SlideShare una empresa de Scribd logo
1 de 24
132/33KV SUBSTATION RAJA KA TALAB
VARANASI
SUBMITED BY- -
JAGDEESH KUMAR MAURYA
1342220904
E.E. 4th YEAR
BANSAL INSTITUTE OF ENGINEERING & TECHNOLOGY
LUCKNOW
SUBMITED TO -
Mr. B.R. SINGH
HOD OF E.E
132KV INCOMING
 132KV INCOMING MANDUADIH, GAJOKHAR & AUARI
132KV INCOMING
132KV INCOMING MANDUADHI
LIGHTNING ARRESTORS
LIGHTNING ARRESTORS
 It is connected between line and earth so diverts the incoming high
voltage wave to earth.
 When a lightning surge travels along the power line to the arrester, the
current from the surge is diverted through the arrestor in most cases to
CURRENT TRANSFORMERS [C.T.]
400/200/100/1A (BHEL)
CURRENT TRANSFORMERS
 A Current transformer (CT) is used for measurement of alternating
currents.
 A Current transformer is 400amp to 1amp step up T/F .
 CT is connected in series with circuit.
BUS ISOLATOR
BUS ISOLATOR
 The line through the Bus isolator is distributed in the substation main
bus.
 It is disconnects the circuit from the main power supply.
 Open the isolator on no load .
VacuumCIRCUITBREAKERS
(CGL)
CIRCUIT BREAKERS
 Circuit beaker used to protect the equipment by opening the circuit for
over current and over voltage.
 A circuit breaker which can open or close a circuit under normal as well
RELAY
 When a short circuit occurs at any point on the transmission line the
current flowing in the increases to the enormous value. This result in a
heavy current flow through the relay coil, causing the to operate by closing
its contacts
Main bus-bar
MAIN BUS BAR
 ACSR moose conductor use in main bus bar and consist of a 54 wires in
aluminium and 7wires in steel
POTENTIAL
TRANSFORMERS [P.T.]
POTENTIAL TRANSFORMERS
 A Potential transformer is used for measurement of voltage.
 PT is used in power system to step down extra high voltage and
provide a low voltage, for measurement or to operate a protective
relay
TRANSFER BUS
TRANSFER BUS
 It is used in ACSR conductor.
 It is transfer bus through supply in different -2 transformer
SF6 CIRCUIIT BREAKERS (ABB)
SF6 CIRCUIT BREAKERS
 Sulfur hexafluoride (sf6) gas is used as the arc quenching Medium.
 The sf6 is an electronegative gas and has a strong tendency to absorb
free electrons.
 CB has developed for voltage 115kv to 230kv.
Vacuum circuit breaker
VACUUM CB
 Vacuum circuit breakers are circuit breakers which are used to protect
medium and high voltage circuits from dangerous electrical situations
LINE
ISOLATORS
LINE ISOLATORS
 Line isolator is line side isolator
CURRENT TRANSFORMERS [C.T.]
400/200/100/1a (BHEL)
CURRENT TRANSFORMERS
 A Current transformer (CT) is used for measurement of alternating
currents.
 A Current transformer is 400amp to 1amp step up T/F .
 CT is connected in series with circuit.
post
INSULATOR
LIGHTNING ARRESTORS
132/33 ADITYA
TRANSFORMER
HV
SIDE
63MVA 132/33 STAR-
STAR T/F
CONSERVATOR TANK
BUCHHOLZ’S
RELAY
SILICA GEL
132/33 ADITYA TRANSFORMER
COOLING FINS
TAP CHANGER SWITCH
NUTRAL TERMINEL
 Transformer is a heart of substations. These are used to reduce the
LIGHTNING ARRESTORS
CIRCUIT BREAKERSCURRENT TRANSFORMERS[C.T.]
33kv busbar
33KV BUSBAR
 33kv bus bar in connected in parallel operation in two transformer. one
is 40MVA and 63MVA
 33KV BUS WITH PARALLEL OPErATION IN 40MVA &
63MVA
33KV PIN INSULATOR
PARALLEL OPerATION
40 MVA 132/33 TRANSFORMER
LIGHTNING ARRESTORS
C.T.
LIGHTNING ARRESTORS
132/33 ,40MVA TRANSFORMER
COOLING FANS
 132/33, 40MVA, BHARAT BIJALI transformer step down transformer.
 It is connected in parallel operation.
 It is load share in parallel.
33KV OUTGOING VACUUM CB
33 KV OUTGOING
 33kv 7 outgoing ROHANIA , ADALPURA , LOHTA, SEWAPURI, JAMUA ,
THATRA and JAKHANI.
10MVA 33/11 TRANSFORMERS
33/11 TRANSFORMERS
 33/11 STEP DOWN TRANSFORMER .
wall
CAPACITOR BANK
CAPACITOR BANK
 The load on the power system is varying being high during morning
and low in evening which increases the load current. This result in the
decreased power factor.
 In order to improve the power factor come device taking leading
power should be connected in parallel with load . One of device can be
132/33KV Substation Layout and Components

