Project NameCommunication PlanOverviewEffective and .docx
Building Formulas And Dashboard In Ms Project
1. Building a Project Dashboard with Formulas
in MS Project
Relu Rosenberg
PMP, Six Sigma Black Belt
2. Introduction
This presentation will show how to build a Project Dashboard using Excel like formulas and
functions in MS Project
The study case will walk through the steps for creating a field called “Task Progress” to
calculate the Progress status of a task and use graphical indicators for creating a dashboard
view for active tasks (task level) or project summary view (Summary tasks level)
Steps
Define the logic
Build the formula
Add graphical indicators for quick identification of tasks status, issues
Build filter based on calculated values to select tasks of interest (focus tasks)
Make customizations available to all your Project plans
Make customizations available to someone else , publish a template plan
Benefits
Automated calculation and identification of active tasks
Automated identification of tasks requiring attention
One step preparation of high level project status report for management
As always, a good, detailed plan will drive the quality of the resulting report !
10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 2
3. Introduction - 2
The end result will take you from a project plan with no easy way to identify a status (left) to a
toolbox to produce one click status reports, issues , focus tasks list (right side).
If this interests you, follow the rest of this presentation !
10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 3
4. Logic #1 - Calculate Task Progress based on Start/End dates
10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 4
5. Logic #1 – Notes
•Logic #1 is very simple to implement as it is based only on
“% Complete” and Start, End dates of the task.
It automates calculation and identification of 8 task status values !
•If %Complete is >0 it will know task work started and it will mark as “In
progress”
•Doesn’t require accurate estimate of %Complete.
•It is suitable for tasks of short duration, w/o interim milestones
•This calculation cannot establish if a task in progress is late or ahead of
the schedule. This is where logic #2 and #3 will help
10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 5
6. Logic #2 – Use task “Status” field
Task Status Field
Condition
Display Value
%Complete = 100 Complete 0
Timephased Cumulative %Complete >0 on midnight of day before On Schedule 1
Timephased Cumulative %Complete =0 on midnight before Late 2
Task Start Date > Today Future Task 3
Go To View->More Views ->”Task Usage”
To add fields
Format -> “Detail Styles” and add “Cumulative Percent Complete” to show pane
To change displayed fields
Format->”Details” and Check/Uncheck fields
Note:
In order to use Task Status and be able to display “Cumulative %Complete“ you
must assign a resource (real or generic) to each task !
10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 6
7. Logic #2 – Notes
•Logic #2 leverages the “Status” task field from Microsoft Project. This
will help to determine not just if a task is in Progress but also if it is on
Schedule or Late.
•It is the correct way to calculate because the time phased
“% Complete” accounts for the actual work performed over elapsed
time.
•A resource can have days off , days not worked full time, etc and
comparing ((Date()-*Start+)/*Duration+) with “% Complete” is
misleading.
•Requires more accurate estimate of %Complete of a task
•It’s suitable for tasks of longer duration where %Complete can be
measured
10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 7
8. Logic 2 - Task Progress using “Status” field (task field)
10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 8
9. Logic 3 - Using EVM SPI
Resources
Define all resources
Assign rates to each resource (Std. Rate,
Ovt. Rate)
Assign resource to each task
Define Earned Value Calculation options
(Tools ->Options -> Calculation)
Default task Earned Value method:
% Complete
Edits to total task % complete will be
spread to the status date (to see SPI>1)
Baseline project
Re-baseline every time you add tasks and
resources or change tasks, resources
10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 9
10. Logic 3 – Notes
• Logic #3 is the most sophisticated and accurate. It will allow to
determine if a task in progress is Behind Schedule, On Schedule, Ahead
of Schedule.
• It uses Earned Value Methodology and specifically it uses Schedule
Performance Index.
• For older versions of Microsoft Project which don’t have the SPI
calculated you can add SPI as a customized field, Number , with
following formula:
IIf([BCWS]>0,[BCWP]/[BCWS],0)
Since BCWS is 0 For future tasks in MS Project 2000, the formula checks
and returns SPI=0 to prevent Error due to division by 0.
