Republic of the Philippines
         Cordillera Administrative Region
         Regional Project Monitoring Committee



 Third Quarter
   CY 2012
RPMES REPORT




                 Prepared by the
 National Economic and Development Authority
        Cordillera Administrative Region
                RPMC Secretariat
CY 2012 Major Programs and Projects                       ---------   1
Project Implementation Status                             ---------   2
CY 2012 Priority Sectoral Programs/ Projects              ---------   4
RPMC Project Site Inspections                             ---------   5


Annexes:
  A    List of Major Programs/Projects                    --------- A-1
  B    Eight Priority Sectoral Programs/Projects
       Second Cordillera Highland Agricultural Resource   --------- B-1
       Management Program (CHARMP 2)
       4 Pantawid Pamilyang Pilipino Program (4Ps)        --------- B-5
       Agrarian Reform Infrastructure Support Program     --------- B-10
       (ARISP)
       Kabugao, Apayao – Solsona, Ilocos Norte Road       --------- B-13
       Kabugao-Pudtol-Luna-Cagayan Boundary               --------- B-17
       Cordillera-wide Strengthening of Local Systems     --------- B-20
       for Effective and Efficient Delivery of Maternal
       and Child Health Services
       National Greening Program (NGP)                    --------- B-21
       Red and Black School Building Program              --------- B-24
  C    Inspection Reports
       Kabugao-Pudtol-Luna- Cagayan Boundary Road         --------- C-1
       Kabugao, Apayao – Solsona, Ilocos Norte Road       --------- C-4
Third Quarter CY 2012 RPMES Report

The Regional Project Monitoring and Evaluation System (RPMES) report is prepared on a
quarterly basis to provide an overall view on the status of major program/project (P/Ps)
implementation in the region. The report is based on the submission of eleven regional line
agencies (RLAs).

   I. CY 2012 Major Programs/Projects

For CY 2012, there are 46 major P/Ps with an aggregate cost of Php 10.633 Billion of which
about Php 5.9 billion or 55.52 percent are new P/Ps, Php 3.9 billion or 37.52 percent are
multi-year projects, and Php 0.740 billion or 6.96 percent are carryover projects.




In terms of cost, the economic development sector has the highest at 51.21 percent or Php
5,445 billion, followed by the infrastructure sector at 27 percent or Php 2,794 billion, and the
social sector having the least at 18.68 percent or Php 1,985.883 billion. Also included are
rehabilitation and reconstruction projects under the Strategic Action Plan (SAP) on areas
affected by typhoons “Pedring” and “Quiel” in 2011 amounting to 4 percent or Php 407 million.




                                                   1
                                   Third Quarter CY 2012 RPMES Report
In terms of funding source, 67 percent is locally funded while 32 percent is foreign assisted.
The foreign- assisted projects are: (a) Second Cordillera Highland Agriculture Resource
Management Program (CHARMP II), Php 3.2 Billion, (b) Agrarian Reform Infrastructure Support
Program (ARISP), Php 903 Million; and (c) Rural Micro-Enterprises Promotion Program
(RuMEPP), Php 1.8 Million.


   II. Project Implementation Status

For the third quarter, the overall status of project implementation is 43 percent, a 10 percent
increase from the second quarter. The SAP projects posted the highest accomplishment
followed the social sector, then the infrastructure sector. The economic sector’s low
performance is the due to the delayed implementation of its banner project, the CHARMP 2.
(Please refer to Annex A for the detailed status of the 46 projects)

Projects identified under the SAP of areas affected by typhoons Pedring, Quiel and Juan posted
an accomplishment of 96.41 percent, most of which are roads and school building projects.

The Social Sector obtained an overall accomplishment of 52.82 percent. The projects
reported under the sector are DSWD’s Pantawid Pamilyang Pilipino Program (4Ps), DepEd’s Red
and Black Schoolbuilding Program, Rehabilitation of School Building including Water Sanitation
Facilites and Philippines’ Response to Indigenous and Muslim Education (PRIME), DOH’s Health
Facilities and Water System Projects and foreign-assisted Cordillera-wide Strengthening of Local


                                                   2
                                   Third Quarter CY 2012 RPMES Report
Health System for Effective and Efficient Delivery of Maternal and child Health Service.

The Infrastructure Sector had an overall accomplishment of 47.09 percent, composed of
DPWH’s priority roads and bridge projects. These priority roads are mainly laterals that link
CAR to Regions I and II.

The Economic Sector posted an overall accomplishment of 45.57 percent. The sector’s
accomplishment is relatively the lowest due to the negative slippages incurred by two of its
major projects, these are: DA’s foreign-assisted project Second Phase of Cordillera Highland
Agricultural Resource Management Project or CHARMP 2 costing about Php 3 Billion, and
DENR’s National Government Priority, National Greening Program (NGP) costing about Php 124
Million. The other projects under the sector are DAR’s Agrarian Reform Infrastructure Support
Project (ARISP III), DA’s Farm-to-Market Roads, NIA’s Irrigation Projects, DTI’s One Town One
Product Program (OTOP) and Shared Service Facilities SSF, and DOST’s completed Small
Enterprises Technology Program (SETUP), and Packaging and Labeling Project.



                           Implementation Status (as Sept. 2012)

               100.00%                                                   96.41%

                80.00%
                                52.82%
                 60.00%                     45.57% 47.09%
                                                                                  49.27 %
                 40.00%

                 20.00%

                   0.00%




                                                    3
                                    Third Quarter CY 2012 RPMES Report
The overall performance during the quarter translates to four (4) P/P completed – the SETUP of
DOST, two (2) sections of the Abra-Kalinga Road, and Gurel-Bokod-Kabayan-Buguias-Abatan
Road, eight (8) P/P are ahead of schedule, 20 are on track, and 14 behind schedule.

Of the 14 projects reported behind schedule, 11 projects incurred negative slippages less than
negative 15 percent. The common reason reported was due to inclement weather/typhoons
in the project area. Agencies have adopted catch-up plans to put the projects on track. The
DA implemented CHARMP 2 had a negative 26 percent slippage because it underwent another
NEDA ICC process for project reconfiguration to address the issue on LGU counterpart.
CHARMP will have to retarget its work schedule once reconfiguration has been in effect. The
National Greening Program (NGP) also experienced a big slippage of negative 19.63 percent due
to change in procurement process. The NGP also adopted a catch-up plan to put the project
on track. The Philippine Response to Indigenous and Muslim Education (PRIME) of DepEd, is the
most problematic project that has a negative 51 percent slippage. DepEd acknowledges the
delay and has undertaken actions to put the project on track.

   III. CY 2012 Priority Sectoral Programs/ Projects

From the 46 programs/projects, eight (8) were identified as priority sectoral programs/projects
by the sectoral committees and tagged as their banner projects. These programs/projects
with an aggregate cost of Php 5.3 billion are being closely monitored by the RPMC. These
were selected based on the criteria set during the RPMES national forum: (a) foreign- assisted
projects (FAP/ODA), (b) interprovincial, (c) large scale cost, (d) national priority, critical projects
by the Office of the President (OP), and (e) regional priority. These programs/projects are as
follows:

  1. Second Cordillera Highland Agricultural Resource Management Project (CHARMP 2)
  2. Pantawid Pamilyang Pilipino Program (4Ps)
  3. Agrarian Reform Infrastructure Support Project, Phase III
  4. Kabugao-Solsona, Apayao-Ilocos Norte Road
  5. Kabugao-Pudtol- Luna- Cagayan Boundary Road
  6. Cordillera-wide Strengthening of Local health System for Effective and Efficient Delivery of
     Maternal and Child Health Services
  7. National Greening Program
  8. Red and Black School Building Program

Of the eight (8) priority P/Ps, five (5) have been inspected/validated, while the remaining three
(3) are scheduled for inspection by the RPMC before the year ends, these are CHARMP, 4Ps and
the Cordillera-wide Strengthening of Local Health Systems for Effective and Efficient Delivery of
Maternal and Child Health Services. The JICA-assisted Cordillera-wide Strengthening of Local
Health Systems launched in the first quarter has accordingly procured medical equipment for
the provinces of Abra and Apayao. (Please refer to Annex B for the details of the eight priority
sectoral programs/projects)

                                                      4
                                      Third Quarter CY 2012 RPMES Report
IV. RPMC Project Site Inspections

An inspection/validation of the Kabugao-Pudtol-Luna-Cagayan Boundary Road and the Road
Opening of Kabugao, Apayao-Solsona, Ilocos Norte Road (Apayao Side) was conducted by the
RPMC Inspectorate Team on October 9 - 10, 2012. These are regional priority projects and
major components of the Cordillera Roads Improvement Project (CRIP). The roads are among
Apayao national roads upgraded from secondary to arterial classification through DPWH
Memorandum dated November 2, 2011 by DPWH Secretary Rogelio Singson. This
memorandum was a result of an RDC-CAR dialogue with the DPWH Secretary held August 5,
2011 in Baguio City.

During the site inspection, the Kabugao-Pudtol-Luna-Cagayan Boundary Road is proceeding
smoothly having a status of 64.79 percent. The other project, the Kabugao, Apayao – Solsona,
Ilocos Norte Road, 0.50 percent status, was recently issued a resume order after a suspension
due to recent typhoons. It has been observed that the construction of several bridges in both
projects have to be programmed to make them passable. (Please refer to Annex C for
Inspection Reports)




                                                  5
                                  Third Quarter CY 2012 RPMES Report
Annex A
LIST OF MAJOR PROGRAMS/PROJECTS
Third Quarter RPMES Report
                                 CY 2012 MAJOR PROGRAMS/PROJECTS
                                    Cordillera Administrative Region
                                          As of September 2012

                                         IMPLEMENTING     PROJECT COST     FUNDING     STATUS/
         PROGRAM/PROJECT
                                            AGENCY          (PhP M)         SOURCE     REMARKS

                                           SOCIAL SECTOR
1. Pantawid Pamilyang Pilipino              DSWD             888.889        Loan        63.06%
   Program (4Ps)
                                                                                       Slippage:
                                                                                        -3.62%
2. Red and Black School Building             DepEd          CY 2011:        GOP        CY 2011
   Program                                                  166.944                     95.94%
                                                                                     209 Classrooms

                                                            CY 2012:                    CY 2012
                                                            115.200                     34.16%
                                                                                     143 Classrooms

3. Cordillera-wide Strengthening of       DOH & LGUs          43.00         JICA          5%
   Local Health System for Effective      Abra Apayao
   and Efficient Delivery of Maternal       Benguet
   and Child Health Services
4. National Household Targeting              DSWD            41.025         GOP,        59.41%
   System for Poverty Reduction                                             Loan
   Program
5. Rehabilitation of School Building         DepEd       School Building    GOP
   including Water Sanitation                               CY 2011:                 CY 2011 Fund:
   Facilities                                                15.468                     88.92%

                                                            WATSAN
                                                            CY 2011:                 CY 2011 Fund:
                                                             15.861                     96.48%

                                                         School Building
                                                            CY 2012:                 CY 2012 Fund:
                                                             28.633                   Waiting for
                                                                                         SARO
                                                            WATSAN
                                                            CY 2012:
                                                             29.340
6. Philippine Response to Indigenous         DepEd           3.978         AusAid        31%
   People’s (IP) and Muslim
   Education (PRIME)                                                                   Slippage:
                                                                                          -51%


                                                A-1
Third Quarter RPMES Report
                               CY 2012 MAJOR PROGRAMS/PROJECTS
                                  Cordillera Administrative Region
                                        As of September 2012

                                       IMPLEMENTING     PROJECT COST     FUNDING     STATUS/
         PROGRAM/PROJECT
                                          AGENCY          (PhP M)         SOURCE     REMARKS

7. Construction of Various Health           DOH            CY 2011:       GOP       CY 2011 fund:
   Facility                                                117.867                    58.55%

                                                           CY 2012:                CY 2012 fund:
                                                           335.179                     6.49%

8. Water Supply System                      DOH            184.500        GOP         76.64%


Sub-Total                                             1,985.883                       52.82%
                                       ECONOMIC SECTOR
9. Second Cordillera Highland              DA         3,081.862           IFAD,       34.25%
   Agricultural Resource                                                  ADB.
   Management Project (CHARMP2)                                           OFID       Slippage:
                                                                                     -26.61%
10. Agrarian Reform Infrastructure          DAR         Total Project     Loan        72.26%
    Support Project Phase III                              Cost:          GOP
    (Abra, Apayao, Benguet, Ifugao,                       903.863                    Slippage:
    Kalinga and Mt. Province)                                                        +22.25%
                                                          CY 2011:
                                                         (2 projects)
                                                            16.718

                                                           CY 2012:
                                                         (12 projects)
                                                           176.027
11. National Greening Program (NGP)        DENR            124.339        GOP         73.44%

                                                                                     Slippage:
                                                                                     -19.63%
12. Farm-to-Market Roads                    DA             CY 2011:       Grant      CY 2011:
    (CY 2011 Fund: Abra, Kalinga and                        53.00                     85.66%
    Mt. Province)

   (CY 2012 Fund: Abra, Baguio City,                       CY 2012:                   CY 2012:
   Benguet, Ifugao, Kalinga and Mt.                        161.803                    18.58%
   Province)




                                              A-2
Third Quarter RPMES Report
                                  CY 2012 MAJOR PROGRAMS/PROJECTS
                                     Cordillera Administrative Region
                                           As of September 2012

                                          IMPLEMENTING     PROJECT COST     FUNDING       STATUS/
          PROGRAM/PROJECT
                                             AGENCY          (PhP M)         SOURCE       REMARKS

13. Irrigation Projects                        NIA           1,078.046        GOP          53.13%
                                                           (432 projects)
14. One Town One Product Program               DTI             2.747          GOP          84.68%
    (OTOP)

15. Rural Micro Enterprise Promotion           DTI             1.800        IFAD with       90%
    Programme (RuMEPP)                                                          GOP
                                                                             Counter
                                                                                Part
16. Shared Service Facilities Project          DTI             8.388          NEDAC      Awarding of
    (SSF)                                                                       Fund       bidding
                                                                            (National     suppliers
                                                                               Export
                                                                             Develop-
                                                                            ment and
                                                                            Competi-
                                                                             tiveness)
17. Small Enterprise Technology               DOST            28.673            GOP         100%
   Upgrading Program (SETUP)
   Core and Non-Core Funded
   Projects
18. Packaging and Labeling                    DOST             0.688          GOP           76%

Sub-Total                                                 5,445.208                        45.57%
                                        INFRASTRUCTURE SECTOR
Abra
19. Abra-Ilocos Sur Road                      DPWH            106.195         GOP          55.25%

                                                                                          Slippage:
                                                                                           -8.68%
20. Abra-Kalinga Road, K0467+000-             DPWH            147.691         GOP            14%
      K0474+305
                                                                                          Slippage:
                                                                                           +2.67%




                                                 A-3
Third Quarter RPMES Report
                               CY 2012 MAJOR PROGRAMS/PROJECTS
                                  Cordillera Administrative Region
                                        As of September 2012

                                       IMPLEMENTING     PROJECT COST   FUNDING   STATUS/
         PROGRAM/PROJECT
                                          AGENCY          (PhP M)       SOURCE   REMARKS

21. Abra-Ilocos Norte, K0436+700-          DPWH             62.00       GOP      13.83%
      K0439+395
                                                                                 Slippage:
                                                                                 -11.17%

22. Road Upgrading along Abra-             DPWH             60.00       GOP      24.77%
    Cervantes Road (Realigned from
    Sto. Tomas-Manabo Bridge)                                                    Slippage:
                                                                                  +3.60%

23. Sto. Tomas-Manabo Bridge               DPWH            160.00       GOP      76.81%
    (P160.0 M)
                                                                                 Slippage:
                                                                                  -9.03%