Más contenido relacionado

La actualidad más candente

industrial training on 132 kv substation
industrial training on 132 kv substationindustrial training on 132 kv substation
industrial training on 132 kv substationpk130992
 
Presentation on 132/33KV BSPTCL(Bodhgaya Substation)
Presentation on 132/33KV BSPTCL(Bodhgaya Substation)Presentation on 132/33KV BSPTCL(Bodhgaya Substation)
Presentation on 132/33KV BSPTCL(Bodhgaya Substation)Rahul Prajapati
 
Shubham chamoli 132 kv substation presenttation
Shubham  chamoli 132 kv substation presenttationShubham  chamoli 132 kv substation presenttation
Shubham chamoli 132 kv substation presenttationshubhamchamoli
 
Pole mounted substaion in kerala
Pole mounted substaion in keralaPole mounted substaion in kerala
Pole mounted substaion in keralasebinkb
 
220kv sub station kishangarh bas, alwar
220kv sub station kishangarh bas, alwar220kv sub station kishangarh bas, alwar
220kv sub station kishangarh bas, alwarDevendra khairiya
 
220kv gss pindwara(sirohi)
220kv gss pindwara(sirohi)220kv gss pindwara(sirohi)
220kv gss pindwara(sirohi)Pankaj Rawal
 
Srijan tripathi(220kv gss) ppt
Srijan tripathi(220kv gss) pptSrijan tripathi(220kv gss) ppt
Srijan tripathi(220kv gss) pptsrijan tripathi
 
WBSETCL Subhash Gram 220KV Substation Training Report
WBSETCL Subhash Gram 220KV Substation Training ReportWBSETCL Subhash Gram 220KV Substation Training Report
WBSETCL Subhash Gram 220KV Substation Training ReportArijit Basu
 
industrial Training report in PTCUL Substation dehradun
industrial Training report in PTCUL Substation dehradunindustrial Training report in PTCUL Substation dehradun
industrial Training report in PTCUL Substation dehradunsurendra rawat
 
Power Supply System - Single Line Diagram
Power Supply System - Single Line DiagramPower Supply System - Single Line Diagram
Power Supply System - Single Line DiagramKamran Hassan
 
132kv substation inplant training seminar
132kv substation inplant training seminar132kv substation inplant training seminar
132kv substation inplant training seminarShrikant Bhansali
 
Ppt on 132 kv gss by ashok khoja
Ppt on  132 kv gss  by ashok khojaPpt on  132 kv gss  by ashok khoja
Ppt on 132 kv gss by ashok khojaASHOK KHOJA
 
132 kv GSS Mahaveer Nagar Kota
132 kv GSS Mahaveer Nagar Kota 132 kv GSS Mahaveer Nagar Kota
132 kv GSS Mahaveer Nagar Kota PramodNagar5
 
A PPT ON 220 KV GSS HINDAUN CITY
A PPT ON 220 KV GSS HINDAUN CITYA PPT ON 220 KV GSS HINDAUN CITY
A PPT ON 220 KV GSS HINDAUN CITYRohitashav Goyal
 

La actualidad más candente (20)

industrial training on 132 kv substation
industrial training on 132 kv substationindustrial training on 132 kv substation
industrial training on 132 kv substation
 
