SlideShare una empresa de Scribd logo
1 de 4
Descargar para leer sin conexión
Safe Use of M obile Cranes in
Constr uction Sites
OSD / ENG CIR / LE / 4/01

By Occupation Safety and Health Division
Ministry of Manpower

Introduction
There are approximately 10,000 mobile
cranes being used in Singapore. The
majority of these cranes are used in the
construction industry to increase the
productivity of the building construction.
However the misuse, failure to follow
safe practices and procedures or
complacency often led to accidents.
Such
accidents
could
have
a
catastrophic impact to the safety of
workers and members of public.
This safety circular is meant to provide
guidelines for the safe use of mobile
cranes in construction sites.

Causes of Crane Accidents
The main causes of accidents that had
been identified can be traced to the
following:
a) Lack of planning and supervision;
b) Incorrect siting or setup of cranes;
c) Failure to correctly calculate or
estimate the load;
d) Failure of personnel to carry out the
correct procedures;
e) Careless & Complacent;
f) Use of wrong lifting gears;
g) Faulty devices or machines;
h) Lack of proper maintenance.
Accident Case 1: August 2000

Accident Statistics
In year 2000, there were a total of 32
incidents involving mobile cranes, of
which 2 cases resulted in fatalities and
16 cases resulted in varying degrees of
injury.
Another 14 cases involved
damages to properties.
No. of accidents involving
mobile cranes in year 2000
16

The boom of a crawler crane flipped
backwards when the steel casing (for
bore piling operation) it was lifting broke
at the tip where it was shackled. The
boom and the hook block landed on the
expressway and hit a vehicle.

12
8
4
0
Resulted in Resulted in Resulted in
death of Injury to damages to
worker
workers properties
only

Safe Use of Mobile Cranes in Construction Sites

Selecting the crane
Cranes should always be selected to
handle the maximum anticipated load
with
capacity
to
spare.
Other
consideration for the selection of the
cranes are the nature of lift, ground
condition, site constraints, etc.

1
The crane operator
The crane shall only be operated by a
trained and competent operator. The
operator must also be registered with
the Chief Inspector of Factories.
Documents for the crane
When the crane arrives on site, the
following documents should come along
with the crane for inspection and review
when requested:
a) A valid Certificate of Test / Thorough
Visual
Examination
of
Lifting
Equipment for the mobile crane (LM
Certificate);
b) Valid Certificates of Test / Thorough
Visual
Examination
of
Lifting
Equipment for all lifting gears that
comes with the crane;
c) The log-book or log sheet for the
recording of the operational tests
carried out by the operator before the
start of every workshift;

If the operator is unable to produce the
above documents, the crane supplier
should be contacted and the documents
obtained before the machine is put into
use. It is advisable to state that the
production of these documents will be
required when the crane is hired.
Siting of Crane
The stability of the crane depends
heavily on the proper siting and setting
of the crane. Unless stated by the
manufacturer, the crane should have its
outriggers fully extended with the
wheels off the ground. The ground
should be level and
capable of supporting
the full weight of the
crane and its load. In
addition, sufficient and
suitable packing in the
form of steel plates or

Safe Use of Mobile Cranes in Construction Sites

timber mats should be placed under the
outriggers to evenly distribute the
weight.
The crane should also be positioned so
that:
a) The operator has a clear view of
the operation as far as practicable;
b) There is sufficient operating space;
c) It is well away from edges of
excavation and fixed structures
which people may be trapped by
the
moving
parts
such
as
counterweights, etc

Planning and Supervision
All lifting operation should be properly
planned by a competent person before
the actual execution and not left solely
to the crane operator.
Investigation into crane accidents
revealed that one of the root causes of
these accidents was due to lack of
proper planning and supervision. This is
particularly so for simple routine lifts.
Hence, all contractors are advised not to
be complacent during any lifting
operation, and to plan and supervise the
operation carefully.
Site constraints that would have an
impact on the safe operation of the
lifting should be considered before the
execution of the lift. Examples of such
constraints are:
a) Lifting next to or over an
excavation pit;
b) Materials or machines placed
along the access way thereby
reducing the available space to
extend the outriggers;
c) Site is located nearby busy traffic,
or existing building or structures.