24. Abra-Kalinga Road K0410+000-           DPWH             50.45       GOP       100%
      K0413+810
25. Abra-Kalinga Road K0437+490-           DPWH            143.67       GOP       100%
     K0455+890, K0432+000
     K0450+800
Apayao
26. Kabugao-Pudtol-Luna Cagayan            DPWH            58.827       GOP      62.51%
    Boundary Road
      K0661+000 - K0661+321,                                                     Slippage:
      K0643+646 - K0645+825                                                       -4.90%
     Gravel to Concrete
27. Kabugao, Apayao-Solsona, Ilocos        DPWH            100.00       GOP       0.05%
    Norte Road
                                                                                 Slippage:
                                                                                  -1.98%

Benguet
28. Rehab./Reconst’n/Upgrading of          DPWH            54.433       GOP      31.31%
    Kennon Road
                                                                                 Slippage:
                                                                                  -9.49%




                                              A-4
Third Quarter RPMES Report
                              CY 2012 MAJOR PROGRAMS/PROJECTS
                                 Cordillera Administrative Region
                                       As of September 2012

                                      IMPLEMENTING     PROJECT COST   FUNDING   STATUS/
         PROGRAM/PROJECT
                                         AGENCY          (PhP M)       SOURCE   REMARKS

29. Baguio-Bontoc Road (Pico-             DPWH            98.674       GOP      28.77%
    Lamtang Rd., Baguio Itogon &
    Baguio-Bontoc)                                                              Slippage:
                                                                                +14.27%

30. Baguio-Bontoc Road, K0269+000-        DPWH            109.332      GOP        17%
    K0275+000 (v.s.)& K0299+000-
    K0300+900 (v.s.) & K0305+000-                                               Slippage:
    K0308+500 (v.s.) & K0309+000-                                                +1.60%
    K0311+000 (v.s.), K0317+415-
    K0318+500 (v.s.), & K0323+000 –
    K0328+000 (v.s.)
31. Gurel-Bokod-Kabayan-Buguias-          DPWH             98.50       GOP      91.10%
    Abatan Road
                                                                                Slippage:
                                                                                 +2.20%

32. Gurel-Bokod-Kabayan-Buguias-          DPWH            116.50       GOP       100%
    Abatan Road K0303+600-
    K03012+000
33. Rehab./Impv’t. of Gurel-Bokod-        DPWH            148.00       GOP      41.30%
    Kabayan-Buguias Road including
    RROW                                                                        Slippage:
                                                                                +19.70%

34. Gurel-Bokod-Kabayan-Buguias-          DPWH            68.921       GOP        46%
    Abatan Road, K0345+513-
    K0359+300 (vs.)                                                             Slippage:
                                                                                -12.39%

Ifugao
35. Banaue-Mayoyao-A Lista-Isabela        DPWH            58.064       GOP      17.35%
    Bdry. Road
                                                                                Slippage:
                                                                                -13.96%




                                             A-5
Third Quarter RPMES Report
                               CY 2012 MAJOR PROGRAMS/PROJECTS
                                  Cordillera Administrative Region
                                        As of September 2012

                                        IMPLEMENTING    PROJECT COST   FUNDING     STATUS/
         PROGRAM/PROJECT
                                           AGENCY         (PhP M)       SOURCE     REMARKS

36. Nueva Vizcaya-Ifugao-Mt.               DPWH            54.163       GOP          65%
    Province Road
                                                                                   Slippage:
                                                                                    -6.64%

Kalinga
37. Kalinga-Abra Road, K0470+000-          DPWH            53.057       GOP         39.98%
    K0472+267
                                                                                   Slippage:
                                                                                    -4.95%

38. Kalinga-Abra Road, K0476+000-          DPWH            135.27       GOP          8.75%
    K0480+1000, K0480+1000-
    K0482+700 (with exceptions)                                                    Slippage:
                                                                                    +1.44%

39. Balbalan-Pinukpuk Road                 DPWH            100.00       GOP           87%
    K0485+000-K0489+000                                                            Slippage:
                                                                                    -9.40%

40. Balbalan-Pinukpuk Road                 DPWH            245.00       GOP            62%
    K0560+1061-K0520+449                                                           Slippage:
                                                                                      -10%

41. Mt. Province Bdry. –Calanan-           DPWH            209.00       GOP         49.37%
    Pinukpuk –Abbut Road (Pinukpuk)
    (P209.0 M) K0499+674-                                                          Slippage:
    K0509+294 (I.S.)                                                               -50.63%

42. Balbalan-Pinukpuk Road, Abut A         DPWH            183.239      GOP         Notice of
    of Baay Bridge+(-18502) to Abut A                                             award issued
    of Baay Bridge+0                                                              September 6,
                                                                                 2012. Contract
                                                                                   papers on
                                                                                    process.




                                              A-6
Third Quarter RPMES Report
                                CY 2012 MAJOR PROGRAMS/PROJECTS
                                   Cordillera Administrative Region
                                         As of September 2012

                                         IMPLEMENTING      PROJECT COST     FUNDING     STATUS/
         PROGRAM/PROJECT
                                            AGENCY           (PhP M)         SOURCE     REMARKS

Mountain Province
43. Mt. Province –Ilocos Sur via Tue         DPWH             81.815          GOP       31.17%
    Road
                                                                                        Slippage:
                                                                                         -6.28%

44. Mt. Province-Ilocos Sur via Kayan        DPWH              92.00          GOP       54.40%

                                                                                        Slippage:
                                                                                         -4.66%

Sub-Total                                                     2,794.801                 47.09%
                                      STRATEGIC ACTION PLAN (SAP)
                       (Rehabilitation and Recovery of Areas Affected by Disasters)
45. Disaster Related Rehabilitation           DPWH                           DRRP
    Project (DRRP)                                                           Calamity
                                                                             Fund
                                                                             CY 2011
    a. Apayao 1st District Engineering                         74,550.0                 87.73%
        Office (16 projects)
    b. Apayao 2nd District                                     14,000.0                  100%
        Engineering Office (5 projects)
    c. Benguet 1st District                                    45,469.0                  100%
        Engineering Office (15
        projects)
    d. Benguet 2nd District                                    39,279.1                  100%
        Engineering Office (6 projects)
    e. Baguio City District                                     600.0                    100%
        Engineering
        Office (1 project)
    f. Ifugao 1st District Engineering                             8,580.0               100%
        Office (2 projects)
    g. Ifugao 2nd District Engineering                            25,850.0               100%
        Office (4 projects)
    h. Kalinga District Engineering                               85,910.5              95.93%
        Office (9 projects)
    i. Mt. Province District Office                              102,459.4               100%
       (28 projects)


                                                 A-7
Third Quarter RPMES Report
                               CY 2012 MAJOR PROGRAMS/PROJECTS
                                  Cordillera Administrative Region
                                        As of September 2012

                                       IMPLEMENTING     PROJECT COST     FUNDING   STATUS/
          PROGRAM/PROJECT
                                          AGENCY          (PhP M)         SOURCE   REMARKS

 Sub-Total                                                    396.697              96.81%
 46. Quick Response Fund (QRF)              DepEd                           GOP
     a. Cabaroan ES Dolores, Abra                                1.202              56%
        (Construction of 1 unit-2
        classroom in Bldg.1)
     b. Cabaroan ES Dolores, Abra                                1.202              100%
        (Construction of 1 unit-2
        classroom in Bldg.2)
     c. Cabaroan ES Dolores, Abra                                318.0              79%
        (Construction of 3 Seater
        Toilet – type III with
        handwashing)
     d. Cabaroan ES Dolores, Abra                                219.0              71%
        (1 classroom repair)
     e. Tonglo Carino PS, Buguias,                               1.202              15%
        Benguet
     f. Talubin NHS, Bontoc Mt.                                  1.143              85%
        Province
        (Construction of 2cl /
        Replacement of Burned Bldg.)
     g. Tumog Es, Luna, Apayao                                   1.942              95%
        (Construction of 1stry 3
        Classroom 7x9 type I)
     h. Lagawe CS, Lagawe, Ifugao                                1.200              100%
        (Construction of 2cl /
        Replacement of Burned Bldg.)
     i. Bañacao ES, Bangued West,                                1.600              100%
        Abra
        (Repair of Classrooms /
        Construction of Slope
        Protection /Water System)
 Sub-Total                                                     10.027              80.56%
 SAP Sub-Total                                                406.724              96.41%

              CAR Total                                    10,632.616              49.27%

Sources: RLAs RPMES PMC Form I-1 and RPMES PMC Form I-2 as of September 2012.




                                              A-8
Annex B
EIGHT (8) PRIORITY PROGRAMS/PROJECTS
Second Cordillera Highland Agricultural Resource Management Project
                               (CHARMP 2)

PROJECT PROFILE

Implementing Agency: Department of Agriculture-CAR
Fund Sources:
      GOP: Department of Agriculture
      Loan: IFAD, OFID, ADB
      Grant: IFAD
       Total Project Cost: Php 3,081,862,000
Location/Area Coverage: 6 provinces, 37 municipalities, 170 barangays
       Abra: Lacub, Licuan-baay, Malibcong, Luba, Tubo, Sallapadan, Bucloc, Boliney
       Apayao: Calanasan, Kabugao, Conner
       Benguet: Bokod, Kabayan, Bakun, Kibungan,Buguias,Kapangan, Atok, Sablan,
       Mountain Province: Barlig, Besao, Sadanga, Sagada, Bontoc, Tadian, Bauko, Sabangan
       Kalinga: Balbalan, Pasil, Lubuagan, Tanudan, Tinglayan
       Ifugao: Hingyon, Hungduan, Tinoc, Asipulo, Mayoyao

Description:
The project goal is to reduce the poverty and improve the livelihood of poor rural women and men in
indigenous communities in the upland areas of the Cordillera Administrative Region. The objectives are
to (1) increase the household income of poor farmers through sustainable agricultural development;
and (2) enhance the quality of life of targeted communities by improving land tenure security, food
security and watershed conservation.

The project has five components: (1) community mobilization, participatory planning of investments,
and land titling; (2) community watershed conservation (including forest management and agro forestry
development); (3) agricultural and agribusiness development, and promotion of income-generating
activities; (4) rural infrastructure development; and (5) project management and coordination.




             Farm to market access                                        Agro-forestry plots
                                                   B-1
                                     Third Quarter CY 2012 RPMES Report
Second Cordillera Highland Agricultural Resource Management Project




                     Meeting with the beneficiaries& Project field assessment


                                  PROJECT PROGRESS REPORT
                                    As of September 2012

Project Duration:
                       Start: January 1, 2009                                     End: December 31, 2015
CY2009- CY2015
    For CY 2012         AO 1st Quarter        AO 2nd Quarter             AO 3rd Quarter     AO 4th Quarter
Target                     49.72%                  53.43%                    57.15%            60.86%
Actual                     18.45%                  20.65%                    34.25%
Slippage                   -31.27%                 -32.78%                  -22.90%
Cumulative Status:                Status                           Physical                 Financial
(Since start of
                       Target                                      60.86%                 FOA+ Grant:
project)
                                                                                          Php 2,417.48

                       Actual                                      34.25%             * Php 870.93 (36% of
                                                                                           FOA+Grant)
                                                                                      * (57.03% of the total
                                                                                       allotment released)
                                                                                          Php 1,527.073
                                                                                      from CY 2009-CY2012

                       Slippage                                    -26.61%




                                                  B-2
                                    Third Quarter CY 2012 RPMES Report
Current             1. Delayed implementation of infra subprojects due to difficulty of LGUs
Implementation         in providing cash counterpart required as indicated in the NG-LGU
Issues and/or          cost sharing policy.
Problems
Encountered         2. Approval of the proposed rural finance scheme/Livelihood Assistance
(if any):              Finance (LAF) in place of the credit subcomponent.

                    3. Extension of OFID Loan Agreement which will close in July 2013

Actions Taken/   1. The project is waiting for the approval of the proposed NG-LGU cost
Recommendations:    sharing mix of 60%-40% for 1st-2nd class LGUs, 70%-30% for 3rd-6th
                    class LGUs from the NEDA Board. While waiting for its approval, the
                    Project recommended LGUs regardless of their classification to opt for
                    the cost-sharing arrangement included in the Project Financing
                    Agreement, where the CHARMP2 will shoulder 60% and LGUs will
                    provide 40% equity in order to proceed with the implementation of
                    proposed subprojects. However, only a few LGUs were able to provide
                    counterpart based on this scheme.

                        To initiate implementation of 25 submitted infra subproject proposals
                        from LGUs that could not afford said NG-LGU cost sharing scheme,
                        fund assistance from the DA-OSEC was sought to cover 30% of the
                        total cost of subprojects. The Project and the concerned LGUs are now
                        waiting for the release of CFA in the amount of Php 50 million from
                        the DA-OSEC.

                        As of June 2012, another batch of 71 subproject proposals was
                        submitted to DA-OSEC for fund support in the amount of Php 89
                        million.

                    2. Since the credit scheme as a subcomponent of the original Project
                       Design is not feasible for poor target beneficiaries in CAR, the Project
                       proposed for the Livelihood Fund Assistance (LAF) that would assist
                       livelihood and income generating activities of target groups. This
                       proposal is part of the revised Project Design which is now for
                       approval by the ICC/Government.

                    3. The Project requested for an extension of the loan validity to coincide
                       with the loan closing of the IFAD loan (June 2016). Request was
                       reiterated to DA-CO for submission to Department of Finance mid of
                       October 2012.

Remarks:            The project is waiting for the final approval of the Revised Project Design
                    by NEDA ICC Board/ National Government.

                                              B-3
                                Third Quarter CY 2012 RPMES Report
Agency Contact   DIR. MARILYN V. STA. CATALINA, CESO IV
Person:          Regional Executive Director, DA-RFU-CAR &
                 Project Director, CHARMP2

                 CAMERON P. ODSEY
                 Project Manager, CHARMP2

Address:         PROJECT SUPPORT OFFICE
                 Baguio Stock Farm Compound, Marcos Highway corner Sto. Tomas Road,
                 2600 Baguio City

Telefax:         +63.74.444.8329/ Tel No. +63. 74. 444.7991
Email:           charm@mozcom.com




                                          B-4
                            Third Quarter CY 2012 RPMES Report
Agrarian Reform Infrastructure Support (ARISP III)


PROJECT PROFILE

Implementing Agency: DAR-CAR / DPWH-CAR / NIA-CAR / LGUs

Fund Sources:
      GOP:
      Loan: JICA

Total Project Cost:         Php 903,863,055.00
       Project Cost (2011): Php 16.718 M
       Loan/Grant Proceeds: Php 677,897,291.25
       Peso Counterpart:    Php 225,965,763.75
       Project Cost (2012): Php 176.027 M

Location/Area Coverage:
       Abra: Daguioman, Lacub and Luba ARCs
       Apayao: Sta. Marcela, Flora and Pudtol ARCs
       Benguet: Bakun, Kapangan and Kibungan ARCs
       Ifugao: Asipulo, Hingyon and Tinoc ARCs
       Kalinga: Tinglayan, Rizal and Pasil ARCs
       Mt. Province: Sadanga, Bauko and Bontoc ARCs

Description:

The Agrarian Reform Infrastructure Support Project (ARISP) Phase III is a foreign-assisted
project of DAR, designed to provide basic support services to help develop Agrarian Reform
Communities (ARCs). It is funded from a concessional loan from the Government of Japan with
counterpart financing from the DAR, Local Government Units and the beneficiaries. The project
timetable is from CY 2008 to CY 2014.

The project espouses the concept of integrated area development in the ARCs wherein basic
infrastructure, organization / institutional, agricultural and enterprise development support are
combined to produce incremental growth in productivity and income among farmers.
Specifically, the project considers the provision of farm-to-market roads (FMR) and bridges,
irrigation projects, post-harvest facilities, and potable water supply system under its
infrastructure component.

For institutional development component, this entails the organizing and strengthening of
various organizations in the ARCs to build their capabilities to operate and manage the
infrastructure facilities and agri-business in a sustainable basis. The project also supports the

                                                 B-10
                                    Third Quarter CY 2012 RPMES Report
development of viable agribusiness in the ARCs to harness the agricultural potentials, add value
to agricultural products, and make them more competitive in the market.