Presentation on 132/33KV BSPTCL(Bodhgaya Substation)
Presentation on 132/33KV BSPTCL(Bodhgaya Substation)Presentation on 132/33KV BSPTCL(Bodhgaya Substation)
Presentation on 132/33KV BSPTCL(Bodhgaya Substation)
 
Summer Training presentation on 132/33 KV sub-station Minto park, Allahabad
Summer Training presentation on 132/33 KV sub-station Minto park, AllahabadSummer Training presentation on 132/33 KV sub-station Minto park, Allahabad
Summer Training presentation on 132/33 KV sub-station Minto park, Allahabad
 
Shubham chamoli 132 kv substation presenttation
Shubham  chamoli 132 kv substation presenttationShubham  chamoli 132 kv substation presenttation
Shubham chamoli 132 kv substation presenttation
 
220 kv gss renwal ppt
220 kv gss renwal ppt220 kv gss renwal ppt
220 kv gss renwal ppt
 
Pole mounted substaion in kerala
Pole mounted substaion in keralaPole mounted substaion in kerala
Pole mounted substaion in kerala
 
220kv sub station kishangarh bas, alwar
220kv sub station kishangarh bas, alwar220kv sub station kishangarh bas, alwar
220kv sub station kishangarh bas, alwar
 
220kv gss pindwara(sirohi)
220kv gss pindwara(sirohi)220kv gss pindwara(sirohi)
220kv gss pindwara(sirohi)
 
Switch yard & Protection
Switch yard & ProtectionSwitch yard & Protection
Switch yard & Protection
 
220 66 kv nrs sub report
220 66 kv nrs sub report220 66 kv nrs sub report
220 66 kv nrs sub report
 
Srijan tripathi(220kv gss) ppt
Srijan tripathi(220kv gss) pptSrijan tripathi(220kv gss) ppt
Srijan tripathi(220kv gss) ppt
 
WBSETCL Subhash Gram 220KV Substation Training Report
WBSETCL Subhash Gram 220KV Substation Training ReportWBSETCL Subhash Gram 220KV Substation Training Report
WBSETCL Subhash Gram 220KV Substation Training Report
 
industrial Training report in PTCUL Substation dehradun
industrial Training report in PTCUL Substation dehradunindustrial Training report in PTCUL Substation dehradun
industrial Training report in PTCUL Substation dehradun
 
Power Supply System - Single Line Diagram
Power Supply System - Single Line DiagramPower Supply System - Single Line Diagram
Power Supply System - Single Line Diagram
 
132kv substation inplant training seminar
132kv substation inplant training seminar132kv substation inplant training seminar
132kv substation inplant training seminar
 
Ppt on 132 kv gss by ashok khoja
Ppt on  132 kv gss  by ashok khojaPpt on  132 kv gss  by ashok khoja
Ppt on 132 kv gss by ashok khoja
 
My training
My trainingMy training
My training
 
132 KV GSS CHAMBAL JAIPUR
132 KV GSS CHAMBAL JAIPUR132 KV GSS CHAMBAL JAIPUR
132 KV GSS CHAMBAL JAIPUR
 
132 kv GSS Mahaveer Nagar Kota
132 kv GSS Mahaveer Nagar Kota 132 kv GSS Mahaveer Nagar Kota
132 kv GSS Mahaveer Nagar Kota
 
A PPT ON 220 KV GSS HINDAUN CITY
A PPT ON 220 KV GSS HINDAUN CITYA PPT ON 220 KV GSS HINDAUN CITY
A PPT ON 220 KV GSS HINDAUN CITY
 

Similar a 132/33KV Substation Layout and Components

PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...
PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...
PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...Rishabhlko
 
Uttar pradesh power corporation limited
Uttar pradesh power corporation limitedUttar pradesh power corporation limited
Uttar pradesh power corporation limitedVSRAGHU
 
the substation components study
the substation components study the substation components study
the substation components study Krishnaveni Reddy
 
introductory presentation on the transformer
introductory presentation on the transformer   introductory presentation on the transformer
introductory presentation on the transformer Sagarkv3
 
132 KV Grid Station Intern ship training report
132 KV Grid Station Intern ship training report132 KV Grid Station Intern ship training report
132 KV Grid Station Intern ship training reportMuntazir Mehdi
 
pptravi-191011011024 (1).pdf
pptravi-191011011024 (1).pdfpptravi-191011011024 (1).pdf
pptravi-191011011024 (1).pdfHariomgupta90
 