2
Careful planning is especially critical fpr
difficult lifts such as pick and carry
operations, tandem lifting and tilt-up
operation.
“The change in radius caused by
booming down and/or telescoping out
shall be considered when determining
the lifting capacity of the crane. The
reduction in the boom angle, caused by
the load when just lifted off the ground,
and the consequential increase in the
radius shall also be considered in
determining the safety of a lift.”
– SS CP 37: Safe Use of Mobile Cranes

Special consideration should be given
when the load is required to be placed
at a distant further away from the crane
than when it is being picked up, i.e. an
increase in the crane’s working radius.
Personnel
The Factories (Operation of Cranes)
Regulations
1998
requires
the
appointment of the following personnel
for all mobile crane operation:
• Trained lifting supervisor;
• Trained riggers; and
• Trained signalman.
Fatal Accident Case 2: August 2000

All contractors are advised to familiarise
themselves with the duties of these
appointees as spelt out in the regulation
and ensure that the only trained and
competent personnel are appointed.
In the case where the lifting operation is
out of the view of the operator (such as
lifting a load from the rooftop of a
building), the occupier is obligated to
appoint sufficient number of signalman
for the operation.
The Load
The weight of the load should always be
known from specifications or through
calculations. It is important to note that
the safe working loads (SWL) indicated
in most load capacity charts are gross
SWL. This means that the weight of the
hook block, and all lifting gears used
must be deducted from this gross SWL
to obtain the net SWL that the crane is
able to lift at that configuration.
Load Radius Indicator
The mandatory load radius indicator
gives the safe working load at the
configuration that the crane has been
set, and gives a warning signal when
the radius is unsafe. The indicator:
•
•

The deceased
and the
platform fell
from the 5 th
storey to the
ground.

The crane operator lifted and placed a
pallet of bricks onto a work platform on
th
the 5 storey without being instructed or
signaled to do so.
The platform
collapsed together with a worker. The
worker died subsequently

Safe Use of Mobile Cranes in Construction Sites

•

must be calibrated regularly;
must be configured for both main and
auxiliary hooks (when both hooks are
used)
The operator must be trained to use /
set the indicator correctly to tally with
the actual configuration adopted;

It is important to note that the load
radius indicator served primarily as an
operational aid. Although the indicator
can warn the operator of an impending
overload, it should not be used as the
only tool to test the stability limit of the
crane during operations.

3
Supervisors and foreman are advised
not to rely on the operator to use the
indicator to determine the weight of the
load. They should instead have prior
knowledge of the weight of the load.
This is especially critical when the lifting
operation involves the dismantling of
machinery or structure from heights.
Singapore
Standards
Code
of
Practice 37: Safe Use of Mobile
Cranes: 2000
The Factories (Singapore Standards
and Code of Practice) Order 2001 has
gazetted the SS CP 37 as a mandatory
code for compliance by any user. The
code
provides
comprehensive
requirements on the application, safe
operation, maintenance and testing of
mobile cranes.
The guidelines and requirement laid out
in this circular are extracted from the
code.
The crane's safe working load is always
indicated for freely suspended loads. It is
expressly forbidden to use the crane to drag
any load, or any operation that may cause the
hoist line to be out of plumb.

Accident Case 3: June 2000
The crane operator had lowered his hook
block from an opening into the basement
infrastructure.
The workers at the
basement then pulled the hook block
away from the opening and rigged up a
truss structure.
They then gave the
signal to the operator to lift. The boom of
the crane snapped when the load was
dragged out.

û
Dragging is expressively forbidden

Checks and Maintenance
The crane should be in good working
condition when it arrives on site and
before the start of the workshift. In
addition to the statutory annual
inspection,
the
manufacturer’s
recommendation on the inspection and
maintenance regime should also be
followed closely.
Types

Slewing should be done slowly to maintain
control of the load.
Tag lines should be used where applicable to
minimise swing

Functional
Checks

The operator should stay at the controls at all
time when the loads are suspended.
Interpolation of the safe working load in the
load capacity is disallowed unless specifically
allowed by the manufacturer. Extrapolation is
strictly disallowed.
No additional counterweight shall be added to
the crane unless specifically allowed by the
manufacturer.