In CAR, actual project implementation commenced in CY 2011. From CY 2008 to 2010, the pre-
implementation activities conducted are indicative development planning, site validation,
project prioritization and individual project designs. There are 61 projects confirmed with an
aggregate cost of Php 903.86 M.

For CY 2011, two (2) projects (irrigation project and water system) were implemented and
recently completed with an aggregate cost of Php 16.72 M. These are located in the provinces
of Abra and Benguet.




DAR and NIA ARISP III Project Management Office representatives conducted Final Project
Inspection and Test Run of the newly rehabilitated Daguioman Communal Irrigation System ,
Daguioman, Abra with a service area of 89 hectares.




Completed Dalingoan Potable Water Supply System, Kapangan, Benguet. The project costing
P 2,094,916.00 will benefit around 89 Agrarian Reform Beneficiary Households.


                                                B-11
                                   Third Quarter CY 2012 RPMES Report
For CY 2012, 12 projects (10 irrigation projects and 2 FMRs) are programmed for
implementation with a total cost of Php 167.44 M. These are located in the provinces of
Apayao, Benguet, Ifugao, Kalinga and Mountain Province.

                                    PROJECT PROGRESS REPORT
                                      As of September 2012

Project Duration:          Start: April 2008                                                End: April 2014

      For CY 2012          AO 1st Quarter           AO 2nd Quarter         AO 3rd Quarter    AO 4th Quarter

Target                         29.16 %                   48.87 %                 45.26%
Actual                         23.88 %                   36.87 %                 69.62%
Slippage                       (5.28%)                  (12.00 %)                (24.36%)

Cumulative Status:                   Status                           Physical               Financial
(Since start of project)
                           Target                                      50.01%

                           Actual                                      72.26%

                           Slippage                                    22.25%

Current                    1. Undue project delay due to lack of equipment and manpower
Implementation Issues      2. Absence of DPWH QAU representative during inspection.
and/or Problems
Encountered (if any):      3. Inclement weather


Actions Taken/             1. Conducted Strategy Planning and monthly Area Implementation
Recommendations:              Team (AIT) meetings participated by representatives from DAR
                              Provincial / Municipal Office, DPWH, LGU and the Contractor to
                              draw catch-up plan.


Remarks:

Agency Contact             DIR. FRANKLIN E. COCOY
Person:                    OIC-Regional Director, DAR-CAR
                           #39 m. Roxas St., Brgy. Tabora, Baguio City

                           ENGR. WILLIE GARCIA
                           445-4497



                                                   B-12
                                      Third Quarter CY 2012 RPMES Report
Kabugao (Apayao)-Solsona (Ilocos Norte) Road

PROJECT PROFILE

Implementing Agency: Department of Public Works and Highways – CAR

Fund Source: GOP
      Total Project Cost: Php 100 M.
      Contract Cost: Php 89.089 M.

Location/Area Coverage: Barangay Madatag, Kabugao, Apayao

Description:

The road is a major component of the
Cordillera Roads Improvement Project
(CRIP) as lateral road; it connects Ilocos
Region and the Northern Cordilleras. It                 Kabugao-Apayao-
traverses the municipalities of Kabugao                  Solsona-Ilocos
and Calanasan in Apayao and turns west                     Norte Rd
to Solsona in Ilocos Norte.

The 76.48 km road stretch is a segment of
the San Nicolas-Solsona-Kabugao-Conner-
Abbut Lateral Road as Apayao’s direct
access to Laoag International Airport. The
road starts at PoblacionKabugao and ends
in Solsona. At the Ilocos Norte side,
concrete paving is being completed up to
the regional boundary. Approximately 10
km. is for opening at the Kabugao side.
Likewise, seven (7) major bridges are to be
constructed with a total length of 445 lm.
crossing several tributaries of the Apayao
River.     However, the whole stretch
remains a gap (unpaved) even after the
project.                                                                 PROJECT LOCATION

The road is among the Apayao national roads recently upgraded from secondary classification
to arterial through DPWH Memorandum dated November 2, 2011 by Sec. Rogelio L. Singson.
This memorandum was an immediate result of the RDC-CAR dialogue with Sec. Singson held at
the DPWH-CAR office on August 5, 2011.

The specific project output is road opening and gravelling of 9.56 kms.

                                                 B-13
                                    Third Quarter CY 2012 RPMES Report
PROJECT PROGRESS REPORT
                                   As of September 2012

Project Duration:       Start: June 27, 2012 End: July 21, 2013

    For CY 2012         AO 1st Quarter        AO 2nd Quarter             AO 3rd Quarter   AO 4th Quarter

Target                                               0.50%                   1.53%

Actual                                               0.50%                   0.7%

Slippage                                                                    -0.83%

Cumulative Status:                 Status                         Physical                Financial
(Since start of
project)                Target                                     2.03%

                        Actual                                     0.05%                   8.88%

                        Slippage                                   -1.98%

Current                 Project Suspension was issued on July 1, 2012 since the contractor
Implementation          cannot mobilize due to series of slides and road cut along the 21 km
Issues and/or           road leading to the project site.
Problems
Encountered (if any):
Actions Taken/          To address this, the DPWH-CAR requested DPWH-CO to utilize
Recommendations:        savings for the removal of slides and restoration of road cuts costing
                        Php 2.38 M. This was eventually approved and the contractor was
                        advised to resume effective September 30, 2012.

Remarks:

Agency Contact          DIR. EDILBERTO P. CARABBACAN
Person:                 Regional Director, DPWH– CAR
                        Engineer’s Hill
                        2600 Baguio City
                        Tel. 444-8838




                                                 B-14
                                    Third Quarter CY 2012 RPMES Report
Kabugao Section




             B-15
Third Quarter CY 2012 RPMES Report
LANDMARKS




Kabugao (Apayao) Municipal Hall                                 Solsona Welcome Arch




                      Junction San Nicolas, Ilocos Norte



                                        B-16
                           Third Quarter CY 2012 RPMES Report
Kabugao-Pudtol-Luna Cagayan Boundary Road


PROJECT PROFILE

Implementing Agency: Department of Public Works and Highways – CAR
Fund Source: GOP
      Total Project Cost: Php58.827 M.
      Contract Cost     : Php 49.574 M.
Location/Area Coverage: Barangays Swan and Mataguisi, Pudtol, Apayao

Description:

The road is a major component of the
Cordillera Roads Improvement Project
(CRIP) as the northern tip of the regional
backbone. The 95.7 km. road stretch                                                    Kabugao-Pudtol-
directly links the capital town Kabugao to                                              Luna Cagayan
Lower Apayao, the seat of provincial                                                      Bdry Road
government and business growth center
in the Municipality of Luna.

The road starts at junction Lenneng along
the Kabugao-Conner-Abbut Road and
going north-east traverses municipalities
of Kabugao, Pudtol and Luna and ends at
Junction Luna in Abulug, Cagayan along
the Pan-Philippine Highway. The Pan-
Philippine Highway connects Laoag,
Ilocos Norte and Tuguegarao, Cagayan.
The gap at the Kabugao side (19.359
km.), traverses a rugged mountainous
terrain, then slowly goes down to the
Paco Valley, which was then proposed as
government center. The road will also
traverse the Mataguisi Valley in Pudtol.                            PROJECT LOCATION
The valleys have vast potential for
agricultural production.

The road is among the Apayao national roads recently upgraded from secondary classification
to arterial through DPWH Memorandum dated November 2, 2011 by Sec. Rogelio L. Singson.
This memorandum was an immediate result of the RDC-CAR dialogue with Sec. Singson held at
the DPWH-CAR office on August 5, 2011.


                                                B-17
                                   Third Quarter CY 2012 RPMES Report
The bridges across Apayao River (Babulayan Bridge) and tributaries Maton and Nagan Rivers
have been completed. However, two (2) more major bridges across Malilibag River (60 lm) and
Paco River (36 lm) are yet to be constructed to finally complete the road link. On top of this,
there are six (6) temporary bridges to be replaced with permanent bridge structures with a
total length of 90 lm.

The specific project output is road construction of 2.4 km. After the project, the road has still a
gap (unpaved) of 16.959 km.

                                  PROJECT PROGRESS REPORT
                                    As of September 2012

 Project Duration:           Start: February 20, 2012                           End: December 12, 2012

   For CY 2012        AO 1st Quarter        AO 2nd Quarter             AO 3rd Quarter   AO 4th Quarter

 Target                     5%                      50%                    17.41%

 Actual                     5%                    35.7%                    26.81%

 Slippage

 Cumulative Status:                   Status                        Physical             Financial
 (Since start of project)
                             Target                                  67.41%

                             Actual                                  62.51%               69.49%

                             Slippage                               (4.90%)

 Current Implementation       The 4.9 % negative slippage is attributed to the work
 Issues and/or Problems       interruption during the past months due to inclement weather
 Encountered (if any):        caused by Typhoons Gener, Helen, and Igme.

 Actions Taken/              To address this, the DPWH advised the contractor to provide
 Recommendations:            additional manpower and equipment to fast track
                             implementation.

 Remarks:

 Agency Contact Person:      DIR. EDILBERTO P. CARABBACAN
                             Regional Director, DPWH– CAR
                             Engineer’s Hill
                             2600 Baguio City
                             Tel. 444-8838


                                                   B-18
                                      Third Quarter CY 2012 RPMES Report
Mataguisi Valley




Babulayan Bridge across Apayao River




    Junction Lenneng (Kabugao)                                      Paco Valley




                                          B-19
                             Third Quarter CY 2012 RPMES Report
National Greening Program (NGP)


PROJECT PROFILE

Implementing Agency: DENR–CAR

Fund Source:          GOP

Total Project Cost:   P124,339,000.00

Location/Area Coverage: Region wide
       The locations are spread out all over the
       six provinces of CAR including Baguio City
       with a total area of 15,258 hectares to be
       planted through social mobilization.


Description:

An administration priority program (Executive Order No. 26) that seeks to attain asustainable
Human development, economic and ecological security through the planting of 1.5 billion trees
in around 1.5 million hectares of public land within six years from year 2011 to 2016.

The NGP also aims to ensure food security, biodiversity conservation and address climate
change.

In the Cordillera, the target for CY 2012 is 7.5 million trees covering 15,000 hectares with a
project cost of Php 103.663 M. The project components are: (a) seedling production, Php
62.382 M; plantation site preparation; Php 17.469 M; and maintenance and protection, Php
23,812 M.




  Seedling production (gmelina) of one of the
                                                         Seedling production (mahogany) of one
  People’s Organization (PO) – Baroña Family
                                                         of the POs in Conner, Apayao
  Association (BFA) in Poblacion, Lacub, Abra.

                                                B-21
                                   Third Quarter CY 2012 RPMES Report
Seedling production (mahogany) of one of
Seedling production (Benguet pine) of one            the POs – Federation of Responsive
of the POs in Benguet                                Association for Magat Ecology Inc. in Ifugao




                                                      Seedling production (mahogany,
Seedling production (gmelina) of one of the           narra&gmelina) of one of the POs in Natonin,
POs in Tabuk, Kalinga                                 Mountain Province




                                         Benguet Pine

                                             B-22
                                Third Quarter CY 2012 RPMES Report
PROJECT PROGRESS REPORT
                                  As of September 2012

Project Duration:          Start: January 2012                                     End: December 2012

      For CY 2012          AO 1st Quarter         AO 2nd Quarter         AO 3rd Quarter   AO 4th Quarter

Target                         11.16%                  60.50%                 21.41%          6.92%
Actual                         14.49%                  34.49%                 24.46%
Slippage                       (3.33%)                (26.01%)                (3.05%)

Cumulative Status:                  Status                         Physical               Financial
(Since start of project)   Target                                   93.07%                95.71%
                           Actual                                   73.44%                95.71%
                           Slippage                                (19.62%)                 (0%)

Current                    1. For the second year, project was delayed due the difficulty of
Implementation Issues         following the prescribed procurement procedure. Seedlings
and/or Problems               should be produced by the beneficiaries themselves, unlike
Encountered (if any):         during the first year that these may be acquired from outside of
                              the project area.

                           2. Critical areas for tree planting due to climatic condition are: Abra,
                              Benguet and western Mountain Province. In these areas, tree
                              planting should be done only during rainy season.

Actions Taken/             1. Procurement guideline was issued by DENR-CO to facilitate
Recommendations:              implementation.

                           2. Adopted catch-up plan

Remarks:

Agency Contact Person:     DIR. CLARENCE L. BAGUILAT
                           Regional Executive Director, DENR-CAR
                           No. 80 Diego Silang St., 2600 Baguio City, (442-4531, RD/F)

                           Mr. JOSEPH MAUTING
                           PMD, DENR-CAR (443-94-06)




                                                 B-23
                                    Third Quarter CY 2012 RPMES Report
Red and Black School Building Program


PROJECT PROFILE

Implementing Agency: Department of Education-CAR

Fund Source: GOP
      Total Project Cost:
      (CY 2011) P166.944 M
      (CY 2012) P115.200M

Location/Area Coverage: Region wide

Description:

The Regular School Building Program specifically targets schools which are categorized under
the Red Zone or those which have a ratio of 56 or more students to one classroom: and the
Black Zone, or schools which make use of makeshift classrooms and facilities.

The standard DepEd design is 7m x 9m classroom for rural areas with a classroom-student ratio
of 1:45. This standard also applies to all public secondary schools, regardless of location and
class size.

In CAR, the carry-over CY 2011projectshas a total project cost of Php166.944 M. covering 147
school sites for new 209 classrooms. The table below shows the details per province/city:


                             No. of               No. of                                   Status
      Province/City      sites(CY 2011)                              Project Cost
                                               Classrooms                              (AO Sept. 2012)
   Abra                        18                    16                   18,427,000           90.43%
   Apayao                      21                    26                   15,812,000           96.57%
   Benguet                     18                    28                   25,793,000             100%
   Ifugao                      13                    21                   28,493,000           98.69%
   Kalinga                     41                    65                   44,636,000           95.12%
   Mt. Province                30                    34                   20,042,000           90.45%
   Baguio                      6                     10                   13,740,000             100%
   CAR                        147                   209                  166,943,500           95.94%



                                                 B-24
                                    Third Quarter CY 2012 RPMES Report
Mankayan Central School – On going construction (May 28, 2012)




               Bulalacao National High School




                Bangao National High School




                               B-25
                  Third Quarter CY 2012 RPMES Report
For CY 2012 projects, construction started during the second quarter. There are 147 school sites
to have 207 new classrooms with a total project cost of Php 115.2 M. The next table shows the
details per province/city:


                           No. of sites             No. of                                   Status
      Province/City                              Classrooms            Project Cost      (AO Sept. 2012)
                            (CY 2012)
   Abra                        18                      26                    7,920,000           89.49%
   Apayao                      21                      26                   10,080,000                0%
   Benguet                     18                      28                   15,840,000           90.57%
   Ifugao                      13                      21                   10,800,000           27.24%
   Kalinga                     41                      65                   29,520,000           18.53%
   Mt. Province                30                      31                   23,760,000           27.69%
   Baguio                       6                      10                   17,280,000           16.91%
   CAR                         147                    207                  115,200,000           34.16%

                                    PROJECT PROGRESS REPORT
                                      As of September 2012

Project Duration:          Start: January                                                   End: December
                                 st                       nd                     rd
       For CY 2012          AO 1 Quarter           AO 2 Quarter             AO 3 Quarter     AO 4th Quarter
Target
Actual (CY 2011)                8.44%                    0.78%                   6.72%
        (CY 2012)                                        7.69%                  26.47%
Slippage
Cumulative Status:                    Status                        Physical                 Financial
(Since start of project)   Target
                           Actual (CY 2011)                         95.94%
                                  (CY 2012)                         34.16%
Current Implementation
Issues and/or Problems
Encountered (if any):
Actions Taken/
Recommendations:
Remarks:                   Implementation of CY 2012 projects comments during this quarter.
Agency Contact Person:     DIR. ELLEN B. DONATO
                           Regional Director
                           Wangal, La Trinidad, 2601 Benguet


                                                   B-26
                                      Third Quarter CY 2012 RPMES Report
Annex C
INSPECTION REPORTS
RPMC-CAR Inspection Report on the
                       Road Upgrading (Gravel to Concrete) along
                      Kabugao-Pudtol-Luna-Cagayan Boundary Road
                             conducted on 09 October 2012


1. The RPMC Inspectorate Team

   The Regional Project Monitoring Committee (RPMC-CAR) Inspectorate Team conducted on
   09 October 2012 a project-site inspection on the Kabugao- Pudtol-Luna- Cagayan Boundary
   Road. This is a regional priority sectoral project implemented by the DPWH-CAR regional
   office.

