SlideShare una empresa de Scribd logo
1 de 36
COMPONENTS OF CONCRETE
PAVEMENT
A. Concrete slabs with a determinedthickness
Concrete is a construction material that is made of portland
cement ,aggregate s and water mixed in predetermined
proportions. Concrete solidifies and hardens after mixing
and placement due to a chemical process known asb
hydration.
B. Joints (both transverse and longitudinal)
Concrete slabs will crack randomly from natural
actions such as shrinkage or curling.
Therefore, joints are vital elements introduced into
CP to control cracking and horizontal
movements of the slabs.
Transverse Joints Perpendicular to Lane
Lines and Longitudinal Joints
Longitudinal Joint at Lane Line
Tie bars are typically used at longitudinal joints and
transverse construction joint in a nondoweled
shoulder addition/reconstruction to hold tight the
faces of abutting concrete in contact.
C. Tie bars
Load transfer is the ability of a joint to transfer a portion of
an applied load (the truck wheel)
from one side of the joint to the other.
Dowel Bars in a Transverse Joint
Slab Movements in Non-doweled SlabSlab Movements in Doweled Slab
E. Base layer
~It can provide a stable platform for the
concrete paving, provides for additional load
distribution, and contributes to drainage (if
permeable base is used) and frost resistance.
F.Subbase layer (if required),
~the subbase layer is a planned thickness of
specified material that is placed on the subgrade
or under the basement material.
G.Subgrade
~greater subgrade structural capacity can
result in more economical pavement structures.
The general pavement
Construction
practices involve:
• subgrade, base and subbase preparation
conforming to the thickness and cross section
requirements,
• proper placement of tie bars and dowel bars to
be embedded, carefully examining for bending
which could injure the material, oil, dirt, rust and
other coatings that would prevent or reduce
bonding to concrete.
• proper concrete placement including
consolidation, finishing, texturing, curing and
jointing essential for a strong durable pavement
Sub-grade, Sub-base and Base Preparation
Sub-grade Preparation
~ minimum depth of 0.5 feet below the grading plane
for the width between the outer edges of shoulders, or
~ minimum depth of 2.5 feet below the finished grade for
the width of the traveled way and auxiliary lanes
including 3 feet on both sides as specified in Section
19-5.03 of the Standard Specifications
Sub-base Layer Preparation
•The Department uses Aggregate Sub-base (AS)
for use in JPCP construction to provide a foundation
or working platform for the base when the sub-grade R-
value is less than 40.
•The maximum thickness of any one layer should not
exceed 0.50 foot after watering and compaction.
Where the required thickness is more than 0.50 foot,
spreading, watering and compaction should be
conducted in 2 or more lifts of approximately equal
thickness.
Base Layer Preparation
The Department uses Hot Mix Asphalt (HMA) Type A,
Lean Concrete Base (LCB), Asphalt Treated Permeable Base
(ATPB), and Aggregate Base (AB) to provide a construction
platform underneath the CP.
•Hot Mix Asphalt Type A (HMA-A)
HMA-Type A consists of one or more layers
placed on a prepared sub-base or sub-grade in conformity
with the alignment and grades shown on the project plans.
HMA-A is placed at a 20 temperature of no less than 310
°F and only when the sub-base or sub-grade surface is dry
and in satisfactory condition.
•Lean Concrete Base (LCB) ~ LCB is placed,
constructed and finished in no less than 12-foot widths
separated by contact joints. Widths that are greater than
26 feet are constructed with longitudinal weakened plane
joints at no more than 3 feet from the centerline of the
width being constructed.
•Aggregate Base (AB) ~ where the required thickness
is 0.50-foot or less, is spread and compacted in one layer.
If the required thickness is more than 0.50-foot, spread
and compact AB in two or more lifts in approximately
equal thickness, and each lift shall not exceed 0.50-foot.
Steel Placement
Tie Bar Placement
Tie bars are not to be used at a
joint where concrete and asphalt
concrete pavements abut. Tie bars
are placed:
(a) along longitudinal weakened
plane in multilane paving, and
(b) at longitudinal and transverse
contact joint in a nondoweled
lane/shoulder addition or
reconstruction. These tie bars are
placed at mid depth of the
concrete slab.
• Dowel Bar Placement
Dowel bars are placed as shown on the plans
by using either dowel bar baskets, drilling and
bonding, or mechanical insertion.
• Bar Reinforcement Placement
Although CP does not typically have bar
reinforcement, bar reinforcement can be
found in a few situations such as pavement
transitions ,gore areas, and around drainage
inlets.
• Concrete Placement ~ Concrete is transported to
the paving site by dump trucks or ready-mix trucks
with the goal to deliver a uniform, well-mixed and
workable concrete from batch to batch.
• Consolidation ~ it is the process that compacts
fresh concrete to mold it within the forms and
around steel reinforcements and to remove
undesirable voids.
• Finishing ~it involves any equipment or procedures