All contractors are advised to familiarise
themselves with the requirement
stipulated in the code.

Safe Use of Mobile Cranes in Construction Sites

Integrity
Checks

Checks
• Check limit switches e.g.
over-derricking; over
hoisting
• Slewing
• Telescoping
• Travelling
• Safety devices
• Wire ropes
• Rope terminations
• Hook block
• Boom section
• Rope pulleys
• Rope guards

The checks listed in this table are not exhaustive.

Issued by
THE CHIEF INSPECTOR OF FACTORIES
MINISTRY OF MANPOWER

4

Más contenido relacionado

La actualidad más candente

Crane operator safety procedure
Crane operator safety procedureCrane operator safety procedure
Crane operator safety procedure
Abdul Shukur
 
Safe use of Mobile Cranes
Safe use of Mobile CranesSafe use of Mobile Cranes
Safe use of Mobile Cranes
Mihajlo Stupar
 
Lifting plans for non-crane lifts on small construction sites
Lifting plans for non-crane lifts on small construction sitesLifting plans for non-crane lifts on small construction sites
Lifting plans for non-crane lifts on small construction sites
Simon Faulkner-Duke
 

La actualidad más candente (20)

Crane Safety Awareness by University of Texas Arlington
Crane Safety Awareness by University of Texas ArlingtonCrane Safety Awareness by University of Texas Arlington
Crane Safety Awareness by University of Texas Arlington
 
Crane Operation - Lifting
Crane Operation -  LiftingCrane Operation -  Lifting
Crane Operation - Lifting
 
36 elevating employees
36 elevating employees36 elevating employees
36 elevating employees
 
Safe Operations of Cranes, Hoists and Truck Hoists by Reagan Safety
Safe Operations of Cranes, Hoists and Truck Hoists by Reagan SafetySafe Operations of Cranes, Hoists and Truck Hoists by Reagan Safety
Safe Operations of Cranes, Hoists and Truck Hoists by Reagan Safety
 
Crane Incident Handbook
Crane Incident Handbook Crane Incident Handbook
Crane Incident Handbook
 
Crane operator safety procedure
Crane operator safety procedureCrane operator safety procedure
Crane operator safety procedure
 
CRANE SAFETY HANDBOOK
CRANE SAFETY HANDBOOK CRANE SAFETY HANDBOOK
CRANE SAFETY HANDBOOK
 
Rigging Requirements Training by L&I Washington
Rigging Requirements Training by L&I WashingtonRigging Requirements Training by L&I Washington
Rigging Requirements Training by L&I Washington
 
Safe use of Mobile Cranes
Safe use of Mobile CranesSafe use of Mobile Cranes
Safe use of Mobile Cranes
 
A Part 6 Lifting Operations
A  Part 6 Lifting OperationsA  Part 6 Lifting Operations
A Part 6 Lifting Operations
 
Lifting plan template
Lifting plan templateLifting plan template
Lifting plan template
 
10. lifting-plan-checklist-and-method-statement-2
10. lifting-plan-checklist-and-method-statement-210. lifting-plan-checklist-and-method-statement-2
10. lifting-plan-checklist-and-method-statement-2
 
SAFE USE OF LIFTING EQUIPMENT LEEA
SAFE USE OF LIFTING EQUIPMENT LEEASAFE USE OF LIFTING EQUIPMENT LEEA
SAFE USE OF LIFTING EQUIPMENT LEEA
 
Crane | Crane Safety | Crane Safety Parts | Gaurav Singh Rajput
Crane | Crane Safety | Crane Safety Parts | Gaurav Singh RajputCrane | Crane Safety | Crane Safety Parts | Gaurav Singh Rajput
Crane | Crane Safety | Crane Safety Parts | Gaurav Singh Rajput
 
