• Project quality management
• Project human resource management
• Project communication management
• Project procure management
• Project sack holder management
6/13/2019 13Project Managers Cliub of PUNE
14. PROJECT ENGINEERING
• Detailed Project Engineering is core activity
• The scope and service by engineers are Integrated by
engineering
• It is a multi disciplinary engineering team activity
• Ensure seamless integration project phases
• Helps in understanding interface activities and scope
• Plant design , plant O&M needs (productivity, design
duties) and engineering requirements are integrated
• Contribution of project engineers of stack holds ensure
timely completion of project
• Project Planning and project performance improve
• Leads to higher proficiency of project management
6/13/2019 14Project Managers Cliub of PUNE
15. Mechanical
• Prepare final layout and flow sheet based on the main
machinery selected, with proper code.
• Review and approve data and drawings from suppliers.
• Prepare general arrangement drawings for ducting and
chutes.
• Review & approve fabrication drawings (steel GAs) for
all chutes, ducts. Belt conveyor galleries, trestles, short
supports, foundations and transfer towers.
• Prepare steel GA’s for any interface areas, where
required.
• Procurement Services - Mechanical Contractor.
6/13/2019 15Project Managers Cliub of PUNE
16. Electrical
• System design for power system, Earthing system and
lightning protection system for the plant, based on the
machinery selected, approved layout/ flow-sheet and
to keep the capital and operating costs at the optimum
level.
• Procurement Services – Electrical Equipment.
• Scrutinize the GA drawings, power and control
schematics and design details for the equipment
submitted by the suppliers.
• Prepare layout drawings and general arrangement with
fixing detail for various electrical systems in the plant.
• Procurement Services - Electrical Contractor.
6/13/2019 16Project Managers Cliub of PUNE
17. Instrumentation and safety
• Prepare control concept of the plant, identify number of
control rooms, type of microprocessor controls, control
loops for optimised operation of the plant, system
architecture for central control based on latest
programmable controllers available.
• Procurement Services - total C&I system as a single
turnkey package.
• Scrutinize the GA drawings, control schematics,
interface/inter-connection diagrams, I/O addresses etc
submitted by the supplier.
• Prepare detailed design and schemes for various
components of the C&I system for the entire plant.
6/13/2019 17Project Managers Cliub of PUNE
18. Civil and Structural
• Prepare specifications for releasing to tenders for carrying out soil
investigation and topographic survey work to the extent required. Supervise
and evaluate soil investigation results and topographic survey carried out by
independent external specialist agencies.
• Design foundations, buildings and structural's in conformity with the project
engineering and general arrangement drawings for the process departments
and material handling sections. Foundations will be designed on the load data
provided by different suppliers of the machinery.
• The design of all duct supports, conveyor belt supports / foundations, bins
and hoppers, stacks, stairs, platforms, railing etc shall form part of civil
design scope.
• Prepare RCC working drawings to enable the civil contractor(s) to prepare
bar bending schedule and execute the work at site.
• Prepare structural steel drawings (Steel GA’s only) “Good for fabrication”
giving details of structural system, shape and size of members, splices details
for the members to enable the fabricator to prepare shop floor details.
• Prepare schematic drawings for the plant services within the plant area such
as Roads, drainage, Sanitary system etc.
• Procurement Services - Civil and structural Contractor.
6/13/2019 18Project Managers Cliub of PUNE
19. Provide requisite technical support for obtaining clearances from
relevant statutory agencies /authorities.
Coverage Greenfield Brownfield
Moderniza
tion
Rehabilitat
ion
Process Engineering √ √ √ √
Mechanical Engineering √ √ √ √
Electrical Engineering √ √ √ √
Instrument & Control Engineering √ √ √ √
Civil & Structural Engineering √ √ √ √
6/13/2019 19Project Managers Cliub of PUNE
20. Methodology:
• Mechanical, Electrical, Instrumentation & control
and Civil & Structural engineering follows clearly
established guidelines and practices align with
applicable statutory norms/ standards.
• Identify scope
• Indentify interface
– Engineering
– Scope
– Alignment
6/13/2019 20Project Managers Cliub of PUNE
21. Benefits:
• Access to Holtec’s vast database for advance engineering
and early lead of civil works construction drawings.
• Cross benefit from knowledge of different engineering
standards & practices of global cement manufacturing
players.
• Availability of integrated multi disciplinary engineering
team under one roof.
• Streamlined co-ordination with one lead manager.
• Arresting omissions/ commissions at design stage.
• Cross benefits due to incorporation of solutions
implemented in other projects with resultant benefit both for
CAPEX as well as O&M.
6/13/2019 21Project Managers Cliub of PUNE
22. Case study –Power plant cooling tower project
Process Principle -Basic Engineering
In this process cooling water is circulated across the cooling tower to remove the
heat generated in process plant equipments. The cooling water from cooling
tower is supplied to process equipments of plant; and returned to cooling tower
from process as closed loop water system. This system maintains the
temperature of process. The cooling water picks up the heat from process
equipments; this results in rise in temperature of cooling water. This heat is
rejecting to environment in cooling tower. The cooling water temperature is
reduced by3-7 oC depending on ambient conditions of project site. This drop in
temperature depends on geographical local conditions such as ambient
temperature, humidity and its variation during the day and different seasons.
6/13/2019 22Project Managers Cliub of PUNE
23. Case-Project Engineering
• Process steps - basic engineering
• Process detailing - Sizing of equipment
– Cooling tower
– Pump
– Heat exchanger
– Piping
– Instrumentation
• Detail engineering
– Detailing of Components of cooling tower
– Different sizes pipe rooting
– Electrical system detailing
– Plant layout
• Specifications of plant
– Civil, Mechanical ,electrical instrumentation
6/13/2019 23Project Managers Cliub of PUNE
24. Cooling Tower system
1. Civil Engineering Scope
2. Mechanical Engineering scope
3. Electrical Engineering Scope
4. Instrumentation Engineering Scope
5. Interface engineering activities
6. Resources for work and interface
Onion Model for Engineering Projects
6/13/2019 24Project Managers Cliub of PUNE
25. Civil work Mechanical Work Electrical work Instrumentation
work
Design conditions
check with site
conditions
Design ,fabrication
and installation of
fame for fan
Pump and motor
assembly
Control Logic
design, installation
and commissioning
Civil work of
cooling water room
Installation of fan Fan and motor
assembly
Installation of
instruments on
piping system
Civil work for
Chimney
Alignment of fan
and motor
Local control panel Positioning of
instrument and its
erection
commissioning
Foundation work for
CWC pump
Water distribution
system in cooling
tower
Energy Meters
Piping of circulation
pump
Details of scope to Define the activates for work
6/13/2019 25Project Managers Cliub of PUNE