used to impart desirable surface characteristics.
• Curing ~ it is the maintenance of satisfactory
moisture and temperature in the concrete as it sets
and hardens such that the desired properties can
develop.
Flexible pavement design
This section describes the design for both asphalt
concrete pavements and surface treatments which
carry significant levels of traffic over the
performance period
Modifications Included in Flexible Pavement
design procedures
• The soil support number is replaced by the resilient modulus
to provide a rational testing procedure that may be used by an
agency to define the material properties.
• The layer coefficients for the various materials are defined in
terms of resilient modulus as well as standard methods (CBR
and R-value).
• The environmental factors of moisture and temperature
objectively included in the Guide so that the environmental
consdiderations could be ratioanally accounted for in the
design procedure.
• Reliability is introduced to permit the designer to use the
concept of risk analysis for various classes of roadways.
• Stage construction design procedures are incorporated.
Design Of Flexible Pavement
• Design Of Flexible Pavement By Group Index Method
Group Index is function of percentage material passing 200 mesh sieve
(0.074mm), liquid limit and plasticity index of soil and is given by
equation:
GI=0.2a+0.005ac+0.01bd
Here,
a=that portion of material passing 0.074mm sieve, greater than 35 And not
exceeding 75 %
b=that portion of material passing 0.074mm sieve, greater than 15 And not
exceeding 35%
c = that value of liquid limit in excess of 40 and less than 60
d = that value of plasticity index exceeding 10 and not more than 30
California Resistance Value Method
pavements thickness varies directly with R value and
logarithm of load repetitions. It varies inversely with fifth
root of Computer value.
T=K (TI) (90-R)/C1/5
Here :
T=total thickness of pavement, cm
K=numerical constant=0.166
TI=traffic index
R=stabilometer resistance value
C =Cohesiometer value
Triaxial Method
Here
T=Pavement thickness, cm
Es=modulus of elasticity of sub grade from triaxial test
result, Kg/cm2
A=radius of contact area, cm
∆=design deflection (0.25 cm)
Other.....
Rigid pavement design
As the name implies, rigid pavements are rigid , they do not
extend much under loading like flexible pavements. They are
constructed using cement concrete. In this case, the load carrying
capacity is mainly due to the rigidity and high modulus of elasticity
of the slab (slab action).
Modifications Included in Rigid
Pavement design procedures:
• Reliability concepts identical to those used
for the flexible pavements are introduced.
• The environmental aspects of design are
introduced in the same format as for flexible
pavements.
• The design procedure is modified to include
such factors as tied shoulders, subbase
erosion, and lean subbase designs.
Rigid Pavement Response
• Curling stress
– Differences in temperature between the top and
bottom surfaces of a PCC slab will cause the
slab to curl. Since slab weight and contact with
the base restrict its movement, stresses are
created.
where:
σt=slab interior warping stress
E=modulus of elasticity of PCC
e=thermal coefficient of PCC (» 0.000005/°F)
Δ T=temperature differential between the top and bottom of the
slab
µ=Poisson’s ratio for PCC (» 0.15)
β=radius of wheel load distribution for corner loading
where:
l=radius of relative stiffness
E=modulus of elasticity of PCC
h=slab thickness
k=modulus of subgrade reaction
m=Poisson’s ratio for PCC (» 0.15)
Load stress
Loads on a PCC slab will create both compressive and
tensile stresses within the slab and any adjacent one (as
long as load transfer efficiency is > 0).
a. Interior loading. Occurs when a load is applied on the
interior of a slab s.urface which is “remote” from all edges.
b. Edge loading. Occurs when a load is applied on a slab
edge “remote” from a slab corner.
c. Corner loading. Occurs when the center of a load is
located on the bisector of the corner angle.
Shrinkage and expansion
• In addition to curling, environmental temperatures will
cause PCC slabs to expand (when hot) and contract
(when cool), which causes joint movement.
where:
z=joint opening = change in slab length (inches)
C=base/slab frictional restraint factor
= 0.65 for stabilized bases
= 0.80 for granular bases
L=slab length (inches)
It is observed that flexible pavements are more economical for
lesser volume of traffic.The life of flexible pavement is near about 15
years whose initial cost is low needs a periodic maintenance after a
certain period and maintenance costs very high.
The life of rigid pavement is much more than the
flexible pavement of about 40 years approx 2.5 times life of
flexible pavement whose initial cost is much more then the
flexible pavement but maintenance cost is very less.
References:
http://www.pavementinteractive.org/article/rigid
-pavement-response/#sthash.ISwV8mbT.dpuf
pavement-procedures-construction-and-re-
construction.pdf
“Start by doing what’s necessary;
then do what’s possible;
and suddenly your are doing the
impossible.”
~Francis of Assisi~
Prepared by:
FONTE, EDDIE RED
ZULUETA, ERWIN JOHN