   The RPMC member-agency representatives were the following:

    Rene V. Valera, DILG-CAR                      Jerome B. Agaloos, NEDA-CAR
    James M. Degsi, DBM-CAR                       Manilyn S. Dulay, NEDA-CAR

   The Team was assisted by the following DPWH Apayao 2nd Engineering District and
   Contractor’s representative:

    ADE Rustom Martinez, DPWH Apayao II                   Galo Aplod, OCDC
    Jerry Ragojos, DPWH Apayao II

   Before the field inspection, the group paid courtesy to the Apayao Provincial Government
   officials at the Provincial Capitol in Luna, Apayao. The Team met with the Provincial
   Administrator Vincent Talattad and Chief Executive Atty. Xandred Claveria.

2. Project Profile

   The road is a major component of the Cordillera Roads Improvement Project (CRIP) as the
   northern tip of the regional backbone. It traverses the municipalities of Kabugao, Pudtol
   and Luna in Apayao and turns east to Abulog in Cagayan. The 95.7 km. road stretch directly
   links the capital town Kabugao to Lower Apayao, the seat of provincial government and
   business growth center.

   The road is among the Apayao national roads recently upgraded from secondary
   classification to arterial through DPWH Memorandum dated November 2, 2011 by Sec.
   Rogelio L. Singson. This memorandum was an immediate result of the RDC-CAR dialogue
   with Sec. Singson held at the DPWH-CAR office on August 5, 2011.

   The bridges across Apayao River (Babulayan Bridge) and tributaries Maton and Nagan Rivers
   have been completed. However, two (2) more major bridges across Malilibag River (60 lm)
                                            C-1
and Paco River (36 lm) are yet to be constructed to finally complete the road link. On top of
   this, there are six (6) temporary bridges to be replaced with permanent bridge structures
   with a total length of 90 lm.

3. Project Basic Information

     Specific Location                              Barangays Swan & Mataguisi, Pudtol,
                                                    Apayao
     Station Limits                                 KO 661+000 – KO 661+321 &
                                                    KO 643+520- KO646+080
     Length of Road Project                         2.4 km
     Project Cost                                   Php 58.827 M.
     Contract Cost                                  Php 49.574 M.
     Source of Fund                                 CY 2012 DPWH Regular Infra Program
     Project Schedule                               Feb. 20, 2012 to Dec. 12, 2012
     Contractor                                     OCDC
     Major Work Items                               PCCP (2.4 km), RCPC, stone masonry,
                                                    concrete curb & gutter and road signs
     Project Status                                 64.79 %, slippage (2.62 %)

4. Findings

   The road construction is smoothly on progress. The mere 2.62 % negative slippage is
   attributed to the work interruption during the past months due to inclement weather
   caused by Typhoons Gener, Helen, and Igme. To address this, the DPWH advised the
   contractor to provide additional manpower and equipment to fast track implementation.

5. Comment(s)/ Recommendation(s)

   The work progress is commendable. It is however recommended that the DPWH should
   also prioritize the programming for the construction of the bridges across Paco River
   (District I) and Malilibag River (District 2) to finally open the road up to Kabugao.




                                              C-2
PHOTO DOCUMENTATION




                 On-going concreting of Kabugao-Pudtol-Luna-Cagayan Boundary Road
                         (2.4 km along Barangays Swan & Mataguisi section)




Completed Babulayan Bridge            Concrete approach of Babulayan      Recently completed road
          across                                  Bridge                     concreting project
      Apayao River
                                            EXIT CONFERENCE




                                                                         The RPMC Inspectorate Team
     Courtesy call on Apayao Provincial Administrator Vincent Talattad   meets ADE Rustom Martinez,
                  and Chief of Staff Atty. Xandred Claveria                   DPWH Apayao II (L)

                                                     C-3
RPMC-CAR Inspection Report on the
        Road Opening of Kabugao, Apayao- Solsona-Ilocos Norte Road (Apayao Side)
                             conducted on 10 October 2012


1. The RPMC Inspectorate Team

   The Regional Project Monitoring Committee (RPMC-CAR) Inspectorate Team conducted on
   10 October 2012 a project-site inspection on the Kabugao, Apayao- Solsona-Ilocos Norte
   Road. This is a regional priority sectoral project implemented by the DPWH-CAR regional
   office.

   The RPMC member-agency representatives were the following:

    Rene V. Valera, DILG-CAR                      Jerome B. Agaloos, NEDA-CAR
    James M. Degsi, DBM-CAR                       Manilyn S. Dulay, NEDA-CAR

   The Team was assisted by the following DPWH Apayao 1st Engineering District and LGU
   Kabugao staff:

    Antonio Baguec (PE), DPWH Apayao I                Arne Paul Ligwang, LGU Kabugao
    Domingo Enciso, DPWH Apayao I                     Harold Aboran, LGU Kabugao

   The group paid courtesy and held separate exit conferences with DPWH Apayao 1st District
   ADE Edward P. Magno and LGU Kabugao Municipal Administrator Romeo B. Tamot.

2. Project Profile

   The road is a major component of the Cordillera Roads Improvement Project (CRIP) as a
   lateral road. It directly connects Apayao Province to Ilocos Region. It traverses the
   municipalities of Kabugao and Calanasan in Apayao and turns west to Solsona in Ilocos
   Norte. The 76.48 km road stretch is a segment of the San Nicolas-Solsona-Kabugao-
   Conner-Abbut Lateral Road as Apayao’s direct access to Laoag International Airport. At the
   Ilocos Norte side, concrete paving is being completed up to the regional boundary.

   The road is among the Apayao national roads recently upgraded from secondary
   classification to arterial through DPWH Memorandum dated November 2, 2011 by Sec.
   Rogelio L. Singson. This memorandum was an immediate result of the RDC dialogue with
   Sec. Singson held at the DPWH-CAR office on August 5, 2011.

   It was noted that even after the project, the whole stretch remains a gap until concreted.
   Likewise, seven (7) major bridges are to be constructed with a total length of 445 lm.
   crossing several tributaries of the Apayao River.
                                            C-4
3. Project Basic Information

     Specific Location                 Barangays Madatag, Kabugao, Apayao
     Station Limits                    KO 627+840 – KO 637+400
     Length of Road Project            9.56 km
     Project Cost                      Php 100 M.
     Contract Cost                     Php 89.089 M.
     Source of Fund                    CY 2012 DPWH Infra Program
     Original Project Schedule         June 27, 2012 to April 22, 2013
     Suspension Order No.1             July 1, 2012
     Resume Order No 1                 September 30, 2012
     Expected Completion               July 21, 2013
     Contractor                        PBO Construction
     Major Work Items                  Roadway & drainage excavation, gravelling, stone
                                       masonry & installation of cross drainages, catch
                                       basins, common earth & solid rock excavation
     Project Status                    0.50 %

4. Findings

   Project Suspension was issued on July 1, 2012 since the contractor cannot mobilize due to
   series of slides and road cut along the 21 km section leading to the project site. To address
   this, the DPWH-CAR requested DPWH-CO to utilize savings for the removal of slides and
   restoration of road cuts costing Php 2.38 M. This was eventually approved and the
   contractor was advised to resume effective September 30, 2012. Due to the slides and road
   cuts, the group had to cruise Apayao River for two (2) hours using a motor-banca and hike
   for an hour to reach the project site.

   It was found out that the road alignment follows an old logging road of which some portions
   were later widened by the AFP Engineering Brigade. Accordingly, the AFP had a military
   camp at Barangay Madatag. The area has a vast potential for agriculture, water recreation
   and Philippine eagle watching. The forest area along the river and within the Apayao-Ilocos
   Norte boundary is a perfect eagle’s habitat.

5. Comment(s)/ Recommendation(s)

   The leadership of Apayao Province and MLGU Kabugao in cooperation with the DPWH
   Apayao I are commended for the swift conduct of a parcellary survey on August 2011 along
   the road line to delineate private properties from road right-of-way (RROW). This was
   among the conditions set by Secretary Singson prior to the issuance of the memorandum
   and funding release.

   For FY 2013-2016, the DPWH should program the construction of the seven (7) major
   bridges with a total length of 445 lm. crossing several tributaries of the Apayao River.
   Meanwhile, the contractor should immediately resume construction work.
                                           C-5
PROJECT PHOTO-DOCUMENTATION
                                Actual Project Site at Barangay Madatag




                                 Location: KO627+840-KO637+400




On July 1, 2012 the suspension order was issued since the contractor cannot mobilize due to series of
            massive slides and road cuts along the 21 km section leading to the project site.




                                                C-6
The DPWH-CO recently approved to utilized savings for the removal of slides and restoration of road
cuts costing Php 2.38 M. Consequently, the contractor was advised to resume effective Sept. 30, 2012




                                 Location: KO627+840-KO637+400




                                        The area has a vast
                                           potential for
                                           agriculture,
                                       water recreation and
                                         Philippine eagle
                                             watching




                                               C-7
Junction Kabugao, Apayao                                 Kabugao section




                    Junction San Nicolas, Ilocos Norte




                           Solsona Welcome Arch


                                C-8
Ongoing concreting work, near regional boundary



               COURTESY CALL and EXIT CONFERENCE




                       Exit conference with Kabugao Municipal
                         Administrator Romeo Tamot (2nd R)




With Engr. Domingo Enciso (R) and                 Exit conference with DPWH Apayao I
     Kabugao Local Officials                ADE Edward P. Magno (R) and Engr. Domigo Enciso
                                                   (L) and PE Antonio Banguec (2nd L)

                                      C-9

Más contenido relacionado

La actualidad más candente

Local Planning and Budgeting Linkage
Local Planning and Budgeting LinkageLocal Planning and Budgeting Linkage
Local Planning and Budgeting Linkageyee tandog
 
Strategic Planning Models by Dr. Eusebio F. Miclat Jr. Development Planning &...
Strategic Planning Models by Dr. Eusebio F. Miclat Jr. Development Planning &...Strategic Planning Models by Dr. Eusebio F. Miclat Jr. Development Planning &...
Strategic Planning Models by Dr. Eusebio F. Miclat Jr. Development Planning &...Jo Balucanag - Bitonio
 
Local development planning
Local development planningLocal development planning
Local development planningGil Sr.
 
Barangay integrated development plan
Barangay integrated development planBarangay integrated development plan
Barangay integrated development planRigino Macunay Jr.
 
Overview in Barangay Budgeting
Overview in Barangay BudgetingOverview in Barangay Budgeting
Overview in Barangay Budgetingyee tandog
 
General Provisions of RA 9184
General Provisions of RA 9184General Provisions of RA 9184
General Provisions of RA 9184Emily Marundan
 
Property and Supply Management w/ introduction to R.A. 9184 Government Procur...
Property and Supply Management w/ introduction to R.A. 9184 Government Procur...Property and Supply Management w/ introduction to R.A. 9184 Government Procur...
Property and Supply Management w/ introduction to R.A. 9184 Government Procur...Juan Paolo Somorostro - Aranas, MPA, BSOSM
 
Philippine Public Financial Management System and its Role in National Develo...
Philippine Public Financial Management System and its Role in National Develo...Philippine Public Financial Management System and its Role in National Develo...
Philippine Public Financial Management System and its Role in National Develo...O C
 
Seal of Good Local Governance
Seal of Good Local GovernanceSeal of Good Local Governance
Seal of Good Local GovernanceAlvin Almo
 
(institutional sector) rev
(institutional  sector) rev(institutional  sector) rev
(institutional sector) revPrimum Nocere
 
Implementing Rules of the Local Government Code of the Philippines
Implementing Rules of the Local Government Code of the PhilippinesImplementing Rules of the Local Government Code of the Philippines
Implementing Rules of the Local Government Code of the PhilippinesHarve Abella
 
Philippine Rural Development Problems Issues and Directions.pptx
Philippine Rural Development Problems Issues and Directions.pptxPhilippine Rural Development Problems Issues and Directions.pptx
Philippine Rural Development Problems Issues and Directions.pptxJo Balucanag - Bitonio
 
Mainstreaming Gender and Development (GAD) in Cooperatives
Mainstreaming Gender and Development (GAD)  in CooperativesMainstreaming Gender and Development (GAD)  in Cooperatives
Mainstreaming Gender and Development (GAD) in Cooperativesjo bitonio
 

La actualidad más candente (20)

Local Development Planning
Local Development PlanningLocal Development Planning
Local Development Planning
 
Logical framework
Logical frameworkLogical framework
Logical framework
 
Rationalized Planning System
Rationalized Planning SystemRationalized Planning System
Rationalized Planning System
 
Local Planning and Budgeting Linkage
Local Planning and Budgeting LinkageLocal Planning and Budgeting Linkage
Local Planning and Budgeting Linkage
 
project dev't cycle
project dev't cycleproject dev't cycle
project dev't cycle
 
Strategic Planning Models by Dr. Eusebio F. Miclat Jr. Development Planning &...
Strategic Planning Models by Dr. Eusebio F. Miclat Jr. Development Planning &...Strategic Planning Models by Dr. Eusebio F. Miclat Jr. Development Planning &...
Strategic Planning Models by Dr. Eusebio F. Miclat Jr. Development Planning &...
 
Local development planning
Local development planningLocal development planning
Local development planning
 
Barangay integrated development plan
Barangay integrated development planBarangay integrated development plan
Barangay integrated development plan
 
Overview in Barangay Budgeting
Overview in Barangay BudgetingOverview in Barangay Budgeting
Overview in Barangay Budgeting
 
Voluntary Sector Management
Voluntary Sector ManagementVoluntary Sector Management
Voluntary Sector Management
 
General Provisions of RA 9184
General Provisions of RA 9184General Provisions of RA 9184
General Provisions of RA 9184
 
Property and Supply Management w/ introduction to R.A. 9184 Government Procur...
Property and Supply Management w/ introduction to R.A. 9184 Government Procur...Property and Supply Management w/ introduction to R.A. 9184 Government Procur...
Property and Supply Management w/ introduction to R.A. 9184 Government Procur...
 
Philippine Public Financial Management System and its Role in National Develo...
Philippine Public Financial Management System and its Role in National Develo...Philippine Public Financial Management System and its Role in National Develo...
Philippine Public Financial Management System and its Role in National Develo...
 