400 KV GSS HEERAPURA, JAIPUR
400 KV GSS HEERAPURA, JAIPUR400 KV GSS HEERAPURA, JAIPUR
400 KV GSS HEERAPURA, JAIPURsahid raja khan
 
Rajasthan Rajya Vidyut Prasaran Nigam.pptx
Rajasthan Rajya Vidyut Prasaran Nigam.pptxRajasthan Rajya Vidyut Prasaran Nigam.pptx
Rajasthan Rajya Vidyut Prasaran Nigam.pptxsohaib268827
 
PPT ON 33/11KV SUBSTATION
PPT ON 33/11KV SUBSTATIONPPT ON 33/11KV SUBSTATION
PPT ON 33/11KV SUBSTATIONRavi Phadtare
 
fdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptxfdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptxAkshaiSai2
 
vishal-170827171239 (1).pdf
vishal-170827171239 (1).pdfvishal-170827171239 (1).pdf
vishal-170827171239 (1).pdfSunnyYadav735981
 
PPT on 33/11 sub-station uppcl
PPT on 33/11 sub-station uppclPPT on 33/11 sub-station uppcl
PPT on 33/11 sub-station uppclVISHAL VERMA
 
Substation Training presentation
Substation Training presentationSubstation Training presentation
Substation Training presentationKamal Mittal
 
PPT ON SUMMER VOCATIONAL TRAINING ON 132/33 KV AT MOHADDIPUR, SUB-STATION, GO...
PPT ON SUMMER VOCATIONAL TRAINING ON 132/33 KV AT MOHADDIPUR, SUB-STATION, GO...PPT ON SUMMER VOCATIONAL TRAINING ON 132/33 KV AT MOHADDIPUR, SUB-STATION, GO...
PPT ON SUMMER VOCATIONAL TRAINING ON 132/33 KV AT MOHADDIPUR, SUB-STATION, GO...Abrar Ahmad
 

Similar a 132/33KV Substation Layout and Components (20)

PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...
PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...
PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...
 
Uttar pradesh power corporation limited
Uttar pradesh power corporation limitedUttar pradesh power corporation limited
Uttar pradesh power corporation limited
 
Ashish.pptx
Ashish.pptxAshish.pptx
Ashish.pptx
 
the substation components study
the substation components study the substation components study
the substation components study
 
rough.pptx
rough.pptxrough.pptx
rough.pptx
 
uppcl.pptx
uppcl.pptxuppcl.pptx
uppcl.pptx
 
introductory presentation on the transformer
introductory presentation on the transformer   introductory presentation on the transformer
introductory presentation on the transformer
 
132 KV Grid Station Intern ship training report
132 KV Grid Station Intern ship training report132 KV Grid Station Intern ship training report
132 KV Grid Station Intern ship training report
 
pptravi-191011011024 (1).pdf
pptravi-191011011024 (1).pdfpptravi-191011011024 (1).pdf
pptravi-191011011024 (1).pdf
 
400 KV GSS HEERAPURA, JAIPUR
400 KV GSS HEERAPURA, JAIPUR400 KV GSS HEERAPURA, JAIPUR
400 KV GSS HEERAPURA, JAIPUR
 
Rajasthan Rajya Vidyut Prasaran Nigam.pptx
Rajasthan Rajya Vidyut Prasaran Nigam.pptxRajasthan Rajya Vidyut Prasaran Nigam.pptx
Rajasthan Rajya Vidyut Prasaran Nigam.pptx
 
PPT ON 33/11KV SUBSTATION
PPT ON 33/11KV SUBSTATIONPPT ON 33/11KV SUBSTATION
PPT ON 33/11KV SUBSTATION
 
Transformer.pptx
Transformer.pptxTransformer.pptx
Transformer.pptx
 
TRANSFORMER PPT
TRANSFORMER PPT TRANSFORMER PPT
TRANSFORMER PPT
 
fdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptxfdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptx
 
vishal-170827171239 (1).pdf
vishal-170827171239 (1).pdfvishal-170827171239 (1).pdf
vishal-170827171239 (1).pdf
 