Aerial Lifts and Elevated Platform Safety by QSC Safety Consulting
Aerial Lifts and Elevated Platform Safety by QSC Safety ConsultingAerial Lifts and Elevated Platform Safety by QSC Safety Consulting
Aerial Lifts and Elevated Platform Safety by QSC Safety Consulting
 
Lifting plans for non-crane lifts on small construction sites
Lifting plans for non-crane lifts on small construction sitesLifting plans for non-crane lifts on small construction sites
Lifting plans for non-crane lifts on small construction sites
 
HSE
HSEHSE
HSE
 
Preventing and Protecting Against OSHA’s Top 10 Workplace Accidents
Preventing and Protecting Against OSHA’s Top 10 Workplace AccidentsPreventing and Protecting Against OSHA’s Top 10 Workplace Accidents
Preventing and Protecting Against OSHA’s Top 10 Workplace Accidents
 
Scissor lift safety
Scissor lift safetyScissor lift safety
Scissor lift safety
 
Suspended personnel platforms 2017
Suspended personnel platforms 2017Suspended personnel platforms 2017
Suspended personnel platforms 2017
 

Similar a 2000 08 safe use of mobile cranes in construction sites

9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docx9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
Crane-Safety-PowerPoint-Presentation.pptx
Crane-Safety-PowerPoint-Presentation.pptxCrane-Safety-PowerPoint-Presentation.pptx
Crane-Safety-PowerPoint-Presentation.pptx
VikasMore37
 
TS-1 - PPT - VISHNURAJ G.ppt
TS-1 - PPT - VISHNURAJ G.pptTS-1 - PPT - VISHNURAJ G.ppt
TS-1 - PPT - VISHNURAJ G.ppt
ajith30276
 

Similar a 2000 08 safe use of mobile cranes in construction sites (20)

9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docx9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docx
 
9 lifting operations with tower crane risk assessment templates
9 lifting operations with tower crane risk assessment templates9 lifting operations with tower crane risk assessment templates
9 lifting operations with tower crane risk assessment templates
 
Rigger safety .pdf
Rigger safety                        .pdfRigger safety                        .pdf
Rigger safety .pdf
 
Rigging Course .pdf
Rigging Course                       .pdfRigging Course                       .pdf
Rigging Course .pdf
 
Truck crane training bill brown
Truck crane training bill brownTruck crane training bill brown
Truck crane training bill brown
 
Crane-Safety-PowerPoint-Presentation.pptx
Crane-Safety-PowerPoint-Presentation.pptxCrane-Safety-PowerPoint-Presentation.pptx
Crane-Safety-PowerPoint-Presentation.pptx
 
Campion_Crane-Safety.pdf
Campion_Crane-Safety.pdfCampion_Crane-Safety.pdf
Campion_Crane-Safety.pdf
 
Safety Tip: 10 Steps to Safer Crane Operation
Safety Tip: 10 Steps to Safer Crane OperationSafety Tip: 10 Steps to Safer Crane Operation
Safety Tip: 10 Steps to Safer Crane Operation
 
الروافع البرجيه واخطارها والتعامل معها. ومكوناتها
الروافع البرجيه واخطارها والتعامل معها. ومكوناتهاالروافع البرجيه واخطارها والتعامل معها. ومكوناتها
الروافع البرجيه واخطارها والتعامل معها. ومكوناتها
 
Crane Safety Tips for Construction Project..pdf
Crane Safety Tips for Construction Project..pdfCrane Safety Tips for Construction Project..pdf
Crane Safety Tips for Construction Project..pdf
 
TS-1 - PPT - VISHNURAJ G.ppt
TS-1 - PPT - VISHNURAJ G.pptTS-1 - PPT - VISHNURAJ G.ppt
TS-1 - PPT - VISHNURAJ G.ppt
 
apm-et13e-chapter-16-hoisting-and-conveying-equipment.ppt
apm-et13e-chapter-16-hoisting-and-conveying-equipment.pptapm-et13e-chapter-16-hoisting-and-conveying-equipment.ppt
apm-et13e-chapter-16-hoisting-and-conveying-equipment.ppt
 
Lifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptxLifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptx
 
22 casting of concrete columns risk assessment templates
22 casting of concrete columns risk assessment templates22 casting of concrete columns risk assessment templates
22 casting of concrete columns risk assessment templates
 
www.scanrent.com.au
www.scanrent.com.au www.scanrent.com.au
www.scanrent.com.au
 
Quality Control Operator Training &.pptx
Quality Control Operator Training &.pptxQuality Control Operator Training &.pptx
Quality Control Operator Training &.pptx
 
MEWP TRAINING 27.07.2022.pptx
MEWP TRAINING 27.07.2022.pptxMEWP TRAINING 27.07.2022.pptx
MEWP TRAINING 27.07.2022.pptx
 
24 casting of bridge decks risk assessment templates
24 casting of bridge decks risk assessment templates24 casting of bridge decks risk assessment templates
24 casting of bridge decks risk assessment templates
 
32 use of aluminium mobile scaffolding risk assessment templates
32 use of aluminium mobile scaffolding risk assessment templates32 use of aluminium mobile scaffolding risk assessment templates
32 use of aluminium mobile scaffolding risk assessment templates
 
23 casting of concrete slabs risk assessment templates
23 casting of concrete slabs risk assessment templates23 casting of concrete slabs risk assessment templates
23 casting of concrete slabs risk assessment templates
 

Último

Structuring and Writing DRL Mckinsey (1).pdf
Structuring and Writing DRL Mckinsey (1).pdfStructuring and Writing DRL Mckinsey (1).pdf
Structuring and Writing DRL Mckinsey (1).pdf
laloo_007
 
Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for Viewing
Nauman Safdar
 
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al MizharAl Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
allensay1
 
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pillsMifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
Abortion pills in Kuwait Cytotec pills in Kuwait
 
Mifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in Oman
Mifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in OmanMifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in Oman
Mifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in Oman
instagramfab782445
 

Último (20)

Structuring and Writing DRL Mckinsey (1).pdf
Structuring and Writing DRL Mckinsey (1).pdfStructuring and Writing DRL Mckinsey (1).pdf
Structuring and Writing DRL Mckinsey (1).pdf
 
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAIGetting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
 
TVB_The Vietnam Believer Newsletter_May 6th, 2024_ENVol. 006.pdf
TVB_The Vietnam Believer Newsletter_May 6th, 2024_ENVol. 006.pdfTVB_The Vietnam Believer Newsletter_May 6th, 2024_ENVol. 006.pdf
TVB_The Vietnam Believer Newsletter_May 6th, 2024_ENVol. 006.pdf
 
Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for Viewing
 
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
 
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al MizharAl Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
 
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pillsMifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
 
BeMetals Investor Presentation_May 3, 2024.pdf
BeMetals Investor Presentation_May 3, 2024.pdfBeMetals Investor Presentation_May 3, 2024.pdf
BeMetals Investor Presentation_May 3, 2024.pdf
 
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGParadip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
 
Cannabis Legalization World Map: 2024 Updated
Cannabis Legalization World Map: 2024 UpdatedCannabis Legalization World Map: 2024 Updated
Cannabis Legalization World Map: 2024 Updated
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
Mifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in Oman
Mifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in OmanMifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in Oman
Mifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in Oman
 
Buy Verified TransferWise Accounts From Seosmmearth
Buy Verified TransferWise Accounts From SeosmmearthBuy Verified TransferWise Accounts From Seosmmearth
Buy Verified TransferWise Accounts From Seosmmearth
 
Falcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business Potential
 
Falcon Invoice Discounting: Aviate Your Cash Flow Challenges
Falcon Invoice Discounting: Aviate Your Cash Flow ChallengesFalcon Invoice Discounting: Aviate Your Cash Flow Challenges
Falcon Invoice Discounting: Aviate Your Cash Flow Challenges
 
Falcon Invoice Discounting: Tailored Financial Wings
Falcon Invoice Discounting: Tailored Financial WingsFalcon Invoice Discounting: Tailored Financial Wings
Falcon Invoice Discounting: Tailored Financial Wings
 