Seal of Good Local Governance
Seal of Good Local GovernanceSeal of Good Local Governance
Seal of Good Local Governance
 
(institutional sector) rev
(institutional  sector) rev(institutional  sector) rev
(institutional sector) rev
 
Implementing Rules of the Local Government Code of the Philippines
Implementing Rules of the Local Government Code of the PhilippinesImplementing Rules of the Local Government Code of the Philippines
Implementing Rules of the Local Government Code of the Philippines
 
Report on decentralized planning
Report on decentralized planningReport on decentralized planning
Report on decentralized planning
 
Philippine Rural Development Problems Issues and Directions.pptx
Philippine Rural Development Problems Issues and Directions.pptxPhilippine Rural Development Problems Issues and Directions.pptx
Philippine Rural Development Problems Issues and Directions.pptx
 
National Government and Local Government Budget Process
National Government and Local Government Budget ProcessNational Government and Local Government Budget Process
National Government and Local Government Budget Process
 
Mainstreaming Gender and Development (GAD) in Cooperatives
Mainstreaming Gender and Development (GAD)  in CooperativesMainstreaming Gender and Development (GAD)  in Cooperatives
Mainstreaming Gender and Development (GAD) in Cooperatives
 

Destacado

Destacado (10)

1st qtr rpmes 2013
1st qtr rpmes 20131st qtr rpmes 2013
1st qtr rpmes 2013
 
Dar arisp iii 2nd qtr_f
Dar arisp iii 2nd qtr_fDar arisp iii 2nd qtr_f
Dar arisp iii 2nd qtr_f
 
ARISP III Inspection Report
ARISP III Inspection ReportARISP III Inspection Report
ARISP III Inspection Report
 
2nd qtr rpmes report
2nd qtr rpmes report2nd qtr rpmes report
2nd qtr rpmes report
 
Dpwh kabugao solsona_2nd qtr_f
Dpwh kabugao solsona_2nd qtr_fDpwh kabugao solsona_2nd qtr_f
Dpwh kabugao solsona_2nd qtr_f
 
Researchpaper (2)
Researchpaper (2)Researchpaper (2)
Researchpaper (2)
 
2012 yearend report
2012 yearend report2012 yearend report
2012 yearend report
 
4PS Ict slide share
4PS Ict slide share4PS Ict slide share
4PS Ict slide share
 
4 p's
4 p's4 p's
4 p's
 
How to make a tarpapel
How to make a tarpapelHow to make a tarpapel
How to make a tarpapel
 

Similar a 3rd qtr rpmes report

Annual report 2015 edited
Annual report 2015 editedAnnual report 2015 edited
Annual report 2015 editedValerie Alarcon
 
Pasig River Rehabilitation ADB-Evaluation-Study V Loan 1746.pdf
Pasig River Rehabilitation ADB-Evaluation-Study V Loan 1746.pdfPasig River Rehabilitation ADB-Evaluation-Study V Loan 1746.pdf
Pasig River Rehabilitation ADB-Evaluation-Study V Loan 1746.pdfABLoveria
 
Infrastructure Investments to Return Philippine Economy to Growth
Infrastructure Investments to Return Philippine Economy to GrowthInfrastructure Investments to Return Philippine Economy to Growth
Infrastructure Investments to Return Philippine Economy to GrowthFernando Penarroyo
 
Public Private Partnerships. Infrastructure Projects Plan in Indonesia.
Public Private Partnerships. Infrastructure Projects Plan in Indonesia.Public Private Partnerships. Infrastructure Projects Plan in Indonesia.
Public Private Partnerships. Infrastructure Projects Plan in Indonesia.Oswar Mungkasa
 
LECTURE-1 Introduction to Project Concept, Lifecycle .pptx
LECTURE-1 Introduction to Project Concept, Lifecycle .pptxLECTURE-1 Introduction to Project Concept, Lifecycle .pptx
LECTURE-1 Introduction to Project Concept, Lifecycle .pptxmansoor584949
 
Presentación Ministra Orozco CIS + Panel infraestructura 8 de octubre
Presentación Ministra Orozco CIS + Panel infraestructura 8 de octubrePresentación Ministra Orozco CIS + Panel infraestructura 8 de octubre
Presentación Ministra Orozco CIS + Panel infraestructura 8 de octubreProColombia
 
Vol.9 appendices to environmental impact assessment and resettlement aspects
Vol.9  appendices to environmental impact assessment and resettlement aspectsVol.9  appendices to environmental impact assessment and resettlement aspects
Vol.9 appendices to environmental impact assessment and resettlement aspectszubeditufail
 
Public Private Partnership Brochure May2012
Public Private Partnership Brochure May2012Public Private Partnership Brochure May2012
Public Private Partnership Brochure May2012Ezzedin Tago
 
2. COSOP results review mtr 2016
2. COSOP results review mtr 20162. COSOP results review mtr 2016
2. COSOP results review mtr 2016ifadseahub
 
Ifad west africa hub compile case studies 2019-en
Ifad west africa hub compile case studies 2019-enIfad west africa hub compile case studies 2019-en
Ifad west africa hub compile case studies 2019-enBenoît THIERRY
 

Similar a 3rd qtr rpmes report (20)

2nd qtr rpmes 2013
2nd qtr rpmes 20132nd qtr rpmes 2013
2nd qtr rpmes 2013
 
2nd qtr rpmes 2012
2nd qtr rpmes 20122nd qtr rpmes 2012
2nd qtr rpmes 2012
 
2nd qtr rpmes 2012
2nd qtr rpmes 20122nd qtr rpmes 2012
2nd qtr rpmes 2012
 
2nd qtr rpmes report
2nd qtr rpmes report2nd qtr rpmes report
2nd qtr rpmes report
 
Annual report 2015 edited
Annual report 2015 editedAnnual report 2015 edited
Annual report 2015 edited
 
O18_ CBFM2
O18_ CBFM2O18_ CBFM2
O18_ CBFM2
 
Pasig River Rehabilitation ADB-Evaluation-Study V Loan 1746.pdf
Pasig River Rehabilitation ADB-Evaluation-Study V Loan 1746.pdfPasig River Rehabilitation ADB-Evaluation-Study V Loan 1746.pdf
Pasig River Rehabilitation ADB-Evaluation-Study V Loan 1746.pdf
 
1. River Basin Planning - some key developments - Colin Byrne, DHPLG
1. River Basin Planning - some key developments - Colin Byrne, DHPLG1. River Basin Planning - some key developments - Colin Byrne, DHPLG
1. River Basin Planning - some key developments - Colin Byrne, DHPLG
 
Da charmp 2 2nd qtr_f
Da charmp 2 2nd qtr_fDa charmp 2 2nd qtr_f
Da charmp 2 2nd qtr_f
 
Infrastructure Investments to Return Philippine Economy to Growth
Infrastructure Investments to Return Philippine Economy to GrowthInfrastructure Investments to Return Philippine Economy to Growth
Infrastructure Investments to Return Philippine Economy to Growth
 
Staurt Earl - ARCC Programme for APM Awards.pptx
Staurt Earl - ARCC Programme for APM Awards.pptxStaurt Earl - ARCC Programme for APM Awards.pptx
Staurt Earl - ARCC Programme for APM Awards.pptx
 
Monthly progress report , Resettlement ,Rehabilitation , Livelihood and Rest...
Monthly progress report , Resettlement  ,Rehabilitation , Livelihood and Rest...Monthly progress report , Resettlement  ,Rehabilitation , Livelihood and Rest...
Monthly progress report , Resettlement ,Rehabilitation , Livelihood and Rest...
 
Public Private Partnerships. Infrastructure Projects Plan in Indonesia.
Public Private Partnerships. Infrastructure Projects Plan in Indonesia.Public Private Partnerships. Infrastructure Projects Plan in Indonesia.
Public Private Partnerships. Infrastructure Projects Plan in Indonesia.
 
LECTURE-1 Introduction to Project Concept, Lifecycle .pptx
LECTURE-1 Introduction to Project Concept, Lifecycle .pptxLECTURE-1 Introduction to Project Concept, Lifecycle .pptx
LECTURE-1 Introduction to Project Concept, Lifecycle .pptx
 
Presentación Ministra Orozco CIS + Panel infraestructura 8 de octubre
Presentación Ministra Orozco CIS + Panel infraestructura 8 de octubrePresentación Ministra Orozco CIS + Panel infraestructura 8 de octubre
Presentación Ministra Orozco CIS + Panel infraestructura 8 de octubre
 
Vol.9 appendices to environmental impact assessment and resettlement aspects
Vol.9  appendices to environmental impact assessment and resettlement aspectsVol.9  appendices to environmental impact assessment and resettlement aspects
Vol.9 appendices to environmental impact assessment and resettlement aspects
 
Public Private Partnership Brochure May2012
Public Private Partnership Brochure May2012Public Private Partnership Brochure May2012
Public Private Partnership Brochure May2012
 
2. COSOP results review mtr 2016
2. COSOP results review mtr 20162. COSOP results review mtr 2016
2. COSOP results review mtr 2016
 
Ifad west africa hub compile case studies 2019-en
Ifad west africa hub compile case studies 2019-enIfad west africa hub compile case studies 2019-en
Ifad west africa hub compile case studies 2019-en
 
British Columbia Capital Projects Inventory 2019-2021
British Columbia Capital Projects Inventory 2019-2021British Columbia Capital Projects Inventory 2019-2021
British Columbia Capital Projects Inventory 2019-2021
 

Más de Rdc Cordillera

Search for cordillera champions
Search for cordillera championsSearch for cordillera champions
Search for cordillera championsRdc Cordillera
 
Dep ed red & black school buildngs_2nd qtr_f
Dep ed red & black school buildngs_2nd qtr_fDep ed red & black school buildngs_2nd qtr_f
Dep ed red & black school buildngs_2nd qtr_fRdc Cordillera
 
Doh local health system 2nd_qtr_f
Doh local health system 2nd_qtr_fDoh local health system 2nd_qtr_f
Doh local health system 2nd_qtr_fRdc Cordillera
 
Dpwh kabugao pudtol_2nd qtr_f
Dpwh kabugao pudtol_2nd qtr_fDpwh kabugao pudtol_2nd qtr_f
Dpwh kabugao pudtol_2nd qtr_fRdc Cordillera
 
Summary of priority sectoral program projects
Summary of priority sectoral program projectsSummary of priority sectoral program projects
Summary of priority sectoral program projectsRdc Cordillera
 
2nd qtr major program projects
2nd qtr major program projects2nd qtr major program projects
2nd qtr major program projectsRdc Cordillera
 
State of the Nation Address 2012
State of the Nation Address 2012State of the Nation Address 2012
State of the Nation Address 2012Rdc Cordillera
 
State of the region address cordillera administrative region
State of the region address   cordillera administrative regionState of the region address   cordillera administrative region
State of the region address cordillera administrative regionRdc Cordillera
 
Summary of programs and projects as of first quarter 2012
Summary of programs and projects as of first quarter 2012Summary of programs and projects as of first quarter 2012
Summary of programs and projects as of first quarter 2012Rdc Cordillera
 
Red and black schoolbuilding program inspection report
Red and black schoolbuilding program inspection reportRed and black schoolbuilding program inspection report
Red and black schoolbuilding program inspection reportRdc Cordillera
 
National greening program inspection report
National greening program inspection reportNational greening program inspection report
National greening program inspection reportRdc Cordillera
 
2012 rpmc inspection reports
2012 rpmc inspection reports2012 rpmc inspection reports
2012 rpmc inspection reportsRdc Cordillera
 

Más de Rdc Cordillera (19)

1st qtr rpmes report
1st qtr rpmes report1st qtr rpmes report
1st qtr rpmes report
 
Search for cordillera champions
Search for cordillera championsSearch for cordillera champions
Search for cordillera champions
 
Nomination form
Nomination formNomination form
Nomination form
 
Vacaciesjan2012 1
Vacaciesjan2012 1Vacaciesjan2012 1
Vacaciesjan2012 1
 
Dpwh kabugao
Dpwh kabugaoDpwh kabugao
Dpwh kabugao
 
Dep ed red & black school buildngs_2nd qtr_f
Dep ed red & black school buildngs_2nd qtr_fDep ed red & black school buildngs_2nd qtr_f
Dep ed red & black school buildngs_2nd qtr_f
 
Doh local health system 2nd_qtr_f
Doh local health system 2nd_qtr_fDoh local health system 2nd_qtr_f
Doh local health system 2nd_qtr_f
 
Dpwh kabugao pudtol_2nd qtr_f
Dpwh kabugao pudtol_2nd qtr_fDpwh kabugao pudtol_2nd qtr_f
Dpwh kabugao pudtol_2nd qtr_f
 
Dswd 4 ps_2nd qtr_f
Dswd 4 ps_2nd qtr_fDswd 4 ps_2nd qtr_f
Dswd 4 ps_2nd qtr_f
 
Summary of priority sectoral program projects
Summary of priority sectoral program projectsSummary of priority sectoral program projects
Summary of priority sectoral program projects
 
Denr ngp 2nd qtr_f
Denr ngp 2nd qtr_fDenr ngp 2nd qtr_f
Denr ngp 2nd qtr_f
 
2nd qtr major program projects
2nd qtr major program projects2nd qtr major program projects
2nd qtr major program projects
 
State of the Nation Address 2012
State of the Nation Address 2012State of the Nation Address 2012
State of the Nation Address 2012
 
State of the region address cordillera administrative region
State of the region address   cordillera administrative regionState of the region address   cordillera administrative region
State of the region address cordillera administrative region
 
Summary of programs and projects as of first quarter 2012
Summary of programs and projects as of first quarter 2012Summary of programs and projects as of first quarter 2012
Summary of programs and projects as of first quarter 2012
 
Red and black schoolbuilding program inspection report
Red and black schoolbuilding program inspection reportRed and black schoolbuilding program inspection report
Red and black schoolbuilding program inspection report
 
National greening program inspection report
National greening program inspection reportNational greening program inspection report
National greening program inspection report
 
2012 rpmc inspection reports
2012 rpmc inspection reports2012 rpmc inspection reports
2012 rpmc inspection reports
 