Más contenido relacionado

La actualidad más candente

Pavement materials and testing
Pavement materials and testingPavement materials and testing
Pavement materials and testingArchana Shagoti
 
Bitumen and modified bitumen
Bitumen and modified bitumenBitumen and modified bitumen
Bitumen and modified bitumenpradip dangar
 
Marshall Mix Design
Marshall Mix Design Marshall Mix Design
Marshall Mix Design Akhil Ahuja
 
HIGHWAY CONSTRUCTION MATERIAL & PRACTICE
HIGHWAY  CONSTRUCTION  MATERIAL  &  PRACTICEHIGHWAY  CONSTRUCTION  MATERIAL  &  PRACTICE
HIGHWAY CONSTRUCTION MATERIAL & PRACTICEFresher Thinking
 
Determining equivalent single wheel load.(ESWL)
Determining equivalent single wheel load.(ESWL) Determining equivalent single wheel load.(ESWL)
Determining equivalent single wheel load.(ESWL) Imran Nawaz
 
ppt on pavement design
ppt on pavement designppt on pavement design
ppt on pavement designRohit Ranjan
 
Construction of flexible pavements
Construction of flexible pavementsConstruction of flexible pavements
Construction of flexible pavementspradip dangar
 
Design of flexible pavement
Design of flexible pavementDesign of flexible pavement
Design of flexible pavementBhavik A Shah
 
Chapter 1 traffic characterstics
Chapter 1 traffic charactersticsChapter 1 traffic characterstics
Chapter 1 traffic charactersticsAnkit Patel
 
Pavement materials in Road Construction
Pavement materials in Road ConstructionPavement materials in Road Construction
Pavement materials in Road Constructionsrinivas2036
 
PAVEMENT DESIGN & TYPES
PAVEMENT DESIGN & TYPES PAVEMENT DESIGN & TYPES
PAVEMENT DESIGN & TYPES Mahendra meena
 
Highway Construction Materials and Practice
Highway Construction Materials and PracticeHighway Construction Materials and Practice
Highway Construction Materials and PracticeSenthamizhan M
 
Rigid pavement
Rigid pavementRigid pavement
Rigid pavementpjainrahul
 
rigid and flexiable pavement design ppt
rigid and flexiable pavement design pptrigid and flexiable pavement design ppt
rigid and flexiable pavement design pptrakeshchoudhary129
 

La actualidad más candente (20)

Pavement materials and testing
Pavement materials and testingPavement materials and testing
Pavement materials and testing
 
Bitumen and modified bitumen
Bitumen and modified bitumenBitumen and modified bitumen
Bitumen and modified bitumen
 
Marshall Mix Design
Marshall Mix Design Marshall Mix Design
Marshall Mix Design
 
HIGHWAY CONSTRUCTION MATERIAL & PRACTICE
HIGHWAY  CONSTRUCTION  MATERIAL  &  PRACTICEHIGHWAY  CONSTRUCTION  MATERIAL  &  PRACTICE
HIGHWAY CONSTRUCTION MATERIAL & PRACTICE
 
Determining equivalent single wheel load.(ESWL)
Determining equivalent single wheel load.(ESWL) Determining equivalent single wheel load.(ESWL)
Determining equivalent single wheel load.(ESWL)
 