PPT on 33/11 sub-station uppcl
PPT on 33/11 sub-station uppclPPT on 33/11 sub-station uppcl
PPT on 33/11 sub-station uppcl
 
Gss ppt by kanhaiya
Gss ppt  by kanhaiyaGss ppt  by kanhaiya
Gss ppt by kanhaiya
 
Substation Training presentation
Substation Training presentationSubstation Training presentation
Substation Training presentation
 
PPT ON SUMMER VOCATIONAL TRAINING ON 132/33 KV AT MOHADDIPUR, SUB-STATION, GO...
PPT ON SUMMER VOCATIONAL TRAINING ON 132/33 KV AT MOHADDIPUR, SUB-STATION, GO...PPT ON SUMMER VOCATIONAL TRAINING ON 132/33 KV AT MOHADDIPUR, SUB-STATION, GO...
PPT ON SUMMER VOCATIONAL TRAINING ON 132/33 KV AT MOHADDIPUR, SUB-STATION, GO...
 

Último

A Good Girl's Guide to Murder (A Good Girl's Guide to Murder, #1)
A Good Girl's Guide to Murder (A Good Girl's Guide to Murder, #1)A Good Girl's Guide to Murder (A Good Girl's Guide to Murder, #1)
A Good Girl's Guide to Murder (A Good Girl's Guide to Murder, #1)Christopher H Felton
 
Film cover research (1).pptxsdasdasdasdasdasa
Film cover research (1).pptxsdasdasdasdasdasaFilm cover research (1).pptxsdasdasdasdasdasa
Film cover research (1).pptxsdasdasdasdasdasa494f574xmv
 
办理(UofR毕业证书)罗切斯特大学毕业证成绩单原版一比一
办理(UofR毕业证书)罗切斯特大学毕业证成绩单原版一比一办理(UofR毕业证书)罗切斯特大学毕业证成绩单原版一比一
办理(UofR毕业证书)罗切斯特大学毕业证成绩单原版一比一z xss
 
定制(Management毕业证书)新加坡管理大学毕业证成绩单原版一比一
定制(Management毕业证书)新加坡管理大学毕业证成绩单原版一比一定制(Management毕业证书)新加坡管理大学毕业证成绩单原版一比一
定制(Management毕业证书)新加坡管理大学毕业证成绩单原版一比一Fs
 
Potsdam FH学位证,波茨坦应用技术大学毕业证书1:1制作
Potsdam FH学位证,波茨坦应用技术大学毕业证书1:1制作Potsdam FH学位证,波茨坦应用技术大学毕业证书1:1制作
Potsdam FH学位证,波茨坦应用技术大学毕业证书1:1制作ys8omjxb
 
Call Girls Service Adil Nagar 7001305949 Need escorts Service Pooja Vip
Call Girls Service Adil Nagar 7001305949 Need escorts Service Pooja VipCall Girls Service Adil Nagar 7001305949 Need escorts Service Pooja Vip
Call Girls Service Adil Nagar 7001305949 Need escorts Service Pooja VipCall Girls Lucknow
 
Magic exist by Marta Loveguard - presentation.pptx
Magic exist by Marta Loveguard - presentation.pptxMagic exist by Marta Loveguard - presentation.pptx
Magic exist by Marta Loveguard - presentation.pptxMartaLoveguard
 
办理多伦多大学毕业证成绩单|购买加拿大UTSG文凭证书
办理多伦多大学毕业证成绩单|购买加拿大UTSG文凭证书办理多伦多大学毕业证成绩单|购买加拿大UTSG文凭证书
办理多伦多大学毕业证成绩单|购买加拿大UTSG文凭证书zdzoqco
 
PHP-based rendering of TYPO3 Documentation
PHP-based rendering of TYPO3 DocumentationPHP-based rendering of TYPO3 Documentation
PHP-based rendering of TYPO3 DocumentationLinaWolf1
 
Top 10 Interactive Website Design Trends in 2024.pptx
Top 10 Interactive Website Design Trends in 2024.pptxTop 10 Interactive Website Design Trends in 2024.pptx
Top 10 Interactive Website Design Trends in 2024.pptxDyna Gilbert
 