Eo no. 78 2012
Eo no. 78 2012Eo no. 78 2012
Eo no. 78 2012
 

3rd qtr rpmes report

  • 1. Republic of the Philippines Cordillera Administrative Region Regional Project Monitoring Committee Third Quarter CY 2012 RPMES REPORT Prepared by the National Economic and Development Authority Cordillera Administrative Region RPMC Secretariat
  • 2. CY 2012 Major Programs and Projects --------- 1 Project Implementation Status --------- 2 CY 2012 Priority Sectoral Programs/ Projects --------- 4 RPMC Project Site Inspections --------- 5 Annexes: A List of Major Programs/Projects --------- A-1 B Eight Priority Sectoral Programs/Projects Second Cordillera Highland Agricultural Resource --------- B-1 Management Program (CHARMP 2) 4 Pantawid Pamilyang Pilipino Program (4Ps) --------- B-5 Agrarian Reform Infrastructure Support Program --------- B-10 (ARISP) Kabugao, Apayao – Solsona, Ilocos Norte Road --------- B-13 Kabugao-Pudtol-Luna-Cagayan Boundary --------- B-17 Cordillera-wide Strengthening of Local Systems --------- B-20 for Effective and Efficient Delivery of Maternal and Child Health Services National Greening Program (NGP) --------- B-21 Red and Black School Building Program --------- B-24 C Inspection Reports Kabugao-Pudtol-Luna- Cagayan Boundary Road --------- C-1 Kabugao, Apayao – Solsona, Ilocos Norte Road --------- C-4
  • 3. Third Quarter CY 2012 RPMES Report The Regional Project Monitoring and Evaluation System (RPMES) report is prepared on a quarterly basis to provide an overall view on the status of major program/project (P/Ps) implementation in the region. The report is based on the submission of eleven regional line agencies (RLAs). I. CY 2012 Major Programs/Projects For CY 2012, there are 46 major P/Ps with an aggregate cost of Php 10.633 Billion of which about Php 5.9 billion or 55.52 percent are new P/Ps, Php 3.9 billion or 37.52 percent are multi-year projects, and Php 0.740 billion or 6.96 percent are carryover projects. In terms of cost, the economic development sector has the highest at 51.21 percent or Php 5,445 billion, followed by the infrastructure sector at 27 percent or Php 2,794 billion, and the social sector having the least at 18.68 percent or Php 1,985.883 billion. Also included are rehabilitation and reconstruction projects under the Strategic Action Plan (SAP) on areas affected by typhoons “Pedring” and “Quiel” in 2011 amounting to 4 percent or Php 407 million. 1 Third Quarter CY 2012 RPMES Report
  • 4. In terms of funding source, 67 percent is locally funded while 32 percent is foreign assisted. The foreign- assisted projects are: (a) Second Cordillera Highland Agriculture Resource Management Program (CHARMP II), Php 3.2 Billion, (b) Agrarian Reform Infrastructure Support Program (ARISP), Php 903 Million; and (c) Rural Micro-Enterprises Promotion Program (RuMEPP), Php 1.8 Million. II. Project Implementation Status For the third quarter, the overall status of project implementation is 43 percent, a 10 percent increase from the second quarter. The SAP projects posted the highest accomplishment followed the social sector, then the infrastructure sector. The economic sector’s low performance is the due to the delayed implementation of its banner project, the CHARMP 2. (Please refer to Annex A for the detailed status of the 46 projects) Projects identified under the SAP of areas affected by typhoons Pedring, Quiel and Juan posted an accomplishment of 96.41 percent, most of which are roads and school building projects. The Social Sector obtained an overall accomplishment of 52.82 percent. The projects reported under the sector are DSWD’s Pantawid Pamilyang Pilipino Program (4Ps), DepEd’s Red and Black Schoolbuilding Program, Rehabilitation of School Building including Water Sanitation Facilites and Philippines’ Response to Indigenous and Muslim Education (PRIME), DOH’s Health Facilities and Water System Projects and foreign-assisted Cordillera-wide Strengthening of Local 2 Third Quarter CY 2012 RPMES Report
  • 5. Health System for Effective and Efficient Delivery of Maternal and child Health Service. The Infrastructure Sector had an overall accomplishment of 47.09 percent, composed of DPWH’s priority roads and bridge projects. These priority roads are mainly laterals that link CAR to Regions I and II. The Economic Sector posted an overall accomplishment of 45.57 percent. The sector’s accomplishment is relatively the lowest due to the negative slippages incurred by two of its major projects, these are: DA’s foreign-assisted project Second Phase of Cordillera Highland Agricultural Resource Management Project or CHARMP 2 costing about Php 3 Billion, and DENR’s National Government Priority, National Greening Program (NGP) costing about Php 124 Million. The other projects under the sector are DAR’s Agrarian Reform Infrastructure Support Project (ARISP III), DA’s Farm-to-Market Roads, NIA’s Irrigation Projects, DTI’s One Town One Product Program (OTOP) and Shared Service Facilities SSF, and DOST’s completed Small Enterprises Technology Program (SETUP), and Packaging and Labeling Project. Implementation Status (as Sept. 2012) 100.00% 96.41% 80.00% 52.82% 60.00% 45.57% 47.09% 49.27 % 40.00% 20.00% 0.00% 3 Third Quarter CY 2012 RPMES Report
  • 6. The overall performance during the quarter translates to four (4) P/P completed – the SETUP of DOST, two (2) sections of the Abra-Kalinga Road, and Gurel-Bokod-Kabayan-Buguias-Abatan Road, eight (8) P/P are ahead of schedule, 20 are on track, and 14 behind schedule. Of the 14 projects reported behind schedule, 11 projects incurred negative slippages less than negative 15 percent. The common reason reported was due to inclement weather/typhoons in the project area. Agencies have adopted catch-up plans to put the projects on track. The DA implemented CHARMP 2 had a negative 26 percent slippage because it underwent another NEDA ICC process for project reconfiguration to address the issue on LGU counterpart. CHARMP will have to retarget its work schedule once reconfiguration has been in effect. The National Greening Program (NGP) also experienced a big slippage of negative 19.63 percent due to change in procurement process. The NGP also adopted a catch-up plan to put the project on track. The Philippine Response to Indigenous and Muslim Education (PRIME) of DepEd, is the most problematic project that has a negative 51 percent slippage. DepEd acknowledges the delay and has undertaken actions to put the project on track. III. CY 2012 Priority Sectoral Programs/ Projects From the 46 programs/projects, eight (8) were identified as priority sectoral programs/projects by the sectoral committees and tagged as their banner projects. These programs/projects with an aggregate cost of Php 5.3 billion are being closely monitored by the RPMC. These were selected based on the criteria set during the RPMES national forum: (a) foreign- assisted projects (FAP/ODA), (b) interprovincial, (c) large scale cost, (d) national priority, critical projects by the Office of the President (OP), and (e) regional priority. These programs/projects are as follows: 1. Second Cordillera Highland Agricultural Resource Management Project (CHARMP 2) 2. Pantawid Pamilyang Pilipino Program (4Ps) 3. Agrarian Reform Infrastructure Support Project, Phase III 4. Kabugao-Solsona, Apayao-Ilocos Norte Road 5. Kabugao-Pudtol- Luna- Cagayan Boundary Road 6. Cordillera-wide Strengthening of Local health System for Effective and Efficient Delivery of Maternal and Child Health Services 7. National Greening Program 8. Red and Black School Building Program Of the eight (8) priority P/Ps, five (5) have been inspected/validated, while the remaining three (3) are scheduled for inspection by the RPMC before the year ends, these are CHARMP, 4Ps and the Cordillera-wide Strengthening of Local Health Systems for Effective and Efficient Delivery of Maternal and Child Health Services. The JICA-assisted Cordillera-wide Strengthening of Local Health Systems launched in the first quarter has accordingly procured medical equipment for the provinces of Abra and Apayao. (Please refer to Annex B for the details of the eight priority sectoral programs/projects) 4 Third Quarter CY 2012 RPMES Report
  • 7. IV. RPMC Project Site Inspections An inspection/validation of the Kabugao-Pudtol-Luna-Cagayan Boundary Road and the Road Opening of Kabugao, Apayao-Solsona, Ilocos Norte Road (Apayao Side) was conducted by the RPMC Inspectorate Team on October 9 - 10, 2012. These are regional priority projects and major components of the Cordillera Roads Improvement Project (CRIP). The roads are among Apayao national roads upgraded from secondary to arterial classification through DPWH Memorandum dated November 2, 2011 by DPWH Secretary Rogelio Singson. This memorandum was a result of an RDC-CAR dialogue with the DPWH Secretary held August 5, 2011 in Baguio City. During the site inspection, the Kabugao-Pudtol-Luna-Cagayan Boundary Road is proceeding smoothly having a status of 64.79 percent. The other project, the Kabugao, Apayao – Solsona, Ilocos Norte Road, 0.50 percent status, was recently issued a resume order after a suspension due to recent typhoons. It has been observed that the construction of several bridges in both projects have to be programmed to make them passable. (Please refer to Annex C for Inspection Reports) 5 Third Quarter CY 2012 RPMES Report
  • 8. Annex A LIST OF MAJOR PROGRAMS/PROJECTS
  • 9. Third Quarter RPMES Report CY 2012 MAJOR PROGRAMS/PROJECTS Cordillera Administrative Region As of September 2012 IMPLEMENTING PROJECT COST FUNDING STATUS/ PROGRAM/PROJECT AGENCY (PhP M) SOURCE REMARKS SOCIAL SECTOR 1. Pantawid Pamilyang Pilipino DSWD 888.889 Loan 63.06% Program (4Ps) Slippage: -3.62% 2. Red and Black School Building DepEd CY 2011: GOP CY 2011 Program 166.944 95.94% 209 Classrooms CY 2012: CY 2012 115.200 34.16% 143 Classrooms 3. Cordillera-wide Strengthening of DOH & LGUs 43.00 JICA 5% Local Health System for Effective Abra Apayao and Efficient Delivery of Maternal Benguet and Child Health Services 4. National Household Targeting DSWD 41.025 GOP, 59.41% System for Poverty Reduction Loan Program 5. Rehabilitation of School Building DepEd School Building GOP including Water Sanitation CY 2011: CY 2011 Fund: Facilities 15.468 88.92% WATSAN CY 2011: CY 2011 Fund: 15.861 96.48% School Building CY 2012: CY 2012 Fund: 28.633 Waiting for SARO WATSAN CY 2012: 29.340 6. Philippine Response to Indigenous DepEd 3.978 AusAid 31% People’s (IP) and Muslim Education (PRIME) Slippage: -51% A-1
  • 10. Third Quarter RPMES Report CY 2012 MAJOR PROGRAMS/PROJECTS Cordillera Administrative Region As of September 2012 IMPLEMENTING PROJECT COST FUNDING STATUS/ PROGRAM/PROJECT AGENCY (PhP M) SOURCE REMARKS 7. Construction of Various Health DOH CY 2011: GOP CY 2011 fund: Facility 117.867 58.55% CY 2012: CY 2012 fund: 335.179 6.49% 8. Water Supply System DOH 184.500 GOP 76.64% Sub-Total 1,985.883 52.82% ECONOMIC SECTOR 9. Second Cordillera Highland DA 3,081.862 IFAD, 34.25% Agricultural Resource ADB. Management Project (CHARMP2) OFID Slippage: -26.61% 10. Agrarian Reform Infrastructure DAR Total Project Loan 72.26% Support Project Phase III Cost: GOP (Abra, Apayao, Benguet, Ifugao, 903.863 Slippage: Kalinga and Mt. Province) +22.25% CY 2011: (2 projects) 16.718 CY 2012: (12 projects) 176.027 11. National Greening Program (NGP) DENR 124.339 GOP 73.44% Slippage: -19.63% 12. Farm-to-Market Roads DA CY 2011: Grant CY 2011: (CY 2011 Fund: Abra, Kalinga and 53.00 85.66% Mt. Province) (CY 2012 Fund: Abra, Baguio City, CY 2012: CY 2012: Benguet, Ifugao, Kalinga and Mt. 161.803 18.58% Province) A-2
  • 11. Third Quarter RPMES Report CY 2012 MAJOR PROGRAMS/PROJECTS Cordillera Administrative Region As of September 2012 IMPLEMENTING PROJECT COST FUNDING STATUS/ PROGRAM/PROJECT AGENCY (PhP M) SOURCE REMARKS 13. Irrigation Projects NIA 1,078.046 GOP 53.13% (432 projects) 14. One Town One Product Program DTI 2.747 GOP 84.68% (OTOP) 15. Rural Micro Enterprise Promotion DTI 1.800 IFAD with 90% Programme (RuMEPP) GOP Counter Part 16. Shared Service Facilities Project DTI 8.388 NEDAC Awarding of (SSF) Fund bidding (National suppliers Export Develop- ment and Competi- tiveness) 17. Small Enterprise Technology DOST 28.673 GOP 100% Upgrading Program (SETUP) Core and Non-Core Funded Projects 18. Packaging and Labeling DOST 0.688 GOP 76% Sub-Total 5,445.208 45.57% INFRASTRUCTURE SECTOR Abra 19. Abra-Ilocos Sur Road DPWH 106.195 GOP 55.25% Slippage: -8.68% 20. Abra-Kalinga Road, K0467+000- DPWH 147.691 GOP 14% K0474+305 Slippage: +2.67% A-3
  • 12. Third Quarter RPMES Report CY 2012 MAJOR PROGRAMS/PROJECTS Cordillera Administrative Region As of September 2012 IMPLEMENTING PROJECT COST FUNDING STATUS/ PROGRAM/PROJECT AGENCY (PhP M) SOURCE REMARKS 21. Abra-Ilocos Norte, K0436+700- DPWH 62.00 GOP 13.83% K0439+395 Slippage: -11.17% 22. Road Upgrading along Abra- DPWH 60.00 GOP 24.77% Cervantes Road (Realigned from Sto. Tomas-Manabo Bridge) Slippage: +3.60% 23. Sto. Tomas-Manabo Bridge DPWH 160.00 GOP 76.81% (P160.0 M) Slippage: -9.03% 24. Abra-Kalinga Road K0410+000- DPWH 50.45 GOP 100% K0413+810 25. Abra-Kalinga Road K0437+490- DPWH 143.67 GOP 100% K0455+890, K0432+000 K0450+800 Apayao 26. Kabugao-Pudtol-Luna Cagayan DPWH 58.827 GOP 62.51% Boundary Road K0661+000 - K0661+321, Slippage: K0643+646 - K0645+825 -4.90% Gravel to Concrete 27. Kabugao, Apayao-Solsona, Ilocos DPWH 100.00 GOP 0.05% Norte Road Slippage: -1.98% Benguet 28. Rehab./Reconst’n/Upgrading of DPWH 54.433 GOP 31.31% Kennon Road Slippage: -9.49% A-4
  • 13. Third Quarter RPMES Report CY 2012 MAJOR PROGRAMS/PROJECTS Cordillera Administrative Region As of September 2012 IMPLEMENTING PROJECT COST FUNDING STATUS/ PROGRAM/PROJECT AGENCY (PhP M) SOURCE REMARKS 29. Baguio-Bontoc Road (Pico- DPWH 98.674 GOP 28.77% Lamtang Rd., Baguio Itogon & Baguio-Bontoc) Slippage: +14.27% 30. Baguio-Bontoc Road, K0269+000- DPWH 109.332 GOP 17% K0275+000 (v.s.)& K0299+000- K0300+900 (v.s.) & K0305+000- Slippage: K0308+500 (v.s.) & K0309+000- +1.60% K0311+000 (v.s.), K0317+415- K0318+500 (v.s.), & K0323+000 – K0328+000 (v.s.) 31. Gurel-Bokod-Kabayan-Buguias- DPWH 98.50 GOP 91.10% Abatan Road Slippage: +2.20% 32. Gurel-Bokod-Kabayan-Buguias- DPWH 116.50 GOP 100% Abatan Road K0303+600- K03012+000 33. Rehab./Impv’t. of Gurel-Bokod- DPWH 148.00 GOP 41.30% Kabayan-Buguias Road including RROW Slippage: +19.70% 34. Gurel-Bokod-Kabayan-Buguias- DPWH 68.921 GOP 46% Abatan Road, K0345+513- K0359+300 (vs.) Slippage: -12.39% Ifugao 35. Banaue-Mayoyao-A Lista-Isabela DPWH 58.064 GOP 17.35% Bdry. Road Slippage: -13.96% A-5
  • 14. Third Quarter RPMES Report CY 2012 MAJOR PROGRAMS/PROJECTS Cordillera Administrative Region As of September 2012 IMPLEMENTING PROJECT COST FUNDING STATUS/ PROGRAM/PROJECT AGENCY (PhP M) SOURCE REMARKS 36. Nueva Vizcaya-Ifugao-Mt. DPWH 54.163 GOP 65% Province Road Slippage: -6.64% Kalinga 37. Kalinga-Abra Road, K0470+000- DPWH 53.057 GOP 39.98% K0472+267 Slippage: -4.95% 38. Kalinga-Abra Road, K0476+000- DPWH 135.27 GOP 8.75% K0480+1000, K0480+1000- K0482+700 (with exceptions) Slippage: +1.44% 39. Balbalan-Pinukpuk Road DPWH 100.00 GOP 87% K0485+000-K0489+000 Slippage: -9.40% 40. Balbalan-Pinukpuk Road DPWH 245.00 GOP 62% K0560+1061-K0520+449 Slippage: -10% 41. Mt. Province Bdry. –Calanan- DPWH 209.00 GOP 49.37% Pinukpuk –Abbut Road (Pinukpuk) (P209.0 M) K0499+674- Slippage: K0509+294 (I.S.) -50.63% 42. Balbalan-Pinukpuk Road, Abut A DPWH 183.239 GOP Notice of of Baay Bridge+(-18502) to Abut A award issued of Baay Bridge+0 September 6, 2012. Contract papers on process. A-6