Rigid pavements
Rigid pavements Rigid pavements
Rigid pavements
 
ppt on pavement design
ppt on pavement designppt on pavement design
ppt on pavement design
 
Construction of flexible pavements
Construction of flexible pavementsConstruction of flexible pavements
Construction of flexible pavements
 
Design of flexible pavement
Design of flexible pavementDesign of flexible pavement
Design of flexible pavement
 
Chapter 1 traffic characterstics
Chapter 1 traffic charactersticsChapter 1 traffic characterstics
Chapter 1 traffic characterstics
 
Pavement design
Pavement designPavement design
Pavement design
 
Cbr test
Cbr testCbr test
Cbr test
 
Pavement materials in Road Construction
Pavement materials in Road ConstructionPavement materials in Road Construction
Pavement materials in Road Construction
 
Unit 5
Unit 5Unit 5
Unit 5
 
PAVEMENT DESIGN & TYPES
PAVEMENT DESIGN & TYPES PAVEMENT DESIGN & TYPES
PAVEMENT DESIGN & TYPES
 
Highway Construction Materials and Practice
Highway Construction Materials and PracticeHighway Construction Materials and Practice
Highway Construction Materials and Practice
 
Rigid pavement
Rigid pavementRigid pavement
Rigid pavement
 
rigid and flexiable pavement design ppt
rigid and flexiable pavement design pptrigid and flexiable pavement design ppt
rigid and flexiable pavement design ppt
 
Road Aggregates
Road AggregatesRoad Aggregates
Road Aggregates
 
Highway Materials Unit-III
Highway Materials  Unit-IIIHighway Materials  Unit-III
Highway Materials Unit-III
 

Destacado

Lect 6 pavement design
Lect 6 pavement designLect 6 pavement design
Lect 6 pavement designM Firdaus
 
Modern Trends In Pavement Design
Modern Trends In Pavement DesignModern Trends In Pavement Design
Modern Trends In Pavement DesignLatif Hyder Wadho
 
Design Of Flexible Pavements
Design Of Flexible PavementsDesign Of Flexible Pavements
Design Of Flexible Pavementswhutton1
 
Introduction to Pavement Design Concepts
Introduction to Pavement Design ConceptsIntroduction to Pavement Design Concepts
Introduction to Pavement Design ConceptsLatif Hyder Wadho
 
Highway engineering at high altitudes
Highway engineering at high altitudesHighway engineering at high altitudes
Highway engineering at high altitudesPrashant Shekhar
 
Lec 09 Pavement Design (Transportation Engineering)
Lec 09 Pavement Design (Transportation Engineering) Lec 09 Pavement Design (Transportation Engineering)
Lec 09 Pavement Design (Transportation Engineering) Hossam Shafiq I
 
Rigid pavement
Rigid pavementRigid pavement
Rigid pavementpjainrahul
 
Design and construction of highway (flexible pavement
Design and construction of highway (flexible pavementDesign and construction of highway (flexible pavement
Design and construction of highway (flexible pavementsuraj vishwakarma
 
Construction of flexible pavement in brief.
Construction of flexible pavement in brief.Construction of flexible pavement in brief.
Construction of flexible pavement in brief.AJINKYA THAKRE
 
Pavement thickness design
Pavement thickness designPavement thickness design
Pavement thickness designSohail Khan
 
Construction of flexible pavement
Construction of flexible pavementConstruction of flexible pavement
Construction of flexible pavementUTU Dehradun
 
CONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROADCONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROADGLA University
 
Soil mechanics in_pavement_engineering
Soil mechanics in_pavement_engineeringSoil mechanics in_pavement_engineering
Soil mechanics in_pavement_engineeringAlexander Gómez
 
Ví dụ tke dg btxm theo qd 3230 qd-bgtvt
Ví dụ tke dg btxm theo qd 3230 qd-bgtvtVí dụ tke dg btxm theo qd 3230 qd-bgtvt
Ví dụ tke dg btxm theo qd 3230 qd-bgtvtĐiềm Nhan
 