Arti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfArti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdf
 

2000 08 safe use of mobile cranes in construction sites

  • 1. Safe Use of M obile Cranes in Constr uction Sites OSD / ENG CIR / LE / 4/01 By Occupation Safety and Health Division Ministry of Manpower Introduction There are approximately 10,000 mobile cranes being used in Singapore. The majority of these cranes are used in the construction industry to increase the productivity of the building construction. However the misuse, failure to follow safe practices and procedures or complacency often led to accidents. Such accidents could have a catastrophic impact to the safety of workers and members of public. This safety circular is meant to provide guidelines for the safe use of mobile cranes in construction sites. Causes of Crane Accidents The main causes of accidents that had been identified can be traced to the following: a) Lack of planning and supervision; b) Incorrect siting or setup of cranes; c) Failure to correctly calculate or estimate the load; d) Failure of personnel to carry out the correct procedures; e) Careless & Complacent; f) Use of wrong lifting gears; g) Faulty devices or machines; h) Lack of proper maintenance. Accident Case 1: August 2000 Accident Statistics In year 2000, there were a total of 32 incidents involving mobile cranes, of which 2 cases resulted in fatalities and 16 cases resulted in varying degrees of injury. Another 14 cases involved damages to properties. No. of accidents involving mobile cranes in year 2000 16 The boom of a crawler crane flipped backwards when the steel casing (for bore piling operation) it was lifting broke at the tip where it was shackled. The boom and the hook block landed on the expressway and hit a vehicle. 12 8 4 0 Resulted in Resulted in Resulted in death of Injury to damages to worker workers properties only Safe Use of Mobile Cranes in Construction Sites Selecting the crane Cranes should always be selected to handle the maximum anticipated load with capacity to spare. Other consideration for the selection of the cranes are the nature of lift, ground condition, site constraints, etc. 1
  • 2. The crane operator The crane shall only be operated by a trained and competent operator. The operator must also be registered with the Chief Inspector of Factories. Documents for the crane When the crane arrives on site, the following documents should come along with the crane for inspection and review when requested: a) A valid Certificate of Test / Thorough Visual Examination of Lifting Equipment for the mobile crane (LM Certificate); b) Valid Certificates of Test / Thorough Visual Examination of Lifting Equipment for all lifting gears that comes with the crane; c) The log-book or log sheet for the recording of the operational tests carried out by the operator before the start of every workshift; If the operator is unable to produce the above documents, the crane supplier should be contacted and the documents obtained before the machine is put into use. It is advisable to state that the production of these documents will be required when the crane is hired. Siting of Crane The stability of the crane depends heavily on the proper siting and setting of the crane. Unless stated by the manufacturer, the crane should have its outriggers fully extended with the wheels off the ground. The ground should be level and capable of supporting the full weight of the crane and its load. In addition, sufficient and suitable packing in the form of steel plates or Safe Use of Mobile Cranes in Construction Sites timber mats should be placed under the outriggers to evenly distribute the weight. The crane should also be positioned so that: a) The operator has a clear view of the operation as far as practicable; b) There is sufficient operating space; c) It is well away from edges of excavation and fixed structures which people may be trapped by the moving parts such as counterweights, etc Planning and Supervision All lifting operation should be properly planned by a competent person before the actual execution and not left solely to the crane operator. Investigation into crane accidents revealed that one of the root causes of these accidents was due to lack of proper planning and supervision. This is particularly so for simple routine lifts. Hence, all contractors are advised not to be complacent during any lifting operation, and to plan and supervise the operation carefully. Site constraints that would have an impact on the safe operation of the lifting should be considered before the execution of the lift. Examples of such constraints are: a) Lifting next to or over an excavation pit; b) Materials or machines placed along the access way thereby reducing the available space to extend the outriggers; c) Site is located nearby busy traffic, or existing building or structures. 2