• It requires accurate measurement of %Complete to provide accurate
indicator of progress status (Ahead, On Schedule, Behind)
10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 10
11. Logic 3 - Task Progress using EVM SPI
10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 11
12. Creating a custom field
The are several types of fields you can customize, depending on desired data type
Text, Date , Number are the most used
Start, Finish, Cost, Duration, Flag are additional types
Right click on project headings to “Insert Column” , will choose Text type field, Text2 for “Task Progress”
field
10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 12
13. Customize field applet
Right click on field header and select Customize field
Use Rename to rename the field from Text2 to “Task Progress” for use in formulas
Check the boxes for Formula and Graphical Indicators buttons for customization
10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 13
14. Writing Formulas – simple examples
We will use these statements and functions
IIf(expression-to-test, Do-this-if-true,Do-this-if-False)
Date() - returns current system date
Project fields - designated as [field-name]
Examples
Flag all active tasks (Start < Date < Finish)
IIf((Date() > [Start]) And (Date() < [Finish]),"Active Task","")
Flag all overdue tasks – (Finish < Date) and (%Complete <100)
IIf(([Finish] < Date()) And ([% Complete] < 100),"Overdue","")
Flag active and overdue tasks – combine the above
IIf((Date()>[Start]) And (Date()<[Finish]),
"Active Task",
IIf(([Finish]<Date()) And ([% Complete]<100),"Overdue","")
)
10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 14
15. Writing the Formulas for “Task Progress” logic
Below formulas implement the logic diagrams (decision trees) depicted in slides
It is recommended to check each decision path in the formula using the Logic diagram
Easiest way to test the values is by adjusting the % Complete
Logic 1 - % Complete and Start/Finish Dates
IIf(*% Complete+=100,"Complete",IIf(*Estimated+=Yes,"TBD",IIf(Date()>*Finish+,”Not Finished",
IIf(Date()>*Start+,IIf(*% Complete+=0,“Not Started",IIf((*Finish+-Date())<7,"Ending Next",
"In progress")),IIf([Start]-Date()<7,"Starting Next","Future")))))
Logic 2 - % Complete, Task Status and Start/Finish Dates
IIf([% Complete]=100,"Complete",IIf([Estimated]=Yes,"TBD",IIf(Date()>[Finish],"Not
Finished",IIf(Date()>[Start],IIf([% Complete]=0,"Not Started",IIf(([Finish]-Date())<7,"Ending
Next",IIf([Status]=1,"On Schedule","Late"))),IIf([Start]-Date()<7,"Starting Next","Future")))))
Logic 3 - Use SPI and Start/Finish Dates
IIf([% Complete]=100,"Complete",IIf([Estimated]=Yes,"TBD",IIf(Date()>[Finish],"Not
Finished",IIf(Date()>[Start],IIf([% Complete]=0,"Not Started",IIf(([Finish]-Date())<7,"Ending
Next",IIf([SPI]<1,"Late",IIf([SPI]>1,"Ahead","On Schedule")))),IIf([Start]-Date()<7,"Starting
Next","Future")))))
10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 15
16. Formula written in structured format
IIf([ % Complete]=100,
“Complete"
IIf([Estimated]=Yes,
"TBD",
IIf(Date()>[Finish],
"Not Finished",
IIf(Date()>[Start],
IIf([%Complete]=0,
"Not Started",
IIf(([Finish]-Date())<7,
"Ending Next",
IIf([Status]=1,
“On Schedule”,
“Late”
)
)
),
IIf([Start]-Date()<7,
"Starting Next",
"Future Task"
)
)
)
)
)
10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 16
17. Using Formula Applet
Press Formula button to open the applet
Use Field button to inserts field names in formula and Function button to select functions
To learn more about functions search for “Project functions” in Help
10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 17
18. Add Graphical Indicators
Check Graphical Indicators … Radio button to enable
Press Graphical Indicator… Button to define the values
Select “Nonsummary rows” to display indicator for tasks only
Assign icon for each status value – right click and select from pull-down menu
10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 18
19. Set Calculations Mode
Confirm/Set Calculations mode to Automatic
Tools->Options->Calculation Tab
Check/Set Calculation Mode: Automatic
10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 19
20. Project Plan without Graphical Indicators
Very difficult to understand tasks status
10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 20
21. Project Plan with Calculated Status & Graphical Indicators
10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 21
22. Project Plan with Graphical Indicators – 2
Optional – Display also Status Values (can also be seen when pointing over the Indicator )
10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 22
23. Project tasks review using filters
Select tasks of interest
In progress, Ending Next, Starting Next
Select issues
Not started, Late, Not Finished, TBD (Dates not Confirmed)
Create Filter
Got to Project->Filtered For->More Filters
Select New
Check radio button for Task filter
In New Filter Applet
o Define the Name
o Check Show In Menu to see it in Filters list
o Define the rules for tasks selection
10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 23
25. Project tasks review – Filter: Focus tasks (less clutter)
Optional – Data can be seen also when pointer is over the indicator
10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 25
26. Project tasks review – Filter: Issues
Not Started, Not Finished, Late, Duration estimated (TBD)
10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 26
27. Project Dashboard – phase level report for management
Apply Dashboard filter to produce this phase level view ((Outline level <=2) And (Summary=Yes))
10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 27
28. Project Dashboard – Phase & Major Activities review
Add filter with ((Outline level <=3) And (Summary=Yes))
10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 28
29. Share customizations
Make customizations available to all your projects
Any MS Project object customized in a project plan will be saved within the project file only.
In order to make these objects available to the other projects they need to be saved in the global template.
Identify all customizations
o Tools->Organizer and go through each tab (object category).
o Left side “Global.MPT” represents global objects, right side shows the objects exiting only in the specific project
file.
o Select object from Fields, Filters, Views, etc, on right side, press Copy and it will be copied to Global Template.
10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 29
30. Share customizations - 2
Share customizations with others
Create a blank project files
Copy all customizations from Global to the Project file
o Tools->Organizer and go through each tab (object category).
o Left side “Global.MPT” represents global objects, right side shows the objects exiting only in the specific project
file.
o Select a an object field, filter, etc, on Left side, Global Template, and press Copy to copy to project file
10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 30
31. Questions ?
Email: relur@comcast.net
10/6/2010 Relu Rosenberg, PMP, Six Sigma Black Belt 31