S60 mb proper_20_pccp_20design_20details_20for_20performance_20__20road_20sch...
S60 mb proper_20_pccp_20design_20details_20for_20performance_20__20road_20sch...S60 mb proper_20_pccp_20design_20details_20for_20performance_20__20road_20sch...
S60 mb proper_20_pccp_20design_20details_20for_20performance_20__20road_20sch...R C Patil Patil
 
Proper Concrete Design Methodology
Proper Concrete Design MethodologyProper Concrete Design Methodology
Proper Concrete Design Methodologycrazedbuckeye
 

Destacado (20)

Lect 6 pavement design
Lect 6 pavement designLect 6 pavement design
Lect 6 pavement design
 
Modern Trends In Pavement Design
Modern Trends In Pavement DesignModern Trends In Pavement Design
Modern Trends In Pavement Design
 
Design Of Flexible Pavements
Design Of Flexible PavementsDesign Of Flexible Pavements
Design Of Flexible Pavements
 
Pavement design
Pavement designPavement design
Pavement design
 
Introduction to Pavement Design Concepts
Introduction to Pavement Design ConceptsIntroduction to Pavement Design Concepts
Introduction to Pavement Design Concepts
 
Highway engineering at high altitudes
Highway engineering at high altitudesHighway engineering at high altitudes
Highway engineering at high altitudes
 
Lec 09 Pavement Design (Transportation Engineering)
Lec 09 Pavement Design (Transportation Engineering) Lec 09 Pavement Design (Transportation Engineering)
Lec 09 Pavement Design (Transportation Engineering)
 
Rigid pavement
Rigid pavementRigid pavement
Rigid pavement
 
Design and construction of highway (flexible pavement
Design and construction of highway (flexible pavementDesign and construction of highway (flexible pavement
Design and construction of highway (flexible pavement
 
28 pavement design
28 pavement design28 pavement design
28 pavement design
 
Pavement ppt
Pavement pptPavement ppt
Pavement ppt
 
Construction of flexible pavement in brief.
Construction of flexible pavement in brief.Construction of flexible pavement in brief.
Construction of flexible pavement in brief.
 
Pavement thickness design
Pavement thickness designPavement thickness design
Pavement thickness design
 
Construction of flexible pavement
Construction of flexible pavementConstruction of flexible pavement
Construction of flexible pavement
 
CONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROADCONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROAD
 
Soil mechanics in_pavement_engineering
Soil mechanics in_pavement_engineeringSoil mechanics in_pavement_engineering
Soil mechanics in_pavement_engineering
 
Ví dụ tke dg btxm theo qd 3230 qd-bgtvt
Ví dụ tke dg btxm theo qd 3230 qd-bgtvtVí dụ tke dg btxm theo qd 3230 qd-bgtvt
Ví dụ tke dg btxm theo qd 3230 qd-bgtvt
 
Concrete pavement design
Concrete pavement designConcrete pavement design
Concrete pavement design
 
S60 mb proper_20_pccp_20design_20details_20for_20performance_20__20road_20sch...
S60 mb proper_20_pccp_20design_20details_20for_20performance_20__20road_20sch...S60 mb proper_20_pccp_20design_20details_20for_20performance_20__20road_20sch...
S60 mb proper_20_pccp_20design_20details_20for_20performance_20__20road_20sch...
 
Proper Concrete Design Methodology
Proper Concrete Design MethodologyProper Concrete Design Methodology
Proper Concrete Design Methodology
 

Similar a PAVEMENT DESIGN (Group 9)

Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptxAsif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptxsfQyoom
 
CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
CONSTRUCTION_OF_RIGID_PAVEMENT.pptxCONSTRUCTION_OF_RIGID_PAVEMENT.pptx
CONSTRUCTION_OF_RIGID_PAVEMENT.pptxJaySinghchib1
 
Construction of rigid pavement
Construction of rigid pavementConstruction of rigid pavement
Construction of rigid pavementpradip dangar
 
highway materials and desihn.pptx
highway materials and desihn.pptxhighway materials and desihn.pptx
highway materials and desihn.pptxSekharJ4
 
Types of pavement- Transportation Engg. I
Types of pavement- Transportation Engg. ITypes of pavement- Transportation Engg. I
Types of pavement- Transportation Engg. IGauri kadam
 
Types of Pavements.pptx
Types of Pavements.pptxTypes of Pavements.pptx
Types of Pavements.pptxssuser33b5501
 