  • 15. Third Quarter RPMES Report CY 2012 MAJOR PROGRAMS/PROJECTS Cordillera Administrative Region As of September 2012 IMPLEMENTING PROJECT COST FUNDING STATUS/ PROGRAM/PROJECT AGENCY (PhP M) SOURCE REMARKS Mountain Province 43. Mt. Province –Ilocos Sur via Tue DPWH 81.815 GOP 31.17% Road Slippage: -6.28% 44. Mt. Province-Ilocos Sur via Kayan DPWH 92.00 GOP 54.40% Slippage: -4.66% Sub-Total 2,794.801 47.09% STRATEGIC ACTION PLAN (SAP) (Rehabilitation and Recovery of Areas Affected by Disasters) 45. Disaster Related Rehabilitation DPWH DRRP Project (DRRP) Calamity Fund CY 2011 a. Apayao 1st District Engineering 74,550.0 87.73% Office (16 projects) b. Apayao 2nd District 14,000.0 100% Engineering Office (5 projects) c. Benguet 1st District 45,469.0 100% Engineering Office (15 projects) d. Benguet 2nd District 39,279.1 100% Engineering Office (6 projects) e. Baguio City District 600.0 100% Engineering Office (1 project) f. Ifugao 1st District Engineering 8,580.0 100% Office (2 projects) g. Ifugao 2nd District Engineering 25,850.0 100% Office (4 projects) h. Kalinga District Engineering 85,910.5 95.93% Office (9 projects) i. Mt. Province District Office 102,459.4 100% (28 projects) A-7
  • 16. Third Quarter RPMES Report CY 2012 MAJOR PROGRAMS/PROJECTS Cordillera Administrative Region As of September 2012 IMPLEMENTING PROJECT COST FUNDING STATUS/ PROGRAM/PROJECT AGENCY (PhP M) SOURCE REMARKS Sub-Total 396.697 96.81% 46. Quick Response Fund (QRF) DepEd GOP a. Cabaroan ES Dolores, Abra 1.202 56% (Construction of 1 unit-2 classroom in Bldg.1) b. Cabaroan ES Dolores, Abra 1.202 100% (Construction of 1 unit-2 classroom in Bldg.2) c. Cabaroan ES Dolores, Abra 318.0 79% (Construction of 3 Seater Toilet – type III with handwashing) d. Cabaroan ES Dolores, Abra 219.0 71% (1 classroom repair) e. Tonglo Carino PS, Buguias, 1.202 15% Benguet f. Talubin NHS, Bontoc Mt. 1.143 85% Province (Construction of 2cl / Replacement of Burned Bldg.) g. Tumog Es, Luna, Apayao 1.942 95% (Construction of 1stry 3 Classroom 7x9 type I) h. Lagawe CS, Lagawe, Ifugao 1.200 100% (Construction of 2cl / Replacement of Burned Bldg.) i. Bañacao ES, Bangued West, 1.600 100% Abra (Repair of Classrooms / Construction of Slope Protection /Water System) Sub-Total 10.027 80.56% SAP Sub-Total 406.724 96.41% CAR Total 10,632.616 49.27% Sources: RLAs RPMES PMC Form I-1 and RPMES PMC Form I-2 as of September 2012. A-8
  • 17. Annex B EIGHT (8) PRIORITY PROGRAMS/PROJECTS
  • 18. Second Cordillera Highland Agricultural Resource Management Project (CHARMP 2) PROJECT PROFILE Implementing Agency: Department of Agriculture-CAR Fund Sources: GOP: Department of Agriculture Loan: IFAD, OFID, ADB Grant: IFAD Total Project Cost: Php 3,081,862,000 Location/Area Coverage: 6 provinces, 37 municipalities, 170 barangays Abra: Lacub, Licuan-baay, Malibcong, Luba, Tubo, Sallapadan, Bucloc, Boliney Apayao: Calanasan, Kabugao, Conner Benguet: Bokod, Kabayan, Bakun, Kibungan,Buguias,Kapangan, Atok, Sablan, Mountain Province: Barlig, Besao, Sadanga, Sagada, Bontoc, Tadian, Bauko, Sabangan Kalinga: Balbalan, Pasil, Lubuagan, Tanudan, Tinglayan Ifugao: Hingyon, Hungduan, Tinoc, Asipulo, Mayoyao Description: The project goal is to reduce the poverty and improve the livelihood of poor rural women and men in indigenous communities in the upland areas of the Cordillera Administrative Region. The objectives are to (1) increase the household income of poor farmers through sustainable agricultural development; and (2) enhance the quality of life of targeted communities by improving land tenure security, food security and watershed conservation. The project has five components: (1) community mobilization, participatory planning of investments, and land titling; (2) community watershed conservation (including forest management and agro forestry development); (3) agricultural and agribusiness development, and promotion of income-generating activities; (4) rural infrastructure development; and (5) project management and coordination. Farm to market access Agro-forestry plots B-1 Third Quarter CY 2012 RPMES Report
  • 19. Second Cordillera Highland Agricultural Resource Management Project Meeting with the beneficiaries& Project field assessment PROJECT PROGRESS REPORT As of September 2012 Project Duration: Start: January 1, 2009 End: December 31, 2015 CY2009- CY2015 For CY 2012 AO 1st Quarter AO 2nd Quarter AO 3rd Quarter AO 4th Quarter Target 49.72% 53.43% 57.15% 60.86% Actual 18.45% 20.65% 34.25% Slippage -31.27% -32.78% -22.90% Cumulative Status: Status Physical Financial (Since start of Target 60.86% FOA+ Grant: project) Php 2,417.48 Actual 34.25% * Php 870.93 (36% of FOA+Grant) * (57.03% of the total allotment released) Php 1,527.073 from CY 2009-CY2012 Slippage -26.61% B-2 Third Quarter CY 2012 RPMES Report
  • 20. Current 1. Delayed implementation of infra subprojects due to difficulty of LGUs Implementation in providing cash counterpart required as indicated in the NG-LGU Issues and/or cost sharing policy. Problems Encountered 2. Approval of the proposed rural finance scheme/Livelihood Assistance (if any): Finance (LAF) in place of the credit subcomponent. 3. Extension of OFID Loan Agreement which will close in July 2013 Actions Taken/ 1. The project is waiting for the approval of the proposed NG-LGU cost Recommendations: sharing mix of 60%-40% for 1st-2nd class LGUs, 70%-30% for 3rd-6th class LGUs from the NEDA Board. While waiting for its approval, the Project recommended LGUs regardless of their classification to opt for the cost-sharing arrangement included in the Project Financing Agreement, where the CHARMP2 will shoulder 60% and LGUs will provide 40% equity in order to proceed with the implementation of proposed subprojects. However, only a few LGUs were able to provide counterpart based on this scheme. To initiate implementation of 25 submitted infra subproject proposals from LGUs that could not afford said NG-LGU cost sharing scheme, fund assistance from the DA-OSEC was sought to cover 30% of the total cost of subprojects. The Project and the concerned LGUs are now waiting for the release of CFA in the amount of Php 50 million from the DA-OSEC. As of June 2012, another batch of 71 subproject proposals was submitted to DA-OSEC for fund support in the amount of Php 89 million. 2. Since the credit scheme as a subcomponent of the original Project Design is not feasible for poor target beneficiaries in CAR, the Project proposed for the Livelihood Fund Assistance (LAF) that would assist livelihood and income generating activities of target groups. This proposal is part of the revised Project Design which is now for approval by the ICC/Government. 3. The Project requested for an extension of the loan validity to coincide with the loan closing of the IFAD loan (June 2016). Request was reiterated to DA-CO for submission to Department of Finance mid of October 2012. Remarks: The project is waiting for the final approval of the Revised Project Design by NEDA ICC Board/ National Government. B-3 Third Quarter CY 2012 RPMES Report
  • 21. Agency Contact DIR. MARILYN V. STA. CATALINA, CESO IV Person: Regional Executive Director, DA-RFU-CAR & Project Director, CHARMP2 CAMERON P. ODSEY Project Manager, CHARMP2 Address: PROJECT SUPPORT OFFICE Baguio Stock Farm Compound, Marcos Highway corner Sto. Tomas Road, 2600 Baguio City Telefax: +63.74.444.8329/ Tel No. +63. 74. 444.7991 Email: charm@mozcom.com B-4 Third Quarter CY 2012 RPMES Report
  • 22. Agrarian Reform Infrastructure Support (ARISP III) PROJECT PROFILE Implementing Agency: DAR-CAR / DPWH-CAR / NIA-CAR / LGUs Fund Sources: GOP: Loan: JICA Total Project Cost: Php 903,863,055.00 Project Cost (2011): Php 16.718 M Loan/Grant Proceeds: Php 677,897,291.25 Peso Counterpart: Php 225,965,763.75 Project Cost (2012): Php 176.027 M Location/Area Coverage: Abra: Daguioman, Lacub and Luba ARCs Apayao: Sta. Marcela, Flora and Pudtol ARCs Benguet: Bakun, Kapangan and Kibungan ARCs Ifugao: Asipulo, Hingyon and Tinoc ARCs Kalinga: Tinglayan, Rizal and Pasil ARCs Mt. Province: Sadanga, Bauko and Bontoc ARCs Description: The Agrarian Reform Infrastructure Support Project (ARISP) Phase III is a foreign-assisted project of DAR, designed to provide basic support services to help develop Agrarian Reform Communities (ARCs). It is funded from a concessional loan from the Government of Japan with counterpart financing from the DAR, Local Government Units and the beneficiaries. The project timetable is from CY 2008 to CY 2014. The project espouses the concept of integrated area development in the ARCs wherein basic infrastructure, organization / institutional, agricultural and enterprise development support are combined to produce incremental growth in productivity and income among farmers. Specifically, the project considers the provision of farm-to-market roads (FMR) and bridges, irrigation projects, post-harvest facilities, and potable water supply system under its infrastructure component. For institutional development component, this entails the organizing and strengthening of various organizations in the ARCs to build their capabilities to operate and manage the infrastructure facilities and agri-business in a sustainable basis. The project also supports the B-10 Third Quarter CY 2012 RPMES Report
  • 23. development of viable agribusiness in the ARCs to harness the agricultural potentials, add value to agricultural products, and make them more competitive in the market. In CAR, actual project implementation commenced in CY 2011. From CY 2008 to 2010, the pre- implementation activities conducted are indicative development planning, site validation, project prioritization and individual project designs. There are 61 projects confirmed with an aggregate cost of Php 903.86 M. For CY 2011, two (2) projects (irrigation project and water system) were implemented and recently completed with an aggregate cost of Php 16.72 M. These are located in the provinces of Abra and Benguet. DAR and NIA ARISP III Project Management Office representatives conducted Final Project Inspection and Test Run of the newly rehabilitated Daguioman Communal Irrigation System , Daguioman, Abra with a service area of 89 hectares. Completed Dalingoan Potable Water Supply System, Kapangan, Benguet. The project costing P 2,094,916.00 will benefit around 89 Agrarian Reform Beneficiary Households. B-11 Third Quarter CY 2012 RPMES Report
  • 24. For CY 2012, 12 projects (10 irrigation projects and 2 FMRs) are programmed for implementation with a total cost of Php 167.44 M. These are located in the provinces of Apayao, Benguet, Ifugao, Kalinga and Mountain Province. PROJECT PROGRESS REPORT As of September 2012 Project Duration: Start: April 2008 End: April 2014 For CY 2012 AO 1st Quarter AO 2nd Quarter AO 3rd Quarter AO 4th Quarter Target 29.16 % 48.87 % 45.26% Actual 23.88 % 36.87 % 69.62% Slippage (5.28%) (12.00 %) (24.36%) Cumulative Status: Status Physical Financial (Since start of project) Target 50.01% Actual 72.26% Slippage 22.25% Current 1. Undue project delay due to lack of equipment and manpower Implementation Issues 2. Absence of DPWH QAU representative during inspection. and/or Problems Encountered (if any): 3. Inclement weather Actions Taken/ 1. Conducted Strategy Planning and monthly Area Implementation Recommendations: Team (AIT) meetings participated by representatives from DAR Provincial / Municipal Office, DPWH, LGU and the Contractor to draw catch-up plan. Remarks: Agency Contact DIR. FRANKLIN E. COCOY Person: OIC-Regional Director, DAR-CAR #39 m. Roxas St., Brgy. Tabora, Baguio City ENGR. WILLIE GARCIA 445-4497 B-12 Third Quarter CY 2012 RPMES Report
  • 25. Kabugao (Apayao)-Solsona (Ilocos Norte) Road PROJECT PROFILE Implementing Agency: Department of Public Works and Highways – CAR Fund Source: GOP Total Project Cost: Php 100 M. Contract Cost: Php 89.089 M. Location/Area Coverage: Barangay Madatag, Kabugao, Apayao Description: The road is a major component of the Cordillera Roads Improvement Project (CRIP) as lateral road; it connects Ilocos Region and the Northern Cordilleras. It Kabugao-Apayao- traverses the municipalities of Kabugao Solsona-Ilocos and Calanasan in Apayao and turns west Norte Rd to Solsona in Ilocos Norte. The 76.48 km road stretch is a segment of the San Nicolas-Solsona-Kabugao-Conner- Abbut Lateral Road as Apayao’s direct access to Laoag International Airport. The road starts at PoblacionKabugao and ends in Solsona. At the Ilocos Norte side, concrete paving is being completed up to the regional boundary. Approximately 10 km. is for opening at the Kabugao side. Likewise, seven (7) major bridges are to be constructed with a total length of 445 lm. crossing several tributaries of the Apayao River. However, the whole stretch remains a gap (unpaved) even after the project. PROJECT LOCATION The road is among the Apayao national roads recently upgraded from secondary classification to arterial through DPWH Memorandum dated November 2, 2011 by Sec. Rogelio L. Singson. This memorandum was an immediate result of the RDC-CAR dialogue with Sec. Singson held at the DPWH-CAR office on August 5, 2011. The specific project output is road opening and gravelling of 9.56 kms. B-13 Third Quarter CY 2012 RPMES Report
  • 26. PROJECT PROGRESS REPORT As of September 2012 Project Duration: Start: June 27, 2012 End: July 21, 2013 For CY 2012 AO 1st Quarter AO 2nd Quarter AO 3rd Quarter AO 4th Quarter Target 0.50% 1.53% Actual 0.50% 0.7% Slippage -0.83% Cumulative Status: Status Physical Financial (Since start of project) Target 2.03% Actual 0.05% 8.88% Slippage -1.98% Current Project Suspension was issued on July 1, 2012 since the contractor Implementation cannot mobilize due to series of slides and road cut along the 21 km Issues and/or road leading to the project site. Problems Encountered (if any): Actions Taken/ To address this, the DPWH-CAR requested DPWH-CO to utilize Recommendations: savings for the removal of slides and restoration of road cuts costing Php 2.38 M. This was eventually approved and the contractor was advised to resume effective September 30, 2012. Remarks: Agency Contact DIR. EDILBERTO P. CARABBACAN Person: Regional Director, DPWH– CAR Engineer’s Hill 2600 Baguio City Tel. 444-8838 B-14 Third Quarter CY 2012 RPMES Report
  • 27. Kabugao Section B-15 Third Quarter CY 2012 RPMES Report
  • 28. LANDMARKS Kabugao (Apayao) Municipal Hall Solsona Welcome Arch Junction San Nicolas, Ilocos Norte B-16 Third Quarter CY 2012 RPMES Report
  • 29. Kabugao-Pudtol-Luna Cagayan Boundary Road PROJECT PROFILE Implementing Agency: Department of Public Works and Highways – CAR Fund Source: GOP Total Project Cost: Php58.827 M. Contract Cost : Php 49.574 M. Location/Area Coverage: Barangays Swan and Mataguisi, Pudtol, Apayao Description: The road is a major component of the Cordillera Roads Improvement Project (CRIP) as the northern tip of the regional backbone. The 95.7 km. road stretch Kabugao-Pudtol- directly links the capital town Kabugao to Luna Cagayan Lower Apayao, the seat of provincial Bdry Road government and business growth center in the Municipality of Luna. The road starts at junction Lenneng along the Kabugao-Conner-Abbut Road and going north-east traverses municipalities of Kabugao, Pudtol and Luna and ends at Junction Luna in Abulug, Cagayan along the Pan-Philippine Highway. The Pan- Philippine Highway connects Laoag, Ilocos Norte and Tuguegarao, Cagayan. The gap at the Kabugao side (19.359 km.), traverses a rugged mountainous terrain, then slowly goes down to the Paco Valley, which was then proposed as government center. The road will also traverse the Mataguisi Valley in Pudtol. PROJECT LOCATION The valleys have vast potential for agricultural production. The road is among the Apayao national roads recently upgraded from secondary classification to arterial through DPWH Memorandum dated November 2, 2011 by Sec. Rogelio L. Singson. This memorandum was an immediate result of the RDC-CAR dialogue with Sec. Singson held at the DPWH-CAR office on August 5, 2011. B-17 Third Quarter CY 2012 RPMES Report