  • 3. Careful planning is especially critical fpr difficult lifts such as pick and carry operations, tandem lifting and tilt-up operation. “The change in radius caused by booming down and/or telescoping out shall be considered when determining the lifting capacity of the crane. The reduction in the boom angle, caused by the load when just lifted off the ground, and the consequential increase in the radius shall also be considered in determining the safety of a lift.” – SS CP 37: Safe Use of Mobile Cranes Special consideration should be given when the load is required to be placed at a distant further away from the crane than when it is being picked up, i.e. an increase in the crane’s working radius. Personnel The Factories (Operation of Cranes) Regulations 1998 requires the appointment of the following personnel for all mobile crane operation: • Trained lifting supervisor; • Trained riggers; and • Trained signalman. Fatal Accident Case 2: August 2000 All contractors are advised to familiarise themselves with the duties of these appointees as spelt out in the regulation and ensure that the only trained and competent personnel are appointed. In the case where the lifting operation is out of the view of the operator (such as lifting a load from the rooftop of a building), the occupier is obligated to appoint sufficient number of signalman for the operation. The Load The weight of the load should always be known from specifications or through calculations. It is important to note that the safe working loads (SWL) indicated in most load capacity charts are gross SWL. This means that the weight of the hook block, and all lifting gears used must be deducted from this gross SWL to obtain the net SWL that the crane is able to lift at that configuration. Load Radius Indicator The mandatory load radius indicator gives the safe working load at the configuration that the crane has been set, and gives a warning signal when the radius is unsafe. The indicator: • • The deceased and the platform fell from the 5 th storey to the ground. The crane operator lifted and placed a pallet of bricks onto a work platform on th the 5 storey without being instructed or signaled to do so. The platform collapsed together with a worker. The worker died subsequently Safe Use of Mobile Cranes in Construction Sites • must be calibrated regularly; must be configured for both main and auxiliary hooks (when both hooks are used) The operator must be trained to use / set the indicator correctly to tally with the actual configuration adopted; It is important to note that the load radius indicator served primarily as an operational aid. Although the indicator can warn the operator of an impending overload, it should not be used as the only tool to test the stability limit of the crane during operations. 3
  • 4. Supervisors and foreman are advised not to rely on the operator to use the indicator to determine the weight of the load. They should instead have prior knowledge of the weight of the load. This is especially critical when the lifting operation involves the dismantling of machinery or structure from heights. Singapore Standards Code of Practice 37: Safe Use of Mobile Cranes: 2000 The Factories (Singapore Standards and Code of Practice) Order 2001 has gazetted the SS CP 37 as a mandatory code for compliance by any user. The code provides comprehensive requirements on the application, safe operation, maintenance and testing of mobile cranes. The guidelines and requirement laid out in this circular are extracted from the code. The crane's safe working load is always indicated for freely suspended loads. It is expressly forbidden to use the crane to drag any load, or any operation that may cause the hoist line to be out of plumb. Accident Case 3: June 2000 The crane operator had lowered his hook block from an opening into the basement infrastructure. The workers at the basement then pulled the hook block away from the opening and rigged up a truss structure. They then gave the signal to the operator to lift. The boom of the crane snapped when the load was dragged out. û Dragging is expressively forbidden Checks and Maintenance The crane should be in good working condition when it arrives on site and before the start of the workshift. In addition to the statutory annual inspection, the manufacturer’s recommendation on the inspection and maintenance regime should also be followed closely. Types Slewing should be done slowly to maintain control of the load. Tag lines should be used where applicable to minimise swing Functional Checks The operator should stay at the controls at all time when the loads are suspended. Interpolation of the safe working load in the load capacity is disallowed unless specifically allowed by the manufacturer. Extrapolation is strictly disallowed. No additional counterweight shall be added to the crane unless specifically allowed by the manufacturer. All contractors are advised to familiarise themselves with the requirement stipulated in the code. Safe Use of Mobile Cranes in Construction Sites Integrity Checks Checks • Check limit switches e.g. over-derricking; over hoisting • Slewing • Telescoping • Travelling • Safety devices • Wire ropes • Rope terminations • Hook block • Boom section • Rope pulleys • Rope guards The checks listed in this table are not exhaustive. Issued by THE CHIEF INSPECTOR OF FACTORIES MINISTRY OF MANPOWER 4