Conen 442 module3 S2021 Pavement Design and Construction
Conen  442 module3  S2021 Pavement Design and Construction Conen  442 module3  S2021 Pavement Design and Construction
Conen 442 module3 S2021 Pavement Design and Construction Wael ElDessouki
 
Minor Project on design and analysis of flexible pavement with cement treated...
Minor Project on design and analysis of flexible pavement with cement treated...Minor Project on design and analysis of flexible pavement with cement treated...
Minor Project on design and analysis of flexible pavement with cement treated...PrashannaKumar2
 
Design of concrete Structure 2
Design of concrete Structure 2Design of concrete Structure 2
Design of concrete Structure 2SHARIQUE AHMAD
 
Rigid Pavements Design Part - I
Rigid Pavements Design Part - IRigid Pavements Design Part - I
Rigid Pavements Design Part - ISachin Kulkarni
 
Pavement construction methods
Pavement construction methodsPavement construction methods
Pavement construction methodsshrikanth16
 

Similar a PAVEMENT DESIGN (Group 9) (20)

Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptxAsif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
 
CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
CONSTRUCTION_OF_RIGID_PAVEMENT.pptxCONSTRUCTION_OF_RIGID_PAVEMENT.pptx
CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
 
Construction of rigid pavement
Construction of rigid pavement Construction of rigid pavement
Construction of rigid pavement
 
Construction of rigid pavement
Construction of rigid pavementConstruction of rigid pavement
Construction of rigid pavement
 
Ppt rcc road design
Ppt rcc road designPpt rcc road design
Ppt rcc road design
 
highway materials and desihn.pptx
highway materials and desihn.pptxhighway materials and desihn.pptx
highway materials and desihn.pptx
 
Pavements and paths
Pavements and pathsPavements and paths
Pavements and paths
 
Types of pavement- Transportation Engg. I
Types of pavement- Transportation Engg. ITypes of pavement- Transportation Engg. I
Types of pavement- Transportation Engg. I
 
Pavement
PavementPavement
Pavement
 
Types of Pavements.pptx
Types of Pavements.pptxTypes of Pavements.pptx
Types of Pavements.pptx
 
Pavement
PavementPavement
Pavement
 
Highway Pavement
Highway PavementHighway Pavement
Highway Pavement
 
Formwork
FormworkFormwork
Formwork
 
Conen 442 module3 S2021 Pavement Design and Construction
Conen  442 module3  S2021 Pavement Design and Construction Conen  442 module3  S2021 Pavement Design and Construction
Conen 442 module3 S2021 Pavement Design and Construction
 
Minor Project on design and analysis of flexible pavement with cement treated...
Minor Project on design and analysis of flexible pavement with cement treated...Minor Project on design and analysis of flexible pavement with cement treated...
Minor Project on design and analysis of flexible pavement with cement treated...
 
Design of concrete Structure 2
Design of concrete Structure 2Design of concrete Structure 2
Design of concrete Structure 2
 
Rigid Pavements Design Part - I
Rigid Pavements Design Part - IRigid Pavements Design Part - I
Rigid Pavements Design Part - I
 
CONCRETE GROUND FLOORS.ppt
CONCRETE GROUND FLOORS.pptCONCRETE GROUND FLOORS.ppt
CONCRETE GROUND FLOORS.ppt
 
Pavement construction methods
Pavement construction methodsPavement construction methods
Pavement construction methods
 
Flat_slab.pptx
Flat_slab.pptxFlat_slab.pptx
Flat_slab.pptx
 

Último

Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesPrabhanshu Chaturvedi
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 

Último (20)

Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and Properties
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 

PAVEMENT DESIGN (Group 9)