  • 30. The bridges across Apayao River (Babulayan Bridge) and tributaries Maton and Nagan Rivers have been completed. However, two (2) more major bridges across Malilibag River (60 lm) and Paco River (36 lm) are yet to be constructed to finally complete the road link. On top of this, there are six (6) temporary bridges to be replaced with permanent bridge structures with a total length of 90 lm. The specific project output is road construction of 2.4 km. After the project, the road has still a gap (unpaved) of 16.959 km. PROJECT PROGRESS REPORT As of September 2012 Project Duration: Start: February 20, 2012 End: December 12, 2012 For CY 2012 AO 1st Quarter AO 2nd Quarter AO 3rd Quarter AO 4th Quarter Target 5% 50% 17.41% Actual 5% 35.7% 26.81% Slippage Cumulative Status: Status Physical Financial (Since start of project) Target 67.41% Actual 62.51% 69.49% Slippage (4.90%) Current Implementation The 4.9 % negative slippage is attributed to the work Issues and/or Problems interruption during the past months due to inclement weather Encountered (if any): caused by Typhoons Gener, Helen, and Igme. Actions Taken/ To address this, the DPWH advised the contractor to provide Recommendations: additional manpower and equipment to fast track implementation. Remarks: Agency Contact Person: DIR. EDILBERTO P. CARABBACAN Regional Director, DPWH– CAR Engineer’s Hill 2600 Baguio City Tel. 444-8838 B-18 Third Quarter CY 2012 RPMES Report
  • 31. Mataguisi Valley Babulayan Bridge across Apayao River Junction Lenneng (Kabugao) Paco Valley B-19 Third Quarter CY 2012 RPMES Report
  • 32. National Greening Program (NGP) PROJECT PROFILE Implementing Agency: DENR–CAR Fund Source: GOP Total Project Cost: P124,339,000.00 Location/Area Coverage: Region wide The locations are spread out all over the six provinces of CAR including Baguio City with a total area of 15,258 hectares to be planted through social mobilization. Description: An administration priority program (Executive Order No. 26) that seeks to attain asustainable Human development, economic and ecological security through the planting of 1.5 billion trees in around 1.5 million hectares of public land within six years from year 2011 to 2016. The NGP also aims to ensure food security, biodiversity conservation and address climate change. In the Cordillera, the target for CY 2012 is 7.5 million trees covering 15,000 hectares with a project cost of Php 103.663 M. The project components are: (a) seedling production, Php 62.382 M; plantation site preparation; Php 17.469 M; and maintenance and protection, Php 23,812 M. Seedling production (gmelina) of one of the Seedling production (mahogany) of one People’s Organization (PO) – Baroña Family of the POs in Conner, Apayao Association (BFA) in Poblacion, Lacub, Abra. B-21 Third Quarter CY 2012 RPMES Report
  • 33. Seedling production (mahogany) of one of Seedling production (Benguet pine) of one the POs – Federation of Responsive of the POs in Benguet Association for Magat Ecology Inc. in Ifugao Seedling production (mahogany, Seedling production (gmelina) of one of the narra&gmelina) of one of the POs in Natonin, POs in Tabuk, Kalinga Mountain Province Benguet Pine B-22 Third Quarter CY 2012 RPMES Report
  • 34. PROJECT PROGRESS REPORT As of September 2012 Project Duration: Start: January 2012 End: December 2012 For CY 2012 AO 1st Quarter AO 2nd Quarter AO 3rd Quarter AO 4th Quarter Target 11.16% 60.50% 21.41% 6.92% Actual 14.49% 34.49% 24.46% Slippage (3.33%) (26.01%) (3.05%) Cumulative Status: Status Physical Financial (Since start of project) Target 93.07% 95.71% Actual 73.44% 95.71% Slippage (19.62%) (0%) Current 1. For the second year, project was delayed due the difficulty of Implementation Issues following the prescribed procurement procedure. Seedlings and/or Problems should be produced by the beneficiaries themselves, unlike Encountered (if any): during the first year that these may be acquired from outside of the project area. 2. Critical areas for tree planting due to climatic condition are: Abra, Benguet and western Mountain Province. In these areas, tree planting should be done only during rainy season. Actions Taken/ 1. Procurement guideline was issued by DENR-CO to facilitate Recommendations: implementation. 2. Adopted catch-up plan Remarks: Agency Contact Person: DIR. CLARENCE L. BAGUILAT Regional Executive Director, DENR-CAR No. 80 Diego Silang St., 2600 Baguio City, (442-4531, RD/F) Mr. JOSEPH MAUTING PMD, DENR-CAR (443-94-06) B-23 Third Quarter CY 2012 RPMES Report
  • 35. Red and Black School Building Program PROJECT PROFILE Implementing Agency: Department of Education-CAR Fund Source: GOP Total Project Cost: (CY 2011) P166.944 M (CY 2012) P115.200M Location/Area Coverage: Region wide Description: The Regular School Building Program specifically targets schools which are categorized under the Red Zone or those which have a ratio of 56 or more students to one classroom: and the Black Zone, or schools which make use of makeshift classrooms and facilities. The standard DepEd design is 7m x 9m classroom for rural areas with a classroom-student ratio of 1:45. This standard also applies to all public secondary schools, regardless of location and class size. In CAR, the carry-over CY 2011projectshas a total project cost of Php166.944 M. covering 147 school sites for new 209 classrooms. The table below shows the details per province/city: No. of No. of Status Province/City sites(CY 2011) Project Cost Classrooms (AO Sept. 2012) Abra 18 16 18,427,000 90.43% Apayao 21 26 15,812,000 96.57% Benguet 18 28 25,793,000 100% Ifugao 13 21 28,493,000 98.69% Kalinga 41 65 44,636,000 95.12% Mt. Province 30 34 20,042,000 90.45% Baguio 6 10 13,740,000 100% CAR 147 209 166,943,500 95.94% B-24 Third Quarter CY 2012 RPMES Report
  • 36. Mankayan Central School – On going construction (May 28, 2012) Bulalacao National High School Bangao National High School B-25 Third Quarter CY 2012 RPMES Report
  • 37. For CY 2012 projects, construction started during the second quarter. There are 147 school sites to have 207 new classrooms with a total project cost of Php 115.2 M. The next table shows the details per province/city: No. of sites No. of Status Province/City Classrooms Project Cost (AO Sept. 2012) (CY 2012) Abra 18 26 7,920,000 89.49% Apayao 21 26 10,080,000 0% Benguet 18 28 15,840,000 90.57% Ifugao 13 21 10,800,000 27.24% Kalinga 41 65 29,520,000 18.53% Mt. Province 30 31 23,760,000 27.69% Baguio 6 10 17,280,000 16.91% CAR 147 207 115,200,000 34.16% PROJECT PROGRESS REPORT As of September 2012 Project Duration: Start: January End: December st nd rd For CY 2012 AO 1 Quarter AO 2 Quarter AO 3 Quarter AO 4th Quarter Target Actual (CY 2011) 8.44% 0.78% 6.72% (CY 2012) 7.69% 26.47% Slippage Cumulative Status: Status Physical Financial (Since start of project) Target Actual (CY 2011) 95.94% (CY 2012) 34.16% Current Implementation Issues and/or Problems Encountered (if any): Actions Taken/ Recommendations: Remarks: Implementation of CY 2012 projects comments during this quarter. Agency Contact Person: DIR. ELLEN B. DONATO Regional Director Wangal, La Trinidad, 2601 Benguet B-26 Third Quarter CY 2012 RPMES Report
  • 39. RPMC-CAR Inspection Report on the Road Upgrading (Gravel to Concrete) along Kabugao-Pudtol-Luna-Cagayan Boundary Road conducted on 09 October 2012 1. The RPMC Inspectorate Team The Regional Project Monitoring Committee (RPMC-CAR) Inspectorate Team conducted on 09 October 2012 a project-site inspection on the Kabugao- Pudtol-Luna- Cagayan Boundary Road. This is a regional priority sectoral project implemented by the DPWH-CAR regional office. The RPMC member-agency representatives were the following: Rene V. Valera, DILG-CAR Jerome B. Agaloos, NEDA-CAR James M. Degsi, DBM-CAR Manilyn S. Dulay, NEDA-CAR The Team was assisted by the following DPWH Apayao 2nd Engineering District and Contractor’s representative: ADE Rustom Martinez, DPWH Apayao II Galo Aplod, OCDC Jerry Ragojos, DPWH Apayao II Before the field inspection, the group paid courtesy to the Apayao Provincial Government officials at the Provincial Capitol in Luna, Apayao. The Team met with the Provincial Administrator Vincent Talattad and Chief Executive Atty. Xandred Claveria. 2. Project Profile The road is a major component of the Cordillera Roads Improvement Project (CRIP) as the northern tip of the regional backbone. It traverses the municipalities of Kabugao, Pudtol and Luna in Apayao and turns east to Abulog in Cagayan. The 95.7 km. road stretch directly links the capital town Kabugao to Lower Apayao, the seat of provincial government and business growth center. The road is among the Apayao national roads recently upgraded from secondary classification to arterial through DPWH Memorandum dated November 2, 2011 by Sec. Rogelio L. Singson. This memorandum was an immediate result of the RDC-CAR dialogue with Sec. Singson held at the DPWH-CAR office on August 5, 2011. The bridges across Apayao River (Babulayan Bridge) and tributaries Maton and Nagan Rivers have been completed. However, two (2) more major bridges across Malilibag River (60 lm) C-1
  • 40. and Paco River (36 lm) are yet to be constructed to finally complete the road link. On top of this, there are six (6) temporary bridges to be replaced with permanent bridge structures with a total length of 90 lm. 3. Project Basic Information Specific Location Barangays Swan & Mataguisi, Pudtol, Apayao Station Limits KO 661+000 – KO 661+321 & KO 643+520- KO646+080 Length of Road Project 2.4 km Project Cost Php 58.827 M. Contract Cost Php 49.574 M. Source of Fund CY 2012 DPWH Regular Infra Program Project Schedule Feb. 20, 2012 to Dec. 12, 2012 Contractor OCDC Major Work Items PCCP (2.4 km), RCPC, stone masonry, concrete curb & gutter and road signs Project Status 64.79 %, slippage (2.62 %) 4. Findings The road construction is smoothly on progress. The mere 2.62 % negative slippage is attributed to the work interruption during the past months due to inclement weather caused by Typhoons Gener, Helen, and Igme. To address this, the DPWH advised the contractor to provide additional manpower and equipment to fast track implementation. 5. Comment(s)/ Recommendation(s) The work progress is commendable. It is however recommended that the DPWH should also prioritize the programming for the construction of the bridges across Paco River (District I) and Malilibag River (District 2) to finally open the road up to Kabugao. C-2
  • 41. PHOTO DOCUMENTATION On-going concreting of Kabugao-Pudtol-Luna-Cagayan Boundary Road (2.4 km along Barangays Swan & Mataguisi section) Completed Babulayan Bridge Concrete approach of Babulayan Recently completed road across Bridge concreting project Apayao River EXIT CONFERENCE The RPMC Inspectorate Team Courtesy call on Apayao Provincial Administrator Vincent Talattad meets ADE Rustom Martinez, and Chief of Staff Atty. Xandred Claveria DPWH Apayao II (L) C-3
  • 42. RPMC-CAR Inspection Report on the Road Opening of Kabugao, Apayao- Solsona-Ilocos Norte Road (Apayao Side) conducted on 10 October 2012 1. The RPMC Inspectorate Team The Regional Project Monitoring Committee (RPMC-CAR) Inspectorate Team conducted on 10 October 2012 a project-site inspection on the Kabugao, Apayao- Solsona-Ilocos Norte Road. This is a regional priority sectoral project implemented by the DPWH-CAR regional office. The RPMC member-agency representatives were the following: Rene V. Valera, DILG-CAR Jerome B. Agaloos, NEDA-CAR James M. Degsi, DBM-CAR Manilyn S. Dulay, NEDA-CAR The Team was assisted by the following DPWH Apayao 1st Engineering District and LGU Kabugao staff: Antonio Baguec (PE), DPWH Apayao I Arne Paul Ligwang, LGU Kabugao Domingo Enciso, DPWH Apayao I Harold Aboran, LGU Kabugao The group paid courtesy and held separate exit conferences with DPWH Apayao 1st District ADE Edward P. Magno and LGU Kabugao Municipal Administrator Romeo B. Tamot. 2. Project Profile The road is a major component of the Cordillera Roads Improvement Project (CRIP) as a lateral road. It directly connects Apayao Province to Ilocos Region. It traverses the municipalities of Kabugao and Calanasan in Apayao and turns west to Solsona in Ilocos Norte. The 76.48 km road stretch is a segment of the San Nicolas-Solsona-Kabugao- Conner-Abbut Lateral Road as Apayao’s direct access to Laoag International Airport. At the Ilocos Norte side, concrete paving is being completed up to the regional boundary. The road is among the Apayao national roads recently upgraded from secondary classification to arterial through DPWH Memorandum dated November 2, 2011 by Sec. Rogelio L. Singson. This memorandum was an immediate result of the RDC dialogue with Sec. Singson held at the DPWH-CAR office on August 5, 2011. It was noted that even after the project, the whole stretch remains a gap until concreted. Likewise, seven (7) major bridges are to be constructed with a total length of 445 lm. crossing several tributaries of the Apayao River. C-4
  • 43. 3. Project Basic Information Specific Location Barangays Madatag, Kabugao, Apayao Station Limits KO 627+840 – KO 637+400 Length of Road Project 9.56 km Project Cost Php 100 M. Contract Cost Php 89.089 M. Source of Fund CY 2012 DPWH Infra Program Original Project Schedule June 27, 2012 to April 22, 2013 Suspension Order No.1 July 1, 2012 Resume Order No 1 September 30, 2012 Expected Completion July 21, 2013 Contractor PBO Construction Major Work Items Roadway & drainage excavation, gravelling, stone masonry & installation of cross drainages, catch basins, common earth & solid rock excavation Project Status 0.50 % 4. Findings Project Suspension was issued on July 1, 2012 since the contractor cannot mobilize due to series of slides and road cut along the 21 km section leading to the project site. To address this, the DPWH-CAR requested DPWH-CO to utilize savings for the removal of slides and restoration of road cuts costing Php 2.38 M. This was eventually approved and the contractor was advised to resume effective September 30, 2012. Due to the slides and road cuts, the group had to cruise Apayao River for two (2) hours using a motor-banca and hike for an hour to reach the project site. It was found out that the road alignment follows an old logging road of which some portions were later widened by the AFP Engineering Brigade. Accordingly, the AFP had a military camp at Barangay Madatag. The area has a vast potential for agriculture, water recreation and Philippine eagle watching. The forest area along the river and within the Apayao-Ilocos Norte boundary is a perfect eagle’s habitat. 5. Comment(s)/ Recommendation(s) The leadership of Apayao Province and MLGU Kabugao in cooperation with the DPWH Apayao I are commended for the swift conduct of a parcellary survey on August 2011 along the road line to delineate private properties from road right-of-way (RROW). This was among the conditions set by Secretary Singson prior to the issuance of the memorandum and funding release. For FY 2013-2016, the DPWH should program the construction of the seven (7) major bridges with a total length of 445 lm. crossing several tributaries of the Apayao River. Meanwhile, the contractor should immediately resume construction work. C-5
  • 44. PROJECT PHOTO-DOCUMENTATION Actual Project Site at Barangay Madatag Location: KO627+840-KO637+400 On July 1, 2012 the suspension order was issued since the contractor cannot mobilize due to series of massive slides and road cuts along the 21 km section leading to the project site. C-6
  • 45. The DPWH-CO recently approved to utilized savings for the removal of slides and restoration of road cuts costing Php 2.38 M. Consequently, the contractor was advised to resume effective Sept. 30, 2012 Location: KO627+840-KO637+400 The area has a vast potential for agriculture, water recreation and Philippine eagle watching C-7
  • 46. Junction Kabugao, Apayao Kabugao section Junction San Nicolas, Ilocos Norte Solsona Welcome Arch C-8
  • 47. Ongoing concreting work, near regional boundary COURTESY CALL and EXIT CONFERENCE Exit conference with Kabugao Municipal Administrator Romeo Tamot (2nd R) With Engr. Domingo Enciso (R) and Exit conference with DPWH Apayao I Kabugao Local Officials ADE Edward P. Magno (R) and Engr. Domigo Enciso (L) and PE Antonio Banguec (2nd L) C-9