Git and Github workshop GDSC MLRITM
Git and Github  workshop GDSC MLRITMGit and Github  workshop GDSC MLRITM
Git and Github workshop GDSC MLRITMgdsc13
 
定制(Lincoln毕业证书)新西兰林肯大学毕业证成绩单原版一比一
定制(Lincoln毕业证书)新西兰林肯大学毕业证成绩单原版一比一定制(Lincoln毕业证书)新西兰林肯大学毕业证成绩单原版一比一
定制(Lincoln毕业证书)新西兰林肯大学毕业证成绩单原版一比一Fs
 
Font Performance - NYC WebPerf Meetup April '24
Font Performance - NYC WebPerf Meetup April '24Font Performance - NYC WebPerf Meetup April '24
Font Performance - NYC WebPerf Meetup April '24Paul Calvano
 
Call Girls Near The Suryaa Hotel New Delhi 9873777170
Call Girls Near The Suryaa Hotel New Delhi 9873777170Call Girls Near The Suryaa Hotel New Delhi 9873777170
Call Girls Near The Suryaa Hotel New Delhi 9873777170Sonam Pathan
 
Blepharitis inflammation of eyelid symptoms cause everything included along w...
Blepharitis inflammation of eyelid symptoms cause everything included along w...Blepharitis inflammation of eyelid symptoms cause everything included along w...
Blepharitis inflammation of eyelid symptoms cause everything included along w...Excelmac1
 
Contact Rya Baby for Call Girls New Delhi
Contact Rya Baby for Call Girls New DelhiContact Rya Baby for Call Girls New Delhi
Contact Rya Baby for Call Girls New Delhimiss dipika
 
Call Girls South Delhi Delhi reach out to us at ☎ 9711199012
Call Girls South Delhi Delhi reach out to us at ☎ 9711199012Call Girls South Delhi Delhi reach out to us at ☎ 9711199012
Call Girls South Delhi Delhi reach out to us at ☎ 9711199012rehmti665
 

Último (20)

A Good Girl's Guide to Murder (A Good Girl's Guide to Murder, #1)
A Good Girl's Guide to Murder (A Good Girl's Guide to Murder, #1)A Good Girl's Guide to Murder (A Good Girl's Guide to Murder, #1)
A Good Girl's Guide to Murder (A Good Girl's Guide to Murder, #1)
 
Film cover research (1).pptxsdasdasdasdasdasa
Film cover research (1).pptxsdasdasdasdasdasaFilm cover research (1).pptxsdasdasdasdasdasa
Film cover research (1).pptxsdasdasdasdasdasa
 
办理(UofR毕业证书)罗切斯特大学毕业证成绩单原版一比一
办理(UofR毕业证书)罗切斯特大学毕业证成绩单原版一比一办理(UofR毕业证书)罗切斯特大学毕业证成绩单原版一比一
办理(UofR毕业证书)罗切斯特大学毕业证成绩单原版一比一
 
定制(Management毕业证书)新加坡管理大学毕业证成绩单原版一比一
定制(Management毕业证书)新加坡管理大学毕业证成绩单原版一比一定制(Management毕业证书)新加坡管理大学毕业证成绩单原版一比一
定制(Management毕业证书)新加坡管理大学毕业证成绩单原版一比一
 
Potsdam FH学位证,波茨坦应用技术大学毕业证书1:1制作
Potsdam FH学位证,波茨坦应用技术大学毕业证书1:1制作Potsdam FH学位证,波茨坦应用技术大学毕业证书1:1制作
Potsdam FH学位证,波茨坦应用技术大学毕业证书1:1制作
 
Call Girls Service Adil Nagar 7001305949 Need escorts Service Pooja Vip
Call Girls Service Adil Nagar 7001305949 Need escorts Service Pooja VipCall Girls Service Adil Nagar 7001305949 Need escorts Service Pooja Vip
Call Girls Service Adil Nagar 7001305949 Need escorts Service Pooja Vip
 
Hot Sexy call girls in Rk Puram 🔝 9953056974 🔝 Delhi escort Service
Hot Sexy call girls in  Rk Puram 🔝 9953056974 🔝 Delhi escort ServiceHot Sexy call girls in  Rk Puram 🔝 9953056974 🔝 Delhi escort Service
Hot Sexy call girls in Rk Puram 🔝 9953056974 🔝 Delhi escort Service
 