  • 1.
  • 3. A. Concrete slabs with a determinedthickness Concrete is a construction material that is made of portland cement ,aggregate s and water mixed in predetermined proportions. Concrete solidifies and hardens after mixing and placement due to a chemical process known asb hydration.
  • 4. B. Joints (both transverse and longitudinal) Concrete slabs will crack randomly from natural actions such as shrinkage or curling. Therefore, joints are vital elements introduced into CP to control cracking and horizontal movements of the slabs. Transverse Joints Perpendicular to Lane Lines and Longitudinal Joints Longitudinal Joint at Lane Line
  • 5. Tie bars are typically used at longitudinal joints and transverse construction joint in a nondoweled shoulder addition/reconstruction to hold tight the faces of abutting concrete in contact. C. Tie bars
  • 6. Load transfer is the ability of a joint to transfer a portion of an applied load (the truck wheel) from one side of the joint to the other. Dowel Bars in a Transverse Joint Slab Movements in Non-doweled SlabSlab Movements in Doweled Slab
  • 7. E. Base layer ~It can provide a stable platform for the concrete paving, provides for additional load distribution, and contributes to drainage (if permeable base is used) and frost resistance. F.Subbase layer (if required), ~the subbase layer is a planned thickness of specified material that is placed on the subgrade or under the basement material. G.Subgrade ~greater subgrade structural capacity can result in more economical pavement structures.
  • 8.
  • 10. • subgrade, base and subbase preparation conforming to the thickness and cross section requirements, • proper placement of tie bars and dowel bars to be embedded, carefully examining for bending which could injure the material, oil, dirt, rust and other coatings that would prevent or reduce bonding to concrete. • proper concrete placement including consolidation, finishing, texturing, curing and jointing essential for a strong durable pavement
  • 11. Sub-grade, Sub-base and Base Preparation Sub-grade Preparation ~ minimum depth of 0.5 feet below the grading plane for the width between the outer edges of shoulders, or ~ minimum depth of 2.5 feet below the finished grade for the width of the traveled way and auxiliary lanes including 3 feet on both sides as specified in Section 19-5.03 of the Standard Specifications
  • 12. Sub-base Layer Preparation •The Department uses Aggregate Sub-base (AS) for use in JPCP construction to provide a foundation or working platform for the base when the sub-grade R- value is less than 40. •The maximum thickness of any one layer should not exceed 0.50 foot after watering and compaction. Where the required thickness is more than 0.50 foot, spreading, watering and compaction should be conducted in 2 or more lifts of approximately equal thickness.
  • 13. Base Layer Preparation The Department uses Hot Mix Asphalt (HMA) Type A, Lean Concrete Base (LCB), Asphalt Treated Permeable Base (ATPB), and Aggregate Base (AB) to provide a construction platform underneath the CP. •Hot Mix Asphalt Type A (HMA-A) HMA-Type A consists of one or more layers placed on a prepared sub-base or sub-grade in conformity with the alignment and grades shown on the project plans. HMA-A is placed at a 20 temperature of no less than 310 °F and only when the sub-base or sub-grade surface is dry and in satisfactory condition.
  • 14. •Lean Concrete Base (LCB) ~ LCB is placed, constructed and finished in no less than 12-foot widths separated by contact joints. Widths that are greater than 26 feet are constructed with longitudinal weakened plane joints at no more than 3 feet from the centerline of the width being constructed. •Aggregate Base (AB) ~ where the required thickness is 0.50-foot or less, is spread and compacted in one layer. If the required thickness is more than 0.50-foot, spread and compact AB in two or more lifts in approximately equal thickness, and each lift shall not exceed 0.50-foot.
  • 15. Steel Placement Tie Bar Placement Tie bars are not to be used at a joint where concrete and asphalt concrete pavements abut. Tie bars are placed: (a) along longitudinal weakened plane in multilane paving, and (b) at longitudinal and transverse contact joint in a nondoweled lane/shoulder addition or reconstruction. These tie bars are placed at mid depth of the concrete slab.
  • 16. • Dowel Bar Placement Dowel bars are placed as shown on the plans by using either dowel bar baskets, drilling and bonding, or mechanical insertion. • Bar Reinforcement Placement Although CP does not typically have bar reinforcement, bar reinforcement can be found in a few situations such as pavement transitions ,gore areas, and around drainage inlets.
  • 17. • Concrete Placement ~ Concrete is transported to the paving site by dump trucks or ready-mix trucks with the goal to deliver a uniform, well-mixed and workable concrete from batch to batch. • Consolidation ~ it is the process that compacts fresh concrete to mold it within the forms and around steel reinforcements and to remove undesirable voids. • Finishing ~it involves any equipment or procedures used to impart desirable surface characteristics. • Curing ~ it is the maintenance of satisfactory moisture and temperature in the concrete as it sets and hardens such that the desired properties can develop.