Magic exist by Marta Loveguard - presentation.pptx
Magic exist by Marta Loveguard - presentation.pptxMagic exist by Marta Loveguard - presentation.pptx
Magic exist by Marta Loveguard - presentation.pptx
 
办理多伦多大学毕业证成绩单|购买加拿大UTSG文凭证书
办理多伦多大学毕业证成绩单|购买加拿大UTSG文凭证书办理多伦多大学毕业证成绩单|购买加拿大UTSG文凭证书
办理多伦多大学毕业证成绩单|购买加拿大UTSG文凭证书
 
PHP-based rendering of TYPO3 Documentation
PHP-based rendering of TYPO3 DocumentationPHP-based rendering of TYPO3 Documentation
PHP-based rendering of TYPO3 Documentation
 
young call girls in Uttam Nagar🔝 9953056974 🔝 Delhi escort Service
young call girls in Uttam Nagar🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Uttam Nagar🔝 9953056974 🔝 Delhi escort Service
young call girls in Uttam Nagar🔝 9953056974 🔝 Delhi escort Service
 
Top 10 Interactive Website Design Trends in 2024.pptx
Top 10 Interactive Website Design Trends in 2024.pptxTop 10 Interactive Website Design Trends in 2024.pptx
Top 10 Interactive Website Design Trends in 2024.pptx
 
Git and Github workshop GDSC MLRITM
Git and Github  workshop GDSC MLRITMGit and Github  workshop GDSC MLRITM
Git and Github workshop GDSC MLRITM
 
定制(Lincoln毕业证书)新西兰林肯大学毕业证成绩单原版一比一
定制(Lincoln毕业证书)新西兰林肯大学毕业证成绩单原版一比一定制(Lincoln毕业证书)新西兰林肯大学毕业证成绩单原版一比一
定制(Lincoln毕业证书)新西兰林肯大学毕业证成绩单原版一比一
 
Model Call Girl in Jamuna Vihar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in  Jamuna Vihar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in  Jamuna Vihar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Jamuna Vihar Delhi reach out to us at 🔝9953056974🔝
 
Font Performance - NYC WebPerf Meetup April '24
Font Performance - NYC WebPerf Meetup April '24Font Performance - NYC WebPerf Meetup April '24
Font Performance - NYC WebPerf Meetup April '24
 
Call Girls Near The Suryaa Hotel New Delhi 9873777170
Call Girls Near The Suryaa Hotel New Delhi 9873777170Call Girls Near The Suryaa Hotel New Delhi 9873777170
Call Girls Near The Suryaa Hotel New Delhi 9873777170
 
Blepharitis inflammation of eyelid symptoms cause everything included along w...
Blepharitis inflammation of eyelid symptoms cause everything included along w...Blepharitis inflammation of eyelid symptoms cause everything included along w...
Blepharitis inflammation of eyelid symptoms cause everything included along w...
 
Contact Rya Baby for Call Girls New Delhi
Contact Rya Baby for Call Girls New DelhiContact Rya Baby for Call Girls New Delhi
Contact Rya Baby for Call Girls New Delhi
 
Call Girls South Delhi Delhi reach out to us at ☎ 9711199012
Call Girls South Delhi Delhi reach out to us at ☎ 9711199012Call Girls South Delhi Delhi reach out to us at ☎ 9711199012
Call Girls South Delhi Delhi reach out to us at ☎ 9711199012
 