  • 18.
  • 19. Flexible pavement design This section describes the design for both asphalt concrete pavements and surface treatments which carry significant levels of traffic over the performance period
  • 20. Modifications Included in Flexible Pavement design procedures • The soil support number is replaced by the resilient modulus to provide a rational testing procedure that may be used by an agency to define the material properties. • The layer coefficients for the various materials are defined in terms of resilient modulus as well as standard methods (CBR and R-value). • The environmental factors of moisture and temperature objectively included in the Guide so that the environmental consdiderations could be ratioanally accounted for in the design procedure. • Reliability is introduced to permit the designer to use the concept of risk analysis for various classes of roadways. • Stage construction design procedures are incorporated.
  • 21. Design Of Flexible Pavement • Design Of Flexible Pavement By Group Index Method Group Index is function of percentage material passing 200 mesh sieve (0.074mm), liquid limit and plasticity index of soil and is given by equation: GI=0.2a+0.005ac+0.01bd Here, a=that portion of material passing 0.074mm sieve, greater than 35 And not exceeding 75 % b=that portion of material passing 0.074mm sieve, greater than 15 And not exceeding 35% c = that value of liquid limit in excess of 40 and less than 60 d = that value of plasticity index exceeding 10 and not more than 30
  • 22. California Resistance Value Method pavements thickness varies directly with R value and logarithm of load repetitions. It varies inversely with fifth root of Computer value. T=K (TI) (90-R)/C1/5 Here : T=total thickness of pavement, cm K=numerical constant=0.166 TI=traffic index R=stabilometer resistance value C =Cohesiometer value
  • 23. Triaxial Method Here T=Pavement thickness, cm Es=modulus of elasticity of sub grade from triaxial test result, Kg/cm2 A=radius of contact area, cm ∆=design deflection (0.25 cm)
  • 25. Rigid pavement design As the name implies, rigid pavements are rigid , they do not extend much under loading like flexible pavements. They are constructed using cement concrete. In this case, the load carrying capacity is mainly due to the rigidity and high modulus of elasticity of the slab (slab action).
  • 26. Modifications Included in Rigid Pavement design procedures: • Reliability concepts identical to those used for the flexible pavements are introduced. • The environmental aspects of design are introduced in the same format as for flexible pavements. • The design procedure is modified to include such factors as tied shoulders, subbase erosion, and lean subbase designs.
  • 27. Rigid Pavement Response • Curling stress – Differences in temperature between the top and bottom surfaces of a PCC slab will cause the slab to curl. Since slab weight and contact with the base restrict its movement, stresses are created.
  • 28. where: σt=slab interior warping stress E=modulus of elasticity of PCC e=thermal coefficient of PCC (» 0.000005/°F) Δ T=temperature differential between the top and bottom of the slab µ=Poisson’s ratio for PCC (» 0.15) β=radius of wheel load distribution for corner loading where: l=radius of relative stiffness E=modulus of elasticity of PCC h=slab thickness k=modulus of subgrade reaction m=Poisson’s ratio for PCC (» 0.15)
  • 29. Load stress Loads on a PCC slab will create both compressive and tensile stresses within the slab and any adjacent one (as long as load transfer efficiency is > 0). a. Interior loading. Occurs when a load is applied on the interior of a slab s.urface which is “remote” from all edges. b. Edge loading. Occurs when a load is applied on a slab edge “remote” from a slab corner.
  • 30. c. Corner loading. Occurs when the center of a load is located on the bisector of the corner angle.
  • 31. Shrinkage and expansion • In addition to curling, environmental temperatures will cause PCC slabs to expand (when hot) and contract (when cool), which causes joint movement. where: z=joint opening = change in slab length (inches) C=base/slab frictional restraint factor = 0.65 for stabilized bases = 0.80 for granular bases L=slab length (inches)
  • 32.
  • 33.
  • 34. It is observed that flexible pavements are more economical for lesser volume of traffic.The life of flexible pavement is near about 15 years whose initial cost is low needs a periodic maintenance after a certain period and maintenance costs very high. The life of rigid pavement is much more than the flexible pavement of about 40 years approx 2.5 times life of flexible pavement whose initial cost is much more then the flexible pavement but maintenance cost is very less.
  • 36. “Start by doing what’s necessary; then do what’s possible; and suddenly your are doing the impossible.” ~Francis of Assisi~ Prepared by: FONTE, EDDIE RED ZULUETA, ERWIN JOHN

Notas del editor

  1. 1