132/33KV Substation Layout and Components

  • 1. 132/33KV SUBSTATION RAJA KA TALAB VARANASI SUBMITED BY- - JAGDEESH KUMAR MAURYA 1342220904 E.E. 4th YEAR BANSAL INSTITUTE OF ENGINEERING & TECHNOLOGY LUCKNOW SUBMITED TO - Mr. B.R. SINGH HOD OF E.E
  • 2. 132KV INCOMING  132KV INCOMING MANDUADIH, GAJOKHAR & AUARI 132KV INCOMING
  • 4. LIGHTNING ARRESTORS LIGHTNING ARRESTORS  It is connected between line and earth so diverts the incoming high voltage wave to earth.  When a lightning surge travels along the power line to the arrester, the current from the surge is diverted through the arrestor in most cases to
  • 5. CURRENT TRANSFORMERS [C.T.] 400/200/100/1A (BHEL) CURRENT TRANSFORMERS  A Current transformer (CT) is used for measurement of alternating currents.  A Current transformer is 400amp to 1amp step up T/F .  CT is connected in series with circuit.
  • 6. BUS ISOLATOR BUS ISOLATOR  The line through the Bus isolator is distributed in the substation main bus.  It is disconnects the circuit from the main power supply.  Open the isolator on no load .
  • 7. VacuumCIRCUITBREAKERS (CGL) CIRCUIT BREAKERS  Circuit beaker used to protect the equipment by opening the circuit for over current and over voltage.  A circuit breaker which can open or close a circuit under normal as well
  • 8. RELAY  When a short circuit occurs at any point on the transmission line the current flowing in the increases to the enormous value. This result in a heavy current flow through the relay coil, causing the to operate by closing its contacts
  • 9. Main bus-bar MAIN BUS BAR  ACSR moose conductor use in main bus bar and consist of a 54 wires in aluminium and 7wires in steel
  • 10. POTENTIAL TRANSFORMERS [P.T.] POTENTIAL TRANSFORMERS  A Potential transformer is used for measurement of voltage.  PT is used in power system to step down extra high voltage and provide a low voltage, for measurement or to operate a protective relay
  • 11. TRANSFER BUS TRANSFER BUS  It is used in ACSR conductor.  It is transfer bus through supply in different -2 transformer
  • 12. SF6 CIRCUIIT BREAKERS (ABB) SF6 CIRCUIT BREAKERS  Sulfur hexafluoride (sf6) gas is used as the arc quenching Medium.  The sf6 is an electronegative gas and has a strong tendency to absorb free electrons.  CB has developed for voltage 115kv to 230kv.
  • 13. Vacuum circuit breaker VACUUM CB  Vacuum circuit breakers are circuit breakers which are used to protect medium and high voltage circuits from dangerous electrical situations
  • 14. LINE ISOLATORS LINE ISOLATORS  Line isolator is line side isolator
  • 15. CURRENT TRANSFORMERS [C.T.] 400/200/100/1a (BHEL) CURRENT TRANSFORMERS  A Current transformer (CT) is used for measurement of alternating currents.  A Current transformer is 400amp to 1amp step up T/F .  CT is connected in series with circuit.
  • 17. HV SIDE 63MVA 132/33 STAR- STAR T/F CONSERVATOR TANK BUCHHOLZ’S RELAY SILICA GEL 132/33 ADITYA TRANSFORMER COOLING FINS TAP CHANGER SWITCH NUTRAL TERMINEL  Transformer is a heart of substations. These are used to reduce the
  • 18. LIGHTNING ARRESTORS CIRCUIT BREAKERSCURRENT TRANSFORMERS[C.T.] 33kv busbar 33KV BUSBAR  33kv bus bar in connected in parallel operation in two transformer. one is 40MVA and 63MVA
  • 19.  33KV BUS WITH PARALLEL OPErATION IN 40MVA & 63MVA 33KV PIN INSULATOR PARALLEL OPerATION
  • 20. 40 MVA 132/33 TRANSFORMER LIGHTNING ARRESTORS C.T. LIGHTNING ARRESTORS 132/33 ,40MVA TRANSFORMER COOLING FANS  132/33, 40MVA, BHARAT BIJALI transformer step down transformer.  It is connected in parallel operation.  It is load share in parallel.
  • 21. 33KV OUTGOING VACUUM CB 33 KV OUTGOING  33kv 7 outgoing ROHANIA , ADALPURA , LOHTA, SEWAPURI, JAMUA , THATRA and JAKHANI.
  • 22. 10MVA 33/11 TRANSFORMERS 33/11 TRANSFORMERS  33/11 STEP DOWN TRANSFORMER . wall
  • 23. CAPACITOR BANK CAPACITOR BANK  The load on the power system is varying being high during morning and low in evening which increases the load current. This result in the decreased power factor.  In order to improve the power factor come device taking leading power should be connected in parallel with load . One of device can be